Monthly State Let Construction Report For Dallas District As Of May 15, 2013 Page 3 Of 8

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCOLLIN
Highway US 380
From WEST OF CR 608 IN FARMERSVILLE
To EAST OF FLOYD RD
CSJ 0135-05-025
Proj ID C 135-5-25
Work Type GR, STRS, PVT, CUL, CURB AND GTRS
 
1.307 18186687.16 1034662.86 5795563.54 31.8
Work Order 05-10-12
Work Began 11-05-12
Work Completed  
Time Computed 11-05-12
Contract Working Days 551
Addl Days Granted 0
Working Days Charged 137
Percent Time Used 24
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0135-05-025
BREDA COMPANY, INC.(0.68%)
CONCRETE CUTTING BY BOND (0.21%)
CRAIG OLDEN, INC.(1.58%)
DUSTROL, INC.(0.63%)
FORTSON CONTRACTING, INC.(0.28%)
JUST GROOVING, LTD.(0.01%)
K & S UTILITY CONTRACTORS, INC.(4.42%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(6.11%)
SCOTT DERR PAINTING CO, LLC(0.01%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.11%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.04%)
WYLIE DRILLING & DRAINAGE, INC.(7.43%)
MCL CONTRACTING, LLC (0.77%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.18%)
BRENDA PRICE TRUCKING(0.02%)
Contract # 07113204
Totals 18186687.16 1034662.86 5795563.54 31.8

CountyCOLLIN
Highway FM 3537
From SH 289
To FM 2478
CSJ 0135-12-025
Proj ID C 135-12-25
Work Type WDN GR STRS & SURF
 
4.055 23788820.89 0.00 0.00 0.0
Work Order 10-21-11
Work Began 00-00-00
Work Completed  
Time Computed 04-18-12
Contract Working Days 680
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0135-12-025
ARLINGTON PAVERS, INC. (0.43%)
CONCRETE CUTTING BY BOND (0.33%)
DALLAS LITE AND BARRICADE INC. (0.24%)
FORTSON CONTRACTING, INC.(0.39%)
INDUS CONSTRUCTION, L.P. (0.96%)
INLET STRUCTURE SPECIALTIES LTD. (5.42%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 17.27%)
ROADWAY SOLUTIONS, INC.(6.35%)
TEX OP CONSTRUCTION, LP(0.64%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.33%)
USA EROSION, INC.(1.69%)
W.O.E. CONSTRUCTION(0.65%)
Contract # 06113007
Totals 23788820.89 0.00 0.00 0.0

CountyNAVARRO
Highway SH 31
From 28TH STREET
To 15TH ST IN THE CITY OF CORSICANA
CSJ 0162-04-047
Proj ID C 162-4-47
Work Type STRM SEWERS & INLETS;REP CONC PAV;ADA
 
1.351 9138952.54 311165.77 5010049.64 54.8
Work Order 09-14-10
Work Began 07-22-11
Work Completed  
Time Computed 03-13-11
Contract Working Days 532
Addl Days Granted 73
Working Days Charged 455
Percent Time Used 75
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0162-04-047
DALLAS LITE AND BARRICADE INC. (0.51%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.98%)
ALLSTATE SIGNAL & CONSTRUCTION, LLC(0.98%)
BIG CREEK CONSTRUCTION, LTD. (8.65%)
UNDERGROUND COALITION, INC.( 12.39%)
A BROTHERS (0.97%)
RIVER CITIES SAWING, LLC (0.00%)
INDUS CONSTRUCTION, L.P. (0.49%)
W.O.E. CONSTRUCTION(0.41%)
C & C DIRECTIONAL BORING (0.07%)
INLET STRUCTURE SPECIALTIES LTD. (2.35%)
Contract # 08103003
Totals 9138952.54 311165.77 5010049.64 54.8

CountyNAVARRO
Highway IH 45
From FREESTONE COUNTY LINE
To CR 507
CSJ 0166-01-047
Proj ID IM 0453(133)
Work Type EDGE RP, BS REP, LEV - UP OV
 
3.377 2218764.93 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 124
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0166-01-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133021
Totals 2218764.93 0.00 0.00 0.0

CountyELLIS
Highway US 287
From JOHNSON C/L
To BU 287Q (OLD FT. WORTH HWY)
CSJ 0172-04-042
Proj ID NH 2012(631)
Work Type ACP OVERLAY AND PAVEMENT MARKINGS
 
14.992 4420536.84 10670.00 5005524.31 100.0
Work Order 07-16-12
Work Began 10-15-12
Work Completed 04-12-13
Time Computed 09-14-12
Contract Working Days 73
Addl Days Granted 11
Working Days Charged 97
Percent Time Used 115
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0172-04-042
TOTAL HIGHWAY MAINTENANCE, LLC (2.83%)
HIGHWAY TECHNOLOGIES, INC. (0.18%)
Contract # 06123224
Totals 4420536.84 10670.00 5005524.31 100.0

CountyELLIS
Highway US 287
From SARDIS
To PARKS SCHOOL HOUSE ROAD
CSJ 0172-05-108
Proj ID NH 2012(395)
Work Type REPAIR AND OVERLAY
 
7.301 5279326.58 20125.00 4839505.04 91.6
Work Order 06-04-12
Work Began 08-02-12
Work Completed  
Time Computed 08-02-12
Contract Working Days 83
Addl Days Granted 8
Working Days Charged 91
Percent Time Used 100
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0172-05-108
HIGHWAY TECHNOLOGIES, INC. (0.12%)
DUSTROL, INC.(0.34%)
STRIPING TECHNOLOGY, L.P.(1.72%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(0.07%)
FORTSON CONTRACTING, INC.(0.68%)
BRENDA PRICE TRUCKING(2.27%)
Contract # 03123205
Totals 5279326.58 20125.00 4839505.04 91.6

CountyELLIS
Highway US 287
From BUS US 287 IN ENNIS
To SOUTH OF SH 34
CSJ 0172-08-050
Proj ID DMO 2005(474)
Work Type WIDENING OF A NON - FREEWAY FACILITY
 
3.181 34561014.77 600992.26 31142626.99 90.2
CountyELLIS
Highway US 287
From BUS US 287 IN ENNIS
To SOUTH OF SH 34
CSJ 0172-08-054
Proj ID RW 172-8-54
Work Type ROW ACQ., AND UTL. ADJ.
 
2.797 93744.00 0.00 93658.00 99.9
Work Order 01-07-10
Work Began 03-09-10
Work Completed  
Time Computed 03-09-10
Contract Working Days 563
Addl Days Granted 195
Working Days Charged 780
Percent Time Used 102
Contractor(s)
SAFECO INSURANCE COMPANIES
SUBCONTRACTOR(S) FOR CCSJ: 0172-08-050
COWTOWN TRAFFIC CONTROL, INC.(0.04%)
FORTSON CONTRACTING, INC.(0.42%)
MURRAY CONSTRUCTION(0.19%)
GIBSON & ASSOCIATES, INC.(0.03%)
SCOTT DERR PAINTING CO (0.06%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.38%)
AK MILLING, LLC(0.46%)
WEBBER BARRIER SERVICES, INC.(0.61%)
F & W ELECTRICAL CONTRACTORS, INC. (0.65%)
JAMES CONSTRUCTION GROUP, L.L.C. ( 10.21%)
JAG TRUCKING INC (6.20%)
SAR TRANSPORTATION, LLC(2.64%)
S & S TRUCKING (0.17%)
APAC-TEXAS, INC. ( 25.44%)
V. FERNANDEZ TRUCKING, INC.(0.43%)
EAGLE AGGREGATE TRANSPORTATION, LLC. (1.00%)
ALLIED FENCE COMPANY (0.04%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.00%)
GREAT WESTERN ERECTORS (0.05%)
WEBBER BARRIER SERVICES, INC.(0.32%)
WYLIE DRILLING & DRAINAGE, INC.(0.76%)
RIVER CITIES SAWING LLC(0.02%)
SCOTT DERR PAINTING CO (0.01%)
J.L. STEEL REINFORCING, LLC(0.19%)
METRO CUTTING AND SEALING, INC.(0.00%)
CIRCLE H CONTRACTORS, L.P. (0.05%)
COWBOY CORING CORPORATION(0.00%)
GEORGETOWN GRASS AND LAWN COMPANY, INC.(0.02%)
LINDSEY CONTRACTORS, INC.(0.17%)
EXTREME ENVIRONMENTAL SERVICES (0.00%)
ANDERSON COLUMBIA CO., INC.( 63.13%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.94%)
RANGER EXCAVATING, L.P.(4.12%)
DUSTROL, INC.(0.09%)
BRENDA PRICE TRUCKING(1.68%)
EMPIRE CIVIL CONSTRUCTION, L.L.C.(9.74%)
BIG CREEK CONSTRUCTION, LTD. ( 16.41%)
UNDERGROUND COALITION, INC.(2.26%)
ECO-REBAR CO (0.02%)
NORTH TEXAS REBAR, LLC (0.07%)
CLAYCON CONSTRUCTION, LLC(1.22%)
MP GRINDING & GROOVING, LLC(0.02%)
MTM EXCAVATION (0.06%)
Contract # 10093001
Totals 34654758.77 600992.26 31236284.99 90.3

CountyKAUFMAN
Highway SH 34
From AIRPORT RD
To HIGH ST IN TERRELL
CSJ 0173-04-024
Proj ID RW 173-4-24
Work Type ACQUISITION OF ROW
 
0.303 663290.10 0.00 572679.35 86.3
CountyKAUFMAN
Highway SH 34
From AIRPORT RD
To HIGH ST. IN TERRELL
CSJ 0173-04-025
Proj ID STP 2011(798)
Work Type GR, PVMT, & GRADE SEP RR O / P
 
1.032 14656545.90 921157.74 12351581.92 84.2
Work Order 06-14-11
Work Began 10-04-11
Work Completed  
Time Computed 09-12-11
Contract Working Days 440
Addl Days Granted 2
Working Days Charged 388
Percent Time Used 87
Contractor(s)
AUI CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0173-04-025
DUSTROL, INC.(0.51%)
HAYWARD BAKER, INC.(1.49%)
INLET STRUCTURE SPECIALTIES LTD. (3.97%)
NORTH TEXAS REBAR, LLC (7.18%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(6.66%)
SCOTT DERR PAINTING CO (0.90%)
STORM WATER MANAGEMENT, INC. (0.68%)
T-BAR FENCE, INC.(0.48%)
TEXAS SHAFTS, INC. (1.11%)
DURABLE SPECIALTIES, INC.(2.31%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.86%)
THELIN RECYCLING CO., LLC(0.23%)
TRAC-WORK, INC.(1.46%)
CROSSROADS, L.P. (0.26%)
MCALLISTER"S LANDSCAPE MANAGEMENT(0.67%)
RIVER CITIES SAWING, LLC (0.29%)
RAIL LABOR PROVIDERS (0.05%)
STRAIGHT LINE SAWING & SEALING (0.19%)
EL CALA CONSTRUCTION LLC (2.11%)
Contract # 03113211
Totals 15319836.00 921157.74 12924261.27 84.3

CountyKAUFMAN
Highway SH 34
From US 80
To N. FRANCES STREET IN TERRELL
CSJ 0173-05-032
Proj ID STP 2013(665)
Work Type HOT MIX OVLY, BASE, BLADE, PAV MARKS
 
0.977 1979270.82 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 152
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0173-05-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133023
Totals 1979270.82 0.00 0.00 0.0

CountyDENTON
Highway IH 35 ETC
From US 77
To COOKE COUNTY LINE; FRONTAGE ROADS
CSJ 0195-02-067
Proj ID IM 0356(437)
Work Type SEAL COAT, PVMT MKGS, & MAILBOXES
 
172.893 10957185.08 694411.80 1845105.99 16.8
Work Order 11-09-12
Work Began 02-26-13
Work Completed  
Time Computed 02-02-13
Contract Working Days 189
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 25
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0195-02-067
SOUTHWEST ENVIRONMENT SERVICES, INC. (0.10%)
STRIPE-A-ZONE, INC.( 18.82%)
Contract # 10123215
Totals 10957185.08 694411.80 1845105.99 16.8

CountyDENTON
Highway IH 35E
From 0.2 MILES SOUTH OF EAGLE POINT RD
To 0.04 MILES NORTH OF EAGLE POINT RD
CSJ 0196-02-122
Proj ID IM 0356(439)
Work Type INSTALL SAFETY LIGHTING
 
1.016 158400.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-03-13
Work Began 04-29-13
Work Completed  
Time Computed 04-29-13
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ROADWAY SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0196-02-122
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133209
Totals 158400.00 0.00 0.00 0.0

CountyDALLAS
Highway IH 35E
From COMMERCE ST
To OAKLAWN AVE
CSJ 0196-03-257
Proj ID IM 0356(436)
Work Type FULL DEPTH REPAIR
 
1.566 402995.80 0.00 230128.83 57.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-18-12
Work Began 11-12-12
Work Completed  
Time Computed 11-12-12
Contract Working Days 41
Addl Days Granted 5
Working Days Charged 22
Percent Time Used 47
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0196-03-257
HIGHWAY TECHNOLOGIES, INC. (0.63%)
ARTEX ELECTRIC, INC. (2.13%)
PENHALL COMPANY(2.14%)
J. MUNOZ TRUCKING(3.47%)
Contract # 09123026
Totals 402995.80 0.00 230128.83 57.1

CountyDALLAS
Highway IH 35E
From VALLEY VIEW LANE
To WHITLOCK LN/SANDY LAKE ROAD
CSJ 0196-03-259
Proj ID IM 0356(435)
Work Type FULL DEP REP AND OV
 
3.390 1743690.74 67612.85 67612.85 3.8
Work Order 12-12-12
Work Began 04-08-13
Work Completed  
Time Computed 02-10-13
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 32
Contractor(s)
TEXAS HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0196-03-259
TOTAL HIGHWAY MAINTENANCE, LLC (4.97%)
DUSTROL, INC.(4.56%)
COWBOY TRUCKING(5.07%)
PEACHTREE CONSTRUCTION, LTD. ( 64.98%)
BUYERS BARRICADES, INC.(0.96%)
TEX OP CONSTRUCTION, LP(1.80%)
A BROTHERS MILLING, LLC(3.68%)
W.O.E. CONSTRUCTION(0.29%)
Contract # 10123229
Totals 1743690.74 67612.85 67612.85 3.8

CountyDALLAS
Highway SH 352
From ASH LN.
To SPRING AVE.
CSJ 0197-01-011
Proj ID NH 2013(096)
Work Type FULL DEPTH CONCRETE PAVEMENT REPAIR
 
2.134 170413.86 52822.57 80103.22 100.0
Work Order 11-09-12
Work Began 03-13-13
Work Completed 05-06-13
Time Computed 01-08-13
Contract Working Days 26
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 100
Contractor(s)
TEXAS HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0197-01-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10123010
Totals 170413.86 52822.57 80103.22 100.0

CountyDALLAS
Highway US 175
From LAKE JUNE ROAD
To IH 20
CSJ 0197-02-106
Proj ID NH 2013(317)
Work Type FDR, ACP OVERLAY AND PVMNT MARKING
 
5.198 2490572.71 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-26-13
Work Began 04-30-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 166
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0197-02-106
STRAIGHT LINE SAWING & SEALING (2.27%)
BRENDA PRICE TRUCKING(3.21%)
HIGHWAY TECHNOLOGIES, INC. (0.58%)
DUSTROL, INC.(5.81%)
APAC-TEXAS, INC. ( 28.53%)
DURABLE SPECIALTIES, INC.(0.39%)
ENVIRONMENTAL STANDARDS, INC.(0.20%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.89%)
Contract # 01133215
Totals 2490572.71 0.00 0.00 0.0

CountyKAUFMAN
Highway US 175
From AT SH 243
To .
CSJ 0197-04-076
Proj ID NH 1102(089)
Work Type LANDSCAPE DEVELOPMENT
 
4.866 153652.45 0.00 156318.70 99.9
Work Order 07-22-11
Work Began 10-13-11
Work Completed  
Time Computed 08-07-11
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 92
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0197-04-076
TX DOWN UNDER CONSTRUCTION LLC (3.35%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.95%)
CEN-TEX IRRIGATION SYSTEMS ( 27.33%)
Contract # 06113012
Totals 153652.45 0.00 156318.70 99.9

CountyELLIS
Highway US 67
From AT RAILPORT PARKWAY
To .
CSJ 0260-02-038
Proj ID PTF 2011(809)
Work Type GRADING, BASE, ACP PVMNT, STRUCTURES
 
1.459 8811943.85 677771.87 7285581.56 82.6
Work Order 04-05-11
Work Began 04-22-11
Work Completed  
Time Computed 04-22-11
Contract Working Days 303
Addl Days Granted 243
Working Days Charged 517
Percent Time Used 94
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0260-02-038
STRIPING TECHNOLOGY, L.P.(0.69%)
RAMBO CONTRACTING, INC.(2.21%)
RICE ENVIRONMENTAL SERVICES(0.94%)
HIGHWAY TECHNOLOGIES, INC. (0.21%)
BUILDER SERVICES CO. (0.59%)
FORTSON CONTRACTING, INC.(0.71%)
MELS ELECTRIC, L.P.(0.45%)
J. T. LANSFORD & SONS, INC.(0.34%)
BAKER BRIDGE, L.P. ( 16.29%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.30%)
GARY A. CRAIN, INC.(0.23%)
ENVIRONMENTAL STANDARDS, INC.(0.14%)
SAN-ANN-CO., INC.(0.24%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.12%)
PENHALL COMPANY(0.06%)
TEX OP CONSTRUCTION, LP(0.10%)
DUSTROL, INC.(0.20%)
REBCON, INC. ( 10.24%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.24%)
A R DANIEL CONSTRUCTION SERVICES, INC. (0.39%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.11%)
WEST TEXAS REBAR PLACERS INC.(0.25%)
WEBBER BARRIER SERVICES, LLC.(0.58%)
Contract # 02113005
Totals 8811943.85 677771.87 7285581.56 82.6

CountyELLIS
Highway US 67
From OVERLOOK DRIVE
To EIGHTH ST
CSJ 0261-01-037
Proj ID C 261-1-37
Work Type CONSTRUCT NEW FRONTAGE ROADS
 
0.585 8956100.80 653709.85 3036541.62 33.9
Work Order 08-20-12
Work Began 10-29-12
Work Completed  
Time Computed 10-19-12
Contract Working Days 367
Addl Days Granted 0
Working Days Charged 133
Percent Time Used 36
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0261-01-037
J.L. STEEL REINFORCING, LLC(0.56%)
COWTOWN TRAFFIC CONTROL, INC.(0.15%)
FORTSON CONTRACTING, INC.(0.63%)
HOUSTON SAWING & DRILLING(0.09%)
TEX OP CONSTRUCTION, LP(0.16%)
SCOTT DERR PAINTING CO (0.14%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.77%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 10.35%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.84%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.44%)
FARR FOUNDATION, INC.(3.98%)
PANTHER CREEK TRANSPORTATION, INC. (1.30%)
NORTH TEXAS REBAR, LLC (0.14%)
Contract # 06123005
Totals 8956100.80 653709.85 3036541.62 33.9

CountyDALLAS
Highway US 67
From ELLIS COUNTY LINE
To WHEATLAND RD
CSJ 0261-02-072
Proj ID NH 2013(098)
Work Type FDRCP AND HMAC OVERLAY
 
8.823 541244.57 0.00 31197.30 5.7
Work Order 11-09-12
Work Began 12-04-12
Work Completed  
Time Computed 11-25-12
Contract Working Days 61
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 6
Contractor(s)
TEXAS HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0261-02-072
PEACHTREE CONSTRUCTION, LTD. ( 34.91%)
W.O.E. CONSTRUCTION(2.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.08%)
COWBOY TRUCKING(0.00%)
XTREEME SAWING & SEALING, INC. (0.49%)
Contract # 10123016
Totals 541244.57 0.00 31197.30 5.7

CountyDALLAS
Highway US 67
From NORTH OF IH 20
To SOUTH OF RED BIRD LN
CSJ 0261-03-053
Proj ID NH 2011(346)
Work Type SUBGRADE, ACP BASE, CONC PAV STR
 
0.994 3685288.00 0.00 3356904.11 92.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-20-10
Work Began 02-14-11
Work Completed  
Time Computed 11-05-10
Contract Working Days 172
Addl Days Granted 0
Working Days Charged 244
Percent Time Used 141
Contractor(s)
ARK CONTRACTING SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0261-03-053
BUYER BARRICADES (1.22%)
MCMAHON CONTRACTING, L.P.( 13.34%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.41%)
ANDREWS PAVING & CONSTRUCTION(8.00%)
BROCK ENVIRONMENTAL, LLC (0.32%)
S & V CONSTRUCTION LLC (3.75%)
SUPREME SAWING AND SEALING (0.09%)
D.E.E.R. TRUCKING, LLC (1.26%)
SCIENTIFIC CONSTRUCTION GROUP, INC.(1.13%)
WYLIE DRILLING & DRAINAGE, INC.(0.91%)
J-N CONSTRUCTION COMPANY, INC. (7.89%)
J. LIFESTYLES(0.10%)
HIGHWAY TECHNOLOGIES, INC. (1.00%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.83%)
CONCRETE PENETRATING CO. (0.28%)
TEXAS UTI, LLC (0.04%)
WEBBER BARRIER SERVICES, INC.(1.06%)
FORTSON CONTRACTING, INC.(0.81%)
DUSTROL, INC.(0.20%)
AUGER DRILLING, INC. (0.13%)
J.L. STEEL REINFORCING, LLC(0.01%)
MICA CORPORATION (0.65%)
Contract # 08103034
Totals 3685288.00 0.00 3356904.11 92.6

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8