Traffic impacts
Skip to main content

Traffic impacts

To provide the most accurate information about upcoming traffic impacts, the project team will provide as much notice as possible for lane closures and traffic switches. See below for a live map of traffic closures in San Antonio.

For a list of lane closures across Texas, visit TxDOT’s interative map website DriveTexas™.

I-35 NEX lane closures for June 29 - July 3

This page is updated weekly. To find the most up to date and current lane closures, follow the TxDOT San Antonio District on social media or contact us for email updates at i35NEX@txdot.gov.

This week's lane closures (weather permitting and subject to change):

Maintenance

  • No closures at this time.

I-35 from FM 3009 to FM 1518

Northbound
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple mainlane closures (3), exit ramp, and entrance ramp of northbound I-35 from Evans Road to Roy Richard Drive (FM 3009) for pavement, roadway, and drainage work. Traffic should use next available ramps.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure of Corporate Drive at I-35 intersection for bridge, column, and cap work. Traffic should follow detour signs.
  • Monday, June 30, until Wednesday, July 2, 9 a.m. to 3 p.m. Rolling closure project wide for sweeping operation.
Southbound
  • Through Sunday, July 13, long-term closure (24/7). Left lane closure on I-35 southbound frontage road from Schertz Parkway to FM 3009 for drainage work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple mainlane closures (3), and entrance ramp, and exit ramp of southbound I-35 from Roy Richard Drive (FM 3009) to Schertz Parkway for column and cap work. Traffic should use next available ramps.

I-35 from FM 1518 to Loop 1604

Northbound
  • Through Saturday, Aug. 2, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Forum Parkway to Forum Access Road for construction work.
  • Through Sunday, July 20, long-term closure (24/7). Exit ramp closure on northbound I-35 to Evans Road for construction work.
  • Sunday, June 29, 8 p.m. to 6 a.m. Full closure of northbound I-35 frontage road and exit ramp from Forum Parkway to Olympia Parkway for cap work. Traffic should follow detour signs.
Southbound
  • Through Tuesday, July 14, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from Forum Parkway to Old Austin Road for bridge and roadway work.
  • Through Tuesday, July 14, long-term closure (24/7). Right lane closure on I-35 southbound mainlanes from Olympia Parkway to Loop 1604 interchange for construction work.
  • Through Tuesday, July 14, long-term closure (24/7). Right lane closure on I-35 southbound collector distributor from Forum Parkway to Loop 1604 interchange for construction work.
  • Through Tuesday, July 1, long-term closure (24/7). Entrance ramp closure on I-35 southbound frontage road from Old Austin Road to I-35 southbound mainlanes for construction work.
  • Through Sunday, July 13, long-term closure (24/7). Full closure on I-35 southbound to northbound turnaround at Corporate Drive for construction work.
  • Sunday, June 29, until Wednesday, July 2, 8 p.m. to 6 a.m. Multiple mainlane closures (3) on southbound I-35 from Schertz Parkway to Forum Parkway for bridge deck pour, traffic shift, and lane striping.
  • Sunday, June 29, until Tuesday, July 1, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Olympia Parkway to Forum Parkway for paving and bridge deck work. Traffic should follow detour signs.
  • Sunday, June 29, until Tuesday, July 1, 8 p.m. to 6 a.m. Full closure of southbound I-35 frontage road from Retama Parkway to Forum Parkway for moving barrier and paving and opening for the Traffic shift. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 8 p.m. to 6 a.m. Full closure of southbound I-35 frontage road from Forum Parkway to Gateway Boulevard for column and cap work. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from Arcadia Drive to Olympia Parkway, entrance ramp closure at Old Austin Road, full closure on westbound Loop 1604 collector distributor at I-35 interchange and northbound I-35 ramp to westbound Loop 1604 mainlanes, southbound I-35 collector distributor to westbound Loop 1604 mainlanes, eastbound Loop 1604 frontage road from entrance ramp to IKEA-RBFCU Parkway intersection, and IKEA-RBFCU Parkway intersection at Loop 1604 for column, cap, and bridge deck work. Traffic should follow detour signs.

I-35 and Loop 1604 Interchange

Northbound
  • Through Thursday, July 31, long-term closure (24/7). Entrance ramp closure on I-35 northbound collector distributor to I-35 northbound mainlanes for construction work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure of northbound I-35 collector distributor at the Loop 1604 interchange for drilled shaft work. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure of northbound I-35 collector distributor at Loop 1604 interchange, northbound I-35 bypass bridge at Pat Booker Road, and westbound Loop 1604 frontage road at Agora Parkway to northbound I-35 frontage road at Forum Parkway for column, cap, and bridge beam work. Traffic should follow detour signs.
  • Monday, June 30, until Wednesday, July 2, 8 p.m. to 6 a.m. Full closure on northbound I-35 frontage road from Olympia Parkway to Pasatiempo for asphalt paving. Traffic should follow detour signs.
  • Tuesday, July 1, until Wednesday, July 2, 8 p.m. to 6 a.m. Full closure on the northbound mainlanes and full closure on northbound collector distributor after northbound to eastbound direct connector ramp at I-35 from Shin oak to Loop 1604 for bridge cap pour. Traffic follows the detour signs.
Southbound
  • Through Thursday, July 31, long-term closure (24/7). Right lane closure on I-35 southbound connector ramp to Loop 1604 westbound mainlanes for construction work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 6 a.m. Full closure on eastbound Loop 1604 frontage road at IKEA-RBFCU Parkway to southbound I-35 frontage road at Pat Booker Road, eastbound Loop 1604 ramp to southbound I-35 mainlanes, and southbound I-35 collector distributor closure at the Loop 1604 interchange for bridge deck work. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure on westbound Loop 1604 collector distributor at I-35 interchange, southbound I-35 collector distributor at Loop 1604 interchange, northbound and southbound I-35 ramps to westbound Loop1604 mainlanes, eastbound Loop 1604 ramp to northbound and southbound I-35 mainlanes, northbound I-35 exit ramp to Olympia Parkway, eastbound Loop 1604 frontage road from IKEA-RBFCU Parkway entrance ramp to McMorris Boulevard, and IKEA-RBFCU Parkway intersection at Loop 1604 for bridge column, cap, and deck work. Traffic should follow detour signs.

Loop 1604 from I-35 Interchange to Nacogdoches Road

Eastbound
  • Through Sunday, Aug.17, long-term closure (24/7). Left lane closure on eastbound frontage road of Loop 1604 from Lookout Road to IKEA-RBFCU Boulevard for construction.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 collector distributor at I-35 interchange and eastbound Loop 1604 entrance ramp from Lookout Road to IKEA-RBFCU Parkway for bridge column and cap work. Traffic should follow detour signs.
  • Monday, June 30, until Wednesday, July 2, 9 p.m. to 5 a.m. Alternating mainlane closures of eastbound Loop 1604 from Nacogdoches Road to Pat Booker Road for bridge column work.
  • Tuesday, July 1, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 mainlanes from Gateway Boulevard to Pat Booker Road, eastbound Loop 1604 collector distributor at I-35 interchange and southbound I-35 collector distributor at Loop 1604 interchange for steel girder work. Traffic should follow detour signs.
Westbound
  • Through Thursday, July 31, long-term closure (24/7). Full closure on Loop 1604 westbound to eastbound turnaround at Lookout Road for construction work.
  • Through Monday, July 14, long-term closure (24/7). Entrance ramp closure on Loop 1604 westbound from Union Pacific Railroad to Loop 1604 westbound mainlanes for construction.
  • Sunday, June 29, until Tuesday, July 1, 9 p.m. to 5 a.m. Full closure on westbound Loop 1604 mainlanes from Pat Booker Road to Gateway Boulevard, westbound Loop 1604 collector distributor at I-35 interchange, northbound I-35 ramp to westbound Loop 1604 mainlanes, and southbound I-35 collector distributor at Loop 1604 interchange for steel girders welding work. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure of Lookout Road and turnarounds at Loop 1604 intersection for bridge deck work. Traffic should follow detour signs.
  • Monday, June 30, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 frontage road from Gateway Boulevard to Gateway Place for bridge deck work. Traffic should follow detour signs.
  • Monday, June 30, until Wednesday, July 2, 9 p.m. to 5 a.m. Alternating mainlane closures of westbound Loop 1604 from Pat Booker Road to Nacogdoches Road for bridge deck and barrier work.

I-35 from Loop 1604 to Toepperwein Road

Northbound
  • Through Thursday, July 31, long-term closure (24/7). Full closure on I-35 northbound collector exit ramp.
  • Through Thursday, July 31, long-term closure (24/7). Entrance ramp closure from I-35 northbound collector distributor to I-35 northbound mainlanes for construction work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road from Shin Oak Drive to Pat Booker Road for bridge structure work. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, entrance ramp and exit ramp closures from Toepperwein Road to Pat Booker Road for drilled shaft, column, and cap work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure of eastbound and westbound lanes of Toepperwein Road at I-35 for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple mainlane closures (3) of northbound I-35 from I-35 Access Road bridge near Shin Oak Drive to Forum Parkway for bridge structure work.
  • Monday, June 30, 9 p.m. to 5 a.m. Full closure of I-35 Access Road bridge near Shin Oak Drive for bridge deck work. Traffic should follow detour signs.
Southbound
  • Through Tuesday, July 7, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from McMorris Boulevard to Pat Booker Road for construction.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Shin Oak Drive to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple mainlane closures (3) on southbound I-35 from Forum Parkway to McMorris Boulevard for bridge column and cap work.

I-35 from Toepperwein Road to O’Connor Road

Northbound
  • Through Thursday, July 31, long-term closure (24/7). Right lane closure on northbound I-35 frontage road from O’Connor Road to Bludau-Bishop Road for construction work.
  • Through Friday, Dec. 11, long-term closure (24/7). Exit ramp closure on I-35 northbound mainlanes to O’Connor Road for construction work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp and entrance ramp closures from O’Connor Road to Judson Road for drilled shaft, column, and cap work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, and exit ramp closure from Judson Road to Toepperwein Road for drilled shaft, column, and cap work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road and exit ramp from Judson Road to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road, entrance ramp and exit ramp from O’Connor Road to Judson Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Monday, June 30, until Tuesday, July 1, 9 a.m. to 3 p.m. Rolling closure from O’Connor Road to Toepperwein Road for checking bore direction.
Southbound
  • Through Thursday, July 31, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 at Crownpoint Drive for construction work.
  • Through Sunday, September 14, long-term closure (24/7). Full closure on Crownpoint Drive for utility work.
  • Through Thursday, Sept. 25, long-term closure (24/7). Entrance ramp closure on I-35 southbound frontage road from O’Connor Road to I-35 southbound mainlanes for construction work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Toepperwein Road to Judson Road for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Judson Road to Crownpoint Drive for column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, June 29, until Tuesday, July 1, 9 p.m. to 5 a.m. Multiple (2) lane closure on southbound frontage road of I-35 at Judson Road for traffic signal installation work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Crownpoint Drive to O’Connor Road for cap form work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure from Pat Booker Road to Toepperwein Road for column, cap, and bridge deck work.

I-35 from O'Connor Road to Thousand Oaks Drive

Northbound
  • Through Friday, Dec. 11, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Weidner Road to O’Connor Road for bridge work.
  • Through Friday, Aug. 1, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Starlight Terrace to Weidner Road for construction work.
  • Through Thursday, July 31, long-term closure (24/7). Full closure on I-35 northbound to southbound turnaround at Weidner Road for construction work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, multiple lane closures (2) of northbound I-35 frontage road, entrance ramp from Weidner Road to O’Connor Road for drainage and drilled shaft work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure on northbound I-35 frontage road from Weidner Road to O’Connor Road for barrier and striping work. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure on northbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to O’Connor Road, southbound to northbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work. Traffic follows detour signs.
  • Monday, June 30, until Wednesday, July 2, 8 p.m. to 6 a.m. Multiple main lane closures (3) on northbound I-35 from Weidner Road to O’Connor Road for bridge beam setting. Traffic should follow detour signs.
  • Monday, June 30, until Wednesday, July 2, 8 p.m. to 6 a.m. Full closure of Weidner Road intersection at I-35 for bridge beam setting. Traffic should follow detour signs.
  • Monday, June 30, until Wednesday, July 2, 8 p.m. to 6 a.m. Full closure on northbound I-35 frontage road, and entrance ramp from Weidner Road to O’Connor Road, southbound to northbound turnaround at Weidner Road and I-35 intersection for bridge beam setting. Traffic should follow detour signs.
Southbound
  • Through Thursday, July 31, long-term closure (24/7). Right lane closure on southbound frontage road of I-35 from Weidner Road to Thousand Oaks Drive for bridge work.
  • Through Thursday, July 31, long-term closure (24/7). Entrance ramp closure on southbound I-35 from O’Connor Road for bridge work.
  • Through Thursday, July 31, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from Tech Com to Weidner Road for construction work.
  • Through Thursday, July 31, long-term closure (24/7). Full closure on I-35 southbound to northbound turnaround at Weidner Road for construction work.
  • Through Wednesday, October 8, long-term closure (24/7). Exit ramp closure on I-35 southbound mainlanes to Weidner Road for construction work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from O’Connor Road to Tech Com Drive for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from Tech Com Drive to Weidner Road for cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive for sidewalk and curb installation work. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, and exit ramp from Toepperwein Road to Judson Road for bridge deck work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp, and exit ramp closure from Judson Road to O’Connor Road for drilled shaft, column, and cap work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, alternating lane closures (2) on southbound I-35 frontage road, and exit ramp closure from O’Connor Road to Weidner Road for drilled shaft, column, and cap work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, and entrance ramp and exit ramp closures from Weidner Road to Thousand Oaks Drive for drainage and drilled shaft work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from O’Connor Road to Weidner Road for cap work. Traffic should follow detour signs.
  • Monday, June 30, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road, entrance ramp, and exit ramp from Weidner Road to Thousand Oaks Drive for cap work. Traffic should follow detour signs.

I-35 from Thousand Oaks Drive to I-410 North Interchange

Northbound
  • Through Monday, Sept. 1, long-term (24/7). Left lane closure on northbound frontage road of I-35 from Randolph Boulevard to Starlight Terrace for bridge work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road, entrance ramp, and exit ramp from Starlight Terrace to Weidner Road, southbound to northbound turnaround at I-35 and Thousand Oaks/Starlight Terrace intersection, northbound to southbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road from Crestway Drive to Weidner Road and Starlight Terrace at I-35 intersection for column and cap work. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, alternating lane closures (2) on northbound I-35 frontage road, and exit ramp closure from Starlight Terrace to Weidner Road for drainage and drilled shaft work.
  • Monday, June 30, until Wednesday, July 2, 12 p.m. to 5 a.m. Left lane closure on northbound frontage road of I-35 from Crestway Drive to Starlight Terrace for beam staging.
Southbound
  • Through Thursday, July 31, long-term closure (24/7). Alternating lane closures on southbound I-35 frontage road between Thousand Oaks Drive and Whirlwind Drive for roadway reconstruction and structural work.
  • Through Thursday, July 31, long-term closure (24/7). Exit ramp closure on I-35 southbound mainlanes to Thousand Oaks for construction work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple mainlane closures (3) on southbound I-35 from Thousand Oaks Drive to Randolph Boulevard for panel and deck work. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road, and exit ramp from Thousand Oaks Drive to Randolph Boulevard, and northbound to southbound turnaround at Thousand Oaks Drive and I-35 intersection for panel and deck work. Traffic should follow detour signs.

I-35 and I-410 North Interchange

Northbound
  • No closures at this time.
Southbound
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure of eastbound I-410 ramp to southbound I-35 mainlanes for bridge deck work. Traffic should follow detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure of southbound I-35 ramp to westbound I-410 mainlanes for cap work. Traffic should follow detour signs.

I-410 North from Starcrest Drive to Harry Wurzbach Road

Eastbound
  • No closures at this time.
Westbound
  • No closures at this time.

I-410 North from I-35 Interchange to Starcrest Drive

Eastbound
  • Through Thursday, July 31, long-term (24/7). Left lane closure on I-410 eastbound frontage road from Starcrest Drive to Perrin Beitel for construction work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple (2) lane closures on eastbound I-410 mainlanes from Perrin Beitel entrance ramp to Austin Highway exit ramp for cap and column work.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure on eastbound frontage road, westbound to eastbound turnaround closure, entrance ramp and exit ramp closure of I-410 from Starcrest Drive to Perrin Beitel for deck work. Traffic follows the detour signs.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple mainlane closures (2) and entrance ramp of eastbound I-410 from Quail Creek Drive to Perrin Beitel for deck work.
Westbound
  • Through Friday, Aug. 15, long-term closure (24/7). Left lane closure on westbound frontage road of I-410 from Perrin Creek to Austin Highway (Loop 368) for construction.
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Multiple (2) lane closures on westbound I-410 mainlanes from Perrin Beitel exit ramp to Perrin Beitel intersection for bridge deck work.

I-410 North from Starcrest Drive to Nacogdoches Road

Eastbound
  • Through Tuesday, Sept. 30, long-term closure (24/7). Left lane closure on eastbound frontage road of I-410 from Harry Wurzbach to Starcrest Drive for construction work.
  • Through Tuesday, Sept. 30, long-term closure (24/7). Exit ramp closure on I-410 eastbound mainlanes to Starcrest Drive for construction work.
Westbound
  • No closures at this time.

I-410 North and Austin Highway (Loop 368)

Northbound
  • No closures at this time.
Southbound
  • No closures at this time.

I-35 from I-410 North Interchange to Walzem Road

Northbound
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Southbound to northbound turnaround closure at Walzem Road and I-35 intersection, alternating lane closures (2) on northbound I-35 frontage road, and alternating entrance and exit ramp closures from Walzem Road to Crestway Drive for column work.
  • Wednesday, July 2, 9 a.m. to 3 p.m. Right lane closure on northbound frontage road of I-35 from Windcrest Drive to Tradewind Drive for traffic signal equipment installation work.
  • Thursday, July 3, 9 a.m. to 12 p.m. Rolling closure on northbound frontage road of I-35 from Walzem Road to Tradewind Drive for traffic signal installation work.
Southbound
  • Sunday, June 29, until Wednesday, July 2, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, exit ramp, and entrance ramp from Randolph Boulevard to Walzem Road for bridge deck work. Traffic should follow detour signs.
  • Monday, June 30, 9 a.m. to 3 p.m. Right lane closure on southbound frontage road of I-35 from Walzem Road exit ramp to Walzem Road for traffic signal equipment installation work.

I-35 from Walzem Road to Eisenhauer Road

Northbound
  • Sunday, June 29, until Thursday, July 3, 9 p.m. to 5 a.m. Multiple left lane closures (2) on northbound I-35 frontage road from Eisenhauer Road to Walzem Road for deck panel work.
Southbound
  • Monday, June 30, until Thursday, July 3, 9 p.m. to 5 a.m. Entrance ramp closure on southbound I-35 frontage road between Lanark Drive and Eisenhauer Road for utility work. Traffic should use next entrance ramp.
  • Monday, June 30, 10 a.m. to 12 a.m. Right lane closure on southbound I-35 frontage road from Lanark Drive to Eisenhauer Road for beam staging.

I-35 from Eisenhauer Road to Rittiman Road

Northbound
  • No closures at this time.
Southbound

  • Monday, June 30, until Thursday, July 3, 9 p.m. to 5 a.m. Right lane closure southbound I-35 frontage road from Fairdale Drive to Rittman Road for utility work.
Eastbound
  • No closures at this time.
Westbound
  • No closures at this time.

I-35 from Rittiman Road to I-410 South Interchange

Northbound
  • Through Friday, Aug. 15, long-term closure (24/7). Left lane closure on northbound I-35 frontage road from Greatfare to Rittiman Road for drainage and bridge work.
Southbound
  • No closures at this time.
Eastbound
  • No closures at this time.

I-35 and I-410 South Interchange

Northbound
  • No closures at this time.
Southbound
  • No closures at this time.

I-35 from I-410 South to Petroleum Drive

Northbound
  • Monday, June 30, until Thursday, July 3, 9 p.m. to 5 a.m. Left lane closure on northbound I-410 frontage road from Macro to Rittiman Road for drilled shaft work.
Southbound
  • Sunday, June 29, until Thursday, July 3, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from Rittiman Road to Petroleum Drive for cap work. Traffic should follow detour signs.
  • Sunday, June 29, until Thursday, July 3, 9 p.m. to 5 a.m. Full closure on southbound I-35 connector ramp and entrance ramp to I-410 South for bridge work. Traffic should follow detour signs.
  • Sunday, June 29, until Thursday, July 3, 9 p.m. to 5 a.m. Exit ramp closure on southbound I-410 mainlanes between Rittiman Road and Binz Engleman for cap work. Traffic should use previous exit ramp.
  • Monday, June 30, until Thursday, July 3, 9 p.m. to 5 a.m. Left lane closure on southbound I-35 frontage road from Rittiman Road to Petroleum Drive for drilled shaft work.
  • Monday, June 30, until Thursday, July 3, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road entrance ramp to southbound I-410 South for drilled shaft work. Traffic should follow detour signs.
  • Sunday, June 29, until Thursday, July 3, 9 p.m. to 5 a.m. Multiple right lane closures (2) on southbound mainlanes of I-35 from Rittiman Road to Petroleum Drive for beam setting.

I-410 South from I-35 to Binz Engleman Road

Northbound
  • Monday, June 30, until Thursday, July 3, 9 p.m. to 5 a.m. Rolling closure on northbound and southbound mainlanes of I-35 from George Beach Avenue to Walzem Road and I-410 from Binz Engleman Road to Space Center Drive for sweeping and debris work.
Southbound
  • Tuesday, July 29, long-term closure (24/7). Left lane closure on southbound frontage road from Winnco Drive to Binz Engleman Road.

I-35/I-410 S Interchange to FM 78

Northbound
  • Sunday, June 29, until Thursday, July 3, 9 p.m. to 5 a.m. Left lane closure on northbound I-410 frontage road from northbound I-410 (Exit 32) to Wehman Drive for ITS installation.
  • Monday, June 30, until Thursday, July 3, 8 a.m. to 12 p.m. Left lane closure on northbound I-410 frontage road from northbound I-410 (Exit 32) to Wehman Drive for ITS installation.
Southbound
  • Sunday, June 29, until Thursday, July 3, 9 p.m. to 5 a.m. Left lane closure on southbound I-410 frontage road from Petroleum Drive to Binz Engleman Road for drainage work.
Eastbound
  • No closures at this time.
Westbound
  • Sunday, June 29, until Thursday, July 3, 9 p.m. to 5 a.m. Westbound Binz Engleman closure from southbound I-410 frontage road to northbound I-410 frontage road for drainage work.

Other lane closures

  • For your information, there are other lane closures underway within the I-35 NEX project this week, but they are not expected to affect traffic or create notable delays.