Letting Schedule for August, 2013 (FY 2013)
| August, 2013 (FY 2013) | (see Links) |
| SEP 2012 | OCT 2012 | NOV 2012 | DEC 2012 | JAN 2013 | FEB 2013 | MAR 2013 | APR 2013 | MAY 2013 | JUN 2013 | JUL 2013 | AUG 2013 | ||||||
| CCSJ | County/ District |
Highway | Let Status | Contract Cost |
Fund Cat |
Description |
|---|---|---|---|---|---|---|
| 0156-05-048 | Archer/ Wichita Falls |
US 277 | Approved | $15,500,000 | 8 | UPGRADE TO 4 LANE DIVIDED FACILITY |
| 0114-06-030 | Bastrop/ Austin |
US 290 | Approved | $22,286,595 | 3 | WIDEN TO 4 LANE DIVIDED |
| 0914-18-094 | Bastrop/ Austin |
VA | Approved | $2,393,241 | 3 | DOWNTOWN TRANSIT STOP & BIKE / PED CONNS |
| 0909-36-135 | Bell/ Waco |
CS | Approved | $2,294,576 | 3 | CONSTRUCT ALTERNATE TRANSPORATION ROUTE CONSISTING OF |
| 0915-12-394 | Bexar/ San Antonio |
CS | Approved | $676,938 | 7 | CONSTRUCT BIKE LANE |
| 0915-12-510 | Bexar/ San Antonio |
CS | Approved | $3,940,630 | 7 | RECONSTRUCT ROADWAY AND INCLUDES SIDEWALKS, CURB, DRAINAGE |
| 0253-02-030 | Blanco/ Austin |
US 281 | Approved | $6,062,000 | 3 | UPGRADE TO SUPER 2 (ADD PASSING LANE) |
| 0912-31-224 | Brazoria/ Houston |
CR | Approved | $12,159,874 | 3 | RECONSTRUCT AND WIDEN TO 4 LANES DIVIDED |
| 0912-31-270 | Brazoria/ Houston |
CS | Approved | $4,416,560 | 3 | CONSTRUCT 4 LANE DIVIDED ROADWAY WITH RAISED MEDIANS |
| 0648-03-050 | Burleson/ Bryan |
FM 60 | Approved | $7,800,000 | 3 | NEW LOCATION NON - FREEWAY FACILITY CONSISTING OF GRADING, |
| 0152-02-070 | Caldwell/ Austin |
US 183 | Approved | $10,825,756 | 3 | RECONSTRUCT TO 5 - LANE URBAN SECTION |
| 0709-01-024 | Colorado/ Yoakum |
FM 102 | Approved | $4,510,000 | 8 | PAVEMENT REPAIR & SHOULDER WIDENING |
| 0215-02-048 | Comal/ San Antonio |
BS 46-C | Approved | $9,000,000 | 3 | EXPAND FROM 2 LANES TO 4 LANES |
| 0253-03-068 | Comal/ San Antonio |
US 281 | Approved | $3,000,000 | 3 | CONSTRUCT TURNAROUNDS |
| 0923-17-073 | Comanche/ Brownwood |
CR | Approved | $1,136,623 | 6 | REPLACE BRIDGE AND APPROACHES |
| 1702-02-001 | Dallam/ Amarillo |
SS 24 | Approved | $2,992,884 | 11 | NEW LOCATION 2 LANE RDWY |
| 0196-03-264 | Dallas/ Dallas |
IH 35E | Approved | $280,207 | 3 | UPDATE OF SIGNS ON TXDOT FACILITIES WITH NTTA INTERCHANGES |
| 0918-45-761 | Dallas/ Dallas |
CS | Approved | $1,745,959 | ROW | REPLACE BRIDGE AND APPROACHES |
| 0918-47-012 | Dallas/ Dallas |
CS | Approved | $754,211 | 8 | PEDESTRIAN WALKWAY IMPROVEMENTS |
| 1047-03-063 | Dallas/ Dallas |
FM 1382 | Approved | $1,596,419 | 3 | WIDEN FROM 4 LANES TO 6 LANES AND UPGRADE TRAFFIC SIGNALS |
| 0380-06-015 | Dawson/ Lubbock |
SH 349 | Approved | $17,164,000 | 11 | WIDEN NON - FREEWAY |
| 0136-03-044 | Delta/ Paris |
SH 24 | Approved | $34,355,059 | 6 | UPGRADING OF EXISTING 2 - LANE TO A 4 - LANE DIVIDED HIGHWAY |
| 0081-03-051 | Denton/ Dallas |
US 377 | Approved | $3,656,076 | 6 | REHABILITATE AND WIDEN BRIDGE AND APPROACHES |
| 0918-46-255 | Denton/ Dallas |
CS | Approved | $1,055,654 | 8 | CONSTRUCT SIDEWALKS, INSTALL SCHOOL ZONE SIGNS, INSTALL |
| 0918-46-258 | Denton/ Dallas |
CS | Approved | $574,658 | 9 | DENTON A - TRAIN COMMUNITY ENHANCEMENTS - INSTALL SAFETY |
| 0913-17-035 | Dewitt/ Yoakum |
CR | Approved | $340,398 | 6 | REPLACE BRIDGE AND APPROACHES |
| 0228-06-082 | Ector/ Odessa |
US 385 | Approved | $3,000,000 | 8 | INTERSECTION IMPROVEMENTS, TURN LANES, SIGNALIZATION, |
| 0002-01-090 | El Paso/ El Paso |
SH 20 | Approved | $8,914,375 | 3 | ROADWAY IMPROVEMENTS AND REHABILITATION (PHASE II) |
| 0002-02-052 | El Paso/ El Paso |
SH 20 | Approved | $240,000 | 8 | INTERSECTION IMPROVEMENTS |
| 0002-14-040 | El Paso/ El Paso |
FM 258 | Approved | $336,538 | 1 | REPLACE STRUCTURE |
| 0374-02-094 | El Paso/ El Paso |
US 62 | Approved | $4,601,514 | 3 | ROADWAY WIDENING (SHOULDER IMPROVE, SIDEWALKS, TRAFFIC |
| 0924-06-429 | El Paso/ El Paso |
CS | Approved | $1,164,936 | 3 | BRIDGE RECONSTRUCTION |
| 0924-06-432 | El Paso/ El Paso |
CS | Approved | $2,918,003 | 3 | PASEO DEL NORTE IMPROVEMENTS |
| 2121-03-153 | El Paso/ El Paso |
IH 10 | Approved | $9,465,001 | 3 | AESTHETICS AT AIRWAY INTERSECTION TO INCLUDE FENCING, LANDSC |
| 2121-04-092 | El Paso/ El Paso |
IH 10 | Approved | $21,857,753 | 3 | WESTBOUND BRAIDED RAMPS |
| 0834-01-013 | Ellis/ Dallas |
FM 308 | Approved | $3,500,000 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
| 0918-22-145 | Ellis/ Dallas |
CR | Approved | $199,110 | 6 | REPLACE BRIDGE AND APPROACHES |
| 0079-08-003 | Erath/ Fort Worth |
US 67 | Approved | $12,763,214 | 11 | CONSTRUCT US 67 ON ALTERNATE ROUTE SOUTH AND WEST OF DUBLIN |
| 0908-23-027 | Fisher/ Abilene |
CR | Approved | $252,196 | 6 | REPLACE BRIDGE AND APPROACHES |
| 0908-23-029 | Fisher/ Abilene |
CR | Approved | $320,481 | 6 | REPLACE BRIDGE AND APPROACHES |
| 0908-23-030 | Fisher/ Abilene |
CR | Approved | $666,477 | 6 | REPLACE BRIDGE |
| 0187-05-050 | Fort Bend/ Houston |
SP 10 | Approved | $21,999,740 | 3 | CONSTRUCT 2 - LANE RURAL FACILITY ON A NEW LOCATION AND REMOVE |
| 0912-34-159 | Fort Bend/ Houston |
CR | Approved | $279,000 | 6 | REPLACE BRIDGE AND APPROACHES (NBI# 12080AA0905001) |
| 1258-03-042 | Fort Bend/ Houston |
FM 1093 | Approved | $32,000,000 | 3 | CONSTRUCT 4 TOLL LANES WITH TWO 2 - LANE FRONTAGE ROADS |
| 1258-03-043 | Fort Bend/ Houston |
FM 1093 | Approved | $28,000,000 | 3 | 4 TOLL LNS FROM W OF SPRING GREEN TO W OF KATY - GASTON & TWO |
| 0017-07-132 | Frio/ San Antonio |
IH 35 | Approved | $980,000 | 8 | INSTALL TRAFFIC SIGNAL |
| 0912-73-120 | Galveston/ Houston |
CR | Approved | $355,000 | 6 | REPLACE BRIDGE |
| 0976-03-100 | Galveston/ Houston |
FM 518 | Approved | $2,410,400 | 3 | ACCESS MANAGEMENT IMPROVEMENTS INCLUDING RAISED MEDIANS, |
| 2523-01-024 | Galveston/ Houston |
FM 2004 | Approved | $1,026,796 | 1 | INTERSECTION IMPROVEMENTS |
| 1007-02-017 | Gonzales/ Yoakum |
FM 532 | Approved | $6,675,040 | 8 | ROADWAY WIDENING |
| 0047-03-076 | Grayson/ Paris |
US 75 | Approved | $9,461,281 | 3 | UPGRADE ASPHALT TO CONCRETE PAVEMENT |
| 0047-03-077 | Grayson/ Paris |
US 75 | Approved | $638,221 | 3 | RELOCATE EXISTING EXIT RAMP |
| 0047-18-068 | Grayson/ Paris |
US 75 | Approved | $5,891,000 | 11 | WIDEN EXISTING BRIDGE OVERPASS |
| 0138-01-095 | Gregg/ Tyler |
SH 31 | Approved | $229,330 | 10 | LANDSCAPING |
| 0138-16-003 | Gregg/ Tyler |
US 259 | Approved | $450,000 | 11 | CONSTRUCT LEFT TURN LANE |
| 0424-03-024 | Gregg/ Tyler |
FM 349 | Approved | $1,200,000 | 3 | WIDEN 2 LN ROADWAY FOR CENTER TWO - WAY LEFT TURN LANE (TWLTL) |
| 0545-04-046 | Gregg/ Tyler |
SH 42 | Approved | $4,500,000 | 3 | CONSTRUCT CENTER TWO - WAY LEFT TURN LANE (TWLTL) |
| 2158-01-013 | Gregg/ Tyler |
FM 2275 | Approved | $13,640,938 | 3 | CONSTRUCT 4 LANE DIVIDED ROADWAY ON NEW LOCATION (PH 2 OF 3) |
| 0050-03-090 | Grimes/ Bryan |
SH 6 | Approved | $2,700,000 | 8 | UPGRADING OF A FREEWAY FACILITY CONSISTING OF GRADING, |
| 0920-03-073 | Hardin/ Beaumont |
VA | Approved | $3,423,077 | 5 | CONSTRUCT A HIKE AND BIKE TRAIL |
| 0027-09-100 | Harris/ Houston |
US 90A | Approved | $1,662,239 | 8 | INSTALL SAFTY LIGHTING |
| 0050-06-081 | Harris/ Houston |
US 290 | Approved | $85,000,000 | 2M | RECONSTRUCT AND WIDEN TO 8 MAIN LANES WITH 2 REVERSIBLE |
| 0051-02-079 | Harris/ Houston |
SH 3 | Approved | $1,824,030 | 1 | ADDITION OF RIGHT TURN LANE STORAGE, SIDEWALKS, RAILROAD |
| 0271-14-213 | Harris/ Houston |
IH 610 | Approved | 130,000,000 | 5 | RECONSTRUCT US 290 / IH 610 INTERCHANGE WITH DIRECT CONNECTORS |
| 0271-14-224 | Harris/ Houston |
IH 610 | Approved | $1,800,000 | 1 | ASPHALT OVERLAY OF IH 610 MAIN LANES AT IH 45 |
| 0500-03-574 | Harris/ Houston |
IH 45 | Approved | $45,000,000 | 7 | CONSTRUCT DIRECT CONNECTOR IH 610 EB TO IH 45 NB |
| 0508-01-276 | Harris/ Houston |
IH 10 | Approved | $38,328,980 | ROW | REPLACE BRIDGE AND APPROACHES |
| 0912-00-424 | Harris/ Houston |
VA | Approved | $2,213,019 | 3 | PEDESTRIAN AND SIGNAL IMPROVEMENTS IN AIRLINE DISTRICT |
| 0912-00-484 | Harris/ Houston |
VA | Approved | $700,000 | 8 | UPGRADE & MODERNIZE SIGNALS |
| 0912-71-005 | Harris/ Houston |
VA | Approved | $1,300,000 | 3 | INSTALL UPS / BATTERY BACKUPS AT VARIOUS LOCATIONS CITYWIDE |
| 0912-72-061 | Harris/ Houston |
CR | Approved | $722,819 | 6 | REPLACE BRIDGE (NBI# 12102AA0207001) |
| 0912-72-199 | Harris/ Houston |
VA | Approved | $4,133,875 | 3 | HARRIS COUNTY RCTSS PROGRAM PHASE 3 |
| 0976-01-019 | Harris/ Houston |
FM 865 | Approved | $12,600,000 | 3 | WIDEN FROM 2 TO 4 LANES WITH CURB AND GUTTER |
| 1685-07-019 | Harris/ Houston |
BF1960A | Approved | $10,280,376 | 3 | BASE REPAIR, MILL, SEAL COAT, 1.5" ACP OVERLAY, |
| 0238-01-030 | Hartley/ Amarillo |
US 54 | Approved | $4,500,000 | 6 | REPLACE BRIDGE & APPR |
| 0016-02-133 | Hays/ Austin |
IH 35 | Approved | $11,038,521 | 3 | WIDEN EXISTING BRIDGE & ADD TURNAROUND BRDG @ CEMENT PLANT |
| 0016-02-135 | Hays/ Austin |
IH 35 | Approved | $14,574,670 | ROW | REPLACE BRIDGE |
| 0285-03-053 | Hays/ Austin |
RM 12 | Approved | $1,848,752 | 3 | INSTALL CENTER TURN LANE & SHLDRS |
| 0286-01-053 | Hays/ Austin |
SH 80 | Approved | $5,343,351 | 3 | INTERSECTION IMPROVEMENTS |
| 0914-33-065 | Hays/ Austin |
VA | Approved | $559,595 | 3 | CONSTRUCT 2650 LF OF ADA SIDEWALK, CROSSWALKS, BICYCLE & |
| 2293-01-023 | Hays/ Austin |
FM 2439 | Approved | $1,991,563 | 3 | ADD CENTER TURN LANE & 2 - LANE DIVIDED SECTION WITH SHOULDERS |
| 2293-01-024 | Hays/ Austin |
FM 2439 | Approved | $5,176,147 | ROW | ADD CENTER TURN LANE |
| 0458-01-022 | Henderson/ Tyler |
FM 59 | Approved | $7,500,000 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
| 0864-01-065 | Hidalgo/ Pharr |
FM 494 | Approved | $578,988 | 3 | SIGNAL RETIMING & ADD LANES @ US 83 |
| 0080-11-001 | Hood/ Fort Worth |
US 377 | Approved | $21,602,108 | 3 | CONSTRUCT 4 LANES ON NEW LOCATION AS ALTERNATE ROUTE IN |
| 0108-09-043 | Hopkins/ Paris |
SH 19 | Approved | $1,500,000 | 8 | SEAL COAT AND RESTRIPE FOR SUPER 2 |
| 0908-12-019 | Howard/ Abilene |
VA | Approved | $51,423,661 | 1 | CONSTRUCT NEW RELIEF ROUTE |
| 0002-06-051 | Hudspeth/ El Paso |
IH 10 | Approved | $8,146,000 | 8 | INSTALL MEDIAN BARRIER |
| 1497-01-012 | Hunt/ Paris |
FM 1568 | Approved | $2,842,904 | 1 | REHABILITATION OF EXISTING ROAD |
| 0920-38-239 | Jefferson/ Beaumont |
CS | Approved | $718,011 | 9 | CONSTRUCT HIKE AND BIKE TRAIL |
| 0019-01-139 | Johnson/ Fort Worth |
SH 174 | Approved | $290,538 | 3 | INSTALLATION OF FULL TRAFFIC ACTUATED TRAFFIC SIGNAL |
| 0902-50-079 | Johnson/ Fort Worth |
CS | Approved | $1,546,000 | 3 | CONSTRUCT PARK AND RIDE FACILITY |
| 0902-50-108 | Johnson/ Fort Worth |
CR | Approved | $385,331 | 6 | REPLACE BRIDGE AND APPROACHES |
| 0270-07-029 | Karnes/ Corpus Christi |
SH 72 | Approved | $18,500,000 | 8 | REHAB AND ADD PASSING LANES |
| 0751-01-044 | Kaufman/ Dallas |
FM 148 | Approved | $1,412,563 | 3 | WIDEN EXISTING 2 LANE FACILITY TO 4 LANES |
| 0950-02-012 | King/ Childress |
FM 193 | Approved | $609,373 | 6 | UPGRADE BRIDGE RAILING AND APPROACH GUARD FENCE |
| 0017-08-085 | La Salle/ Laredo |
IH 35 | Approved | $3,202,500 | 8 | CABLE BARRIER |
| 0913-29-043 | Lavaca/ Yoakum |
CR | Approved | $361,348 | 6 | REPLACE BRIDGE AND APPROACHES |
| 0813-01-096 | Liberty/ Beaumont |
FM 787 | Approved | $1,057,692 | 6 | REPLACE BRIDGE AND APPROACHES |
| 1421-01-024 | Liberty/ Beaumont |
FM 1413 | Approved | $1,800,000 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH (WIDENING TO 28 FT.) |
| 0700-04-045 | Llano/ Austin |
SH 71 | Approved | $4,040,222 | 1 | UPGRADE TO SUPER 2 & ADD LTL'S |
| 0035-05-055 | Menard/ San Angelo |
US 83 | Approved | $6,809,400 | 8 | ADD PASSING LANES |
| 0338-11-051 | Montgomery/ Houston |
LP 336 | Approved | $5,701,486 | 1 | WIDEN TO 4 LANES UNDIVIDED RURAL |
| 0093-02-015 | Navarro/ Dallas |
SH 14 | Approved | $8,580,576 | 3 | REPLACE RAILROAD UNDERPASS |
| 0916-00-071 | Nueces/ Corpus Christi |
VA | Approved | $8,500,000 | 8 | INTERSECTION IMPROVEMENTS |
| 0916-00-073 | Nueces/ Corpus Christi |
VA | Approved | $2,100,000 | 8 | INTERSECTION IMPROVEMENTS |
| 2263-03-029 | Nueces/ Corpus Christi |
SH 361 | Approved | $12,400,000 | 3 | CONST 4 LANE CURB & GUTTER WITH RAISED MEDIAN & HIKE / BIKE PATH |
| 2343-01-036 | Nueces/ Corpus Christi |
FM 2444 | Approved | $20,000,000 | 3 | CONSTRUCT ADDITIONAL LANES AND ACCESS MANAGEMENT |
| 0306-01-059 | Orange/ Beaumont |
SH 73 | Approved | $7,216,860 | 6 | REPAIR BRIDGE |
| 1894-01-020 | Panola/ Atlanta |
FM 1971 | Approved | $240,000 | 6 | REHABILITATE BRIDGE AND APPROACHES |
| 3516-01-015 | Parker/ Fort Worth |
FM 3325 | Approved | $3,393,560 | 1 | WIDEN 2 - 12 LANES W / 8' SHOULDERS FROM FM 1886 TO WHITE |
| 0177-01-099 | Polk/ Lufkin |
US 59 | Approved | $2,210,000 | 8 | REMOVE CROSSOVERS AND CONSTRUCT TURN - AROUNDS WITH |
| 2635-02-022 | Randall/ Amarillo |
LP 335 | Approved | $33,126,137 | 3 | ADDITIONAL 2 LANES AND BRIDGES |
| 1014-03-049 | Rockwall/ Dallas |
FM 740 | Approved | $13,334,493 | 3 | WIDEN 2 LANE TO 4 LANE DIVIDED URBAN |
| 1091-04-019 | Rockwall/ Dallas |
FM 740 | Approved | $1,489,340 | 8 | CONSTRUCT SIDEWALKS, INSTALL CROSSWALKS AND INSTALL SCHOOL |
| 0245-08-040 | Rusk/ Tyler |
SH 64 | Approved | $1,300,000 | 11 | PROVIDE OPERATIONAL IMPROVEMENT TO ELIMINATE BOTTLENECK |
| 0177-02-089 | San Jacinto/ Lufkin |
US 59 | Approved | $8,586,339 | 11 | ADD SB FRONTAGE RD & RECONSTRUCT MAIN LANES |
| 2521-01-015 | San Patricio/ Corpus Christi |
FM 1068 | Approved | $1,068,213 | 8 | WIDEN ROADWAY |
| 0424-01-045 | Smith/ Tyler |
SH 31 | Approved | $3,015,356 | 1 | WIDEN 2 LN ROADWAY TO SUPER - 2 (3 LANE) CRITERIA |
| 2075-02-045 | Smith/ Tyler |
LP 323 | Approved | $6,500,000 | 3 | WIDEN FROM 4 LNS TO 6 LNS & REPLACE COTTON BELT R / R U / P |
| 0364-06-011 | Tarrant/ Fort Worth |
SH 26 | Approved | $1,669,232 | 3 | GRAPEVINE LINKS HIKE AND BIKE TRAIL CONNECTION |
| 0718-02-065 | Tarrant/ Fort Worth |
FM 156 | Approved | $326,000 | 8 | CONSTRUCT RIGHT TURN LANE - SB SIDE ONLY |
| 0902-00-134 | Tarrant/ Fort Worth |
VA | Approved | $400,000 | 1 | NO TRUCKS LEFT LANE SIGN STRUCTURES TO IMPLEMENT |
| 0902-48-186 | Tarrant/ Fort Worth |
CS | Approved | $549,248 | 3 | INTERSECTION IMPROVEMENTS |
| 0902-48-539 | Tarrant/ Fort Worth |
CS | Approved | $10,084,969 | 12 | REPLACE BRIDGE |
| 0902-48-645 | Tarrant/ Fort Worth |
VA | Approved | $200,000 | 3 | INSTALL GATES AT HALTOM RD & DART;UPGRADE ELECTRONICS IN PRE |
| 0902-48-777 | Tarrant/ Fort Worth |
CS | Approved | $254,569 | 8 | 2009 SRTS INFRASTRUCTURE PROJECT;CROSSWALK IMPROVEMENTS, BIKE |
| 0902-48-791 | Tarrant/ Fort Worth |
VA | Approved | $5,520,125 | 3 | CONSTRUCT FIVE PEDESTRIAN AND BICYCLE CONNECTIONS TO TRINITY |
| 0902-48-802 | Tarrant/ Fort Worth |
VA | Approved | $764,915 | 7 | TRAVEL DEMAND MANAGEMENT - COMPUTERIZED GIS FOR SUPPLY AND |
| 0902-48-829 | Tarrant/ Fort Worth |
VA | Approved | $625,954 | 3 | FORT WORTH URBAN VILLAGES AND COMMERCIAL CORRIDORS |
| 1068-03-021 | Tarrant/ Fort Worth |
SS 341 | Approved | $300,000 | 3 | LANDSCAPE ENHANCEMENT IN WHITE SETTLEMENT |
| 2079-01-041 | Tarrant/ Fort Worth |
FM 1220 | Approved | $5,501,022 | 1 | CONSTRUCT LEFT TURN BAYS, 10'SHLDERS, EXTEND CULVERTS, REPAIR |
| 0034-01-124 | Taylor/ Abilene |
US 83 | Approved | $3,721,952 | 3 | RELOCATE RAMPS AND RECONSTRUCT FRONTAGE ROADS |
| 0699-03-017 | Taylor/ Abilene |
FM 613 | Approved | $1,404,889 | 8 | REHAB & WIDEN |
| 2398-01-047 | Taylor/ Abilene |
LP 322 | Approved | $4,080,946 | 3 | RELOCATE RAMPS AND RECONSTRUCT FRONTAGE ROADS |
| 1384-01-021 | Titus/ Atlanta |
FM 1402 | Approved | $1,425,796 | 3 | IMPROVE ALIGNMENT AND ADD TURN LANES AT HART'S BLUFF SCHOOL |
| 0015-10-061 | Travis/ Austin |
IH 35 | Approved | $295,000 | 10 | LANDSCAPING AND IRRIGATION |
| 0015-13-362 | Travis/ Austin |
IH 35 | Approved | $2,949,183 | 3 | CONSTRUCT NB COLLECTOR - DISTRIBUTOR |
| 0015-13-375 | Travis/ Austin |
IH 35 | Approved | $150,000 | 10 | LANDSCAPING & IRRIGATION |
| 0015-13-376 | Travis/ Austin |
IH 35 | Approved | $220,000 | 10 | LANDSCAPING & IRRIGATION |
| 0114-02-096 | Travis/ Austin |
US 290 | Approved | $1,973,636 | ROW | EXTENSION OF GREGG MANOR ROAD AND RECONFIGURE SIGNALS |
| 0700-03-123 | Travis/ Austin |
SH 71 | Approved | $8,269,089 | 3 | ADD LEFT TURN LANE & SHOULDERS |
| 0700-03-125 | Travis/ Austin |
SH 71 | Approved | $8,852,489 | 3 | ADD LEFT TURN LANE & SHOULDERS |
| 0914-00-374 | Travis/ Austin |
VA | Approved | $754,399 | 8 | IMPROVE TRAFFIC SIGNALS_ (SH 16, SH 29, RM 2244, RM 152 ETC.) |
| 0914-04-255 | Travis/ Austin |
CR | Approved | $17,500,000 | 3 | CONST 4 - LN DIVIDED RDWY W / BIKE LN & SIDEWALKS |
| 1200-03-028 | Travis/ Austin |
FM 973 | Approved | $11,833,390 | ROW | REPLACE BRIDGE & APPROACHES |
| 1200-06-007 | Travis/ Austin |
SH 45 | Approved | $626,479 | 8 | INSTALL LTL & PAVED SHOULDERS |
| 3136-01-172 | Travis/ Austin |
LP 1 | Approved | $4,821,068 | 3 | ADD BICYCLE BRIDGE |
| 0402-02-024 | Upshur/ Atlanta |
SH 154 | Approved | $998,184 | 3 | WIDEN EXISTING ROADWAY |
| 3621-01-009 | Val Verde/ Laredo |
SL 79 | Approved | $4,997,768 | 4 | FOR THE CONSTRUCTION OF A 2 LANE UNDIVIDED HIGHWAY |
| 0089-19-009 | Victoria/ Yoakum |
BU 59-T | Approved | $400,000 | 3 | ADD TURN LANE |
| 0913-27-053 | Victoria/ Yoakum |
CR | Approved | $209,795 | 6 | REPLACE BRIDGE AND APPROACHES |
| 0018-06-171 | Webb/ Laredo |
IH 35 | Approved | $1,150,000 | 8 | ADD 2 WAY LEFT TURN LANE |
| 0922-00-054 | Webb/ Laredo |
VA | Approved | $920,516 | 11 | METAL BEAM GUARD FENCE AND SGT UPGRADE |
| 0922-33-091 | Webb/ Laredo |
CR | Approved | $730,000 | 6 | FOR THE CONSTRUCTION OF THE REPLACEMENT OF AN EXISTING |
| 0089-08-095 | Wharton/ Yoakum |
US 59 | Approved | $1,900,000 | 8 | ADDING ACCEL / DECEL LANES |
| 0544-01-020 | Wichita/ Wichita Falls |
SH 258 | Approved | $6,038,005 | 8 | WIDEN STRUCTURES AND ADD SHOULDERS |
| 0151-05-097 | Williamson/ Austin |
US 183 | Approved | $550,127 | 3 | CONSTRUCT DECELERATION LANE |
| 0151-05-103 | Williamson/ Austin |
US 183 | Approved | $255,572 | 3 | ADD RTL & DUAL LTL LANES |
| 0757-01-020 | Williamson/ Austin |
FM 685 | Approved | $12,900,000 | 3 | RECONSTRUCT TO 4 - LANE DIVIDED ROADWAY WITH BRIDGE STRUCTURE |
| 1202-01-016 | Williamson/ Austin |
FM 972 | Approved | $553,393 | 6 | REAHBILITATE BRIDGE AND APPROACHES |
| 1378-02-039 | Williamson/ Austin |
RM 1431 | Approved | $4,116,509 | 3 | INNOVATIVE INTERSECTION IMPROVEMENTS |
| 0100-03-076 | Wilson/ San Antonio |
US 181 | Approved | $1,240,000 | 8 | INSTALL TRAFFIC SIGNAL |
| 0013-08-127 | Wise/ Fort Worth |
US 81 | Approved | $14,304,889 | 1 | BU 81 (SOUTH) 4 LANE OVERPASS @ US81 / 287 |
| 1098-01-020 | Wise/ Fort Worth |
FM 718 | Approved | $4,955,716 | 8 | WIDEN ROADWAY TO 2 - 12' LANES WITH 6' SHOULDERS |
| 1179-01-039 | Wise/ Fort Worth |
FM 920 | Approved | $4,715,374 | 1 | REHABILITATE AND WIDEN ROADWAY WITH SHOULDERS |
|