Monthly State Let Construction Report For Dallas District As Of Dec 10, 2014 Page 8 Of 9

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDENTON
Highway FM 720
From ELDORADO PKWY (FM 720)
To SOUTH OF MARTOP
CSJ 1567-01-025
Proj ID C 1567-1-25
Work Type GR, STRS & PVT
 
2.565 15597320.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 420
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-025
S & S BRIDGE PAINTING, INC.(0.13%)
Contract # 02143001
Totals 15597320.25 0.00 0.00 0.0

CountyDENTON
Highway FM 423
From STEWARTS CREEK ROAD
To SH 121
CSJ 1567-02-032
Proj ID C 1567-2-32
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.761 49691109.92 3530567.86 3530567.86 7.1
CountyDENTON
Highway FM 423
From STEWARTS CREEK ROAD
To SH 121
CSJ 1567-02-033
Proj ID RW 1567-2-33
Work Type ADJUSTMENT OF UTILITIES
 
3.761 8252384.38 963093.35 963093.35 11.6
Work Order 08-27-14
Work Began 00-00-00
Work Completed  
Time Computed 09-12-14
Contract Working Days 756
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 3
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1567-02-032
ATS DRILLING, INC. (1.12%)
C.T. AND S. METALWORKS, INC. (0.32%)
DUSTROL, INC.(0.52%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.08%)
HOUSTON SAWING & DRILLING(0.00%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (0.31%)
MEL"S ELECTRIC SERVICE, INC. (6.02%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(8.40%)
DALLAS LITE AND BARRICADE INC. (0.14%)
SCOTT DERR PAINTING CO, LLC(0.66%)
STORM WATER MANAGEMENT, INC. (0.14%)
STRIPING TECHNOLOGY, L.P.(0.73%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.13%)
WEST TEXAS REBAR PLACERS INC.(0.35%)
W.O.E. CONSTRUCTION(4.60%)
MCL CONTRACTING, LLC (0.06%)
BORE COMPANY (2.11%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.19%)
Contract # 05143001
Totals 57943494.30 4493661.21 4493661.21 7.7

CountyDENTON
Highway FM 407
From FM 1830
To WEST OF LANTANA TRAIL
CSJ 1785-01-028
Proj ID C 1785-1-28
Work Type GR, STRS & PVT.
 
6.126 12873212.87 201107.76 14283392.40 99.9
Work Order 09-16-11
Work Began 03-01-12
Work Completed  
Time Computed 03-01-12
Contract Working Days 497
Addl Days Granted 195
Working Days Charged 693
Percent Time Used 100
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1785-01-028
BREDA COMPANY, INC.(1.11%)
BRENDA PRICE TRUCKING(0.00%)
CONCRETE CUTTING BY BOND (0.50%)
FARR FOUNDATION, INC.(0.24%)
FORTSON CONTRACTING, INC.(0.13%)
HIGHWAY TECHNOLOGIES, INC. (0.00%)
IOWA BRIDGE & CULVERT, LC(1.16%)
MICA CORPORATION (2.69%)
MIKE ALBERT, INC.(4.47%)
TEXAS CURB CUT, LP (0.05%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.82%)
THELIN RECYCLING CO., LLC(0.23%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.45%)
C.T. AND S. METALWORKS, INC. (0.00%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(2.03%)
PENHALL COMPANY(0.00%)
STRIPING TECHNOLOGY, L.P.(0.99%)
DURABLE SPECIALTIES, INC.(2.56%)
Contract # 07113205
Totals 12873212.87 201107.76 14283392.40 99.9

CountyDENTON
Highway FM 407
From W. OF CHIN CHAPEL
To W. OF BRIARHILL BLVD.
CSJ 1950-01-026
Proj ID C 1950-1-26
Work Type GRADING, STRUCTURES, BAND AND SURF
 
1.369 5419912.44 0.00 6233520.05 99.9
Work Order 02-16-10
Work Began 09-21-10
Work Completed  
Time Computed 05-17-10
Contract Working Days 300
Addl Days Granted 209
Working Days Charged 485
Percent Time Used 95
Contractor(s)
TISEO PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 1950-01-026
AXIS CONTRACTING, INC. (1.90%)
BROCK ENVIRONMENTAL, LLC (0.38%)
BUYERS BARRICADES, INC.(0.52%)
DURABLE SPECIALTIES, INC.(1.95%)
FORTSON CONTRACTING, INC.(0.02%)
IOWA BRIDGE & CULVERT, LC(1.45%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 17.25%)
STRIPE-A-ZONE, INC.(1.19%)
T & R EXCAVATION, INC. ( 21.56%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.21%)
TOMAS REYES TRUCKING, INC. (2.93%)
W.O.E. CONSTRUCTION(0.14%)
TEXAS INLETS, INC. (3.48%)
DUSTROL, INC.(3.03%)
Contract # 01103007
Totals 5419912.44 0.00 6233520.05 99.9

CountyCOLLIN
Highway FM 2551
From FM 544
To FM 2514
CSJ 2056-01-045
Proj ID C 2056-1-45
Work Type GR., STR., BASE AND PAVEMENT
 
2.953 15783469.03 1432180.11 13021542.01 82.5
Work Order 12-07-11
Work Began 11-26-12
Work Completed  
Time Computed 06-25-12
Contract Working Days 480
Addl Days Granted 5
Working Days Charged 454
Percent Time Used 93
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2056-01-045
ARTEX ELECTRIC, INC. (3.54%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 14.01%)
DALLAS LITE AND BARRICADE INC. (0.25%)
DUSTIN ALLEN, INC. (0.30%)
SOUTHWEST CONSTRUCTION SERVICES(0.46%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.90%)
WYLIE DRILLING & DRAINAGE, INC.(0.19%)
BROCK ENVIRONMENTAL, LLC (0.15%)
THELIN RECYCLING COMPANY, L.P. (0.16%)
DUSTROL, INC.(0.35%)
JM MATERIALS, INC. (4.40%)
PANTHER CREEK TRANSPORTATION, INC. (0.57%)
USA SWPPP INSPECTIONS, INC.(0.01%)
MCL CONTRACTING, LLC (0.01%)
BREDA COMPANY, INC.(0.00%)
CTBX, INC. (0.52%)
HERDEZ TRUCKING, INC.(0.00%)
A BROTHERS MILLING, LLC(0.41%)
Contract # 06113239
Totals 15783469.03 1432180.11 13021542.01 82.5

CountyCOLLIN
Highway FM 2551
From FM 544
To FM 2514 (PARKER ROAD)
CSJ 2056-01-048
Proj ID STP 2015(223)
Work Type LANDSCAPE DEVELOPMENT
 
3.090 373099.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-18-14
Work Began 00-00-00
Work Completed  
Time Computed 12-04-14
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2056-01-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143017
Totals 373099.80 0.00 0.00 0.0

CountyDENTON
Highway LP 288
From IH 35
To US 377 / US 380
CSJ 2250-02-016
Proj ID STP 2014(661)
Work Type FULL DEPTH CONCRETE PAVEMENT REPAIR
 
6.722 3653118.00 144692.28 686573.58 18.7
Work Order 06-30-14
Work Began 10-06-14
Work Completed  
Time Computed 08-29-14
Contract Working Days 210
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 16
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2250-02-016
ALTUS TRAFFIC MANAGEMENT LLC (0.47%)
BRENDA PRICE TRUCKING(6.28%)
PEACHTREE CONSTRUCTION, LTD. (3.78%)
STRAIGHT LINE SAWING & SEALING (5.96%)
STRIPING TECHNOLOGY, L.P.(1.01%)
ACU CONSTRUCTION LLC (0.44%)
USA EROSION, INC.(0.36%)
Contract # 05143209
Totals 3653118.00 144692.28 686573.58 18.7

CountyDALLAS
Highway IH 635
From EAST OF CENTERVILLE RD.
To NORTHWEST HIGHWAY
CSJ 2374-02-124
Proj ID C 2374-2-124
Work Type GR, PVMT, SIGNS, PVMT MRKGS
 
1.288 7718650.04 67818.63 8800592.40 99.9
Work Order 10-12-09
Work Began 04-05-11
Work Completed  
Time Computed 04-10-10
Contract Working Days 459
Addl Days Granted 150
Working Days Charged 711
Percent Time Used 116
Contractor(s)
GLENN THURMAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2374-02-124
DALLAS LITE AND BARRICADE INC. (0.26%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(7.66%)
TEX OP CONSTRUCTION, LP(1.06%)
NORTH TEXAS BOMANITE, INC. (0.63%)
AMERICAN INTELOCK & MODULAR CONSTRUCTION, INC. (4.79%)
DT CONSTRUCTION SERVICES (0.52%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.77%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.92%)
CONCRETE CUTTING BY BOND (0.21%)
INDUS CONSTRUCTION, L.P. (0.54%)
INTEGRATED ROADWAY SERVICES, INC.(5.14%)
CRAIG OLDEN, INC.(1.40%)
LARRETT, INC.( 21.33%)
CB SERVICES, INC.(1.91%)
MIKE ALBERT, INC.(6.03%)
CONCRETE PENETRATING CO. (0.09%)
SOUTHWEST CONSTRUCTION SERVICES(2.19%)
CROSSROADS, L.P. (0.12%)
Contract # 09093060
Totals 7718650.04 67818.63 8800592.40 99.9

CountyDALLAS
Highway IH 635
From IH 20
To IH 30
CSJ 2374-02-136
Proj ID CM 1402(030)
Work Type FULL ITS
 
14.781 6594770.84 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 2374-02-136
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143229
Totals 6594770.84 0.00 0.00 0.0

CountyDALLAS
Highway IH 20
From AT IH 45 RAMP FROM EB IH 20
To NB IH 45
CSJ 2374-03-057
Proj ID IM 0205(151)
Work Type ADD LANE TO DIRECT CONNECTION RAMP
 
1.418 5699998.00 0.00 4268601.09 74.8
Work Order 10-07-11
Work Began 01-12-12
Work Completed  
Time Computed 12-06-11
Contract Working Days 471
Addl Days Granted 0
Working Days Charged 401
Percent Time Used 85
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 2374-03-057
ALLIANCE GEOTECHNICAL GROUP(0.86%)
AXIS CONTRACTING, INC. (1.14%)
BREDA COMPANY, INC.(0.96%)
BROCK ENVIRONMENTAL, LLC (0.71%)
CONCRETE CUTTING BY BOND (0.26%)
DUSTIN ALLEN, INC. (1.41%)
DUSTROL, INC.(0.87%)
FOUNDATION DRILLERS, INC.(1.05%)
HIGHWAY TECHNOLOGIES, INC. (0.55%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (1.12%)
MELS ELECTRIC, L.P.(0.34%)
STRIPING TECHNOLOGY, L.P.(0.93%)
GREAT WESTERN ERECTORS (0.06%)
ERWIN STEEL WORKS, LLC (0.11%)
RG PAINTING(0.39%)
MAGNUM SAWING(0.34%)
D & D STUD WELDING (0.17%)
Contract # 08113245
Totals 5699998.00 0.00 4268601.09 74.8

CountyDALLAS
Highway IH 20
From IH 35E
To IH 45
CSJ 2374-03-076
Proj ID CM 2013(987)
Work Type ITS
 
14.982 1858920.39 194030.46 915917.97 49.2
Work Order 03-13-14
Work Began 07-15-14
Work Completed  
Time Computed 06-12-14
Contract Working Days 164
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 64
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2374-03-076
CITY BUILD UTILITY SUPPLY(3.38%)
ALTUS TRAFFIC MANAGEMENT LLC (0.71%)
ODUM SERVICES, L.P.(1.51%)
INTEGRATED ROADWAY SERVICES, INC.( 39.01%)
ADVANCED FIBER SERVICES(0.79%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.41%)
Contract # 09133012
Totals 1858920.39 194030.46 915917.97 49.2

CountyDALLAS
Highway IH 20
From EAST OF POLK RD
To EAST OF IH 45
CSJ 2374-03-081
Proj ID IM 0205(153)
Work Type LANDSCAPE DEVELOPMENT
 
9.604 399270.75 500.00 361256.07 90.4
Work Order 10-17-13
Work Began 11-12-13
Work Completed  
Time Computed 11-02-13
Contract Working Days 103
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 100
Contractor(s)
BEVERLY SUE GLOBAL SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2374-03-081
GONZALES CONSTRUCTION( 32.56%)
BUYERS BARRICADES, INC.(2.50%)
SATELLITE CABLE CONSTTRUCTION, INC.(7.51%)
ERASMO SPRINKLER & REPAIR( 25.04%)
FOX CONCRETE INNOVATIONS (9.35%)
FAIRWAY LANDSCAPE AND NURSERY, INC.(3.89%)
GUERREROS CONSTRUCTION (7.51%)
Contract # 07133215
Totals 399270.75 500.00 361256.07 90.4

CountyDALLAS
Highway IH 20
From TARRANT COUNTY LINE
To EAST OF CARRIER PARKWAY
CSJ 2374-04-072
Proj ID IM 0205(154)
Work Type FULL DEPTH REPAIR, MILL AND INLAY
 
1.799 3004430.00 0.00 3033175.22 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-21-13
Work Began 04-10-14
Work Completed 10-17-14
Time Computed 12-20-13
Contract Working Days 117
Addl Days Granted 0
Working Days Charged 107
Percent Time Used 91
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 2374-04-072
CROSSROADS, L.P. (0.37%)
HALL BROTHERS, INC.( 12.68%)
O. TREVINO CONSTRUCTION, LLC ( 12.02%)
STRIPING TECHNOLOGY, L.P.(1.73%)
W.O.E. CONSTRUCTION(0.06%)
Contract # 07133008
Totals 3004430.00 0.00 3033175.22 100.0

CountyDALLAS
Highway IH 635
From BELTLINE ROAD
To 0.55 MILES WEST OF BELTINE ROAD
CSJ 2374-07-058
Proj ID CC 2374-7-58
Work Type GRADING, STRUCTURING, SURFACING
 
0.658 2084781.89 2222.10 2222.10 0.1
Work Order 09-09-14
Work Began 11-17-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 237
Addl Days Granted 0
Working Days Charged 1
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2374-07-058
TOTAL HIGHWAY MAINTENANCE, LLC (1.21%)
DUSTROL, INC.(0.95%)
PEACHTREE CONSTRUCTION, LTD. (8.65%)
MCL CONTRACTING, LLC (0.64%)
W.O.E. CONSTRUCTION(0.24%)
SYNERGY SIGNS & SERVICES, LLC(0.30%)
USA SWPPP INSPECTIONS, INC.(6.86%)
Contract # 06143210
Totals 2084781.89 2222.10 2222.10 0.1

CountyDALLAS
Highway IH 635
From BELTLINE RD
To FARMERS BRANCH CREEK
CSJ 2374-07-067
Proj ID IM 6356(447)
Work Type FDRCP, LVL UP, ACP OV
 
5.204 2938210.07 19691.86 2838616.53 96.6
Work Order 05-13-14
Work Began 06-17-14
Work Completed  
Time Computed 06-17-14
Contract Working Days 117
Addl Days Granted 0
Working Days Charged 108
Percent Time Used 92
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2374-07-067
ALTUS TRAFFIC MANAGEMENT LLC (0.48%)
W.O.E. CONSTRUCTION(1.10%)
BRENDA PRICE TRUCKING(0.95%)
AUSTIN BRIDGE & ROAD, LP ( 37.21%)
ACU CONSTRUCTION LLC (5.61%)
DURABLE SPECIALTIES, INC.(0.06%)
EROSION CONTROL MANAGEMENT SERVICES(0.35%)
TRP CONSTRUCTION GROUP, LLC(5.79%)
HALL BROTHERS, INC.( 11.44%)
Contract # 04143007
Totals 2938210.07 19691.86 2838616.53 96.6

CountyKAUFMAN
Highway FM 2728
From US 80
To FM 429 (NORTH)
CSJ 2512-01-011
Proj ID STP 2014(767)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
8.715 9419882.39 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-07-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 246
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2512-01-011
DUSTROL, INC.(8.20%)
PEACHTREE CONSTRUCTION, LTD. ( 11.30%)
USA SWPPP INSPECTIONS, INC.(2.01%)
BAHENA CONSTRUCTION CO.,INC. (6.78%)
LONE STAR BARRIER SERVICES, LLC(0.71%)
TRP CONSTRUCTION GROUP, LLC(0.55%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.13%)
BRENDA PRICE TRUCKING(0.05%)
Contract # 06143002
Totals 9419882.39 0.00 0.00 0.0

CountyKAUFMAN
Highway FM 2728
From SH 34
To IH 20
CSJ 2512-03-007
Proj ID STP 2014(768)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
6.415 4288102.16 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-14-14
Work Began 00-00-00
Work Completed  
Time Computed 11-30-14
Contract Working Days 158
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2512-03-007
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143220
Totals 4288102.16 0.00 0.00 0.0

CountyKAUFMAN
Highway FM 548
From US 80
To FM 1641
CSJ 2588-01-015
Proj ID STP 2015(452)
Work Type LANDSCAPE DEVELOPMENT
 
0.316 204934.68 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-05-14
Work Began 00-00-00
Work Completed  
Time Computed 12-21-14
Contract Working Days 46
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2588-01-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143022
Totals 204934.68 0.00 0.00 0.0

CountyCOLLIN
Highway FM 428
From DENTON COUNTY LINE
To FM 455
CSJ 2678-01-009
Proj ID STP 2014(963)
Work Type SHLDR WDN, BS REP, UNDERSEAL, OV
 
3.855 2519272.50 343709.95 807521.05 32.0
Work Order 08-07-14
Work Began 09-22-14
Work Completed  
Time Computed 08-23-14
Contract Working Days 118
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 37
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2678-01-009
USA EROSION, INC.(3.79%)
STRIPING TECHNOLOGY, L.P.(2.36%)
SAMMY G. SMALLWOOD (1.37%)
PEACHTREE CONSTRUCTION, LTD. ( 33.59%)
FORTSON CONTRACTING, INC.(0.74%)
DUSTROL, INC.(3.84%)
CROSSROADS, L.P. (0.57%)
BROCK ENVIRONMENTAL, LLC (1.33%)
Contract # 06143053
Totals 2519272.50 343709.95 807521.05 32.0

CountyDENTON
Highway FM 2499
From FM 2181 N
To IH 35E
CSJ 2681-01-012
Proj ID C 2681-1-12
Work Type GR, DR, STR, SURF & CONC PAV
 
2.918 34857000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-12-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 505
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2681-01-012
THELIN RECYCLING COMPANY, L.P. (0.28%)
Contract # 07143002
Totals 34857000.00 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9