Monthly State Let Construction Report For Dallas District As Of Nov 9, 2016 Page 6 Of 8

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDALLAS
Highway CS
From BELT LINE ROAD AT DALLAS PKWY
To .
CSJ 0918-47-120
Proj ID STP 1602(110)HES
Work Type IMPROVE TRAFFIC SIGNALS
 
1.000 1300500.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-08-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 172
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-120
ROAD MASTER STRIPING LLC (5.59%)
Contract # 05163228
Totals 1300500.00 0.00 0.00 0.0

CountyCOLLIN
Highway FM 546
From SH 5
To EAST OF COUNTRY LN/AIRPORT RD
CSJ 1013-01-026
Proj ID C 1013-1-26
Work Type GR, PVMT, STR, SIGNS, PVMT MKGS
 
1.724 17391616.98 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-11-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 411
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1013-01-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163037
Totals 17391616.98 0.00 0.00 0.0

CountyROCKWALL
Highway FM 548
From SH 276
To SH 66
CSJ 1014-02-041
Proj ID STP 2016(145)
Work Type WDN, STR, REMX, OL, PV MRKS
 
12.751 13784401.35 1089113.45 5539819.42 40.1
Work Order 02-03-16
Work Began 03-28-16
Work Completed  
Time Computed 03-28-16
Contract Working Days 363
Addl Days Granted 0
Working Days Charged 165
Percent Time Used 45
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1014-02-041
TEXOP CONSTRUCTION (1.79%)
EROSION CONTROL MANAGEMENT SERVICES(0.48%)
PREMIER PAVING, LTD. ( 22.61%)
SCOTT PAVING, INC. (3.33%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.66%)
TRP CONSTRUCTION GROUP, LLC(0.94%)
DALLAS LITE AND BARRICADE INC. (0.54%)
COMEN ENTERPRISE (1.34%)
COWBOY TRUCKING(4.54%)
FARR FOUNDATION, INC.(0.61%)
Contract # 10153205
Totals 13784401.35 1089113.45 5539819.42 40.1

CountyROCKWALL
Highway FM 740
From FM 549 / FM 550 INTERSECTION
To FM 1140 NORTH IN HEATH
CSJ 1014-03-049
Proj ID C 1014-3-49
Work Type GRADING, STRUCTURES, DRAINAGE, & PVMT
 
1.856 12967453.42 709064.62 4499552.68 34.6
Work Order 11-14-13
Work Began 07-20-15
Work Completed  
Time Computed 08-11-14
Contract Working Days 412
Addl Days Granted 1
Working Days Charged 218
Percent Time Used 52
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1014-03-049
W.O.E. CONSTRUCTION(0.30%)
TEX OP CONSTRUCTION, LP(2.01%)
TEXAS INLETS, INC. (3.62%)
SYNERGY SIGNS & SERVICES, LLC(0.37%)
HAYWARD BAKER, INC.(0.81%)
STRIPING TECHNOLOGY, L.P.(0.99%)
USA SWPPP INSPECTIONS, INC.(1.23%)
PREMIER PAVING, LTD. (4.86%)
DURABLE SPECIALTIES, INC.(3.25%)
BREDA COMPANY, INC.(0.67%)
BUYERS BARRICADES, INC.(0.31%)
BRENDA PRICE TRUCKING(4.98%)
FANNIN TREE FARM, LTD(0.33%)
Contract # 08133209
Totals 12967453.42 709064.62 4499552.68 34.6

CountyROCKWALL
Highway FM 3549
From SH 66
To FM 552
CSJ 1015-01-022
Proj ID STP 2015(590)
Work Type BASE REPAIR, LEVEL UP, OVERLAY
 
2.319 2576274.62 7164.36 2973960.14 99.9
Work Order 03-30-15
Work Began 08-05-15
Work Completed  
Time Computed 04-15-15
Contract Working Days 165
Addl Days Granted 31
Working Days Charged 195
Percent Time Used 99
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 1015-01-022
PEACHTREE CONSTRUCTION, LTD. ( 14.69%)
K & S UTILITY CONTRACTORS, INC.(9.85%)
ALTUS TRAFFIC MANAGEMENT LLC (0.36%)
USA SWPPP INSPECTIONS, INC.(2.61%)
STRIPING TECHNOLOGY, L.P.(1.47%)
BAHENA CONSTRUCTION CO.,INC. (0.28%)
RAMBO CONTRACTING, INC.(2.41%)
Contract # 02153221
Totals 2576274.62 7164.36 2973960.14 99.9

CountyROCKWALL
Highway FM 551
From NORTH OF IH 30
To SH 66
CSJ 1016-01-027
Proj ID STP 2014(766)
Work Type BASE REPAIR, LEVEL UP, OVERLAY
 
2.479 5349450.72 62132.70 5124650.64 95.7
Work Order 08-07-14
Work Began 06-15-15
Work Completed  
Time Computed 02-03-15
Contract Working Days 126
Addl Days Granted 94
Working Days Charged 220
Percent Time Used 100
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1016-01-027
DUSTROL, INC.(4.85%)
PREMIER PAVING, LTD. ( 12.35%)
USA SWPPP INSPECTIONS, INC.(1.91%)
FORTSON CONTRACTING, INC.(1.26%)
STRIPING TECHNOLOGY, L.P.(0.71%)
HAYWOOD BAKER(1.24%)
SYNERGY SIGNS & SERVICES, LLC(0.86%)
BRENDA PRICE TRUCKING(1.08%)
FANNIN TREE FARM, LTD(0.13%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.42%)
NE-TEX CONSTRUCTION, LTD.(2.81%)
Contract # 06143232
Totals 5349450.72 62132.70 5124650.64 95.7

CountyROCKWALL
Highway FM 1138
From SH 66
To COLLIN COUNTY LINE
CSJ 1016-03-013
Proj ID STP 1602(216)
Work Type BASE REPAIR, LEVEL UP, OVERLAY
 
1.065 1329420.20 358343.85 721030.52 54.2
CountyROCKWALL
Highway FM 35
From IH 30
To HUNT COUNTY LINE
CSJ 1017-02-012
Proj ID STP 1602(216)
Work Type MILL, BS REP, OV
 
1.539 627099.96 0.00 422924.27 67.4
Work Order 07-01-16
Work Began 08-04-16
Work Completed  
Time Computed 08-04-16
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 85
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1016-03-013
ALL AMERICAN MILLING, LLC(6.17%)
FLEX SUPPLY, LLC (0.40%)
JM YANEZ CONSTRUCTION, INC.(9.90%)
SYNERGY SIGNS & SERVICES, LLC(1.36%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (7.47%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.04%)
Contract # 05163033
Totals 1956520.16 358343.85 1143954.79 58.4

CountyELLIS
Highway FM 85
From IH 45
To FM 1182
CSJ 1050-01-017
Proj ID STP 2016(146)
Work Type ACP OVERLAY, GR, STR, PVMT MKGS
 
8.401 12874396.21 438439.52 3940465.69 30.6
Work Order 12-21-15
Work Began 03-14-16
Work Completed  
Time Computed 03-14-16
Contract Working Days 490
Addl Days Granted 5
Working Days Charged 160
Percent Time Used 32
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1050-01-017
FARR FOUNDATION, INC.(0.78%)
LONE STAR BARRIER SERVICES, LLC(0.82%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.18%)
SHALOM SERVICES CORPORATION(1.22%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.24%)
WOLFE CONSTRUCTION GROUP, INC. (0.30%)
STRIPING TECHNOLOGY, L.P.(0.81%)
PROJECT 2015, LLC(3.53%)
UNDER CONSTRUCTION INC.(0.00%)
GLL CORPORATION DBA MG TRUCKING(0.01%)
NIXON ENGINEERING(0.00%)
Contract # 10153212
Totals 12874396.21 438439.52 3940465.69 30.6

CountyELLIS
Highway FM 664
From NORTH OF US 287
To SOUTH OF RED OAK CREEK IN OVILLA
CSJ 1051-01-042
Proj ID STP 2015(654)
Work Type ADD 3 - FOOT PAVED SHOULDERS
 
7.303 11142221.20 1505505.20 9270338.78 83.5
Work Order 04-20-15
Work Began 06-22-15
Work Completed  
Time Computed 12-23-15
Contract Working Days 293
Addl Days Granted 29
Working Days Charged 355
Percent Time Used 110
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1051-01-042
BROCK ENVIRONMENTAL SERVICES, LLC(0.31%)
CROSSROADS, L.P. (0.48%)
DUSTROL, INC.(1.95%)
STRIPING TECHNOLOGY, L.P.(0.63%)
PEACHTREE CONSTRUCTION, LTD. ( 33.79%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.89%)
JE CASEY, LLC(1.56%)
SYNERGY SIGNS & SERVICES (0.72%)
OSCAR ORDUNO, INC. (2.36%)
BRENDA PRICE TRUCKING(1.09%)
AAA DRILLING FOUNDATION CO., INC.(0.32%)
FORTSON CONTRACTING, INC.(0.58%)
LONE STAR BARRIER SERVICES, LLC(0.53%)
TEXOP CONSTRUCTION (0.08%)
APAC-TEXAS, INC. (2.25%)
Contract # 03153213
Totals 11142221.20 1505505.20 9270338.78 83.5

CountyELLIS
Highway FM 876
From AT BIG ONION CREEK
To .
CSJ 1051-02-017
Proj ID BR 2015(591)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.255 1721378.55 180672.98 1609581.54 93.5
Work Order 04-03-15
Work Began 09-15-15
Work Completed  
Time Computed 09-15-15
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 287
Percent Time Used 79
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1051-02-017
N-LINE TRAFFIC MAINTENANCE, L.P. (0.93%)
IOWA BRIDGE & CULVERT, LC(3.59%)
STRIPING TECHNOLOGY, L.P.(1.60%)
GJ SEEDING, LLC(5.27%)
FOUNDATION DRILLERS, INC.(3.17%)
FRAIRE"S REBAR, INC(4.42%)
F & K BUILDERS (2.81%)
PEACHTREE CONSTRUCTION, LTD. (6.81%)
CLEMONS TRUCKING (2.17%)
JANEK & WHITTEN CONSTRUCTION INC.(0.43%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(5.70%)
FORTSON CONTRACTING, INC.(1.45%)
DUSTROL, INC.(0.26%)
Contract # 02153207
Totals 1721378.55 180672.98 1609581.54 93.5

CountyTARRANT
Highway IH 30
From 0.5 MILES WEST OF N. FIELDER ROAD
To DALLAS/TARRANT COUNTY LINE
CSJ 1068-02-135
Proj ID C 1068-2-135
Work Type ITS, ETC, SIGNS
 
6.091 6960302.24 32855.31 6695503.00 96.1
CountyDALLAS
Highway IH 30
From TARRANT/DALLAS COUNTY LINE
To SYLVAN AVE.
CSJ 1068-04-147
Proj ID IM 0305(082)
Work Type STR, GR, PVMT, PVMT MKGS, SIGNS, ITS
 
12.664 56121468.07 135880.51 58272228.32 99.9
Work Order 02-28-13
Work Began 03-25-13
Work Completed  
Time Computed 03-16-13
Contract Working Days 728
Addl Days Granted 84
Working Days Charged 960
Percent Time Used 118
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-147
COWTOWN TRAFFIC CONTROL, INC.(0.04%)
THE ANCHOR GROUP, INC. (0.02%)
ANTIGO CONSTRUCTION, INC.(0.02%)
DUSTROL, INC.(0.33%)
DUSTIN ALLEN, INC. (0.41%)
HOUSTON SAWING & DRILLING(0.02%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.09%)
PENHALL COMPANY(0.06%)
STORM WATER MANAGEMENT, INC. (0.13%)
VSTRUCTURAL LLC(0.42%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.12%)
W.O.E. CONSTRUCTION(0.64%)
STRIPING TECHNOLOGY, L.P.(2.08%)
MICA CORPORATION ( 19.67%)
W. W. FOUNDATION DRILLING, LTD.(2.65%)
K & S UTILITY CONTRACTORS, INC.(4.66%)
INDUS CONSTRUCTION, L.P. (0.56%)
PRESSURE CLEANING SERVICE, INC. DBA WATERBLASTING.COM(0.06%)
RAMBO CONTRACTING, INC.(1.19%)
NORTH TEXAS REBAR, LLC (0.00%)
HERDEZ TRUCKING, INC.(0.09%)
J.H. PAINTING COMPANY(0.41%)
MCL CONTRACTING, LLC (0.09%)
CB SERVICES, INC.(0.06%)
VFC, INC (0.11%)
STRIPE-A-ZONE, INC.(1.00%)
DALLAS LITE AND BARRICADE INC. (0.00%)
DBI SERVICES, LLC(0.02%)
Contract # 12123201
Totals 63081770.31 168735.82 64967731.32 99.9

CountyDALLAS
Highway IH 30
From BELTLINE ROAD
To MAC ARTHUR BLVD.
CSJ 1068-04-122
Proj ID C 1068-4-122
Work Type GR, STRS & PAV
 
1.522 24620668.27 1448614.97 4534778.98 18.4
CountyDALLAS
Highway IH 30
From BELT LINE RD
To MACARTHUR RD
CSJ 1068-04-137
Proj ID ROW 1068-4-137
Work Type ROW ACQ, UTIL & RELOC
 
0.760 565255.00 254836.00 336346.00 59.5
Work Order 02-16-16
Work Began 07-25-16
Work Completed  
Time Computed 06-15-16
Contract Working Days 538
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 15
Contractor(s)
HAYDON CENTRAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-122
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(2.91%)
LAYFIELD CONSTRUCTION, INC (0.24%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.38%)
FORTSON CONTRACTING, INC.(0.19%)
SOUTH TEXAS PAINTING COMPANY (0.01%)
ROBERTS TRUCKING (0.07%)
W.O.E. CONSTRUCTION(0.20%)
ANCORTEX, INC. ( 10.39%)
T-BAR FENCE, INC.(0.11%)
INTEGRATED ROADWAY SERVICES, INC.(3.09%)
TOMMY ELECTRIC, LLC(0.15%)
THELIN RECYCLING COMPANY, L.P. (0.13%)
BOWMAN ENGINEERING & CONSULTING, INC (9.83%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.04%)
FLASHFILL SERVICES, LLC(0.96%)
Contract # 12153004
Totals 25185923.27 1703450.97 4871124.98 19.3

CountyDALLAS
Highway IH 30
From NW 7TH STREET
To BELTLINE ROAD
CSJ 1068-04-148
Proj ID STP 2016(740)MM
Work Type GR, DRN, RET WLS, CONC PAV, SIG, PV MRKS
 
1.011 7991673.30 231459.63 1481428.63 18.5
Work Order 04-01-16
Work Began 05-18-16
Work Completed  
Time Computed 05-18-16
Contract Working Days 380
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 15
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-148
ALTUS TRAFFIC MANAGEMENT LLC (0.17%)
W.O.E. CONSTRUCTION(2.42%)
C.T. AND S. METALWORKS, INC. (0.37%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.22%)
FORTSON CONTRACTING, INC.(0.31%)
K & S UTILITY CONTRACTORS, INC.( 12.19%)
MICA CORPORATION (3.52%)
STORM WATER MANAGEMENT, INC. (0.23%)
STRIPE-A-ZONE, INC.(1.02%)
SYNERGY SIGNS & SERVICES (0.36%)
TEXAS BOMANITE (0.05%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.32%)
TEXAS SHAFTS, INC. (0.67%)
BOWMAN ENGINEERING & CONSTRUCTION, INC.(1.25%)
SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.01%)
Contract # 02163225
Totals 7991673.30 231459.63 1481428.63 18.5

CountyDALLAS
Highway IH 30
From COCKRELL HILL ROAD
To WESTMORELAND RD IN DALLAS
CSJ 1068-04-154
Proj ID C 1068-4-154
Work Type GRADING, PAVEMENT, SIGNS, PVMT MKGS
 
2.704 9814841.51 198089.44 8920344.90 93.0
Work Order 09-09-14
Work Began 11-11-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 321
Addl Days Granted 5
Working Days Charged 514
Percent Time Used 157
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-154
K & S UTILITY CONTRACTORS, INC.(9.08%)
OSCAR ORDUNO, INC. (4.26%)
STORM WATER MANAGEMENT, INC. (0.29%)
SLATON BROTHERS, INC.(4.57%)
W.O.E. CONSTRUCTION(7.63%)
MICA CORPORATION (1.31%)
DURABLE SPECIALTIES, INC.(1.31%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.44%)
J.H. PAINTING COMPANY(0.16%)
DCCS, LLC(0.11%)
DUSTIN ALLEN, INC. (0.49%)
Contract # 07143214
Totals 9814841.51 198089.44 8920344.90 93.0

CountyKAUFMAN
Highway FM 741
From US 175
To EAST OF FM 548
CSJ 1092-01-017
Proj ID STP 2015(778)
Work Type GR, BASE, ACP OVERLAY, PVMT MKGS
 
7.726 4550316.19 0.00 4535863.70 99.9
Work Order 03-23-15
Work Began 06-03-15
Work Completed  
Time Computed 04-23-15
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 277
Percent Time Used 148
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1092-01-017
ALTUS TRAFFIC MANAGEMENT LLC (0.26%)
TEXAS ENVIRONMENTAL MANAGEMENT SA, INC.(4.68%)
DUSTROL, INC.(4.57%)
MARCOM"S MOWING SERVICE, LLC (1.16%)
J & M CONTRACTING, COMPANY (7.65%)
STRIPING TECHNOLOGY, L.P.(1.43%)
FORTSON CONTRACTING, INC.(0.60%)
C & J TREE SERVICE (0.03%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.68%)
Contract # 02153235
Totals 4550316.19 0.00 4535863.70 99.9

CountyELLIS
Highway FM 875
From AT WAXAHACHIE CREEK
To .
CSJ 1159-01-022
Proj ID BR 2013(604)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.471 3724841.00 0.00 26660.86 0.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-15
Work Began 00-00-00
Work Completed  
Time Computed 12-11-15
Contract Working Days 467
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1159-01-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153025
Totals 3724841.00 0.00 26660.86 0.7

CountyELLIS
Highway FM 879
From 2.1 MILES WEST OF IKE RD
To 0.3 MILE WEST OF FM 1722
CSJ 1159-02-032
Proj ID STP 1502(328)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
6.667 9549753.04 733007.38 6503832.46 68.1
Work Order 07-31-15
Work Began 09-03-15
Work Completed  
Time Computed 07-31-15
Contract Working Days 315
Addl Days Granted 12
Working Days Charged 319
Percent Time Used 97
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1159-02-032
CROSS ROADS, L.P.(0.38%)
BROCK ENVIRONMENTAL SERVICES, LLC(0.19%)
ACU CONSTRUCTION LLC (1.24%)
STRIPING TECHNOLOGY, L.P.(0.61%)
SYNERGY SIGNS & SERVICES (0.28%)
FORTSON CONTRACTING, INC.(1.62%)
NORTH EASTERN PAVERS (4.90%)
PEACHTREE CONSTRUCTION, LTD. ( 13.21%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.95%)
HAYWARD BAKER, INC.(0.67%)
BRENDA PRICE TRUCKING(6.89%)
DFW MATERIALS LP (2.63%)
Contract # 06153225
Totals 9549753.04 733007.38 6503832.46 68.1

CountyELLIS
Highway FM 984
From AT DRAW, 1.7 MI SOUTH OF SH 34
To .
CSJ 1211-01-018
Proj ID BR 2015(483)
Work Type REPL BR AND APPR
 
0.117 879623.40 628.12 313182.35 35.6
CountyELLIS
Highway FM 984
From AT ONION CREEK RELIEF #1 AND #2
To .
CSJ 1211-01-019
Proj ID BR 2015(484)
Work Type REPL BR
 
0.156 1453823.50 67949.88 556796.66 38.2
Work Order 03-02-15
Work Began 02-25-16
Work Completed  
Time Computed 02-25-16
Contract Working Days 379
Addl Days Granted 0
Working Days Charged 175
Percent Time Used 46
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 1211-01-018
FORTSON CONTRACTING, INC.(2.16%)
USA EROSION, INC.(3.94%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.48%)
STRIPING TECHNOLOGY, L.P.(1.23%)
TEX OP CONSTRUCTION, LP(1.11%)
W. W. FOUNDATION DRILLING, LTD.(5.36%)
DFW REBAR, INC.(0.68%)
Contract # 01153012
Totals 2333446.90 68578.00 869979.01 37.2

CountyKAUFMAN
Highway FM 1388
From FM 148
To US 175
CSJ 1217-03-019
Proj ID STP 2016(360)
Work Type GR, BASE, ACP OVERLAY, PVMT MKGS
 
12.030 17608683.44 1097689.39 5027238.88 28.5
CountyKAUFMAN
Highway FM 1388
From AT KINGS CREEK RELIEF #2
To .
CSJ 1217-03-020
Proj ID BR 2016(361)
Work Type REPLACE BRIDGE
 
0.495 4432389.14 97783.03 1046089.32 23.6
Work Order 01-29-16
Work Began 04-11-16
Work Completed  
Time Computed 04-11-16
Contract Working Days 580
Addl Days Granted 0
Working Days Charged 159
Percent Time Used 27
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1217-03-019
ALTUS TRAFFIC MANAGEMENT LLC (0.13%)
SOUTHWEST CONSTRUCTION SERVICES(0.39%)
K & S UTILITY CONTRACTORS, INC.(9.31%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.05%)
PEACHTREE CONSTRUCTION, LTD. (4.40%)
SOUTHERN CROSS CONTRACTORS, LLC(0.08%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(5.40%)
SYNERGY SIGNS & SERVICES, LLC(0.39%)
FARR FOUNDATION, INC.(0.56%)
FORTSON CONTRACTING, INC.(0.74%)
TRP CONSTRUCTION GROUP, LLC(0.60%)
HERDEZ TRUCKING, INC.(2.17%)
RAMBO CONTRACTING, INC.(4.73%)
TEXOP CONSTRUCTION (0.07%)
EJ SMITH CONSTRUCTION COMPANY, LLC (7.55%)
BEAIRD DRILLING(0.35%)
W.O.E. CONSTRUCTION(1.62%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.36%)
Contract # 12153205
Totals 22041072.58 1195472.42 6073328.20 27.5

CountyNAVARRO
Highway FM 1126
From AT CHAMBERS CREEK, SW OF IH 45
To .
CSJ 1289-01-029
Proj ID BR 1602(046)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.890 6714487.74 1105466.54 1693479.68 25.2
Work Order 06-02-16
Work Began 08-09-16
Work Completed  
Time Computed 07-05-16
Contract Working Days 386
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 14
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1289-01-029
A. L. HELMCAMP, INC. ( 22.43%)
IOWA BRIDGE & CULVERT, LC(1.25%)
AARON CONCRETE CONTRACTORS, L.P. (3.51%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.82%)
FORTSON CONTRACTING, INC.(0.29%)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(0.29%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.26%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.42%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.37%)
MCL CONTRACTING, LLC (0.26%)
Contract # 04163237
Totals 6714487.74 1105466.54 1693479.68 25.2

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8