|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | COLLIN |
| Highway |
SH 289 |
| From |
FM 455 |
| To |
N BUS 289C, NORTH OF CELINA |
| CSJ |
0091-03-021 |
| Proj ID |
C 91-3-21 |
| Work Type |
GRD, STR, PVMT, SIGNS |
| |
|
3.448 |
15996401.11 |
5500.00 |
1024740.00 |
6.4 |
| Work Order |
08-22-12 |
| Work Began |
02-14-13 |
| Work Completed |
|
| Time Computed |
02-14-13 |
| Contract Working Days |
520 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| MARIO SINACOLA & SONS EXCAVATING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0091-03-021 ALLIANCE GEOTECHNICAL GROUP(0.21%) ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.11%) SOUTHWEST ENVIRONMENT SERVICES LLC (0.14%) FORTSON CONTRACTING, INC.(0.10%) HIGHWAY TECHNOLOGIES, INC. (0.93%) INDUS CONSTRUCTION, L.P. (0.90%) JAGOE-PUBLIC COMPANY ( 13.49%) ENVIRONMENTAL SAFETY SERVICES, INC.(0.97%) LONE STAR BARRIER SERVICES, LLC(0.24%) LONE STAR MANHOLE & STRUCTURES, LLC(4.63%) TEX OP CONSTRUCTION, LP(0.74%) MIKE ALBERT, INC.(1.33%) W.O.E. CONSTRUCTION(0.29%) EROSION CONTROL MANAGEMENT SERVICES(0.47%)
|
| Contract # |
06123003 |
|
Totals |
15996401.11 |
5500.00 |
1024740.00 |
6.4 |
|
| County | COLLIN |
| Highway |
SH 289 |
| From |
NORTH BUS 289-C |
| To |
GRAYSON COUNTY LINE |
| CSJ |
0091-03-024 |
| Proj ID |
STP 2013(566) |
| Work Type |
BS REP, UNDERSEAL, OV |
| |
|
2.348 |
771988.36 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
40 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| AUSTIN BRIDGE & ROAD, LP |
SUBCONTRACTOR(S) FOR CCSJ: 0091-03-024 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03133032 |
|
Totals |
771988.36 |
0.00 |
0.00 |
0.0 |
|
| County | COLLIN |
| Highway |
SH 289 |
| From |
US 380 INTERCHANGE |
| To |
NORTH OF FM 1461 / BS 289D |
| CSJ |
0091-04-050 |
| Proj ID |
C 91-4-50 |
| Work Type |
GRD, STR, PVMT, SIGNS, RAMPS |
| |
|
3.144 |
17270901.44 |
41641.43 |
8774203.19 |
50.8 |
| Work Order |
10-13-11 |
| Work Began |
03-23-12 |
| Work Completed |
|
| Time Computed |
03-23-12 |
| Contract Working Days |
619 |
| Addl Days Granted |
0 |
| Working Days Charged |
328 |
| Percent Time Used |
52 |
| Contractor(s) |
| MARIO SINACOLA & SONS EXCAVATING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0091-04-050 ALLIANCE GEOTECHNICAL GROUP(0.20%) ARLINGTON PAVERS, INC. (0.03%) CONCRETE CUTTING BY BOND (0.36%) DUSTROL, INC.(0.64%) HIGHWAY TECHNOLOGIES, INC. (1.44%) INDUS CONSTRUCTION, L.P. (1.13%) MIKE ALBERT, INC.(1.20%) REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 14.69%) ROADWAY SOLUTIONS, INC.(4.41%) TEXAS INLETS, INC. (4.43%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.10%) STORM WATER MANAGEMENT, INC. (0.45%) SKAGGS ROAD BORING INC.(0.12%) SYNERGY SIGNS & SERVICES, LLC(0.15%) ANCHOR FENCE GROUP, LLC(0.08%)
|
| Contract # |
07113202 |
|
Totals |
17270901.44 |
41641.43 |
8774203.19 |
50.8 |
|
| County | COLLIN |
| Highway |
SH 289 |
| From |
NORTH OF FM 1461 / BS 289D |
| To |
FM 455 IN CELINA |
| CSJ |
0091-04-055 |
| Proj ID |
C 91-4-55 |
| Work Type |
GR, STR, PVMT, SIGNS, PVMT MKGS |
| |
|
4.090 |
18214018.09 |
123300.85 |
5004253.91 |
27.4 |
| Work Order |
10-18-11 |
| Work Began |
06-22-12 |
| Work Completed |
|
| Time Computed |
04-15-12 |
| Contract Working Days |
519 |
| Addl Days Granted |
0 |
| Working Days Charged |
307 |
| Percent Time Used |
59 |
| Contractor(s) |
| MARIO SINACOLA & SONS EXCAVATING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0091-04-055 ALLIANCE GEOTECHNICAL GROUP(0.18%) ARLINGTON PAVERS, INC. (0.02%) CONCRETE CUTTING BY BOND (0.32%) DUSTROL, INC.(0.73%) FORTSON CONTRACTING, INC.(0.15%) HIGHWAY TECHNOLOGIES, INC. (0.88%) INDUS CONSTRUCTION, L.P. (0.90%) LONE STAR MANHOLE & STRUCTURES, LLC(6.25%) REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 15.14%) STORM WATER MANAGEMENT, INC. (0.29%) ROADWAY SOLUTIONS, INC.(1.97%) FARR FOUNDATION, INC.(0.02%) ENVIRONMENTAL SAFETY SERVICES, INC.(0.73%)
|
| Contract # |
07113203 |
|
Totals |
18214018.09 |
123300.85 |
5004253.91 |
27.4 |
|
| County | DALLAS |
| Highway |
SH 289 |
| From |
ON SH 289 (PRESTON) |
| To |
AT ROYAL |
| CSJ |
0091-06-049 |
| Proj ID |
STP 2013(727)MM |
| Work Type |
INTERSECTION IMPROVEMENT |
| |
|
0.166 |
674540.86 |
0.00 |
0.00 |
0.0 |
| County | DALLAS |
| Highway |
SH 289 |
| From |
ON SH 289 |
| To |
AT ROYAL LANE |
| CSJ |
0091-06-055 |
| Proj ID |
STP 2012(375)MM |
| Work Type |
ROW ACQ & UTIL ADJ |
| |
|
0.010 |
44707.50 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
118 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| REBCON, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0091-06-049 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05133228 |
|
Totals |
719248.36 |
0.00 |
0.00 |
0.0 |
|
| County | ELLIS |
| Highway |
IH 45 |
| From |
SH 34 |
| To |
FM 879 |
| CSJ |
0092-04-070 |
| Proj ID |
IM 0453(132) |
| Work Type |
INSTALL GUIDE SIGNS |
| |
|
17.893 |
376016.55 |
0.00 |
0.00 |
0.0 |
| County | ELLIS |
| Highway |
IH 45 |
| From |
FM 1182 |
| To |
FM 1181 |
| CSJ |
0092-05-049 |
| Proj ID |
STP 2013(530)MM |
| Work Type |
TRUCK LANE RESTRICTIONS |
| |
|
6.780 |
63617.45 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
96 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| SIEMENS INDUSTRY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0092-05-049 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04133011 |
|
Totals |
439634.00 |
0.00 |
0.00 |
0.0 |
|
| County | DALLAS |
| Highway |
IH 45 |
| From |
LOOP 12 |
| To |
IH 30 |
| CSJ |
0092-14-079 |
| Proj ID |
IM 0453(131) |
| Work Type |
ITS |
| |
|
7.889 |
496968.00 |
9353.45 |
469184.35 |
95.2 |
| Work Order |
05-15-12 |
| Work Began |
08-09-12 |
| Work Completed |
|
| Time Computed |
08-09-12 |
| Contract Working Days |
60 |
| Addl Days Granted |
0 |
| Working Days Charged |
67 |
| Percent Time Used |
111 |
| Contractor(s) |
| SIEMENS INDUSTRY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0092-14-079 DOWN UNDER CONSTRUCTION(0.86%) INTEGRATED ROADWAY SERVICES, INC.( 16.70%) TCB FOUNDATION DRILLERS, INC.(1.15%)
|
| Contract # |
04123010 |
|
Totals |
496968.00 |
9353.45 |
469184.35 |
95.2 |
|
| County | DALLAS |
| Highway |
SH 183 |
| From |
E. ABUTMENT OF TRINITY RIVER BRIDGE |
| To |
IH 35E |
| CSJ |
0094-07-041 |
| Proj ID |
NH 2013(651) |
| Work Type |
MILL, INLAY, FDRCP, PAV MRKS |
| |
|
1.535 |
2164097.25 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
86 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| AUSTIN BRIDGE & ROAD, LP |
SUBCONTRACTOR(S) FOR CCSJ: 0094-07-041 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04133030 |
|
Totals |
2164097.25 |
0.00 |
0.00 |
0.0 |
|
| County | DALLAS |
| Highway |
US 80 |
| From |
AT SH 352 (COLLINS RD) SUNNYVALE |
| To |
. |
| CSJ |
0095-02-100 |
| Proj ID |
STP 2009(022)MM |
| Work Type |
RECONSTRUCT, GRADING, BASE, PAVING |
| |
|
0.812 |
24968164.67 |
0.00 |
24381818.03 |
99.9 |
| Work Order |
01-05-09 |
| Work Began |
01-21-09 |
| Work Completed |
|
| Time Computed |
01-21-09 |
| Contract Working Days |
560 |
| Addl Days Granted |
35 |
| Working Days Charged |
900 |
| Percent Time Used |
151 |
| Contractor(s) |
| W.W. WEBBER, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0095-02-100 CRAIG OLDEN, INC.(4.95%) USA EROSION, INC.(0.26%) FORTSON CONTRACTING, INC.(0.16%) NORTH TEXAS BOMANITE, INC. (0.94%) PREMIER PAVING, LTD. ( 18.93%) RIVER CITIES SAWING LLC(0.06%) TEXAS SHAFTS, INC. (1.20%) HIGHWAY TECHNOLOGIES, INC. (0.55%) ROADWAY SOLUTIONS, INC.(1.75%) BREDA COMPANY, INC.(0.39%) SCOTT DERR PAINTING CO (0.39%) RAMBO CONTRACTING, INC.(0.34%) BEAR CREEK CONSTRUCTION, LLC (0.23%) FARR FOUNDATION, INC.(0.18%) STAR OPERATIONS, INC.(0.17%)
|
| Contract # |
10083201 |
|
Totals |
24968164.67 |
0.00 |
24381818.03 |
99.9 |
|
| County | DALLAS |
| Highway |
US 80 |
| From |
CULVERT 0.3 MI E OF E FORK RD |
| To |
. |
| CSJ |
0095-02-109 |
| Proj ID |
NH 2013(381) |
| Work Type |
REPAIR SLOPE WITH HEADWALL |
| |
|
0.024 |
256468.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-10-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
50 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| WEST GENERAL CONTRACTORS CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 0095-02-109 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02133218 |
|
Totals |
256468.00 |
0.00 |
0.00 |
0.0 |
|
| County | KAUFMAN |
| Highway |
US 80 |
| From |
AT FM 740 SOUTH |
| To |
IN FORNEY |
| CSJ |
0095-03-086 |
| Proj ID |
NH 2013(382) |
| Work Type |
REHABILITATION OF TRAFFIC SIGNALS |
| |
|
0.002 |
247839.23 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-03-13 |
| Work Began |
05-06-13 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
60 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ROADWAY SOLUTIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0095-03-086 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02133021 |
|
Totals |
247839.23 |
0.00 |
0.00 |
0.0 |
|
| County | KAUFMAN |
| Highway |
US 80 |
| From |
AT PROPOSED FORNEY PARKWAY |
| To |
. |
| CSJ |
0095-04-064 |
| Proj ID |
C 95-4-64 |
| Work Type |
GR, STR, DRAINAGE, PVMT, SIGNS |
| |
|
1.030 |
17050215.03 |
107963.84 |
13115532.61 |
76.9 |
| Work Order |
03-06-12 |
| Work Began |
04-09-12 |
| Work Completed |
|
| Time Computed |
03-22-12 |
| Contract Working Days |
473 |
| Addl Days Granted |
0 |
| Working Days Charged |
311 |
| Percent Time Used |
65 |
| Contractor(s) |
| HAYDON BUILDING CORP. |
SUBCONTRACTOR(S) FOR CCSJ: 0095-04-064 BEAIRD DRILLING(2.99%) BUYERS BARRICADES, INC.(0.19%) DUSTROL, INC.(0.14%) FORTSON CONTRACTING, INC.(0.57%) PEACHTREE CONSTRUCTION, LTD. (3.69%) STAR OPERATIONS, INC.(1.93%) STORM WATER MANAGEMENT, INC. (0.08%) TOTAL HIGHWAY MAINTENANCE, LLC (0.32%) SOUTH TEXAS PAINTING COMPANY (1.00%) CONCRETE CUTTING BY BOND (0.07%) USA SWPPP INSPECTIONS, INC.(0.64%) W. W. FOUNDATION DRILLING, LTD.(2.82%) J.L. STEEL REINFORCING, LLC(1.20%) PETERSON CONTRACTORS, INC. (0.00%) COWBOY TRUCKING(0.00%)
|
| Contract # |
01123202 |
|
Totals |
17050215.03 |
107963.84 |
13115532.61 |
76.9 |
|
| County | KAUFMAN |
| Highway |
US 80 |
| From |
AT NINTH ST AND SP 87 (DELLIS ST) |
| To |
IN TERRELL |
| CSJ |
0095-05-056 |
| Proj ID |
STP 2013(728) |
| Work Type |
REHABILITATION OF TRAFFIC SIGNALS |
| |
|
1.462 |
184862.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
60 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| SIEMENS INDUSTRY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0095-05-056 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05133225 |
|
Totals |
184862.00 |
0.00 |
0.00 |
0.0 |
|
| County | DALLAS |
| Highway |
IH 20 |
| From |
I.H. 635 |
| To |
SEAGOVILLE ROAD. |
| CSJ |
0095-13-025 |
| Proj ID |
IM 0205(146) |
| Work Type |
GRADING, PAVING, SIGNING, LANDSCAPING |
| |
|
0.841 |
4972861.19 |
536338.96 |
2658680.58 |
53.4 |
| Work Order |
06-21-12 |
| Work Began |
10-01-12 |
| Work Completed |
|
| Time Computed |
10-01-12 |
| Contract Working Days |
147 |
| Addl Days Granted |
0 |
| Working Days Charged |
141 |
| Percent Time Used |
95 |
| Contractor(s) |
| HAYDON BUILDING CORP. |
SUBCONTRACTOR(S) FOR CCSJ: 0095-13-025 NORTH TEXAS REBAR, LLC (0.68%) FORTSON CONTRACTING, INC.(1.00%) INTEGRATED ROADWAY SERVICES, INC.(1.49%) S & S PAINTING (0.25%) W.O.E. CONSTRUCTION(0.21%) AXIS CONTRACTING, INC. (8.00%) HOUSTON SAWING & DRILLING(0.05%) USA SWPPP INSPECTIONS, INC.(0.47%) DUSTROL, INC.(0.54%) DALLAS LITE AND BARRICADE INC. (0.28%) TOTAL HIGHWAY MAINTENANCE, LLC (1.23%) THELIN RECYCLING COMPANY, L.P. (0.24%) REYNOLDS ASPHALT & CONSTRUCTION COMPANY(9.28%) W. W. FOUNDATION DRILLING, LTD.(2.12%) THE ANCHOR GROUP, INC. (0.78%) NORTH TEXAS REBAR, LLC (0.09%) COWBOY TRUCKING(0.40%)
|
| Contract # |
05123247 |
|
Totals |
4972861.19 |
536338.96 |
2658680.58 |
53.4 |
|
| County | KAUFMAN |
| Highway |
IH 20 |
| From |
DALLAS/KAUFMAN COUNTY LINE |
| To |
0.21 MI WEST OF ROSEHILL ROAD |
| CSJ |
0095-14-016 |
| Proj ID |
IM 0205(127) |
| Work Type |
2" HMAC OVERLAY |
| |
|
13.189 |
3165908.57 |
205588.57 |
1875345.54 |
59.2 |
| Work Order |
11-16-11 |
| Work Began |
04-10-12 |
| Work Completed |
|
| Time Computed |
01-15-12 |
| Contract Working Days |
83 |
| Addl Days Granted |
89 |
| Working Days Charged |
119 |
| Percent Time Used |
69 |
| Contractor(s) |
| AUSTIN BRIDGE & ROAD, LP |
SUBCONTRACTOR(S) FOR CCSJ: 0095-14-016 BUYERS BARRICADES, INC.(0.27%) DUSTROL, INC.(1.34%) HIGHWAY TECHNOLOGIES, INC. (5.17%) W.O.E. CONSTRUCTION(1.62%) O. TREVINO CONSTRUCTION, LLC (2.27%) BRENDA PRICE TRUCKING(0.09%) TOTAL HIGHWAY MAINTENANCE, LLC (0.37%)
|
| Contract # |
10113014 |
|
Totals |
3165908.57 |
205588.57 |
1875345.54 |
59.2 |
|
| County | DENTON |
| Highway |
US 380 |
| From |
DENTON/WISE COUNTY LINE ROAD |
| To |
WEST OF FM 156 |
| CSJ |
0134-09-029 |
| Proj ID |
STP 2012(184)SB |
| Work Type |
GR, STR, DRAINAGE, BASE, PVMT, AND |
| |
|
7.860 |
26379472.05 |
1052813.73 |
10142991.72 |
38.4 |
| Work Order |
02-22-12 |
| Work Began |
05-14-12 |
| Work Completed |
|
| Time Computed |
05-14-12 |
| Contract Working Days |
588 |
| Addl Days Granted |
0 |
| Working Days Charged |
236 |
| Percent Time Used |
40 |
| Contractor(s) |
| JAGOE-PUBLIC COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0134-09-029 GLENN THURMAN, INC.( 14.17%) HIGHWAY TECHNOLOGIES, INC. (1.04%) BROCK ENVIRONMENTAL, LLC (0.65%) SOUTHWEST ENVIRONMENT SERVICES LLC (0.42%) CEN CONCRETE CONSTRUCTION COMPANY, INC.(2.02%) DUSTROL, INC.(0.64%) FORTSON CONTRACTING, INC.(0.87%) MIKE ALBERT, INC.(2.69%) MURRAY CONSTRUCTION(0.35%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.85%) IOWA BRIDGE & CULVERT, LC(0.33%) TEXAS SHAFTS, INC. (0.15%) MCL CONTRACTING, LLC (0.01%) LKT & ASSOCIATES (2.33%)
|
| Contract # |
12113201 |
|
Totals |
26379472.05 |
1052813.73 |
10142991.72 |
38.4 |
|
| County | DENTON |
| Highway |
US 380 |
| From |
WEST OF BONNIE BRAE ST |
| To |
US 377 |
| CSJ |
0134-09-034 |
| Proj ID |
STP 2013(181) |
| Work Type |
STRUCTURES, BASE, PAVEMENT |
| |
|
1.625 |
15088445.93 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-03-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
420 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| JAGOE-PUBLIC COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0134-09-034 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11123002 |
|
Totals |
15088445.93 |
0.00 |
0.00 |
0.0 |
|
| County | DENTON |
| Highway |
US 380 |
| From |
WEST OF FM 156 |
| To |
IH 35 |
| CSJ |
0134-09-063 |
| Proj ID |
NH 2012(635) |
| Work Type |
GR, STR, DRAINAGE, PVMT, C & G, SIGNS |
| |
|
4.702 |
39346679.90 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
03-12-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
755 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| TEXAS STERLING CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0134-09-063 BROCK ENVIRONMENTAL, LLC (0.23%) BUYERS BARRICADES, INC.(0.19%) FORTSON CONTRACTING, INC.(0.67%) THELIN RECYCLING COMPANY, L.P. (0.29%) CRAIG OLDEN, INC.(0.26%) JAGOE-PUBLIC COMPANY ( 13.71%) NORTH TEXAS BOMANITE, INC. (0.70%) TEXAS INLETS, INC. (2.35%) TEX OP CONSTRUCTION, LP(0.64%) TRAC-WORK, INC.(1.82%) WYLIE DRILLING & DRAINAGE, INC.(1.19%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.08%) CHOCTAW ERECTORS, INC. (0.76%) INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(1.04%) TOTAL HIGHWAY MAINTENANCE, LLC (0.94%) INLET STRUCTURE SPECIALTIES LTD. (0.96%) MCL CONTRACTING, LLC (1.02%)
|
| Contract # |
07123002 |
|
Totals |
39346679.90 |
0.00 |
0.00 |
0.0 |
|
| County | COLLIN |
| Highway |
US 380 |
| From |
EAST OF FM 2478 (CUSTER RD) |
| To |
EAST OF LAKE FOREST DRIVE |
| CSJ |
0135-02-045 |
| Proj ID |
C 135-2-45 |
| Work Type |
BASE, PVMT, SIGNS, MKGS |
| |
|
3.124 |
11650909.58 |
330486.94 |
10441714.95 |
89.6 |
| Work Order |
10-05-11 |
| Work Began |
01-03-12 |
| Work Completed |
|
| Time Computed |
01-03-12 |
| Contract Working Days |
315 |
| Addl Days Granted |
25 |
| Working Days Charged |
339 |
| Percent Time Used |
99 |
| Contractor(s) |
| JAGOE-PUBLIC COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0135-02-045 BROCK ENVIRONMENTAL, LLC (0.25%) DUSTROL, INC.(0.43%) FORTSON CONTRACTING, INC.(0.52%) HIGHWAY TECHNOLOGIES, INC. (1.15%) IOWA BRIDGE & CULVERT, LC( 10.95%) K & S UTILITY CONTRACTORS, INC.( 14.92%) MIKE ALBERT, INC.( 11.79%) ROADWAY SOLUTIONS, INC.(1.36%) SHILLING CONSTRUCTION COMPANY(1.60%) TOTAL HIGHWAY MAINTENANCE, LLC (0.35%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.25%) FOUNDATION DRILLERS, INC.(0.72%) CF SOUTHWEST ENVIRONMENT SERVICES LLC(0.06%) C.B. SERVICES, INC.(0.21%) WYLIE DRILLING & DRAINAGE, INC.(0.21%) SCOTT DERR PAINTING CO, LLC(0.23%) TEXAS BOMANITE (1.70%)
|
| Contract # |
07113269 |
|
Totals |
11650909.58 |
330486.94 |
10441714.95 |
89.6 |
|
| County | COLLIN |
| Highway |
US 380 |
| From |
EAST OF FLOYD RD |
| To |
CR 698 (HUNT COUNTY LINE) |
| CSJ |
0135-05-023 |
| Proj ID |
C 135-5-23 |
| Work Type |
GR, STRS, PAVT, CUL, CURB AND GTRS |
| |
|
3.172 |
16564930.23 |
755.23 |
16767248.30 |
99.9 |
| Work Order |
08-17-10 |
| Work Began |
04-11-11 |
| Work Completed |
|
| Time Computed |
02-13-11 |
| Contract Working Days |
394 |
| Addl Days Granted |
5 |
| Working Days Charged |
373 |
| Percent Time Used |
93 |
| Contractor(s) |
| TEXAS STERLING CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0135-05-023 CRAIG OLDEN, INC.(0.40%) DALLAS LITE AND BARRICADE INC. (0.16%) INLET STRUCTURE SPECIALTIES LTD. (1.44%) REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 13.58%) RIVER CITIES SAWING, LLC (0.46%) W.O.E. CONSTRUCTION(1.43%) S & V CONSTRUCTION LLC (1.47%) BEAIRD DRILLING(0.24%) TEX OP CONSTRUCTION, LP(0.42%) BREDA COMPANY, INC.(1.19%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.68%) TOTAL HIGHWAY MAINTENANCE, LLC (0.63%) FORTSON CONTRACTING, INC.(1.34%) TEXAS STAR TRANSPORT, LP (0.27%) E W WELLS GROUP LLC(0.34%) WYLIE DRILLING & DRAINAGE, INC.(0.14%) CONCRETE CUTTING BY BOND (0.21%) INTEGRATED ROADWAY SERVICES, INC.(0.25%)
|
| Contract # |
07103211 |
|
Totals |
16564930.23 |
755.23 |
16767248.30 |
99.9 |
|