Lady Bird Lake Segment (Holly Street to SH 71/Ben White Boulevard)
I-35 Capital Express Central Project

Segment overview
Add two high-occupancy-vehicle (HOV) managed lanes in both directions along I-35. In addition, the project will reconstruct the Lady Bird Lake bridge, construct a single-point urban interchange (SPUI) at Riverside Drive that will accommodate future Capital Metro light rail routes, add a pedestrian-only bridge at Woodland Avenue, and improve bicycle and pedestrian paths along the corridor.
Major impacts/activity
- Southbound I-35 Woodland Avenue exit (232) closed April 14, 2025, and is expected to reopen early 2026, weather permitting. Drivers on southbound I-35 will use the Riverside Drive exit (233).
Schedule
- Construction start: early 2025
- Anticipated construction completion: 2033, weather permitting
Contractor
- Balfour Beatty Construction