Lady Bird Lake Segment (Holly Street to SH 71/Ben White Boulevard)
I-35 Capital Express Central Project
Connect with us
Segment overview
The project will add two high-occupancy-vehicle (HOV) managed lanes in both directions, reconstruct Lady Bird Lake bridge and build a single-point urban interchange (SPUI) at Riverside Drive. It will enhance safety and connectivity with a pedestrian-only bridge at Woodland Avenue, bike and pedestrian paths along the corridor and will accommodate future Capital Metro routes.
Major impacts/activity
- Eastbound Riverside Drive reduced to one lane between the southbound I-35 frontage road and Travis Heights Boulevard through early 2026, weather permitting.
- Kenwood Avenue at Riverside Drive will be closed through early 2026, weather permitting. Drivers will detour via Travis Heights Boulevard to access East Riverside Drive.
- East Avenue between the southbound I-35 frontage road and Nash Hernandez Senior Road will be closed through early 2026, weather permitting.
- Woodland Avenue under I-35 will be closed and crews will construct temporary U-turns in both directions at the intersection. Eastbound traffic on Woodland Avenue will turn right onto the southbound I-35 frontage road, use the Oltorf Street U-turn, and then return to Woodland Avenue. Westbound traffic on Woodland Avenue will turn right onto the northbound I-35 frontage road, use the signalized intersection at Riverside Drive to travel south on the frontage road, and reconnect with Woodland Avenue. Pedestrians will detour to nearby cross-streets.
Trail impacts/activity
- Crews opened a temporary trail detour along the north shore of Lady Bird Lake, just west of I-35. This detour will be in place through 2033.
- Waterway traffic under the I-35 bridge will be limited to a 75-foot-wide passage under the center portion of the bridge and away from work zones through 2033 to maintain user safety.
- The parking lot under the I-35 bridge will be closed through 2033. Pedestrian access will be maintained under the bridge.
Schedule
- Construction start: early 2025
- Anticipated construction completion: 2033, weather permitting
Contractor
- Balfour Beatty Construction