Monthly State Let Construction Report For Dallas District As Of Aug 12, 2013 Page 8 Of 8

Last Update: Monday, August 12, 2013
FTP Icon Text Version
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDALLAS
Highway IH 20
From AT IH 45 RAMP FROM EB IH 20
To NB IH 45
CSJ 2374-03-057
Proj ID IM 0205(151)
Work Type ADD LANE TO DIRECT CONNECTION RAMP
 
1.418 5699998.00 2467.00 4206301.43 73.7
Work Order 10-07-11
Work Began 01-12-12
Work Completed  
Time Computed 12-06-11
Contract Working Days 471
Addl Days Granted 0
Working Days Charged 342
Percent Time Used 72
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 2374-03-057
ALLIANCE GEOTECHNICAL GROUP(0.00%)
AXIS CONTRACTING, INC. (1.14%)
BREDA COMPANY, INC.(0.96%)
BROCK ENVIRONMENTAL, LLC (0.71%)
CONCRETE CUTTING BY BOND (0.26%)
DUSTIN ALLEN, INC. (1.41%)
DUSTROL, INC.(0.87%)
FOUNDATION DRILLERS, INC.(1.05%)
HIGHWAY TECHNOLOGIES, INC. (0.55%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (1.12%)
MELS ELECTRIC, L.P.(0.34%)
STRIPING TECHNOLOGY, L.P.(0.93%)
GREAT WESTERN ERECTORS (0.06%)
ERWIN STEEL WORKS, LLC (0.11%)
RG PAINTING(0.39%)
MAGNUM SAWING(0.34%)
D & D STUD WELDING (0.17%)
FORTSON CONTRACTING, INC.(0.00%)
Contract # 08113245
Totals 5699998.00 2467.00 4206301.43 73.7

CountyDALLAS
Highway IH 20
From EAST OF POLK RD
To EAST OF IH 45
CSJ 2374-03-081
Proj ID IM 0205(153)
Work Type LANDSCAPE DEVELOPMENT
 
9.604 399270.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 103
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BEVERLY SUE GLOBAL SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2374-03-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07133215
Totals 399270.75 0.00 0.00 0.0

CountyDALLAS
Highway IH 20
From TARRANT COUNTY LINE
To EAST OF CARRIER PARKWAY
CSJ 2374-04-072
Proj ID IM 0205(154)
Work Type FULL DEPTH REPAIR, MILL AND INLAY
 
1.799 3004430.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 117
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 2374-04-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07133008
Totals 3004430.00 0.00 0.00 0.0

CountyCOLLIN
Highway FM 2514
From LAVON PKWY
To BROWN ST
CSJ 2679-03-012
Proj ID STP 2013(834)
Work Type BS REP, OV
 
3.368 1013312.94 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2679-03-012
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07133018
Totals 1013312.94 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8