Letting Schedule for Fort Worth District (FY 2014)
| Fort Worth District (FY 2014) |
| Erath | Jack | Johnson | Palo Pinto | Parker | Tarrant | Wise | ||||||
Erath County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
|---|---|---|---|---|---|---|
| 0079-05-052 | US 67 | Tentative | SEP 2013 | $78,425 | 1 | PLACE GABIONS ALONG INTERIOR BENT AND MATTRESSES BACK TO |
| 0257-06-026 | SH 6 | Tentative | APR 2014 | $1,841,607 | 1 | FLEX BASE REPAIR, MILL AND HMAC OVERLAY |
| 0902-49-063 | CR | Tentative | MAY 2014 | $480,766 | 6 | REPLACE BRIDGE AND APPROACHES |
Jack County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0902-40-022 | CR | Tentative | DEC 2013 | $425,325 | 6 | REPLACE BRIDGE AND APPROACHES |
| 1309-01-029 | FM 1156 | Tentative | JUN 2014 | $909,695 | 6 | REPLACE THE BRIDGE AND APPROACHES |
| 1333-03-018 | FM 1191 | Tentative | MAY 2014 | $2,536,022 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH, PROPOSED 2 - 12'LANES |
Johnson County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0259-04-039 | US 67 | Tentative | MAY 2014 | $3,932,745 | 1 | HOTMIX OVERLAY |
| 0259-05-070 | US 67 | Tentative | AUG 2014 | $2,226,504 | 1 | RESURFACE ROADWAY |
| 0259-05-071 | US 67 | Tentative | OCT 2013 | $150,377 | 1 | WORK CONSISTING OF INSTALLATION OF A FULL TRAFFIC - ACTUATED |
| 1181-02-035 | FM 917 | Tentative | APR 2014 | $2,332,544 | 1 | HOTMIX OVERLAY |
| 1599-02-014 | FM 916 | Tentative | AUG 2014 | $5,259,283 | 1 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
| 2213-01-013 | FM 2331 | Tentative | SEP 2013 | $4,240,180 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
| 2464-01-014 | FM 2415 | Tentative | MAY 2014 | $2,491,315 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
| 3372-01-014 | FM 3391 | Tentative | NOV 2013 | $203,200 | 3 | INSTALLATION OF A FULL TRAFFIC ACTUATED TRAFFIC SIGNAL |
Palo Pinto County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0250-02-044 | US 281 | Tentative | APR 2014 | $388,795 | 1 | REMOVAL OF ASBESTOS FROM BRIDGE |
| 0539-03-004 | SP 397 | Tentative | OCT 2013 | $406,032 | 1 | SEAL MAIN LANES |
| 1178-01-026 | FM 919 | Tentative | APR 2014 | $971,075 | 6 | REPLACE BRIDGE |
Parker County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0008-03-092 | IH 20 | Tentative | AUG 2014 | $4,000,000 | 1 | RELOCATION ENTRANCE AND EXIT RAMPS |
| 0008-03-103 | IH 20 | Tentative | AUG 2014 | $5,029,440 | 3 | WIDEN BRIDGE OVER IH 20 TO ACCOMMODATE 4 THRU LANES AND |
| 0080-06-029 | US 377 | Tentative | OCT 2013 | $889,423 | 1 | SEAL MAIN LANES AND SHOULDERS |
| 0313-07-017 | FM 51 | Tentative | OCT 2013 | $786,163 | 1 | SEAL MAIN LANES AND SHOULDERS |
| 0314-01-076 | IH 20 | Tentative | AUG 2014 | $2,674,659 | 1 | RESURFACE ROADWAY |
| 0314-01-080 | IH 20 | Tentative | OCT 2013 | $955,266 | 1 | SEAL FRONTAGE ROADS AND SHOULDERS |
| 0314-07-037 | IH 20 | Tentative | JAN 2014 | $9,131,296 | 1 | RECONSTRUCT AND EXTEND EBFR TO FM 1884 AND REVERSE ENTRANCE |
| 1068-05-011 | IH 30 | Tentative | OCT 2013 | $103,537 | 1 | SEAL FRONTAGE ROADS AND SHOULDERS |
| 1468-01-024 | FM 1189 | Tentative | AUG 2014 | $5,103,000 | 1 | WIDEN TO 2 - 11 FT LANES W / 3 FT SHOULDERS AND OVERLAY |
| 1605-01-014 | FM 1886 | Tentative | MAR 2014 | $4,585,220 | 1 | WIDEN ROADWAY TO 2 - 12' LANES WITH 4' SHOULDERS; CEMENT TREAT |
| 2291-01-013 | FM 1187 | Tentative | APR 2014 | $5,471,808 | 1 | PAVEMENT REHAB, ADD SHOULDERS AND HMAC OVERLAY WITH PAVEMENT |
Tarrant County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0014-01-022 | BU 287P | Tentative | NOV 2013 | $15,470,800 | 3 | CONSTRUCT NEW BRIDGE AT PROPOSED LOCATION OF BYPASS CHANNEL |
| 0014-01-024 | BU 287P | Tentative | NOV 2013 | ROW | ACQUISITION | |
| 0081-01-046 | US 377 | Tentative | MAY 2014 | $2,540,220 | 3 | INTERSECTION IMPROVEMENTS TO REDESIGN INTERCHANGE TO |
| 0171-04-073 | SH 199 | Tentative | MAR 2014 | $585,705 | 1 | SEAL COAT, PAVEMENT REPAIR, HMAC OVERLAY & PAVEMENT MARKINGS |
| 0171-05-081 | SH 199 | Tentative | NOV 2013 | $19,798,106 | 3 | CONSTRUCT BRIDGE AT NEW LOCATION OF PROPOSED BYPASS CHANNEL |
| 0172-02-072 | BU 287P | Tentative | MAY 2014 | $921,964 | 3 | CONSTRUCT BIKE / PEDESTRIAN PATH ON KENNEDALE PARKWAY |
| 0172-06-090 | US 287 | Tentative | MAR 2014 | $3,372,601 | 1 | HMAC OVERLAY; MAIN LANES, SHOULDERS AND RAMPS |
| 0718-02-063 | FM 156 | Tentative | JAN 2014 | $150,000 | 1 | INSTALLATION OF TRAFFIC - ACTUATED TRAFFIC SIGNAL |
| 0747-04-065 | FM 157 | Tentative | MAY 2014 | $8,844,005 | 8 | CONCRETE PAVEMENT REPAIRS, TRAFFIC SIGNAL, REPAIR AND |
| 0902-00-126 | VA | Tentative | SEP 2013 | $1,546,263 | 1 | CONCRETE PAVEMENT REPAIR; SPOT REPAIR |
| 0902-00-128 | VA | Tentative | SEP 2013 | $1,000,000 | 1 | PAVEMENT MARKINGS FOR FY 13 SEAL COAT |
| 0902-48-545 | VA | Tentative | SEP 2013 | $300,000 | 5 | CONSTRUCT PARK AND RIDE FACILITY IN TXDOT ROW BENEATH |
| 0902-48-576 | CS | Tentative | AUG 2014 | $3,620,103 | 3 | INTERSECTION IMPROVEMENTS |
| 0902-48-577 | CS | Tentative | APR 2014 | $9,582,358 | 3 | WIDEN FROM 5 LANE TO 7 LANES WITH TURN LANES AT MAJOR |
| 0902-48-582 | CS | Tentative | MAY 2014 | $427,893 | 3 | WESTRIDGE VILLAGE PEDESTRIAN DISTRICT INCLUDING CAMP BOWIE, |
| 0902-48-688 | VA | Tentative | MAR 2014 | $1,302,300 | 3 | CLOSE EAST 1ST XING @ UPRR; INSTALL MEDIAN AT PEACH @ BNSF; |
| 0902-48-722 | CS | Tentative | AUG 2014 | $1,316,000 | 7 | REPLACE EXISTING 2 LANE BRIDGE WITH NEW BRIDGE TO ACCOMMODAT |
| 0902-48-742 | CS | Tentative | MAY 2014 | $1,986,732 | 6 | REPLACE BRIDGE |
| 0902-48-756 | VA | Tentative | MAY 2014 | $1,654,750 | 3 | ADDITION OF QUAD GATES AT 3 CROSSINGS |
| 0902-48-827 | VA | Tentative | AUG 2014 | $652,371 | 3 | CITY OF FORT WORTH CORRIDOR REDEVELOPMENT PROGRAM |
| 0902-48-828 | VA | Tentative | AUG 2014 | $180,571 | 3 | CITY OF FORT WORTH CORRIDOR REDEVELOPMENT PROGRAM |
| 0902-48-838 | CS | Tentative | SEP 2013 | $8,445,280 | 3 | CONSTRUCT NEW ROADWAY AND BRIDGE ACROSS IH 20 - - - EXTENSION OF |
| 0902-48-844 | VA | Tentative | OCT 2013 | 10 | CONSTRUCT CURB RAMPS ON US 377, SH 26, SH 10, FM 1938 AND FM | |
| 1068-02-129 | IH 30 | Tentative | APR 2014 | $350,000 | 1 | REPAIR TO UNDERPASS |
| 1068-02-137 | IH 30 | Tentative | OCT 2013 | $265,000 | 10 | LANDSCAPE MONUMENT ON NORTHSIDE |
| 1068-02-141 | IH 30 | Tentative | MAR 2014 | $5,175,179 | 1 | REPAIR FAILURES, HMAC OVERLAY AND PAVEMENT MARKINGS |
| 1098-02-013 | FM 718 | Tentative | OCT 2013 | $126,985 | 1 | SEAL MAIN LANES AND SHOULDERS |
| 1603-03-033 | FM 1709 | Tentative | JAN 2014 | $845,666 | 3 | INTERSECTION IMPROVEMENT; WIDEN PAVEMENT FOR TURN LANE |
| 1603-03-036 | FM 1709 | Tentative | JAN 2014 | 5 | ACQUISITION | |
| 2266-02-136 | SH 360 | Tentative | NOV 2013 | 248,768,000 | 3 | CONSTRUCT 4 LANE TOLLWAY |
Wise County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0312-04-032 | FM 730 | Tentative | OCT 2013 | $10,666,572 | 1 | SEAL MAIN LANES AND SHOULDERS |
| 0902-20-097 | CR | Tentative | JUN 2014 | $1,079,004 | 6 | REPLACE BRIDGE AND APPROACHES |
| 0902-20-099 | CR | Tentative | AUG 2014 | $615,002 | 6 | REPLACE BRIDGE AND APPROACHES |
| 0902-20-100 | CR | Tentative | APR 2014 | $1,284,797 | 6 | REPLACE BRIDGE AND APPROACHES |
| 1310-03-025 | FM 2264 | Tentative | APR 2014 | $3,815,309 | 1 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH, PROPSED 2 - 12'LANES |
| 1606-02-019 | FM 2123 | Tentative | APR 2014 | $3,263,513 | 1 | WIDEN SHOULDER; 32' TOTAL WIDTH |
|