Letting Schedule for October, 2013 (FY 2014)

Last Update: Monday, November 17, 2014
October, 2013 (FY 2014) (see Links)
SEP 2013 | OCT 2013 | NOV 2013 | DEC 2013 | JAN 2014 | FEB 2014 | MAR 2014 | APR 2014 | MAY 2014 | JUN 2014 | JUL 2014 | AUG 2014
CCSJ County/
District
Highway Let Status Contract
Cost
Fund
Cat
Description
0915-12-394 Bexar/
San Antonio
CS Actual $748,040 3 CONSTRUCT BIKE LANE
0912-31-265 Brazoria/
Houston
CR Actual $448,818 6 REPLACE BRIDGE AND APPROACHES (NBI# 12020AA0862005)
1425-02-015 Cameron/
Pharr
FM 1420 Actual $1,725,817 1 SEAL COAT
0919-00-069 Cass/
Atlanta
VA Actual $5,620,239 1 2014 DISTRICT SEAL COAT
0549-03-023 Collin/
Dallas
SH 121 Actual $3,039,939 1 BASE REPAIR, MILL, AND OVERLAY
0253-03-068 Comal/
San Antonio
US 281 Actual $3,132,254 3 CONSTRUCT TURNAROUNDS
0800-04-009 Crosby/
Lubbock
FM 378 Actual $2,664,168 1 REHABILITATION OF ROADWAY
0040-01-046 Dallam/
Amarillo
US 87 Actual $10,070,697 1 SEAL COAT
0048-01-062 Dallas/
Dallas
SH 342 Actual $7,850,200 1 SEAL COAT, PVMT MKGS
0918-47-012 Dallas/
Dallas
CS Actual $896,210 3 PEDESTRIAN WALKWAY IMPROVEMENTS
0918-46-255 Denton/
Dallas
CS Actual $912,023 3 CONSTRUCT SIDEWALKS, INSTALL SCHOOL ZONE SIGNS, INSTALL
0042-06-067 Donley/
Childress
US 287 Actual $2,248,103 11 ASPHALTIC CONCRETE PAVEMENT OVERLAY
0005-01-105 Ector/
Odessa
BI 20-E Actual $1,504,556 8 TEXTURIZE SHOULDERS
2224-01-011 Ector/
Odessa
LP 338 Actual $362,379 8 INSTALL TRAFFIC SIGNAL
1046-01-024 El Paso/
El Paso
FM 659 Actual $799,990 3 FIBER INTERCONNECT FOR FM 659_ (ZARAGOZA ROAD)
0188-09-043 Fort Bend/
Houston
FM 723 Actual $180,487 1 INSTALL LEFT TURN LANE
0912-34-159 Fort Bend/
Houston
CR Actual $395,576 6 REPLACE BRIDGE AND APPROACHES (NBI# 12080AA0905001)
0917-20-011 Freestone/
Bryan
CR Actual $448,407 6 REPLACE BRIDGE AND APPROACHES
0017-07-130 Frio/
San Antonio
IH 35 Actual $3,224,249 1 RECONSTRUCT & RECONFIGURE RAMPS AND FRONTAGE ROAD
0405-01-024 Glasscock/
San Angelo
SH 158 Actual $19,242,154 1 GRADING, BASE, STRUCTURES, SURFACING
0025-06-052 Gonzales/
Yoakum
US 90A Actual $5,288,543 1 SEAL COAT
0666-01-024 Grayson/
Paris
FM 691 Actual $3,093,915 1 REHABILITATE & WIDEN EXISTING ROADWAY
0043-02-071 Hardeman/
Childress
US 287 Actual $1,474,833 1 ASPHALTIC CONCRETE PAVEMENT OVERLAY
0500-03-574 Harris/
Houston
IH 45 Actual $48,776,267 1 CONSTRUCT DIRECT CONNECTOR IH 610 EB TO IH 45 NB
0502-01-207 Harris/
Houston
SH 225 Actual $1,050,534 1 CLEAN AND SEAL JOINTS, FULL DEPTH REPAIR, MILLING AND 1.5"
0912-00-424 Harris/
Houston
VA Actual $2,697,458 3 PEDESTRIAN AND SIGNAL IMPROVEMENTS IN AIRLINE DISTRICT
0016-02-135 Hays/
Austin
IH 35 Actual $12,215,171 ROW REPLACE BRIDGE
2293-01-024 Hays/
Austin
FM 2439 Actual $6,950,845 ROW ADD CENTER TURN LANE
0888-01-020 Hill/
Waco
FM 934 Actual $3,393,641 1 WIDEN PAVEMENT TO ADD SHOULDERS, PROVIDE SAFETY UPGRADES AND
0909-37-050 Hill/
Waco
PW Actual $525,684 10 RESURFACE AIRSTRIP RUNWAY / TAXIWAY, PARKING LOTS AND
2182-02-008 Hockley/
Lubbock
FM 1585 Actual $3,762,235 1 REHABILITATION OF EXISTING ROAD
0010-02-088 Hopkins/
Paris
IH 30 Actual $7,079,441 1 SEAL COAT
0086-11-044 Jim Wells/
San Antonio
SH 44 Actual $7,493,684 1 2014 DISTRICT WIDE SEAL COAT (LOW CONTROL CSJ)
0259-05-071 Johnson/
Fort Worth
US 67 Actual $131,000 1 WORK CONSISTING OF INSTALLATION OF A FULL TRAFFIC - ACTUATED
0688-02-053 Lamar/
Paris
FM 79 Actual $398,452 3 CONSTRUCT SIDEWALKS, INSTALL CROSSWALKS, INSTALL SIGNS,
0952-01-051 Liberty/
Beaumont
FM 1008 Actual $3,175,645 8 PROVIDE ADDITIONAL PAVED SURFACE WIDTH
0582-02-018 Lipscomb/
Amarillo
SH 305 Actual $7,694,756 11 RESTORING SHOULDERS AND MINOR SAFETY UPGRADE
0463-03-042 Midland/
Odessa
SH 158 Actual $10,798,004 11 PAVEMENT STRUCTURE RESTORATION
2133-03-019 Milam/
Bryan
FM 2269 Actual $3,309,495 8 SAFETY WORK CONSISTING OF SUBGRADE WIDENING, FLEXIBLE BASE,
1062-01-029 Montgomery/
Houston
FM 1485 Actual $1,568,959 8 BASE REPAIR AND 2" ACP O / L
0053-12-057 Nolan/
Abilene
US 84 Actual $11,548,045 1 RECONSTRUCTION, REALIGNMENT, WIDENING, STRUCTURES, SAFETY
2263-03-029 Nueces/
Corpus Christi
SH 361 Actual $12,988,211 3 CONST 4 LANE CURB & GUTTER WITH RAISED MEDIAN & HIKE / BIKE PATH
1894-01-020 Panola/
Atlanta
FM 1971 Actual $437,577 6 REHABILITATE BRIDGE AND APPROACHES
0314-07-037 Parker/
Fort Worth
IH 20 Actual $9,453,090 1 RECONSTRUCT AND EXTEND EBFR TO FM 1884 AND REVERSE ENTRANCE
2444-01-009 Parmer/
Lubbock
FM 1172 Actual $3,262,224 11 REHABILITATION OF EXISTING ROAD
0213-03-096 Polk/
Lufkin
US 190 Actual $35,564 8 INSTALL ADVANCE WARNING SIGNALS AND SIGNS
0213-12-009 Polk/
Lufkin
PR 56 Actual $1,144,070 1 REHAB & WIDEN EXISTING PAVEMENT
0910-00-098 Smith/
Tyler
VA Actual $177,096 11 INSTALL DYNAMIC MESSAGE SIGNS (DMS) FOR TRAFFIC MANAGEMENT
0039-13-015 Starr/
Pharr
FM 1430 Actual $2,855,201 1 SEAL COAT
0405-02-024 Sterling/
San Angelo
SH 158 Actual $22,606,154 1 GRADING, BASE, STRUCTURES, SURFACING
0014-16-179 Tarrant/
Fort Worth
IH 35W Actual 129,997,000 12 RECONSTRUCT FREEWAY AND ADD MANAGED TOLL LANES
0902-48-777 Tarrant/
Fort Worth
CS Actual $384,637 3 2009 SRTS INFRASTRUCTURE PROJECT;CROSSWALK IMPROVEMENTS, BIKE
0902-48-831 Tarrant/
Fort Worth
VA Actual $31,992,540 3 DEFERRAL REINSTATEMENT
0902-48-844 Tarrant/
Fort Worth
VA Actual $1,813,397 10 CONSTRUCT CURB RAMPS ON US 377, SH 26, SH 10, FM 1938 AND FM
1384-01-021 Titus/
Atlanta
FM 1402 Actual $1,351,579 3 IMPROVE ALIGNMENT AND ADD TURN LANES AT HART'S BLUFF SCHOOL
0914-04-255 Travis/
Austin
CR Actual $17,614,337 3 CONST 4 - LN DIVIDED RDWY W / BIKE LN & SIDEWALKS
3136-01-172 Travis/
Austin
LP 1 Actual $7,773,016 3 ADD BICYCLE BRIDGE
0402-02-024 Upshur/
Atlanta
SH 154 Actual $1,272,044 3 WIDEN EXISTING ROADWAY
0675-06-099 Walker/
Bryan
IH 45 Actual $5,387,237 1 OVERLAY CONSISTING OF MILLING, HMA LEVEL - UP, SMA OVERLAY AND
0043-09-121 Wichita/
Wichita Falls
IH 44 Actual $5,404,266 1 SEAL COAT
0312-04-032 Wise/
Fort Worth
FM 730 Actual $6,971,232 1 SEAL MAIN LANES AND SHOULDERS


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract