Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDALLAS
Highway SH 78
From (GARLAND RD) @ LP 12 (BUCKNER BLVD)
To IN THE CITY OF DALLAS
CSJ 0009-02-050
Proj ID CM 2001(77)
Work Type GRADING, BASE AND PAVING
 
0.227 2763441.70 375340.96 1507827.12 54.5
Work Order 12-31-07
Work Began 05-05-08
Work Completed  
Time Computed 05-05-08
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 125
Percent Time Used 70
Contractor(s)
J.L. STEEL, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0009-02-050
NORTH TEXAS CONTRACTING, INC.( 37.95%)
CROSSROADS DECORATIVE PAVEMENT (2.50%)
HIGHWAY TECHNOLOGIES (0.58%)
INTEGRATED ROADWAY SERVICES, INC.(3.95%)
ROAD MASTER STRIPING LLC (1.04%)
BRENDA PRICE TRUCKING(0.85%)
CONCRETE CUTTING BY BOND (1.26%)
TEX OP CONSTRUCTION, LP(1.17%)
PEACHTREE CONSTRUCTION, LTD. (9.82%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.60%)
CB SERVICES, INC.(2.17%)
A & A CONSTRUCTION (2.37%)
W.O.E. CONSTRUCTION(0.36%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.07%)
INLET STRUCTURE SPECIALTIES LTD. (0.37%)
Contract # 08073016
Totals 2763441.70 375340.96 1507827.12 54.5

CountyDALLAS
Highway IH 30
From IH 35E
To WEST OF LOOP 12 (BUCKNER BLVD)
CSJ 0009-11-188
Proj ID IM 30-1(45)
Work Type CONTINUOUS ILLUMINATION
 
8.840 3798061.36 39811.09 3709635.58 99.9
Work Order 11-10-05
Work Began 05-22-06
Work Completed  
Time Computed 03-10-06
Contract Working Days 280
Addl Days Granted 88
Working Days Charged 368
Percent Time Used 100
Contractor(s)
J & V COMMUNICATION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-11-188
UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(1.54%)
CARTHAGE DRILLING, INC.(8.23%)
DOWN UNDER CONSTRUCTION(0.81%)
FORTSON CONTRACTING, INC.(0.33%)
Contract # 07053011
Totals 3798061.36 39811.09 3709635.58 99.9

CountyDALLAS
Highway IH 30
From 250' EAST OF HUNNICUT
To 900' EAST OF NORTHWEST DR.
CSJ 0009-11-202
Proj ID CM 2006(202)
Work Type EXTEND CONTRAFLOW HOV LANE
 
6.613 13478706.38 0.00 14262723.81 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-06
Work Began 08-21-06
Work Completed  
Time Computed 04-27-06
Contract Working Days 115
Addl Days Granted 231
Working Days Charged 323
Percent Time Used 93
Contractor(s)
W.W. WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-11-202
DALLAS LITE AND BARRICADE INC. (0.08%)
MICA CORPORATION ( 13.57%)
TEXAS HIGHWAY MARKINGS, LLC(0.30%)
APAC-TEXAS, INC. (1.29%)
DUSTROL, INC. (ROANOKE)(0.22%)
FLORES TECHNICAL SERVICES(0.21%)
EAGLE BUILDING SYSTEMS, LTD(0.10%)
Contract # 02063226
Totals 13478706.38 0.00 14262723.81 99.9

CountyDALLAS
Highway IH 30
From WEST OF GOOD-LATIMER EXPRESSWAY
To WEST OF 2ND AVENUE
CSJ 0009-11-205
Proj ID IM 0301(050)
Work Type PVMT WIDENING, DRAINAGE, CTB
 
0.675 2689000.00 0.00 1995975.39 74.2
Work Order 12-01-06
Work Began 01-29-07
Work Completed  
Time Computed 12-17-06
Contract Working Days 173
Addl Days Granted 19
Working Days Charged 185
Percent Time Used 96
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0009-11-205
CAPROCK SPECIALITY CONTRACTORS (0.38%)
DUSTROL, INC. (ROANOKE)(1.87%)
W.W. WEBBER INC. (0.09%)
TEXAS HIGHWAY MARKINGS, LLC(1.60%)
SCOTT DERR PAINTING CO (5.76%)
PEACHTREE CONSTRUCTION, LTD. (6.62%)
FORTSON CONTRACTING, INC.(0.54%)
S & J ELECTRIC (7.70%)
RAMBO CONTRACTING, INC.(5.55%)
ABLE COMMUNICATIONS(1.97%)
EVANS ENVIRONMENTAL CONTRACTING, LLC.(0.06%)
Contract # 11063204
Totals 2689000.00 0.00 1995975.39 74.2

CountyDALLAS
Highway IH 30
From AT BIG TOWN BLVD. (NB)
To .
CSJ 0009-11-206
Proj ID BR 2006(763)
Work Type REHAB. BR
 
0.128 2122914.06 41010.81 2262168.18 99.9
Work Order 09-13-06
Work Began 09-04-07
Work Completed  
Time Computed 09-29-06
Contract Working Days 234
Addl Days Granted 63
Working Days Charged 302
Percent Time Used 101
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-11-206
TEXAS HIGHWAY MARKINGS, LLC(0.85%)
COWTOWN TRAFFIC CONTROL, INC.(1.09%)
J.L. STEEL, L.P. (0.79%)
ODUM SERVICES, L.P.(0.61%)
ARTEX ELECTRIC, INC. (0.69%)
PEACHTREE CONSTRUCTION, LTD. (0.93%)
DUSTROL, INC. (ROANOKE)(0.44%)
STOMPER DEMOLITION (5.46%)
Contract # 08063024
Totals 2122914.06 41010.81 2262168.18 99.9

CountyDALLAS
Highway IH 30
From AT INTERCHANGE WITH PRES GEORGE
To BUSH TOLLWAY IN GARLAND
CSJ 0009-11-210
Proj ID BOR 2005(995)
Work Type GR, STR, PVMT, SIGNS
 
1.395 179236396.32 0.00 0.00 0.0
CountyDALLAS
Highway IH 30
From AT INTRCHG PRES. GEORGE BUSH TOLLWY
To IN GARLAND
CSJ 0009-11-214
Proj ID RW 9-11-214
Work Type ROW ACQ., UTIL. ADJ.; RELOC ASSIST
 
1.395 740589.39 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-23-08
Work Began 00-00-00
Work Completed  
Time Computed 11-08-08
Contract Working Days 972
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0009-11-210
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08083004
Totals 179976985.71 0.00 0.00 0.0

CountyDALLAS
Highway IH 30
From IH 635
To ROCKWALL COUNTY LINE
CSJ 0009-11-216
Proj ID IM 0301(052)
Work Type GUIDE SIGN REFURBISHING
 
33.658 537964.01 124632.44 334009.50 62.0
Work Order 04-14-08
Work Began 07-08-08
Work Completed  
Time Computed 07-08-08
Contract Working Days 170
Addl Days Granted 0
Working Days Charged 75
Percent Time Used 44
Contractor(s)
TIME STRIPING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-11-216
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03083013
Totals 537964.01 124632.44 334009.50 62.0

CountyDALLAS
Highway IH 30
From LOOP 12
To NORTHWEST DRIVE
CSJ 0009-11-217
Proj ID NH 2007(517)
Work Type FULL DEPTH REPAIR
 
17.047 2400357.20 182887.41 2310025.46 96.7
Work Order 06-20-07
Work Began 10-25-07
Work Completed  
Time Computed 07-06-07
Contract Working Days 136
Addl Days Granted 177
Working Days Charged 327
Percent Time Used 104
Contractor(s)
SILVER CREEK CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-11-217
STRIPING TECHNOLOGY, L.P.(0.70%)
Contract # 05073028
Totals 2400357.20 182887.41 2310025.46 96.7

CountyROCKWALL
Highway IH 30 ETC
From AT WEBB CHAPEL, ROSSER AND
To AT PRESTON RD IN DALLAS
CSJ 0009-12-071
Proj ID IM 0305(077)
Work Type REMOVE AND REPLACE DYNAMIC MSG SIGN
 
5.296 297723.29 0.00 322851.86 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-13-06
Work Began 05-21-07
Work Completed  
Time Computed 10-11-06
Contract Working Days 30
Addl Days Granted 11
Working Days Charged 34
Percent Time Used 82
Contractor(s)
J & V COMMUNICATION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-12-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05063015
Totals 297723.29 0.00 322851.86 99.9

CountyROCKWALL
Highway IH 30
From SH 205 AND ON SH 205 FROM SIDS
To YELLOWJACKET
CSJ 0009-12-205
Proj ID IM 0305(076)
Work Type ROW ACQUISITION & UTILITIES
 
0.700 625920.06 -1353.51 706100.58 99.9
CountyROCKWALL
Highway SH 205
From SH 276 TO SIDS, AND
To YELLOWJACKET TO N. OF SH 66
CSJ 0451-01-032
Proj ID HP 2006(694)
Work Type WDN GR STRS & SURF
 
3.600 39495688.83 1609369.53 28983144.72 73.3
Work Order 10-13-06
Work Began 01-29-07
Work Completed  
Time Computed 01-29-07
Contract Working Days 826
Addl Days Granted 0
Working Days Charged 473
Percent Time Used 57
Contractor(s)
BALFOUR BEATTY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0451-01-032
BREDA COMPANY, INC.(0.77%)
ROADWAY SOLUTIONS, INC.(2.94%)
ODUM SERVICES, L.P.(0.63%)
J.H. PAINTING COMPANY(0.14%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(7.55%)
DANIEL CONSTRUCTION SERVICES, INC. (AR DANIEL...)(0.46%)
W.W. WEBBER, LLC (0.47%)
CRAIG OLDEN, INC.(0.84%)
CTF STRIPING (0.89%)
CAPROCK SPECIALITY CONTRACTORS (0.29%)
INLET STRUCTURE SPECIALTIES LTD. (1.98%)
USA EROSION, INC.(0.08%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (1.37%)
A & A CONSTRUCTION (0.70%)
THE ANCHOR GROUP, INC. (0.26%)
DESTRUCTORS, INC.(0.81%)
W. W. FOUNDATION DRILLING, LTD.(0.64%)
DUSTROL, INC. (ROANOKE)(0.44%)
J.G. TRUCKING(0.41%)
PJC UTILITY CONTRACTORS, INC.(5.54%)
MUNICIPAL SERVICE, INC.(0.44%)
J.L. STEEL, L.P. (0.03%)
RICE TUNNELING & BORING, INC.(0.01%)
HIGHWAY TECHNOLOGIES, L.P. (0.59%)
Contract # 07063202
Totals 40121608.89 1608016.02 29689245.30 73.9

CountyCOLLIN
Highway US 75
From COLLIN COUNTY LINE
To SOUTH OF EXCHANGE PARKWAY
CSJ 0047-06-115
Proj ID CM 2006(511)
Work Type STR, CONC PAV, ITS SIGN & MOUNT BAR
 
14.047 18075773.73 292264.07 16507278.80 91.3
Work Order 07-19-06
Work Began 08-28-06
Work Completed  
Time Computed 08-04-06
Contract Working Days 220
Addl Days Granted 335
Working Days Charged 506
Percent Time Used 91
Contractor(s)
W.W. WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0047-06-115
UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(0.47%)
TEXAS HIGHWAY MARKINGS, LLC(5.45%)
MICA CORPORATION ( 61.88%)
CAPROCK SPECIALITY CONTRACTORS (0.13%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.19%)
LAYFIELD CONSTRUCTION, INC (2.20%)
COLE CONSTRUCTION, INC.(0.01%)
Contract # 05063203
Totals 18075773.73 292264.07 16507278.80 91.3

CountyCOLLIN
Highway US 75
From AT SH 190 NORTHBOUND EXIT RAMP
To .
CSJ 0047-06-124
Proj ID STP 2007(351)MM
Work Type ADD LANE FOR DUAL EXIT
 
0.660 706733.92 0.00 693655.10 98.1
Work Order 04-13-07
Work Began 05-21-07
Work Completed  
Time Computed 04-29-07
Contract Working Days 116
Addl Days Granted 0
Working Days Charged 108
Percent Time Used 93
Contractor(s)
REBCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0047-06-124
TEXAS HIGHWAY MARKINGS, LLC(0.67%)
CAPROCK SPECIALITY CONTRACTORS (0.21%)
CRAWFORD YANT(1.01%)
TEXAS SHAFTS, INC. (0.48%)
SCOTT DERR PAINTING CO (0.18%)
MICA CORPORATION ( 13.90%)
ROAD MASTER STRIPING LLC (2.66%)
LAYFIELD CONSTRUCTION, INC (0.28%)
Contract # 03073031
Totals 706733.92 0.00 693655.10 98.1

CountyCOLLIN
Highway US 75
From CHASE OAKS
To BETHANY
CSJ 0047-06-132
Proj ID STP 2008(700)MM
Work Type GR, PVMT, SIGNS, PVMT MKGS
 
0.966 1559000.00 280889.09 636435.63 40.8
Work Order 08-08-08
Work Began 09-02-08
Work Completed  
Time Computed 08-24-08
Contract Working Days 158
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 25
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0047-06-132
AUSTIN BRIDGE & ROAD, LP (5.57%)
CAPROCK SPECIALITY CONTRACTORS (0.63%)
DUSTROL, INC.(0.79%)
FORTSON CONTRACTING, INC.(0.83%)
K & S UTILITY CONTRACTORS, INC.(6.44%)
MICA CORPORATION ( 13.28%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.15%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.18%)
Contract # 06083210
Totals 1559000.00 280889.09 636435.63 40.8

CountyCOLLIN
Highway US 75
From AT PARKER ROAD
To .
CSJ 0047-06-134
Proj ID STP 2008(360)MM
Work Type RECONSTRUCT INTERCHANGE
 
0.814 20172428.77 453528.13 1798289.79 8.9
Work Order 06-18-08
Work Began 09-05-08
Work Completed  
Time Computed 08-17-08
Contract Working Days 647
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 7
Contractor(s)
W.W. WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0047-06-134
CRAIG OLDEN, INC.(0.46%)
PAVER 1(0.12%)
EVANS ENVIRONMENTAL CONTRACTING, LLC.(1.14%)
FORTSON CONTRACTING, INC.(0.12%)
FOUNDATION DRILLERS, INC.(1.94%)
HARDSCAPE SPECIALTIES, INC.(0.16%)
HIGHWAY TECHNOLOGIES (0.45%)
INDUS CONSTRUCTION, L.P. (3.62%)
J.T. DERSNER INC.(3.19%)
MICA CORPORATION (3.65%)
PRIMATE CONSTRUCTION, INC. (0.05%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(5.62%)
TEXAS HIGHWAY MARKINGS, LLC(0.60%)
Contract # 04083002
Totals 20172428.77 453528.13 1798289.79 8.9

CountyCOLLIN
Highway US 75
From N. OF EXCHANGE PKWY
To S. OF STACY RD
CSJ 0047-06-140
Proj ID CC 47-6-140
Work Type GR, PVMT, STR, PVMT MKGS
 
0.990 1869778.72 681770.88 681770.88 36.4
Work Order 09-16-08
Work Began 10-02-08
Work Completed  
Time Computed 10-02-08
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 17
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0047-06-140
BREDA COMPANY, INC.(0.61%)
CAPROCK SPECIALITY CONTRACTORS (0.55%)
K & S UTILITY CONTRACTORS, INC.(4.79%)
MICA CORPORATION (7.42%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.38%)
PEACHTREE CONSTRUCTION, LTD. (7.94%)
SCOTT DERR PAINTING CO (0.11%)
SOUTHWEST ENVIRONMENT SERVICES, INC. (1.42%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.11%)
Contract # 08083222
Totals 1869778.72 681770.88 681770.88 36.4

CountyDALLAS
Highway US 75
From SP 366 TO IH 635 IN DALLAS AND
To @ COLLIN BLVD IN CITY OF RICHARDSON
CSJ 0047-07-202
Proj ID C 47-7-202
Work Type REHAB OF DETECTION SYSTEM
 
9.230 314305.29 32570.33 312542.87 99.9
Work Order 08-10-06
Work Began 01-03-07
Work Completed  
Time Computed 12-08-06
Contract Working Days 40
Addl Days Granted 2
Working Days Charged 38
Percent Time Used 90
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0047-07-202
AMERICAN TRAFFIC CONTROL (8.68%)
Contract # 07063252
Totals 314305.29 32570.33 312542.87 99.9

CountyDALLAS
Highway US 75
From SPUR 366
To RICHARDSON CITY LIMITS
CSJ 0047-07-211
Proj ID CL 47-7-211
Work Type LANDSCAPE DEVELOPMENT
 
10.528 1182665.00 37093.85 905547.52 80.5
Work Order 02-20-07
Work Began 03-08-07
Work Completed  
Time Computed 03-08-07
Contract Working Days 506
Addl Days Granted 0
Working Days Charged 421
Percent Time Used 83
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD
SUBCONTRACTOR(S) FOR CCSJ: 0047-07-211
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01073015
Totals 1182665.00 37093.85 905547.52 80.5

CountyCOLLIN
Highway SH 5
From STACY ROAD
To EXCHANGE PARKWAY
CSJ 0047-09-029
Proj ID STP 2007(433)MM
Work Type GR, STRS & SURF
 
1.072 6227504.83 905355.76 2754515.17 44.2
Work Order 06-08-07
Work Began 11-13-07
Work Completed  
Time Computed 06-24-07
Contract Working Days 361
Addl Days Granted 82
Working Days Charged 239
Percent Time Used 53
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0047-09-029
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.83%)
TEX OP CONSTRUCTION, LP(1.89%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 12.39%)
BREDA COMPANY, INC.(0.77%)
PAVER SYSTEMS INTERNATIONAL(1.14%)
RAMBO CONTRACTING, INC.(5.00%)
PRIMATE CONSTRUCTION, INC. (0.46%)
MEL'S ELECTRIC SERVICE, INC. (2.32%)
ODUM SERVICES, L.P.(0.32%)
TEXAS HIGHWAY MARKINGS, LLC(1.57%)
EAGLE AGGREGATE TRANSPORTATION, LLC. (0.96%)
BRENDA PRICE TRUCKING(0.24%)
BRENDA PRICE TRUCKING(0.72%)
LONE STAR MANHOLE & STRUCTURES, LLC(4.02%)
Contract # 04073208
Totals 6227504.83 905355.76 2754515.17 44.2

CountyCOLLIN
Highway US 75
From AT US 380
To .
CSJ 0047-14-063
Proj ID STP 2008(363)MM
Work Type STR, GR, PVMT, SIGNS, SIGNALS
 
1.052 25662948.02 257066.29 257066.29 1.0
Work Order 05-08-08
Work Began 10-13-08
Work Completed  
Time Computed 10-13-08
Contract Working Days 659
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0047-14-063
BREDA COMPANY, INC.(0.90%)
C.B. SERVICES, INC.(0.33%)
CRAIG OLDEN, INC.(1.33%)
CROSSROADS, L.P. (0.28%)
FORTSON CONTRACTING, INC.(0.88%)
FOUNDATION DRILLERS, INC.(0.76%)
HUERTA'S TRUCKING, INC.(4.37%)
HOUSTON SAWING & DRILLING(0.04%)
INLET STRUCTURE SPECIALTIES LTD. (1.95%)
INTEGRATED ROADWAY SERVICES, INC.(5.25%)
JAGOE-PUBLIC COMPANY ( 13.29%)
MAS-TEK ENGINEERING & ASSOCIATES, INC. (0.07%)
RAYMOND PAINTING, INC. (0.08%)
RMI WORLDWIDE, LLC (0.09%)
SITESAFE PRODUCTS TEXAS(0.11%)
SOUTHWEST CONSTRUCTION SERVICES(0.25%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.63%)
W.W. WEBBER INC. (0.92%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.59%)
Contract # 02083201
Totals 25662948.02 257066.29 257066.29 1.0

CountyDALLAS
Highway SH 342
From BELT LINE ROAD
To PLEASANT RUN ROAD
CSJ 0048-01-057
Proj ID STP 2006(259)
Work Type BASE, CONC PVMT, PVMT MKGS
 
1.373 3746297.80 21341.82 4027390.68 99.9
Work Order 03-28-06
Work Began 05-24-06
Work Completed  
Time Computed 04-03-06
Contract Working Days 267
Addl Days Granted 127
Working Days Charged 380
Percent Time Used 96
Contractor(s)
TISEO PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0048-01-057
AXIS CONTRACTING, INC. (4.12%)
BUYER BARRICADES (0.75%)
CEN-TEX SEEDING, INC.(0.37%)
K & S UTILITY CONTRACTORS, INC.(7.84%)
MELS ELECTRIC, L.P.(1.46%)
PAVER SYSTEMS INTERNATIONAL(0.33%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 21.91%)
ROAD MASTER STRIPING LLC (0.79%)
CAPROCK SPECIALITY CONTRACTORS (0.81%)
CRAIG DEVELOPMENT, INC.( 10.03%)
DUSTROL, INC. (ROANOKE)(1.25%)
REBAR SPECIALISTS(0.71%)
COASTAL CONCEPTS, LLC(0.18%)
Contract # 02063209
Totals 3746297.80 21341.82 4027390.68 99.9