Monthly State Let Construction Report For Dallas District As Of Mar 13, 2017 Page 5 Of 8

Last Update: Monday, March 13, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCOLLIN
HighwayFM 455
FromUS 75 NB FRONTAGE ROAD
ToSH 5
CSJ0816-04-044
Proj IDC 816-4-44
Work TypeGR,STRS,BASE,SURF,PAV,MARK
 
1.96012399737.4710829719.6787.5
Work Order09-03-13
Work Began08-10-15
Work Completed
Time Computed03-02-14
Contract Working Days251
Addl Days Granted42
Working Days Charged311
Percent Time Used106
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0816-04-044
TOTAL HIGHWAY MAINTENANCE, LLC (0.95)
PARKER TREE SERVICES (0.24)
W.O.E. CONSTRUCTION (0.30)
FARR FOUNDATION, INC. (0.31)
CTBX, INC. (0.10)
DURABLE SPECIALTIES, INC. (1.42)
PREMIER PAVING, LTD. (9.45)
TEXAS SHAFTS, INC. (0.40)
J.R. STEEL TIE (0.66)
LIONS GATE LOGISTICS (0.45)
C.T. AND S. METALWORKS, INC. (1.32)
DUSTROL, INC. (0.17)
ODUM SERVICES, L.P. (0.12)
Contract #03133204
Totals12399737.47174161.5110829719.6787.5

CountyCOLLIN
HighwayFM 455
From0.21 MILE WEST OF FM 3356
ToUS 75
CSJ0816-04-054
Proj IDSTP 2016(144)
Work TypeSHLD WDN, BS REP,OV, GUARD RAIL
 
5.0323866001.583459236.2089.4
Work Order01-29-16
Work Began03-01-16
Work Completed
Time Computed03-01-16
Contract Working Days188
Addl Days Granted0
Working Days Charged179
Percent Time Used95
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0816-04-054
TOTAL HIGHWAY MAINTENANCE, LLC (0.48)
STRIPING TECHNOLOGY, L.P. (1.28)
AUSTIN BRIDGE & ROAD SERVICES, LP (18.06)
MOORE CONSTRUCTION, INC. (1.31)
OLDEN, INC. (2.03)
BAHENA CONSTRUCTION CO.,INC. (11.03)
LONE STAR BARRIER SERVICES, LLC (5.22)
DUSTROL, INC. (2.99)
CKJ TRUCKING (8.73)
STRIPING SYSTEMS, INC. (0.01)
ALTUS TRAFFIC MANAGEMENT LLC (0.39)
MARCOM"S MOWING SERVICE, LLC (1.03)
DUSTIN ALLEN, INC. (3.94)
Contract #10153008
Totals3866001.582021.253459236.2089.4

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN DALLAS DISTRICT
CSJ0918-00-185
Proj IDSTP 1402(027)
Work TypeNON SITE SPECIFIC SIGNAL CONTRACT
 
0.0011297700.001236961.5295.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-28-14
Work Began07-09-15
Work Completed
Time Computed01-26-15
Contract Working Days346
Addl Days Granted0
Working Days Charged313
Percent Time Used90
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-185
DYNAMIC VISION CO., INC. (1.45)
ROAD MASTER STRIPING LLC (3.76)
Contract #08143248
Totals1297700.000.001236961.5295.3

CountyDALLAS
HighwayVA
FromAT VARIOUS LOCATIONS
To.
CSJ0918-00-187
Proj IDSTP 1602(109)
Work TypeNON SITE SPECIFIC SIGNAL CONTRACT
 
0.0011276600.00138432.4210.8
Work Order06-27-16
Work Began12-07-16
Work Completed
Time Computed09-28-16
Contract Working Days548
Addl Days Granted0
Working Days Charged58
Percent Time Used10
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-187
ROAD MASTER STRIPING LLC (4.59)
Contract #05163018
Totals1276600.003221.00138432.4210.8

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS IN DISTRICT
ToAT DIAMOND INTERCHANGES
CSJ0918-00-263
Proj IDNH 2017(084)
Work TypePAVEMENT MARKINGS,SIGNS,SIGNALS
 
0.0011785330.8712364.800.6
Work Order10-25-16
Work Began02-22-17
Work Completed
Time Computed12-24-16
Contract Working Days548
Addl Days Granted0
Working Days Charged5
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-263
TOTAL HIGHWAY MAINTENANCE, LLC (8.18)
WG ENGINEERING & CONSTRUCTION, LLC (19.16)
Contract #09163210
Totals1785330.8712364.8012364.800.6

CountyNAVARRO
HighwayCR
FromON CR SE 3040 AT CEDAR CREEK
To.
CSJ0918-18-125
Proj IDBR 2013(500)
Work TypeREPL BR & APPRS
 
0.066434362.49107861.7524.8
CountyNAVARRO
HighwayCR
FromNW CR 2310 AT RUSH CREEK
To.
CSJ0918-18-126
Proj IDBR 2013(501)
Work TypeREPL BR & APPRS
 
0.064298231.14130321.0043.6
CountyNAVARRO
HighwayCS
FromON CR SE 0120 AT RUSH CREEK
To.
CSJ0918-18-129
Proj IDBR 1602(217)
Work TypeREPL BR & APPRS
 
0.071389584.1480902.0020.7
Work Order11-15-16
Work Began01-03-17
Work Completed
Time Computed12-16-16
Contract Working Days341
Addl Days Granted0
Working Days Charged39
Percent Time Used11
Contractor(s)
PIERCE R & B LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-18-125
TOTAL HIGHWAY MAINTENANCE, LLC (1.23)
FORTSON CONTRACTING, INC. (2.25)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.41)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (5.43)
PEACHTREE CONSTRUCTION, LTD. (5.57)
PENHALL COMPANY (0.30)
DFW REBAR, INC. (0.38)
Contract #09163020
Totals1122177.77169661.75319084.7528.4

CountyELLIS
HighwayCR
FromRICHLAND BEND ROAD
ToAT RICHLAND CREEK
CSJ0918-22-086
Proj IDBR 2013(494)
Work TypeREPL BR
 
0.152934144.91850264.4893.6
Work Order06-15-15
Work Began08-10-15
Work Completed
Time Computed08-24-15
Contract Working Days129
Addl Days Granted31
Working Days Charged201
Percent Time Used125
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-22-086
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.79)
ALTUS TRAFFIC MANAGEMENT LLC (0.68)
PEACHTREE CONSTRUCTION, LTD. (3.75)
FORTSON CONTRACTING, INC. (1.87)
USA SWPPP INSPECTIONS, INC. (2.87)
JUST GROOVING, LTD. (0.26)
MCL CONTRACTING, LLC (0.27)
PENHALL COMPANY (AUSTIN) (0.30)
Contract #04153012
Totals934144.910.00850264.4893.6

CountyELLIS
HighwayCR
FromFOREST BROOK DR AT RED OAK CREEK
ToCITY OF OAK LEAF
CSJ0918-22-141
Proj IDBR 2013(598)
Work TypeREPL BR
 
0.0841038508.40572491.3355.1
Work Order03-07-16
Work Began01-03-17
Work Completed
Time Computed07-05-16
Contract Working Days82
Addl Days Granted0
Working Days Charged38
Percent Time Used46
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-22-141
PEACHTREE CONSTRUCTION, LTD. (1.71)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.07)
REALSEARCH OF TEXAS, LLC (0.57)
TOTAL HIGHWAY MAINTENANCE, LLC (0.31)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.13)
WOLFE CONSTRUCTION GROUP, INC. (0.72)
DENALI SERVICES & TRANSPORT LLC (1.85)
Contract #12153036
Totals1038508.40317973.53572491.3355.1

CountyDALLAS
HighwayCS
FromON PLEASANT RUN RD. AT BEE BRANCH
ToIN CITY OF DESOTO
CSJ0918-45-731
Proj IDBR 2006(473)
Work TypeREPL BR & APPRS
 
0.2593181746.723091247.7797.1
Work Order09-30-14
Work Began03-24-15
Work Completed
Time Computed10-16-14
Contract Working Days247
Addl Days Granted39
Working Days Charged286
Percent Time Used100
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-731
TOTAL HIGHWAY MAINTENANCE, LLC (0.45)
ACU CONSTRUCTION LLC (0.53)
TISEO PAVING CO. (11.06)
RICE ENVIRONMENTAL SERVICES (0.12)
MELS ELECTRIC, L.P. (0.36)
FORTSON CONTRACTING, INC. (0.20)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.41)
MCL CONTRACTING, LLC (0.05)
PREMIER PAVING, LTD. (4.57)
T & R EXCAVATION, INC. (5.83)
STRIPE-A-ZONE, INC. (0.81)
UNDERGROUND COALITION, INC. (3.67)
USA SWPPP INSPECTIONS, INC. (1.36)
ENVIRONMENTAL SAFETY SERVICES, INC. (5.47)
FOUNDATION DRILLERS, INC. (1.52)
FARR FOUNDATION, INC. (0.76)
DFW SERVICES, LLC (3.67)
KDAT (2.65)
VENUS CONSTRUCTION (1.32)
Contract #07143014
Totals3181746.720.003091247.7797.1

CountyDALLAS
HighwayCS
FromS MARSALIS AVE AT FIVEMILE CREEK
To.
CSJ0918-45-761
Proj IDBR 2007(306)
Work TypeREPL BR & APPRS
 
0.0772688948.212599504.4199.2
CountyDALLAS
HighwayCS
FromS MARSALIS AVE AT FIVEMILE CREEK
To.
CSJ0918-47-085
Proj IDRW 918-47-85
Work TypeADJUSTMENT OF UTILITIES
 
0.090255486.60145989.8657.1
Work Order09-22-14
Work Began03-30-15
Work Completed
Time Computed11-21-14
Contract Working Days353
Addl Days Granted0
Working Days Charged440
Percent Time Used124
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-761
ALTUS TRAFFIC MANAGEMENT LLC (0.97)
BROCK ENVIRONMENTAL, LLC (0.53)
ATS DRILLING, INC. (7.00)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (1.19)
FRAIRE"S REBAR, INC (8.53)
STRIPE-A-ZONE, INC. (0.16)
ACTION SERVICES (0.29)
FORTSON CONTRACTING, INC. (0.26)
IOWA BRIDGE & CULVERT, LC (0.33)
METRO CUTTING AND SEALING, INC. (0.20)
DUSTROL, INC. (0.30)
J & M MANHOLE CONSTRUCTION (0.30)
RICE TUNNELING & BORING, INC. (0.25)
MAGNUM MANHOLE & UNDERGROUND COMPANY (0.36)
CLEMONS TRUCKING (1.23)
FOUNDATION DRILLERS, INC. (1.17)
K & A STEEL, LLC (1.73)
XIT PAVING AND CONSTRUCTION INC. (1.11)
F & K BUILDERS (4.45)
TOTAL HIGHWAY MAINTENANCE, LLC (0.72)
S & W FOUNDATION CONTRACTORS, INC. (4.75)
Contract #06143014
Totals2944434.8171884.632745494.2795.5

CountyDALLAS
HighwayCS
FromRED OAK RD AT TEN MILE CREEK
ToIN THE CITY OF LANCASTER
CSJ0918-45-791
Proj IDBR 2013(493)
Work TypeREHAB BRIDGE AND APPROACHES
 
0.1001305085.001175071.0290.0
Work Order03-15-16
Work Began05-17-16
Work Completed
Time Computed05-17-16
Contract Working Days247
Addl Days Granted0
Working Days Charged199
Percent Time Used80
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-791
PENHALL COMPANY (0.24)
PEACHTREE CONSTRUCTION, LTD. (1.41)
S&S BRIDGE PAINTING (22.66)
ODUM SERVICES, L.P. (1.39)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.46)
ACU CONSTRUCTION LLC (1.01)
USA SWPPP INSPECTIONS, INC. (2.02)
Contract #11153230
Totals1305085.0090751.331175071.0290.0

CountyDALLAS
HighwayCS
FromON WHITLOCK RD, FROM IH 35E
ToOLD DENTON RD IN CARROLLTON
CSJ0918-45-864
Proj IDSTP 2009(860)MM
Work TypeGR, STRS & SURF
 
0.5053063573.24271983.888.8
CountyDALLAS
HighwayCS
FromON WHITLOCK RD, FROM IH 35E
ToOLD DENTON RD IN CARROLLTON
CSJ0918-47-116
Proj IDRW 918-47-116
Work TypeADJUSTMENT OF UTILITIES IN CONSTRUC
 
0.505372163.901390599.6099.9
Work Order09-11-14
Work Began10-11-16
Work Completed
Time Computed12-09-14
Contract Working Days276
Addl Days Granted0
Working Days Charged94
Percent Time Used34
Contractor(s)
TISEO PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-864
DALLAS LITE AND BARRICADE INC. (0.86)
T-BAR FENCE, INC. (0.49)
LARRETT, INC. (16.98)
AXIS CONTRACTING, INC. (8.17)
RPM XCONSTRUCTION, LLC (18.81)
BROCK ENVIRONMENTAL SERVICES, LLC (0.10)
SUPERSCAPES LANDSCAPING, INC. (4.86)
TEX OP CONSTRUCTION, LP (0.18)
STRIPE-A-ZONE, INC. (0.71)
DURABLE SPECIALTIES, INC. (3.66)
J R STEEL (1.11)
SYNERGY SIGNS & SERVICES (0.45)
METROPLEX PAVEMENT MARKINGS (0.71)
Contract #07143222
Totals3435737.14320809.951662583.4848.3

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS ON STATE HIGHWAYS
ToIN DALLAS COUNTY
CSJ0918-47-052
Proj IDSTP 1102(553)
Work TypeCONSTRUCT CURB RAMPS
 
0.0012270944.302162311.9595.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-25-14
Work Began09-02-14
Work Completed
Time Computed09-02-14
Contract Working Days244
Addl Days Granted0
Working Days Charged239
Percent Time Used97
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-052
CLASSIC TEJAS CONSTRUCTION, INC. (17.31)
ACTION SERVICES (1.21)
Contract #06143039
Totals2270944.300.002162311.9595.2

CountyDALLAS
HighwayCS
FromCEDAR HILL STATE PARK
ToNEW CLARK RD IN CITY OF CEDAR HILL
CSJ0918-47-097
Proj IDSTP 2014(156)TE
Work TypeHIKE AND BIKE TRAIL
 
1.3682766088.000.000.0
CountyDALLAS
HighwayFM 1382
FromAT CEDAR HILL STATE PARK SPINE RD
To.
CSJ1047-03-066
Proj IDC 1047-3-66
Work TypeGR, BS, ASPH PVMT, PVMT MKGS
 
0.2671257559.700.000.0
CountyDALLAS
HighwayFM 1382
FromSOUTHEAST OF WEST SPINE ROAD
ToWEST OF NEW CLARK ROAD
CSJ1047-03-068
Proj IDCM 1602(423)
Work TypeINTERSECTION IMPROVEMENTS
 
0.6001197552.400.000.0
CountyDALLAS
HighwayFM 1382
FromAT CEDAR HILL STATE PARK SPINE RD
To.
CSJ1047-03-070
Proj IDNH 1602(422)
Work TypeTRAF SIG
 
0.196827701.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-16-16
Work Began03-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-097
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (6.94)
STRIPING TECHNOLOGY, L.P. (0.87)
STRIPING SYSTEMS, INC. (0.01)
COWBOY TRUCKING (0.11)
GJ SEEDING, LLC (3.14)
UNDER CONSTRUCTION INC. (0.09)
XTREEME SAWING & SEALING, INC. (0.09)
Contract #07163040
Totals6048901.100.000.000.0

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS ON STATE HIGHWAYS
ToIN DALLAS COUNTY
CSJ0918-47-100
Proj IDNH 2015(653)
Work TypeCONSTRUCT CURB RAMPS
 
0.0013464886.463134017.9590.4
Work Order04-22-15
Work Began06-22-15
Work Completed
Time Computed05-08-15
Contract Working Days315
Addl Days Granted0
Working Days Charged259
Percent Time Used82
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-100
CLASSIC TEJAS CONSTRUCTION, INC. (10.16)
AMERICAN STRIPING COMPANY, INC. (4.17)
Contract #03153224
Totals3464886.460.003134017.9590.4

CountyDALLAS
HighwayCS
FromJEFFERSON ST AT MERRIFIELD ST
To.
CSJ0918-47-101
Proj IDSTP 1502(494)HES
Work TypeINSTALL TRAFFIC SIGNAL
 
0.100395282.15311615.6881.6
CountyDALLAS
HighwayCS
FromWESTMORELAND AT CLARENDON
To.
CSJ0918-47-103
Proj IDSTP 1502(496)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.100257625.45289731.5399.9
CountyDALLAS
HighwayCS
FromMCKINNEY AT MAPLE
To.
CSJ0918-47-110
Proj IDSTP 1502(495)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.100150048.25171676.0599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-05-15
Work Began02-29-16
Work Completed
Time Computed02-29-16
Contract Working Days140
Addl Days Granted0
Working Days Charged158
Percent Time Used112
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-101
DALLAS LITE AND BARRICADE INC. (1.43)
MABAK DIRECTIONAL DRILLING (4.36)
AUGER DRILLING, INC. (0.99)
STRIPING TECHNOLOGY, L.P. (4.76)
Contract #07153012
Totals802955.850.00773023.2697.6

CountyDALLAS
HighwayCS
FromBELT LINE ROAD AT DALLAS PKWY
To.
CSJ0918-47-120
Proj IDSTP 1602(110)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
1.0001300500.00532240.3540.9
Work Order08-08-16
Work Began11-09-16
Work Completed
Time Computed11-06-16
Contract Working Days172
Addl Days Granted0
Working Days Charged39
Percent Time Used22
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-120
ROAD MASTER STRIPING LLC (5.59)
LUZ LERMA CONSTRUCTION, INC. (15.28)
Contract #05163228
Totals1300500.0084420.68532240.3540.9

CountyNAVARRO
HighwayFM 1838
From0.939 MI N OF CR 4270
ToFM 638
CSJ0997-02-039
Proj IDSTP 2016(992)HES
Work TypeCONSTRUCT PAVED SHOULDERS
 
1.5531991914.540.000.0
CountyNAVARRO
HighwayFM 3383
FromFM 1126
ToCR 1110
CSJ3401-01-007
Proj IDSTP 2016(993)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
1.5001883297.660.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-24-17
Work Completed
Time Computed00-00-00
Contract Working Days251
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0997-02-039
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.66)
ODUM SERVICES, L.P. (0.35)
SAN-ANN-CO., INC. (0.90)
TOTAL HIGHWAY MAINTENANCE, LLC (0.57)
BEAR CREEK CONSTRUCTION, LLC (21.49)
POTTER TRUCKING (1.29)
Contract #12163029
Totals3875212.200.000.000.0

CountyCOLLIN
HighwayFM 546
FromSH 5
ToEAST OF COUNTRY LN/AIRPORT RD
CSJ1013-01-026
Proj IDC 1013-1-26
Work TypeGR, PVMT, STR, SIGNS, PVMT MKGS
 
1.72417391616.982938020.7316.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days411
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1013-01-026
SCOTT DERR PAINTING CO, LLC (0.13)
LIRA ELECTRIC (0.49)
ROYAL REBAR (0.95)
PANIOLO CONSTRUCTION SERVICES, LLC (3.60)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.18)
BROCK ENVIRONMENTAL, LLC (0.13)
LINDAMOOD DEMOLITION, INC. (0.05)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (8.87)
WYLIE DRILLING & DRAINAGE, INC. (1.41)
W.O.E. CONSTRUCTION (0.16)
ALLIANCE GEOTECHNICAL GROUP (0.28)
STRIPING TECHNOLOGY, L.P. (0.56)
Contract #05163037
Totals17391616.980.002938020.7316.8

CountyROCKWALL
HighwayFM 548
FromSH 276
ToSH 66
CSJ1014-02-041
Proj IDSTP 2016(145)
Work TypeWDN,STR,REMX,OL,PV MRKS
 
12.75113784401.358313990.1560.3
Work Order02-03-16
Work Began03-28-16
Work Completed
Time Computed03-28-16
Contract Working Days363
Addl Days Granted0
Working Days Charged246
Percent Time Used67
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1014-02-041
TEXOP CONSTRUCTION (1.79)
EROSION CONTROL MANAGEMENT SERVICES (0.48)
PREMIER PAVING, LTD. (22.61)
SCOTT PAVING, INC. (3.33)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.66)
TRP CONSTRUCTION GROUP, LLC (0.94)
DALLAS LITE AND BARRICADE INC. (0.54)
COMEN ENTERPRISE (1.34)
COWBOY TRUCKING (4.54)
FARR FOUNDATION, INC. (0.61)
Contract #10153205
Totals13784401.35843982.468313990.1560.3

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8