To provide the most accurate information about upcoming traffic impacts, the project team will provide as much notice as possible for lane closures and traffic switches. See below for a live map of traffic closures in San Antonio.
For a list of lane closures across Texas, visit TxDOT’s interative map website DriveTexas™.
I-35 NEX lane closures for Sept. 14 - 20
This page is updated weekly. To find the most up to date and current lane closures, follow the TxDOT San Antonio District on social media or contact us for email updates at i35NEX@txdot.gov.
This week's lane closures (weather permitting and subject to change):
Maintenance
- No closures at this time.
I-35 from FM 3009 to FM 1518
Northbound
- Tuesday, Sept. 16, until Thursday, Sept. 18, 9 p.m. to 5 a.m. Multiple mainlane closures (3), exit ramp, and entrance ramp of northbound I-35 from Evans Road to Roy Richard Drive (FM 3009) for pavement, roadway, and drainage work. Traffic should use next available ramps.
Southbound
- Monday, Sept. 15, until Wednesday, Sept. 17, 9 p.m. to 5 a.m. Multiple mainlane closures (3), and entrance ramp, and exit ramp of southbound I-35 from Roy Richard Drive (FM 3009) to Schertz Parkway for slip barrier. Traffic should use next available ramps.
- Monday, Sept. 15, until Thursday, Sept. 18, 8 p.m. to 6 a.m. Full closure of Corporate Drive at I-35 intersection for bridge, column, and cap work. Traffic should follow detour signs.
- Friday, Sept. 19, until Monday, Sept. 22, 8 p.m. to 5 a.m. Full closure of southbound I-35 frontage road, entrance ramp and exit ramp from Schertz Parkway to Corporate Drive for paving. Traffic should follow detour signs.
Eastbound
- No closures at this time.
I-35 from FM 1518 to Loop 1604
Northbound
- Through Monday, Oct. 20, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Forum Parkway to Forum Access Road for construction work.
- Through Monday, Oct. 20, long-term closure (24/7). Exit ramp closure on northbound I-35 to Evans Road for construction work.
- Sunday, Sept. 14, until Tuesday, Sept. 16, 9 p.m. to 5 a.m. Full closure of Evans Road and northbound to southbound turnaround at I-35 intersection for bridge deck work. Traffic should follow detour signs.
- Monday, Sept. 15, 9 p.m. to 5 a.m. Full closure on northbound I-35 frontage road from Forum Parkway to Forum Access Road for bridge structure work. Traffic should follow detour signs.
- Monday, Sept. 15, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Full closure on northbound frontage road of I-35 at Pasatiempo intersection for drilling work.
- Monday, Sept. 15, until Saturday, Sept. 20, 8 p.m. to 6 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, exit ramp, and entrance ramp from Forum Parkway to Evans Road for bridge deck work. Traffic should use next exit and entrance ramps.
Southbound
- Through Monday, Oct. 20, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from Forum Parkway to Old Austin Road for bridge and roadway work.
- Through Monday, Oct. 20, long-term closure (24/7). Right lane closure on I-35 southbound mainlanes from Olympia Parkway to Loop 1604 interchange for construction work.
- Through Monday, Oct. 20, long-term closure (24/7). Right lane closure on I-35 southbound collector distributor from Forum Parkway to Loop 1604 interchange for construction work.
- Through Monday, Oct. 20, long-term closure (24/7). Entrance ramp closure on I-35 southbound frontage road from Old Austin Road to I-35 southbound mainlanes for construction work.
- Through Monday, Oct. 20, long-term closure (24/7). Full closure on I-35 southbound to northbound turnaround at Corporate Drive for construction work.
- Sunday, Sept. 14, until Tuesday, Sept. 16, 8 p.m. to 6 a.m. Full closure of southbound I-35 frontage road from Corporate Drive to Evans Road and Evans Road at I-35 intersection for bridge structure work. Traffic should follow detour signs.
- Sunday, Sept. 14, until Wednesday, Sept. 17, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from Retama Parkway to Forum Parkway for moving barrier, paving, and traffic shift. Traffic should follow detour signs.
- Sunday, Sept. 14, until Thursday, Sept. 18, 9 p.m. to 5 a.m. Multiple mainlane closures (3) on southbound I-35 from Schertz Parkway to Forum Parkway for bridge deck pour, traffic shift, and lane striping.
- Sunday, Sept. 14, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Evans Road to Arcadia Drive and northbound to southbound turnaround of Evans Road at I-35 intersection for traffic shift. Traffic should follow detour signs.
- Sunday, Sept. 14, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road and exit ramp from Forum Parkway to Evans Road for utility work. Traffic should follow detour signs.
- Monday, Sept. 15, 12 a.m. to 6 a.m. Multiple mainlane closures (3) on southbound I-35 from Schertz Parkway to Forum Parkway for bridge construction.
- Monday, Sept. 15, 12 a.m. to 6 a.m. Full closure on southbound I-35 frontage road and exit ramp from Evans Road to Arcadia Drive and northbound to southbound turnaround of Evans Road at I-35 intersection for drainage installation work. Traffic should follow detour signs.
- Monday, Sept. 15, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure on northbound I-35 frontage road from Olympia Parkway to Pasatiempo for asphalt paving. Traffic should follow detour signs.
- Monday, Sept. 15, until Thursday, Sept. 18, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Olympia Parkway to Forum Parkway for paving and bridge deck work. Traffic should follow detour signs.
- Monday, Sept. 15, until Friday, Sept. 19, 8 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Evans Road to Arcadia Drive and northbound to southbound turnaround of Evans Road at I-35 intersection for column cap setting. Traffic should follow detour signs.
- Monday, Sept. 15, until Friday, Sept. 19, 8 p.m. to 5 a.m. Multiple main lane (3) closures on southbound I-35 from Evans to Olympia for column cap setting. Traffic should follow detour signs.
- Tuesday, Sept. 16, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from Corporate Drive to Evans Road and Evans Road at I-35 intersection for bridge structure work. Traffic should follow detour signs.
- Thursday, Sept. 18, until Saturday, Sept. 20, 8 p.m. to 6 a.m. Multiple mainlane closures (3) on southbound I-35 from Schertz Parkway to Forum Parkway for bridge deck pour, traffic shift, and lane striping.
- Friday, Sept. 19, 9 p.m. to 9 a.m. Full closure on southbound I-35 frontage road and exit ramp from Evans Road to Arcadia Drive and northbound to southbound turnaround of Evans Road at I-35 intersection for column cap setting. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 9 a.m. Multiple main lane (3) closures on southbound I-35 from Evans to Olympia for column cap setting. Traffic should follow detour signs.
- Friday, Sept. 19, until Monday, Sept. 22, 8 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Evans Road to Arcadia Drive and northbound to southbound turnaround of Evans Road at I-35 intersection for drainage installation work. Traffic should follow detour signs.
I-35 and Loop 1604 Interchange
Northbound
- Through Monday, Oct. 20, long-term closure (24/7). Entrance ramp closure on I-35 northbound collector distributor to I-35 northbound mainlanes for construction work.
- Sunday, Sept. 14, until Saturday, Sept. 20, 8 p.m. to 6 a.m. Full closure on northbound I-35 collector distributor at Loop 1604 interchange, northbound I-35 frontage road from Pat Booker Road to Loop 1604 interchange and westbound Loop 1604 frontage road at Agora Parkway to I-35 frontage road at Forum Parkway for traffic switch, barrier, cap work. Traffic should follow detour signs.
- Monday, Sept. 15, until Friday, Sept. 19, 8 p.m. to 5 a.m. Full closure on northbound I-35 exit ramp and entrance ramp at Toepperwein Road, I-35 northbound collector distributor, northbound I-35 frontage road from Pat Booker Road to Loop 1604 and westbound Loop 1604 frontage road from Agora Parkway to Forum Parkway for bridge beam setting. Traffic should follow detour signs.
- Monday, Sept. 15, until Friday, Sept. 19, 9 p.m. to 5 a.m. Multiple mainlane closures (3) of northbound I-35 from I-35 Access Road bridge near Shin Oak Drive to Forum Parkway for bridge structure work.
- Monday, Sept. 15, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Multiple mainlane closures (3), exit ramp of northbound I-35 from I-35 Access Road bridge near Shin Oak Drive to Forum Parkway for bridge structure work. Traffic should use next available ramps.
- Monday, Sept. 15, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure of northbound I-35 collector distributor at Loop 1604 interchange, northbound I-35 bypass bridge at Pat Booker Road, and westbound Loop 1604 frontage road at Agora Parkway to northbound I-35 frontage road at Forum Parkway for column, cap, and bridge beam work. Traffic should follow detour signs.
- Tuesday, Sept. 16, until Thursday, Sept. 18, 9 p.m. to 5 a.m. Full closure on westbound Loop 1604 mainlanes from Pat Booker Road to Gateway Boulevard, westbound Loop 1604 collector distributor at I-35 interchange, northbound I-35 ramp to westbound Loop 1604 mainlanes, and southbound I-35 collector distributor at Loop 1604 interchange for steel girders welding work. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Multiple mainlane closures (3) of northbound I-35 from I-35 Access Road bridge near Shin Oak Drive to Forum Parkway for bridge structure work.
- Friday, Sept. 19, 9 p.m. to 9 a.m. Full closure on northbound I-35 exit ramp and entrance ramp at Toepperwein Road, I-35 northbound collector distributor, northbound I-35 frontage road from Pat Booker Road to Loop 1604 and westbound Loop 1604 frontage road from Agora Parkway to Forum Parkway for bridge beam setting. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure of northbound I-35 collector distributor at Loop 1604 interchange, northbound I-35 bypass bridge at Pat Booker Road, and westbound Loop 1604 frontage road at Agora Parkway to northbound I-35 frontage road at Forum Parkway for column, cap, and bridge beam work. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure on westbound Loop 1604 mainlanes from Pat Booker Road to Gateway Boulevard, westbound Loop 1604 collector distributor at I-35 interchange, northbound I-35 ramp to westbound Loop 1604 mainlanes, and southbound I-35 collector distributor at Loop 1604 interchange for bridge deck work. Traffic should follow detour signs.
Southbound
- Through Monday, Oct. 20, long-term closure (24/7). Right lane closure on I-35 southbound connector ramp to Loop 1604 westbound mainlanes for construction work.
- Sunday, Sept. 14, until Thursday, Sept. 18, 9 p.m. to 5 a.m. Multiple mainlane closures (3) of southbound I-35 from Forum Parkway to Ferrell Road for bridge deck work.
- Sunday, Sept. 14, until Tuesday, Sept. 16, 9 p.m. to 5 a.m. Full closure on eastbound Loop 1604 frontage road at IKEA-RBFCU Parkway to southbound I-35 frontage road at Pat Booker Road, eastbound Loop 1604 ramp to southbound I-35 mainlanes, and southbound I-35 collector distributor closure at the Loop 1604 interchange for bridge deck work. Traffic should follow detour signs.
- Sunday, Sept. 14, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Full closure on westbound Loop 1604 collector distributor at I-35 interchange, southbound I-35 collector distributor at Loop 1604 interchange, northbound I-35 ramp to westbound Loop1604 mainlanes, eastbound Loop 1604 collector distributor at I-35 interchange, northbound I-35 exit ramp to Olympia Parkway, eastbound Loop 1604 frontage road from IKEA-RBFCU Parkway entrance ramp to McMorris Boulevard, and IKEA-RBFCU Parkway intersection at Loop 1604 for barrier movement and striping. Traffic should follow detour signs.
- Monday, Sept. 15, until Friday, Sept. 19, 8 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from Arcadia Drive to Olympia Parkway, southbound I-35 entrance ramp at Old Austin Road, southbound I-35 collector distributor, westbound Loop 1604 collector distributor, eastbound Loop 1604 frontage road from IKEA-RBFCU Parkway entrance ramp to IKEA-RBFCU Parkway intersection, and IKEA-RBFCU Parkway intersection at Loop 1604 for column cap setting. Traffic should follow detour signs.
- Monday, Sept. 15, until Saturday, Sept. 20, 8 p.m. to 6 a.m. Full closure on southbound I-35 frontage road from Arcadia Drive to Olympia Parkway, southbound I-35 entrance ramp at Old Austin Road, westbound I-35 collector distributor, northbound and southbound I-35 ramp to westbound Loop 1604 mainlanes, eastbound Loop 1604 frontage road from IKEA-RBFCU Parkway entrance ramp to IKEA-RBFCU Parkway intersection, and IKEA-RBFCU Parkway intersection at Loop 1604 for column cap work and traffic switch. Traffic should follow detour signs.
- Monday, Sept. 15, until Friday, Sept. 19, 8 p.m. to 6 a.m. Full closure on southbound I-35 frontage road from Arcadia Drive to Olympia Parkway, entrance ramp closure at Old Austin Road, full closure on westbound Loop 1604 collector distributor at I-35 interchange and northbound I-35 ramp to westbound Loop 1604 mainlanes, southbound I-35 collector distributor to westbound Loop 1604 mainlanes, eastbound Loop 1604 frontage road from entrance ramp to IKEA-RBFCU Parkway intersection, and IKEA-RBFCU Parkway intersection at Loop 1604 for column, cap, and bridge deck work. Traffic should follow detour signs.
- Monday, Sept. 15, until Friday, Sept. 19, 8 p.m. to 6 a.m. Multiple mainlane closures (3) on southbound I-35 from Forum Parkway to McMorris Boulevard for bridge column and cap work.
- Monday, Sept. 15, until Friday, Sept. 19, 8 p.m. to 5 a.m. Multiple mainlane closures (3) on southbound I-35 from Forum Parkway to IKEA-RBFCU Parkway for column cap setting.
- Monday, Sept. 15, until Friday, Sept. 19, 8 p.m. to 5 a.m. Full closure on southbound I-35 collector distributor at Loop 1604 interchange for column cap setting. Traffic should follow detour signs.
- Thursday, Sept. 18, until Saturday, Sept. 20, 8 p.m. to 6 a.m. Multiple mainlane closures (3) of southbound I-35 from Forum Parkway to Ferrell Road for bridge deck work.
- Monday, Sept. 15, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure on westbound Loop 1604 mainlanes from Pat Booker Road to Gateway Boulevard, westbound Loop 1604 collector distributor at I-35 interchange, northbound I-35 ramp to westbound Loop 1604 mainlanes, and southbound I-35 collector distributor at Loop 1604 interchange for bridge deck work. Traffic should follow detour signs.
- Wednesday, Sept. 17, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 mainlanes from Gateway Boulevard to Pat Booker Road, eastbound Loop 1604 collector distributor at I-35 interchange and southbound I-35 collector distributor at Loop 1604 interchange for steel girder work. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 9 a.m. Multiple mainlane closures (3) on southbound I-35 from Forum Parkway to IKEA-RBFCU Parkway for column cap setting.
- Friday, Sept. 19, 9 p.m. to 9 a.m. Full closure on southbound I-35 collector distributor at Loop 1604 interchange for column cap setting. Traffic should follow detour signs.
- Friday, Sept. 19, 8 p.m. to 7 a.m. Multiple mainlane closures (3) on southbound I-35 from Forum Parkway to McMorris Boulevard for bridge column and cap work.
- Friday, Sept. 19, 8 p.m. to 7 a.m. Full closure on southbound I-35 frontage road from Arcadia Drive to Olympia Parkway, entrance ramp closure at Old Austin Road, full closure on westbound Loop 1604 collector distributor at I-35 interchange and northbound I-35 ramp to westbound Loop 1604 mainlanes, southbound I-35 collector distributor to westbound Loop 1604 mainlanes, eastbound Loop 1604 frontage road from entrance ramp to IKEA-RBFCU Parkway intersection, and IKEA-RBFCU Parkway intersection at Loop 1604 for column, cap, and bridge deck work. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 9 a.m. Full closure on southbound I-35 frontage road from Arcadia Drive to Olympia Parkway, southbound I-35 entrance ramp at Old Austin Road, southbound I-35 collector distributor, westbound Loop 1604 collector distributor, eastbound Loop 1604 frontage road from IKEA-RBFCU Parkway entrance ramp to IKEA-RBFCU Parkway intersection, and IKEA-RBFCU Parkway intersection at Loop 1604 for column cap setting. Traffic should follow detour signs.
Loop 1604 from I-35 Interchange to Nacogdoches Road
Eastbound
- Through Monday, Sept. 29, long-term closure (24/7). Left lane closure on eastbound frontage road of Loop 1604 from Lookout Road to IKEA-RBFCU Boulevard for construction.
- Monday, Sept. 15, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure on eastbound Loop 1604 frontage road, and exit ramp closure from Lookout Road to IKEA-RBFCU Parkway intersection and westbound to eastbound turnaround of Lookout Road at Loop 1604 intersection for bridge deck work. Traffic follows the detour signs.
- Monday, Sept. 15, until Wednesday, Sept. 17, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 collector distributor at I-35 interchange and eastbound Loop 1604 entrance ramp from Lookout Road to IKEA-RBFCU Parkway For Bridge deck work. Traffic to follow detour sign.
- Monday, Sept. 15, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 mainlanes from Nacogdoches Road to Pat Booker Road for bridge deck work. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure on eastbound Loop 1604 frontage road, and exit ramp closure from Lookout Road to IKEA-RBFCU Parkway intersection and westbound to eastbound turnaround of Lookout Road at Loop 1604 intersection for bridge deck work. Traffic follows the detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure of eastbound Loop 1604 mainlanes from Nacogdoches Road to Pat Booker Road for bridge deck work. Traffic should follow detour signs.
Westbound
- Through Monday, Sept. 29, long-term closure (24/7). Full closure on Loop 1604 westbound to eastbound turnaround at Lookout Road for construction work.
- Through Monday, Sept. 29, long-term closure (24/7). Entrance ramp closure on Loop 1604 westbound from Union Pacific Railroad to Loop 1604 westbound mainlanes for construction.
- Monday, Sept. 15, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 frontage road from Gateway Boulevard to Gateway Place for bridge deck work. Traffic should follow detour signs.
- Monday, Sept. 15, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure on westbound Loop 1604 frontage road, and exit ramp from Lookout Road to Nacogdoches Road and eastbound to westbound turnarounds at Union Pacific Railroad and Lookout Road intersection at Loop 1604 for bridge deck work. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure of westbound Loop 1604 frontage road from Gateway Boulevard to Gateway Place for bridge deck work. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure on westbound Loop 1604 frontage road, and exit ramp from Lookout Road to Nacogdoches Road and eastbound to westbound turnarounds at Union Pacific Railroad and Lookout Road intersection at Loop 1604 for bridge deck work. Traffic should follow detour signs.
I-35 from Loop 1604 to Toepperwein Road
Northbound
- Through Tuesday, Sept. 30, long-term closure (24/7). Full closure on I-35 northbound collector exit ramp.
- Through Tuesday, Sept. 30, long-term closure (24/7). Entrance ramp closure from I-35 northbound collector distributor to I-35 northbound mainlanes for construction work.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure of eastbound and westbound lanes of Toepperwein Road at I-35 intersection for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, Sept. 14, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road, exit ramp, and entrance ramp from Pat Booker Road to Loop 1604 interchange for bridge staddle bent cap work. Traffic should follow detour signs.
- Sunday, Sept. 14, until Saturday, Sept. 20, 9 a.m. to 5 p.m. Full closure on Sandpiper Drive at northbound I-35 frontage road for utilities work. Traffic should follow detour signs.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, entrance ramp and exit ramp closures from Toepperwein Road to Pat Booker Road for drilled shaft, column, and cap work.
- Sunday, Sept. 14, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Full closure of I-35 access road on northbound of I-35 from Shin Oak Drive to Pat booker Road for utility work. Traffic follows detour sign.
- Monday, Sept. 15, until Saturday, Sept. 20, 8 p.m. to 6 a.m. Full closure of northbound I-35 frontage road from Shin Oak Drive to Pat Booker Road for bridge structure work. Traffic should follow detour signs.
- Monday, Sept. 15, until Friday, Sept. 19, 8 p.m. to 5 a.m. Multiple main lane closures (2) on northbound I-35 from Pat Booker Road to Loop 1604 for bridge beam setting. Traffic should follow detour signs.
- Monday, Sept. 15, until Saturday, Sept. 20, 8 p.m. to 6 a.m. Full closure of northbound I-35 Access Road from Shin Oak Drive to Pat Booker Road for cap work. Traffic should follow detour signs.
- Tuesday, Sept. 16, 8 p.m. to 6 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, entrance ramp and exit ramp closures from Toepperwein Road to Pat Booker Road for drilled shaft, column, and cap work.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure of eastbound and westbound lanes of Toepperwein Road at I-35 intersection for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 9 a.m. Multiple main lane closures (2) on northbound I-35 from Pat Booker Road to Loop 1604 for bridge beam setting. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, entrance ramp and exit ramp closures from Toepperwein Road to Pat Booker Road for drilled shaft, column, and cap work.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Full closure of eastbound and westbound lanes of Toepperwein Road at I-35 intersection for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, entrance ramp and exit ramp closures from Toepperwein Road to Pat Booker Road for drilled shaft, column, and cap work.
Southbound
- Through Monday, Oct. 20, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from McMorris Boulevard to Pat Booker Road for construction.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Shin Oak Drive to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure from Pat Booker Road to Toepperwein Road for column, cap, and bridge deck work.
- Tuesday, Sept. 16, 8 p.m. to 6 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Shin Oak Drive to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Tuesday, Sept. 16, 8 p.m. to 6 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure from Pat Booker Road to Toepperwein Road for column, cap, and bridge deck work.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Shin Oak Drive to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure from Pat Booker Road to Toepperwein Road for column, cap, and bridge deck work.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Shin Oak Drive to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure from Pat Booker Road to Toepperwein Road for column, cap, and bridge deck work.
Eastbound
- No closures at this time.
I-35 from Toepperwein Road to O’Connor Road
Northbound
- Through Tuesday, Sept. 30, long-term closure (24/7). Right lane closure on northbound I-35 frontage road from O’Connor Road to Bludau-Bishop Road for construction work.
- Through Friday, Dec. 11, long-term closure (24/7). Exit ramp closure on I-35 northbound mainlanes to O’Connor Road for construction work.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp closure from Judson Road to Toepperwein Road for drilled shaft, column, and cap work.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp and entrance ramp closures from O'Connor Road to Judson Road for drilled shaft, column, and cap work.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road, entrance ramp and exit ramp from O'Connor Road to Judson Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road and exit ramp from Judson Road to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs
- Friday, Sept. 19, 9 p.m. to 7 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp closure from Judson Road to Toepperwein Road for drilled shaft, column, and cap work.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road and exit ramp from Judson Road to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp and entrance ramp closures from O'Connor Road to Judson Road for drilled shaft, column, and cap work.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road, entrance ramp and exit ramp from O'Connor Road to Judson Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp and entrance ramp closures from O'Connor Road to Judson Road for drilled shaft, column, and cap work.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp closure from Judson Road to Toepperwein Road for drilled shaft, column, and cap work.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Full closure of northbound I-35 frontage road and exit ramp from Judson Road to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Full closure of northbound I-35 frontage road, entrance ramp and exit ramp from O'Connor Road to Judson Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
Southbound
- Through Sunday Sept. 14, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 at Crownpoint Drive for construction work.
- Through Sunday, Sept. 14, long-term closure (24/7). Full closure on Crownpoint Drive for utility work.
- Through Thursday, Sept. 25, long-term closure (24/7). Entrance ramp closure on I-35 southbound frontage road from O’Connor Road to I-35 southbound mainlanes for construction work.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, and exit ramp from Toepperwein Road to Judson Road for bridge deck work.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Judson Road to Crownpoint Drive for column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Crownpoint Drive to O'Connor Road for cap form work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Toepperwein Road to Judson Road for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp, and exit ramp closure from Judson Road to O'Connor Road for drilled shaft, column, and cap work.
- Tuesday, Sept. 16, 8 p.m. to 6 a.m. Full closure on southbound I-35 frontage road and exit ramp from Crownpoint Drive to O'Connor Road for cap form work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, and exit ramp from Toepperwein Road to Judson Road for bridge deck work.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp, and exit ramp closure from Judson Road to O'Connor Road for drilled shaft, column, and cap work.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Judson Road to Crownpoint Drive for column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road and exit ramp from Crownpoint Drive to O'Connor Road for cap form work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road and exit ramp from Toepperwein Road to Judson Road for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, and exit ramp from Toepperwein Road to Judson Road for bridge deck work.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp, and exit ramp closure from Judson Road to O'Connor Road for drilled shaft, column, and cap work.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Judson Road to Crownpoint Drive for column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Full closure on southbound I-35 frontage road and exit ramp from Crownpoint Drive to O'Connor Road for cap form work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Full closure on southbound I-35 frontage road and exit ramp from Toepperwein Road to Judson Road for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
I-35 from O'Connor Road to Thousand Oaks Drive
Northbound
- Through Friday, Dec. 11, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Weidner Road to O’Connor Road for bridge work.
- Through Monday, Sept. 29, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Starlight Terrace to Weidner Road for construction work.
- Through Tuesday, Sept. 30, long-term closure (24/7). Full closure on I-35 northbound to southbound turnaround at Weidner Road for construction work.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure on northbound I-35 frontage road from Weidner Road to O'Connor Road for barrier and striping work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, Sept. 14, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road, entrance ramp, and exit ramp from Starlight Terrace to Weidner Road, southbound to northbound turnaround at I-35 and Starlight Terrace intersection, northbound to southbound turnaround at I-35 and Weidner Road intersection for barrier slipping, temporary barriers moving. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure on northbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to O'Connor Road, southbound to northbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, alternating lane closures (2) on northbound I-35 frontage road, and exit ramp closure from Starlight Terrace to Weidner Road for drainage and drilled shaft work.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road, entrance ramp, and exit ramp from Starlight Terrace to Weidner Road, southbound to northbound turnaround at I-35 and Starlight Terrace intersection, northbound to southbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, multiple lane closures (2) of northbound I-35 frontage road, entrance ramp from Weidner Road to O'Connor Road for drainage and drilled shaft work.
- Monday, Sept. 15, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road from Crestway Drive to Weidner Road and Starlight Terrace at I-35 intersection for cap work. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure on northbound I-35 frontage road from Weidner Road to O'Connor Road for barrier and striping work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, multiple lane closures (2) of northbound I-35 frontage road, entrance ramp from Weidner Road to O'Connor Road for drainage and drilled shaft work.
- Friday, Sept. 19, 11 p.m. to 7 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, alternating lane closures (2) on northbound I-35 frontage road, and exit ramp closure from Starlight Terrace to Weidner Road for drainage and drilled shaft work.
- Friday, Sept. 19, until Saturday, Sept. 20, 11 p.m. to 7 a.m. Full closure of northbound I-35 frontage road from Crestway Drive to Weidner Road and Starlight Terrace at I-35 intersection for cap work. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure on northbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to O'Connor Road, southbound to northbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Friday, Sept. 19, 11 p.m. to 7 a.m. Full closure on southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive for sidewalk and curb installation work. Traffic should follow detour signs.
- Friday, Sept. 19, 11 p.m. to 7 a.m. Full closure of northbound I-35 frontage road, entrance ramp, and exit ramp from Starlight Terrace to Weidner Road, southbound to northbound turnaround at I-35 and Starlight Terrace intersection, northbound to southbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, multiple lane closures (2) of northbound I-35 frontage road, entrance ramp from Weidner Road to O'Connor Road for drainage and drilled shaft work.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, alternating lane closures (2) on northbound I-35 frontage road, and exit ramp closure from Thousand Oaks Drive/Starlight Terrace to Weidner Road for drainage and drilled shaft work.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Full closure of northbound I-35 frontage road, entrance ramp, and exit ramp from Starlight Terrace to Weidner Road, southbound to northbound turnaround at I-35 and Starlight Terrace intersection, northbound to southbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Full closure on northbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to O'Connor Road, southbound to northbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Full closure on northbound I-35 frontage road from Weidner Road to O'Connor Road for barrier and striping work. Accommodations will be made for local traffic. Traffic should follow detour signs.
Southbound
- Through Tuesday, Sept. 30, long-term closure (24/7). Right lane closure on southbound frontage road of I-35 from Weidner Road to Thousand Oaks Drive for bridge work.
- Through Tuesday, Sept. 30, long-term closure (24/7). Entrance ramp closure on southbound I-35 from O’Connor Road for bridge work.
- Through Tuesday, Sept. 30, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from Tech Com to Weidner Road for construction work.
- Through Tuesday, Sept. 30, long-term closure (24/7). Full closure on I-35 southbound to northbound turnaround at Weidner Road for construction work.
- Through Wednesday, Oct. 8, long-term closure (24/7). Exit ramp closure on I-35 southbound mainlanes to Weidner Road for construction work.
- Sunday, Sept. 14, until Tuesday, Sept. 16, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from Tech Com Drive to Weidner Road for cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, Sept. 14, until Tuesday, Sept. 16, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from O'Connor Road to Tech Com Drive for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, Sept. 14, until Friday, Sept. 19, 8 p.m. to 5 a.m. Full closure of southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive for cap work and drainage work. Traffic should follow detour signs.
- Sunday, Sept. 14, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive for cap work and drainage work. Traffic should follow detour signs.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, exit ramp from O'Connor Road to Weidner Road for cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, and entrance ramp and exit ramp closures from Weidner Road to Thousand Oaks Drive for drainage and drilled shaft work.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, alternating lane closures (2) on southbound I-35 frontage road, and exit ramp closure from O'Connor Road to Weidner Road for drilled shaft, column, and cap work.
- Monday, Sept. 15, until Friday, Sept. 19, 8 p.m. to 5 a.m. Multiple mainlane closures (3) on southbound I-35 from Weidner Road to Thousand Oaks Drive for column cap setting.
- Monday, Sept. 15, until Friday, Sept. 19, 8 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive and northbound to southbound turnaround of Weidner Road at I-35 intersection for column cap setting. Traffic should follow detour signs.
- Tuesday, Sept. 16, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Tech Com Drive to Weidner Road for cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Tuesday, Sept. 16, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, and exit ramp from O'Connor Road to Tech Com Drive for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Tuesday, Sept. 16, 8 p.m. to 6 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp, and exit ramp closure from Judson Road to O'Connor Road for drilled shaft, column, and cap work.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road and exit ramp from Tech Com Drive to Weidner Road for cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road, exit ramp from O'Connor Road to Weidner Road for cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Friday, Sept. 19, 11 p.m. to 9 a.m. Multiple mainlane closures (3) on southbound I-35 from Weidner Road to Thousand Oaks Drive for column cap setting.
- Friday, Sept. 19, 11 p.m. to 9 a.m. Full closure on southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive and northbound to southbound turnaround of Weidner Road at I-35 intersection for column cap setting. Traffic should follow detour signs.
- Friday, Sept. 19, 11 p.m. to 7 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, and entrance ramp and exit ramp closures from Weidner Road to Thousand Oaks Drive for drainage and drilled shaft work.
- Friday, Sept. 19, 11 p.m. to 5 a.m. Full closure of northbound I-35 frontage road, entrance ramp, and exit ramp from Starlight Terrace to Weidner Road, southbound to northbound turnaround at I-35 and Starlight Terrace intersection, northbound to southbound turnaround at I-35 and Weidner Road intersection for barrier slipping, temporary barriers moving. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, alternating lane closures (2) on southbound I-35 frontage road, and exit ramp closure from O'Connor Road to Weidner Road for drilled shaft, column, and cap work.
- Friday, Sept. 19, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road, and exit ramp from O'Connor Road to Tech Com Drive for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Friday, Sept. 19, 11 p.m. to 5 a.m. Full closure of southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive for cap work and drainage work. Traffic should follow detour signs.
- Friday, Sept. 19, until Saturday, Sept. 20, 11 p.m. to 7 a.m. Full closure of southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive for cap work and drainage work. Traffic should follow detour signs.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Full closure on southbound I-35 frontage road and exit ramp from Tech Com Drive to Weidner Road for cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Full closure on southbound I-35 frontage road, exit ramp from O'Connor Road to Weidner Road for cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, and entrance ramp and exit ramp closures from Weidner Road to Thousand Oaks Drive for drainage and drilled shaft work.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, alternating lane closures (2) on southbound I-35 frontage road, and exit ramp closure from O'Connor Road to Weidner Road for drilled shaft, column, and cap work.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Full closure on southbound I-35 frontage road, and exit ramp from O'Connor Road to Tech Com Drive for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Saturday, Sept. 20, 9 p.m. to 8 a.m. Full closure on southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive for sidewalk and curb installation work. Traffic should follow detour signs.
I-35 from Thousand Oaks Drive to I-410 North Interchange
Northbound
- Through Monday, Sept. 29, long-term (24/7). Left lane closure on northbound frontage road of I-35 from Randolph Boulevard to Starlight Terrace for bridge work.
Southbound
- Through Tuesday, Sept. 30, long-term closure (24/7). Alternating lane closures on southbound I-35 frontage road between Thousand Oaks Drive and Whirlwind Drive for roadway reconstruction and structural work.
- Sunday, Sept. 14, until Friday, Sept. 19, 8 p.m. to 5 a.m. Multiple mainlane closures (3) on southbound I-35 from Thousand Oaks Drive to Randolph Boulevard for panel and deck work. Traffic should follow detour signs.
- Sunday, Sept. 14, until Friday, Sept. 19, 8 p.m. to 5 a.m. Full closure of southbound I-35 frontage road, and exit ramp from Thousand Oaks Drive to Randolph Boulevard, and northbound to southbound turnaround at Thousand Oaks Drive and I-35 intersection for panel and deck work. Traffic should follow detour signs.
- Sunday, Sept. 14, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Multiple mainlane closures (3) on southbound I-35 from Thousand Oaks Drive to Randolph Boulevard for panel and deck work. Traffic should follow detour signs.
- Monday, Sept. 15, until Friday, Sept. 19, 8 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Thousand Oaks Drive to Randolph Boulevard and northbound to southbound turnaround of Thousand Oaks Drive at I-35 intersection for bridge beam setting. Traffic should follow detour signs.
- Monday, Sept. 15, until Friday, Sept. 19, 8 p.m. to 5 a.m. Multiple main lane closures (3) on southbound I-35 from Thousand Oaks Drive to Randolph Boulevard for bridge beam setting. Traffic should follow detour signs.
- Friday, Sept. 19, 11 p.m. to 9 a.m. Multiple main lane closures (3) on southbound I-35 from Thousand Oaks Drive to Randolph Boulevard for bridge beam setting. Traffic should follow detour signs.
- Friday, Sept. 19, 11 p.m. to 5 a.m. Multiple mainlane closures (3) on southbound I-35 from Thousand Oaks Drive to Randolph Boulevard for panel and deck work. Traffic should follow detour signs.
- Friday, Sept. 19, until Saturday, Sept. 20, 8 p.m. to 7 a.m. Multiple mainlane closures (3) on southbound I-35 from Thousand Oaks Drive to Randolph Boulevard for panel and deck work. Traffic should follow detour signs.
- Friday, Sept. 19, until Saturday, Sept. 20, 8 p.m. to 7 a.m. Full closure of southbound I-35 frontage road, and exit ramp from Thousand Oaks Drive to Randolph Boulevard, and northbound to southbound turnaround at Thousand Oaks Drive and I-35 intersection for panel and deck work. Traffic should follow detour signs.
- Friday, Sept. 19, 11 p.m. to 9 a.m. Full closure on southbound I-35 frontage road and exit ramp from Thousand Oaks Drive to Randolph Boulevard and northbound to southbound turnaround of Thousand Oaks Drive at I-35 intersection for bridge beam setting. Traffic should follow detour signs.
I-35 and I-410 North Interchange
Northbound
- Sunday, Sept. 14, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Full closure of eastbound I-410 ramp to northbound I-35 mainlanes for cap work. Traffic should follow detour signs.
- Sunday, Sept. 14, until Friday, Sept. 19, 8 p.m. to 5 a.m. Full closure of northbound I-35 connector ramp to westbound I-410 mainlanes and entrance ramp closure from Randolph Boulevard to westbound I-410 mainlanes for cap work. Traffic should follow detour signs.
- Friday, Sept. 19, until Saturday, Sept. 20, 8 p.m. to 7 a.m. Full closure of northbound I-35 connector ramp to westbound I-410 mainlanes and entrance ramp closure from Randolph Boulevard to westbound I-410 mainlanes for cap work. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure of eastbound I-410 ramp to northbound I-35 mainlanes for cap work. Traffic should follow detour signs.
Southbound
- Sunday, Sept. 14, until Friday, Sept. 19, 8 p.m. to 5 a.m. Full closure of southbound I-35 ramp to westbound I-410 mainlanes for cap work. Traffic should follow detour signs.
- Monday, Sept. 15, until Friday, Sept. 19, 8 p.m. to 5 a.m. Full closure of southbound I-35 connector ramp to westbound I-410 main lanes, Randolph Boulevard intersection at I-35, and southbound I-35 frontage road from Randolph Boulevard to Fratt Road for bridge beam setting. Traffic should follow detour signs.
- Friday, Sept. 19, 11 p.m. to 9 a.m. Full closure of southbound I-35 connector ramp to westbound I-410 main lanes, Randolph Boulevard intersection at I-35, and southbound I-35 frontage road from Randolph Boulevard to Fratt Road for bridge beam setting. Traffic should follow detour signs.
- Friday, Sept. 19, until Saturday, Sept. 20, 8 p.m. to 7 a.m. Full closure of southbound I-35 ramp to westbound I-410 mainlanes for cap work. Traffic should follow detour signs.
I-410 North from Starcrest Drive to Harry Wurzbach Road
Eastbound
- No closures at this time.
Westbound
- No closures at this time.
I-410 North from I-35 Interchange to Starcrest Drive
Eastbound
- Through Monday, Sept. 29, long-term (24/7). Left lane closure on I-410 eastbound frontage road from Starcrest Drive to Perrin Beitel for construction work.
- Sunday, Sept. 14, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Multiple (2) lane closures on eastbound I-410 mainlanes from Perrin Beitel to Austin Highway exit ramp for deck work, barrier and shore tower setting.
- Sunday, Sept. 14, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Full closure on eastbound frontage road, westbound to eastbound turnaround closure, entrance ramp and exit ramp closure of I-410 from Starcrest Drive to Perrin Beitel for deck work. Traffic follows the detour signs.
- Sunday, Sept. 14, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Full closure of eastbound frontage road, close the eastbound to westbound turnaround, close the westbound to eastbound turnaround and close the entrance ramp on I-410 from Perrin Beitel to Vicar drive and full closure of Perrin Beitel intersection on I-410 for deck work. Traffic follows the detour signs.
- Sunday, Sept. 14, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Entrance ramp closure from Perrin Beitel to Austin Highway (Loop 368) for cap work.
- Monday, Sept. 15, until Friday, Sept. 19, 8 p.m. to 5 a.m. Full closure of Austin Highway bridge from eastbound I-410 frontage road to westbound I-410 frontage road, full closure on eastbound I-410 frontage road from Perrin Beitel to Vicar Drive, and full closure on northbound Austin Highway (Loop 368) from Walzem Road to eastbound I-410 frontage road for bridge beam setting. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 9 a.m. Full closure of Austin Highway bridge from eastbound I-410 frontage road to westbound I-410 frontage road, full closure on eastbound I-410 frontage road from Perrin Beitel to Vicar Drive, and full closure on northbound Austin Highway (Loop 368) from Walzem Road to eastbound I-410 frontage road for bridge beam setting. Traffic should follow detour signs.
- Friday, Sept. 19, 9 p.m. to 5 a.m. Multiple (2) lane closures on eastbound I-410 mainlanes from Perrin Beitel to Austin Highway exit ramp for deck work, barrier, and shore tower setting.
- Friday, Sept. 19, 9 p.m. to 5 a.m. Entrance ramp closure from Perrin Beitel to Austin Highway (Loop 368) for cap work.
- Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure of eastbound frontage road, close the eastbound to westbound turnaround, close the westbound to eastbound turnaround and close the entrance ramp on I-410 from Perrin Beitel to Vicar drive and full closure of Perrin Beitel intersection on IH-410 for deck work. Traffic follows the detour signs.
Westbound
- Through Tuesday, Sept. 30, long-term closure (24/7). Left lane closure on westbound frontage road of I-410 from Perrin Creek to Austin Highway (Loop 368) for construction.
- Monday, Sept. 15, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure on westbound I-410 frontage road from Randolph Boulevard to Perrin Creek and northbound Austin Highway (Loop 368) frontage road from Interchange Parkway to westbound I-410 frontage road for deck work. Traffic should follow detour signs.
- Monday, Sept. 15, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure of entrance ramp on westbound I-410 frontage road to Austin Highway and exit ramp to Austin Highway (Loop 368) from westbound I-410 mainlanes for deck work. Traffic should follow detour signs.
- Wednesday, Sept. 17, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure of westbound I-410 frontage road and exit ramp from Perrin Creek to Perrin Beitel, and ramp from northbound Austin Highway (Loop 368) to westbound I-410 frontage road for bridge deck work. Traffic should follow detour signs.
- Friday, Sept. 19, until Saturday, Sept. 20, 9 p.m. to 7 a.m. Full closure of entrance ramp on westbound I-410 frontage road to Austin Highway and exit ramp to Austin Highway (Loop 368) from westbound I-410 mainlanes for deck work. Traffic should follow detour signs.
I-410 North from Starcrest Drive to Nacogdoches Road
Eastbound
- Through Tuesday, Sept. 30, long-term closure (24/7). Left lane closure on eastbound frontage road of I-410 from Harry Wurzbach to Starcrest Drive for construction work.
- Through Tuesday, Sept. 30, long-term closure (24/7). Exit ramp closure on I-410 eastbound mainlanes to Starcrest Drive for construction work.
- Sunday, Sept. 14, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Multiple mainlane closures (3), entrance ramp of eastbound I-410 from Harry Wurzbach Road to Quail Creek Drive, and the exit ramp to Starcrest & Perrin Beitel Road for drilled shaft work. Traffic should use previous exit ramp.
- Monday, Sept. 15, until Friday, Sept. 19, 9 p.m. to 5 a.m. Full closure of eastbound I-410 frontage road, and entrance ramp from Harry Wurzbach Road to Ira Lee Road, and westbound to eastbound turnaround at Harry Wurzbach Road and I-35 intersection, and eastbound frontage road bypass closure of I-410 from Harry Wurzbach Road to Ira Lee Road for drilled shaft work. Traffic should follow detour signs.
- Sunday, Sept. 14, until Friday, Sept. 19, 9 p.m. to 5 a.m. Left lane closure on eastbound I-410 mainlanes from Vandiver Road to Starcrest Drive and left lane closure on westbound I-410 mainlanes from Starcrest Drive to Vandiver Road for illumination work.
- Friday, Sept. 19, until Saturday, Sept. 20, 9 p.m. to 7 a.m. Full closure of eastbound I-410 frontage road, and entrance ramp from Harry Wurzbach Road to Ira Lee Road, and westbound to eastbound turnaround at Harry Wurzbach Road and I-35 intersection, and eastbound frontage road bypass closure of I-410 from Harry Wurzbach Road to Ira Lee Road for drilled shaft work. Traffic should follow detour signs.
- Friday, Sept. 19, until Saturday, Sept. 20, 9 p.m. to 7 a.m. Full closure on westbound I-410 frontage road from Randolph Boulevard to Perrin Creek and northbound Austin Highway (Loop 368) frontage road from Interchange Parkway to westbound I-410 frontage road for deck work. Traffic should follow detour signs.
- Friday, Sept. 19, 11 p.m. to 5 a.m. Multiple mainlane closures (3), entrance ramp of eastbound I-410 from Harry Wurzbach Road to Quail Creek Drive, and the exit ramp to Starcrest & Perrin Beitel Road for drilled shaft work. Traffic should use previous exit ramp.
Westbound
- No closures at this time.
I-410 North and Austin Highway (Loop 368)
Northbound
- No closures at this time.
Southbound
- No closures at this time.
I-35 from I-410 North Interchange to Walzem Road
Northbound
- Sunday, Sept. 14, until Saturday, Sept. 20, 9 p.m. to 5 a.m. Southbound to northbound turnaround closure at Walzem Road and I-35 intersection, alternating lane closures (2) on northbound I-35 frontage road, and alternating entrance and exit ramp closures from Walzem Road to Crestway Drive for cap and column work.
- Friday, Sept. 19, 11 p.m. to 5 a.m. Southbound to northbound turnaround closure at Walzem Road and I-35 intersection, alternating lane closures (2) on northbound I-35 frontage road, and alternating entrance and exit ramp closures from Walzem Road to Crestway Drive for cap and column work.
Southbound
- Sunday, Sept. 14, until Friday, Sept. 19, 8 p.m. to 5 a.m. Full closure of eastbound I-410 to southbound I-35 connector ramp and full closure of southbound frontage road of I-35 from Fratt Road to Walzem Road for construction work. Traffic follows detour signs.
- Friday, Sept. 19, until Saturday, Sept. 20, 8 p.m. to 7 a.m. Full closure of eastbound I-410 to southbound I-35 connector ramp and full closure of southbound frontage road of I-35 from Fratt Road to Walzem Road for construction work. Traffic follows detour signs.
I-35 from Walzem Road to Eisenhauer Road
Northbound
- Sunday, Sept. 14, until Sunday, Sept. 21, 9 p.m. to 5 a.m. Multiple left lane closures (2) on northbound I-35 frontage road from Eisenhauer Road to Walzem Road for deck panel work.
- Sunday, Sept. 14, until Sunday, Sept. 21, 9 p.m. to 5 a.m. Multiple right lane closures (2) on northbound I-35 mainlanes from Eisenhauer Road to Walzem Road for bridge work.
- Sunday, Sept. 14, until Sunday, Sept. 21, 9 p.m. to 5 a.m. Exit ramp closure on northbound I-35 mainlanes between Eisenhauer Road and Walzem Road for superstructure work. Traffic should use previous exit.
Southbound
- No closures at this time.
I-35 from Eisenhauer Road to Rittiman Road
Northbound
- No closures at this time.
Southbound
- No closures at this time.
Eastbound
- No closures at this time.
Westbound
- No closures at this time.
I-35 from Rittiman Road to I-410 South Interchange
Northbound
- Through Friday, Sept. 19, long-term closure (24/7). Left lane closure on northbound I-35 frontage road from Greatfare to Rittiman Road for drainage and bridge work.
- Tuesday, Sept. 16, until Tuesday, Sept. 23, 9 p.m. to 5 a.m. Entrance ramp closure on northbound I-35 frontage road between Winnco Drive and Rittiman Road for drilled shaft work. Traffic should use next entrance ramp.
Southbound
- Through Sunday, Jan. 25, long-term closure (24/7). Left lane closure on southbound I-35 frontage road from Rittiman Road to Petroleum Drive for drilled shaft work.
- Sunday, Sept. 14, until Sunday, Sept. 21, 9 p.m. to 5 a.m. Multiple right lane closures (2) on southbound mainlanes of I-35 from Rittiman Road to Petroleum Drive for beam setting.
Eastbound
- No closures at this time.
I-35 and I-410 South Interchange
Northbound
- Monday, Sept. 15, until Saturday, Sept. 20, 9 p.m. to 7 a.m. Rolling closure on northbound and southbound mainlanes of I-35 from George Beach Avenue to Walzem Road and I-410 from Binz Engleman Road to Space Center Drive for sweeping and debris work.
- Tuesday, Sept. 16, until Tuesday, Sept. 23, 9 p.m. to 5 a.m. Left lane closure on northbound I-35 frontage road from Winnco Drive to Space Center Drive for drilled shaft work.
Southbound
- Sunday, Sept. 14, until Sunday, Sept. 21, 9 p.m. to 5 a.m. Full closure on southbound I-35 connector ramp and entrance ramp to I-410 South for cap work. Traffic should follow detour signs.
- Friday, Sept. 19, until Sunday, Sept. 21, 11 p.m. to 8 a.m. Full closure of southbound I-35 frontage road entrance ramp to southbound I-410 South for column work. Traffic should follow detour signs.
I-35 from I-410 South to Petroleum Drive
Northbound
- No closures at this time.
Southbound
- Sunday, Sept. 14, until Sunday, Sept. 21, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from Tejasco to Petroleum Drive and exit ramp closure on southbound I-35 mainlanes to George Beach Avenue for cap work. Traffic should follow detour signs.
I-410 South from I-35 to Binz Engleman Road
Northbound
- Sunday, Sept. 14, until Tuesday, Sept. 16, 9 p.m. to 5 a.m. Left lane closure on northbound and southbound I-410 mainlanes from Binz-Engleman Road to Space Center Drive for roadway work.
- Sunday, Sept. 14, until Sunday, Sept. 21, 9 p.m. to 5 a.m. Entrance ramp closure on northbound I-410 frontage road between Binz Engleman and Space Center Drive for superstructure work. Traffic should use next entrance ramp.
- Sunday, Sept. 14, until Sunday, Sept. 21, 9 p.m. to 5 a.m. Left lane closure on northbound I-410 frontage road from Macro to Rittiman Road for beam setting.
- Sunday, Sept. 14, until Sunday, Sept. 21, 9 p.m. to 5 a.m. Right lane closure on northbound I-410 mainlanes from Binz Engleman Road to Space Center Drive for beam setting.
Southbound
- Through Thursday, Sept. 18, long-term closure (24/7). Left lane closure on southbound I-410 frontage road from Winnco Drive to Binz Engleman Road for drainage work.
I-35/I-410 S Interchange to FM 78
Northbound
- No closures at this time.
Southbound
- No closures at this time.
Eastbound
- No closures at this time.
Westbound
- Monday, Sept. 15, 11 a.m. to 5 p.m. Full lane closure on westbound FM 78 from I-410 northbound frontage road to I-410 southbound frontage road for waterline testing.
Other lane closures
- For your information, there are other lane closures underway within the I-35 NEX project this week, but they are not expected to affect traffic or create notable delays.