Monthly State Let Construction Report For Dallas District As Of Apr 11, 2014 Page 1 Of 7

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDALLAS
Highway IH 30
From WEST OF WINSLOW AVE.
To EAST OF DOLPHIN ROAD
CSJ 0009-11-228
Proj ID IM 0305(084)
Work Type LANDSCAPE DEVELOPMENT
 
0.852 226790.08 48977.48 57637.63 25.4
Work Order 09-26-13
Work Began 02-17-14
Work Completed  
Time Computed 10-12-13
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 30
Contractor(s)
ALL AROUND LAWN CARE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-11-228
AQUA BORE(4.59%)
CAPITOL GENERAL CONTRACTORS, LLC ( 15.72%)
Contract # 06133009
Totals 226790.08 48977.48 57637.63 25.4

CountyDALLAS
Highway IH 30
From HASKELL AVE
To SH 78
CSJ 0009-11-230
Proj ID IM 0305(085)
Work Type CONCRETE FULL DEPTH REPAIR
 
1.156 638199.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-11-230
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143011
Totals 638199.00 0.00 0.00 0.0

CountyROCKWALL
Highway IH 30
From INTERCHANGE AT ERBY CAMPBELL BLVD
To .
CSJ 0009-12-074
Proj ID IM 0301(058)
Work Type STR, GRD, BASE, CON PVMT, SIGNS, MRKS
 
1.383 19988908.62 577837.86 10714251.96 53.6
Work Order 03-28-12
Work Began 05-28-13
Work Completed  
Time Computed 09-24-12
Contract Working Days 503
Addl Days Granted 0
Working Days Charged 204
Percent Time Used 40
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-12-074
FORTSON CONTRACTING, INC.(1.59%)
STRAIGHT LINE SAWING & SEALING (0.22%)
MASTERPIECE GRINDING & GROOVING, LLC (0.02%)
STRIPING TECHNOLOGY, L.P.(0.95%)
SOUTHERN CRUSHED CONCRETE LLC(0.10%)
FOUNDATION DRILLERS, INC.(1.19%)
SOUTHERN CRUSHED CONCRETE LLC(0.10%)
WEBBER BARRIER SERVICES, LLC.(0.61%)
PREMIER PAVING, LTD. ( 16.34%)
DUSTROL, INC.(0.33%)
INDUS CONSTRUCTION, L.P. (0.00%)
USA SWPPP INSPECTIONS, INC.(0.78%)
BUYERS BARRICADES, INC.(0.23%)
VENUS CONSTRUCTION (4.48%)
MILLER AND MILLER CUSTOM SERVICES, LLC (5.50%)
B.G. WILLIAMS ASPHALT, LTD (0.47%)
Contract # 01123002
Totals 19988908.62 577837.86 10714251.96 53.6

CountyROCKWALL
Highway IH 30
From AT FM 551
To .
CSJ 0009-12-078
Proj ID C 9-12-78
Work Type STR, GRD, BASE, CONC PVMT, SIGNS, MRKS
 
2.572 30862690.37 0.00 867950.40 2.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 505
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-12-078
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07133203
Totals 30862690.37 0.00 867950.40 2.8

CountyCOLLIN
Highway SH 5
From SP 399
To WILSON CREEK BRIDGE
CSJ 0047-05-051
Proj ID NH 2013(448)
Work Type BASE REPAIR AND OVERLAY
 
1.815 1311303.79 0.00 1421207.95 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-16-13
Work Began 06-13-13
Work Completed  
Time Computed 06-01-13
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 97
Percent Time Used 92
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0047-05-051
DUSTIN ALLEN, INC. (1.48%)
GJ SEEDING, LLC(1.69%)
HALL BROTHERS CONSTRUCTION CO., INC. ( 12.50%)
O. TREVINO CONSTRUCTION, LLC (2.93%)
TOTAL HIGHWAY MAINTENANCE, LLC (4.63%)
L.F. MILLER CONSTRUCTION CO. (4.79%)
Contract # 03133024
Totals 1311303.79 0.00 1421207.95 99.9

CountyCOLLIN
Highway US 75
From SPUR 399 (SH 121 SOUTH)
To WILSON CREEK
CSJ 0047-06-108
Proj ID C 47-6-108
Work Type GR, STRS & SURF
 
3.440 106580042.18 1844088.44 48916899.23 45.8
Work Order 04-18-11
Work Began 01-30-12
Work Completed  
Time Computed 10-15-11
Contract Working Days 1,024
Addl Days Granted 1
Working Days Charged 640
Percent Time Used 62
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0047-06-108
A R DANIEL CONSTRUCTION SERVICES, INC. (0.98%)
NORTH TEXAS CONTRACTING, INC.(4.85%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.79%)
DCCS, LLC(2.42%)
MICA CORPORATION (3.01%)
TEX OP CONSTRUCTION, LP(0.38%)
JAGOE-PUBLIC COMPANY ( 10.82%)
W.O.E. CONSTRUCTION( 15.34%)
ATS DRILLING, L.P. (1.24%)
E W WELLS GROUP LLC(0.09%)
INDUS CONSTRUCTION, L.P. (1.04%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.25%)
CRAIG OLDEN, INC.(0.01%)
EXPERT REBAR SERVICES(0.60%)
SOUTHERN CRUSHED CONCRETE LLC(0.10%)
HERDEZ TRUCKING, INC.(0.09%)
INLET STRUCTURE SPECIALTIES LTD. (0.00%)
DURABLE SPECIALTIES, INC.(0.55%)
BIG DOG DRILLING, LLC(0.01%)
BIG CITY CRUSHED CONCRETE(0.64%)
JET UNDERGROUND UTILITIES, INC.(0.58%)
WYLIE DRILLING & DRAINAGE, INC.(0.01%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.00%)
TREVWAY, INC.(0.25%)
FORTSON CONTRACTING, INC.(0.15%)
SCOTT DERR PAINTING CO (0.06%)
Contract # 03113001
Totals 106580042.18 1844088.44 48916899.23 45.8

CountyCOLLIN
Highway US 75
From SPRING CREEK PARKWAY
To SH 121 (SAM RAYBURN TOLLWAY)
CSJ 0047-06-139
Proj ID C 47-6-139
Work Type GRADE, PAVEMENT, DRAINAGE, STRUCTUR
 
6.509 47531666.94 0.00 0.00 0.0
Work Order 03-04-14
Work Began 00-00-00
Work Completed  
Time Computed 03-20-14
Contract Working Days 766
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 0047-06-139
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12133001
Totals 47531666.94 0.00 0.00 0.0

CountyCOLLIN
Highway SH 5
From AT DGNO RAILROAD UNDERPASS
To RAILROAD DOT NO. 763 390W
CSJ 0047-09-027
Proj ID STP 2012(564)
Work Type GRADING, PVMT, REMOVE STRUCTURE
 
0.407 3522660.11 271834.75 2762161.22 79.7
Work Order 09-24-12
Work Began 04-29-13
Work Completed  
Time Computed 03-22-13
Contract Working Days 188
Addl Days Granted 0
Working Days Charged 235
Percent Time Used 125
Contractor(s)
MCMAHON CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0047-09-027
APAC-TEXAS, INC. (8.87%)
FARR FOUNDATION, INC.(6.42%)
HIGHWAY TECHNOLOGIES, INC. (0.19%)
J. E. GUZMAN CONSTRUCTION, INC.(4.48%)
TEX OP CONSTRUCTION, LP(0.65%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.13%)
WYLIE DRILLING & DRAINAGE, INC.(6.58%)
USA SWPPP INSPECTIONS, INC.(1.88%)
MCL CONTRACTING, LLC (0.80%)
STRIPE-A-ZONE, INC.(0.19%)
ORNELAS & SON"S TRUCKING (4.04%)
Contract # 07123216
Totals 3522660.11 271834.75 2762161.22 79.7

CountyCOLLIN
Highway US 75
From SOUTH OF BLOOMDALE IN MCKINNEY
To TELEPHONE RD (CR 275)
CSJ 0047-14-067
Proj ID C 47-14-67
Work Type GRADING, BASE, PVMT, STR, SIGNS
 
2.453 68107530.26 1369165.71 38333478.28 56.2
Work Order 01-26-12
Work Began 11-05-12
Work Completed  
Time Computed 07-24-12
Contract Working Days 780
Addl Days Granted 0
Working Days Charged 397
Percent Time Used 50
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0047-14-067
LAYFIELD CONSTRUCTION, INC (0.38%)
ANTIGO CONSTRUCTION, INC.(0.10%)
W.O.E. CONSTRUCTION(1.78%)
AUSTIN BRIDGE & ROAD, LP (9.72%)
HAYWARD BAKER, INC.(1.20%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.06%)
INTERSTATE FOUNDATION, LLC (2.05%)
LONE STAR MANHOLE & STRUCTURES, LLC(0.81%)
MICA CORPORATION (1.48%)
RG PAINTING(0.34%)
STRIPING TECHNOLOGY, L.P.(0.62%)
TEX OP CONSTRUCTION, LP(0.47%)
THELIN RECYCLING COMPANY, L.P. (0.14%)
PANTHER CREEK TRANSPORTATION, INC. (0.07%)
HERDEZ TRUCKING, INC.(5.51%)
COWBOY TRUCKING(0.42%)
USA EROSION, INC.(1.00%)
J.L. STEEL REINFORCING, LLC(0.12%)
INDUS CONSTRUCTION, L.P. (0.94%)
HORIZON TRUCKING, LLC(0.20%)
C & B SERVICES, INC. (0.04%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.01%)
TEXAS SHAFTS, INC. (0.13%)
FOUNDATION DRILLERS, INC.(1.64%)
Contract # 12113001
Totals 68107530.26 1369165.71 38333478.28 56.2

CountyCOLLIN
Highway US 75
From TELEPHONE RD (CR 275)
To NORTH OF MELISSA ROAD
CSJ 0047-14-068
Proj ID C 47-14-68
Work Type GRADING, BASE, PVMT, STR, SIGNS
 
3.146 63579301.85 2182411.16 14568940.90 22.9
Work Order 11-16-12
Work Began 09-09-13
Work Completed  
Time Computed 08-03-13
Contract Working Days 920
Addl Days Granted 0
Working Days Charged 158
Percent Time Used 17
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0047-14-068
ANTIGO CONSTRUCTION, INC.(0.07%)
ARTEX ELECTRIC, INC. (0.83%)
DUSTROL, INC.(1.19%)
FORTSON CONTRACTING, INC.(0.42%)
JAGOE-PUBLIC COMPANY ( 15.30%)
J.L. STEEL REINFORCING, LLC(0.91%)
LONE STAR MANHOLE & STRUCTURES, LLC(0.37%)
SCOTT DERR PAINTING CO, LLC(0.22%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.55%)
W.O.E. CONSTRUCTION(0.27%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.93%)
WYLIE DRILLING & DRAINAGE, INC.(0.69%)
CRAIG OLDEN, INC.(0.29%)
COWBOY TRUCKING(0.62%)
TRANSPORT TRUST(0.00%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.01%)
J.L. STEEL REINFORCING, LLC(0.03%)
BRENDA PRICE TRUCKING(2.31%)
THELIN RECYCLING COMPANY, L.P. (0.11%)
Contract # 08123001
Totals 63579301.85 2182411.16 14568940.90 22.9

CountyCOLLIN
Highway US 75
From AT WILMETH ROAD
To IN MCKINNEY
CSJ 0047-14-077
Proj ID NH 2014(476)
Work Type LANDSCAPE DEVELOPMENT
 
0.492 253211.61 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 56
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0047-14-077
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143019
Totals 253211.61 0.00 0.00 0.0

CountyDALLAS
Highway SH 342
From W 8TH ST
To WINTERGREEN
CSJ 0048-01-060
Proj ID NH 2013(731)
Work Type FULL DEPTH CONCRETE PAVEMENT REPAIR
 
1.439 548845.00 0.00 239431.27 43.6
Work Order 09-26-13
Work Began 10-21-13
Work Completed  
Time Computed 10-21-13
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 50
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0048-01-060
DURABLE SPECIALTIES, INC.(0.70%)
RICE ENVIRONMENTAL SERVICES(0.42%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.01%)
I & H CONCRETE CUTTING, INC. (2.36%)
Contract # 05133211
Totals 548845.00 0.00 239431.27 43.6

CountyDALLAS
Highway SH 342 ETC
From 3.131 MILES N OF ELLIS C/L
To NEAR RED OAK RD
CSJ 0048-01-062
Proj ID NH 2014(067)
Work Type SEAL COAT, PVMT MKGS
 
154.979 7850198.09 0.00 54508.83 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-16-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 184
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 2
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0048-01-062
INTERSTATE BARRICADES & MARKINGS, INC. ( 18.33%)
Contract # 10133206
Totals 7850198.09 0.00 54508.83 0.6

CountyELLIS
Highway US 77
From OVERHILL DRIVE
To NORTH OF US 287 IN WAXAHACHIE
CSJ 0048-03-080
Proj ID STP 2013(527)HES
Work Type INSTALL RAISED MEDIAN
 
2.122 1755231.90 4157.44 1436458.50 83.3
Work Order 06-05-13
Work Began 08-19-13
Work Completed  
Time Computed 08-04-13
Contract Working Days 93
Addl Days Granted 0
Working Days Charged 126
Percent Time Used 135
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0048-03-080
STRIPING TECHNOLOGY, L.P.(3.02%)
ENVIRONMENTAL STANDARDS(1.38%)
BRENDA PRICE TRUCKING(0.40%)
W.O.E. CONSTRUCTION(0.14%)
DUSTROL, INC.(0.37%)
PEACHTREE CONSTRUCTION, LTD. (8.20%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.64%)
INTEGRATED ROADWAY SERVICES, INC.( 35.66%)
PRIME UTILITY CONSTRUCTION (1.16%)
Contract # 04133212
Totals 1755231.90 4157.44 1436458.50 83.3

CountyELLIS
Highway US 77 ETC
From NORTH OF US 287 IN WAXAHACHIE
To SH 342
CSJ 0048-03-084
Proj ID STP 2014(343)HESG
Work Type PROFILE PAVEMENT MARKINGS
 
35.046 569367.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-14-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0048-03-084
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01143219
Totals 569367.05 0.00 0.00 0.0

CountyELLIS
Highway IH 35E
From US 287
To SOUTH OF US 77 NORTH
CSJ 0048-04-083
Proj ID HP 2013(099)
Work Type BASE REPAIR AND OVERLAY
 
5.313 7458514.93 33564.90 7494402.09 99.9
Work Order 11-09-12
Work Began 02-04-13
Work Completed  
Time Computed 01-08-13
Contract Working Days 124
Addl Days Granted 43
Working Days Charged 166
Percent Time Used 99
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0048-04-083
FORTSON CONTRACTING, INC.(1.12%)
HIGHWAY TECHNOLOGIES, INC. (0.15%)
STRIPING TECHNOLOGY, L.P.(0.62%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.86%)
TEX OP CONSTRUCTION, LP(1.51%)
TRP CONSTRUCTION GROUP, LLC(0.04%)
VENUS CONSTRUCTION (0.12%)
Contract # 10123005
Totals 7458514.93 33564.90 7494402.09 99.9

CountyELLIS
Highway IH 35E
From SOUTH OF BILL LEWIS RD
To SOUTH OF WAXAHACHIE LAKE
CSJ 0048-08-048
Proj ID IM 0356(445)
Work Type REHAB FRTG RD PV
 
7.000 1574118.58 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-14-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0048-08-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01143009
Totals 1574118.58 0.00 0.00 0.0

CountyDENTON
Highway US 377
From AT HICKORY CREEK AND RELIEF
To .
CSJ 0081-03-051
Proj ID BR 2013(177)
Work Type REHAB AND WIDEN BRIDGE AND APPROACH
 
0.739 4078318.50 588674.68 1267335.74 31.0
Work Order 10-30-13
Work Began 01-07-14
Work Completed  
Time Computed 12-29-13
Contract Working Days 157
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 38
Contractor(s)
REBCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0081-03-051
ACU CONSTRUCTION LLC (0.42%)
C.T. AND S. METALWORKS, INC. (1.69%)
COWTOWN TRAFFIC CONTROL, INC.(0.18%)
JAGOE-PUBLIC COMPANY (4.76%)
LAYFIELD CONSTRUCTION, INC (2.00%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (2.51%)
S & S BRIDGE PAINTING, INC.( 10.86%)
SOUTHEAST GRINDING & GROOVING, LLC (0.11%)
STRIPING TECHNOLOGY, L.P.(1.08%)
WEST TEXAS REBAR PLACERS INC.(1.34%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.89%)
W.O.E. CONSTRUCTION(0.14%)
Contract # 08133029
Totals 4078318.50 588674.68 1267335.74 31.0

CountyDENTON
Highway US 377
From TARRANT COUNTY LINE
To HICKORY CREEK
CSJ 0081-03-052
Proj ID STP 2013(180)
Work Type BASE REP, OV
 
15.648 4479766.95 624644.92 2561196.92 57.1
Work Order 01-03-13
Work Began 03-25-13
Work Completed  
Time Computed 03-04-13
Contract Working Days 222
Addl Days Granted 1
Working Days Charged 186
Percent Time Used 83
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0081-03-052
HIGHWAY TECHNOLOGIES, INC. (0.36%)
STRIPING TECHNOLOGY, L.P.(3.33%)
TEX OP CONSTRUCTION, LP(2.63%)
BUYERS BARRICADES, INC.(0.17%)
Contract # 11123009
Totals 4479766.95 624644.92 2561196.92 57.1

CountyDENTON
Highway US 377
From SOUTH OF BUS 377E
To BUS 377E NORTH OF PILOT POINT
CSJ 0081-06-029
Proj ID C 81-6-29
Work Type REHAB ROADWAY
 
3.702 7501346.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-07-14
Work Began 00-00-00
Work Completed  
Time Computed 03-23-14
Contract Working Days 264
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0081-06-029
CRAIG OLDEN, INC.(1.15%)
DUSTROL, INC.(1.24%)
IOWA BRIDGE & CULVERT, LC(3.94%)
K & S UTILITY CONTRACTORS, INC.( 28.85%)
MARCOM"S MOWING SERVICE, LLC (1.70%)
MEL"S ELECTRIC SERVICE, INC. (0.51%)
STORM WATER MANAGEMENT, INC. (0.37%)
STRIPING TECHNOLOGY, L.P.(2.42%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.73%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.56%)
Contract # 01143003
Totals 7501346.55 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7