Traffic impacts
Skip to main content

Traffic impacts

To provide the most accurate information about upcoming traffic impacts, the project team will provide as much notice as possible for lane closures and traffic switches. See below for a live map of traffic closures in San Antonio.

For a list of lane closures across Texas, visit TxDOT’s interative map website DriveTexas™.

I-35 NEX lane closures for June 8 - 14

This page is updated weekly. To find the most up to date and current lane closures, follow the TxDOT San Antonio District on social media or contact us for email updates at i35NEX@txdot.gov.

This week's lane closures (weather permitting and subject to change):

Maintenance

  • No closures at this time.

I-35 from FM 3009 to FM 1518

Northbound
  • Sunday, June 8, until Friday, June 13, 9 p.m. to 5 a.m. Multiple mainlane closures (3), exit ramp, and entrance ramp of northbound I-35 from Evans Road to Roy Richard Drive (FM 3009) for roadway work. Traffic should use next available ramps.
  • Monday, June 9, until Friday, June 13, 9 a.m. to 3 p.m. Rolling closure project-wide for sweeping.
Southbound
  • Through Sunday, July 13, long-term closure (24/7). Left lane closure on I-35 southbound frontage road from Schertz Parkway to FM 3009 for drainage work.
  • Sunday, June 8, until Saturday, June 14, 8 p.m. to 6 a.m. Multiple mainlane closures (3) on southbound I-35 from Schertz Parkway to Forum Parkway for bridge deck pour.
  • Sunday, June 8, until Wednesday, June 11, 9 p.m. to 5 a.m. Multiple mainlane closures (3), and entrance ramp, and exit ramp of southbound I-35 from Roy Richard Drive (FM 3009) to Schertz Parkway for column and cap work. Traffic should use next available ramps.
  • Thursday, June 12, until Saturday, June 14, 8 p.m. to 5 a.m. Full closure of southbound I-35 frontage road, entrance ramp and exit ramp from Schertz Parkway to Corporate Drive for bridge beam setting. Traffic should follow detour signs.
  • Thursday, June 12, until Saturday, June 14, 8 p.m. to 5 a.m. Multiple mainlane closures (3) on southbound I-35 from Schertz Parkway to Evans Road for bridge beam setting and cap setting.
  • Friday, June 13, until Monday, June 16, 8 p.m. to 6 a.m. Full closure of southbound I-35 frontage road, entrance ramp and exit ramp from Schertz Parkway to Corporate Drive for barrier and drainage work. Traffic should follow detour signs.

I-35 from FM 1518 to Loop 1604

Northbound
  • Through Saturday, Aug. 2, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Forum Parkway to Forum Access Road for construction work.
  • Through Sunday, July 20, long-term closure (24/7). Exit ramp closure on northbound I-35 to Evans Road for construction work.
  • Sunday, June 8, until Thursday, June 12, 9 p.m. to 5 a.m. Full closure of Evans Road and northbound to southbound turnaround at I-35 intersection for bridge work. Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road and exit ramp from Forum Parkway to Olympia Parkway for cap work. Traffic should follow detour signs.
  • Sunday, June 8, until Friday, June 13, 9 p.m. to 5 a.m. Full closure of Corporate Drive at I-35 intersection for bridge Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, exit ramp, and entrance ramp from Forum Parkway to Evans Road for bridge deck work. Traffic should use next exit and entrance ramps.
  • Monday, June 9, 9 p.m. to 5 a.m. Full closure on northbound I-35 frontage road from Olympia Parkway to Pasatiempo for column and cap work. Traffic should follow detour signs.
  • Wednesday, June 11, until Saturday, June 14, 8 p.m. to 5 a.m. Multiple mainlane closures (3) on northbound I-35 from Forum Access Road to Pasatiempo for bridge beam setting.
  • Wednesday, June 11, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road and exit ramp from Forum Parkway to Evans Road for utility construction work. Traffic should follow detour signs.
  • Thursday, June 12, until Saturday, June 14, 8 p.m. to 5 a.m. Full closure of Corporate Drive at I-35 intersection for bridge beam setting. Traffic should follow detour signs.
Southbound
  • Through Tuesday, June 16, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from Forum Parkway to Old Austin Road for bridge and roadway work.
  • Through Tuesday, June 16, long-term closure (24/7). Right lane closure on I-35 southbound mainlanes from Olympia Parkway to Loop 1604 interchange for construction work.
  • Through Tuesday, June 16, long-term closure (24/7). Right lane closure on I-35 southbound collector distributor from Forum Parkway to Loop 1604 interchange for construction work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Olympia Parkway to Forum Parkway for bridge deck work. Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 8 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from Corporate Drive to Evans Road and Evans Road at I-35 intersection for bridge column and cap work. Traffic should follow detour signs.
  • Sunday, June 8, until Friday, June 13, 9 p.m. to 6 a.m. Full closure on southbound I-35 frontage road from Forum Parkway to Gateway Boulevard, southbound I-35 collector distributor at Loop 1604 interchange, and IKEA-RBFCU Parkway intersection at Loop 1604 for bridge structure work. Traffic should follow detour signs.
  • Sunday, June 8, until Wednesday, June 11, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from Old Austin Road to Forum Parkway and Forum Parkway intersection at I-35 for bridge substructure work. Traffic should follow the detour signs.
  • Sunday, June 8, until Saturday, June 14, 8 p.m. to 5 a.m. Multiple mainlane closures (3) of southbound I-35 from Forum Parkway to Ferrell Road for bridge deck work.
  • Sunday, June 8, until Saturday, June 14, 8 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from Arcadia Drive to Olympia Parkway, southbound I-35 entrance ramp at Old Austin Road, westbound I-35 collector distributor, northbound and southbound I-35 ramp to westbound Loop 1604 mainlanes, eastbound Loop 1604 frontage road from IKEA-RBFCU Parkway entrance ramp to IKEA-RBFCU Parkway intersection, and IKEA-RBFCU Parkway intersection at Loop 1604 for column cap work and traffic switch. Traffic should follow detour signs.
  • Sunday, June 8, until Wednesday, June 11, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from Retama Parkway to Forum Parkway for bridge deck work. Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 8 p.m. to 6 a.m. Full closure of southbound I-35 frontage road from Forum Parkway to Gateway Boulevard for bridge substructure work. Traffic should follow detour signs.
  • Sunday, June 8, until Wednesday, June 11, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Evans Road to Arcadia Drive and northbound to southbound turnaround of Evans Road at I-35 intersection for roadway work. Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Multiple mainlane closures (3) on southbound I-35 from Forum Parkway to McMorris Boulevard for bridge column and cap work.
  • Monday, June 9, until Saturday, June 14, 8 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from Corporate Drive to Evans Road and full closure of Evans Road intersection at I-35 for bridge beam setting. Traffic should follow detour signs.
  • Monday, June 9, until Thursday, June 12, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from Old Austin Road to Forum Parkway, westbound Loop 1604 frontage road at Agora Parkway to northbound I-35 frontage road at Forum Parkway and Forum Parkway Intersection at I-35 for column and cap work. Traffic should follow detour signs.
  • Wednesday, June 11, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Olympia Parkway to Forum Parkway for utility construction work. Traffic should follow detour signs.
  • Thursday, June 12, until Tuesday, June 17, 8 p.m. to 6 a.m. Full closure of southbound I-35 frontage road from Corporate Drive to Evans Road and Evans Road at I-35 intersection for bridge column and cap work. Traffic should follow detour signs.
  • Friday, June 13, until Monday, June 16, 8 p.m. to 6 a.m. Full closure of southbound I-35 frontage road from Corporate Drive to Evans Road and Evans Road at I-35 intersection for bridge column and cap work. Traffic should follow detour signs.
  • Friday, June 13, until Monday, June 16, 8 p.m. to 6 a.m. Full Weekend closure on southbound I-35 frontage road and exit ramp from Evans Road to Arcadia Drive and northbound to southbound turnaround of Evans Road at I-35 intersection for roadway work. Traffic should follow detour signs.

I-35 and Loop 1604 Interchange

Northbound
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure of northbound I-35 collector distributor at the Loop 1604 interchange for drilled shaft work. Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 8 p.m. to 5 a.m. Full closure on northbound I-35 collector distributor at Loop 1604 interchange, northbound I-35 frontage road from Pat Booker Road to Loop 1604 interchange and westbound Loop 1604 frontage road at Agora Parkway to I-35 frontage road at Forum Parkway for traffic switch, barrier, cap work. Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 8 p.m. to 5 a.m. Full closure on westbound Loop 1604 frontage road to northbound I-35 frontage road, and northbound I-35 connector ramp from Agora Parkway to Forum Parkway for column and cap work. Traffic should follow detour signs.
Southbound
  • Through Tuesday, June 16, long-term closure (24/7). Right lane closure on I-35 southbound connector ramp to Loop 1604 westbound mainlanes for construction work.
  • Sunday, June 8, until Wednesday, June 11, 9 p.m. to 5 a.m. Full closure on eastbound Loop 1604 frontage road at IKEA-RBFCU Parkway to southbound I-35 frontage road at Pat Booker Road, eastbound Loop 1604 ramp to southbound I-35 mainlanes, and southbound I-35 collector distributor closure at the Loop 1604 interchange for bridge deck work. Traffic should follow detour signs.
  • Sunday, June 8, until Friday, June 13, 9 p.m. to 5 a.m. Full closure on westbound Loop 1604 collector distributor at I-35 interchange, southbound I-35 collector distributor at Loop 1604 interchange, northbound and southbound I-35 ramps to westbound Loop1604 mainlanes, eastbound Loop 1604 ramp to northbound and southbound I-35 mainlanes, northbound I-35 exit ramp to Olympia Parkway, eastbound Loop 1604 frontage road from IKEA-RBFCU Parkway entrance ramp to McMorris Boulevard, and IKEA-RBFCU Parkway intersection at Loop 1604 for bridge column, cap, and deck work. Traffic should follow detour signs.

Loop 1604 from I-35 Interchange to Nacogdoches Road

Eastbound
  • Through Sunday, Aug. 17, long-term closure (24/7). Left lane closure on eastbound frontage road of Loop 1604 from Lookout Road to IKEA-RBFCU Boulevard for construction.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 collector distributor at I-35 interchange and eastbound Loop 1604 entrance ramp from Lookout Road to IKEA-RBFCU Parkway for bridge column and cap work. Traffic should follow detour signs.
  • Monday, June 9, until Wednesday, June 11, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 mainlanes from Lookout Road to Pat Booker Road for bridge deck work. Traffic should follow detour signs.
  • Monday, June 9, until Saturday, June 14, 9 p.m. to 5 a.m. Alternating mainlane closures of eastbound Loop 1604 from Nacogdoches Road to Pat Booker Road for bridge column work.
  • Monday, June 9, until Wednesday, June 11, 9 p.m. to 5 a.m. Full closure on eastbound Loop 1604 frontage road, exit ramp, entrance ramp, and westbound to eastbound turnaround from Nacogdoches Road to Union Pacific Railroad for overhead sign board removal. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Wednesday, June 11, until Friday, June 13, 8 p.m. to 6 a.m. Full closure of eastbound Loop 1604 mainlanes from Gateway Boulevard to Pat Booker Road, eastbound Loop 1604 collector distributor at I-35 interchange and southbound I-35 collector distributor at Loop 1604 interchange for steel girder work. Traffic should follow detour signs.
Westbound
  • Through Thursday, June 26, long-term closure (24/7). Full closure on Loop 1604 westbound to eastbound turnaround at Lookout Road for construction work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure of Lookout Road and turnarounds at Loop 1604 intersection for bridge deck work. Traffic should follow detour signs.
  • Monday, June 9, until Wednesday, June 11, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 frontage road from Gateway Boulevard to Gateway Place for bridge deck work. Traffic should follow detour signs.
  • Monday, June 9, until Wednesday, June 11, 9 p.m. to 5 a.m. Alternating mainlane closures of westbound Loop 1604 from Pat Booker Road to Nacogdoches Road for bridge deck and barrier work.
  • Wednesday, June 11, until Saturday, June 14, 9 p.m. to 5 a.m. Alternating mainlane closures of westbound Loop 1604 from Pat Booker Road to Nacogdoches Road for bridge deck and barrier work.

I-35 from Loop 1604 to Toepperwein Road

Northbound
  • Through Monday, June 30, long-term closure (24/7). Full closure on I-35 northbound collector exit ramp.
  • Through Monday, June 30, long-term closure (24/7). Entrance ramp closure from I-35 northbound collector distributor to I-35 northbound mainlanes for construction work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, entrance ramp and exit ramp closures from Toepperwein Road to Pat Booker Road for drilled shaft, column, and cap work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure of I-35 access road on northbound of I-35 from Shin Oak Drive to Pat booker Road for utility work. Traffic follows detour sign.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Multiple mainlane closures (3) of northbound I-35 from I-35 Access Road bridge near Shin Oak Drive to Forum Parkway for bridge structure work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure of Pat Booker Road at I-35 intersection and northbound I-35 exit ramp to Pat Booker Road for bridge structure work. Traffic should follow detour signs.
  • Sunday, June 8, until Thursday, June 12, 9 p.m. to 5 a.m. Multiple mainlane closures (3), exit ramp of northbound I-35 from I-35 Access Road bridge near Shin Oak Drive to Forum Parkway for asphalt paving and traffic switch. Traffic should use next available ramps.
  • Sunday, June 8, until Saturday, June 14, 8 p.m. to 5 a.m. Full closure of northbound I-35 Access Road from Shin Oak Drive to Pat Booker Road for drilled shaft, column, and cap work. Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road from Shin Oak Drive to Pat Booker Road for bridge structure work. Traffic should follow detour signs.
  • Monday, June 9, until Thursday, June 12, 8 p.m. to 6 a.m. Multiple mainlane closures (2) on northbound I-35 from Pat Booker Road to Loop 1604 for column cap setting. Traffic should follow detour signs.
  • Monday, June 9, 9 p.m. to 5 a.m. Full closure of I-35 Access Road bridge near Shin Oak Drive at I-35 for bridge deck work. Traffic should follow detour signs.
Southbound
  • Through Tuesday, July 7, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from McMorris Boulevard to Pat Booker Road for construction.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Shin Oak Drive to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure from Pat Booker Road to Toepperwein Road for column, cap, and bridge deck work.
  • Sunday, June 8, until Tuesday, June 10, 8 p.m. to 6 a.m. Closure of southbound I-35 Pat Booker Road exit for bridge deck work. Traffic should follow detour signs.

I-35 from Toepperwein Road to O’Connor Road

Northbound
  • Through Monday, June 30, long-term closure (24/7). Right lane closure on northbound I-35 frontage road from O’Connor Road to Bludau-Bishop Road for construction work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp and entrance ramp closures from O’Connor Road to Judson Road for drilled shaft, column, and cap work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp closure from Judson Road to Toepperwein Road for drilled shaft, column, and cap work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road and exit ramp from Judson Road to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road, entrance ramp and exit ramp from O’Connor Road to Judson Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, June 8, 9 p.m. to 5 a.m. Full closure on the northbound frontage road of I-35 at Judson Intersection for construction work. Traffic follows detour signs.
  • Monday, June 9, 9 p.m. to 5 a.m. Full closure on northbound mainlanes of I-35 from Judson Road exit ramp to Toepperwein Road exit ramp for traffic signal equipment installation.
Southbound
  • Through Monday, June 30, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 at Crownpoint Drive for construction work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Toepperwein Road to Judson Road for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Judson Road to Crownpoint Drive for column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, and exit ramp closure from Toepperwein Road to Judson Road for bridge deck work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp, and exit ramp closure from Judson Road to O’Connor Road for drilled shaft, column, and cap work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Crownpoint Drive to O’Connor Road for cap form work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Monday, June 9, until Saturday, June 14, 8 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Crownpoint Drive to O’Connor Road for column cap setting. Traffic should follow detour signs.
  • Monday, June 9, until Saturday, June 14, 8 p.m. to 5 a.m. Multiple mainlane closures (3) on southbound I-35 from Judson Road to O’Connor Road for column cap setting.
  • Monday, June 9, until Saturday, June 14, 8 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Judson Road to Crownpoint Drive for column cap setting. Traffic should follow detour signs.
  • Tuesday, June 10, 9 p.m. to 5 a.m. Full closure on southbound mainlanes of I-35 from Judson Road exit ramp to Judson Road entrance ramp for traffic signal equipment installation.
  • Wednesday, June 11, until Friday, June 13, 9 p.m. to 5 a.m. Full closure on the southbound frontage road of I-35 at Judson Intersection for construction work. Traffic follows detour signs.

I-35 from O'Connor Road to Thousand Oaks Drive

Northbound
  • Through Monday, June 30, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Weidner Road to O’Connor Road for bridge work.
  • Through Friday, Aug. 1, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Starlight Terrace to Weidner Road for construction work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road, entrance ramp, and exit ramp from Starlight Terrace to Weidner Road, southbound to northbound turnaround at I-35 and Starlight Terrace intersection, northbound to southbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure on northbound I-35 frontage road, after Weidner entrance ramp to Judson Intersection for barrier and striping work. Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, alternating lane closures (2) on northbound I-35 frontage road, and exit ramp closure from Starlight Terrace to Weidner Road for drainage and drilled shaft work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, multiple lane closures (2) of northbound I-35 frontage road, entrance ramp from Weidner Road to O’Connor Road for drainage and drilled shaft work.
Southbound
  • Through Wednesday, June 25, long-term closure (24/7). Right lane closure on southbound frontage road of I-35 from Weidner Road to Thousand Oaks Drive for bridge work.
  • Through Monday, June 30, long-term closure (24/7). Entrance ramp closure on southbound I-35 from O’Connor Road for bridge work.
  • Through Monday, June 30, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from Tech Com to Weidner Road for construction work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, and exit ramp from O’Connor Road to Tech Com Drive for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Tech Com Drive to Weidner Road for cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, alternating lane closures (2) on southbound I-35 frontage road, and exit ramp closure from O’Connor Road to Weidner Road for drilled shaft, column, and cap work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, and entrance ramp and exit ramp closures from Weidner Road to Thousand Oaks Drive for drainage and drilled shaft work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, exit ramp from O’Connor Road to Weidner Road for cap work. Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive for sidewalk and curb installation work. Traffic should follow detour signs.
  • Monday, June 9, 9 a.m. to 3 p.m. Right lane closure on southbound frontage road of I-35 from Whirlwind Drive to westbound Frontage Road of I-410 for traffic signal equipment installation work.
  • Monday, June 9, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive for cap work. Traffic should follow detour signs.

I-35 from Thousand Oaks Drive to I-410 North Interchange

Northbound
  • Through Monday, Sept. 1, long-term (24/7). Left lane closure on northbound frontage road of I-35 from Randolph Boulevard to Starlight Terrace for bridge work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road from Crestway Drive to Weidner Road and Starlight Terrace at I-35 intersection for column and cap work. Traffic should follow detour signs.
  • Wednesday, June 11, until Saturday, June 14, 8 p.m. to 5 a.m. Full closure northbound I-35 frontage road from Crestway Drive to Weidner Road and Starlight Terrace intersection at I-35 for column cap setting. Traffic should follow detour signs.
  • Wednesday, June 11, until Saturday, June 14, 8 p.m. to 5 a.m. Multiple mainlane closures (3) on northbound I-35 from Crestway Drive to Starlight Terrace for column cap setting.
Southbound
  • Through Monday, June 30, long-term closure (24/7). Alternating lane closures on southbound I-35 frontage road between Thousand Oaks Drive and Whirlwind Drive for roadway reconstruction and structural work.
  • Through Monday, June 30, long-term closure (24/7). Exit ramp closure on I-35 southbound mainlanes to Thousand Oaks for construction work.
  • Monday, June 9, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road, and exit ramp from Thousand Oaks Drive to Randolph Boulevard, and northbound to southbound turnaround at Thousand Oaks Drive and I-35 intersection for panel and deck work. Traffic should follow detour signs.
  • Monday, June 9, until Saturday, June 14, 9 p.m. to 5 a.m. Multiple mainlane closures (3) on southbound I-35 from Thousand Oaks Drive to Randolph Boulevard for panel and deck work. Traffic should follow detour signs.
  • Monday, June 9, until Thursday, June 12, 8 p.m. to 6 a.m. Full closure on southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive and northbound to southbound turnaround of Weidner Road at I-35 intersection for bridge beam setting. Traffic should follow detour signs.
  • Monday, June 9, until Thursday, June 12, 8 p.m. to 6 a.m. Multiple mainlane closures (3) on southbound I-35 from Weidner Road to Thousand Oaks Drive for bridge beam setting.

I-35 and I-410 North Interchange

Northbound
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure of northbound I-35 ramp to westbound I-410 mainlanes and entrance ramp from Randolph Boulevard to westbound I-410 mainlanes for column and cap work. Traffic should follow detour signs.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure of eastbound I-410 ramp to northbound I-35 mainlanes for deck work. Traffic should follow detour signs.
  • Monday, June 9, until Friday, June 13, 8 p.m. to 6 a.m. Full closure of eastbound I-410 connector ramp to northbound I-35 mainlanes, eastbound I-410 exit ramp to Randolph Boulevard, and exit ramp from Windcrest Drive to Randolph Boulevard for bridge beam setting. Traffic should follow detour signs.
  • Wednesday, June 11, 9 p.m. to 5 a.m. Full closure of northbound I-35 ramp to westbound I-410 mainlanes and entrance ramp closure from Randolph Boulevard to westbound I-410 mainlanes for column and cap work. Traffic should follow detour signs.
Southbound
  • Monday, June 9, until Thursday, June 12, 9 p.m. to 5 a.m. Full closure of eastbound I-410 ramp to southbound I-35 mainlanes for bridge deck work. Traffic should follow detour signs.

I-410 North from Starcrest Drive to Harry Wurzbach Road

Eastbound
  • No closures at this time.
Westbound
  • No closures at this time.

I-410 North from I-35 Interchange to Starcrest Drive

Eastbound
  • Through Monday, June 30, long-term (24/7). Left lane closure on I-410 eastbound frontage road from Starcrest Drive to Perrin Beitel for construction work.
  • Monday, June 9, until Thursday, June 12, 8 p.m. to 6 a.m. Full closure of eastbound frontage road, close the eastbound to westbound turnaround, close the westbound to eastbound turnaround and close the entrance ramp on IH-410 from Perrin Beitel to Vicar drive and full closure of Perrin Beitel intersection on IH-410 for bridge beam setting. Traffic should follow detour signs.
  • Wednesday, June 11, until Saturday, June 14, 8 p.m. to 5 a.m. Full closure on eastbound I-410 frontage road, westbound to eastbound turnaround, entrance ramp, and exit ramp from Starcrest Drive to Perrin Beitel for bridge beam setting. Traffic should follow detour signs.
  • Wednesday, June 11, until Saturday, June 14, 8 p.m. to 5 a.m. Multiple mainlane closures (2) on eastbound I-410 from Perrin Beitel to Austin Highway (Loop 368) exit ramp for bridge beam setting.
  • Friday, June 13, 9 p.m. to 5 a.m. Alternating lane closures on eastbound I-410 frontage road and entrance ramp closure from Perrin Beitel to Austin Highway (Loop 368) for cap work. Traffic should follow detour signs.
Westbound
  • Through Friday, Aug. 15, long-term closure (24/7). Left lane closure on westbound frontage road of I-410 from Perrin Creek to Austin Highway (Loop 368) for construction.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Multiple (2) lane closures on westbound I-410 mainlanes from Perrin Beitel exit ramp to Perrin Beitel intersection for bridge deck work.
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure of westbound I-410 frontage road and exit ramp from Perrin Creek to Perrin Beitel, and ramp from northbound Austin Highway (Loop 368) to westbound I-410 frontage road for bridge deck work. Traffic should follow detour signs.
  • Wednesday, June 11, until Saturday, June 14, 8 p.m. to 5 a.m. Full closure of Austin Highway (Loop 368) ramp to westbound I-410 frontage road, eastbound I-410 frontage road from Perrin Beitel exit ramp to Perrin Beitel and full closure of Austin Highway (Loop 368) from Walzem Road to I-410 interchange for column cap setting. Traffic should follow detour signs.
  • Friday, June 13, 9 p.m. to 5 a.m. Full closure of entrance ramp on westbound I-410 frontage road to Austin Highway and exit ramp to Austin Highway (Loop 368) from westbound I-410 mainlanes for cap work. Traffic should follow detour signs.

I-410 North from Starcrest Drive to Nacogdoches Road

Eastbound
  • Through Tuesday, Sept. 30, long-term closure (24/7). Left lane closure on eastbound frontage road of I-410 from Harry Wurzbach to Starcrest Drive for construction.
Westbound
  • No closures at this time.

I-410 North and Austin Highway (Loop 368)

Northbound
  • No closures at this time.
Southbound
  • No closures at this time.

I-35 from I-410 North Interchange to Walzem Road

Northbound
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Southbound to northbound turnaround closure at Walzem Road and I-35 intersection, alternating lane closures (2) on northbound I-35 frontage road, and alternating entrance and exit ramp closures from Walzem Road to Crestway Drive for column work.
  • Tuesday, June 10, until Friday, June 13, 9 a.m. to 3 p.m. Right lane closure on northbound frontage road of I-35 from Crestwind Drive to Fourwinds Drive for traffic signal equipment installation work.
Southbound
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, exit ramp, and entrance ramp from Randolph Boulevard to Walzem Road for bridge deck work. Traffic should follow detour signs.
  • Monday, June 9, until Saturday, June 14, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, exit ramp, and entrance ramp from Randolph Boulevard to Walzem Road for bridge deck work. Traffic should follow detour signs.

I-35 from Walzem Road to Eisenhauer Road

Northbound
  • Through Monday, July 21, long-term closure (24/7). Left lane closure on southbound I-410 frontage road from Winnco Drive to Binz Engleman Road
  • Sunday, June 8, until Thursday, June 12, 9 p.m. to 5 a.m. Exit ramp closure on southbound I-410 to Binz Engleman Road for cap work. Traffic should use previous exit ramp.
  • Sunday, June 8, 7p.m. to 5 a.m. Left lane closure on southbound I-410 frontage road from Winnco Drive to Binz Engleman Road for striping work.
  • Monday, June 9, until Tuesday, June 10, 9 p.m. to 5 a.m. Left lane closure on southbound I-410 frontage road from Winnco Drive to Binz Engleman Road for striping work.
  • Friday, June 13, 9 p.m. to 5 a.m. Exit ramp closure on southbound I-410 to Binz Engleman Road for cap work. Traffic should use previous exit ramp.
  • Friday, June 13, 9 p.m. to 7 a.m. Entrance ramp closure on southbound I-410 frontage road between Winnco Drive and Binz Engleman Road for striping work. Traffic should follow detour signs.
  • Friday, June 13, 11 p.m. to 7 a.m. Full closure on southbound I-35 entrance ramp to I-410 South for drilled shaft work. Traffic should follow detour signs.
  • Saturday, June 14, 9 p.m. to 8 a.m. Entrance ramp closure on southbound I-410 frontage road between Winnco Drive and Binz Engleman Road for striping work. Traffic should follow detour signs.
  • Saturday, June 14, 9 p.m. to 8 a.m. Full closure on southbound I-35 entrance ramp to I-410 South for drilled shaft work. Traffic should follow detour signs.
  • Saturday, June 14, 9 p.m. to 8 a.m. Exit ramp closure on southbound I-410 to Binz Engleman Road for cap work. Traffic should use previous exit ramp.
Southbound
  • No closures at this time.

I-35 from Eisenhauer Road to Rittiman Road

Northbound
  • Through Saturday, June 14, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Rittiman Road to Center Park Boulevard for drainage work.
Southbound

  • No closures at this time.
Eastbound
  • No closures at this time.
Westbound
  • No closures at this time.

I-35 from Rittiman Road to I-410 South Interchange

Northbound
  • No closues at this time.
Southbound
  • No closures at this time.
Eastbound
  • No closures at this time.

I-35 and I-410 South Interchange

Northbound
  • Through Friday, Aug. 15, long-term closure (24/7). Left lane closure on northbound I-35 frontage road from Greatfare to Rittiman Road for drainage and bridge work.
  • Sunday, June 8, until Thursday, June 12, 9 p.m. to 5 a.m. Left lane closure on the northbound I-35 frontage road to the southbound I-410 frontage road for cap work.
  • Sunday, June 8, until Thursday, June 12, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road to northbound I-410 frontage road for drilled shaft work. Traffic should follow detour signs.
  • Friday, June 13, 9 p.m. to 5 a.m. Left lane closure on the northbound I-35 frontage road to the southbound I-410 frontage road for cap work.
  • Friday, June 13, 11 p.m. to 7 a.m. Full closure of northbound I-35 frontage road to northbound I-410 frontage road for drilled shaft work. Traffic should follow detour signs.
  • Saturday, June 14, 9 p.m. to 8 a.m. Left lane closure on the northbound I-35 frontage road to the southbound I-410 frontage road for cap work.
  • Saturday, June 14, 9 p.m. to 8 a.m. Full closure of northbound I-35 frontage road to northbound I-410 frontage road for drilled shaft work. Traffic should follow detour signs.
Southbound
  • Monday, June 9, until Thursday, June 12, 9 p.m. to 5 a.m. Left lane closure on southbound I-35 frontage road from Rittiman Road to Petroleum Drive for drilled shaft work.
  • Sunday, June 10, until Thursday, June 12, 9 p.m. to 5 a.m. Multiple right lane closures (2) on southboond mainlanes of I-35 from Rittiman Road to Petroleum Drive for beam setting.
  • Friday, June 13, 9 p.m. to 5 a.m. Multiple right lane closures (2) on southboond mainlanes of I-35 from Rittiman Road to Petroleum Drive for beam setting.
  • Friday, June 13, 11 p.m. to 7 a.m. Left lane closure on southbound I-35 frontage road from Rittiman Road to Petroleum Drive for drilled shaft work.
  • Saturday, June 14, 9 p.m. to 8 a.m. Multiple right lane closures (2) on southboond mainlanes of I-35 from Rittiman Road to Petroleum Drive for beam setting.
  • Saturday, June 14, 9 p.m. to 8 a.m. Left lane closure on southbound I-35 frontage road from Rittiman Road to Petroleum Drive for drilled shaft work.

I-35 from I-410 South to Petroleum Drive

Northbound
  • No closures at this time.
Southbound
  • Through Saturday, June 14, long-term closure (24/7). Right lane closure on southbound I-35 frontage road from Tejasco and Petroleum Drive for drilled shaft and column work.
  • Friday, June 13, 11 p.m. to 7 a.m. Left lane closure on southbound frontage road of I-35 from Rittiman Road to Tejasco for drainage work.
  • Saturday, June 14, 9 p.m. to 8 a.m. Left lane closure on southbound frontage road of I-35 from Rittiman Road to Tejasco for drainage work.
  • Sunday, June 8, until Thursday, June 12, 9 p.m. to 5 a.m. Full closure on southbound I-35 connector ramp and entrance ramp to I-410 South for deck panel work. Traffic should follow detour signs.

I-410 South from I-35 to Binz Engleman Road

Northbound
  • Monday, June 9, until Thursday, June 12, 9 p.m. to 5 a.m. Rolling closure on northbound and southbound mainlanes of I-35 from George Beach Avenue to Walzem Road and I-410 from Binz Engleman Road to Space Center Drive for sweeping and debris work.
  • Monday, June 9, until Thursday, June 12, 9 p.m. to 5 a.m. Left lane closure on northbound I-410 frontage road from Macro to Rittiman Road for drilled shaft work.
  • Monday, June 9, until Thursday, June 12, 9 p.m. to 5 a.m. Right lane closure on northbound I-35 mainlanes from Winnco Drive to Rittiman Road for drilled shaft work.
  • Friday, June 13, 11 p.m. to 7 a.m. Left lane closure on northbound I-410 frontage road from Macro to Rittiman Road for drilled shaft work.
  • Friday, June 13, 11 p.m. to 7 a.m. Right lane closure on northbound I-35 mainlanes from Winnco Drive to Rittiman Road for drilled shaft work.
  • Friday, June 13, 11 p.m. to 7 a.m. Rolling closure on northbound and southbound mainlanes of I-35 from George Beach Avenue to Walzem Road and I-410 from Binz Engleman Road to Space Center Drive for sweeping and debris work.
  • Saturday, June 14, 9 p.m. to 8 a.m. Left lane closure on northbound I-410 frontage road from Macro to Rittiman Road for drilled shaft work.
  • Saturday, June 14, 9 p.m. to 8 a.m. Rolling closure on northbound and southbound mainlanes of I-35 from George Beach Avenue to Walzem Road and I-410 from Binz Engleman Road to Space Center Drive for sweeping and debris work.
  • Saturday, June 14, 9 p.m. to 8 a.m. Right lane closure on northbound I-35 mainlanes from Winnco Drive to Rittiman Road for drilled shaft work.
Southbound
  • Through Monday, July 21, long-term closure (24/7). Left lane closure on southbound I-410 frontage road from Winnco Drive to Binz Engleman Road
  • Sunday, June 8, until Thursday, June 12, 9 p.m. to 5 a.m. Exit ramp closure on southbound I-410 to Binz Engleman Road for cap work. Traffic should use previous exit ramp.
  • Sunday, June 8, 7 p.m. to 5 a.m. Left lane closure on southbound I-410 frontage road from Winnco Drive to Binz Engleman Road for striping work.
  • Monday, June 9, until Tuesday, June 10, 9 p.m. to 5 a.m. Left lane closure on southbound I-410 frontage road from Winnco Drive to Binz Engleman Road for striping work.
  • Friday, June 13 9 p.m. to 5 a.m. Exit ramp closure on southbound I-410 to Binz Engleman Road for cap work. Traffic should use previous exit ramp.
  • Friday, June 13 9 p.m. to 7 a.m. Entrance ramp closure on southbound I-410 frontage road between Winnco Drive and Binz Engleman Road for striping work. Traffic should follow detour signs.
  • Friday, June 13 11 p.m. to 7 a.m. Full closure on southbound I-35 entrance ramp to I-410 South for drilled shaft work. Traffic should follow detour signs.
  • Saturday, June 14, 9 p.m. to 8 a.m. Entrance ramp closure on southbound I-410 frontage road between Winnco Drive and Binz Engleman Road for striping work. Traffic should follow detour signs.
  • Saturday, June 14, 9 p.m. to 8 a.m. Full closure on southbound I-35 entrance ramp to I-410 South for drilled shaft work. Traffic should follow detour signs.
  • Saturday, June 14, 9 p.m. to 8 a.m. Exit ramp closure on southbound I-410 to Binz Engleman Road for cap work. Traffic should use previous exit ramp.

I-35/I-410 S Interchange to FM 78

Northbound
  • No closures at this time.
Southbound
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Left lane and entrance ramp closure of the I-410 southbound frontage road from Interstate Drive to I-410 southbound entrance ramp for drainage installation work.
Eastbound
  • Sunday, June 8, until Saturday, June 14, 9 p.m. to 5 a.m. Alternating east and westbound lane closure on Binz Engleman Road from the I-410 northbound frontage road to the I-410 southbound frontage road for drainage installation work.
Westbound
  • No closures at this time.

Other lane closures

  • For your information, there are other lane closures underway within the I-35 NEX project this week, but they are not expected to affect traffic or create notable delays.