Detail Letting Schedule for Fisher County (FY 2013)
| Fisher County (FY 2013) |
CCSJ: 0908-23-027 | |||
| District: | Abilene | Let Date: | AUG 2013 |
| Highway: | CR | Let Status: | Approved |
| Project ID: | BR 2011(745) | CSJ: | 0908-23-027 |
| Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
| Limits From: | ON CR 122 | Fund Cat: | 6 |
| Limits To: | AT ALKALI CREEK (PSN 2) | Estimate: | $252,196 |
| Length: | 0.1 Miles | Actual: | |
|
Back... |
Totals for 0908-23-027 | ||
|---|---|---|---|
| Length: | 0.1 Miles | ||
| Estimate: | $252,196 | ||
| Actual: | |||
CCSJ: 0908-23-029 | |||
| District: | Abilene | Let Date: | AUG 2013 |
| Highway: | CR | Let Status: | Approved |
| Project ID: | BR 2011(747) | CSJ: | 0908-23-029 |
| Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
| Limits From: | ON CR 234 | Fund Cat: | 6 |
| Limits To: | AT GYP CREEK TRIB (PSN 2) | Estimate: | $320,481 |
| Length: | 0.1 Miles | Actual: | |
|
Back... |
Totals for 0908-23-029 | ||
| Length: | 0.1 Miles | ||
| Estimate: | $320,481 | ||
| Actual: | |||
CCSJ: 0908-23-030 | |||
| District: | Abilene | Let Date: | AUG 2013 |
| Highway: | CR | Let Status: | Approved |
| Project ID: | BR 2011(764) | CSJ: | 0908-23-030 |
| Description: | REPLACE BRIDGE | Handling Code: |
|
| Limits From: | CR 357 | Fund Cat: | 6 |
| Limits To: | AT SWEETWATER CREEK | Estimate: | $666,477 |
| Length: | 0.1 Miles | Actual: | |
|
Back... |
Totals for 0908-23-030 | ||
| Length: | 0.1 Miles | ||
| Estimate: | $666,477 | ||
| Actual: | |||
CCSJ: 0908-23-031 | |||
| District: | Abilene | Let Date: | MAY 2013 |
| Highway: | CR | Let Status: | Approved |
| Project ID: | BR 2011(765) | CSJ: | 0908-23-031 |
| Description: | REPLACE BRIDEG AND APPROACHES | Handling Code: |
|
| Limits From: | CR 135 | Fund Cat: | 6 |
| Limits To: | AT COTTONWOOD CK | Estimate: | $191,992 |
| Length: | 0.1 Miles | Actual: | |
|
List Showing Order Proposal Req Form Project Addenda Bidders List Back... |
Totals for 0908-23-031 | ||
| Length: | 0.1 Miles | ||
| Estimate: | $191,992 | ||
| Actual: | |||
CCSJ: 0908-23-032 | |||
| District: | Abilene | Let Date: | APR 2013 |
| Highway: | CR | Let Status: | Actual |
| Project ID: | BR 2011(766) | CSJ: | 0908-23-032 |
| Description: | REPLACE BRIDGE | Handling Code: |
|
| Limits From: | CR 246 | Fund Cat: | 6 |
| Limits To: | AT CLEAR FORK BRAZOS | Estimate: | $255,775 |
| Length: | 0.1 Miles | Actual: | $276,104 |
|
Award Status Bid Tabulations Back... |
Totals for 0908-23-032 | ||
| Length: | 0.1 Miles | ||
| Estimate: | $255,775 | ||
| Actual: | $276,104 | ||
CCSJ: 0908-23-033 | |||
| District: | Abilene | Let Date: | APR 2013 |
| Highway: | CR | Let Status: | Actual |
| Project ID: | BR 2011(767) | CSJ: | 0908-23-033 |
| Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
| Limits From: | ON CR 322 (160) | Fund Cat: | 6 |
| Limits To: | AT CLEAR FORK OF BRAZOS (PSN 1) | Estimate: | $219,827 |
| Length: | 0.0 Miles | Actual: | $254,269 |
|
Award Status Bid Tabulations Back... |
Totals for 0908-23-033 | ||
| Length: | 0.0 Miles | ||
| Estimate: | $219,827 | ||
| Actual: | $254,269 | ||
|