Last Update: Friday, March 15, 2024
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings.
Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and
intended for informational purposes only.
|
|
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 |
|
Text version of this page |
County: | TRINITY | Let Date: | 02/28/24 |
Type: | TREE TRIMMING AND BRUSH REMOVAL | Seq No: | 1105 |
Time: | 365 CALENDAR DAYS | Project ID: | RMC - 646283001 |
Highway: | FM0357 | Contract #: | 02241105 |
Length: | 0.000 | CCSJ: | 6462-83-001 |
Limits: | |
From: | TRINITY COUNTY | Check: | $3,000 |
To: | VARIOUS LOCATIONS | Misc Cost: | |
Estimate | $174,825.00 | % Over/Under | Company |
Bidder 1 | $168,000.06 | -3.90% | FLORES TREE SERVICE LLC |
Bidder 2 | $186,100.00 | +6.45% | K & R CONTRACTORS |
Bidder 3 | $233,450.00 | +33.53% | DREWERY CONSTRUCTION COMPANY, INCORPORATED |
Bidder 4 | $344,000.00 | +96.77% | BUSHWACKERS CONTRACTING, LLC |
Bidder 5 | $348,000.00 | +99.06% | GV LANDSCAPE AND CONSTRUCTION LLC |
Bidder 6 | $721,000.00 | +312.41% | LOOKS GREAT SERVICES OF MS, INC. |
Text version of this page |
County: | NACOGDOCHES | Let Date: | 02/28/24 |
Type: | METAL BEAM GUARD FENCE REPAIR | Seq No: | 1106 |
Time: | 365 CALENDAR DAYS | Project ID: | RMC - 646296001 |
Highway: | SH0007 | Contract #: | 02241106 |
Length: | 0.000 | CCSJ: | 6462-96-001 |
Limits: | |
From: | NACOGDOCHES COUNTY | Check: | $3,000 |
To: | VARIOUS LOCATIONS | Misc Cost: | |
Estimate | $172,866.00 | % Over/Under | Company |
Bidder 1 | $161,130.00 | -6.79% | ACE CONTRACTORS, INC. |
Bidder 2 | $174,975.00 | +1.22% | HAZMAT INTERNATIONAL, INC. |
Bidder 3 | $185,643.00 | +7.39% | AUSTIN BARRICADE COMPANY, L.L.C. |
Bidder 4 | $216,235.00 | +25.09% | GARRET SHIELDS INFRASTRUCTURE |
Bidder 5 | $250,000.00 | +44.62% | CATOCON, INC. |
Text version of this page |
County: | NACOGDOCHES | Let Date: | 02/28/24 |
Type: | TREE REMOVAL | Seq No: | 1107 |
Time: | 365 CALENDAR DAYS | Project ID: | RMC - 646297001 |
Highway: | US0059 | Contract #: | 02241107 |
Length: | 0.000 | CCSJ: | 6462-97-001 |
Limits: | |
From: | NACOGDOCHES COUNTY | Check: | $2,000 |
To: | VARIOUS LOCATIONS | Misc Cost: | |
Estimate | $101,295.00 | % Over/Under | Company |
Bidder 1 | $92,775.00 | -8.41% | K & R CONTRACTORS |
Bidder 2 | $93,400.09 | -7.79% | FLORES TREE SERVICE LLC |
Bidder 3 | $104,625.00 | +3.29% | RENEGADE SITE SOLUTIONS, LLC |
Bidder 4 | $113,750.00 | +12.30% | DREWERY CONSTRUCTION COMPANY, INCORPORATED |
Bidder 5 | $135,225.00 | +33.50% | ACE CONTRACTORS, INC. |
Bidder 6 | $214,795.00 | +112.05% | RISE UP CONSTRUCTION LLC |
Bidder 7 | $266,500.00 | +163.09% | GV LANDSCAPE AND CONSTRUCTION LLC |
Bidder 8 | $446,500.00 | +340.79% | LOOKS GREAT SERVICES OF MS, INC. |
Text version of this page |
County: | WOOD | Let Date: | 03/05/24 |
Type: | INTERCHANGE IMPROVEMENT (NEW OR UPDATE) | Seq No: | 3001 |
Time: | 492 WORKING DAYS | Project ID: | C 203-5-39 |
Highway: | US 69 | Contract #: | 03243001 |
Length: | 0.000 | CCSJ: | 0203-05-039 |
Limits: | |
From: | 0.96 MI N OF FM 779, SE | Check: | $100,000 |
To: | 1.03 MI S OF FM 779 | Misc Cost: | $246,250.00 |
Estimate | $46,810,288.72 | % Over/Under | Company |
Bidder 1 | $37,954,683.08 | -18.92% | LAMAR COMPANIES LLC |
Bidder 2 | $41,989,582.79 | -10.30% | LONGVIEW BRIDGE AND ROAD, LTD. |
Bidder 3 | $43,525,687.69 | -7.02% | HIGHWAY 19 CONSTRUCTION LLC |
Bidder 4 | $47,327,662.75 | +1.11% | INDUS ROAD & BRIDGE, INC. |
Bidder 5 | $48,467,077.82 | +3.54% | EAST TEXAS BRIDGE, INC. |
Text version of this page |
County: | FORT BEND | Let Date: | 03/05/24 |
Type: | HIGHWAY IMPROVEMENT | Seq No: | 3002 |
Time: | 687 WORKING DAYS | Project ID: | C 27-12-160 |
Highway: | IH 69 | Contract #: | 03243002 |
Length: | 0.400 | CCSJ: | 0027-12-160 |
Limits: | |
From: | AT BRAZOS RIVER | Check: | $100,000 |
To: | . | Misc Cost: | |
Estimate | $60,124,320.92 | % Over/Under | Company |
Bidder 1 | $53,190,823.06 | -11.53% | SER CONSTRUCTION PARTNERS, LLC |
Bidder 2 | $53,212,272.05 | -11.50% | JAMES CONSTRUCTION GROUP, LLC |
Bidder 3 | $57,358,973.55 | -4.60% | ZACHRY CONSTRUCTION CORPORATION |
Bidder 4 | $64,650,434.71 | +7.53% | PULICE CONSTRUCTION, INC. |
Text version of this page |
County: | DEAF SMITH | Let Date: | 03/05/24 |
Type: | REHABILITATE EXISTING ROADWAY | Seq No: | 3003 |
Time: | 599 WORKING DAYS | Project ID: | C 168-7-43 |
Highway: | US 60 | Contract #: | 03243003 |
Length: | 2.473 | CCSJ: | 0168-07-043 |
Limits: | |
From: | DIVIDED 4 LANE | Check: | $100,000 |
To: | US 385 | Misc Cost: | |
Estimate | $41,529,754.30 | % Over/Under | Company |
Bidder 1 | $73,856,677.90 | +77.84% | WEBBER, LLC |
Text version of this page |
County: | DALLAS | Let Date: | 03/05/24 |
Type: | BRIDGE REPLACEMENT | Seq No: | 3004 |
Time: | 503 WORKING DAYS | Project ID: | F 2022(999) |
Highway: | US 175 | Contract #: | 03243004 |
Length: | 1.654 | CCSJ: | 0197-02-135 |
Limits: | |
From: | 2ND AVENUE | Check: | $100,000 |
To: | AT LAKE JUNE ROAD | Misc Cost: | |
Estimate | $31,570,570.23 | % Over/Under | Company |
Bidder 1 | $26,852,159.34 | -14.95% | INDUS ROAD & BRIDGE, INC. |
Bidder 2 | $31,300,000.00 | -0.86% | HARPER BROTHERS CONSTRUCTION LLC |
Bidder 3 | $31,985,239.00 | +1.31% | GRANITE CONSTRUCTION COMPANY |
Bidder 4 | $34,225,385.40 | +8.41% | RPM XCONSTRUCTION, LLC |
Bidder 5 | $36,543,210.00 | +15.75% | FLUOR HEAVY CIVIL, LLC |
Bidder 6 | $36,574,082.30 | +15.85% | RAGLE CONSTRUCTION, INC. |
Bidder 7 | $37,822,023.23 | +19.80% | ED BELL CONSTRUCTION COMPANY |
Text version of this page |
County: | TARRANT | Let Date: | 03/05/24 |
Type: | RESURFACE ROADWAY | Seq No: | 3005 |
Time: | 150 WORKING DAYS | Project ID: | C 172-6-99 |
Highway: | US 287 | Contract #: | 03243005 |
Length: | 0.000 | CCSJ: | 0172-06-099 |
Limits: | |
From: | IH 30 | Check: | $100,000 |
To: | VILLAGE CREEK RD. | Misc Cost: | |
Estimate | $16,768,998.65 | % Over/Under | Company |
Bidder 1 | $19,292,920.92 | +15.05% | FOUTSCO PAVING COMPANY, LLC |
Bidder 2 | $19,303,449.10 | +15.11% | FNH CONSTRUCTION, LLC |
Bidder 3 | $21,774,959.84 | +29.85% | TEXAS MATERIALS GROUP, INC. |
Text version of this page |
County: | HOUSTON | Let Date: | 03/05/24 |
Type: | RESURFACE ROADWAY | Seq No: | 3006 |
Time: | 140 WORKING DAYS | Project ID: | C 109-3-44 |
Highway: | US 287 | Contract #: | 03243006 |
Length: | 0.000 | CCSJ: | 0109-03-044 |
Limits: | |
From: | ANDERSON COUNTY LINE | Check: | $100,000 |
To: | 2.198 MI N OF FM 2663 | Misc Cost: | |
Estimate | $16,313,621.05 | % Over/Under | Company |
Bidder 1 | $11,224,367.45 | -31.20% | BIG CREEK CONSTRUCTION, LTD. |
Bidder 2 | $12,683,843.86 | -22.25% | TEXAS MATERIALS GROUP, INC. |
Bidder 3 | $14,852,027.25 | -8.96% | VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC |
Text version of this page |
County: | CALLAHAN | Let Date: | 03/05/24 |
Type: | WIDEN ROAD - ADD LANES | Seq No: | 3007 |
Time: | 270 WORKING DAYS | Project ID: | C 181-3-31 |
Highway: | SH 36 | Contract #: | 03243007 |
Length: | 4.515 | CCSJ: | 0181-03-031 |
Limits: | |
From: | CR 459 | Check: | $100,000 |
To: | FM 2707 | Misc Cost: | |
Estimate | $8,134,561.00 | % Over/Under | Company |
Bidder 1 | $7,369,772.59 | -9.40% | FOUTSCO PAVING COMPANY, LLC |
Bidder 2 | $8,948,612.80 | +10.01% | BONTKE BROTHERS CONSTRUCTION COMPANY |
Bidder 3 | $9,314,405.23 | +14.50% | REECE ALBERT, INC. |
Bidder 4 | $10,098,624.35 | +24.14% | CK NEWBERRY, LLC |
Bidder 5 | $10,642,773.54 | +30.83% | JAY MILLS CONTRACTING, INCORPORATED |
Text version of this page |
County: | VICTORIA | Let Date: | 03/05/24 |
Type: | SURFACING/ROADWAY RESTORATION | Seq No: | 3008 |
Time: | 205 WORKING DAYS | Project ID: | C 941-4-19 |
Highway: | FM 237 | Contract #: | 03243008 |
Length: | 5.589 | CCSJ: | 0941-04-019 |
Limits: | |
From: | DEWITT C/L | Check: | $100,000 |
To: | FM 236 | Misc Cost: | |
Estimate | $12,106,203.35 | % Over/Under | Company |
Bidder 1 | $9,911,169.38 | -18.13% | HUNTER INDUSTRIES, LTD. |
Bidder 2 | $10,490,873.08 | -13.34% | CK NEWBERRY, LLC |
Bidder 3 | $11,604,931.72 | -4.14% | CLARK CONSTRUCTION OF TEXAS, INC. |
Text version of this page |
County: | LAVACA | Let Date: | 03/05/24 |
Type: | BRIDGE REPLACEMENT | Seq No: | 3009 |
Time: | 349 WORKING DAYS | Project ID: | BR 2024(508) |
Highway: | UA 90 | Contract #: | 03243009 |
Length: | 0.811 | CCSJ: | 0446-01-050 |
Limits: | |
From: | AT NAVIDAD RIVER | Check: | $100,000 |
To: | STR # 0446-01-007 | Misc Cost: | |
Estimate | $11,635,484.10 | % Over/Under | Company |
Bidder 1 | $10,488,202.65 | -9.86% | E-Z BEL CONSTRUCTION, LLC |
Bidder 2 | $11,410,086.89 | -1.94% | JAMES CONSTRUCTION GROUP, LLC |
Bidder 3 | $12,599,793.16 | +8.29% | TEXAS MATERIALS GROUP, INC. |
Bidder 4 | $12,888,684.14 | +10.77% | C. E. BARKER, LTD. |
Text version of this page |
County: | POTTER | Let Date: | 03/05/24 |
Type: | BRIDGE REPLACEMENT | Seq No: | 3010 |
Time: | 182 WORKING DAYS | Project ID: | BR 2024(779) |
Highway: | IH 40 | Contract #: | 03243010 |
Length: | 0.000 | CCSJ: | 0090-05-107 |
Limits: | |
From: | IH 40/HOPE RD BRIDGE | Check: | $100,000 |
To: | . | Misc Cost: | |
Estimate | $9,565,794.00 | % Over/Under | Company |
Bidder 1 | $10,246,889.59 | +7.12% | ALTUS CONSTRUCTION LLC |
Bidder 2 | $10,650,047.20 | +11.33% | COPPELL CONSTRUCTION CO., INC. |
Bidder 3 | $11,565,191.51 | +20.90% | L A FULLER & SONS CONSTRUCTION, LTD. |
Bidder 4 | $11,687,192.95 | +22.18% | GILVIN-TERRILL, LTD. |
Text version of this page |
County: | EL PASO | Let Date: | 03/05/24 |
Type: | PREVENTIVE MAINTENANCE | Seq No: | 3011 |
Time: | 270 WORKING DAYS | Project ID: | C 374-2-120 |
Highway: | US 62 | Contract #: | 03243011 |
Length: | 0.000 | CCSJ: | 0374-02-120 |
Limits: | |
From: | MAGRUDER ST | Check: | $100,000 |
To: | GLOBAL REACH DR | Misc Cost: | |
Text version of this page |
County: | PECOS | Let Date: | 03/05/24 |
Type: | ROADWAY REHABILITATION | Seq No: | 3012 |
Time: | 194 WORKING DAYS | Project ID: | C 441-7-74 |
Highway: | IH 10 | Contract #: | 03243012 |
Length: | 0.000 | CCSJ: | 0441-07-074 |
Limits: | |
From: | 7.75 MI W OF US 67 | Check: | $100,000 |
To: | 4.75 MI W OF US 67 | Misc Cost: | |
Estimate | $14,670,235.62 | % Over/Under | Company |
Bidder 1 | $12,743,572.55 | -13.13% | FNF CONSTRUCTION, INC. |
Bidder 2 | $13,787,815.54 | -6.02% | JONES BROS. DIRT & PAVING CONTRACTORS, INC. |
Bidder 3 | $15,245,108.23 | +3.92% | KIEWIT INFRASTRUCTURE SOUTH CO. |
Bidder 4 | $15,393,207.27 | +4.93% | DAN WILLIAMS COMPANY |
Text version of this page |
County: | SAN PATRICIO | Let Date: | 03/05/24 |
Type: | TRAFFIC SIGNAL IMPROVEMENTS | Seq No: | 3013 |
Time: | 175 WORKING DAYS | Project ID: | STP 2024(813)HES |
Highway: | SH 234 | Contract #: | 03243013 |
Length: | 7.880 | CCSJ: | 0507-01-021 |
Limits: | |
From: | ON SH234 FROM IH37SB FRTG | Check: | $100,000 |
To: | CR 1969 | Misc Cost: | |
Estimate | $5,822,812.05 | % Over/Under | Company |
Bidder 1 | $5,492,231.22 | -5.68% | J. CARROLL WEAVER, INC. |
Bidder 2 | $5,792,343.35 | -0.52% | LCR TOTAL TRANSPORT LLC |
Bidder 3 | $5,793,862.70 | -0.50% | CK NEWBERRY, LLC |
Bidder 4 | $5,847,269.10 | +0.42% | J E CONSTRUCTION SERVICES, LLC |