Detail Letting Schedule for Jack County (FY 2014)
| Jack County (FY 2014) |
CCSJ: 0902-40-022 | |||
| District: | Fort Worth | Let Date: | DEC 2013 |
| Highway: | CR | Let Status: | Tentative |
| Project ID: | BR 2008(528) | CSJ: | 0902-40-022 |
| Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
| Limits From: | SQUAW MOUNTAIN RD OVER W FRK TRINIT | Fund Cat: | 6 |
| Limits To: | . | Estimate: | $425,325 |
| Length: | 0.1 Miles | Actual: | |
|
Back... |
Totals for 0902-40-022 | ||
|---|---|---|---|
| Length: | 0.1 Miles | ||
| Estimate: | $425,325 | ||
| Actual: | |||
CCSJ: 1309-01-029 | |||
| District: | Fort Worth | Let Date: | JUN 2014 |
| Highway: | FM 1156 | Let Status: | Tentative |
| Project ID: | BR ( ) | CSJ: | 1309-01-029 |
| Description: | REPLACE THE BRIDGE AND APPROACHES | Handling Code: |
|
| Limits From: | FM 1156 OVER BEANS CREEK | Fund Cat: | 6 |
| Limits To: | . | Estimate: | $909,695 |
| Length: | 0.1 Miles | Actual: | |
|
Back... |
Totals for 1309-01-029 | ||
| Length: | 0.1 Miles | ||
| Estimate: | $909,695 | ||
| Actual: | |||
CCSJ: 1333-03-018 | |||
| District: | Fort Worth | Let Date: | MAY 2014 |
| Highway: | FM 1191 | Let Status: | Tentative |
| Project ID: | STP ( )HRR | CSJ: | 1333-03-018 |
| Description: | PROVIDE ADDITIONAL PAVED SURFACE WIDTH, PROPOSED 2 - 12'LANES | Handling Code: |
|
| Limits From: | US 380 | Fund Cat: | 8 |
| Limits To: | YOUNG COUNTY LINE | Estimate: | $2,536,022 |
| Length: | 7.1 Miles | Actual: | |
|
Back... |
Totals for 1333-03-018 | ||
| Length: | 7.1 Miles | ||
| Estimate: | $2,536,022 | ||
| Actual: | |||
|