Letting Schedule for January, 2012 (FY 2012)

 
 
Last Update: Monday, September 24, 2012
January, 2012 (FY 2012) (see Links)
SEP 2011 | OCT 2011 | NOV 2011 | DEC 2011 | JAN 2012 | FEB 2012 | MAR 2012 | APR 2012 | MAY 2012 | JUN 2012 | JUL 2012 | AUG 2012
CCSJ County/
District
Highway Let Status Contract
Cost
Fund
Cat
Description
0916-38-004 Aransas/
Corpus Christi
VA Actual $694,061 3 HIKE AND BIKE TRAIL
0913-20-074 Austin/
Yoakum
CR Actual $237,861 6 REPLACE BRIDGE AND APPROACHES
0052-02-033 Bailey/
Lubbock
US 70 Actual $6,024,404 1 REHABILIATION OF EXISTING ROAD
0231-10-016 Bell/
Waco
BU 190F Actual $2,987,468 1 REHABILITATE ROADWAY
0915-12-470 Bexar/
San Antonio
CS Actual $7,371,286 3 WIDEN ROADWAY TO CONSTRUCT TURN LANES AND UPGRADE SIGNAL
0915-12-497 Bexar/
San Antonio
VA Actual $500,000 1 PURCHASE AND INSTALL WRONG WAY SIGNS AND DETECTION EQUIPMENT
2452-01-043 Bexar/
San Antonio
LP 1604 Actual $15,126,840 ROW CONSTRUCT INTERCHANGE (PHASE 1A - SH 151 ML'S)
0912-31-164 Brazoria/
Houston
CR Actual $815,348 6 REPLACE BRIDGE (NBI# 12020AA0519002)
0912-31-207 Brazoria/
Houston
CS Actual $483,526 6 REPLACE BRIDGE (NBI# 12020M00367001)
0273-03-026 Burnet/
Austin
US 183 Actual $2,154,467 1 SPOT REPAIR, MILL, SEAL, OVERLAY AND MBGF
0152-03-051 Caldwell/
Austin
US 183 Actual $569,738 3 CONSTRUCT CONTINUOUS LEFT TURN LANE & 4' SHOULDERS
0039-07-236 Cameron/
Pharr
US 77 Actual $2,019,306 8 INSTALL MEDIAN BARRIER
0569-01-050 Cass/
Atlanta
SH 43 Actual $1,748,321 1 RESTORE SECTION AND RESURFACE EXISTING 2 - LANE HIGHWAY
0047-14-073 Collin/
Dallas
US 75 Actual $360,000 10 LANDSCAPE DEVELOPMENT TO INCLUDE TREE & SHRUB PLANTING
0044-09-065 Cooke/
Wichita Falls
FM 1199 Actual $61,194 1 LANDSCAPE
0094-03-112 Dallas/
Dallas
SH 183 Actual $79,658 5 UPGRADE EXISTING ISDN TO WIRELESS ITS SYSTEM
0442-02-153 Dallas/
Dallas
IH 35E Actual $224,828 10 LANDSCAPE DEVELOPMENT TO INCLUDE TREE & SHRUB PLANTING
0918-00-189 Dallas/
Dallas
VA Actual $1,250,000 5 FREEWAY INCIDENT MANAGEMENT PROGRAM; FY 2012 FUNDING;
0918-00-190 Dallas/
Dallas
VA Actual $625,000 5 REGIONAL EMISSIONS REDUCTION PROGRAM IMPLEMENTATION
3000-01-022 Dallas/
Dallas
SP 408 Actual $79,693 1 REFURBISH ITS
0913-17-032 Dewitt/
Yoakum
CR Actual $276,156 6 REPLACE BRIDGE AND APPROACHES
1982-01-021 Duval/
Laredo
FM 1329 Actual $3,198,886 1 RESTORATION OF EXISTING HIGHWAY
0007-06-077 Eastland/
Brownwood
IH 20 Actual $5,901,847 1 RECONSTRUCTION ROADWAY - WESTBOUND LANES ONLY
0092-12-004 Ellis/
Dallas
BI 45-H Actual $2,029,788 1 MILL, REPAIR AND OVERLAY
0909-38-027 Falls/
Waco
CR Actual $860,898 6 REPLACE BRIDGE AND APPROACHES
0145-06-023 Floyd/
Lubbock
US 70 Actual $18,689,403 11 OVERLAY
0675-01-061 Freestone/
Bryan
IH 45 Actual $3,808,777 1 OVERLAY CONSISTING OF MILLING, HMA LEVEL - UP, HOT ASPHALT
0072-01-051 Gillespie/
Austin
US 87 Actual $2,178,507 1 LEVEL UP & SEAL COAT
0014-06-040 Hill/
Waco
SH 81 Actual $1,512,675 1 REHABILITATE ROADWAY
1331-03-011 Hood/
Fort Worth
FM 1189 Actual $146,432 1 REPLACE 2 - 72" CGM WITH MULTIPLE BOX CULVERT AND SET
0005-06-114 Howard/
Abilene
IH 20 Actual $171,849 1 SAFETY LIGHTING
0200-04-023 Jasper/
Beaumont
US 69 Actual $11,384,486 1 SEAL COAT
0358-01-025 Jeff Davis/
El Paso
SH 118 Actual $5,763,238 1 SEAL COAT
0920-00-108 Jefferson/
Beaumont
VA Actual $2,540,921 10 CONSTRUCT CURB RAMPS FOR ADA COMPLIANCE
0908-24-036 Jones/
Abilene
VA Actual $649,700 3 SCENIC OR HISTORIC HIGHWAY PROGRAM
0095-04-064 Kaufman/
Dallas
US 80 Actual $17,050,215 3 CONSTRUCT NEW LOCATION INTERCHANGE
0327-05-036 Kenedy/
Pharr
US 77 Actual $5,195,035 1 REHAB OF EXISTING ROADWAY (NORTHBOUND LANES ONLY)
0473-02-032 Lee/
Austin
SH 21 Actual $557,935 1 CONSTRUCT 2WAY TURN & SHOULDER
0131-01-057 Lubbock/
Lubbock
US 62 Actual $7,618,299 1 REHABILITATION OF EXISTING ROAD
1229-01-055 Maverick/
Laredo
FM 1021 Actual $4,274,008 1 SEALCOAT
0338-03-086 Montgomery/
Houston
SH 105 Actual $2,748,533 1 BASE & ASPHALT REPAIR, OCST AND HOT MIX
1062-03-046 Montgomery/
Houston
FM 1485 Actual $3,754,449 1 BASE REPAIR, 1.5" ACP O / L AND CENTERLINE RUMBLE STRIPS
0304-05-034 Newton/
Beaumont
SH 87 Actual $2,777,740 8 PROVIDE ADDITIONAL PAVED SURFACE WIDTH
1558-03-026 Nueces/
Corpus Christi
FM 70 Actual $249,002 8 CENTERLINE RUMBLE STRIPS
0009-12-074 Rockwall/
Dallas
IH 30 Actual $19,988,909 3 CONSTRUCT INTERCHANGE AT ERBY CAMPBELL BLVD
0123-04-019 Rusk/
Tyler
US 84 Actual $2,643,029 1 REHABILITATE 1.6 MI, THEN BASE REPAIR & RESURFACE REMAINDER
0101-03-082 San Patricio/
Corpus Christi
US 181 Actual $4,783,690 1 OVERLAY ROADWAY
0495-04-062 Smith/
Tyler
IH 20 Actual $2,019,407 1 PLANE & REPAVE ROADWAY, WBL ONLY (SECTIONS)
2075-02-061 Smith/
Tyler
LP 323 Actual $2,459,784 1 REPAIR AND RESURFACE ROADWAY
0363-01-137 Tarrant/
Fort Worth
SH 26 Actual $4,229,932 1 MILL, BASE REPAIR, HMA OVERLAY
0902-48-506 Tarrant/
Fort Worth
CS Actual $799,000 6 REPLACE BRIDGE AND APPROACHES
0264-07-029 Tom Green/
San Angelo
SL 306 Actual $6,183,975 11 CONSTRUCT MAIN LANES
0265-01-101 Travis/
Austin
US 183 Actual $554,398 3 CONSTRUCT BIKE TRAIL (AKA LANCE ARMSTRONG TRAIL)
2102-01-065 Travis/
Austin
RM 2244 Actual $1,926,950 1 SEAL COAT AND THIN OVERLAY
0156-04-104 Wichita/
Wichita Falls
US 82 Actual $2,341,824 1 FULL DEPTH REPAIR AND HOT MIX OVERLAY
0156-04-107 Wichita/
Wichita Falls
US 82 Actual $588,120 1 RELOCATE EXIT RAMP
0914-05-167 Williamson/
Austin
CR Actual $1,033,206 3 REBUILD PAVEMENT STR & REALIGN LANES
1378-02-033 Williamson/
Austin
RM 1431 Actual $2,895,176 1 FULL DEPTH REPAIR, SEAL & THIN OV


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract