Monthly State Let Construction Report For Dallas District As Of May 15, 2013 Page 5 Of 8

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyELLIS
Highway FM 66
From HILL COUNTY LINE
To FM 916
CSJ 0596-02-041
Proj ID STP 2013(450)
Work Type BASE & PVMT REPAIR, HMAC OVERLAY
 
9.649 2429911.04 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 191
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0596-02-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133006
Totals 2429911.04 0.00 0.00 0.0

CountyCOLLIN
Highway FM 6
From SH 78
To HUNT COUNTY LINE
CSJ 0619-01-022
Proj ID C 619-1-22
Work Type BASE RESTORATION & HMAC OVERLAY
 
7.888 4383589.74 0.00 3920240.90 91.6
Work Order 06-01-11
Work Began 08-05-11
Work Completed  
Time Computed 07-31-11
Contract Working Days 189
Addl Days Granted 35
Working Days Charged 344
Percent Time Used 153
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0619-01-022
SOUTHWEST ENVIRONMENT SERVICES LLC (0.48%)
DUSTY ALLEN, INC.(2.22%)
DUSTROL, INC. (ROANOKE)(4.00%)
HIGHWAY TECHNOLOGIES, INC. (2.67%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.98%)
W.S. CONSTRUCTION COMPANY( 22.65%)
Contract # 04113230
Totals 4383589.74 0.00 3920240.90 91.6

CountyKAUFMAN
Highway FM 90
From LACY FORK CREEK, UNNAMED TRIBUTARY
To TO LACY FORK CREEK, AND CANEY CREEK
CSJ 0697-04-015
Proj ID BR 2011(878)
Work Type REPL BR & APPRS
 
0.378 3447254.17 17416.00 3459238.54 99.9
Work Order 05-13-11
Work Began 10-11-11
Work Completed  
Time Computed 07-12-11
Contract Working Days 262
Addl Days Granted 47
Working Days Charged 299
Percent Time Used 96
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0697-04-015
SOUTHWEST ENVIRONMENT SERVICES LLC (0.45%)
DUSTROL, INC. (ROANOKE)(0.28%)
FORTSON CONTRACTING, INC.(1.77%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(8.43%)
HIGHWAY TECHNOLOGIES, INC. (0.62%)
HOUSTON SAWING & DRILLING(0.15%)
ATS DRILLING, L.P. (2.89%)
RG PAINTING(0.23%)
NORTH TEXAS REBAR, LLC (0.23%)
SOUTHEAST GRINDING & GROOVING, LLC (0.15%)
Contract # 04113213
Totals 3447254.17 17416.00 3459238.54 99.9

CountyDENTON
Highway FM 156
From 0.1 MI N OF FM 2450
To IH 35
CSJ 0718-01-052
Proj ID C 718-1-52
Work Type ADD 10' SHOULDERS AND REHAB
 
4.682 4152523.54 43706.06 4423907.11 99.9
Work Order 01-11-11
Work Began 04-20-11
Work Completed  
Time Computed 03-12-11
Contract Working Days 175
Addl Days Granted 35
Working Days Charged 175
Percent Time Used 83
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0718-01-052
DUSTROL, INC. (ROANOKE)(0.21%)
HJC FARMS, INC.(1.61%)
HIGHWAY TECHNOLOGIES, INC. (0.97%)
MIKE ALBERT, INC.( 23.83%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.75%)
TEXAS SHAFTS, INC. (0.66%)
J.L. STEEL REINFORCING, LLC(0.04%)
GARY A. CRAIN, INC.(0.14%)
Contract # 12103219
Totals 4152523.54 43706.06 4423907.11 99.9

CountyKAUFMAN
Highway FM 148
From FM 987
To US 175 IN CRANDALL
CSJ 0751-01-033
Proj ID C 751-1-33
Work Type HOT MIX OVERLAY, BASE AND PAV MRKS
 
7.278 8387714.05 9376.92 8487115.38 99.9
CountyKAUFMAN
Highway FM 148
From MAIN LANE AT BUFFALO CREEK
To .
CSJ 0751-01-034
Proj ID BR 2011(084)
Work Type REPLACE BR AND APPRS
 
0.051 797026.18 480.00 920806.98 99.9
Work Order 09-16-10
Work Began 11-09-10
Work Completed  
Time Computed 11-09-10
Contract Working Days 596
Addl Days Granted 42
Working Days Charged 616
Percent Time Used 96
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0751-01-034
LONE STAR EQUIPMENT CO. INC. (INACTIVE--SEE 12687) (2.51%)
COWBELL TRAFFIC SERVICES, INC. (0.27%)
ATS DRILLING, L.P. (2.60%)
BREDA COMPANY, INC.(0.41%)
RK HALL, LLC ( 13.32%)
MOORE CONSTRUCTION, INC. (1.38%)
JUST GROOVING, LTD.(0.06%)
SCOTT DERR PAINTING CO (0.02%)
HJC FARMS, INC.(2.13%)
AARON CONCRETE CONTRACTORS, L.P. (1.63%)
STOMPER DEMOLITION COMPANY, INC. (0.79%)
J & M CONTRACTING, COMPANY (9.73%)
HIGHWAY TECHNOLOGIES, INC. (0.67%)
GIBSON & ASSOCIATES, INC.(0.43%)
A BROTHERS (1.49%)
J.L. STEEL REINFORCING, LLC(0.16%)
TRADE RESOURCES, INC.(1.25%)
LINDAMOOD DEMOLITION, INC. (0.79%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.01%)
CARRUTH NURSERY IRRIGATION & LANDSCAPE, INC. (0.16%)
Contract # 08103005
Totals 9184740.23 9856.92 9407922.36 99.9

CountyELLIS
Highway FM 663
From SOUTH OF US 287
To NORTH OF US 287
CSJ 0815-08-027
Proj ID PTF 2013(451)
Work Type STR, PVMT, PVMT MKGS
 
0.568 4728943.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 161
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0815-08-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133216
Totals 4728943.55 0.00 0.00 0.0

CountyCOLLIN
Highway FM 455
From US 75 NB FRONTAGE ROAD
To SH 5
CSJ 0816-04-044
Proj ID C 816-4-44
Work Type GR, STRS, BASE, SURF, PAV, MARK
 
1.960 12399737.47 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 251
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0816-04-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133204
Totals 12399737.47 0.00 0.00 0.0

CountyCOLLIN
Highway FM 455
From DENTON COUNTY LINE
To EAST OF SH 289
CSJ 0816-04-048
Proj ID STP 2013(182)
Work Type SHLD WDN, BS REP, SEAL, LVL - UP
 
6.097 2971234.98 275055.78 876063.58 29.4
Work Order 01-11-13
Work Began 02-14-13
Work Completed  
Time Computed 02-14-13
Contract Working Days 162
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 31
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0816-04-048
DUSTROL, INC.(0.93%)
ENVIRONMENTAL STANDARDS(0.60%)
HIGHWAY TECHNOLOGIES, INC. (0.38%)
ODUM SERVICES, L.P.(2.16%)
STRIPING TECHNOLOGY, L.P.(1.47%)
TRANSPORT TRUST(2.37%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.13%)
MIKE ALBERT, INC.(1.06%)
Contract # 11123207
Totals 2971234.98 275055.78 876063.58 29.4

CountyDALLAS
Highway VA
From DISTRICTWIDE
To (ON-SYSTEM)
CSJ 0918-00-156
Proj ID STP 2010(038)
Work Type ASBESTOS ABATEMENT ON BRIDGES
 
0.001 690174.50 0.00 329930.46 47.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-06-09
Work Began 01-04-10
Work Completed  
Time Computed 10-22-09
Contract Working Days 252
Addl Days Granted 0
Working Days Charged 218
Percent Time Used 86
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-156
1 PRIORITY ENVIRONMENTAL SERVICES, INC.( 60.27%)
Contract # 09093038
Totals 690174.50 0.00 329930.46 47.8

CountyDALLAS
Highway VA
From DISTRICTWIDE
To .
CSJ 0918-00-158
Proj ID STP 2010(620)
Work Type SIGN AND SIGN STRUCTURE REPLACEMENT
 
0.001 765740.50 0.00 653654.57 85.3
Work Order 04-22-10
Work Began 07-27-10
Work Completed  
Time Computed 07-27-10
Contract Working Days 365
Addl Days Granted 180
Working Days Charged 545
Percent Time Used 100
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-158
FORTSON CONTRACTING, INC.(2.88%)
Contract # 03103011
Totals 765740.50 0.00 653654.57 85.3

CountyDALLAS
Highway VA
From DISTRICTWIDE
To .
CSJ 0918-00-160
Proj ID C 918-00-160
Work Type SIGN AND SIGN STRUCTURE REPLACEMENT
 
0.001 883958.00 29642.25 355455.20 40.2
Work Order 02-10-12
Work Began 06-19-12
Work Completed  
Time Computed 06-19-12
Contract Working Days 365
Addl Days Granted 30
Working Days Charged 145
Percent Time Used 36
Contractor(s)
TIME STRIPING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-160
GIBSON & ASSOCIATES, INC.(3.84%)
FORTSON CONTRACTING, INC.(2.27%)
LONG FOUNDATION DRILLING (0.49%)
Contract # 12113212
Totals 883958.00 29642.25 355455.20 40.2

CountyDALLAS
Highway VA
From DISTRICTWIDE
To .
CSJ 0918-00-161
Proj ID STP 2011(467)ES
Work Type TRAFFIC SIGNAL INSTALLATION
 
0.001 1255000.00 37240.25 1137545.18 90.6
Work Order 11-16-10
Work Began 03-14-11
Work Completed  
Time Computed 02-14-10
Contract Working Days 548
Addl Days Granted 0
Working Days Charged 421
Percent Time Used 76
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-161
ROADMASTER, INC. (2.73%)
Contract # 10103011
Totals 1255000.00 37240.25 1137545.18 90.6

CountyDALLAS
Highway VA
From DISTRICTWIDE
To .
CSJ 0918-00-162
Proj ID STP 2013(452)
Work Type INSTALL GUIDE SIGNS
 
0.001 336139.97 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 540
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-162
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133012
Totals 336139.97 0.00 0.00 0.0

CountyDALLAS
Highway VA
From DISTRICTWIDE
To .
CSJ 0918-00-163
Proj ID STP 1102(197)
Work Type TRAFFIC SIGNAL INSTALLATION
 
0.001 1556550.00 0.00 289630.67 18.6
Work Order 08-11-11
Work Began 03-02-12
Work Completed  
Time Computed 10-10-11
Contract Working Days 548
Addl Days Granted 0
Working Days Charged 102
Percent Time Used 18
Contractor(s)
ROADWAY SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-163
ROADMASTER, INC. (3.01%)
Contract # 07113231
Totals 1556550.00 0.00 289630.67 18.6

CountyDALLAS
Highway VA
From AT VARIOUS LOCATIONS
To IN DALLAS DISTRICT
CSJ 0918-00-172
Proj ID STP 2011(903)
Work Type SIGN REFURBISHMENT
 
0.001 348659.47 25135.12 416686.59 99.9
Work Order 04-18-11
Work Began 12-12-11
Work Completed  
Time Computed 06-17-11
Contract Working Days 365
Addl Days Granted 90
Working Days Charged 454
Percent Time Used 99
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-172
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03113014
Totals 348659.47 25135.12 416686.59 99.9

CountyDALLAS
Highway VA
From VARIOUS LOCATIONS
To IN DALLAS DISTRICT
CSJ 0918-00-186
Proj ID STP 2013(533)
Work Type NON SITE SPECIFIC SIGNAL CONTRACT
 
0.001 1598000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 345
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-186
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133224
Totals 1598000.00 0.00 0.00 0.0

CountyDALLAS
Highway VA
From VARIOUS LOCATIONS
To IN DALLAS DISTRICT
CSJ 0918-00-200
Proj ID STP 2013(534)
Work Type SIGNALIZED INTERSECTION UPGRADES
 
0.001 278458.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-200
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133208
Totals 278458.00 0.00 0.00 0.0

CountyKAUFMAN
Highway CR
From CR 310 AT MUDDY CEDAR CREEK AND
To MUDDY CEDAR CREEK TRIB
CSJ 0918-11-076
Proj ID BR 1102(516)
Work Type REPL BR & APPRS
 
0.460 1974519.71 54683.79 1465433.51 74.2
Work Order 05-01-12
Work Began 07-25-12
Work Completed  
Time Computed 07-25-12
Contract Working Days 413
Addl Days Granted 0
Working Days Charged 176
Percent Time Used 42
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0918-11-076
SOUTHWEST ENVIRONMENT SERVICES LLC (3.35%)
SAMMY G. SMALLWOOD (3.71%)
HIGHWAY TECHNOLOGIES, INC. (0.92%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.42%)
MESA ROD BUSTERS, INC. (0.27%)
Contract # 03123010
Totals 1974519.71 54683.79 1465433.51 74.2

CountyNAVARRO
Highway VA
From VARIOUS LOCATIONS ON STATE HIGHWAYS
To IN NAVARRO COUNTY
CSJ 0918-18-102
Proj ID STP 1102(028)
Work Type CURB RAMPS
 
0.002 2030182.90 0.00 1848934.15 91.3
Work Order 07-06-11
Work Began 07-20-11
Work Completed  
Time Computed 07-22-11
Contract Working Days 225
Addl Days Granted 11
Working Days Charged 242
Percent Time Used 102
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-18-102
ROAD MASTER STRIPING LLC (1.36%)
CLASSIC TEJAS CONSTRUCTION, INC. (1.28%)
HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, CORP. (0.00%)
Contract # 05113221
Totals 2030182.90 0.00 1848934.15 91.3

CountyNAVARRO
Highway CR
From CR NE 0070, 3.5 MI E OF IH 45
To CHAMBERS CREEK
CSJ 0918-18-123
Proj ID BR 2011(796)
Work Type REPL BR & APPR
 
0.320 1416000.00 82994.58 593011.56 41.8
Work Order 05-22-12
Work Began 08-21-12
Work Completed  
Time Computed 07-21-12
Contract Working Days 251
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 72
Contractor(s)
EMPIRE CIVIL CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0918-18-123
FORTSON CONTRACTING, INC.(3.13%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.58%)
NORTH TEXAS REBAR, LLC (0.97%)
SOUTHWEST ENVIRONMENT SERVICES LLC (3.52%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.51%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (5.11%)
Contract # 04123225
Totals 1416000.00 82994.58 593011.56 41.8

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8