I-35 NEX lane closures for August 3 - 9

This page is updated weekly. To find the most up to date and current lane closures, follow the TxDOT San Antonio District on social media or contact us for email updates at i35NEX@txdot.gov.

This week's lane closures (weather permitting and subject to change):

Maintenance

  • No closures at this time.

I-35 from FM 3009 to FM 1518

Northbound
  • No closures at this time.
Southbound
  • No closures at this time.

I-35 from FM 1518 to Loop 1604

Northbound
  • Through Saturday, Aug. 2, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Forum Parkway to Forum Access Road for construction work.
  • Through Monday, Oct. 20, long-term closure (24/7). Exit ramp closure on northbound I-35 to Evans Road for construction work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 8 p.m. to 5 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, exit ramp, and entrance ramp from Forum Parkway to Evans Road for bridge deck work. Traffic should use next exit and entrance ramps.
  • Sunday, Aug. 3, until Thursday Aug. 7, 8 p.m. to 5 a.m. Full closure of northbound I-35 frontage road and exit ramp from Forum Parkway to Evans Road for bridge beam setting. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Tuesday, Aug. 5, 9 p.m. to 5 a.m. Full closure on northbound I-35 frontage road from Forum Parkway to Forum Access Road for bridge structure work. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road and exit ramp from Forum Parkway to Evans Road for utility work. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road and exit ramp from Forum Parkway to Olympia Parkway for cap work. Traffic should follow detour signs
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on northbound I-35 frontage road from Olympia Parkway to Pasatiempo for asphalt paving. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Tuesday Aug. 5, 9 p.m. to 5 a.m. Full closure of Evans Road and northbound to southbound turnaround at I-35 intersection for bridge deck work. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 8 p.m. to 5 a.m. Multiple mainlane closures (3) on northbound I-35 from Loop 1604 interchange to Pasatiempo for bridge beam setting. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of Corporate Drive at I-35 intersection for bridge demo, column and cap work. Traffic should follow detour signs
  • Monday, Aug. 4, until Friday, Aug. 8, 9 a.m. to 3 p.m. Rolling closure project wide for sweeping operation.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road and exit ramp from Forum Parkway to Evans Road for utility work. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road and exit ramp from Forum Parkway to Olympia Parkway for cap work. Traffic should follow detour signs
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road and exit ramp from Forum Parkway to Evans Road for bridge beam setting. Traffic should follow detour signs.
  • Friday, Aug. 8, 8 p.m. to 5 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, exit ramp, and entrance ramp from Forum Parkway to Evans Road for bridge deck work. Traffic should use next exit and entrance ramps.
  • Friday, Aug. 8, 8 p.m. to 6 a.m. Full closure on northbound I-35 frontage road from Olympia Parkway to Pasatiempo for asphalt paving. Traffic should follow detour signs.
  • Friday, Aug. 8, 8 p.m. to 6 a.m. Full closure of Corporate Drive at I-35 intersection for bridge demo, column and cap work. Traffic should follow detour signs.
  • Saturday, Aug. 9, 8 p.m. to 6 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, exit ramp, and entrance ramp from Forum Parkway to Evans Road for bridge deck work. Traffic should use next exit and entrance ramps
  • Saturday, Aug. 9, 8 p.m. to 6 a.m. Full closure on northbound I-35 frontage road from Olympia Parkway to Pasatiempo for asphalt paving. Traffic should follow detour signs.
  • Saturday, Aug. 9, 8 p.m. to 6 a.m. Full closure of Corporate Drive at I-35 intersection for bridge demo, column and cap work. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Full closure of northbound I-35 frontage road and exit ramp from Forum Parkway to Evans Road for utility work. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road and exit ramp from Forum Parkway to Olympia Parkway for cap work. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road and exit ramp from Forum Parkway to Evans Road for bridge beam setting. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure of northbound I-35 collector distributor at Loop 1604 interchange, northbound I-35 bypass bridge at Pat Booker Road, and westbound Loop 1604 frontage road at Agora Parkway to northbound I-35 frontage road at Forum Parkway for column, cap, and bridge beam work. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Multiple mainlane closures (3) on northbound I-35 from Loop 1604 interchange to Pasatiempo for bridge beam setting. Traffic should follow detour signs.
Southbound
  • Through Monday, Oct. 20, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from Forum Parkway to Old Austin Road for bridge and roadway work.
  • Through Monday, Oct. 20, long-term closure (24/7). Right lane closure on I-35 southbound mainlanes from Olympia Parkway to Loop 1604 interchange for construction work.
  • Through Monday, Oct. 20, long-term closure (24/7). Right lane closure on I-35 southbound collector distributor from Forum Parkway to Loop 1604 interchange for construction work.
  • Through Monday, Oct. 20, long-term closure (24/7). Entrance ramp closure on I-35 southbound frontage road from Old Austin Road to I-35 southbound mainlanes for construction work.
  • Through Monday, Oct. 20, long-term closure (24/7). Full closure on I-35 southbound to northbound turnaround at Corporate Drive for construction work.
  • Sunday, Aug. 3, until Friday, Aug. 8, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Olympia Parkway to Forum Parkway for paving and bridge deck work. Traffic should follow detour signs
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on McMorris Boulevard from I-35 southbound frontage road for utility construction work. Traffic follows the detour sign.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from Retama Parkway to Forum Parkway for moving barrier, paving, and traffic shift. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from Forum Parkway to Gateway Boulevard for column and cap work. Traffic should follow detour signs.
  • Monday, Aug. 4, until Thursday, Aug. 7, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from Old Austin Road to Forum Parkway and northbound I-35 exit ramp to Olympia Parkway for bridge deck work. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from Retama Parkway to Forum Parkway for moving barrier, paving, and traffic shift. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 5 a.m. Full closure on McMorris Boulevard from I-35 southbound frontage road for utility construction work. Traffic follows the detour sign.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure of southbound I-35 frontage road from Forum Parkway to Gateway Boulevard for column and cap work. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 5 a.m. Full closure on McMorris Boulevard from I-35 southbound frontage road for utility construction work. Traffic follows the detour sign.
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure of southbound I-35 frontage road from Forum Parkway to Gateway Boulevard for column and cap work. Traffic should follow detour signs.

I-35 and Loop 1604 Interchange

Northbound
  • Through Monday, Oct. 20, long-term closure (24/7). Entrance ramp closure on I-35 northbound collector distributor to I-35 northbound mainlanes for construction work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of northbound I-35 collector distributor at the Loop 1604 interchange for cap work. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of northbound I-35 collector distributor at Loop 1604 interchange, northbound I-35 bypass bridge at Pat Booker Road, and westbound Loop 1604 frontage road at Agora Parkway to northbound I-35 frontage road at Forum Parkway for column, cap, and bridge beam work. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on northbound I-35 collector distributor at Loop 1604 interchange, northbound I-35 frontage road from Pat Booker Road to Loop 1604 interchange and westbound Loop 1604 frontage road at Agora Parkway to I-35 frontage road at Forum Parkway for traffic switch, barrier, cap work. Traffic should follow detour signs.
  • Monday, Aug. 4, until Wednesday, Aug. 6, 9 p.m. to 5 a.m. Full closure on westbound Loop 1604 mainlanes from Pat Booker Road to Gateway Boulevard, westbound Loop 1604 collector distributor at I-35 interchange, northbound I-35 ramp to westbound Loop 1604 mainlanes, and southbound I-35 collector distributor at Loop 1604 interchange for steel girders welding work. Traffic should follow detour signs.
  • Monday, Aug. 4, until Wednesday, Aug. 6, 9 p.m. to 5 a.m. Full closure from westbound Loop 1604 frontage road at Agora Parkway to northbound I-35 frontage road at Forum Parkway, and northbound I-35 ramp to Forum Parkway for column and cap work. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure of northbound I-35 collector distributor at Loop 1604 interchange, northbound I-35 bypass bridge at Pat Booker Road, and westbound Loop 1604 frontage road at Agora Parkway to northbound I-35 frontage road at Forum Parkway for column, cap, and bridge beam work. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on northbound I-35 collector distributor at Loop 1604 interchange, northbound I-35 frontage road from Pat Booker Road to Loop 1604 interchange and westbound Loop 1604 frontage road at Agora Parkway to I-35 frontage road at Forum Parkway for traffic switch, barrier, cap work. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure of northbound I-35 collector distributor at the Loop 1604 interchange for cap work. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure on northbound I-35 collector distributor at Loop 1604 interchange, northbound I-35 frontage road from Pat Booker Road to Loop 1604 interchange and westbound Loop 1604 frontage road at Agora Parkway to I-35 frontage road at Forum Parkway for traffic switch, barrier, cap work. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure of northbound I-35 collector distributor at the Loop 1604 interchange for cap work. Traffic should follow detour signs.
Southbound
  • Through Monday, Oct. 20, long-term closure (24/7). Right lane closure on I-35 southbound collector distributor to Loop 1604 westbound mainlanes for construction work
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from Arcadia Drive to Olympia Parkway, entrance ramp closure at Old Austin Road, full closure on westbound Loop 1604 collector distributor at I-35 interchange and northbound I-35 ramp to westbound Loop 1604 mainlanes, southbound I-35 collector distributor to westbound Loop 1604 mainlanes, eastbound Loop 1604 frontage road from entrance ramp to IKEA-RBFCU Parkway intersection, and IKEA-RBFCU Parkway intersection at Loop 1604 for column, cap, and bridge deck work. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on westbound Loop 1604 collector distributor at I-35 interchange, southbound I-35 collector distributor at Loop 1604 interchange, northbound and southbound I-35 ramps to westbound Loop1604 mainlanes, eastbound Loop 1604 ramp to northbound and southbound I-35 mainlanes, northbound I-35 exit ramp to Olympia Parkway, eastbound Loop 1604 frontage road from IKEA-RBFCU Parkway entrance ramp to McMorris Boulevard, and IKEA-RBFCU Parkway intersection at Loop 1604 for barrier movement and striping. Traffic should follow detour signs
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from Arcadia Drive to Olympia Parkway, southbound I-35 entrance ramp at Old Austin Road, westbound I-35 collector distributor, northbound and southbound I-35 ramp to westbound Loop 1604 mainlanes, eastbound Loop 1604 frontage road from IKEA-RBFCU Parkway entrance ramp to IKEA-RBFCU Parkway intersection, and IKEA-RBFCU Parkway intersection at Loop 1604 for column cap work and traffic switch. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from Forum Parkway to Gateway Boulevard, southbound I-35 collector distributor at Loop 1604 interchange, and IKEA-RBFCU Parkway intersection at Loop 1604 for bridge structure work. Traffic should follow detour signs
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road from Arcadia Drive to Olympia Parkway, southbound I-35 entrance ramp at Old Austin Road, westbound I-35 collector distributor, northbound and southbound I-35 ramp to westbound Loop 1604 mainlanes, eastbound Loop 1604 frontage road from IKEA-RBFCU Parkway entrance ramp to IKEA-RBFCU Parkway intersection, and IKEA-RBFCU Parkway intersection at Loop 1604 for column cap work and traffic switch. Traffic should follow detour signs.
  • Friday, Aug. 8, until Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road from Arcadia Drive to Olympia Parkway, entrance ramp closure at Old Austin Road, full closure on westbound Loop 1604 collector distributor at I-35 interchange and northbound I-35 ramp to westbound Loop 1604 mainlanes, southbound I-35 collector distributor to westbound Loop 1604 mainlanes, eastbound Loop 1604 frontage road from entrance ramp to IKEA-RBFCU Parkway intersection, and IKEA-RBFCU Parkway intersection at Loop 1604 for column, cap, and bridge deck work. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 5 a.m. Full closure on westbound Loop 1604 collector distributor at I-35 interchange, southbound I-35 collector distributor at Loop 1604 interchange, northbound and southbound I-35 ramps to westbound Loop1604 mainlanes, eastbound Loop 1604 ramp to northbound and southbound I-35 mainlanes, northbound I-35 exit ramp to Olympia Parkway, eastbound Loop 1604 frontage road from IKEA-RBFCU Parkway entrance ramp to McMorris Boulevard, and IKEA-RBFCU Parkway intersection at Loop 1604 for barrier movement and striping. Traffic should follow detour signs
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road from Forum Parkway to Gateway Boulevard, southbound I-35 collector distributor at Loop 1604 interchange, and IKEA-RBFCU Parkway intersection at Loop 1604 for bridge structure work. Traffic should follow detour signs
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road from Arcadia Drive to Olympia Parkway, southbound I-35 entrance ramp at Old Austin Road, westbound I-35 collector distributor, northbound and southbound I-35 ramp to westbound Loop 1604 mainlanes, eastbound Loop 1604 frontage road from IKEA-RBFCU Parkway entrance ramp to IKEA-RBFCU Parkway intersection, and IKEA-RBFCU Parkway intersection at Loop 1604 for column cap work and traffic switch. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 5 a.m. Full closure on westbound Loop 1604 collector distributor at I-35 interchange, southbound I-35 collector distributor at Loop 1604 interchange, northbound and southbound I-35 ramps to westbound Loop1604 mainlanes, eastbound Loop 1604 ramp to northbound and southbound I-35 mainlanes, northbound I-35 exit ramp to Olympia Parkway, eastbound Loop 1604 frontage road from IKEA-RBFCU Parkway entrance ramp to McMorris Boulevard, and IKEA-RBFCU Parkway intersection at Loop 1604 for barrier movement and striping. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road from Forum Parkway to Gateway Boulevard, southbound I-35 collector distributor at Loop 1604 interchange, and IKEA-RBFCU Parkway intersection at Loop 1604 for bridge structure work. Traffic should follow detour signs
  • Monday, Aug. 4, 9 p.m. to 5 a.m. Full closure on eastbound Loop 1604 frontage road at IKEA-RBFCU Parkway to southbound I-35 frontage road at Pat Booker Road, eastbound Loop 1604 ramp to southbound I-35 mainlanes, and southbound I-35 collector distributor closure at the Loop 1604 interchange for bridge deck work. Traffic should follow detour signs.

Loop 1604 from I-35 Interchange to Nacogdoches Road

Eastbound
  • Through Sunday, Aug. 17, long-term closure (24/7). Left lane closure on eastbound frontage road of Loop 1604 from Lookout Road to IKEA-RBFCU Boulevard for construction.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 collector distributor at I-35 interchange and eastbound Loop 1604 entrance ramp from Lookout Road to IKEA-RBFCU Parkway for bridge column and cap work. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on eastbound Loop 1604 frontage road, and exit ramp closure from Lookout Road to IKEA-RBFCU Parkway intersection and westbound to eastbound turnaround of Lookout Road at Loop 1604 intersection for bridge deck work. Traffic follows the detour signs.
  • Sunday, Aug. 3, until Wednesday, Aug. 6, 9 p.m. to 5 a.m. Right lane closure and entrance ramp closure on eastbound I-410 mainlanes from Vandiver Road to Harry Wurzbach Road for traffic signal equipment installation work.
  • Monday, Aug. 4, until Thursday Aug. 7, 9 p.m. to 5 A.M. Full closure of eastbound Loop 1604 mainlanes from Union Pacific Railroad to Pat Booker Road for bridge deck work. Traffic should follow detour signs.
  • Monday, Aug. 4, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 mainlanes from Gateway Boulevard to Pat Booker Road, eastbound Loop 1604 collector distributor at I-35 interchange and southbound I-35 collector distributor at Loop 1604 interchange for steel girder work. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure of eastbound Loop 1604 mainlanes from Gateway Boulevard to Pat Booker Road, eastbound Loop 1604 collector distributor at I-35 interchange and southbound I-35 collector distributor at Loop 1604 interchange for steel girder work. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure of eastbound Loop 1604 mainlanes from Union Pacific Railroad to Pat Booker Road for bridge deck work. Traffic should follow detour signs.
Westbound
  • Through Sunday, Aug. 31, long-term closure (24/7). Full closure on Loop 1604 westbound to eastbound turnaround at Lookout Road for construction work.
  • Through Monday, Oct. 20, long-term closure (24/7). Entrance ramp closure on Loop 1604 westbound from Union Pacific Railroad to Loop 1604 westbound mainlanes for construction.
  • Monday, Aug. 4, until Thursday, Aug. 7, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 frontage road from Gateway Boulevard to Gateway Place for bridge deck work. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on eastbound Loop 1604 frontage road, and exit ramp closure from Lookout Road to IKEA-RBFCU Parkway intersection and westbound to eastbound turnaround of Lookout Road at Loop 1604 intersection for bridge deck work. Traffic follows the detour signs.

I-35 from Loop 1604 to Toepperwein Road

Northbound
  • Through Sunday, Aug. 31, long-term closure (24/7). Full closure on I-35 northbound collector exit ramp.
  • Through Sunday, Aug. 31, long-term closure (24/7). Entrance ramp closure from I-35 northbound collector distributor to I-35 northbound mainlanes for construction work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of eastbound and westbound lanes of Toepperwein Road at I-35 intersection for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of northbound I-35 Access Road from Shin Oak Drive to Pat Booker Road for drilled shaft, column and cap work. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 A.M.Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp and entrance ramp closures from O’Connor Road to Judson Road for drilled shaft, column, and cap work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, entrance ramp and exit ramp closures from Toepperwein Road to Pat Booker Road for drilled shaft, column, and cap work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road from Shin Oak Drive to Pat Booker Road for bridge structure work. Traffic should follow detour signs.
  • Monday, Aug. 4, until Thursday Aug. 7, 9 p.m. to 5 a.m. Multiple mainlane closures (3) of northbound I-35 from I-35 Access Road bridge near Shin Oak Drive to Forum Parkway for bridge structure work.
  • Monday, Aug. 4, until Thursday Aug. 7, 8 p.m. to 5 a.m. Multiple mainlane closures (3), exit ramp of northbound I-35 from I-35 Access Road bridge near Shin Oak Drive to Forum Parkway for bridge structure work. Traffic should use next available ramps.Monday, Aug. 4, 9 p.m. to 5 a.m. Full closure of I-35 Access Road bridge near Shin Oak Drive for bridge deck work. Traffic should follow detour signs.
  • Friday, Aug. 8, 8 p.m. to 6 a.m. Multiple mainlane closures (3), exit ramp of northbound I-35 from I-35 Access Road bridge near Shin Oak Drive to Forum Parkway for bridge structure work. Traffic should use next available ramps.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Multiple mainlane closures (3) of northbound I-35 from I-35 Access Road bridge near Shin Oak Drive to Forum Parkway for bridge structure work.
  • Friday, Aug. 8, 8 p.m. to 6 a.m. Full closure of northbound I-35 frontage road from Shin Oak Drive to Pat Booker Road for bridge structure work. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, entrance ramp and exit ramp closures from Toepperwein Road to Pat Booker Road for drilled shaft, column, and cap work.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Multiple mainlane closures (3) on northbound I-35 from Loop 1604 interchange to Pasatiempo for bridge beam setting. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure of eastbound and westbound lanes of Toepperwein Road at I-35 intersection for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp and entrance ramp closures from O’Connor Road to Judson Road for drilled shaft, column, and cap work.
  • Friday, Aug. 8, 8 p.m. to 6 a.m. Full closure of northbound I-35 Access Road from Shin Oak Drive to Pat Booker Road for drilled shaft, column and cap work. Traffic should follow detour signs.
  • Saturday, Aug. 9, 8 p.m. to 6 a.m. Multiple mainlane closures (3), exit ramp of northbound I-35 from I-35 Access Road bridge near Shin Oak Drive to Forum Parkway for bridge structure work. Traffic should use next available ramps.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Full closure of eastbound and westbound lanes of Toepperwein Road at I-35 intersection for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp and entrance ramp closures from O’Connor Road to Judson Road for drilled shaft, column, and cap work
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road from Shin Oak Drive to Pat Booker Road for bridge structure work. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, entrance ramp and exit ramp closures from Toepperwein Road to Pat Booker Road for drilled shaft, column, and cap work.
  • Saturday, Aug. 9, 8 P.M. to 8 a.m. Full closure of northbound I-35 Access Road from Shin Oak Drive to Pat Booker Road for drilled shaft, column and cap work. Traffic should follow detour signs.
Southbound
  • Through Monday, Oct. 20, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from McMorris Boulevard to Pat Booker Road for construction.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Shin Oak Drive to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from at I-35 intersection for bridge structure work. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Right lane closure on Pat Booker Road from northbound frontage road of I-35 to southbound frontage road of I-35 for traffic signal equipment installation work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Multiple mainlane closures (3) on southbound I-35 from Forum Parkway to McMorris Boulevard. for bridge column and cap work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure from Pat Booker Road to Toepperwein Road for column, cap and bridge deck work.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Shin Oak Drive to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure of eastbound and westbound lanes of Toepperwein Road at I-35 intersection for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure from Pat Booker Road to Toepperwein Road for column, cap and bridge deck work.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Multiple mainlane closures (3) on southbound I-35 from Forum Parkway to McMorris Boulevard for bridge column and cap work.
  • Friday, Aug. 8, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from at I-35 intersection for bridge structure work. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Multiple mainlane closures (3) on southbound I-35 from Forum Parkway to McMorris Boulevard for bridge column and cap work.
  • Saturday, Aug. 9, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from at I-35 intersection for bridge structure work. Traffic should follow detour signs
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure from Pat Booker Road to Toepperwein Road for column, cap and bridge deck work.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Shin Oak Drive to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Full closure of eastbound and westbound lanes of Toepperwein Road at I-35 intersection for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Right lane closure on Pat Booker Road from northbound frontage road of I-35 to southbound frontage road of I-35 for traffic signal equipment installation work.

I-35 from Toepperwein Road to O’Connor Road

Northbound
  • Through Tuesday, Sept. 30, long-term closure (24/7). Right lane closure on northbound I-35 frontage road from O’Connor Road to Bludau-Bishop Road for construction work.
  • Through Friday, Dec. 11, long-term closure (24/7). Exit ramp closure on I-35 northbound mainlanes to O’Connor Road for construction work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road, entrance ramp and exit ramp from O’Connor Road to Judson Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road and exit ramp from Judson Road to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp and entrance ramp closures from O’Connor Road to Judson Road for drilled shaft, column, and cap work.
  • Monday, Aug. 4, until Friday Aug. 7, 8 p.m. to 5 a.m. Multiple mainlane closures (2) on northbound I-35 from O’Connor Road to Judson Road for column cap setting. Traffic should follow detour signs.
  • Monday, Aug. 4, until Friday, Aug. 8, 8 p.m. to 5 a.m. Full closure on northbound I-35 frontage road, and exit ramp from O’Connor Road to Judson Road for column cap setting. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp and entrance ramp closures from O’Connor Road to Judson Road for drilled shaft, column, and cap work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp closure from Judson Road to Toepperwein Road for drilled shaft, column, and cap work.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Right lane closure on Pat Booker Road from northbound frontage road of I-35 to southbound frontage road of I-35 for traffic signal equipment installation work.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road and exit ramp from Judson Road to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp closure from Judson Road to Toepperwein Road for drilled shaft, column, and cap work.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp and entrance ramp closures from O’Connor Road to Judson Road for drilled shaft, column, and cap work.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Full closure of northbound I-35 frontage road and exit ramp from Judson Road to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp closure from Judson Road to Toepperwein Road for drilled shaft, column, and cap work.
Southbound
  • Through Sunday, Aug. 31, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 at Crownpoint Drive for construction work.
  • Through Sunday, Sept. 14, long-term closure (24/7). Full closure on Crownpoint Drive for utility work.
  • Through Thursday, Sept. 25, long-term closure (24/7). Entrance ramp closure on I-35 southbound frontage road from O’Connor Road to I-35 southbound mainlanes for construction work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Crownpoint Drive to O’Connor Road for cap form work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, and exit ramp from Toepperwein Road to Judson Road for bridge deck work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp, and exit ramp closure from Judson Road to O’Connor Road for drilled shaft, column, and cap work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Toepperwein Road to Judson Road for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Judson Road to Crownpoint Drive for column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road and exit ramp from Crownpoint Drive to O’Connor Road for cap form work. Accommodations will be made for local traffic. Traffic should
  • follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Judson Road to Crownpoint Drive for column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road and exit ramp from Toepperwein Road to Judson Road for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp, and exit ramp closure from Judson Road to OConnor Road for drilled shaft, column, and cap work.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, and exit ramp from Toepperwein Road to Judson Road for bridge deck work.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Full closure on southbound I-35 frontage road and exit ramp from Crownpoint Drive to O’Connor Road for cap form work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Judson Road to Crownpoint Drive for column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Full closure on southbound I-35 frontage road and exit ramp from Toepperwein Road to Judson Road for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, and exit ramp from Toepperwein Road to Judson Road for bridge deck work.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp, and exit ramp closure from Judson Road to OConnor Road for drilled shaft, column, and cap work.

I-35 from O'Connor Road to Thousand Oaks Drive

Northbound
  • Through Friday, Dec. 11, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Weidner Road to O’Connor Road for bridge work.
  • Through Sunday, Aug. 31, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Starlight Terrace to Weidner Road for construction work.
  • Through Tuesday, Sept. 30, long-term closure (24/7). Full closure on I-35 northbound to southbound turnaround at Weidner Road for construction work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road, entrance ramp, and exit ramp from Starlight Terrace to Weidner Road, southbound to northbound turnaround at I-35 and Starlight Terrace intersection, northbound to southbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on northbound I-35 frontage road, and entrance ramp from Weidner Road to O’Connor Road, southbound to northbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on northbound I-35 frontage road from Weidner Road to O’Connor Road for barrier and striping work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, alternating lane closures (2) on northbound I-35 frontage road,and exit ramp closure from Starlight Terrace to Weidner Road for drainage and drilled shaft work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, multiple lane closures (2) of northbound I-35 frontage road, entrance ramp from Weidner Road to O’Connor Road for drainage and drilled shaft work.
  • Monday, Aug. 4, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road, entrance ramp, and exit ramp from Starlight Terrace to Weidner Road, southbound to northbound turnaround at I-35 and Starlight Terrace intersection, northbound to southbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work, barrier slipping, temporary barriers moving. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road, entrance ramp, and exit ramp from Starlight Terrace to Weidner Road, southbound to northbound turnaround at I-35 and Starlight Terrace intersection, northbound to southbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work, barrier slipping, temporary barriers moving. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, alternating lane closures (2) on northbound I-35 frontage road, and exit ramp closure from Starlight Terrace to Weidner Road for drainage and drilled shaft work.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on northbound I-35 frontage road from Weidner Road to O’Connor Road for barrier and striping work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on northbound I-35 frontage road, and entrance ramp from Weidner Road to O’ConnorRoad, southbound to northbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, multiple lane closures (2) of northbound I-35 frontage road, entrance ramp from Weidner Road to O’Connor Road for drainage and drilled shaft work.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, multiple lane closures (2) of northbound I-35 frontage road, entrance ramp from Weidner Road to O’Connor Road for drainage and drilled shaft work.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Full closure on northbound I-35 frontage road from Weidner Road to O’Connor Road for barrier and striping work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road, entrance ramp and exit ramp from O’Connor Road to Judson Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road, entrance ramp, and exit ramp from Starlight Terrace to Weidner Road, southbound to northbound turnaround at I-35 and Starlight Terrace intersection, northbound to southbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Full closure of northbound I-35 frontage road, entrance ramp and exit ramp from O’Connor Road to Judson Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Full closure of northbound I-35 frontage road, entrance ramp, and exit ramp from Starlight Terrace to Weidner Road, southbound to northbound turnaround at I-35 and Starlight Terrace intersection, northbound to southbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Full closure on northbound I-35 frontage road, and entrance ramp from Weidner Road to O’Connor Road, southbound to northbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, alternating lane closures (2) on northbound I-35 frontage road, and exit ramp closure from Starlight Terrace to Weidner Road for drainage and drilled shaft work.
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road, entrance ramp, and exit ramp from Starlight Terrace to Weidner Road, southbound to northbound turnaround at I-35 and Starlight Terrace intersection, northbound to southbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work, barrier slipping, temporary barriers moving. Accommodations will be made for local traffic. Traffic should follow detour signs.
Southbound
  • Through Tuesday, Sept. 30, long-term closure (24/7). Right lane closure on southbound frontage road of I-35 from Weidner Road to Thousand Oaks Drive for bridge work.
  • Through Tuesday, Sept. 30, long-term closure (24/7). Entrance ramp closure on southbound I-35 from O’Connor Road for bridge work.
  • Through Tuesday, Sept. 30, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from Tech Com to Weidner Road for construction work.
  • Through Tuesday, Sept. 30, long-term closure (24/7). Full closure on I-35 southbound to northbound turnaround at Weidner Road for construction work.
  • Through Wednesday, Oct. 8, long-term closure (24/7). Exit ramp closure on I-35 southbound mainlanes to Weidner Road for construction work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, and exit ramp from O’Connor Road to Tech Com Drive for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, exit ramp from O’Connor Road to Weidner Road for cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, and entrance ramp and exit ramp closures from Weidner Road to Thousand Oaks Drive for drainage and drilled shaft work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes and alternating lane closures (2) on southbound I-35 frontage road from O’Connor Road to Weidner Road for drilled shaft, column, and cap work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive for sidewalk and curb installation work. Traffic should follow detour signs
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Tech Com Drive to Weidner Road for cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Monday, Aug. 4, until Thursday Aug. 7, 8 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive and northbound to southbound turnaround of Weidner Road at I-35 intersection for bridge beam setting. Traffic should follow detour signs.
  • Monday, Aug. 4, until Thursday Aug. 7, 8 p.m. to 5 a.m. Multiple mainlane closures (3) on southbound I-35 from Weidner Road to Thousand Oaks Drive for bridge beam setting.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Multiple lane closures (3) on southbound I-35 mainlanes and alternating lane closures (2) on southbound I-35 frontage road from O’Connor Road to Weidner Road for drilled shaft, column, and cap work.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive and northbound to southbound turnaround of Weidner Road at I-35 intersection for bridge beam setting. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Multiple mainlane closures (3) on southbound I-35 from Weidner Road to Thousand Oaks Drive for bridge beam setting.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road, and exit ramp from O’Connor Road to Tech Com Drive for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road and exit ramp from Tech Com Drive to Weidner Road for cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road, exit ramp from O’Connor Road to Weidner Road for cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive for sidewalk and curb installation work. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, and entrance ramp and exit ramp closures from Weidner Road to Thousand Oaks Drive for drainage and drilled shaft work.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Full closure on southbound I-35 frontage road, and exit ramp from O’Connor Road to Tech Com Drive for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Multiple lane closures (3) on southbound I-35 mainlanes and alternating lane closures (2) on southbound I-35 frontage road from O’Connor Road to Weidner Road for drilled shaft, column, and cap work
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive and northbound to southbound turnaround of Weidner Road at I-35 intersection for bridge beam setting. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Full closure on southbound I-35 frontage road and exit ramp from Tech Com Drive to Weidner Road for cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Full closure on southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive for sidewalk and curb installation work. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Full closure on southbound I-35 frontage road, exit ramp from O’Connor Road to Weidner Road for cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, and entrance ramp and exit ramp closures from Weidner Road to Thousand Oaks Drive for drainage and drilled shaft work.
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Multiple mainlane closures (3) on southbound I-35 from Weidner Road to Thousand Oaks Drive for bridge beam setting.

I-35 from Thousand Oaks Drive to I-410 North Interchange

Northbound
  • Through Monday, Sept. 1, long-term (24/7). Left lane closure on northbound frontage road of I-35 from Randolph Boulevard to Starlight Terrace for bridge work.
  • Monday, Aug. 4, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road from Crestway Drive to Weidner Road and Starlight Terrace at I-35 intersection for cap work. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road from Crestway Drive to Weidner Road and Starlight Terrace at I-35 intersection for cap work. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road from Crestway Drive to Weidner Road and Starlight Terrace at I-35 intersection for cap work. Traffic should follow detour signs.
Southbound
  • Through Tuesday, Sept. 30, long-term closure (24/7). Alternating lane closures on southbound I-35 frontage road between Thousand Oaks Drive and Whirlwind Drive for roadway reconstruction and structural work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Multiple mainlane closures (3) on southbound I-35 from Thousand Oaks Drive to Randolph Boulevard for panel and deck work. Traffic should follow detour signs. Exception requested from 8pm-7am only on nights of deck pour.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Thousand Oaks Drive to Randolph Boulevard and northbound to southbound turnaround of Thousand Oaks Drive at I-35 intersection for utilities construction work. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road and exit ramp from Thousand Oaks Drive to Randolph Boulevard, and northbound to southbound turnaround at Thousand Oaks Drive and I-35 intersection for panel and deck work. Traffic should follow detour signs.
  • Wednesday, Aug. 6, 8 p.m. to 5 a.m. Full closure of southbound I-35 frontage road and exit ramp from Thousand Oaks Drive to Randolph Boulevard, and northbound to southbound turnaround at Thousand Oaks Drive and I-35 intersection for panel and deck work. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure of southbound I-35 frontage road and exit ramp from Thousand Oaks Drive to Randolph Boulevard, and northbound to southbound turnaround at Thousand Oaks Drive and I-35 intersection for panel and deck work. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Thousand Oaks Drive to Randolph Boulevard and northbound to southbound turnaround of Thousand Oaks Drive at I-35 intersection for utilities construction work. Traffic should follow detour signs.
  • Friday, Aug. 8, until Saturday, Aug. 9, 9 p.m. to 7 a.m. Multiple mainlane closures (3) on southbound I-35 from Thousand Oaks Drive to Randolph Boulevard for panel and deck work. Traffic should follow detour signs.
  • Friday, Aug. 8, until Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road and exit ramp from Thousand Oaks Drive to Randolph Boulevard and northbound to southbound turnaround of Thousand Oaks Drive at I-35 intersection for utilities construction work. Traffic should follow detour signs.

I-35 and I-410 North Interchange

Northbound
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of northbound I-35 collector distributor to westbound I-410 mainlanes and entrance ramp closure from Randolph Boulevard to westbound I-410 mainlanes for cap work. Traffic should follow detour signs.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of northbound I-35 collector distributor to westbound I-410 mainlanes and entrance ramp closure from Randolph Boulevard to westbound I-410 mainlanes for barrier work. Traffic should follow detour signs.
  • Friday, Aug. 8, until Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure of northbound I-35 collector distributor to westbound I-410 mainlanes and entrance ramp closure from Randolph Boulevard to westbound I-410 mainlanes for barrier work. Traffic should follow detour signs.
  • Friday, Aug. 8, until Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure of northbound I-35 collector distributor to westbound I-410 mainlanes and entrance ramp closure from Randolph Boulevard to westbound I-410 mainlanes for cap work. Traffic should follow detour signs.
Southbound
  • No closures at this time.

I-410 North from Starcrest Drive to Harry Wurzbach Road

Eastbound
  • No closures at this time.
Westbound
  • No closures at this time.

I-410 North from I-35 Interchange to Starcrest Drive

Eastbound
  • Through Tuesday, Sept. 30, long-term (24/7). Left lane closure on I-410 eastbound frontage road from Starcrest Drive to Perrin Beitel for construction work.
  • Monday, Aug. 4, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of eastbound frontage road on I-410 from Perrin Beitel to Walzem Road for deck work. Traffic should use detour signs.
  • Monday, Aug. 4, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of eastbound frontage road, close the eastbound to westbound turnaround, close the westbound to eastbound turnaround and close the entrance ramp on I-410 from Perrin Beitel to Vicar drive and full closure of Perrin Beitel intersection on I-410 for panel setting on the deck. Traffic follows the detour signs.
  • Friday, Aug. 8, until Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure of eastbound frontage road on I-410 from Perrin Beitel to Walzem Road for deck work. Traffic should use detour signs.
  • Friday, Aug. 8, until Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure of eastbound frontage road, close the eastbound to westbound turnaround, close the westbound to eastbound turnaround and close the entrance ramp on I-410 from Perrin Beitel to Vicar drive and full closure of Perrin Beitel intersection on I-410 for panel setting on the deck. Traffic follows the detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on eastbound frontage road, westbound to eastbound turnaround closure, entrance ramp and exit ramp closure of I-410 from Starcrest Drive to Perrin Beitel for column work. Traffic follows the detour signs.
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure on eastbound frontage road, westbound to eastbound turnaround closure, entrance ramp and exit ramp closure of I-410 from Starcrest Drive to Perrin Beitel for column work. Traffic follows the detour signs.
Westbound
  • Through Friday, Aug. 15, long-term closure (24/7). Left lane closure on westbound frontage road of I-410 from Perrin Creek to Austin Highway (Loop 368) for construction.
  • Sunday, Aug. 3, until Thursday Aug. 7, 8 p.m. to 5 a.m. Full closure of entrance ramp on westbound I-410 frontage road to Austin Highway and exit ramp to Austin Highway (Loop 368) from westbound I-410 mainlanes for steel girders. Traffic should follow detour signs and use next exit ramp.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on westbound I-410 frontage road from Randolph Boulevard to Perrin Creek and northbound Austin Highway (Loop 368) frontage road from Interchange Parkway to westbound I-410 frontage road for steel girder erection work. Traffic should follow detour signs.
  • Monday, Aug. 4, until Thursday Aug. 7, 9 p.m. to 5 a.m. Multiple (2) lane closures on westbound I-410 mainlanes from Austin Highway exit ramp to Perrin Beitel intersection for barrier setting.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Multiple (2) lane closures on westbound I-410 mainlanes from Austin Highway exit ramp to Perrin Beitel intersection for barrier setting.
  • Monday, Aug. 4, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of westbound I-410 frontage road and exit ramp from Perrin Creek to Perrin Beitel, and ramp from northbound Austin Highway (Loop 368) to westbound I-410 frontage road for bridge deck work. Traffic should follow detour signs.
  • Monday, Aug. 4, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on eastbound frontage road, westbound to eastbound turnaround closure, entrance ramp and exit ramp closure of I-410 from Starcrest Drive to Perrin Beitel for column work. Traffic follows the detour signs.
  • Monday, Aug. 4, until Thursday Aug. 7, 8 p.m. to 5 a.m. Exit ramp closure from westbound I-410 mainlanes to southbound Austin Highway (Loop 368) for bridge beam setting. Traffic should follow detour signs.
  • Monday, Aug. 4, until Thursday Aug. 7, 8 p.m. to 5 a.m. Full closure of entrance ramp on westbound I-410 frontage road from Perrin Creek to Perrin Beitel and exit ramp to Austin Highway (Loop 368) from southbound I-35 collector distributor to westbound I-410 mainlanes for column cap setting. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Exit ramp closure from westbound I-410 mainlanes to southbound Austin Highway (Loop 368) for bridge beam setting. Traffic should follow detour signs.
  • Friday, Aug. 8, until Saturday, Aug. 9, 9 p.m. to 5 a.m. Full closure of entrance ramp on westbound I-410 frontage road to Austin Highway and exit ramp to Austin Highway (Loop 368) from westbound I-410 mainlanes for steel girders. Traffic should follow detour signs and use next exit ramp.
  • Friday, Aug. 8, until Saturday, Aug. 9, 9 p.m. to 5 a.m. Full closure of entrance ramp on westbound I-410 frontage road from Perrin Creek to Perrin Beitel and exit ramp to Austin Highway (Loop 368) from southbound I-35 collector distributor to westbound I-410 mainlanes for column cap setting. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on westbound I-410 frontage road from Randolph Boulevard to Perrin Creek and northbound Austin Highway (Loop 368) frontage road from Interchange Parkway to westbound I-410 frontage road for steel girder erection work. Traffic should follow detour signs.
  • Friday, Aug. 8, until Saturday, Aug. 9, 9 p.m. to 5 a.m. Full closure of westbound I-410 frontage road and exit ramp from Perrin Creek to Perrin Beitel, and ramp from northbound Austin Highway (Loop 368) to westbound I-410 frontage road for bridge deck work. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Multiple (2) lane closures on westbound I-410 mainlanes from Austin Highway exit ramp to Perrin Beitel intersection for barrier setting.

I-410 North from Starcrest Drive to Nacogdoches Road

Eastbound
  • Through Tuesday, Sept. 30, long-term closure (24/7). Left lane closure on eastbound frontage road of I-410 from Harry Wurzbach to Starcrest Drive for construction work.
  • Through Tuesday, Sept. 30, long-term closure (24/7). Exit ramp closure on I-410 eastbound mainlanes to Starcrest Drive for construction work.
Westbound
  • No closures at this time.

I-410 North and Austin Highway (Loop 368)

Northbound
  • No closures at this time.
Southbound
  • No closures at this time.

I-35 from I-410 North Interchange to Walzem Road

Northbound
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Southbound to northbound turnaround closure at Walzem Road and I-35 intersection, alternating lane closures (2) on northbound I-35 frontage road, and alternating entrance and exit ramp closures from Walzem Road to Crestway Drive for column work.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Southbound to northbound turnaround closure at Walzem Road and I-35 intersection, alternating lane closures (2) on northbound I-35 frontage road, and alternating entrance and exit ramp closures from Walzem Road to Crestway Drive for column work.
  • Saturday, Aug. 9, 9 p.m. to 7 a.m. Southbound to northbound turnaround closure at Walzem Road and I-35 intersection, alternating lane closures (2) on northbound I-35 frontage road, and alternating entrance and exit ramp closures from Walzem Road to Crestway Drive for column work.
Southbound
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, exit ramp, and entrance ramp from Randolph Boulevard to Walzem Road for bridge deck work. Traffic should follow detour signs.
  • Friday, Aug. 8, until Saturday, Aug. 9, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road, exit ramp, and entrance ramp from Randolph Boulevard to Walzem Road for bridge deck work. Traffic should follow detour signs.

I-35 from Walzem Road to Eisenhauer Road

Northbound
  • Sunday, Aug. 3, until Thursday, Aug. 7, 9 p.m. to 5 a.m. Multiple left lane closures (2) on northbound I-35 frontage road from Eisenhauer Road to Walzem Road for deck panel work.
Southbound
  • No closures at this time.

I-35 from Eisenhauer Road to Rittiman Road

Northbound
  • No closures at this time.
Southbound

  • Sunday, Aug. 3, until Thursday, Aug. 7, 9 p.m. to 5 a.m. Multiple right lane closures (2) on southbound mainlanes of I-35 from Rittiman Road to Petroleum Drive for beam setting.
Eastbound
  • No closures at this time.
Westbound
  • No closures at this time.

I-35 from Rittiman Road to I-410 South Interchange

Northbound
  • Through Friday, Aug. 15, long-term closure (24/7). Left lane closure on northbound I-35 frontage road from Greatfare to Rittiman Road for drainage and bridge work.
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Entrance ramp closure on northbound I-35 frontage road between Winnco Drive and Rittiman Road for drilled shaft mobilization. Traffic should use next entrance ramp.
  • Friday, Aug. 8, 11 p.m. to 7 a.m. Entrance ramp closure on northbound I-35 frontage road between Winnco Drive and Rittiman Road for drilled shaft mobilization. Traffic should use next entrance ramp.
Southbound
  • Through Sunday, Jan. 25, long-term closure (24/7). Left lane closure on southbound I-35 frontage road from Rittiman Road to Petroleum Drive for drilled shaft work.
  • Monday, Aug. 4, until Thursday Aug. 7, 9 p.m. to 5 a.m. Left lane closure on southbound I-35 frontage road from Rittiman Road to Petroleum Drive for column work.
  • Monday, Aug. 4, until Thursday Aug. 7, 9 p.m. to 5 a.m. Left lane closure on northbound I-410 frontage road from Macro to Rittiman Road for column work. Left lane closure on southbound I-35 frontage road from Rittiman Road to Petroleum Drive for column work.
  • Friday, Aug. 8, 11 p.m. to 7 a.m. Left lane closure on southbound I-35 frontage road from Rittiman Road to Petroleum Drive for column work.
  • Friday, Aug. 8, 11 p.m. to 7 a.m. Left lane closure on northbound I-410 frontage road from Macro to Rittiman Road for column work. Left lane closure on southbound I-35 frontage road from Rittiman Road to Petroleum Drive for column work.
Eastbound
  • No closures at this time.

I-35 and I-410 South Interchange

Northbound
  • Monday, Aug. 4, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road to northbound I-410 frontage road for column work. Traffic should follow detour signs.
  • Friday, Aug. 8, 11 P.M. to 7 A.M. Full closure of northbound I-35 frontage road to northbound I-410 frontage road for column work. Traffic should follow detour signs.
Southbound
  • Monday, Aug. 4, until Thursday Aug. 7, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road entrance ramp to southbound I-410 South for column work. Traffic should follow detour signs.
  • Friday, Aug. 8, 11 p.m. to 7 a.m. Full closure of southbound I-35 frontage road entrance ramp to southbound I-410 South for column work. Traffic should follow detour signs.

I-35 from I-410 South to Petroleum Drive

Northbound
  • Thursday, Aug. 7, 9 p.m. to 5 a.m. Multiple lane closures (2) on northbound and southbound I-35 mainlanes from Rittiman to George Beach Boulevard for drilled shaft work.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Multiple lane closures (2) on northbound and southbound I-35 mainlanes from Rittiman to George Beach Boulevard for drilled shaft work.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Multiple lane closures (2) on northbound and southbound I-35 mainlanes from Rittiman to George Beach Boulevard for drilled shaft work.
Southbound
  • Thursday, Aug. 7, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from Tejasco to Petroleum Drive and exit ramp closure on southbound I-35 mainlanes to George Beach Avenue for cap work. Traffic should follow detour signs.
  • Friday, Aug. 8, 9 p.m. to 7 a.m. Full closure on southbound I-35 frontage road from Tejasco to Petroleum Drive and exit ramp closure on southbound I-35 mainlanes to George Beach Avenue for cap work. Traffic should follow detour signs.
  • Saturday, Aug. 9, 9 p.m. to 8 a.m. Full closure on southbound I-35 frontage road from Tejasco to Petroleum Drive and exit ramp closure on southbound I-35 mainlanes to George Beach Avenue for cap work. Traffic should follow detour signs.

I-410 South from I-35 to Binz Engleman Road

Northbound
  • Sunday, Aug. 3, until Thursday Aug. 7, 9 p.m. to 5 a.m. Left lane closure on northbound I-35 frontage road from Winnco Drive to Space Center Drive for drilled shaft mobilization.
  • Monday, Aug. 4, until Thursday Aug. 7, 9 p.m. to 5 a.m. Rolling closure on northbound and southbound mainlanes of I-35 from George Beach Avenue to Walzem Road and I-410 from Binz Engleman Road to Space Center Drive for sweeping and debris work.
  • Friday, Aug. 8, 11 p.m. to 7 a.m. Rolling closure on northbound and southbound mainlanes of I-35 from George Beach Avenue to Walzem Road and I-410 from Binz Engleman Road to Space Center Drive for sweeping and debris work.
  • Saturday, Aug. 9, 9 p.m. to 5 a.m. Rolling closure on northbound and southbound mainlanes of I-35 from George Beach Avenue to Walzem Road and I-410 from Binz Engleman Road to Space Center Drive for sweeping and debris work.
  • Friday, Aug. 8, 11 p.m. to 7 a.m. Left lane closure on northbound I-35 frontage road from Winnco Drive to Space Center Drive for drilled shaft mobilization.
Southbound
  • Through Friday, Aug. 29, long-term closure (24/7). Left lane closure on southbound I-410 frontage road from Winnco Drive to Binz Engleman Road for drainage work.
  • Sunday, Aug. 3, until Thursday, Aug. 7, 9 p.m. to 5 a.m. Right lane closure on southbound I-410 mainlanes from Space Center Drive to Winnco Drive. for cap work.
  • Sunday, Aug. 3, until Thursday, Aug. 7, 9 p.m. to 5 a.m. Exit ramp closure on southbound I-410 to Binz Engleman Road for cap work. Traffic should use previous exit ramp.

I-35/I-410 S Interchange to FM 78

Northbound
  • No closures at this time.
Southbound
  • Tuesday, Aug. 5, 7 a.m. to 5 p.m. Left lane closure from I-35 northbound to I-410 southbound ramp for paving work.
Eastbound
  • No closures at this time.
Westbound
  • No closures at this time.

Other lane closures