Traffic impacts
Skip to main content
Ramp Closed

Traffic impacts

To provide the most accurate information about upcoming traffic impacts, the project team will provide as much notice as possible for lane closures and traffic switches. See below for a live map of traffic closures in San Antonio.

For a list of lane closures across Texas, visit TxDOT’s interative map website DriveTexas™.

I-35 NEX Central lane closures

This page is updated weekly. To find the most up to date and current lane closures, follow the I-35 NEX Central Twitter updates or contact us for email updates at i35nexcentral@txdot.gov.

This week's lane closures (weather permitting and subject to change):

I-35

FM 3009 to FM 1518

Northbound
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (3) on northbound mainlanes, exit ramp closure, and entrance ramp closure of I-35 from Evans Road to Roy Richard Drive for barrier work. Traffic should use next available ramps.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on northbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Evans Road to Schertz Parkway for barrier work. Traffic should use next exit and entrance ramps.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on northbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Schertz Parkway to Roy Richard Drive for barrier work. Traffic should use next exit and entrance ramps.
Southbound
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Southbound to northbound I-35 turnaround closure at Corporate Drive for striping, barrier, and temporary pavement work. Traffic should use Corporate Drive intersection.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Southbound to northbound I-35 turnaround closure at Corporate Drive and full closure of eastbound Corporate Drive at I-35 for striping, barrier, and temporary pavement work. Traffic should use Evans Road intersection.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (3) on southbound I-35 mainlanes, entrance ramp closure, and exit ramp closure from Roy Richard Drive to Schertz Parkway for bridge structure work. Traffic should use next entrance and exit ramps.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on southbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Roy Richard Drive to Schertz Parkway for striping, barrier, and temporary pavement work. Traffic should use next exit and entrance ramps.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on southbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Schertz Parkway to Evans Road for striping, barrier, and temporary pavement work. Traffic should use next exit and entrance ramps.

FM 1518 to Loop 1604

Northbound
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (3) on northbound mainlanes and exit ramp closure of I-35 from Forum Parkway to Evans Road for drainage work. Traffic should use next exit ramp.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on northbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Forum Parkway to Evans Road for drainage and barrier work. Traffic should use next exit and entrance ramps.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures of northbound frontage road of I-35 from Loop 1604 to Forum Parkway for striping, barrier, and temporary pavement work. Traffic should follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Northbound to southbound I-35 turnaround closure at Evans Road and full closure of westbound Evans Road at I-35 for striping, barrier, drainage, and temporary pavement work. Traffic should use Corporate Drive intersection.
Southbound
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on southbound frontage road of I-35 from Forum Parkway to Gateway Boulevard for striping, barrier, temporary pavement, and demolition works. Traffic should follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on southbound frontage road of I-35 and entrance ramp closure from Olympia Parkway to Forum Parkway for bridge work. Traffic should follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (3) on southbound I-35 mainlanes from Schertz Parkway to Forum Parkway for bridge structure work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (3) on southbound I-35 mainlanes from Forum Parkway to Ferrell Road for bridge structure work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Southbound I-35 entrance ramp closure from Old Austin Road to Forum Parkway for construction work. Traffic must use the Forum Parkway turnaround and follow detour signs to access southbound I-35.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on southbound frontage road of I-35 from Old Austin Road to Forum Parkway for bridge work. Traffic should follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on southbound frontage road of I-35 from Retama Parkway to Olympia Parkway for bridge substructure work. Traffic should follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on southbound frontage road and entrance ramp and exit ramp closures of I-35 from Evans Road to Olympia Parkway for bridge foundation, striping, barrier work, and temporary pavement work. Traffic should use prior exit ramp and next entrance ramp.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on southbound frontage road of I-35 from Olympia Parkway to Gateway Boulevard for bridge foundation, temporary pavement, striping and barrier work.

Loop 1604 Interchange

Northbound
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on northbound I-35 collector ramp at the Loop 1604 interchange for striping, barrier, and construction entrance work. Traffic should follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on eastbound Loop 1604 to northbound I-35 connector ramp closure for striping and barrier work. Traffic should follow detour signs.
Southbound
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on eastbound Loop 1604 to southbound I-35 connector ramp closure for striping and barrier work. Traffic must exit at IKEA-RBFCU Parkway and follow the detour signs to southbound I-35.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on westbound Loop 1604 to southbound I-35 connector ramp closure for earthwork. Traffic must exit at Lookout Road and follow the detour signs to southbound I-35.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on southbound I-35 to westbound Loop 1604 connector ramp closure and alternating lane closures on southbound mainlanes of I-35 at the exit to Loop 1604 for bridge substructure work. Southbound I-35 to Loop 1604 traffic should exit at Retama Parkway and follow the detour signs to Loop 1604.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating ramp closures on southbound I-35 connector ramp to Pat Booker Road for striping, barrier, and bridge substructure work. Traffic must exit Loop 1604 (exit 172) and follow the detour signs to Pat Booker Road.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on southbound I-35 collector ramp closure at the Loop 1604 interchange for striping and barrier work. Traffic must use west Loop 1604 (exit 172) to access southbound I-35 and follow detour signs.

Loop 1604 to Toepperwein Road

Northbound
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on northbound frontage road, entrance ramp closure, and alternating exit ramp closures of I-35 from Judson Road to Shin Oak Drive for barrier work. Traffic should follow the detour sign to the available ramps.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (2) on northbound mainlanes of I-35, alternating exit ramp closures, and entrance ramp closure from Toepperwein Road to Loop 1604 for barrier setting and structures work. Traffic should follow the detour signs to the available ramps.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (3) on northbound mainlanes of I-35 from I-35 Access Road near Shin Oak Drive to Forum Parkway for striping, barrier, and temporary pavement work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on northbound frontage road of I-35 and entrance ramp closure from Shin Oak Road to Pat Booker Road for striping, barrier, and temporary pavement work. Traffic should follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure of northbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Pat Booker Road to Loop 1604 interchange for striping, barrier, and temporary pavement work. Traffic should follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure of I-35 Access Road bridge from I-35 northbound frontage road to I-35 southbound frontage road, near Shin Oak Drive for construction work. Traffic should follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure of eastbound and westbound lanes of Pat Booker Road at I-35 for construction work. Traffic should follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on westbound Pat Booker Road at I-35 for striping work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on eastbound Pat Booker Road at I-35 for striping work.
Southbound
  • Through Sunday September 8, 2024, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from McMorris Boulevard to Pat Booker Road for construction.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on southbound frontage road and entrance ramp of I-35 from Shin Oak Drive to Toepperwein Road for cap form erection work. Accommodations will be made for local traffic. Southbound frontage road of I-35 traffic must follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure of southbound frontage road from IKEA-RBFCU Parkway to Pat Booker Road, eastbound Loop 1604 to southbound I-35 connector ramp closure, and southbound I-35 collector ramp closure at the Loop 1604 interchange for striping and barrier work. Traffic should follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating ramp closures on southbound I-35 connector ramp to Pat Booker Road for striping, barrier, and bridge substructure work. Traffic must exit Loop 1604 (exit 172) and follow the detour signs to Pat Booker Road.
  • Thursday, December 7, 9:00 PM to 5:00 AM. Full closure of eastbound and westbound lanes of Toepperwein Road at I-35 for beam setting. Traffic should follow detour signs.

Toepperwein Road to O’Connor Road

Northbound
  • Through Saturday February 3, 2024, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Judson Road to Toepperwein Road for drainage, column, and cap work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on northbound frontage road, right lane closure on northbound mainlanes, and exit ramp closure of I-35 from Bludau-Bishop Road to Gunn Road, right lane closure on the eastbound and westbound at the intersection of Judson Road and Randolph Boulevard and left lane closure on Randolph Boulevard at Judson Road for temporary pavement and signal works. Traffic should use the next exit ramp.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple right lane closures (2) on northbound mainlanes of I-35, entrance ramp closure, and alternating exit ramp closures from O’Connor Road to Toepperwein Road for barrier setting and structures work. Traffic should follow the detour signs to the available ramps.
Southbound
  • Through Saturday, February 3, 2024, long-term closure (24/7). Left lane closure on southbound I-35 frontage road between Toepperwein Road and Judson Road for retaining wall, drilled shaft, column, and cap work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Right lane closure on eastbound Judson Road from Independence Avenue to southbound I-35 frontage road, and right turn lane closure on eastbound Judson Road to southbound I-35 frontage road for utilities work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on southbound frontage road and exit ramp of I-35 from Toepperwein Road to Judson Road for cap form erection work. Accommodations will be made for local traffic. Southbound frontage road of I-35 traffic must follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on southbound frontage road of I-35 from Judson Road to O’Connor Road for earthwork, paving, striping, and barrier work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Right lane closure on southbound mainlanes of I-35, exit ramp closure, entrance ramp closure, and left lane closure on southbound frontage road of I-35 at O’Connor Road for barrier work. Traffic should use available ramps.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (3) on southbound I-35 mainlanes, entrance ramp closure, and exit ramp closure from Pat Booker Road to Judson Road for structures work. Traffic should use next entrance and exit ramps.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple right lane closures (3) on southbound I-35 mainlanes, entrance ramp closure, exit ramp closure, and left lane closures (2) on southbound frontage road of I-35 from Judson Road to O’Connor Road for striping, barrier, and paving work. Traffic should use next entrance and exit ramps.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (3) on southbound I-35 mainlanes from Judson Road to O’Connor Road for striping work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (3) on southbound mainlanes of I-35, exit ramp closure, and alternating lane closures on southbound frontage road of I-35 from Toepperwein Road to Judson Road for earthwork and barrier work. Traffic should use next exit ramp.

O’Connor Road to Thousand Oaks Drive

Northbound
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (3) on northbound mainlanes of I-35 from Thousand Oaks Drive to Weidner Road for striping and barrier work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (2) on northbound frontage road, entrance ramp closure, and exit ramp closures of I-35 from Thousand Oaks Drive to Weidner Road for earthwork and striping. Traffic should use next available ramps.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (2) on northbound frontage road, alternating entrance ramp closures, and exit ramp closure of I-35 from Weidner Road to Bludau-Bishop Road for earthwork and striping. Traffic should follow the detour signs to the available ramps.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (3) on northbound mainlanes of I-35 from Weidner Road to Bludau-Bishop Road for striping and barrier work.
Southbound
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on southbound frontage road and entrance ramp closure of I-35 from O’Connor Road to Tech Com Drive for cap form erection work. Accommodations will be made for local traffic. Southbound frontage road of I-35 traffic must follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on southbound frontage road and exit ramp of I-35 from Tech Com Drive to Weidner Road for cap form erection work. Accommodations will be made for local traffic. Southbound frontage road of I-35 traffic must follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on southbound frontage road of I-35, entrance ramp closure, and exit ramp closure from O’Connor Road to Weidner Road for drainage and barrier work. Traffic should use next entrance and exit ramps.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on southbound frontage road of I-35 and entrance ramp closure from Weidner Road to Thousand Oaks Drive for earthwork, drainage and barrier work. Traffic should use prior entrance ramp.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (3) on southbound mainlanes, entrance and exit ramp closures, and alternating lane closures on southbound frontage road of I-35 from O’Connor Road to Weidner Road for striping work. Traffic should use the next exit and entrance ramps.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (2) on southbound mainlanes, entrance ramp closure, exit ramp closure, and alternating lane closures on southbound frontage road of I-35 from Weidner Road to Thousand Oaks Drive for striping work. Traffic should use the next exit and entrance ramps.

Thousand Oaks Drive to I-410 Interchange

Northbound
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (2) on northbound mainlanes of I-35 from Randolph Boulevard to Thousand Oaks for barrier setting.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on northbound frontage road of I-35 from Crestway Drive to Starlight Terrace for barrier work.
  • Monday, December 4, until Friday, December 8, 9:00 PM to 5:00 AM. Right lane closure on westbound Starlight Terrance at I-35 from northbound frontage road to southbound frontage road for pothole work.
Southbound
  • Through Saturday, December 23, long-term closure (24/7). Alternating lane closures on southbound I-35 frontage road between Thousand Oaks Drive and Whirlwind Drive for roadway reconstruction and structural work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on southbound frontage road of I-35 and exit ramp closure from Thousand Oaks Drive to Randolph Boulevard for permanent widening work. Traffic should use prior exit ramp.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on southbound frontage road and northbound to southbound turnaround closure of I-35 from Thousand Oaks Drive to Whirlwind Drive for drilling work. Traffic should follow detour signs. Accommodations will be made for local traffic.

I-410 Interchange

Northbound
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure of northbound I-35 to westbound I-410 connector ramp for drilling work. Traffic should follow detour signs.
Southbound
  • No closures at this time.

I-410 Interchange to Walzem Road

Northbound
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (2) on northbound mainlanes of I-35 and alternating lane closures on exit ramp from Walzem Road to Randolph Boulevard for barrier setting.
Southbound
  • Through Sunday, December 10, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 at Fratt Road for construction work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Southbound to northbound turnaround closure at Walzem Road, alternating lane closures on northbound frontage road, and alternating entrance and exit ramp closures of I-35 from Walzem Road to Crestway Drive for striping and barrier work. Traffic should follow detour signs for available ramps.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure of Randolph Boulevard and southbound frontage road at I-35 for drainage work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on southbound frontage road of I-35 to Randolph Boulevard for drainage work. Traffic should follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (2) on northbound and southbound of Interchange Parkway from Austin Highway (Loop 368) to Walzem Road and multiple lane closures (2) on eastbound and westbound of Fratt Road from I-35 southbound frontage road to Austin Highway (Loop 368) for barrier work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Entrance ramp closure on southbound frontage road of I-35 from Fratt Drive to Walzem Road for drilled shaft and column work. Traffic to use next entrance ramp.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Right lane closure on southbound mainlanes of I-35 from Randolph Boulevard to Walzem Road for cap work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on southbound frontage road, exit ramp, and entrance ramp of I-35 from Randolph Boulevard to Fratt Road for drilled shaft work. Traffic should follow detour signs.

Loop 1604

Loop 1604 Interchange to Nacogdoches Road

Eastbound
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Exit ramp closure on eastbound mainlanes of Loop 1604 to IKEA-RBFCU Parkway for striping work. Traffic should use prior exit ramp.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Westbound to eastbound Loop 1604 turnaround closure from Lookout Road to Union Pacific Railroad for retaining wall demolition work. Traffic must use Nacogdoches Road turnaround.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure of Lookout Road intersection and turnarounds at Loop 1604 for striping work. Traffic should follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on the eastbound Loop 1604 collector ramp at the I-35 interchange for striping work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on eastbound frontage road of Loop 1604, right lane entrance ramp closure, and turnaround closure from Nacogdoches Road to Union Pacific Railroad for striping work. Traffic should use Lookout Road intersection.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on eastbound frontage road of Loop 1604 from Lookout Road to I-35 for striping and barrier work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating mainlane closures on eastbound Loop 1604 and alternating exit ramp closures from Nacogdoches Road to I-35 for barrier work. Traffic should use next exit ramp.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Eastbound to westbound Loop 1604 turnaround closure from Nacogdoches Road to Union Pacific Railroad for retaining wall demolition work. Traffic should use Lookout Road intersection.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on eastbound mainlanes of Loop 1604 from Lookout Road to I-35 for overhead sign removal. Traffic should follow signs.
Westbound
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on westbound Loop 1604 collector ramp at I-35 interchange for geotechnical work. Traffic should follow the detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on westbound mainlanes of Loop 1604 from Pat Booker Road to Lookout Road for overhead sign removal. Traffic should follow signs and use next entrance ramp.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Westbound to eastbound Loop 1604 turnaround closure at Lookout Road for demolition work. Traffic should use Lookout Road intersection.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating mainlane closures, exit ramp closure, and entrance ramp closure on westbound Loop 1604 from I-35 to Nacogdoches Road for barrier work. Traffic should use prior exit and next entrance ramps.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on westbound frontage road, exit ramp closure, and entrance ramp closure of Loop 1604 from Union Pacific Railroad and Nacogdoches Road for barrier work. Traffic should use next available ramps.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on westbound frontage road and westbound bypass ramp of Loop 1604 from I-35 to Nacogdoches Road for construction entrance and temporary pavement work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Exit ramp closure on westbound mainlanes of Loop 1604 to Lookout Road for pavement and striping work. Traffic should use next exit ramp.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Exit ramp closure to Lookout Road from southbound I-35 to westbound Loop 1604 connector ramp for cap work. Traffic should use next exit ramp.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure on westbound frontage road of Loop 1604 from Gateway Boulevard to Gateway Place for setting caps. Traffic should follow detour signs.

I-410

Austin Highway (Loop 368)
Northbound
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Entrance ramp closure on northbound Austin Highway (Loop 368) to eastbound I-410 for barrier work. Traffic should use next entrance ramp.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on northbound Austin Highway (Loop 368) from Walzem Road to Interchange Parkway for barrier work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on northbound Austin Highway (Loop 368) connector ramp to westbound I-410 for barrier work.
Southbound
  • No closures at this time.

I-410 Interchange to Starcrest Drive

Eastbound
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on eastbound frontage road of I-410, entrance ramp closure, and eastbound to westbound turnaround closure between Starcrest Drive and Perrin Beitel for striping and barrier work. Traffic should use next entrance ramp.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on eastbound frontage road of I-410, entrance ramp closure, and right mainlane closure from Perrin Beitel to Austin Highway (Loop 368) for striping and barrier work. Traffic should follow detour signs.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on eastbound I-410 exit ramp to southbound I-35 frontage road and alternating lane closures on southbound frontage road of I-35 from Randolph Boulevard to Walzem Road for geotechnical, drilled shaft, and column work. Traffic to use next exit ramp.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (2) on eastbound mainlane of I-410 from Austin Highway (Loop 368) to Randolph Boulevard for barrier work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (2) on eastbound mainlanes of I-410 from Starcrest Drive to Randolph Boulevard for barrier setting.
Westbound
  • Through Friday, February 16, 2024, long-term closure (24/7). Left lane closure on westbound frontage road of I-410 from Perrin Creek to Austin Highway (Loop 368) for construction.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on westbound frontage road and exit ramp closure of I-410 from Randolph Boulevard to Perrin Beitel for drilled shaft work. Traffic to use next exit ramp.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (2) on westbound I-410 mainlanes from I-35 to Austin Highway (Loop 368) for cap and barrier work.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple lane closures (3) on westbound mainlanes and exit ramp closure of I-410 from I-35 to Perrin Beitel for striping and barrier work. Traffic should use next exit ramp.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Full closure of entrance ramp on westbound frontage road and exit ramp of I-410 to Austin Highway (Loop 368) for barrier work. Traffic should follow detour signs.

Starcrest Drive to Nacogdoches Road

Eastbound
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Multiple left lane closures (2) and entrance ramp closure on eastbound frontage road of I-410 from Nacogdoches Road to Harry Wurzbach Road for striping and barrier work. Traffic should use next entrance ramp.
  • Sunday, December 3, until Saturday, December 9, 9:00 PM to 5:00 AM. Alternating lane closures on eastbound frontage road of I-410, entrance ramp closure, and exit ramp closure from Harry Wurzbach Road to Starcrest Drive for striping and barrier work. Traffic should use prior entrance and exit ramps.