Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCOLLIN
Highway FM 1138
From ROCKWALL COUNTY LINE
To FM 6 IN NEVADA
CSJ 1016-02-017
Proj ID STP 2014(006)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
4.216 3337173.45 85135.53 1621683.71 48.5
Work Order 12-04-13
Work Began 03-12-14
Work Completed  
Time Computed 02-02-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 104
Percent Time Used 65
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1016-02-017
FORTSON CONTRACTING, INC.(0.17%)
ENVIRONMENTAL STANDARDS, INC.(3.91%)
ALTUS TRAFFIC MANAGEMENT LLC (0.37%)
DUSTROL, INC.(2.74%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.85%)
J & M CONTRACTING, COMPANY ( 19.06%)
Contract # 09133215
Totals 3337173.45 85135.53 1621683.71 48.5

CountyDALLAS
Highway FM 1382
From NEW CLARK ROAD
To WEST OF STRAUS RD IN CEDAR HILL
CSJ 1047-03-063
Proj ID C 1047-3-63
Work Type INTERSECTION IMPROVEMENTS
 
0.493 1893193.60 110097.26 576752.77 30.4
Work Order 01-06-14
Work Began 02-26-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 300
Addl Days Granted 1
Working Days Charged 114
Percent Time Used 37
Contractor(s)
CD BUILDERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1047-03-063
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(7.09%)
ODUM SERVICES, L.P.(0.90%)
SIEMENS INDUSTRY, INC. (2.95%)
USA EROSION, INC.(1.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.17%)
MELS ELECTRIC, L.P.(2.98%)
ALLIANCE GEOTECHNICAL GROUP(0.20%)
GLL CORPORATION DBA MG TRUCKING(3.30%)
W.O.E. CONSTRUCTION(0.82%)
Contract # 11133021
Totals 1893193.60 110097.26 576752.77 30.4

CountyTARRANT
Highway IH 30
From 0.5 MILES WEST OF N. FIELDER ROAD
To DALLAS/TARRANT COUNTY LINE
CSJ 1068-02-135
Proj ID C 1068-2-135
Work Type ITS, ETC, SIGNS
 
6.091 6960302.24 673878.91 4872506.28 70.0
CountyDALLAS
Highway IH 30
From TARRANT/DALLAS COUNTY LINE
To SYLVAN AVE.
CSJ 1068-04-147
Proj ID IM 0305(082)
Work Type STR, GR, PVMT, PVMT MKGS, SIGNS, ITS
 
12.664 56121468.07 1994249.41 29600029.49 52.7
Work Order 02-28-13
Work Began 03-25-13
Work Completed  
Time Computed 03-16-13
Contract Working Days 728
Addl Days Granted 0
Working Days Charged 394
Percent Time Used 54
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-147
COWTOWN TRAFFIC CONTROL, INC.(0.04%)
THE ANCHOR GROUP, INC. (0.02%)
ANTIGO CONSTRUCTION, INC.(0.02%)
DUSTROL, INC.(0.33%)
DUSTIN ALLEN, INC. (0.41%)
HOUSTON SAWING & DRILLING(0.02%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.09%)
PENHALL COMPANY(0.06%)
STORM WATER MANAGEMENT, INC. (0.13%)
VSTRUCTURAL LLC(0.42%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.12%)
W.O.E. CONSTRUCTION(0.64%)
STRIPING TECHNOLOGY, L.P.(2.08%)
MICA CORPORATION ( 19.67%)
W. W. FOUNDATION DRILLING, LTD.(2.65%)
K & S UTILITY CONTRACTORS, INC.(4.66%)
INDUS CONSTRUCTION, L.P. (0.56%)
PRESSURE CLEANING SERVICE, INC. DBA WATERBLASTING.COM(0.06%)
RAMBO CONTRACTING, INC.(1.19%)
NORTH TEXAS REBAR, LLC (0.13%)
HERDEZ TRUCKING, INC.(0.09%)
J.H. PAINTING COMPANY(0.41%)
Contract # 12123201
Totals 63081770.31 2668128.32 34472535.77 54.6

CountyDALLAS
Highway IH 30
From BELT LINE RD. IN GRAND PRAIRIE
To N.E. 15TH ST.
CSJ 1068-04-142
Proj ID STP 2011(706)MM
Work Type GR, STR, PVMT, SIGNS, BUILDING
 
0.767 7282375.53 0.00 9319133.98 99.9
CountyDALLAS
Highway IH 30
From BELT LINE RD.
To MACARTHUR BLVD.
CSJ 1068-04-145
Proj ID C 1068-4-145
Work Type GR, STR, PVMT, SIGNS
 
2.060 7497722.23 3088.80 7525931.66 99.9
Work Order 02-15-11
Work Began 04-22-11
Work Completed  
Time Computed 04-16-11
Contract Working Days 491
Addl Days Granted 219
Working Days Charged 686
Percent Time Used 96
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-142
DUSTROL, INC. (ROANOKE)(0.09%)
FORTSON CONTRACTING, INC.(0.81%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(5.65%)
BUYERS BARRICADES, INC.(0.04%)
THE ANCHOR GROUP, INC. (0.38%)
CONCRETE CUTTING BY BOND (0.06%)
COWTOWN TRAFFIC CONTROL, INC.(0.19%)
FARR FOUNDATION, INC.(6.20%)
GK CONSTRUCTION, LLC (0.66%)
C.T. AND S. METALWORKS, INC. (1.72%)
CENTRAL NORTH CONSTRUCTION, LLC(2.17%)
STAR OPERATIONS, INC.(3.43%)
MCMAHON CONTRACTING, L.P.( 20.81%)
STRIPE-A-ZONE, INC.(0.61%)
ALLIANCE GEOTECHNICAL GROUP(0.15%)
PIBURN & CARSON, LLC (0.50%)
FOUNDATION DRILLERS, INC.(0.15%)
COWBOY TRUCKING(0.13%)
RMI WORLDWIDE, LLC (0.05%)
LONE STAR HIGHWAY PRODUCTS, INC. (2.50%)
USA SWPPP INSPECTIONS, INC.(0.45%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.02%)
SUPREME SAWING AND SEALING (0.24%)
J.L. STEEL REINFORCING, LLC(0.09%)
W.O.E. CONSTRUCTION(0.05%)
L & E HART ENTERPRISES, INC. (2.20%)
STORM WATER MANAGEMENT, INC. (0.03%)
SCOTT DERR PAINTING CO, LLC(0.12%)
STRAIGHT LINE SAWING & SEALING (0.14%)
UTILITY AND ENVIRONMENTAL SERVICES, INCORPORATED (0.10%)
Contract # 12103201
Totals 14780097.76 3088.80 16845065.64 99.9

CountyDALLAS
Highway IH 30
From 0.5 MILES WEST OF WESTMORELAND RD
To EAST OF WESTMORELAND RD
CSJ 1068-04-153
Proj ID C 1068-4-153
Work Type GRADING, PAVEMENT, SIGNS, PVMT MKGS
 
0.574 2655000.00 0.00 2739005.97 99.9
Work Order 01-04-13
Work Began 01-22-13
Work Completed  
Time Computed 01-20-13
Contract Working Days 128
Addl Days Granted 40
Working Days Charged 235
Percent Time Used 139
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-153
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(8.60%)
COWTOWN TRAFFIC CONTROL, INC.(0.57%)
W.O.E. CONSTRUCTION(0.25%)
HIGHWAY TECHNOLOGIES, INC. (0.72%)
BREDA COMPANY, INC.(0.77%)
INLET STRUCTURE SPECIALTIES LTD. (3.56%)
MELS ELECTRIC, L.P.(6.28%)
TEX OP CONSTRUCTION, LP(0.64%)
FORTSON CONTRACTING, INC.(0.27%)
BRENDA PRICE TRUCKING(0.18%)
USA SWPPP INSPECTIONS, INC.(3.16%)
STRIPING TECHNOLOGY, L.P.(1.03%)
Contract # 10123213
Totals 2655000.00 0.00 2739005.97 99.9

CountyDALLAS
Highway IH 30
From COCKRELL HILL ROAD
To WESTMORELAND RD IN DALLAS
CSJ 1068-04-154
Proj ID C 1068-4-154
Work Type GRADING, PAVEMENT, SIGNS, PVMT MKGS
 
2.704 9814841.51 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 321
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-154
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143214
Totals 9814841.51 0.00 0.00 0.0

CountyKAUFMAN
Highway FM 740
From BUFFALO CREEK
To '
CSJ 1091-01-016
Proj ID STP 2009(601)ES
Work Type REPL BR & APPRS
 
0.323 2856520.65 43853.92 3871626.17 99.9
Work Order 09-28-09
Work Began 02-16-10
Work Completed  
Time Computed 10-14-09
Contract Working Days 389
Addl Days Granted 93
Working Days Charged 525
Percent Time Used 108
Contractor(s)
DOUGHTIE CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1091-01-016
BTA SERVICES, LTD. (0.58%)
PREMIER PAVING, LTD. ( 10.17%)
COWTOWN TRAFFIC CONTROL, INC.(0.30%)
CENTRAL TEXAS ENVIRONMENTAL SERVICES, LLC(0.42%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.98%)
D & E CONTRACTORS(8.87%)
HOLES INCORPORATED (0.98%)
TEX OP CONSTRUCTION, LP(0.35%)
JUST GROOVING, LTD.(0.19%)
LONE STAR HIGHWAY PRODUCTS, INC. (3.67%)
CLEMONS TRUCKING (0.36%)
SOUTHWEST CRUSHING, LLC(0.36%)
BREDA COMPANY, INC.(0.24%)
INTERSTATE SAFETY SYSTEMS, INC.(3.92%)
WEBBER BARRIER SERVICES, INC.(3.07%)
ODUM SERVICES, L.P.(0.74%)
Contract # 07093216
Totals 2856520.65 43853.92 3871626.17 99.9

CountyKAUFMAN
Highway FM 740
From RANCH ROAD IN FORNEY
To ROCKWALL COUNTY LINE
CSJ 1091-01-019
Proj ID STP 2013(318)
Work Type GR, BASE, PVMT, HMAC, PVMT MKGS, SI
 
6.023 5599999.92 428447.05 3203043.27 57.4
Work Order 06-20-13
Work Began 07-25-13
Work Completed  
Time Computed 07-06-13
Contract Working Days 210
Addl Days Granted 32
Working Days Charged 253
Percent Time Used 104
Contractor(s)
WESTFIELD INSURANCE GROUP
SUBCONTRACTOR(S) FOR CCSJ: 1091-01-019
PEACHTREE CONSTRUCTION, LTD. ( 39.38%)
HIGHWAY 19 CONSTRUCTION, LLC (8.06%)
TEXAS HIGHWAY MAINTENANCE, LLC (1.20%)
USA SWPPP INSPECTIONS, INC.(2.50%)
DUSTROL, INC.(3.13%)
INTEGRATED ROADWAY SERVICES, INC.(2.53%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.40%)
PEACHTREE CONSTRUCTION, LTD. ( 39.68%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.69%)
USA SWPPP INSPECTIONS, INC.(1.15%)
DUSTROL, INC.(1.91%)
FORTSON CONTRACTING, INC.(0.97%)
BRENDA PRICE TRUCKING(2.54%)
Contract # 04133223
Totals 5599999.92 428447.05 3203043.27 57.4

CountyROCKWALL
Highway FM 740 ETC
From AT AMY PARKS ELEMENTARY SCHOOL
To IN CITY OF HEATH
CSJ 1091-04-019
Proj ID STP 1102(212)SRS
Work Type PEDESTRIAN WALKWAY IMPROVEMENTS#2
 
0.982 1049080.05 7885.11 329846.88 31.4
Work Order 12-03-13
Work Began 05-19-14
Work Completed  
Time Computed 02-01-14
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 48
Percent Time Used 63
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1091-04-019
BRENDA PRICE TRUCKING(1.20%)
DUSTROL, INC.(0.68%)
LONE STAR MANHOLE & STRUCTURES, LLC(1.79%)
ROAD MASTER STRIPING LLC (0.32%)
USA SWPPP INSPECTIONS, INC.(3.66%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.55%)
Contract # 08133057
Totals 1049080.05 7885.11 329846.88 31.4

CountyKAUFMAN
Highway FM 741
From FM 740
To MONITOR BLVD. IN FORNEY
CSJ 1092-01-018
Proj ID STP 2013(453)
Work Type LANDSCAPE DEVELOPMENT
 
1.976 298102.56 5655.66 340502.01 100.0
Work Order 05-20-13
Work Began 07-10-13
Work Completed 08-08-14
Time Computed 06-05-13
Contract Working Days 92
Addl Days Granted 4
Working Days Charged 101
Percent Time Used 105
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1092-01-018
TOTAL HIGHWAY MAINTENANCE, LLC (1.41%)
FIRELINE SERVICES, INC.(2.01%)
SYSTEM ELECTRIC CO. DBA MCBRIDE ELECTRIC (3.65%)
CC TREE FARMS, L.L.C.(5.05%)
AQUA BORE(0.98%)
Contract # 03133221
Totals 298102.56 5655.66 340502.01 100.0

CountyELLIS
Highway FM 879
From AT BRANCH OF MUSTANG CREEK
To .
CSJ 1159-02-031
Proj ID BR 2013(832)
Work Type REPLACE BR & APPRS
 
0.134 889807.76 1045.82 360040.25 40.4
Work Order 10-24-13
Work Began 01-15-14
Work Completed  
Time Computed 12-23-13
Contract Working Days 245
Addl Days Granted 0
Working Days Charged 152
Percent Time Used 62
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1159-02-031
FORTSON CONTRACTING, INC.(2.52%)
HOUSTON SAWING & DRILLING(0.33%)
MCL CONTRACTING, LLC (1.05%)
ALTUS TRAFFIC MANAGEMENT LLC (1.05%)
PEACHTREE CONSTRUCTION, LTD. (5.55%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.38%)
STORM WATER MANAGEMENT, INC. (1.03%)
STRIPING TECHNOLOGY, L.P.(1.46%)
W.O.E. CONSTRUCTION(0.13%)
MCL CONTRACTING, LLC (0.23%)
Contract # 07133013
Totals 889807.76 1045.82 360040.25 40.4

CountyDENTON
Highway FM 1171
From WEST OF US 377
To WEST OF SHILOH RD
CSJ 1311-01-034
Proj ID C 1311-1-34
Work Type GR, STRS, BASE, CRCP, PVMT MKGS, SIGNS
 
7.011 45721253.16 967739.96 3677918.23 8.0
Work Order 06-05-13
Work Began 06-02-14
Work Completed  
Time Computed 03-02-14
Contract Working Days 693
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 5
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1311-01-034
BREDA COMPANY, INC.(0.96%)
BUYERS BARRICADES, INC.(0.20%)
CINTEREX US, INC.(1.17%)
CLLA GROUP, LLC(9.39%)
DUSTROL, INC.(0.30%)
INTEGRATED ROADWAY SERVICES, INC.(2.34%)
JAGOE-PUBLIC COMPANY ( 14.10%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.74%)
THELIN RECYCLING COMPANY, L.P. (0.16%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.10%)
W.O.E. CONSTRUCTION(0.28%)
WYLIE DRILLING & DRAINAGE, INC.(0.83%)
VENUS CONSTRUCTION (3.09%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.35%)
Contract # 03133002
Totals 45721253.16 967739.96 3677918.23 8.0

CountyDENTON
Highway FM 423
From US 380
To 0.8 MI SOUTH OF FM 2934
CSJ 1315-02-009
Proj ID C 1315-2-9
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.488 29826069.73 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-12-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 603
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 1315-02-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09133204
Totals 29826069.73 0.00 0.00 0.0

CountyCOLLIN
Highway FM 1378
From 585 SOUTH OF WHITE ROCK CREEK
To NORTH OF WHITE ROCK CREEK
CSJ 1392-01-035
Proj ID BR 2014(872)
Work Type REPL BRIDGE
 
0.526 1788995.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ACCELERATED CRITICAL PATH, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1392-01-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143231
Totals 1788995.75 0.00 0.00 0.0

CountyELLIS
Highway FM 1387
From WEST OF KENSINGTON DR
To EAST OF WALNUT GROVE RD
CSJ 1394-02-023
Proj ID CC 1394-2-23
Work Type GRADING, PAVING, STRUCTURES, SIGNS
 
0.925 4091255.00 596250.20 1913170.82 46.7
Work Order 08-06-13
Work Began 10-16-13
Work Completed  
Time Computed 10-05-13
Contract Working Days 309
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 68
Contractor(s)
TISEO PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 1394-02-023
BROCK ENVIRONMENTAL, LLC (1.34%)
MEL"S ELECTRIC SERVICE, INC. (3.36%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 16.40%)
RPM XCONSTRUCTION, LLC (8.29%)
STRIPING TECHNOLOGY, L.P.(1.65%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (6.50%)
DALLAS LITE AND BARRICADE INC. (0.65%)
DUSTROL, INC.(0.91%)
CROSSROADS, L.P. (0.37%)
T-BAR FENCE, INC.(0.09%)
W.O.E. CONSTRUCTION(7.41%)
FOUR STAR EXCAVATING INC (9.19%)
INLET STRUCTURE SPECIALTIES LTD. (1.66%)
IRON CONCRETE CONSTRUCTION COMPANY, INC. (1.66%)
J.R. STEEL TIE (0.83%)
Contract # 04133010
Totals 4091255.00 596250.20 1913170.82 46.7

CountyELLIS
Highway FM 55
From SH 34
To 0.14 MI S OF NASH HOWARD RD
CSJ 1451-01-024
Proj ID STP 2014(874)
Work Type GR, BASE, PVMT MKGS, SIGNS
 
5.052 5538628.87 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143018
Totals 5538628.87 0.00 0.00 0.0

CountyDENTON
Highway FM 720
From AT HARTS BRANCH
To .
CSJ 1567-01-021
Proj ID BR 2010(983)
Work Type REPL BR & APPRS
 
0.080 1726268.66 154628.60 1387015.22 80.3
CountyDENTON
Highway FM 720
From AT LITTLE ELM CREEK BRANCH OF LAKE
To LEWISVILLE
CSJ 1567-01-022
Proj ID BR 2010(983)
Work Type REPL BR & APPRS
 
0.484 15758790.61 537708.64 13742609.66 87.2
CountyDENTON
Highway FM 720
From 0.2 MI W OF GARZA LANE (W OF LAKE L
To 0.1 MI WEST OF FM 423
CSJ 1567-01-029
Proj ID STP 2010(982)MM
Work Type GRADING, STR, PVMT, SIGNS
 
4.493 33538923.64 696140.60 23144812.02 69.0
CountyDENTON
Highway FM 720
From 0.2 MILE WEST OF GARZA LANE
To 0.1 MILE WEST OF FM 423
CSJ 1567-01-032
Proj ID RW 1567-1-32
Work Type ROW ACQ. AND UTIL. ADJUST.
 
0.001 3297279.80 0.00 460852.58 13.9
Work Order 09-13-10
Work Began 07-14-11
Work Completed  
Time Computed 03-12-11
Contract Working Days 577
Addl Days Granted 8
Working Days Charged 561
Percent Time Used 95
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-029
ATS DRILLING, L.P. (5.77%)
BRENDA PRICE TRUCKING(0.22%)
CRAIG OLDEN, INC.(0.61%)
DALLAS LITE AND BARRICADE INC. (0.11%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21%)
HIGHWAY TECHNOLOGIES, INC. (0.31%)
L & E HART ENTERPRISES, INC. (2.09%)
MICA CORPORATION (4.78%)
NORTH TEXAS REBAR, LLC (5.54%)
PENHALL COMPANY(0.05%)
RAMBO CONTRACTING, INC.(2.62%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(6.26%)
S & V CONSTRUCTION LLC (0.05%)
SOUTH TEXAS PAINTING COMPANY (0.15%)
STORM WATER MANAGEMENT, INC. (0.10%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.28%)
TEX OP CONSTRUCTION, LP(0.99%)
WEIR BROS.,INC.(5.19%)
GREAT WESTERN ERECTORS (0.12%)
DURABLE SPECIALTIES, INC.(1.39%)
LAYFIELD CONSTRUCTION, INC (0.01%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36%)
GREAT WESTERN ERECTORS (0.49%)
Contract # 07103001
Totals 54321262.71 1388477.84 38735289.48 71.3

CountyDENTON
Highway FM 720
From ELDORADO PKWY (FM 720)
To SOUTH OF MARTOP
CSJ 1567-01-025
Proj ID C 1567-1-25
Work Type GR, STRS & PVT
 
2.565 15597320.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 420
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143001
Totals 15597320.25 0.00 0.00 0.0

CountyDENTON
Highway FM 720
From FINSBURY TRAIL
To FM 423
CSJ 1567-01-035
Proj ID STP 2013(666)
Work Type LANDSCAPE DEVELOPMENT
 
1.160 524000.00 17502.00 527703.25 100.0
Work Order 09-05-13
Work Began 09-25-13
Work Completed 08-04-14
Time Computed 09-21-13
Contract Working Days 83
Addl Days Granted 0
Working Days Charged 72
Percent Time Used 86
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-035
HIGHWAY BARRICADES AND SERVICES, LLC (1.47%)
AQUA BORE(5.66%)
MATERIALS MANAGEMENT SERVICES(0.30%)
Contract # 05133010
Totals 524000.00 17502.00 527703.25 100.0

CountyDENTON
Highway FM 423
From STEWARTS CREEK ROAD
To SH 121
CSJ 1567-02-032
Proj ID C 1567-2-32
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.761 49691109.92 0.00 0.00 0.0
CountyDENTON
Highway FM 423
From STEWARTS CREEK ROAD
To SH 121
CSJ 1567-02-033
Proj ID RW 1567-2-33
Work Type ADJUSTMENT OF UTILITIES
 
3.761 8252384.38 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 756
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1567-02-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143001
Totals 57943494.30 0.00 0.00 0.0