Detail Letting Schedule for Newton County (FY 2012)

 
 
Last Update: Monday, September 24, 2012
Newton County (FY 2012)

CCSJ: 0304-05-034

District: Beaumont Let Date: JAN 2012
Highway: SH 87 Let Status: Actual
Project ID: STP 2012(215)HRR CSJ: 0304-05-034
Description: PROVIDE ADDITIONAL PAVED SURFACE WIDTH Handling
Code:
 
Limits From: 1.1 MI S OF SABINE CO/L, SOUTH Fund Cat: 8
Limits To: FM 1415 Estimate: $2,846,602
Length: 11.6 Miles Actual: $2,777,740
 
Back...

Totals for 0304-05-034
Length: 11.6 Miles
Estimate: $2,846,602
Actual: $2,777,740

CCSJ: 0627-03-024

District: Beaumont Let Date: MAY 2012
Highway: FM 363 Let Status: Actual
Project ID: STP 2012(537) CSJ: 0627-03-024
Description: RAISE ROADWAY AND REPLACE BRIDGE Handling
Code:
 
Limits From: AT THICKETY CREEK Fund Cat: 1
Limits To: (STR 062703004) Estimate: $3,921,404
Length: 0.9 Miles Actual: $3,877,299
 
Back...

Totals for 0627-03-024
Length: 0.9 Miles
Estimate: $3,921,404
Actual: $3,877,299

CCSJ: 0627-04-032

District: Beaumont Let Date: DEC 2011
Highway: FM 1416 Let Status: Actual
Project ID: CRX 627-4-32 CSJ: 0627-04-032
Description: RAILROAD GRADE CROSSING REPLANKING Handling
Code:
XX
Limits From: AT TIBR IN BON WIER Fund Cat: 10
Limits To: (DOT 024154D) Estimate: $20,800
Length: 0.1 Miles Actual: $20,800
 
Back...

Totals for 0627-04-032
Length: 0.1 Miles
Estimate: $20,800
Actual: $20,800


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract