|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | COLLIN |
| Highway |
US 380 |
| From |
WEST OF CR 608 IN FARMERSVILLE |
| To |
EAST OF FLOYD RD |
| CSJ |
0135-05-025 |
| Proj ID |
C 135-5-25 |
| Work Type |
GR, STRS, PVT, CUL, CURB AND GTRS |
| |
|
1.307 |
18186687.16 |
1034662.86 |
5795563.54 |
31.8 |
| Work Order |
05-10-12 |
| Work Began |
11-05-12 |
| Work Completed |
|
| Time Computed |
11-05-12 |
| Contract Working Days |
551 |
| Addl Days Granted |
0 |
| Working Days Charged |
137 |
| Percent Time Used |
24 |
| Contractor(s) |
| ED BELL CONSTRUCTION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0135-05-025 BREDA COMPANY, INC.(0.68%) CONCRETE CUTTING BY BOND (0.21%) CRAIG OLDEN, INC.(1.58%) DUSTROL, INC.(0.63%) FORTSON CONTRACTING, INC.(0.28%) JUST GROOVING, LTD.(0.01%) K & S UTILITY CONTRACTORS, INC.(4.42%) REYNOLDS ASPHALT & CONSTRUCTION COMPANY(6.11%) SCOTT DERR PAINTING CO, LLC(0.01%) TOTAL HIGHWAY MAINTENANCE, LLC (1.11%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.04%) WYLIE DRILLING & DRAINAGE, INC.(7.43%) MCL CONTRACTING, LLC (0.77%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.18%) BRENDA PRICE TRUCKING(0.02%)
|
| Contract # |
07113204 |
|
Totals |
18186687.16 |
1034662.86 |
5795563.54 |
31.8 |
|
| County | COLLIN |
| Highway |
FM 3537 |
| From |
SH 289 |
| To |
FM 2478 |
| CSJ |
0135-12-025 |
| Proj ID |
C 135-12-25 |
| Work Type |
WDN GR STRS & SURF |
| |
|
4.055 |
23788820.89 |
0.00 |
0.00 |
0.0 |
| Work Order |
10-21-11 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
04-18-12 |
| Contract Working Days |
680 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| TEXAS STERLING CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0135-12-025 ARLINGTON PAVERS, INC. (0.43%) CONCRETE CUTTING BY BOND (0.33%) DALLAS LITE AND BARRICADE INC. (0.24%) FORTSON CONTRACTING, INC.(0.39%) INDUS CONSTRUCTION, L.P. (0.96%) INLET STRUCTURE SPECIALTIES LTD. (5.42%) REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 17.27%) ROADWAY SOLUTIONS, INC.(6.35%) TEX OP CONSTRUCTION, LP(0.64%) TOTAL HIGHWAY MAINTENANCE, LLC (1.33%) USA EROSION, INC.(1.69%) W.O.E. CONSTRUCTION(0.65%)
|
| Contract # |
06113007 |
|
Totals |
23788820.89 |
0.00 |
0.00 |
0.0 |
|
| County | NAVARRO |
| Highway |
SH 31 |
| From |
28TH STREET |
| To |
15TH ST IN THE CITY OF CORSICANA |
| CSJ |
0162-04-047 |
| Proj ID |
C 162-4-47 |
| Work Type |
STRM SEWERS & INLETS;REP CONC PAV;ADA |
| |
|
1.351 |
9138952.54 |
311165.77 |
5010049.64 |
54.8 |
| Work Order |
09-14-10 |
| Work Began |
07-22-11 |
| Work Completed |
|
| Time Computed |
03-13-11 |
| Contract Working Days |
532 |
| Addl Days Granted |
73 |
| Working Days Charged |
455 |
| Percent Time Used |
75 |
| Contractor(s) |
| LONE STAR CIVIL CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0162-04-047 DALLAS LITE AND BARRICADE INC. (0.51%) TOTAL HIGHWAY MAINTENANCE, LLC (0.98%) ALLSTATE SIGNAL & CONSTRUCTION, LLC(0.98%) BIG CREEK CONSTRUCTION, LTD. (8.65%) UNDERGROUND COALITION, INC.( 12.39%) A BROTHERS (0.97%) RIVER CITIES SAWING, LLC (0.00%) INDUS CONSTRUCTION, L.P. (0.49%) W.O.E. CONSTRUCTION(0.41%) C & C DIRECTIONAL BORING (0.07%) INLET STRUCTURE SPECIALTIES LTD. (2.35%)
|
| Contract # |
08103003 |
|
Totals |
9138952.54 |
311165.77 |
5010049.64 |
54.8 |
|
| County | NAVARRO |
| Highway |
IH 45 |
| From |
FREESTONE COUNTY LINE |
| To |
CR 507 |
| CSJ |
0166-01-047 |
| Proj ID |
IM 0453(133) |
| Work Type |
EDGE RP, BS REP, LEV - UP OV |
| |
|
3.377 |
2218764.93 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
124 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0166-01-047 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04133021 |
|
Totals |
2218764.93 |
0.00 |
0.00 |
0.0 |
|
| County | ELLIS |
| Highway |
US 287 |
| From |
JOHNSON C/L |
| To |
BU 287Q (OLD FT. WORTH HWY) |
| CSJ |
0172-04-042 |
| Proj ID |
NH 2012(631) |
| Work Type |
ACP OVERLAY AND PAVEMENT MARKINGS |
| |
|
14.992 |
4420536.84 |
10670.00 |
5005524.31 |
100.0 |
| Work Order |
07-16-12 |
| Work Began |
10-15-12 |
| Work Completed |
04-12-13 |
| Time Computed |
09-14-12 |
| Contract Working Days |
73 |
| Addl Days Granted |
11 |
| Working Days Charged |
97 |
| Percent Time Used |
115 |
| Contractor(s) |
| BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0172-04-042 TOTAL HIGHWAY MAINTENANCE, LLC (2.83%) HIGHWAY TECHNOLOGIES, INC. (0.18%)
|
| Contract # |
06123224 |
|
Totals |
4420536.84 |
10670.00 |
5005524.31 |
100.0 |
|
| County | ELLIS |
| Highway |
US 287 |
| From |
SARDIS |
| To |
PARKS SCHOOL HOUSE ROAD |
| CSJ |
0172-05-108 |
| Proj ID |
NH 2012(395) |
| Work Type |
REPAIR AND OVERLAY |
| |
|
7.301 |
5279326.58 |
20125.00 |
4839505.04 |
91.6 |
| Work Order |
06-04-12 |
| Work Began |
08-02-12 |
| Work Completed |
|
| Time Computed |
08-02-12 |
| Contract Working Days |
83 |
| Addl Days Granted |
8 |
| Working Days Charged |
91 |
| Percent Time Used |
100 |
| Contractor(s) |
| APAC-TEXAS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0172-05-108 HIGHWAY TECHNOLOGIES, INC. (0.12%) DUSTROL, INC.(0.34%) STRIPING TECHNOLOGY, L.P.(1.72%) CF SOUTHWEST ENVIRONMENT SERVICES LLC(0.07%) FORTSON CONTRACTING, INC.(0.68%) BRENDA PRICE TRUCKING(2.27%)
|
| Contract # |
03123205 |
|
Totals |
5279326.58 |
20125.00 |
4839505.04 |
91.6 |
|
| County | ELLIS |
| Highway |
US 287 |
| From |
BUS US 287 IN ENNIS |
| To |
SOUTH OF SH 34 |
| CSJ |
0172-08-050 |
| Proj ID |
DMO 2005(474) |
| Work Type |
WIDENING OF A NON - FREEWAY FACILITY |
| |
|
3.181 |
34561014.77 |
600992.26 |
31142626.99 |
90.2 |
| County | ELLIS |
| Highway |
US 287 |
| From |
BUS US 287 IN ENNIS |
| To |
SOUTH OF SH 34 |
| CSJ |
0172-08-054 |
| Proj ID |
RW 172-8-54 |
| Work Type |
ROW ACQ., AND UTL. ADJ. |
| |
|
2.797 |
93744.00 |
0.00 |
93658.00 |
99.9 |
| Work Order |
01-07-10 |
| Work Began |
03-09-10 |
| Work Completed |
|
| Time Computed |
03-09-10 |
| Contract Working Days |
563 |
| Addl Days Granted |
195 |
| Working Days Charged |
780 |
| Percent Time Used |
102 |
| Contractor(s) |
| SAFECO INSURANCE COMPANIES |
SUBCONTRACTOR(S) FOR CCSJ: 0172-08-050 COWTOWN TRAFFIC CONTROL, INC.(0.04%) FORTSON CONTRACTING, INC.(0.42%) MURRAY CONSTRUCTION(0.19%) GIBSON & ASSOCIATES, INC.(0.03%) SCOTT DERR PAINTING CO (0.06%) TOTAL HIGHWAY MAINTENANCE, LLC (0.38%) AK MILLING, LLC(0.46%) WEBBER BARRIER SERVICES, INC.(0.61%) F & W ELECTRICAL CONTRACTORS, INC. (0.65%) JAMES CONSTRUCTION GROUP, L.L.C. ( 10.21%) JAG TRUCKING INC (6.20%) SAR TRANSPORTATION, LLC(2.64%) S & S TRUCKING (0.17%) APAC-TEXAS, INC. ( 25.44%) V. FERNANDEZ TRUCKING, INC.(0.43%) EAGLE AGGREGATE TRANSPORTATION, LLC. (1.00%) ALLIED FENCE COMPANY (0.04%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.00%) GREAT WESTERN ERECTORS (0.05%) WEBBER BARRIER SERVICES, INC.(0.32%) WYLIE DRILLING & DRAINAGE, INC.(0.76%) RIVER CITIES SAWING LLC(0.02%) SCOTT DERR PAINTING CO (0.01%) J.L. STEEL REINFORCING, LLC(0.19%) METRO CUTTING AND SEALING, INC.(0.00%) CIRCLE H CONTRACTORS, L.P. (0.05%) COWBOY CORING CORPORATION(0.00%) GEORGETOWN GRASS AND LAWN COMPANY, INC.(0.02%) LINDSEY CONTRACTORS, INC.(0.17%) EXTREME ENVIRONMENTAL SERVICES (0.00%) ANDERSON COLUMBIA CO., INC.( 63.13%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.94%) RANGER EXCAVATING, L.P.(4.12%) DUSTROL, INC.(0.09%) BRENDA PRICE TRUCKING(1.68%) EMPIRE CIVIL CONSTRUCTION, L.L.C.(9.74%) BIG CREEK CONSTRUCTION, LTD. ( 16.41%) UNDERGROUND COALITION, INC.(2.26%) ECO-REBAR CO (0.02%) NORTH TEXAS REBAR, LLC (0.07%) CLAYCON CONSTRUCTION, LLC(1.22%) MP GRINDING & GROOVING, LLC(0.02%) MTM EXCAVATION (0.06%)
|
| Contract # |
10093001 |
|
Totals |
34654758.77 |
600992.26 |
31236284.99 |
90.3 |
|
| County | KAUFMAN |
| Highway |
SH 34 |
| From |
AIRPORT RD |
| To |
HIGH ST IN TERRELL |
| CSJ |
0173-04-024 |
| Proj ID |
RW 173-4-24 |
| Work Type |
ACQUISITION OF ROW |
| |
|
0.303 |
663290.10 |
0.00 |
572679.35 |
86.3 |
| County | KAUFMAN |
| Highway |
SH 34 |
| From |
AIRPORT RD |
| To |
HIGH ST. IN TERRELL |
| CSJ |
0173-04-025 |
| Proj ID |
STP 2011(798) |
| Work Type |
GR, PVMT, & GRADE SEP RR O / P |
| |
|
1.032 |
14656545.90 |
921157.74 |
12351581.92 |
84.2 |
| Work Order |
06-14-11 |
| Work Began |
10-04-11 |
| Work Completed |
|
| Time Computed |
09-12-11 |
| Contract Working Days |
440 |
| Addl Days Granted |
2 |
| Working Days Charged |
388 |
| Percent Time Used |
87 |
| Contractor(s) |
| AUI CONTRACTORS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0173-04-025 DUSTROL, INC.(0.51%) HAYWARD BAKER, INC.(1.49%) INLET STRUCTURE SPECIALTIES LTD. (3.97%) NORTH TEXAS REBAR, LLC (7.18%) REYNOLDS ASPHALT & CONSTRUCTION COMPANY(6.66%) SCOTT DERR PAINTING CO (0.90%) STORM WATER MANAGEMENT, INC. (0.68%) T-BAR FENCE, INC.(0.48%) TEXAS SHAFTS, INC. (1.11%) DURABLE SPECIALTIES, INC.(2.31%) TOTAL HIGHWAY MAINTENANCE, LLC (0.86%) THELIN RECYCLING CO., LLC(0.23%) TRAC-WORK, INC.(1.46%) CROSSROADS, L.P. (0.26%) MCALLISTER"S LANDSCAPE MANAGEMENT(0.67%) RIVER CITIES SAWING, LLC (0.29%) RAIL LABOR PROVIDERS (0.05%) STRAIGHT LINE SAWING & SEALING (0.19%) EL CALA CONSTRUCTION LLC (2.11%)
|
| Contract # |
03113211 |
|
Totals |
15319836.00 |
921157.74 |
12924261.27 |
84.3 |
|
| County | KAUFMAN |
| Highway |
SH 34 |
| From |
US 80 |
| To |
N. FRANCES STREET IN TERRELL |
| CSJ |
0173-05-032 |
| Proj ID |
STP 2013(665) |
| Work Type |
HOT MIX OVLY, BASE, BLADE, PAV MARKS |
| |
|
0.977 |
1979270.82 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
152 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ED BELL CONSTRUCTION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0173-05-032 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05133023 |
|
Totals |
1979270.82 |
0.00 |
0.00 |
0.0 |
|
| County | DENTON |
| Highway |
IH 35 ETC |
| From |
US 77 |
| To |
COOKE COUNTY LINE; FRONTAGE ROADS |
| CSJ |
0195-02-067 |
| Proj ID |
IM 0356(437) |
| Work Type |
SEAL COAT, PVMT MKGS, & MAILBOXES |
| |
|
172.893 |
10957185.08 |
694411.80 |
1845105.99 |
16.8 |
| Work Order |
11-09-12 |
| Work Began |
02-26-13 |
| Work Completed |
|
| Time Computed |
02-02-13 |
| Contract Working Days |
189 |
| Addl Days Granted |
0 |
| Working Days Charged |
49 |
| Percent Time Used |
25 |
| Contractor(s) |
| BRANNAN PAVING CO., LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0195-02-067 SOUTHWEST ENVIRONMENT SERVICES, INC. (0.10%) STRIPE-A-ZONE, INC.( 18.82%)
|
| Contract # |
10123215 |
|
Totals |
10957185.08 |
694411.80 |
1845105.99 |
16.8 |
|
| County | DENTON |
| Highway |
IH 35E |
| From |
0.2 MILES SOUTH OF EAGLE POINT RD |
| To |
0.04 MILES NORTH OF EAGLE POINT RD |
| CSJ |
0196-02-122 |
| Proj ID |
IM 0356(439) |
| Work Type |
INSTALL SAFETY LIGHTING |
| |
|
1.016 |
158400.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-03-13 |
| Work Began |
04-29-13 |
| Work Completed |
|
| Time Computed |
04-29-13 |
| Contract Working Days |
100 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ROADWAY SOLUTIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0196-02-122 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02133209 |
|
Totals |
158400.00 |
0.00 |
0.00 |
0.0 |
|
| County | DALLAS |
| Highway |
IH 35E |
| From |
COMMERCE ST |
| To |
OAKLAWN AVE |
| CSJ |
0196-03-257 |
| Proj ID |
IM 0356(436) |
| Work Type |
FULL DEPTH REPAIR |
| |
|
1.566 |
402995.80 |
0.00 |
230128.83 |
57.1 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
10-18-12 |
| Work Began |
11-12-12 |
| Work Completed |
|
| Time Computed |
11-12-12 |
| Contract Working Days |
41 |
| Addl Days Granted |
5 |
| Working Days Charged |
22 |
| Percent Time Used |
47 |
| Contractor(s) |
| SCR CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0196-03-257 HIGHWAY TECHNOLOGIES, INC. (0.63%) ARTEX ELECTRIC, INC. (2.13%) PENHALL COMPANY(2.14%) J. MUNOZ TRUCKING(3.47%)
|
| Contract # |
09123026 |
|
Totals |
402995.80 |
0.00 |
230128.83 |
57.1 |
|
| County | DALLAS |
| Highway |
IH 35E |
| From |
VALLEY VIEW LANE |
| To |
WHITLOCK LN/SANDY LAKE ROAD |
| CSJ |
0196-03-259 |
| Proj ID |
IM 0356(435) |
| Work Type |
FULL DEP REP AND OV |
| |
|
3.390 |
1743690.74 |
67612.85 |
67612.85 |
3.8 |
| Work Order |
12-12-12 |
| Work Began |
04-08-13 |
| Work Completed |
|
| Time Computed |
02-10-13 |
| Contract Working Days |
119 |
| Addl Days Granted |
0 |
| Working Days Charged |
39 |
| Percent Time Used |
32 |
| Contractor(s) |
| TEXAS HIGHWAY MAINTENANCE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0196-03-259 TOTAL HIGHWAY MAINTENANCE, LLC (4.97%) DUSTROL, INC.(4.56%) COWBOY TRUCKING(5.07%) PEACHTREE CONSTRUCTION, LTD. ( 64.98%) BUYERS BARRICADES, INC.(0.96%) TEX OP CONSTRUCTION, LP(1.80%) A BROTHERS MILLING, LLC(3.68%) W.O.E. CONSTRUCTION(0.29%)
|
| Contract # |
10123229 |
|
Totals |
1743690.74 |
67612.85 |
67612.85 |
3.8 |
|
| County | DALLAS |
| Highway |
SH 352 |
| From |
ASH LN. |
| To |
SPRING AVE. |
| CSJ |
0197-01-011 |
| Proj ID |
NH 2013(096) |
| Work Type |
FULL DEPTH CONCRETE PAVEMENT REPAIR |
| |
|
2.134 |
170413.86 |
52822.57 |
80103.22 |
100.0 |
| Work Order |
11-09-12 |
| Work Began |
03-13-13 |
| Work Completed |
05-06-13 |
| Time Computed |
01-08-13 |
| Contract Working Days |
26 |
| Addl Days Granted |
0 |
| Working Days Charged |
26 |
| Percent Time Used |
100 |
| Contractor(s) |
| TEXAS HIGHWAY MAINTENANCE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0197-01-011 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10123010 |
|
Totals |
170413.86 |
52822.57 |
80103.22 |
100.0 |
|
| County | DALLAS |
| Highway |
US 175 |
| From |
LAKE JUNE ROAD |
| To |
IH 20 |
| CSJ |
0197-02-106 |
| Proj ID |
NH 2013(317) |
| Work Type |
FDR, ACP OVERLAY AND PVMNT MARKING |
| |
|
5.198 |
2490572.71 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
02-26-13 |
| Work Began |
04-30-13 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
166 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| O. TREVINO CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0197-02-106 STRAIGHT LINE SAWING & SEALING (2.27%) BRENDA PRICE TRUCKING(3.21%) HIGHWAY TECHNOLOGIES, INC. (0.58%) DUSTROL, INC.(5.81%) APAC-TEXAS, INC. ( 28.53%) DURABLE SPECIALTIES, INC.(0.39%) ENVIRONMENTAL STANDARDS, INC.(0.20%) TOTAL HIGHWAY MAINTENANCE, LLC (1.89%)
|
| Contract # |
01133215 |
|
Totals |
2490572.71 |
0.00 |
0.00 |
0.0 |
|
| County | KAUFMAN |
| Highway |
US 175 |
| From |
AT SH 243 |
| To |
. |
| CSJ |
0197-04-076 |
| Proj ID |
NH 1102(089) |
| Work Type |
LANDSCAPE DEVELOPMENT |
| |
|
4.866 |
153652.45 |
0.00 |
156318.70 |
99.9 |
| Work Order |
07-22-11 |
| Work Began |
10-13-11 |
| Work Completed |
|
| Time Computed |
08-07-11 |
| Contract Working Days |
64 |
| Addl Days Granted |
0 |
| Working Days Charged |
59 |
| Percent Time Used |
92 |
| Contractor(s) |
| TEXAS TREE & LANDSCAPE, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0197-04-076 TX DOWN UNDER CONSTRUCTION LLC (3.35%) TOTAL HIGHWAY MAINTENANCE, LLC (1.95%) CEN-TEX IRRIGATION SYSTEMS ( 27.33%)
|
| Contract # |
06113012 |
|
Totals |
153652.45 |
0.00 |
156318.70 |
99.9 |
|
| County | ELLIS |
| Highway |
US 67 |
| From |
AT RAILPORT PARKWAY |
| To |
. |
| CSJ |
0260-02-038 |
| Proj ID |
PTF 2011(809) |
| Work Type |
GRADING, BASE, ACP PVMNT, STRUCTURES |
| |
|
1.459 |
8811943.85 |
677771.87 |
7285581.56 |
82.6 |
| Work Order |
04-05-11 |
| Work Began |
04-22-11 |
| Work Completed |
|
| Time Computed |
04-22-11 |
| Contract Working Days |
303 |
| Addl Days Granted |
243 |
| Working Days Charged |
517 |
| Percent Time Used |
94 |
| Contractor(s) |
| APAC-TEXAS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0260-02-038 STRIPING TECHNOLOGY, L.P.(0.69%) RAMBO CONTRACTING, INC.(2.21%) RICE ENVIRONMENTAL SERVICES(0.94%) HIGHWAY TECHNOLOGIES, INC. (0.21%) BUILDER SERVICES CO. (0.59%) FORTSON CONTRACTING, INC.(0.71%) MELS ELECTRIC, L.P.(0.45%) J. T. LANSFORD & SONS, INC.(0.34%) BAKER BRIDGE, L.P. ( 16.29%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.30%) GARY A. CRAIN, INC.(0.23%) ENVIRONMENTAL STANDARDS, INC.(0.14%) SAN-ANN-CO., INC.(0.24%) SOUTHWEST ENVIRONMENT SERVICES LLC (0.12%) PENHALL COMPANY(0.06%) TEX OP CONSTRUCTION, LP(0.10%) DUSTROL, INC.(0.20%) REBCON, INC. ( 10.24%) N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.24%) A R DANIEL CONSTRUCTION SERVICES, INC. (0.39%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.11%) WEST TEXAS REBAR PLACERS INC.(0.25%) WEBBER BARRIER SERVICES, LLC.(0.58%)
|
| Contract # |
02113005 |
|
Totals |
8811943.85 |
677771.87 |
7285581.56 |
82.6 |
|
| County | ELLIS |
| Highway |
US 67 |
| From |
OVERLOOK DRIVE |
| To |
EIGHTH ST |
| CSJ |
0261-01-037 |
| Proj ID |
C 261-1-37 |
| Work Type |
CONSTRUCT NEW FRONTAGE ROADS |
| |
|
0.585 |
8956100.80 |
653709.85 |
3036541.62 |
33.9 |
| Work Order |
08-20-12 |
| Work Began |
10-29-12 |
| Work Completed |
|
| Time Computed |
10-19-12 |
| Contract Working Days |
367 |
| Addl Days Granted |
0 |
| Working Days Charged |
133 |
| Percent Time Used |
36 |
| Contractor(s) |
| J.D. ABRAMS, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0261-01-037 J.L. STEEL REINFORCING, LLC(0.56%) COWTOWN TRAFFIC CONTROL, INC.(0.15%) FORTSON CONTRACTING, INC.(0.63%) HOUSTON SAWING & DRILLING(0.09%) TEX OP CONSTRUCTION, LP(0.16%) SCOTT DERR PAINTING CO (0.14%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.77%) REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 10.35%) SOUTHWEST ENVIRONMENT SERVICES LLC (0.84%) TOTAL HIGHWAY MAINTENANCE, LLC (0.44%) FARR FOUNDATION, INC.(3.98%) PANTHER CREEK TRANSPORTATION, INC. (1.30%) NORTH TEXAS REBAR, LLC (0.14%)
|
| Contract # |
06123005 |
|
Totals |
8956100.80 |
653709.85 |
3036541.62 |
33.9 |
|
| County | DALLAS |
| Highway |
US 67 |
| From |
ELLIS COUNTY LINE |
| To |
WHEATLAND RD |
| CSJ |
0261-02-072 |
| Proj ID |
NH 2013(098) |
| Work Type |
FDRCP AND HMAC OVERLAY |
| |
|
8.823 |
541244.57 |
0.00 |
31197.30 |
5.7 |
| Work Order |
11-09-12 |
| Work Began |
12-04-12 |
| Work Completed |
|
| Time Computed |
11-25-12 |
| Contract Working Days |
61 |
| Addl Days Granted |
0 |
| Working Days Charged |
4 |
| Percent Time Used |
6 |
| Contractor(s) |
| TEXAS HIGHWAY MAINTENANCE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0261-02-072 PEACHTREE CONSTRUCTION, LTD. ( 34.91%) W.O.E. CONSTRUCTION(2.02%) TOTAL HIGHWAY MAINTENANCE, LLC (2.08%) COWBOY TRUCKING(0.00%) XTREEME SAWING & SEALING, INC. (0.49%)
|
| Contract # |
10123016 |
|
Totals |
541244.57 |
0.00 |
31197.30 |
5.7 |
|
| County | DALLAS |
| Highway |
US 67 |
| From |
NORTH OF IH 20 |
| To |
SOUTH OF RED BIRD LN |
| CSJ |
0261-03-053 |
| Proj ID |
NH 2011(346) |
| Work Type |
SUBGRADE, ACP BASE, CONC PAV STR |
| |
|
0.994 |
3685288.00 |
0.00 |
3356904.11 |
92.6 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
10-20-10 |
| Work Began |
02-14-11 |
| Work Completed |
|
| Time Computed |
11-05-10 |
| Contract Working Days |
172 |
| Addl Days Granted |
0 |
| Working Days Charged |
244 |
| Percent Time Used |
141 |
| Contractor(s) |
| ARK CONTRACTING SERVICES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0261-03-053 BUYER BARRICADES (1.22%) MCMAHON CONTRACTING, L.P.( 13.34%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.41%) ANDREWS PAVING & CONSTRUCTION(8.00%) BROCK ENVIRONMENTAL, LLC (0.32%) S & V CONSTRUCTION LLC (3.75%) SUPREME SAWING AND SEALING (0.09%) D.E.E.R. TRUCKING, LLC (1.26%) SCIENTIFIC CONSTRUCTION GROUP, INC.(1.13%) WYLIE DRILLING & DRAINAGE, INC.(0.91%) J-N CONSTRUCTION COMPANY, INC. (7.89%) J. LIFESTYLES(0.10%) HIGHWAY TECHNOLOGIES, INC. (1.00%) N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.83%) CONCRETE PENETRATING CO. (0.28%) TEXAS UTI, LLC (0.04%) WEBBER BARRIER SERVICES, INC.(1.06%) FORTSON CONTRACTING, INC.(0.81%) DUSTROL, INC.(0.20%) AUGER DRILLING, INC. (0.13%) J.L. STEEL REINFORCING, LLC(0.01%) MICA CORPORATION (0.65%)
|
| Contract # |
08103034 |
|
Totals |
3685288.00 |
0.00 |
3356904.11 |
92.6 |
|