Monthly State Let Construction Report For Dallas District As Of Sep 15, 2014 Page 5 Of 8

Last Update: Monday, September 15, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyELLIS
Highway FM 66
From AT OAK BRANCH
To .
CSJ 0596-02-038
Proj ID BR 2015(066)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.206 1798061.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 343
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0596-02-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143226
Totals 1798061.60 0.00 0.00 0.0

CountyDENTON
Highway FM 544
From FM 2281
To 0.17 MILE WEST OF JOSEY LANE
CSJ 0619-05-034
Proj ID STP 1402(111)MM
Work Type GR, STR, BASE, PVMT, SIGNS, MKGS
 
2.311 21406881.99 0.00 0.00 0.0
CountyDENTON
Highway FM 544
From AT KCS RR, E OF FM 2281
To .
CSJ 0619-05-036
Proj ID BR 2014(763)
Work Type REPL BR & APPR
 
0.060 5316292.06 0.00 0.00 0.0
CountyDENTON
Highway FM 544
From 0.17 MILES WEST OF JOSEY LN
To PARKER/DOZIER RD.
CSJ 0619-05-037
Proj ID HP 2008(733)
Work Type RECONSTRUCT EXISTING ROADWAY
 
1.136 8667784.26 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 755
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 0619-05-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143001
Totals 35390958.31 0.00 0.00 0.0

CountyKAUFMAN
Highway FM 986
From TOWN NORTH DR IN TERRELL
To CR 2326 (NEAR HUNT C/L)
CSJ 0642-05-023
Proj ID STP 2013(768)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
6.560 3869442.70 176522.26 1227602.14 31.7
Work Order 08-19-13
Work Began 10-07-13
Work Completed  
Time Computed 10-07-13
Contract Working Days 207
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 38
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0642-05-023
BAHENA CONSTRUCTION CO.,INC. ( 17.30%)
CATOCON, INC.(0.94%)
DUSTROL, INC.(1.97%)
EROSION CONTROL MANAGEMENT SERVICES(2.13%)
FARR FOUNDATION, INC.(1.26%)
PEACHTREE CONSTRUCTION, LTD. ( 23.73%)
STRIPING TECHNOLOGY, L.P.(1.34%)
ALTUS TRAFFIC MANAGEMENT LLC (0.72%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.10%)
Contract # 06133017
Totals 3869442.70 176522.26 1227602.14 31.7

CountyDENTON
Highway FM 156 ETC
From SOUTH HICKORY CREEK
To 0.1 MI NORTH OF FM 2450
CSJ 0718-01-051
Proj ID STP 2007(014)
Work Type ADD 10' SHOULDERS AND REHAB
 
10.779 7732000.00 165014.31 3915913.11 50.6
Work Order 09-26-13
Work Began 11-11-13
Work Completed  
Time Computed 10-12-13
Contract Working Days 288
Addl Days Granted 0
Working Days Charged 203
Percent Time Used 70
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0718-01-051
W.O.E. CONSTRUCTION(4.24%)
J & M CONTRACTING, COMPANY (4.78%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.95%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.52%)
TEXAS SHAFTS, INC. (1.79%)
MASTERPIECE GRINDING & GROOVING, LLC (0.05%)
HJC FARMS, INC.(0.49%)
FORTSON CONTRACTING, INC.(2.68%)
BREDA COMPANY, INC.(0.42%)
ALTUS TRAFFIC MANAGEMENT LLC (0.50%)
MCL CONTRACTING, LLC (0.09%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.11%)
Contract # 07133229
Totals 7732000.00 165014.31 3915913.11 50.6

CountyKAUFMAN
Highway FM 148
From FM 1390 SOUTH
To US 175 SOUTH
CSJ 0751-02-023
Proj ID STP 2014(660)
Work Type MILL, REPAIR, OL, STR, MRKS, SIGN
 
7.475 10805279.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 246
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0751-02-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143221
Totals 10805279.10 0.00 0.00 0.0

CountyELLIS
Highway FM 663
From SOUTH OF US 287
To NORTH OF US 287
CSJ 0815-08-027
Proj ID PTF 2013(451)
Work Type STR, PVMT, PVMT MKGS
 
0.568 4728943.55 464266.06 1510760.52 31.9
Work Order 05-16-13
Work Began 06-30-14
Work Completed  
Time Computed 06-01-13
Contract Working Days 161
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 18
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0815-08-027
TOTAL HIGHWAY MAINTENANCE, LLC (0.26%)
WYLIE DRILLING & DRAINAGE, INC.(0.75%)
USA SWPPP INSPECTIONS, INC.(1.93%)
STRIPING TECHNOLOGY, L.P.(1.20%)
SOUTHEAST GRINDING & GROOVING, LLC (0.05%)
SCOTT DERR PAINTING CO, LLC(0.20%)
MCL CONTRACTING, LLC (0.48%)
LONE STAR BARRIER SERVICES, LLC(0.83%)
INLET STRUCTURE SPECIALTIES LTD. (1.27%)
DUSTROL, INC.(0.51%)
DURABLE SPECIALTIES, INC.(5.94%)
PREMIER PAVING, LTD. ( 10.88%)
CHRISTINE"S CONCERTE SAWING & SEALING LLC(0.17%)
Contract # 03133216
Totals 4728943.55 464266.06 1510760.52 31.9

CountyDENTON
Highway FM 455
From AT BOOM CREEK
To .
CSJ 0816-02-053
Proj ID BR 2014(764)
Work Type REPLACE EXISTING BRIDGE AND APPROAC
 
1.646 3335495.22 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-09-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 193
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0816-02-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143238
Totals 3335495.22 0.00 0.00 0.0

CountyCOLLIN
Highway FM 455
From US 75 NB FRONTAGE ROAD
To SH 5
CSJ 0816-04-044
Proj ID C 816-4-44
Work Type GR, STRS, BASE, SURF, PAV, MARK
 
1.960 12399737.47 0.00 0.00 0.0
Work Order 09-03-13
Work Began 00-00-00
Work Completed  
Time Computed 03-02-14
Contract Working Days 251
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0816-04-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133204
Totals 12399737.47 0.00 0.00 0.0

CountyCOLLIN
Highway FM 455
From CR 98
To FM 3356
CSJ 0816-04-047
Proj ID STP 2014(700)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
8.080 5536032.38 331248.51 373822.71 6.7
Work Order 06-20-14
Work Began 07-09-14
Work Completed  
Time Computed 07-06-14
Contract Working Days 191
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 17
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0816-04-047
TRP CONSTRUCTION GROUP, LLC(1.04%)
ALTUS TRAFFIC MANAGEMENT LLC (0.26%)
RICE ENVIRONMENTAL SERVICES(2.95%)
W.S. CONSTRUCTION COMPANY( 10.92%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.34%)
Contract # 04143009
Totals 5536032.38 331248.51 373822.71 6.7

CountyELLIS
Highway FM 308
From HILL COUNTY LINE
To US 77
CSJ 0834-01-013
Proj ID STP 2013(953)
Work Type GR, BASE, PVMT, CULVERTS, PVMT MKGS
 
4.806 3096481.32 454172.57 1269122.60 40.9
Work Order 11-19-13
Work Began 02-03-14
Work Completed  
Time Computed 01-18-14
Contract Working Days 252
Addl Days Granted 0
Working Days Charged 158
Percent Time Used 62
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0834-01-013
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(5.13%)
STRIPING TECHNOLOGY, L.P.(1.45%)
FORTSON CONTRACTING, INC.(0.28%)
N-LINE TRAFFIC MAINTENANCE, L.P. (3.26%)
BEAR CREEK CONSTRUCTION, LLC ( 18.14%)
Contract # 08133026
Totals 3096481.32 454172.57 1269122.60 40.9

CountyDALLAS
Highway VA
From DISTRICTWIDE
To (ON-SYSTEM)
CSJ 0918-00-156
Proj ID STP 2010(038)
Work Type ASBESTOS ABATEMENT ON BRIDGES
 
0.001 690174.50 0.00 402991.07 58.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-06-09
Work Began 01-04-10
Work Completed  
Time Computed 10-22-09
Contract Working Days 252
Addl Days Granted 120
Working Days Charged 239
Percent Time Used 64
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-156
1 PRIORITY ENVIRONMENTAL SERVICES, INC.( 60.27%)
Contract # 09093038
Totals 690174.50 0.00 402991.07 58.3

CountyDALLAS
Highway VA
From DISTRICTWIDE
To .
CSJ 0918-00-160
Proj ID C 918-00-160
Work Type SIGN AND SIGN STRUCTURE REPLACEMENT
 
0.001 883958.00 0.00 876203.08 99.1
Work Order 02-10-12
Work Began 06-19-12
Work Completed  
Time Computed 06-19-12
Contract Working Days 365
Addl Days Granted 30
Working Days Charged 209
Percent Time Used 52
Contractor(s)
TIME STRIPING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-160
GIBSON & ASSOCIATES, INC.(3.84%)
FORTSON CONTRACTING, INC.(2.27%)
LONG FOUNDATION DRILLING (0.49%)
Contract # 12113212
Totals 883958.00 0.00 876203.08 99.1

CountyDALLAS
Highway VA
From DISTRICTWIDE
To .
CSJ 0918-00-162
Proj ID STP 2013(452)
Work Type INSTALL GUIDE SIGNS
 
0.001 336139.97 17134.16 206087.67 61.3
Work Order 06-12-13
Work Began 01-16-14
Work Completed  
Time Computed 09-10-13
Contract Working Days 540
Addl Days Granted 0
Working Days Charged 222
Percent Time Used 41
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-162
DYNAMIC VISION CO., INC. ( 10.24%)
MARCOM"S MOWING SERVICE, LLC (2.10%)
Contract # 03133012
Totals 336139.97 17134.16 206087.67 61.3

CountyDALLAS
Highway VA
From DISTRICTWIDE
To .
CSJ 0918-00-163
Proj ID STP 1102(197)
Work Type TRAFFIC SIGNAL INSTALLATION
 
0.001 1556550.00 46426.85 1350384.11 86.7
Work Order 08-11-11
Work Began 03-02-12
Work Completed  
Time Computed 10-10-11
Contract Working Days 548
Addl Days Granted 0
Working Days Charged 471
Percent Time Used 85
Contractor(s)
ROADWAY SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-163
ROADMASTER, INC. (3.01%)
Contract # 07113231
Totals 1556550.00 46426.85 1350384.11 86.7

CountyDALLAS
Highway VA
From VARIOUS LOCATIONS
To IN DALLAS DISTRICT
CSJ 0918-00-185
Proj ID STP 1402(027)
Work Type NON SITE SPECIFIC SIGNAL CONTRACT
 
0.001 1297700.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 346
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-185
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143248
Totals 1297700.00 0.00 0.00 0.0

CountyDALLAS
Highway VA
From VARIOUS LOCATIONS
To IN DALLAS DISTRICT
CSJ 0918-00-186
Proj ID STP 2013(533)
Work Type NON SITE SPECIFIC SIGNAL CONTRACT
 
0.001 1598000.00 0.00 175568.93 10.9
Work Order 06-28-13
Work Began 04-28-14
Work Completed  
Time Computed 09-26-13
Contract Working Days 345
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 26
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-186
DYNAMIC VISION CO., INC. (3.87%)
ROAD MASTER STRIPING LLC (3.33%)
Contract # 04133224
Totals 1598000.00 0.00 175568.93 10.9

CountyDALLAS
Highway VA
From AT VARIOUS LOCATIONS
To IN DALLAS DISTRICT
CSJ 0918-00-228
Proj ID STP 2014(390)
Work Type INSTALL GUIDE SIGNS
 
0.001 479586.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-22-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SOUTH TEXAS ILLUMINATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-228
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143228
Totals 479586.80 0.00 0.00 0.0

CountyDALLAS
Highway VA
From VARIOUS LOCATIONS
To AT DIAMOND INTERSECTIONS
CSJ 0918-00-234
Proj ID C 918-00-234
Work Type PAVEMENT MARKINGS, SIGNS, SIGNALS
 
0.001 714066.00 26796.11 91899.60 12.8
Work Order 02-18-14
Work Began 07-09-14
Work Completed  
Time Computed 04-19-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 6
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-234
STRIPE-A-ZONE, INC.(5.80%)
Contract # 01143209
Totals 714066.00 26796.11 91899.60 12.8

CountyNAVARRO
Highway CR
From CR NE 0070, 3.5 MI E OF IH 45
To CHAMBERS CREEK
CSJ 0918-18-123
Proj ID BR 2011(796)
Work Type REPL BR & APPR
 
0.320 1416000.00 0.00 1250987.46 95.6
Work Order 05-22-12
Work Began 08-21-12
Work Completed  
Time Computed 07-21-12
Contract Working Days 251
Addl Days Granted 0
Working Days Charged 403
Percent Time Used 160
Contractor(s)
EMPIRE CIVIL CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0918-18-123
FORTSON CONTRACTING, INC.(3.13%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.58%)
NORTH TEXAS REBAR, LLC (0.97%)
SOUTHWEST ENVIRONMENT SERVICES LLC (3.52%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.51%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (5.11%)
PIERCE CONSTRUCTION, INC.( 36.30%)
Contract # 04123225
Totals 1416000.00 0.00 1250987.46 95.6

CountyELLIS
Highway CR
From CARTWRIGHT RD @ BIG ONION CRK TRIB
To .
CSJ 0918-22-143
Proj ID BR 2013(502)
Work Type REPL BR & APPRS
 
0.143 602706.08 86823.08 166436.08 27.6
Work Order 05-05-14
Work Began 06-16-14
Work Completed  
Time Computed 05-21-14
Contract Working Days 123
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 41
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-22-143
EROSION CONTROL MANAGEMENT SERVICES(5.46%)
FORTSON CONTRACTING, INC.(2.46%)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(0.76%)
PEACHTREE CONSTRUCTION, LTD. (4.56%)
USA EROSION, INC.(8.47%)
WYLIE DRILLING & DRAINAGE, INC.(6.07%)
Contract # 03143208
Totals 602706.08 86823.08 166436.08 27.6

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8