| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | KAUFMAN |
| Highway |
SH 34 |
| From |
HIGH ST. |
| To |
NORTH OF CR 319 IN TERRELL |
| CSJ |
0173-05-018 |
| Proj ID |
C 173-5-18 |
| Work Type |
GR STRS & SURF ADDL LANES |
| |
|
2.547 |
16491000.91 |
253124.02 |
15718524.44 |
99.2 |
| Work Order |
05-19-06 |
| Work Began |
08-21-06 |
| Work Completed |
|
| Time Computed |
06-04-06 |
| Contract Working Days |
501 |
| Addl Days Granted |
123 |
| Working Days Charged |
577 |
| Percent Time Used |
92 |
| Contractor(s) |
| AUSTIN BRIDGE & ROAD, LP |
SUBCONTRACTOR(S) FOR CCSJ: 0173-05-018 BROWN'S CONSTRUCTION CO. (0.91%) CAPROCK SPECIALITY CONTRACTORS (0.52%) DUSTROL, INC.(0.04%) FORTSON CONTRACTING, INC.(0.10%) FOUNDATION DRILLERS, INC.(5.25%) K & S UTILITY CONTRACTORS, INC.(6.51%) NORTH TEXAS BOMANITE, INC. (0.69%) STRIPE-A-ZONE, INC.(0.50%) TEXAS ENVIRONMENTAL MANAGEMENT, INC(2.17%) T. J. LAMBRECHT CONSTRUCTION, INC. (7.72%) J.L. STEEL, L.P. (1.34%) SCOTT DERR PAINTING CO (0.17%) RAMBO CONTRACTING, INC.(2.34%)
|
| Contract # |
04063017 |
|
Totals |
16491000.91 |
253124.02 |
15718524.44 |
99.2 |
|
| County | DENTON |
| Highway |
IH 35E |
| From |
DALLAS COUNTY LINE |
| To |
N ABUTMENT OF ELM FORK BRIDGE |
| CSJ |
0196-02-116 |
| Proj ID |
IM 0356(408) |
| Work Type |
PLANE, OVERLAY, PAVEMENT MARKING |
| |
|
0.637 |
314871.97 |
335296.74 |
335296.74 |
99.9 |
| Work Order |
08-19-08 |
| Work Began |
10-28-08 |
| Work Completed |
|
| Time Computed |
09-04-08 |
| Contract Working Days |
27 |
| Addl Days Granted |
0 |
| Working Days Charged |
23 |
| Percent Time Used |
85 |
| Contractor(s) |
| AUSTIN BRIDGE & ROAD, LP |
SUBCONTRACTOR(S) FOR CCSJ: 0196-02-116 CROSSROADS, L.P. (1.16%) DUSTROL, INC. (ROANOKE)(8.99%) TEXAS HIGHWAY MARKINGS, LLC(5.09%)
|
| Contract # |
07083224 |
|
Totals |
314871.97 |
335296.74 |
335296.74 |
99.9 |
|
| County | DALLAS |
| Highway |
IH 35E |
| From |
AT SH 183 |
| To |
. |
| CSJ |
0196-03-241 |
| Proj ID |
C 196-3-241 |
| Work Type |
SIGN BRIDGE INSTALLATION |
| |
|
0.002 |
168467.10 |
82021.54 |
248232.84 |
99.9 |
| Work Order |
08-14-06 |
| Work Began |
08-19-08 |
| Work Completed |
|
| Time Computed |
02-10-07 |
| Contract Working Days |
36 |
| Addl Days Granted |
36 |
| Working Days Charged |
56 |
| Percent Time Used |
77 |
| Contractor(s) |
| J & V COMMUNICATION SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0196-03-241 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07063043 |
|
Totals |
168467.10 |
82021.54 |
248232.84 |
99.9 |
|
| County | DALLAS |
| Highway |
IH 35E |
| From |
IH 635 |
| To |
PGBT |
| CSJ |
0196-03-244 |
| Proj ID |
CM 2007(609) |
| Work Type |
DEPLOYMENT OF ITS |
| |
|
5.470 |
2567697.99 |
0.00 |
2386748.37 |
92.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
07-24-07 |
| Work Began |
10-24-07 |
| Work Completed |
|
| Time Computed |
09-22-07 |
| Contract Working Days |
240 |
| Addl Days Granted |
0 |
| Working Days Charged |
239 |
| Percent Time Used |
99 |
| Contractor(s) |
| MICA CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 0196-03-244 TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.66%) LAYFIELD CONSTRUCTION, INC (0.26%)
|
| Contract # |
06073007 |
|
Totals |
2567697.99 |
0.00 |
2386748.37 |
92.9 |
|
| County | DALLAS |
| Highway |
IH 35E |
| From |
IH 635 |
| To |
NORTH OF FARMERS BRANCH CITY LIMITS |
| CSJ |
0196-03-251 |
| Proj ID |
IM 0356(410) |
| Work Type |
ILLUMINATION REFURBISHING |
| |
|
2.200 |
209000.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
09-19-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
56 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ROADWAY SOLUTIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0196-03-251 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08083013 |
|
Totals |
209000.00 |
0.00 |
0.00 |
0.0 |
|
| County | DALLAS |
| Highway |
IH 35E |
| From |
INTERSECTIONS OF EMPIRE CENTRAL, |
| To |
COMMONWEALTH, AND OAK LAWN |
| CSJ |
0196-03-252 |
| Proj ID |
IM 0356(411) |
| Work Type |
UPGRADE TRAFFIC SIGNALS |
| |
|
0.002 |
1117000.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
240 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| DURABLE SPECIALTIES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0196-03-252 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12083210 |
|
Totals |
1117000.00 |
0.00 |
0.00 |
0.0 |
|
| County | DALLAS |
| Highway |
LP 354 |
| From |
IN DALLAS ON HARRY HINES BOULEVARD |
| To |
FROM ROYAL LANE TO IH 35E |
| CSJ |
0196-06-017 |
| Proj ID |
STP 2006(385)MM |
| Work Type |
RECONSTRUCT, GRADING, BASE, PAVING |
| |
|
1.398 |
21020242.40 |
98824.08 |
19645331.18 |
97.3 |
| Work Order |
05-01-06 |
| Work Began |
06-26-06 |
| Work Completed |
|
| Time Computed |
05-17-06 |
| Contract Working Days |
488 |
| Addl Days Granted |
65 |
| Working Days Charged |
537 |
| Percent Time Used |
97 |
| Contractor(s) |
| TEXAS STERLING CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0196-06-017 REYNOLDS ASPHALT & CONSTRUCTION COMPANY(4.71%) STRIPE-A-ZONE, INC.(0.54%) CEN-TEX SEEDING, INC.(0.94%) MAGNUM TUNNELING, LLC( 12.38%) BUYER BARRICADES (0.50%) HUERTA'S TRUCKING, INC.(4.23%) I & H CONCRETE CUTTING, INC. (0.09%) ROADWAY SOLUTIONS, INC.(1.72%) INLET STRUCTURE SPECIALTIES LTD. (1.31%) BREDA COMPANY, INC.(0.22%) AXIS CONTRACTING, INC. (2.20%)
|
| Contract # |
03063002 |
|
Totals |
21020242.40 |
98824.08 |
19645331.18 |
97.3 |
|
| County | DALLAS |
| Highway |
SP 366 |
| From |
IH 35E |
| To |
GULDEN/AMONETTE STREET |
| CSJ |
0196-07-018 |
| Proj ID |
IMD 35E-6(374) |
| Work Type |
GR, STRS & SURF |
| |
|
0.658 |
47458273.81 |
2310000.12 |
2751062.99 |
5.7 |
| Work Order |
08-21-08 |
| Work Began |
10-13-08 |
| Work Completed |
|
| Time Computed |
09-06-08 |
| Contract Working Days |
622 |
| Addl Days Granted |
0 |
| Working Days Charged |
27 |
| Percent Time Used |
4 |
| Contractor(s) |
| J.D. ABRAMS, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0196-07-018 STAR OPERATIONS, INC.(2.18%) ODUM SERVICES, L.P.(0.51%) REYNOLDS ASPHALT & CONSTRUCTION COMPANY(2.61%) MIKE ALBERT, INC.(3.08%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.35%) WEIR BROS., INC. (3.36%) ATS DRILLING, L.P. (5.48%) GREAT WESTERN ERECTORS (0.89%) TEX OP CONSTRUCTION, LP(0.27%) HIGHWAY TECHNOLOGIES, L.P. (0.25%) L & E HART ENTERPRISES, INC. (0.36%) STRIPE-A-ZONE, INC.(0.20%) PRIMATE CONSTRUCTION, INC. (0.17%) RAYMOND PAINTING, INC. (0.62%) CHOCTAW ERECTORS, INC. (1.34%) J.L. STEEL, L.P. (0.23%)
|
| Contract # |
06083216 |
|
Totals |
47458273.81 |
2310000.12 |
2751062.99 |
5.7 |
|
| County | DALLAS |
| Highway |
SP 366 |
| From |
IH 35E |
| To |
US 75 |
| CSJ |
0196-07-025 |
| Proj ID |
CM 2007(673) |
| Work Type |
ATMS |
| |
|
1.460 |
649624.75 |
0.00 |
590105.27 |
90.8 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
08-06-07 |
| Work Began |
11-26-07 |
| Work Completed |
|
| Time Computed |
11-26-07 |
| Contract Working Days |
80 |
| Addl Days Granted |
0 |
| Working Days Charged |
79 |
| Percent Time Used |
98 |
| Contractor(s) |
| MICA CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 0196-07-025 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07073212 |
|
Totals |
649624.75 |
0.00 |
590105.27 |
90.8 |
|
| County | DALLAS |
| Highway |
SP 366 |
| From |
AT TRINITY RIVER, WEST RIVER LEVEE |
| To |
EAST TRINITY RIVER LEVEE |
| CSJ |
0196-07-026 |
| Proj ID |
STP 2006(438)MM |
| Work Type |
STRS, & SURF |
| |
|
0.366 |
69674804.25 |
85950.00 |
21418370.28 |
30.7 |
| Work Order |
01-31-07 |
| Work Began |
06-14-07 |
| Work Completed |
|
| Time Computed |
05-31-07 |
| Contract Working Days |
695 |
| Addl Days Granted |
28 |
| Working Days Charged |
370 |
| Percent Time Used |
51 |
| Contractor(s) |
| WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0196-07-026 SCOTT DERR PAINTING CO (0.08%) TREVCON, INC.(2.17%) ODUM SERVICES, L.P.(0.01%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.07%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09%) INDUS CONSTRUCTION, L.P. (2.81%) COSTRUZIONI CIMOLAI ARMANDO S.P.A. ( 20.84%) MICA CORPORATION (4.42%) VFC, INC (0.10%) LAYFIELD CONSTRUCTION, INC (0.35%)
|
| Contract # |
10063031 |
|
Totals |
69674804.25 |
85950.00 |
21418370.28 |
30.7 |
|
| County | KAUFMAN |
| Highway |
US 175 |
| From |
500 FT. WEST OF KINGS CREEK TRIB |
| To |
SH 243 ENTRANCE RAMP |
| CSJ |
0197-04-067 |
| Proj ID |
STP 2007(795)HES |
| Work Type |
UPGRADE EXISTING FREEWAY FACILITY |
| |
|
0.381 |
1580860.33 |
23750.24 |
1161669.88 |
73.4 |
| Work Order |
01-03-08 |
| Work Began |
01-28-08 |
| Work Completed |
|
| Time Computed |
01-19-08 |
| Contract Working Days |
275 |
| Addl Days Granted |
5 |
| Working Days Charged |
210 |
| Percent Time Used |
75 |
| Contractor(s) |
| J-W PAYNE CONSTRUCTION COMPANY, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0197-04-067 DUSTROL, INC. (ROANOKE)(1.47%) STRIPING TECHNOLOGY, L.P.(2.43%) ODUM SERVICES, L.P.(2.88%) PEACHTREE CONSTRUCTION, LTD. ( 33.13%) STOMPER DEMOLITION (3.03%) CRAWFORD YANT(0.48%) DALLAS LITE AND BARRICADE INC. (1.81%) FOUNDATION DRILLERS, INC.(2.83%) CAPROCK SPECIALITY CONTRACTORS (0.11%) S & S PAINTING (0.41%) THOMAS GRINDING, INC.(0.31%)
|
| Contract # |
11073218 |
|
Totals |
1580860.33 |
23750.24 |
1161669.88 |
73.4 |
|
| County | DALLAS |
| Highway |
US 67 |
| From |
SB FRTG RD AT TEN MILE CREEK |
| To |
. |
| CSJ |
0261-02-061 |
| Proj ID |
BR 2006(690) |
| Work Type |
REPL BRIDGE |
| |
|
0.305 |
1617177.77 |
0.00 |
1608038.55 |
99.9 |
| Work Order |
11-02-06 |
| Work Began |
01-22-07 |
| Work Completed |
|
| Time Computed |
11-18-06 |
| Contract Working Days |
269 |
| Addl Days Granted |
27 |
| Working Days Charged |
344 |
| Percent Time Used |
116 |
| Contractor(s) |
| NORTH TEXAS BRIDGE COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0261-02-061 COWTOWN TRAFFIC CONTROL, INC.(0.63%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.51%) T & R EXCAVATION, INC. (4.06%) SEDIMENT & EROSION CONTROL, INC. (6.38%) REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 11.65%) N.L. SCHUTTE FOUNDATION DRILLING, INC. (1.47%) FORTSON CONTRACTING, INC.(1.57%)
|
| Contract # |
09063222 |
|
Totals |
1617177.77 |
0.00 |
1608038.55 |
99.9 |
|
| County | DALLAS |
| Highway |
US 67 |
| From |
ON FTG ROAD FROM S OF COOPER ST |
| To |
NORTH OF COCKRELL HILL ROAD |
| CSJ |
0261-02-064 |
| Proj ID |
NH 2006(691) |
| Work Type |
HMAC OVERLAY |
| |
|
5.663 |
4909030.64 |
0.00 |
4617362.99 |
94.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
03-21-07 |
| Work Began |
05-03-07 |
| Work Completed |
|
| Time Computed |
04-06-07 |
| Contract Working Days |
242 |
| Addl Days Granted |
52 |
| Working Days Charged |
276 |
| Percent Time Used |
93 |
| Contractor(s) |
| AUSTIN BRIDGE & ROAD, LP |
SUBCONTRACTOR(S) FOR CCSJ: 0261-02-064 UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (0.81%) TEX OP CONSTRUCTION, LP(9.27%) SOIL EXPRESS, LTD. (1.10%) CONCRETE CUTTING BY BOND (0.17%) DURABLE SPECIALTIES, INC.(0.34%) ENVIRONMENTAL ALLIES, L.P. (2.00%) BROCK PAVING INDUSTRIES, INC. (HUB)(1.95%) STRIPING TECHNOLOGY, L.P.(1.52%)
|
| Contract # |
02073004 |
|
Totals |
4909030.64 |
0.00 |
4617362.99 |
94.0 |
|
| County | DALLAS |
| Highway |
US 67 |
| From |
ELLIS/DALLAS COUNTY LINE |
| To |
DALLAS/DUNCANVILLE CITY LIMIT |
| CSJ |
0261-02-070 |
| Proj ID |
NH 2009(026) |
| Work Type |
SIGN REFURBISHING |
| |
|
9.404 |
386126.52 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
10-16-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
100 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| TIME STRIPING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0261-02-070 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09083213 |
|
Totals |
386126.52 |
0.00 |
0.00 |
0.0 |
|
| County | DALLAS |
| Highway |
US 67 |
| From |
NBFR AT FIVE MILE CREEK |
| To |
. |
| CSJ |
0261-03-045 |
| Proj ID |
BR 2006(692) |
| Work Type |
REHAB BR & APPRS |
| |
|
0.058 |
736993.05 |
0.00 |
896370.18 |
99.9 |
| Work Order |
08-10-06 |
| Work Began |
10-03-06 |
| Work Completed |
|
| Time Computed |
08-26-06 |
| Contract Working Days |
213 |
| Addl Days Granted |
29 |
| Working Days Charged |
270 |
| Percent Time Used |
111 |
| Contractor(s) |
| NORTH TEXAS BRIDGE COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0261-03-045 ATS DRILLING, L.P. (5.49%) ARK CONTRACTING SERVICES, LLC( 11.34%) FORTSON CONTRACTING, INC.(1.73%) REYNOLDS ASPHALT & CONSTRUCTION COMPANY(2.60%) STRIPING PLUS, INC.(0.16%) COWTOWN TRAFFIC CONTROL, INC.(1.22%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.95%) PENHALL COMPANY(0.27%)
|
| Contract # |
07063239 |
|
Totals |
736993.05 |
0.00 |
896370.18 |
99.9 |
|
| County | DALLAS |
| Highway |
US 67 ETC |
| From |
AT FIVE MILE CREEK |
| To |
IN CITY OF DALLAS |
| CSJ |
0261-03-056 |
| Proj ID |
NH 2008(293) |
| Work Type |
CLEAN & PAINT EXISTING BRIDGES |
| |
|
1.001 |
975346.00 |
0.00 |
400280.11 |
41.0 |
| Work Order |
04-08-08 |
| Work Began |
06-10-08 |
| Work Completed |
|
| Time Computed |
04-24-08 |
| Contract Working Days |
271 |
| Addl Days Granted |
0 |
| Working Days Charged |
98 |
| Percent Time Used |
36 |
| Contractor(s) |
| GIBSON & ASSOCIATES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0261-03-056 CROSSROADS, L.P. (1.54%)
|
| Contract # |
03083230 |
|
Totals |
975346.00 |
0.00 |
400280.11 |
41.0 |
|
| County | DALLAS |
| Highway |
SH 114 |
| From |
AT SH 161 |
| To |
. |
| CSJ |
0353-04-084 |
| Proj ID |
STP 2005(315)MM |
| Work Type |
ADD U - TURN EB SH 114 TO WB SH 114 |
| |
|
0.312 |
2710250.34 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
09-19-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
10-05-08 |
| Contract Working Days |
205 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| AUSTIN BRIDGE & ROAD, LP |
SUBCONTRACTOR(S) FOR CCSJ: 0353-04-084 CAPROCK HIGHWAY CONSTRUCTION COMPANY (0.19%) DALLAS LITE AND BARRICADE INC. (0.47%) FORTSON CONTRACTING, INC.(1.00%) INTEGRATED ROADWAY SERVICES, INC.(2.06%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.18%) SITE-SAFE PRODUCTS OF TEXAS(1.14%) S & S BRIDGE PAINTING(0.58%) TOTAL HIGHWAY MAINTENANCE, LLC (0.75%)
|
| Contract # |
08083221 |
|
Totals |
2710250.34 |
0.00 |
0.00 |
0.0 |
|
| County | DALLAS |
| Highway |
SH 114 |
| From |
DALLAS/TARRANT COUNTY LINE |
| To |
SPUR 348 |
| CSJ |
0353-04-085 |
| Proj ID |
CM 2007(796) |
| Work Type |
ATMS |
| |
|
10.311 |
3363389.19 |
77027.68 |
2867682.16 |
85.2 |
| Work Order |
09-07-07 |
| Work Began |
11-15-07 |
| Work Completed |
|
| Time Computed |
11-15-07 |
| Contract Working Days |
240 |
| Addl Days Granted |
0 |
| Working Days Charged |
223 |
| Percent Time Used |
92 |
| Contractor(s) |
| MICA CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 0353-04-085 LAYFIELD CONSTRUCTION, INC (0.27%)
|
| Contract # |
08073011 |
|
Totals |
3363389.19 |
77027.68 |
2867682.16 |
85.2 |
|
| County | DALLAS |
| Highway |
LP 12 |
| From |
W. LAWTHER DRIVE |
| To |
EAST OF GOFORTH DRIVE |
| CSJ |
0353-05-084 |
| Proj ID |
NH 2008(361) |
| Work Type |
GRADING, STRS, ACP, SIGNING, PAVT M |
| |
|
0.785 |
28349251.84 |
10000.00 |
10000.00 |
0.0 |
| County | DALLAS |
| Highway |
LP 12 |
| From |
W. LAWTHER DRIVE |
| To |
EAST OF GOFORTH DRIVE |
| CSJ |
0353-05-110 |
| Proj ID |
RW 353-5-110 |
| Work Type |
ROW UTL. ADJ. IN CONSTRUCTION |
| |
|
0.785 |
3131109.30 |
0.00 |
0.00 |
0.0 |
| Work Order |
10-22-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
01-20-09 |
| Contract Working Days |
533 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
REBCON, INC. CONCHO CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0353-05-084 ARK CONTRACTING SERVICES, LLC(1.88%) AUSTIN BRIDGE & ROAD, LP (1.88%) FORTSON CONTRACTING, INC.(0.60%) TEXAS SHAFTS, INC. (5.55%) TOTAL HIGHWAY MAINTENANCE, LLC (0.12%) COWTOWN TRAFFIC CONTROL, INC.(0.12%) DGI-MENARD, INC. (0.55%) DUSTROL, INC. (ROANOKE)(0.38%) MIKE ALBERT, INC.( 10.64%) SOUTHWEST CONSTRUCTION SERVICES(0.05%) WEIR BROS., INC. (5.05%) ENVIRONMENTAL STANDARDS(1.85%) STAR OPERATIONS, INC.(2.94%) RAYMOND PAINTING, INC. (0.22%) J.R. DAVIS AND ASSOCIATES, INC.(1.86%) WEST TEXAS REBAR PLACERS INC.(0.00%)
|
| Contract # |
08083217 |
|
Totals |
31480361.14 |
10000.00 |
10000.00 |
0.0 |
|
| County | DALLAS |
| Highway |
SP 244 |
| From |
AT EASTON AND FERNDALE ROAD |
| To |
. |
| CSJ |
0353-05-099 |
| Proj ID |
CM 2007(008) |
| Work Type |
INTERSECTION IMPROVEMENTS |
| |
|
0.664 |
906639.48 |
38937.94 |
562350.63 |
62.0 |
| Work Order |
10-13-06 |
| Work Began |
03-31-08 |
| Work Completed |
|
| Time Computed |
01-11-07 |
| Contract Working Days |
180 |
| Addl Days Granted |
0 |
| Working Days Charged |
96 |
| Percent Time Used |
53 |
| Contractor(s) |
| MCMAHON CONTRACTING, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0353-05-099 ROADWAY SOLUTIONS, INC.( 27.72%) PEACHTREE CONSTRUCTION, LTD. (7.64%) ROAD MASTER STRIPING LLC (4.39%) INLET STRUCTURE SPECIALTIES LTD. (1.76%)
|
| Contract # |
09063031 |
|
Totals |
906639.48 |
38937.94 |
562350.63 |
62.0 |
|