Detail Letting Schedule for Lubbock County (FY 2013)

Last Update: Monday, May 6, 2013
Lubbock County (FY 2013)

CCSJ: 0052-07-062

District: Lubbock Let Date: JUN 2013
Highway: US 84 Let Status: Approved
Project ID: NH 2013(982) CSJ: 0052-07-062
Description: INSTALLATION OF AWEGS SYSTEM Handling
Code:
 
Limits From: .1 WEST OF FM 2528 Fund Cat: 8
Limits To: .1 EAST OF FM 2528 Estimate: $148,635
Length: 0.0 Miles Actual:  
 
Back...

Totals for 0052-07-062
Length: 0.0 Miles
Estimate: $148,635
Actual:  

CCSJ: 0053-18-040

District: Lubbock Let Date: JAN 2013
Highway: US 84 Let Status: Actual
Project ID: STP 2013(325) CSJ: 0053-18-040
Description: RESTORATION OF EXISTING ROAD Handling
Code:
 
Limits From: 5TH STREET Fund Cat: 11
Limits To: IH 27 Estimate: $1,228,910
Length: 3.8 Miles Actual: $1,521,813
 
Back...

Totals for 0053-18-040
Length: 3.8 Miles
Estimate: $1,228,910
Actual: $1,521,813

CCSJ: 0068-01-066

District: Lubbock Let Date: JUL 2013
Highway: US 87 Let Status: Approved
Project ID: STP 2013(837)MM CSJ: 0068-01-066
Description: NEW INTERCHANGE Handling
Code:
 
Limits From: 700' NORTH OF N INTERSEC. OF LP 493 Fund Cat: 7
Limits To: 300' SOUTH OF S INTERSEC. OF LP 493 Estimate: $9,743,714
Length: 1.2 Miles Actual:  
 
Back...

Totals for 0068-01-066
Length: 1.2 Miles
Estimate: $9,743,714
Actual:  

CCSJ: 0130-05-077

District: Lubbock Let Date: JUN 2013
Highway: SH 114 Let Status: Approved
Project ID: NH 2013(838) CSJ: 0130-05-077
Description: RESTORATION OF EXISTING ROAD Handling
Code:
 
Limits From: QUAKER Fund Cat: 1
Limits To: MILWAUKEE Estimate: $1,473,471
Length: 3.1 Miles Actual:  
 
Back...

Totals for 0130-05-077
Length: 3.1 Miles
Estimate: $1,473,471
Actual:  

CCSJ: 0380-01-081

District: Lubbock Let Date: FEB 2013
Highway: US 62 Let Status: Actual
Project ID: NH 2012(767) CSJ: 0380-01-081
Description: NEW INTERCHANGE Handling
Code:
 
Limits From: 0.499 MI WEST OF MILWAUKEE AVE Fund Cat: 12
Limits To: 0.297 MI EAST OF MILWAUKEE AVE Estimate: $15,262,798
Length: 0.8 Miles Actual: $15,472,464
 
District: Lubbock Let Date: FEB 2013
Highway: SP 327 Let Status: Actual
Project ID: STP 2013(238) CSJ: 0380-15-018
Description: NEW INTERCHANGE Handling
Code:
 
Limits From: 0.31 MI WEST OF MILWAUKEE AVE Fund Cat: 1
Limits To: 0.29 MI EAST OF MILWAUKEE AVE Estimate: $6,865,900
Length: 0.6 Miles Actual: $6,955,598
 
Bid Tabulations
Back...

Totals for 0380-01-081
Length: 1.4 Miles
Estimate: $22,128,698
Actual: $22,428,062

CCSJ: 0905-00-063

District: Lubbock Let Date: FEB 2013
Highway: VA Let Status: Actual
Project ID: STP 2013(391) CSJ: 0905-00-063
Description: DISTRICT WIDE STRIPING Handling
Code:
 
Limits From: VARIOUS LOCATIONS IN Fund Cat: 11
Limits To: THE LUBBOCK DISTRICT Estimate: $3,196,338
Length: 0.0 Miles Actual: $2,755,904
 
Bid Tabulations
Back...

Totals for 0905-00-063
Length: 0.0 Miles
Estimate: $3,196,338
Actual: $2,755,904

CCSJ: 0905-00-067

District: Lubbock Let Date: FEB 2013
Highway: VA Let Status: Actual
Project ID: STP 2013(392) CSJ: 0905-00-067
Description: MISCELLANEOUS CONSTRUCTION Handling
Code:
 
Limits From: VARIOUS LOCATIONS IN Fund Cat: 11
Limits To: THE LUBBOCK DISTRICT Estimate: $495,074
Length: 0.0 Miles Actual: $334,626
 
Bid Tabulations
Back...

Totals for 0905-00-067
Length: 0.0 Miles
Estimate: $495,074
Actual: $334,626

CCSJ: 0905-00-069

District: Lubbock Let Date: JUN 2013
Highway: VA Let Status: Approved
Project ID: STP 2013(806) CSJ: 0905-00-069
Description: REHABILITATION OF EXISTING ROAD Handling
Code:
 
Limits From: VARIOUS LOCATIONS IN Fund Cat: 11
Limits To: THE LUBBOCK DISTRICT Estimate: $969,253
Length: 0.0 Miles Actual:  
 
Proposal Req Form
Back...

Totals for 0905-00-069
Length: 0.0 Miles
Estimate: $969,253
Actual:  

CCSJ: 0905-00-070

District: Lubbock Let Date: NOV 2012
Highway: VA Let Status: Actual
Project ID: STP 2013(154) CSJ: 0905-00-070
Description: CONSTRUCTION OF ADA CURB RAMPS IN COCHRAN, HOCKLEY, LAMB AND Handling
Code:
 
Limits From: VARIOUS LOCATIONS IN Fund Cat: 10
Limits To: THE LUBBOCK DISTRICT Estimate: $1,761,961
Length: 0.0 Miles Actual: $1,488,393
 
Back...

Totals for 0905-00-070
Length: 0.0 Miles
Estimate: $1,761,961
Actual: $1,488,393

CCSJ: 0905-00-077

District: Lubbock Let Date: JUN 2013
Highway: VA Let Status: Approved
Project ID: STP 2013(877) CSJ: 0905-00-077
Description: MISCELLANOUS CONSTRUCTION Handling
Code:
 
Limits From: VARIOUS LOCATIONS IN Fund Cat: 11
Limits To: THE LUBBOCK DISTRICT Estimate: $288,494
Length: 0.0 Miles Actual:  
 
Back...

Totals for 0905-00-077
Length: 0.0 Miles
Estimate: $288,494
Actual:  

CCSJ: 0905-00-078

District: Lubbock Let Date: JUN 2013
Highway: VA Let Status: Approved
Project ID: STP 2013(878) CSJ: 0905-00-078
Description: MISCELLANEOUS CONSTRUCTION Handling
Code:
 
Limits From: VARIOUS LOCATIONS IN Fund Cat: 11
Limits To: THE LUBBOCK DISTRICT Estimate: $111,430
Length: 0.0 Miles Actual:  
 
Proposal Req Form
Back...

Totals for 0905-00-078
Length: 0.0 Miles
Estimate: $111,430
Actual:  

CCSJ: 0905-06-081

District: Lubbock Let Date: DEC 2012
Highway: CS Let Status: Actual
Project ID: STP 2013(019)MM CSJ: 0905-06-081
Description: WIDEN NON FREEWAY Handling
Code:
 
Limits From: SLIDE ROAD, FROM US 84 Fund Cat: 3
Limits To: MARSHALL STREET Estimate: $6,296,808
Length: 1.5 Miles Actual: $5,440,142
 
Official Notice
Back...

Totals for 0905-06-081
Length: 1.5 Miles
Estimate: $6,296,808
Actual: $5,440,142


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract