Monthly State Let Construction Report For Dallas District As Of Apr 11, 2016 Page 7 Of 9

Last Update: Monday, April 11, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTARRANT
Highway IH 30
From 0.5 MILES WEST OF N. FIELDER ROAD
To DALLAS/TARRANT COUNTY LINE
CSJ 1068-02-135
Proj ID C 1068-2-135
Work Type ITS, ETC, SIGNS
 
6.091 6960302.24 382615.33 6366038.57 91.4
CountyDALLAS
Highway IH 30
From TARRANT/DALLAS COUNTY LINE
To SYLVAN AVE.
CSJ 1068-04-147
Proj ID IM 0305(082)
Work Type STR, GR, PVMT, PVMT MKGS, SIGNS, ITS
 
12.664 56121468.07 1331011.45 56198335.87 99.9
Work Order 02-28-13
Work Began 03-25-13
Work Completed  
Time Computed 03-16-13
Contract Working Days 728
Addl Days Granted 69
Working Days Charged 880
Percent Time Used 110
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-147
COWTOWN TRAFFIC CONTROL, INC.(0.04%)
THE ANCHOR GROUP, INC. (0.02%)
ANTIGO CONSTRUCTION, INC.(0.02%)
DUSTROL, INC.(0.33%)
DUSTIN ALLEN, INC. (0.41%)
HOUSTON SAWING & DRILLING(0.02%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.09%)
PENHALL COMPANY(0.06%)
STORM WATER MANAGEMENT, INC. (0.13%)
VSTRUCTURAL LLC(0.42%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.12%)
W.O.E. CONSTRUCTION(0.64%)
STRIPING TECHNOLOGY, L.P.(2.08%)
MICA CORPORATION ( 19.67%)
W. W. FOUNDATION DRILLING, LTD.(2.65%)
K & S UTILITY CONTRACTORS, INC.(4.66%)
INDUS CONSTRUCTION, L.P. (0.56%)
PRESSURE CLEANING SERVICE, INC. DBA WATERBLASTING.COM(0.06%)
RAMBO CONTRACTING, INC.(1.19%)
NORTH TEXAS REBAR, LLC (0.00%)
HERDEZ TRUCKING, INC.(0.09%)
J.H. PAINTING COMPANY(0.41%)
MCL CONTRACTING, LLC (0.09%)
CB SERVICES, INC.(0.06%)
VFC, INC (0.11%)
STRIPE-A-ZONE, INC.(1.00%)
Contract # 12123201
Totals 63081770.31 1713626.78 62564374.44 99.5

CountyDALLAS
Highway IH 30
From BELTLINE ROAD
To MAC ARTHUR BLVD.
CSJ 1068-04-122
Proj ID C 1068-4-122
Work Type GR, STRS & PAV
 
1.522 24620668.27 0.00 0.00 0.0
CountyDALLAS
Highway IH 30
From BELT LINE RD
To MACARTHUR RD
CSJ 1068-04-137
Proj ID ROW 1068-4-137
Work Type ROW ACQ, UTIL & RELOC
 
0.760 565255.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-16-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 538
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAYDON CENTRAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-122
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153004
Totals 25185923.27 0.00 0.00 0.0

CountyDALLAS
Highway IH 30
From NW 7TH STREET
To BELTLINE ROAD
CSJ 1068-04-148
Proj ID STP 2016(740)MM
Work Type GR, DRN, RET WLS, CONC PAV, SIG, PV MRKS
 
1.011 7991673.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 380
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-148
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163225
Totals 7991673.30 0.00 0.00 0.0

CountyDALLAS
Highway IH 30
From COCKRELL HILL ROAD
To WESTMORELAND RD IN DALLAS
CSJ 1068-04-154
Proj ID C 1068-4-154
Work Type GRADING, PAVEMENT, SIGNS, PVMT MKGS
 
2.704 9814841.51 193586.55 5841392.45 59.9
Work Order 09-09-14
Work Began 11-11-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 321
Addl Days Granted 0
Working Days Charged 361
Percent Time Used 112
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-154
K & S UTILITY CONTRACTORS, INC.(9.08%)
OSCAR ORDUNO, INC. (4.26%)
STORM WATER MANAGEMENT, INC. (0.29%)
SLATON BROTHERS, INC.(4.57%)
Contract # 07143214
Totals 9814841.51 193586.55 5841392.45 59.9

CountyKAUFMAN
Highway FM 741
From US 175
To EAST OF FM 548
CSJ 1092-01-017
Proj ID STP 2015(778)
Work Type GR, BASE, ACP OVERLAY, PVMT MKGS
 
7.726 4550316.19 895810.15 3584669.57 78.8
Work Order 03-23-15
Work Began 06-03-15
Work Completed  
Time Computed 04-23-15
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 191
Percent Time Used 102
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1092-01-017
ALTUS TRAFFIC MANAGEMENT LLC (0.26%)
TEXAS ENVIRONMENTAL MANAGEMENT SA, INC.(4.68%)
DUSTROL, INC.(4.57%)
MARCOM"S MOWING SERVICE, LLC (1.16%)
J & M CONTRACTING, COMPANY (7.65%)
STRIPING TECHNOLOGY, L.P.(1.43%)
FORTSON CONTRACTING, INC.(0.60%)
C & J TREE SERVICE (0.03%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.68%)
Contract # 02153235
Totals 4550316.19 895810.15 3584669.57 78.8

CountyELLIS
Highway FM 875
From AT WAXAHACHIE CREEK
To .
CSJ 1159-01-022
Proj ID BR 2013(604)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.471 3724841.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 467
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1159-01-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153025
Totals 3724841.00 0.00 0.00 0.0

CountyELLIS
Highway FM 879
From AT BRANCH OF MUSTANG CREEK
To .
CSJ 1159-02-031
Proj ID BR 2013(832)
Work Type REPLACE BR & APPRS
 
0.134 889807.76 0.00 935140.21 99.9
Work Order 10-24-13
Work Began 01-15-14
Work Completed  
Time Computed 12-23-13
Contract Working Days 245
Addl Days Granted 181
Working Days Charged 426
Percent Time Used 100
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1159-02-031
FORTSON CONTRACTING, INC.(2.52%)
HOUSTON SAWING & DRILLING(0.33%)
MCL CONTRACTING, LLC (1.05%)
ALTUS TRAFFIC MANAGEMENT LLC (1.05%)
PEACHTREE CONSTRUCTION, LTD. (5.55%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.38%)
STORM WATER MANAGEMENT, INC. (1.03%)
STRIPING TECHNOLOGY, L.P.(1.46%)
W.O.E. CONSTRUCTION(0.13%)
MCL CONTRACTING, LLC (0.23%)
WOLFE CONSTRUCTION GROUP, INC. (1.18%)
SOUTHEAST GRINDING & GROOVING, LLC (0.56%)
Contract # 07133013
Totals 889807.76 0.00 935140.21 99.9

CountyELLIS
Highway FM 879
From 2.1 MILES WEST OF IKE RD
To 0.3 MILE WEST OF FM 1722
CSJ 1159-02-032
Proj ID STP 1502(328)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
6.667 9549753.04 428086.10 1801236.27 18.8
Work Order 07-31-15
Work Began 09-03-15
Work Completed  
Time Computed 07-31-15
Contract Working Days 315
Addl Days Granted 0
Working Days Charged 151
Percent Time Used 47
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1159-02-032
CROSS ROADS, L.P.(0.38%)
BROCK ENVIRONMENTAL SERVICES, LLC(0.19%)
ACU CONSTRUCTION LLC (1.24%)
STRIPING TECHNOLOGY, L.P.(0.61%)
SYNERGY SIGNS & SERVICES (0.28%)
FORTSON CONTRACTING, INC.(1.62%)
NORTH EASTERN PAVERS (4.90%)
PEACHTREE CONSTRUCTION, LTD. ( 13.21%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.95%)
HAYWARD BAKER, INC.(0.67%)
BRENDA PRICE TRUCKING(1.44%)
Contract # 06153225
Totals 9549753.04 428086.10 1801236.27 18.8

CountyELLIS
Highway FM 984
From AT DRAW, 1.7 MI SOUTH OF SH 34
To .
CSJ 1211-01-018
Proj ID BR 2015(483)
Work Type REPL BR AND APPR
 
0.117 879623.40 20718.98 26751.71 3.0
CountyELLIS
Highway FM 984
From AT ONION CREEK RELIEF #1 AND #2
To .
CSJ 1211-01-019
Proj ID BR 2015(484)
Work Type REPL BR
 
0.156 1453823.50 165621.50 188921.50 12.9
Work Order 03-02-15
Work Began 02-25-16
Work Completed  
Time Computed 02-25-16
Contract Working Days 379
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 6
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 1211-01-018
FORTSON CONTRACTING, INC.(2.16%)
USA EROSION, INC.(3.94%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.48%)
STRIPING TECHNOLOGY, L.P.(1.23%)
Contract # 01153012
Totals 2333446.90 186340.48 215673.21 9.2

CountyKAUFMAN
Highway FM 1388
From FM 148
To US 175
CSJ 1217-03-019
Proj ID STP 2016(360)
Work Type GR, BASE, ACP OVERLAY, PVMT MKGS
 
12.030 17608683.44 0.00 805.00 0.0
CountyKAUFMAN
Highway FM 1388
From AT KINGS CREEK RELIEF #2
To .
CSJ 1217-03-020
Proj ID BR 2016(361)
Work Type REPLACE BRIDGE
 
0.495 4432389.14 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 580
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1217-03-019
ALTUS TRAFFIC MANAGEMENT LLC (0.13%)
SOUTHWEST CONSTRUCTION SERVICES(0.39%)
K & S UTILITY CONTRACTORS, INC.(9.31%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.72%)
A-CORE, INC. (0.02%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.05%)
PEACHTREE CONSTRUCTION, LTD. (4.40%)
INDUS CONSTRUCTION, L.P. (0.07%)
SOUTHERN CROSS CONTRACTORS, LLC(0.08%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(5.40%)
SYNERGY SIGNS & SERVICES, LLC(0.39%)
FARR FOUNDATION, INC.(0.56%)
FORTSON CONTRACTING, INC.(0.74%)
TRP CONSTRUCTION GROUP, LLC(0.60%)
HERDEZ TRUCKING, INC.(2.17%)
RAMBO CONTRACTING, INC.(4.73%)
Contract # 12153205
Totals 22041072.58 0.00 805.00 0.0

CountyNAVARRO
Highway FM 1126
From AT CHAMBERS CREEK, SW OF IH 45
To .
CSJ 1289-01-029
Proj ID BR 1602(046)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.890 6714487.74 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 386
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1289-01-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163237
Totals 6714487.74 0.00 0.00 0.0

CountyDENTON
Highway FM 1171
From WEST OF US 377
To WEST OF SHILOH RD
CSJ 1311-01-034
Proj ID C 1311-1-34
Work Type GR, STRS, BASE, CRCP, PVMT MKGS, SIGNS
 
7.011 45721253.16 1659173.16 36963999.41 80.8
Work Order 06-05-13
Work Began 06-02-14
Work Completed  
Time Computed 03-02-14
Contract Working Days 693
Addl Days Granted 0
Working Days Charged 453
Percent Time Used 65
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1311-01-034
BREDA COMPANY, INC.(0.96%)
BUYERS BARRICADES, INC.(0.20%)
CINTEREX US, INC.(1.17%)
CLLA GROUP, LLC(9.39%)
DUSTROL, INC.(0.30%)
INTEGRATED ROADWAY SERVICES, INC.(2.34%)
JAGOE-PUBLIC COMPANY ( 14.10%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.74%)
THELIN RECYCLING COMPANY, L.P. (0.16%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.10%)
W.O.E. CONSTRUCTION(0.28%)
WYLIE DRILLING & DRAINAGE, INC.(0.83%)
VENUS CONSTRUCTION (7.23%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.35%)
SLATON BROTHERS, INC.(0.58%)
CB SERVICES, INC.(0.10%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.07%)
LLOYD D. NABORS DEMOLITION LLC (0.12%)
STORM WATER MANAGEMENT, INC. (0.07%)
THE LANE CONSTRUCTION CORPORATION(0.93%)
Contract # 03133002
Totals 45721253.16 1659173.16 36963999.41 80.8

CountyDENTON
Highway FM 1171
From ON CORPS OF ENGINEERS PROPERTY
To NEAR WHITE'S BRANCH
CSJ 1311-01-053
Proj ID C 1311-1-53
Work Type TREES AND PLANTS
 
0.001 148908.50 0.00 61596.76 41.3
CountyDENTON
Highway FM 2499
From FM 2181
To HICKORY CREEK
CSJ 2681-01-022
Proj ID NH 1502(094)
Work Type LANDSCAPE DEVELOPMENT
 
1.112 299148.05 0.00 277336.91 92.7
Work Order 07-20-15
Work Began 08-04-15
Work Completed  
Time Computed 08-04-15
Contract Working Days 60
Addl Days Granted 2
Working Days Charged 34
Percent Time Used 54
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2681-01-022
ALTUS TRAFFIC MANAGEMENT LLC (0.85%)
AMAYA UTILITY(0.56%)
QUICK SET CONCRETE, INC. (5.50%)
Contract # 05153018
Totals 448056.55 0.00 338933.67 75.6

CountyDENTON
Highway FM 1385
From US 380
To APPROX. 2 MILES NORTH OF FM 428
CSJ 1315-01-025
Proj ID STP 1402(028)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
7.588 9063184.19 163479.80 5664477.02 62.4
Work Order 12-10-14
Work Began 07-10-15
Work Completed  
Time Computed 06-08-15
Contract Working Days 378
Addl Days Granted 0
Working Days Charged 186
Percent Time Used 49
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1315-01-025
ALTUS TRAFFIC MANAGEMENT LLC (0.54%)
ASHLAR CONTRACTING COMPANY (8.41%)
SAMMY SMALLWOOD COMPANY(0.61%)
STRIPING TECHNOLOGY, L.P.(1.77%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(7.84%)
W.S. CONSTRUCTION COMPANY(6.71%)
JM YANEZ CONSTRUCTION(8.03%)
Contract # 09143208
Totals 9063184.19 163479.80 5664477.02 62.4

CountyDENTON
Highway FM 423
From US 380
To 0.8 MI SOUTH OF FM 2934
CSJ 1315-02-009
Proj ID C 1315-2-9
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.488 29826069.73 504263.72 15465745.11 51.8
Work Order 12-12-13
Work Began 10-08-14
Work Completed  
Time Computed 09-08-14
Contract Working Days 603
Addl Days Granted 0
Working Days Charged 372
Percent Time Used 61
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 1315-02-009
TOTAL HIGHWAY MAINTENANCE, LLC (0.96%)
STORM WATER MANAGEMENT, INC. (0.28%)
BOWMAN ENGINEERING & CONSULTING, INC.(0.84%)
FORTSON CONTRACTING, INC.(0.09%)
IEA, INC (9.39%)
JAGOE-PUBLIC COMPANY ( 10.82%)
OSCAR ORDUNO, INC. (0.23%)
ROADWAY SOLUTIONS, INC.(4.78%)
ROBERTS TRUCKING (1.98%)
RUSSO CORPORATION(0.55%)
DUSTROL, INC.(0.49%)
W.O.E. CONSTRUCTION(4.50%)
TRANSPORT TRUST(0.96%)
RICHMOND HYDROMULCH AND SEEDING, LLC (0.27%)
Contract # 09133204
Totals 29826069.73 504263.72 15465745.11 51.8

CountyCOLLIN
Highway FM 1378
From 585 SOUTH OF WHITE ROCK CREEK
To NORTH OF WHITE ROCK CREEK
CSJ 1392-01-035
Proj ID BR 2014(872)
Work Type REPL BRIDGE
 
0.526 1788995.75 65525.51 702713.38 39.2
Work Order 10-09-14
Work Began 08-10-15
Work Completed  
Time Computed 04-07-15
Contract Working Days 300
Addl Days Granted 10
Working Days Charged 156
Percent Time Used 50
Contractor(s)
ACCELERATED CRITICAL PATH, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1392-01-035
BREDA COMPANY, INC.(0.40%)
CROSSROADS, L.P. (0.90%)
D & S ENGINEERING LABS (0.45%)
DUSTROL, INC.(2.56%)
FOUNDATION DRILLERS, INC.(0.91%)
CRAIG OLDEN, INC.(1.77%)
LINDAMOOD DEMOLITION, INC. (1.39%)
MCRYAN HAULING, INC. (1.87%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.32%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.08%)
Contract # 07143231
Totals 1788995.75 65525.51 702713.38 39.2

CountyKAUFMAN
Highway FM 1836
From FM 2515
To FM 90
CSJ 1397-01-030
Proj ID STP 2016(289)
Work Type SHLDR WDN, STR EXT, REMX, SC, PAV MRKS
 
6.905 6141935.93 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 218
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 1397-01-030
PEACHTREE CONSTRUCTION, LTD. (1.77%)
S & S BRIDGE PAINTING, INC.(4.51%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.11%)
TRP CONSTRUCTION GROUP, LLC(1.23%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.55%)
DUSTIN ALLEN, INC. (1.46%)
FARR FOUNDATION, INC.(1.51%)
K & S UTILITY CONTRACTORS, INC.(6.21%)
WITHERS CONSTRUCTION, LLC(0.63%)
ALTUS TRAFFIC MANAGEMENT LLC (0.20%)
CAMBRIDGEMOEN LLC(2.28%)
GIBSON & ASSOCIATES, INC.(1.87%)
Contract # 11153024
Totals 6141935.93 0.00 0.00 0.0

CountyKAUFMAN
Highway FM 1836
From SH 34
To 0.28 MI EAST OF CR 146
CSJ 1397-01-031
Proj ID C 1397-1-31
Work Type PROVIDE ADDITIONAL PAVED SURFACE
 
4.269 5943147.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 166
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1397-01-031
ALTUS TRAFFIC MANAGEMENT LLC (0.17%)
ODUM SERVICES, L.P.(1.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.55%)
J & M CONTRACTING, COMPANY ( 20.60%)
Contract # 01163240
Totals 5943147.30 0.00 0.00 0.0

CountyELLIS
Highway FM 55
From AT LITTLE ONION CREEK
To .
CSJ 1451-01-020
Proj ID BR 2005(274)
Work Type REPLACE BRIDGES AND APPROACHES
 
0.312 2010620.16 18707.00 142729.91 7.0
Work Order 07-24-15
Work Began 02-18-16
Work Completed  
Time Computed 11-21-15
Contract Working Days 340
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 8
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-020
TEXOP CONSTRUCTION (1.10%)
FORTSON CONTRACTING, INC.(2.27%)
SAN-ANN-CO., INC.(0.96%)
USA EROSION, INC.(4.31%)
STRIPING TECHNOLOGY, L.P.(1.50%)
Contract # 05153220
Totals 2010620.16 18707.00 142729.91 7.0

CountyELLIS
Highway FM 55
From 0.14 MILE SOUTH OF NASH HOWARD RD
To US 77
CSJ 1451-01-023
Proj ID STP 2015(655)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
5.500 4975101.65 246313.12 3237637.27 65.0
Work Order 05-15-15
Work Began 06-29-15
Work Completed  
Time Computed 06-15-15
Contract Working Days 215
Addl Days Granted 0
Working Days Charged 192
Percent Time Used 89
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-023
ALTUS TRAFFIC MANAGEMENT LLC (0.31%)
RAMBO CONTRACTING, INC.(4.29%)
BEAR CREEK CONSTRUCTION, LLC ( 14.22%)
TEXAS ALTERNATIVE GRASSER, INC.(0.62%)
STRIPING TECHNOLOGY, L.P.(0.91%)
SAN-ANN-CO., INC.(0.99%)
FORTSON CONTRACTING, INC.(1.01%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.65%)
SOUTHWEST MAINTENANCE, LTD (0.01%)
Contract # 03153011
Totals 4975101.65 246313.12 3237637.27 65.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9