County:BRAZOSLet Date:08/08/17
Type:PEDESTRIAN AND BICYCLE IMPROVEMENTSSeq No:3012
Time:140 WORKING DAYSProject ID:STP 2017(099)TAPS
Highway:VAContract #:08173012
Length:1.164CCSJ:0917-29-129
Limits: 
From:ON SH 308 FROM FM 1179Check:$38,000
To:INLOW STREETMisc Cost:$10,000.00
Estimate$1,875,783.66% Over/UnderCompany
Bidder 1$1,803,581.23-3.85%LARRY YOUNG PAVING, INC.
Bidder 2$2,145,570.10+14.38%TI-ZACK CONCRETE, INC.
Bidder 3$2,431,897.00+29.65%FNH CONSTRUCTION, LLC
Bidder 4$2,671,615.64+42.43%BIG CREEK CONSTRUCTION, LTD.
Bidder 5$3,205,597.87+70.89%KNIFE RIVER CORPORATION - SOUTH
State Let Construction Projects for August, 2017

Text version of this page
County:CALLAHANLet Date:08/08/17
Type:BRIDGE REPLACEMENTSeq No:3013
Time:241 WORKING DAYSProject ID:BR 2016(763)
Highway:CRContract #:08173013
Length:0.317CCSJ:0908-34-022
Limits: 
From:ON CR 152 (SIGNED CR 484)Check:$29,000
To:AT DEEP CREEK (PSN 2)Misc Cost:$20,000.00
Estimate$1,449,478.55% Over/UnderCompany
Bidder 1$1,472,447.50+1.58%ELLIS-MCGINNIS CONSTRUCTION CO.
Bidder 2$1,532,176.14+5.71%A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
Bidder 3$1,549,487.98+6.90%REECE CONSTRUCTION CO., INC.
Bidder 4$1,556,492.10+7.38%HODGES AND SON CONSTRUCTION COMPANY, INC.
Bidder 5$1,663,687.50+14.78%EARTH BUILDERS, L.P.
Bidder 6$1,691,212.30+16.68%JAY-REESE CONTRACTORS, INC.
State Let Construction Projects for August, 2017

Text version of this page
County:LUBBOCKLet Date:08/08/17
Type:GRADE, BASE, C&G, ACPSeq No:3014
Time:256 WORKING DAYSProject ID:STP 2014(802)MM
Highway:CSContract #:08173014
Length:1.000CCSJ:0905-06-086
Limits: 
From:ERSKINE ST FROM NORTH TTU PARKWAYCheck:$98,000
To:NORTH INDIANA AVEMisc Cost:$140,500.00
Estimate$4,901,936.52% Over/UnderCompany
Bidder 1$4,085,773.03-16.65%ALLEN BUTLER CONSTRUCTION, INC.
Bidder 2$4,789,865.86-2.29%DUININCK, INC.
Bidder 3$5,093,918.80+3.92%J.M. MARSCHUETZ CONSTRUCTION CO.
State Let Construction Projects for August, 2017

Text version of this page
County:DALLASLet Date:08/08/17
Type:REPL BR & APPRSSeq No:3015
Time:381 WORKING DAYSProject ID:BR 2007(303)
Highway:CSContract #:08173015
Length:0.289CCSJ:0918-45-757
Limits: 
From:2ND AVE SB AT TRIB OF WHITE ROCK CRCheck:$52,000
To:.Misc Cost:$114,438.76
Estimate$2,638,156.95% Over/UnderCompany
Bidder 1$2,883,799.00+9.31%SEMA CONSTRUCTION, INC.
Bidder 2$2,990,247.51+13.35%IOWA BRIDGE & CULVERT, LC
Bidder 3$3,198,554.13+21.24%HIGHWAY 19 CONSTRUCTION LLC
Bidder 4$3,298,078.75+25.01%RAGLE CONSTRUCTION, INC.
Bidder 5$3,979,380.47+50.84%ED BELL CONSTRUCTION COMPANY
State Let Construction Projects for August, 2017

Text version of this page
County:HOUSTONLet Date:08/08/17
Type:SAFETY TREAT FIXED OBJECTSSeq No:3016
Time:223 WORKING DAYSProject ID:STP 1702(636)HES
Highway:FM 227Contract #:08173016
Length:26.636CCSJ:0937-03-016
Limits: 
From:SH 21Check:$36,000
To:SH 7, ETCMisc Cost:$6,000.00
Estimate$1,786,985.50% Over/UnderCompany
Bidder 1$1,576,406.00-11.78%L.C. JORDAN & SON
Bidder 2$1,812,903.30+1.45%DREWERY CONSTRUCTION COMPANY, INCORPORATED
Bidder 3$1,958,587.85+9.60%PIERCE R & B LLC
Bidder 4$2,243,442.00+25.54%A R BROTHERS CONSTRUCTION SERVICES, INC.
Bidder 5$2,246,814.75+25.73%LONGVIEW BRIDGE AND ROAD, LTD.
State Let Construction Projects for August, 2017

Text version of this page
County:ANDERSONLet Date:08/08/17
Type:CLEAN/PAINT STEEL GRDRS,REPL BR RAIL,CONC DK OVLYSeq No:3017
Time:136 WORKING DAYSProject ID:BR 1702(753)
Highway:US 79Contract #:08173017
Length:0.672CCSJ:0206-01-049
Limits: 
From:1.5 MI EAST OF FM 2574Check:$25,000
To:OVER UPRRMisc Cost:$24,000.00
Estimate$1,358,585.31% Over/UnderCompany
Bidder 1$1,646,254.33+21.17%DREWERY CONSTRUCTION COMPANY, INCORPORATED
Bidder 2$1,689,423.00+24.35%GIBSON & ASSOCIATES, INC.
Bidder 3$1,707,364.50+25.67%HIGHWAY 19 CONSTRUCTION LLC
Bidder 4$1,897,694.65+39.68%EAST TEXAS BRIDGE, INC.
Bidder 5$1,984,467.70+46.07%LONGVIEW BRIDGE AND ROAD, LTD.
Bidder 6$2,167,358.10+59.53%HODGES AND SON CONSTRUCTION COMPANY, INC.
Bidder 7$2,207,205.60+62.46%RED BARON BUILDING COMPANY, L.L.C.
State Let Construction Projects for August, 2017

Text version of this page
County:TARRANTLet Date:08/08/17
Type:GR, BS, DR, PAVSeq No:3018
Time:128 WORKING DAYSProject ID:BR 1702(737)
Highway:IH 30Contract #:08173018
Length:0.130CCSJ:1068-01-216
Limits: 
From:WB IH 30 COL DIST FR UNIVERISTY DRCheck:$19,000
To:OVER WB IH 30 EXIT RAMP TO MONTGOMEMisc Cost:$10,350.00
Estimate$932,365.00% Over/UnderCompany
Bidder 1$997,337.74+6.97%IOWA BRIDGE & CULVERT, LC
Bidder 2$1,029,208.45+10.39%RAGLE CONSTRUCTION, INC.
Bidder 3$1,235,043.32+32.46%REBCON, INC.
Bidder 4$1,362,260.90+46.11%HAYDON BUILDING CORP.
Bidder 5$1,385,693.14+48.62%ED BELL CONSTRUCTION COMPANY
State Let Construction Projects for August, 2017

Text version of this page
County:HAYSLet Date:08/08/17
Type:INSTALL WARN/GUIDE SIGNS/DELINEATORSSeq No:3019
Time:38 WORKING DAYSProject ID:STP 2017(895)HES
Highway:CRContract #:08173019
Length:0.001CCSJ:0914-33-070
Limits: 
From:BLANCO C/L ON W FITZUGH RDCheck:$4,000
To:US 290Misc Cost:$2,250.00
Estimate$148,805.00% Over/UnderCompany
Bidder 1$149,765.00+0.65%FLASHER EQUIPMENT COMPANY
Bidder 2$193,195.04+29.83%KEGLEY, INC.
Bidder 3$212,410.00+42.74%CHAMPION INFRASTRUCTURE, LLC
Bidder 4$234,700.00+57.72%IIPL USA LLC
State Let Construction Projects for August, 2017

Text version of this page
County:TARRANTLet Date:08/08/17
Type:GR, DR AND PAVEMENTSeq No:3021
Time:188 WORKING DAYSProject ID:STP 2012(660)MM
Highway:SH 183Contract #:08173021
Length:1.140CCSJ:0094-02-121
Limits: 
From:HANDLEY-EDERVILLE RD.Check:$67,000
To:RUFE SNOW DRIVE; IN RICHLAND HILLSMisc Cost:$24,000.00
Estimate$3,335,706.03% Over/UnderCompany
Bidder 1$3,732,867.33+11.91%RAGLE CONSTRUCTION, INC.
Bidder 2$4,385,951.25+31.48%FNH CONSTRUCTION, LLC
Bidder 3$4,408,800.53+32.17%GIBSON & ASSOCIATES, INC.
Bidder 4$5,139,985.32+54.09%ED BELL CONSTRUCTION COMPANY
State Let Construction Projects for August, 2017

Text version of this page
County:GRAYSONLet Date:08/08/17
Type:SAFETY TREAT FIXED OBJECTSSeq No:3022
Time:57 WORKING DAYSProject ID:STP 1702(745)HES
Highway:US 75Contract #:08173022
Length:10.320CCSJ:0047-02-134
Limits: 
From:SH 91Check:$17,000
To:1.5 MI N OF FM 1417Misc Cost:$26,000.00
Estimate$838,702.20% Over/UnderCompany
Bidder 1$930,195.00+10.91%IIPL USA LLC
Bidder 2$932,086.00+11.13%HIGHWAY 19 CONSTRUCTION LLC
Bidder 3$1,093,546.00+30.39%GHB EQUIPMENT COMPANY, L.L.C.
Bidder 4$1,142,681.50+36.24%SJ&J CONSTRUCTION, LLC
Bidder 5$1,159,498.00+38.25%FNH CONSTRUCTION, LLC
State Let Construction Projects for August, 2017

Text version of this page
County:HARDINLet Date:08/08/17
Type:SAFETY TREAT FIXED OBJECTS, TEXTURIZE SHOULDERSSeq No:3023
Time:43 WORKING DAYSProject ID:STP 1702(634)HES
Highway:SH 105Contract #:08173023
Length:21.587CCSJ:0339-03-037
Limits: 
From:1.169 MI E. OF FM 770 (S)Check:$5,000
To:1.095 MI W OF JEFFERSON C/LMisc Cost:$3,434.00
Estimate$235,930.15% Over/UnderCompany
Bidder 1$220,428.17-6.57%WIDGEON CONSTRUCTION, INC.
Bidder 2$223,960.80-5.07%NORMAN HIGHWAY CONSTRUCTORS, INC.
Bidder 3$250,274.50+6.08%DEZTEX INDUSTRIAL SERVICES, LLC
State Let Construction Projects for August, 2017

Text version of this page
County:BRAZORIALet Date:08/08/17
Type:BRIDGE DECK REPLACEMENTSeq No:3024
Time:307 WORKING DAYSProject ID:STP 1702(629)
Highway:SH 35Contract #:08173024
Length:1.199CCSJ:0179-01-048
Limits: 
From:AT JAMISON SLOUGHCheck:$53,000
To:AND AT OYSTER CREEKMisc Cost:$19,359.00
Estimate$2,646,095.29% Over/UnderCompany
Bidder 1$2,037,263.05-23.01%MAIN LANE INDUSTRIES LTD.
Bidder 2$2,377,172.30-10.16%ISI CONTRACTING, INC.
Bidder 3$2,672,689.42+1.01%RAGLE CONSTRUCTION, INC.
Bidder 4$2,854,317.39+7.87%GIBSON & ASSOCIATES, INC.
State Let Construction Projects for August, 2017

Text version of this page
County:HARRISLet Date:08/08/17
Type:LANDSCAPINGSeq No:3025
Time:60 WORKING DAYSProject ID:NH 1702(628)
Highway:IH 69Contract #:08173025
Length:16.785CCSJ:0177-07-112
Limits: 
From:LITTLE YORK ROADCheck:$15,000
To:FM 1960Misc Cost:$1,500.00
Estimate$746,209.50% Over/UnderCompany
Bidder 1$598,752.55-19.76%YELLOWSTONE LANDSCAPE - CENTRAL, INC.
Bidder 2$765,843.55+2.63%BOYER, INC.
Bidder 3$838,131.00+12.32%TEXAS WALL & LANDSCAPE
State Let Construction Projects for August, 2017

Text version of this page
County:COLLINLet Date:08/08/17
Type:IMPROVE TRAFFIC SIGNALSSeq No:3026
Time:320 WORKING DAYSProject ID:STP 1702(697)HES
Highway:SH 289Contract #:08173026
Length:24.155CCSJ:0091-04-062
Limits: 
From:FRISCO, PLANO, AND DALLASCheck:$41,000
To:Misc Cost:$52,900.00
Estimate$2,204,249.05% Over/UnderCompany
Bidder 1$1,750,000.00-20.61%DURABLE SPECIALTIES, INC.
Bidder 2$2,097,264.99-4.85%AMERICAN LIGHTING AND SIGNALIZATION, LLC
Bidder 3$2,237,573.00+1.51%ROADWAY SOLUTIONS, INC.
Bidder 4$2,982,093.59+35.29%MASSANA CONSTRUCTION INC.
State Let Construction Projects for August, 2017

Text version of this page
County:WHARTONLet Date:08/08/17
Type:REPLACE BRIDGE AND APPROACHESSeq No:3027
Time:60 WORKING DAYSProject ID:BR 2014(682)
Highway:CRContract #:08173027
Length:0.100CCSJ:0913-09-065
Limits: 
From:AT EAST FORK JONES CREEK CR 461Check:$6,000
To:(CR 461) STR # AA06-47-002Misc Cost:$1,500.00
Estimate$316,096.00% Over/UnderCompany
Bidder 1$320,804.30+1.49%3LW CIVIL LLC
Bidder 2$335,237.15+6.06%HILL COUNTRY BRIDGE, INC.
Bidder 3$337,875.29+6.89%REXCO CONSTRUCTION SERVICES, INC.
Bidder 4$343,294.00+8.60%CONSTAR CONSTRUCTION
Bidder 5$353,042.15+11.69%TREVWAY, INC.
Bidder 6$374,476.60+18.47%JOHN REED AND COMPANY, LLC
Bidder 7$388,126.26+22.79%SB CONTRACTORS LLC
Bidder 8$409,679.35+29.61%ISI CONTRACTING, INC.
Bidder 9$452,961.30+43.30%A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
Bidder 10$469,829.95+48.64%TMES LLC
State Let Construction Projects for August, 2017

Text version of this page
County:HARRISONLet Date:08/08/17
Type:INSTALL SAFETY LIGHTINGSeq No:3028
Time:93 WORKING DAYSProject ID:STP 1702(695)HESG
Highway:IH 20Contract #:08173028
Length:15.201CCSJ:0495-08-098
Limits: 
From:0.1 MI. W. OF FM 968Check:$16,000
To:0.7 MI. W. OF_SH 43Misc Cost:$5,000.00
Estimate$708,318.35% Over/UnderCompany
Bidder 1$689,736.00-2.62%SOUTH TEXAS ILLUMINATION, LLC
Bidder 2$726,325.20+2.54%AMERICAN LIGHTING AND SIGNALIZATION, LLC