Monthly State Let Construction Report For Dallas District As Of Jun 12, 2017 Page 6 Of 8

Last Update: Monday, June 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDALLAS
HighwayCS
FromBELT LINE ROAD AT DALLAS PKWY
To.
CSJ0918-47-120
Proj IDSTP 1602(110)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
1.0001300500.00573152.8344.0
Work Order08-08-16
Work Began11-09-16
Work Completed
Time Computed11-06-16
Contract Working Days172
Addl Days Granted0
Working Days Charged95
Percent Time Used55
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-120
ROAD MASTER STRIPING LLC (5.59)
LUZ LERMA CONSTRUCTION, INC. (15.28)
Contract #05163228
Totals1300500.0017412.48573152.8344.0

CountyNAVARRO
HighwayFM 1838
From0.939 MI N OF CR 4270
ToFM 638
CSJ0997-02-039
Proj IDSTP 2016(992)HES
Work TypeCONSTRUCT PAVED SHOULDERS
 
1.5531991914.54263940.1113.2
CountyNAVARRO
HighwayFM 3383
FromFM 1126
ToCR 1110
CSJ3401-01-007
Proj IDSTP 2016(993)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
1.5001883297.661413990.4475.0
Work Order00-00-00
Work Began02-24-17
Work Completed
Time Computed02-24-17
Contract Working Days251
Addl Days Granted0
Working Days Charged66
Percent Time Used26
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0997-02-039
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.66)
ODUM SERVICES, L.P. (0.35)
SAN-ANN-CO., INC. (0.90)
TOTAL HIGHWAY MAINTENANCE, LLC (0.57)
BEAR CREEK CONSTRUCTION, LLC (21.49)
POTTER TRUCKING (1.29)
Contract #12163029
Totals3875212.20653776.111677930.5543.2

CountyCOLLIN
HighwayFM 546
FromSH 5
ToEAST OF COUNTRY LN/AIRPORT RD
CSJ1013-01-026
Proj IDC 1013-1-26
Work TypeGR, PVMT, STR, SIGNS, PVMT MKGS
 
1.72417391616.986236808.4735.8
Work Order08-11-16
Work Began01-04-17
Work Completed
Time Computed11-09-16
Contract Working Days411
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1013-01-026
SCOTT DERR PAINTING CO, LLC (0.13)
LIRA ELECTRIC (0.49)
ROYAL REBAR (0.95)
PANIOLO CONSTRUCTION SERVICES, LLC (3.60)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.18)
BROCK ENVIRONMENTAL, LLC (0.13)
LINDAMOOD DEMOLITION, INC. (0.05)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (8.87)
WYLIE DRILLING & DRAINAGE, INC. (1.41)
W.O.E. CONSTRUCTION (0.16)
ALLIANCE GEOTECHNICAL GROUP (0.28)
STRIPING TECHNOLOGY, L.P. (0.56)
Contract #05163037
Totals17391616.98922542.186236808.4735.8

CountyROCKWALL
HighwayFM 548
FromSH 276
ToSH 66
CSJ1014-02-041
Proj IDSTP 2016(145)
Work TypeWDN,STR,REMX,OL,PV MRKS
 
12.75113784401.3510035559.6872.8
Work Order02-03-16
Work Began03-28-16
Work Completed
Time Computed03-28-16
Contract Working Days363
Addl Days Granted0
Working Days Charged314
Percent Time Used86
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1014-02-041
TEXOP CONSTRUCTION (1.79)
EROSION CONTROL MANAGEMENT SERVICES (0.48)
PREMIER PAVING, LTD. (22.61)
SCOTT PAVING, INC. (3.33)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.66)
TRP CONSTRUCTION GROUP, LLC (0.94)
DALLAS LITE AND BARRICADE INC. (0.54)
COMEN ENTERPRISE (1.34)
COWBOY TRUCKING (4.54)
FARR FOUNDATION, INC. (0.61)
Contract #10153205
Totals13784401.35937609.5610035559.6872.8

CountyROCKWALL
HighwayFM 740
FromFM 549 / FM 550 INTERSECTION
ToFM 1140 NORTH IN HEATH
CSJ1014-03-049
Proj IDC 1014-3-49
Work TypeGRADING,STRUCTURES,DRAINAGE, & PVMT
 
1.85612967453.427375292.2756.8
Work Order11-14-13
Work Began07-20-15
Work Completed
Time Computed08-11-14
Contract Working Days412
Addl Days Granted1
Working Days Charged366
Percent Time Used88
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1014-03-049
W.O.E. CONSTRUCTION (0.30)
TEX OP CONSTRUCTION, LP (2.01)
TEXAS INLETS, INC. (3.62)
SYNERGY SIGNS & SERVICES, LLC (0.37)
HAYWARD BAKER, INC. (0.81)
STRIPING TECHNOLOGY, L.P. (0.99)
USA SWPPP INSPECTIONS, INC. (1.23)
PREMIER PAVING, LTD. (4.86)
DURABLE SPECIALTIES, INC. (3.25)
BREDA COMPANY, INC. (0.67)
BUYERS BARRICADES, INC. (0.31)
BRENDA PRICE TRUCKING (4.98)
FANNIN TREE FARM, LTD (0.33)
Contract #08133209
Totals12967453.42366820.497375292.2756.8

CountyROCKWALL
HighwayFM 3549
FromSH 66
ToFM 552
CSJ1015-01-022
Proj IDSTP 2015(590)
Work TypeBASE REPAIR, LEVEL UP, OVERLAY
 
2.3192576274.622973960.1499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-30-15
Work Began08-05-15
Work Completed
Time Computed04-15-15
Contract Working Days165
Addl Days Granted31
Working Days Charged195
Percent Time Used99
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 1015-01-022
PEACHTREE CONSTRUCTION, LTD. (14.69)
K & S UTILITY CONTRACTORS, INC. (9.85)
ALTUS TRAFFIC MANAGEMENT LLC (0.36)
USA SWPPP INSPECTIONS, INC. (2.61)
STRIPING TECHNOLOGY, L.P. (1.47)
BAHENA CONSTRUCTION CO.,INC. (0.28)
RAMBO CONTRACTING, INC. (2.41)
Contract #02153221
Totals2576274.620.002973960.1499.9

CountyROCKWALL
HighwayFM 1138
FromSH 66
ToCOLLIN COUNTY LINE
CSJ1016-03-013
Proj IDSTP 1602(216)
Work TypeBASE REPAIR,LEVEL UP,OVERLAY
 
1.0651329420.201220147.4993.6
CountyROCKWALL
HighwayFM 35
FromIH 30
ToHUNT COUNTY LINE
CSJ1017-02-012
Proj IDSTP 1602(216)
Work TypeMILL,BS REP,OV
 
1.539627099.96606888.4796.7
Work Order07-01-16
Work Began08-04-16
Work Completed
Time Computed08-04-16
Contract Working Days70
Addl Days Granted0
Working Days Charged101
Percent Time Used144
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1016-03-013
ALL AMERICAN MILLING, LLC (6.17)
FLEX SUPPLY, LLC (0.40)
JM YANEZ CONSTRUCTION, INC. (9.90)
SYNERGY SIGNS & SERVICES, LLC (1.36)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (7.47)
TOTAL HIGHWAY MAINTENANCE, LLC (1.04)
Contract #05163033
Totals1956520.1615790.781827035.9694.6

CountyKAUFMAN
HighwayFM 1392
FromUS 80
ToSH 205
CSJ1016-06-011
Proj IDSTP 2017(888)
Work TypeMILL,REPAIR,OL,STR,MRKS,SIGNS
 
4.5895553284.140.000.0
CountyROCKWALL
HighwayFM 740
From1.361 MI NORTH OF KAUFMAN CO. LINE
ToKAUFMAN COUNTY LINE
CSJ1091-04-027
Proj IDSTP 1702(153)HES
Work TypeWARNING SIGNALS SIGNS AND SURFACE
 
1.361122889.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-11-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days221
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1016-06-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173042
Totals5676173.140.000.000.0

CountyDALLAS
HighwayFM 1382
FromE GRAND PRAIRIE RD
ToNORTH OF SH 180
CSJ1047-03-072
Proj IDNH 1702(085)
Work TypeRETAINING WALL,BRD ABUTM REPAIR
 
0.4551680355.860.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1047-03-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173225
Totals1680355.860.000.000.0

CountyELLIS
HighwayFM 85
FromIH 45
ToFM 1182
CSJ1050-01-017
Proj IDSTP 2016(146)
Work TypeACP OVERLAY,GR,STR,PVMT MKGS
 
8.40112874396.217355289.6357.1
Work Order12-21-15
Work Began03-14-16
Work Completed
Time Computed03-14-16
Contract Working Days490
Addl Days Granted34
Working Days Charged306
Percent Time Used58
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1050-01-017
FARR FOUNDATION, INC. (0.78)
LONE STAR BARRIER SERVICES, LLC (0.82)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.18)
SHALOM SERVICES CORPORATION (1.22)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.24)
WOLFE CONSTRUCTION GROUP, INC. (0.30)
STRIPING TECHNOLOGY, L.P. (0.81)
PROJECT 2015, LLC (3.53)
UNDER CONSTRUCTION INC. (0.00)
GLL CORPORATION DBA MG TRUCKING (0.01)
NIXON ENGINEERING (0.00)
COMEN ENTERPRISE LLC (0.81)
FORTSON CONTRACTING, INC. (0.12)
J.M. YANEZ CONSTRUCTION (3.53)
Contract #10153212
Totals12874396.21673001.607355289.6357.1

CountyELLIS
HighwayFM 664
FromNORTH OF US 287
ToSOUTH OF RED OAK CREEK IN OVILLA
CSJ1051-01-042
Proj IDSTP 2015(654)
Work TypeADD 3-FOOT PAVED SHOULDERS
 
7.30311142221.2011409936.9199.9
Work Order04-20-15
Work Began06-22-15
Work Completed
Time Computed12-23-15
Contract Working Days293
Addl Days Granted29
Working Days Charged463
Percent Time Used143
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1051-01-042
BROCK ENVIRONMENTAL SERVICES, LLC (0.31)
CROSSROADS, L.P. (0.48)
DUSTROL, INC. (1.95)
STRIPING TECHNOLOGY, L.P. (0.63)
PEACHTREE CONSTRUCTION, LTD. (33.79)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.89)
JE CASEY, LLC (1.56)
SYNERGY SIGNS & SERVICES (0.72)
OSCAR ORDUNO, INC. (2.36)
BRENDA PRICE TRUCKING (1.09)
AAA DRILLING FOUNDATION CO., INC. (0.32)
FORTSON CONTRACTING, INC. (0.58)
LONE STAR BARRIER SERVICES, LLC (0.53)
TEXOP CONSTRUCTION (0.08)
APAC-TEXAS, INC. (2.25)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.06)
Contract #03153213
Totals11142221.2036628.7611409936.9199.9

CountyELLIS
HighwayFM 876
FromAT BIG ONION CREEK
To.
CSJ1051-02-017
Proj IDBR 2015(591)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2551721378.551667794.3396.8
Work Order04-03-15
Work Began09-15-15
Work Completed
Time Computed09-15-15
Contract Working Days360
Addl Days Granted0
Working Days Charged352
Percent Time Used97
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1051-02-017
N-LINE TRAFFIC MAINTENANCE, L.P. (0.93)
IOWA BRIDGE & CULVERT, LC (3.59)
STRIPING TECHNOLOGY, L.P. (1.60)
GJ SEEDING, LLC (5.27)
FOUNDATION DRILLERS, INC. (3.17)
FRAIRE"S REBAR, INC (4.42)
F & K BUILDERS (2.81)
PEACHTREE CONSTRUCTION, LTD. (6.81)
CLEMONS TRUCKING (2.17)
JANEK & WHITTEN CONSTRUCTION INC. (0.43)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (5.70)
FORTSON CONTRACTING, INC. (1.45)
DUSTROL, INC. (0.26)
Contract #02153207
Totals1721378.55384.951667794.3396.8

CountyDALLAS
HighwayIH 30
FromBELTLINE ROAD
ToMAC ARTHUR BLVD.
CSJ1068-04-122
Proj IDC 1068-4-122
Work TypeGR, STRS & PAV
 
1.52224620668.2710608700.3443.0
CountyDALLAS
HighwayIH 30
FromBELT LINE RD
ToMACARTHUR RD
CSJ1068-04-137
Proj IDROW 1068-4-137
Work TypeROW ACQ, UTIL & RELOC
 
0.760565255.00538598.0095.2
Work Order02-16-16
Work Began07-25-16
Work Completed
Time Computed06-15-16
Contract Working Days538
Addl Days Granted0
Working Days Charged232
Percent Time Used43
Contractor(s)
HAYDON CENTRAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-122
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (2.91)
LAYFIELD CONSTRUCTION, INC (0.24)
TOTAL HIGHWAY MAINTENANCE, LLC (0.38)
FORTSON CONTRACTING, INC. (0.19)
SOUTH TEXAS PAINTING COMPANY (0.01)
ROBERTS TRUCKING (0.07)
W.O.E. CONSTRUCTION (0.20)
ANCORTEX, INC. (12.10)
T-BAR FENCE, INC. (0.11)
INTEGRATED ROADWAY SERVICES, INC. (3.09)
TOMMY ELECTRIC, LLC (0.15)
THELIN RECYCLING COMPANY, L.P. (0.13)
BOWMAN ENGINEERING & CONSULTING, INC (9.83)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.04)
FLASHFILL SERVICES, LLC (0.96)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.02)
BRUNDAGE-BONE (0.07)
PENHALL COMPANY (0.00)
UNIVERSAL FENCE COMPANY, INC. (0.01)
A-CORE DRILLING AND SAWING (0.09)
MISTER SWEEPER LP (0.00)
A-CORE, INC. (0.09)
FOUNDATION DRILLERS, INC. (0.12)
WRIGHT TREE SERVICES, INC (0.09)
Contract #12153004
Totals25185923.27461747.8411147298.3444.2

CountyDALLAS
HighwayIH 30
FromNW 7TH STREET
ToBELTLINE ROAD
CSJ1068-04-148
Proj IDSTP 2016(740)MM
Work TypeGR,DRN,RET WLS,CONC PAV,SIG,PV MRKS
 
1.0117991673.303313397.5541.4
Work Order04-01-16
Work Began05-18-16
Work Completed
Time Computed05-18-16
Contract Working Days380
Addl Days Granted0
Working Days Charged92
Percent Time Used24
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-148
ALTUS TRAFFIC MANAGEMENT LLC (0.17)
W.O.E. CONSTRUCTION (2.42)
C.T. AND S. METALWORKS, INC. (0.37)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.22)
FORTSON CONTRACTING, INC. (0.31)
K & S UTILITY CONTRACTORS, INC. (12.19)
MICA CORPORATION (3.52)
STORM WATER MANAGEMENT, INC. (0.23)
STRIPE-A-ZONE, INC. (1.02)
SYNERGY SIGNS & SERVICES (0.36)
TEXAS BOMANITE (0.05)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.32)
TEXAS SHAFTS, INC. (0.67)
BOWMAN ENGINEERING & CONSTRUCTION, INC. (1.25)
SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C. (0.01)
Contract #02163225
Totals7991673.30642585.063313397.5541.4

CountyELLIS
HighwayFM 875
FromAT WAXAHACHIE CREEK
To.
CSJ1159-01-022
Proj IDBR 2013(604)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.4713724841.0026660.860.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-13-15
Work Began05-31-17
Work Completed
Time Computed12-11-15
Contract Working Days467
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1159-01-022
K&A STEEL, LLC (3.87)
TOTAL HIGHWAY MAINTENANCE, LLC (0.94)
IOWA BRIDGE & CULVERT, LC (3.19)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (2.30)
TOTAL HIGHWAY MAINTENANCE, LLC (0.54)
BRENDA PRICE TRUCKING (2.54)
FOUNDATION DRILLERS, INC. (2.04)
FORTSON CONTRACTING, INC. (1.88)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (7.37)
Contract #06153025
Totals3724841.000.0026660.860.7

CountyELLIS
HighwayFM 879
From2.1 MILES WEST OF IKE RD
To0.3 MILE WEST OF FM 1722
CSJ1159-02-032
Proj IDSTP 1502(328)HES
Work TypeGR, BASE, PVMT, PVMT MKGS, SIGNS
 
6.6679549753.049355653.3799.2
Work Order07-31-15
Work Began09-03-15
Work Completed
Time Computed07-31-15
Contract Working Days315
Addl Days Granted21
Working Days Charged448
Percent Time Used133
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1159-02-032
CROSS ROADS, L.P. (0.38)
BROCK ENVIRONMENTAL SERVICES, LLC (0.19)
ACU CONSTRUCTION LLC (1.24)
STRIPING TECHNOLOGY, L.P. (0.61)
SYNERGY SIGNS & SERVICES (0.28)
FORTSON CONTRACTING, INC. (1.62)
NORTH EASTERN PAVERS (4.90)
PEACHTREE CONSTRUCTION, LTD. (13.21)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.95)
HAYWARD BAKER, INC. (0.67)
BRENDA PRICE TRUCKING (6.89)
DFW MATERIALS LP (2.63)
Contract #06153225
Totals9549753.0443482.349355653.3799.2

CountyELLIS
HighwayFM 984
FromAT DRAW, 1.7 MI SOUTH OF SH 34
To.
CSJ1211-01-018
Proj IDBR 2015(483)
Work TypeREPL BR AND APPR
 
0.117879623.40332021.6537.7
CountyELLIS
HighwayFM 984
FromAT ONION CREEK RELIEF #1 AND #2
To.
CSJ1211-01-019
Proj IDBR 2015(484)
Work TypeREPL BR
 
0.1561453823.50841398.5457.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-02-15
Work Began02-25-16
Work Completed
Time Computed02-25-16
Contract Working Days379
Addl Days Granted0
Working Days Charged298
Percent Time Used78
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 1211-01-018
FORTSON CONTRACTING, INC. (2.16)
USA EROSION, INC. (3.94)
TOTAL HIGHWAY MAINTENANCE, LLC (0.48)
STRIPING TECHNOLOGY, L.P. (1.23)
TEX OP CONSTRUCTION, LP (1.11)
W. W. FOUNDATION DRILLING, LTD. (5.36)
DFW REBAR, INC. (0.68)
ADVANCED PAVING COMPANY (4.32)
B.G. WILLIAMS ASPHALT, LTD (0.22)
HOUSTON SAWING & DRILLING (0.26)
KNIFE RIVER CORPORATION - SOUTH (0.19)
CTBX, INC. (1.02)
MASTERPIECE GRINDING & GROOVING, LLC (0.25)
AVANZA CONSTRUCTION & EARTHWORKS, LLC (0.00)
Contract #01153012
Totals2333446.900.001173420.1950.2

CountyKAUFMAN
HighwayFM 1388
FromFM 148
ToUS 175
CSJ1217-03-019
Proj IDSTP 2016(360)
Work TypeGR, BASE, ACP OVERLAY, PVMT MKGS
 
12.03017608683.4412100140.5668.7
CountyKAUFMAN
HighwayFM 1388
FromAT KINGS CREEK RELIEF #2
To.
CSJ1217-03-020
Proj IDBR 2016(361)
Work TypeREPLACE BRIDGE
 
0.4954432389.141749205.1439.4
Work Order01-29-16
Work Began04-11-16
Work Completed
Time Computed04-11-16
Contract Working Days580
Addl Days Granted0
Working Days Charged319
Percent Time Used55
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1217-03-019
ALTUS TRAFFIC MANAGEMENT LLC (0.13)
SOUTHWEST CONSTRUCTION SERVICES (0.39)
K & S UTILITY CONTRACTORS, INC. (9.31)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (0.05)
PEACHTREE CONSTRUCTION, LTD. (4.40)
SOUTHERN CROSS CONTRACTORS, LLC (0.08)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (5.40)
SYNERGY SIGNS & SERVICES, LLC (0.39)
FARR FOUNDATION, INC. (0.56)
FORTSON CONTRACTING, INC. (0.74)
TRP CONSTRUCTION GROUP, LLC (0.60)
HERDEZ TRUCKING, INC. (2.17)
RAMBO CONTRACTING, INC. (4.73)
TEXOP CONSTRUCTION (0.07)
EJ SMITH CONSTRUCTION COMPANY, LLC (7.55)
BEAIRD DRILLING (0.35)
W.O.E. CONSTRUCTION (1.62)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.36)
Contract #12153205
Totals22041072.581126822.1213849345.7062.8

CountyNAVARRO
HighwayFM 1126
FromAT CHAMBERS CREEK, SW OF IH 45
To.
CSJ1289-01-029
Proj IDBR 1602(046)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.8906714487.744454373.1666.3
Work Order06-02-16
Work Began08-09-16
Work Completed
Time Computed07-05-16
Contract Working Days386
Addl Days Granted10
Working Days Charged201
Percent Time Used50
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1289-01-029
A. L. HELMCAMP, INC. (22.43)
IOWA BRIDGE & CULVERT, LC (1.25)
AARON CONCRETE CONTRACTORS, L.P. (3.51)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.82)
FORTSON CONTRACTING, INC. (0.29)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.29)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.26)
TOTAL HIGHWAY MAINTENANCE, LLC (0.42)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.37)
MCL CONTRACTING, LLC (0.26)
Contract #04163237
Totals6714487.74750179.634454373.1666.3

CountyDENTON
HighwayFM 1171
FromON CORPS OF ENGINEERS PROPERTY
ToNEAR WHITE'S BRANCH
CSJ1311-01-053
Proj IDC 1311-1-53
Work TypeTREES AND PLANTS
 
0.001148908.5088854.5459.6
CountyDENTON
HighwayFM 2499
FromFM 2181
ToHICKORY CREEK
CSJ2681-01-022
Proj IDNH 1502(094)
Work TypeLANDSCAPE DEVELOPMENT
 
1.112299148.05297282.8899.3
Work Order07-20-15
Work Began08-04-15
Work Completed
Time Computed08-04-15
Contract Working Days60
Addl Days Granted2
Working Days Charged34
Percent Time Used54
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1311-01-053
ALTUS TRAFFIC MANAGEMENT LLC (0.85)
AMAYA UTILITY (0.56)
QUICK SET CONCRETE, INC. (5.50)
Contract #05153018
Totals448056.557281.28386137.4286.1

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8