Monthly State Let Construction Report For Dallas District As Of May 15, 2013 Page 2 Of 8

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCOLLIN
Highway SH 289
From FM 455
To N BUS 289C, NORTH OF CELINA
CSJ 0091-03-021
Proj ID C 91-3-21
Work Type GRD, STR, PVMT, SIGNS
 
3.448 15996401.11 5500.00 1024740.00 6.4
Work Order 08-22-12
Work Began 02-14-13
Work Completed  
Time Computed 02-14-13
Contract Working Days 520
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-03-021
ALLIANCE GEOTECHNICAL GROUP(0.21%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.11%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.14%)
FORTSON CONTRACTING, INC.(0.10%)
HIGHWAY TECHNOLOGIES, INC. (0.93%)
INDUS CONSTRUCTION, L.P. (0.90%)
JAGOE-PUBLIC COMPANY ( 13.49%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.97%)
LONE STAR BARRIER SERVICES, LLC(0.24%)
LONE STAR MANHOLE & STRUCTURES, LLC(4.63%)
TEX OP CONSTRUCTION, LP(0.74%)
MIKE ALBERT, INC.(1.33%)
W.O.E. CONSTRUCTION(0.29%)
EROSION CONTROL MANAGEMENT SERVICES(0.47%)
Contract # 06123003
Totals 15996401.11 5500.00 1024740.00 6.4

CountyCOLLIN
Highway SH 289
From NORTH BUS 289-C
To GRAYSON COUNTY LINE
CSJ 0091-03-024
Proj ID STP 2013(566)
Work Type BS REP, UNDERSEAL, OV
 
2.348 771988.36 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0091-03-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133032
Totals 771988.36 0.00 0.00 0.0

CountyCOLLIN
Highway SH 289
From US 380 INTERCHANGE
To NORTH OF FM 1461 / BS 289D
CSJ 0091-04-050
Proj ID C 91-4-50
Work Type GRD, STR, PVMT, SIGNS, RAMPS
 
3.144 17270901.44 41641.43 8774203.19 50.8
Work Order 10-13-11
Work Began 03-23-12
Work Completed  
Time Computed 03-23-12
Contract Working Days 619
Addl Days Granted 0
Working Days Charged 328
Percent Time Used 52
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-04-050
ALLIANCE GEOTECHNICAL GROUP(0.20%)
ARLINGTON PAVERS, INC. (0.03%)
CONCRETE CUTTING BY BOND (0.36%)
DUSTROL, INC.(0.64%)
HIGHWAY TECHNOLOGIES, INC. (1.44%)
INDUS CONSTRUCTION, L.P. (1.13%)
MIKE ALBERT, INC.(1.20%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 14.69%)
ROADWAY SOLUTIONS, INC.(4.41%)
TEXAS INLETS, INC. (4.43%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.10%)
STORM WATER MANAGEMENT, INC. (0.45%)
SKAGGS ROAD BORING INC.(0.12%)
SYNERGY SIGNS & SERVICES, LLC(0.15%)
ANCHOR FENCE GROUP, LLC(0.08%)
Contract # 07113202
Totals 17270901.44 41641.43 8774203.19 50.8

CountyCOLLIN
Highway SH 289
From NORTH OF FM 1461 / BS 289D
To FM 455 IN CELINA
CSJ 0091-04-055
Proj ID C 91-4-55
Work Type GR, STR, PVMT, SIGNS, PVMT MKGS
 
4.090 18214018.09 123300.85 5004253.91 27.4
Work Order 10-18-11
Work Began 06-22-12
Work Completed  
Time Computed 04-15-12
Contract Working Days 519
Addl Days Granted 0
Working Days Charged 307
Percent Time Used 59
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-04-055
ALLIANCE GEOTECHNICAL GROUP(0.18%)
ARLINGTON PAVERS, INC. (0.02%)
CONCRETE CUTTING BY BOND (0.32%)
DUSTROL, INC.(0.73%)
FORTSON CONTRACTING, INC.(0.15%)
HIGHWAY TECHNOLOGIES, INC. (0.88%)
INDUS CONSTRUCTION, L.P. (0.90%)
LONE STAR MANHOLE & STRUCTURES, LLC(6.25%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 15.14%)
STORM WATER MANAGEMENT, INC. (0.29%)
ROADWAY SOLUTIONS, INC.(1.97%)
FARR FOUNDATION, INC.(0.02%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.73%)
Contract # 07113203
Totals 18214018.09 123300.85 5004253.91 27.4

CountyDALLAS
Highway SH 289
From ON SH 289 (PRESTON)
To AT ROYAL
CSJ 0091-06-049
Proj ID STP 2013(727)MM
Work Type INTERSECTION IMPROVEMENT
 
0.166 674540.86 0.00 0.00 0.0
CountyDALLAS
Highway SH 289
From ON SH 289
To AT ROYAL LANE
CSJ 0091-06-055
Proj ID STP 2012(375)MM
Work Type ROW ACQ & UTIL ADJ
 
0.010 44707.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 118
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REBCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-06-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133228
Totals 719248.36 0.00 0.00 0.0

CountyELLIS
Highway IH 45
From SH 34
To FM 879
CSJ 0092-04-070
Proj ID IM 0453(132)
Work Type INSTALL GUIDE SIGNS
 
17.893 376016.55 0.00 0.00 0.0
CountyELLIS
Highway IH 45
From FM 1182
To FM 1181
CSJ 0092-05-049
Proj ID STP 2013(530)MM
Work Type TRUCK LANE RESTRICTIONS
 
6.780 63617.45 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 96
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0092-05-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133011
Totals 439634.00 0.00 0.00 0.0

CountyDALLAS
Highway IH 45
From LOOP 12
To IH 30
CSJ 0092-14-079
Proj ID IM 0453(131)
Work Type ITS
 
7.889 496968.00 9353.45 469184.35 95.2
Work Order 05-15-12
Work Began 08-09-12
Work Completed  
Time Computed 08-09-12
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 111
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0092-14-079
DOWN UNDER CONSTRUCTION(0.86%)
INTEGRATED ROADWAY SERVICES, INC.( 16.70%)
TCB FOUNDATION DRILLERS, INC.(1.15%)
Contract # 04123010
Totals 496968.00 9353.45 469184.35 95.2

CountyDALLAS
Highway SH 183
From E. ABUTMENT OF TRINITY RIVER BRIDGE
To IH 35E
CSJ 0094-07-041
Proj ID NH 2013(651)
Work Type MILL, INLAY, FDRCP, PAV MRKS
 
1.535 2164097.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0094-07-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133030
Totals 2164097.25 0.00 0.00 0.0

CountyDALLAS
Highway US 80
From AT SH 352 (COLLINS RD) SUNNYVALE
To .
CSJ 0095-02-100
Proj ID STP 2009(022)MM
Work Type RECONSTRUCT, GRADING, BASE, PAVING
 
0.812 24968164.67 0.00 24381818.03 99.9
Work Order 01-05-09
Work Began 01-21-09
Work Completed  
Time Computed 01-21-09
Contract Working Days 560
Addl Days Granted 35
Working Days Charged 900
Percent Time Used 151
Contractor(s)
W.W. WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0095-02-100
CRAIG OLDEN, INC.(4.95%)
USA EROSION, INC.(0.26%)
FORTSON CONTRACTING, INC.(0.16%)
NORTH TEXAS BOMANITE, INC. (0.94%)
PREMIER PAVING, LTD. ( 18.93%)
RIVER CITIES SAWING LLC(0.06%)
TEXAS SHAFTS, INC. (1.20%)
HIGHWAY TECHNOLOGIES, INC. (0.55%)
ROADWAY SOLUTIONS, INC.(1.75%)
BREDA COMPANY, INC.(0.39%)
SCOTT DERR PAINTING CO (0.39%)
RAMBO CONTRACTING, INC.(0.34%)
BEAR CREEK CONSTRUCTION, LLC (0.23%)
FARR FOUNDATION, INC.(0.18%)
STAR OPERATIONS, INC.(0.17%)
Contract # 10083201
Totals 24968164.67 0.00 24381818.03 99.9

CountyDALLAS
Highway US 80
From CULVERT 0.3 MI E OF E FORK RD
To .
CSJ 0095-02-109
Proj ID NH 2013(381)
Work Type REPAIR SLOPE WITH HEADWALL
 
0.024 256468.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-10-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WEST GENERAL CONTRACTORS CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0095-02-109
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133218
Totals 256468.00 0.00 0.00 0.0

CountyKAUFMAN
Highway US 80
From AT FM 740 SOUTH
To IN FORNEY
CSJ 0095-03-086
Proj ID NH 2013(382)
Work Type REHABILITATION OF TRAFFIC SIGNALS
 
0.002 247839.23 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-03-13
Work Began 05-06-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ROADWAY SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0095-03-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133021
Totals 247839.23 0.00 0.00 0.0

CountyKAUFMAN
Highway US 80
From AT PROPOSED FORNEY PARKWAY
To .
CSJ 0095-04-064
Proj ID C 95-4-64
Work Type GR, STR, DRAINAGE, PVMT, SIGNS
 
1.030 17050215.03 107963.84 13115532.61 76.9
Work Order 03-06-12
Work Began 04-09-12
Work Completed  
Time Computed 03-22-12
Contract Working Days 473
Addl Days Granted 0
Working Days Charged 311
Percent Time Used 65
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0095-04-064
BEAIRD DRILLING(2.99%)
BUYERS BARRICADES, INC.(0.19%)
DUSTROL, INC.(0.14%)
FORTSON CONTRACTING, INC.(0.57%)
PEACHTREE CONSTRUCTION, LTD. (3.69%)
STAR OPERATIONS, INC.(1.93%)
STORM WATER MANAGEMENT, INC. (0.08%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.32%)
SOUTH TEXAS PAINTING COMPANY (1.00%)
CONCRETE CUTTING BY BOND (0.07%)
USA SWPPP INSPECTIONS, INC.(0.64%)
W. W. FOUNDATION DRILLING, LTD.(2.82%)
J.L. STEEL REINFORCING, LLC(1.20%)
PETERSON CONTRACTORS, INC. (0.00%)
COWBOY TRUCKING(0.00%)
Contract # 01123202
Totals 17050215.03 107963.84 13115532.61 76.9

CountyKAUFMAN
Highway US 80
From AT NINTH ST AND SP 87 (DELLIS ST)
To IN TERRELL
CSJ 0095-05-056
Proj ID STP 2013(728)
Work Type REHABILITATION OF TRAFFIC SIGNALS
 
1.462 184862.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0095-05-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133225
Totals 184862.00 0.00 0.00 0.0

CountyDALLAS
Highway IH 20
From I.H. 635
To SEAGOVILLE ROAD.
CSJ 0095-13-025
Proj ID IM 0205(146)
Work Type GRADING, PAVING, SIGNING, LANDSCAPING
 
0.841 4972861.19 536338.96 2658680.58 53.4
Work Order 06-21-12
Work Began 10-01-12
Work Completed  
Time Computed 10-01-12
Contract Working Days 147
Addl Days Granted 0
Working Days Charged 141
Percent Time Used 95
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0095-13-025
NORTH TEXAS REBAR, LLC (0.68%)
FORTSON CONTRACTING, INC.(1.00%)
INTEGRATED ROADWAY SERVICES, INC.(1.49%)
S & S PAINTING (0.25%)
W.O.E. CONSTRUCTION(0.21%)
AXIS CONTRACTING, INC. (8.00%)
HOUSTON SAWING & DRILLING(0.05%)
USA SWPPP INSPECTIONS, INC.(0.47%)
DUSTROL, INC.(0.54%)
DALLAS LITE AND BARRICADE INC. (0.28%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.23%)
THELIN RECYCLING COMPANY, L.P. (0.24%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(9.28%)
W. W. FOUNDATION DRILLING, LTD.(2.12%)
THE ANCHOR GROUP, INC. (0.78%)
NORTH TEXAS REBAR, LLC (0.09%)
COWBOY TRUCKING(0.40%)
Contract # 05123247
Totals 4972861.19 536338.96 2658680.58 53.4

CountyKAUFMAN
Highway IH 20
From DALLAS/KAUFMAN COUNTY LINE
To 0.21 MI WEST OF ROSEHILL ROAD
CSJ 0095-14-016
Proj ID IM 0205(127)
Work Type 2" HMAC OVERLAY
 
13.189 3165908.57 205588.57 1875345.54 59.2
Work Order 11-16-11
Work Began 04-10-12
Work Completed  
Time Computed 01-15-12
Contract Working Days 83
Addl Days Granted 89
Working Days Charged 119
Percent Time Used 69
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0095-14-016
BUYERS BARRICADES, INC.(0.27%)
DUSTROL, INC.(1.34%)
HIGHWAY TECHNOLOGIES, INC. (5.17%)
W.O.E. CONSTRUCTION(1.62%)
O. TREVINO CONSTRUCTION, LLC (2.27%)
BRENDA PRICE TRUCKING(0.09%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.37%)
Contract # 10113014
Totals 3165908.57 205588.57 1875345.54 59.2

CountyDENTON
Highway US 380
From DENTON/WISE COUNTY LINE ROAD
To WEST OF FM 156
CSJ 0134-09-029
Proj ID STP 2012(184)SB
Work Type GR, STR, DRAINAGE, BASE, PVMT, AND
 
7.860 26379472.05 1052813.73 10142991.72 38.4
Work Order 02-22-12
Work Began 05-14-12
Work Completed  
Time Computed 05-14-12
Contract Working Days 588
Addl Days Granted 0
Working Days Charged 236
Percent Time Used 40
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0134-09-029
GLENN THURMAN, INC.( 14.17%)
HIGHWAY TECHNOLOGIES, INC. (1.04%)
BROCK ENVIRONMENTAL, LLC (0.65%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.42%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(2.02%)
DUSTROL, INC.(0.64%)
FORTSON CONTRACTING, INC.(0.87%)
MIKE ALBERT, INC.(2.69%)
MURRAY CONSTRUCTION(0.35%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.85%)
IOWA BRIDGE & CULVERT, LC(0.33%)
TEXAS SHAFTS, INC. (0.15%)
MCL CONTRACTING, LLC (0.01%)
LKT & ASSOCIATES (2.33%)
Contract # 12113201
Totals 26379472.05 1052813.73 10142991.72 38.4

CountyDENTON
Highway US 380
From WEST OF BONNIE BRAE ST
To US 377
CSJ 0134-09-034
Proj ID STP 2013(181)
Work Type STRUCTURES, BASE, PAVEMENT
 
1.625 15088445.93 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-03-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 420
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0134-09-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11123002
Totals 15088445.93 0.00 0.00 0.0

CountyDENTON
Highway US 380
From WEST OF FM 156
To IH 35
CSJ 0134-09-063
Proj ID NH 2012(635)
Work Type GR, STR, DRAINAGE, PVMT, C & G, SIGNS
 
4.702 39346679.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 755
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0134-09-063
BROCK ENVIRONMENTAL, LLC (0.23%)
BUYERS BARRICADES, INC.(0.19%)
FORTSON CONTRACTING, INC.(0.67%)
THELIN RECYCLING COMPANY, L.P. (0.29%)
CRAIG OLDEN, INC.(0.26%)
JAGOE-PUBLIC COMPANY ( 13.71%)
NORTH TEXAS BOMANITE, INC. (0.70%)
TEXAS INLETS, INC. (2.35%)
TEX OP CONSTRUCTION, LP(0.64%)
TRAC-WORK, INC.(1.82%)
WYLIE DRILLING & DRAINAGE, INC.(1.19%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.08%)
CHOCTAW ERECTORS, INC. (0.76%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(1.04%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.94%)
INLET STRUCTURE SPECIALTIES LTD. (0.96%)
MCL CONTRACTING, LLC (1.02%)
Contract # 07123002
Totals 39346679.90 0.00 0.00 0.0

CountyCOLLIN
Highway US 380
From EAST OF FM 2478 (CUSTER RD)
To EAST OF LAKE FOREST DRIVE
CSJ 0135-02-045
Proj ID C 135-2-45
Work Type BASE, PVMT, SIGNS, MKGS
 
3.124 11650909.58 330486.94 10441714.95 89.6
Work Order 10-05-11
Work Began 01-03-12
Work Completed  
Time Computed 01-03-12
Contract Working Days 315
Addl Days Granted 25
Working Days Charged 339
Percent Time Used 99
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0135-02-045
BROCK ENVIRONMENTAL, LLC (0.25%)
DUSTROL, INC.(0.43%)
FORTSON CONTRACTING, INC.(0.52%)
HIGHWAY TECHNOLOGIES, INC. (1.15%)
IOWA BRIDGE & CULVERT, LC( 10.95%)
K & S UTILITY CONTRACTORS, INC.( 14.92%)
MIKE ALBERT, INC.( 11.79%)
ROADWAY SOLUTIONS, INC.(1.36%)
SHILLING CONSTRUCTION COMPANY(1.60%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.35%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.25%)
FOUNDATION DRILLERS, INC.(0.72%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(0.06%)
C.B. SERVICES, INC.(0.21%)
WYLIE DRILLING & DRAINAGE, INC.(0.21%)
SCOTT DERR PAINTING CO, LLC(0.23%)
TEXAS BOMANITE (1.70%)
Contract # 07113269
Totals 11650909.58 330486.94 10441714.95 89.6

CountyCOLLIN
Highway US 380
From EAST OF FLOYD RD
To CR 698 (HUNT COUNTY LINE)
CSJ 0135-05-023
Proj ID C 135-5-23
Work Type GR, STRS, PAVT, CUL, CURB AND GTRS
 
3.172 16564930.23 755.23 16767248.30 99.9
Work Order 08-17-10
Work Began 04-11-11
Work Completed  
Time Computed 02-13-11
Contract Working Days 394
Addl Days Granted 5
Working Days Charged 373
Percent Time Used 93
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0135-05-023
CRAIG OLDEN, INC.(0.40%)
DALLAS LITE AND BARRICADE INC. (0.16%)
INLET STRUCTURE SPECIALTIES LTD. (1.44%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 13.58%)
RIVER CITIES SAWING, LLC (0.46%)
W.O.E. CONSTRUCTION(1.43%)
S & V CONSTRUCTION LLC (1.47%)
BEAIRD DRILLING(0.24%)
TEX OP CONSTRUCTION, LP(0.42%)
BREDA COMPANY, INC.(1.19%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.68%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.63%)
FORTSON CONTRACTING, INC.(1.34%)
TEXAS STAR TRANSPORT, LP (0.27%)
E W WELLS GROUP LLC(0.34%)
WYLIE DRILLING & DRAINAGE, INC.(0.14%)
CONCRETE CUTTING BY BOND (0.21%)
INTEGRATED ROADWAY SERVICES, INC.(0.25%)
Contract # 07103211
Totals 16564930.23 755.23 16767248.30 99.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8