Bid Totals Page 24 of 32

Last Update: Monday, May 4, 2015

1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32

Text version of this page
County: WILBARGER Let Date: 04/07/15
Type: REPLACE BRIDGE AND APPROACHES Seq No: 3016
Time: 60 WORKING DAYS Project ID: BR 2015(441)
Highway: CR Contract #: 04153016
Length: 0.121 CCSJ: 0903-30-044
Limits:  
From: CR 274 (CR 123) AT ADAMS CREEK Check: $7,000.00
To: . Misc Cost: $5,000.00
Estimate $328,626.80 % Over/Under Company
Bidder 1 $366,361.40 +11.48% HODGES AND SON CONSTRUCTION COMPANY, INC.
Bidder 2 $388,888.00 +18.34% PIERCE CONSTRUCTION, INC.
Bidder 3 $453,965.60 +38.14% EARTH BUILDERS, L.P.
Bidder 4 $534,555.00 +62.66% GILVIN-TERRILL, LTD.
State Let Construction Projects for April, 2015

Text version of this page
County: HARRIS Let Date: 04/07/15
Type: SEAL BRIDGE DECK CRACKING Seq No: 3017
Time: 36 WORKING DAYS Project ID: NH 1502(004)
Highway: IH 69 Contract #: 04153017
Length: 0.002 CCSJ: 0177-11-150
Limits:  
From: VARIOUS LOCATIONS ON US 59 Check: $56,000.00
To: VARIOUS LOCATIONS ON US 59 Misc Cost: $20,000.00
Estimate $2,578,099.73 % Over/Under Company
Bidder 1 $1,777,777.00 -31.04% THE TRUESDELL CORPORATION
Bidder 2 $2,186,970.82 -15.17% MAIN LANE INDUSTRIES, LTD.
Bidder 3 $2,394,489.42 -7.12% SCR CONSTRUCTION CO., INC.
Bidder 4 $2,584,391.92 +0.24% GIBSON & ASSOCIATES, INC.
State Let Construction Projects for April, 2015

Text version of this page
County: HAYS Let Date: 04/07/15
Type: ADD CENTER TURN LANE AND SHOULDERS Seq No: 3018
Time: 161 WORKING DAYS Project ID: STP 2015(880)
Highway: RM 12 Contract #: 04153018
Length: 4.028 CCSJ: 0285-03-057
Limits:  
From: SADDLERIDGE DR Check: $52,000.00
To: HUGO RD Misc Cost: $24,900.00
Estimate $2,672,807.70 % Over/Under Company
Bidder 1 $3,090,648.52 +15.63% CURRAN CONTRACTING COMPANY
Bidder 2 $3,274,162.77 +22.50% DEAN WORD COMPANY, LTD.
Bidder 3 $3,297,285.87 +23.36% DAN WILLIAMS COMPANY
Bidder 4 $3,308,279.23 +23.78% HUNTER INDUSTRIES, LTD.
State Let Construction Projects for April, 2015

Text version of this page
County: HIDALGO Let Date: 04/07/15
Type: CONSTRUCT CURB RAMPS Seq No: 3019
Time: 200 WORKING DAYS Project ID: STP 2015(930)
Highway: VA Contract #: 04153019
Length: 0.002 CCSJ: 0921-02-319
Limits:  
From: VARIOUS LOCATIONS IN PHARR DISTRICT Check: $33,000.00
To:   Misc Cost: $40,000.00
Estimate $1,481,024.10 % Over/Under Company
Bidder 1 $1,475,632.37 -0.36% CRG
Bidder 2 $1,494,996.26 +0.94% REIM CONSTRUCTION, INC.
Bidder 3 $1,648,337.39 +11.30% VALLEY INFRASTRUCTURE, INC.
Bidder 4 $1,691,285.15 +14.20% ARANDA BROTHERS CONSTRUCTION CO., INC.
Bidder 5 $1,777,888.20 +20.04% TI-ZACK CONCRETE, INC.
Bidder 6 $2,071,733.20 +39.89% ENCINO LANDSCAPE, INC.
Bidder 7 $2,104,905.70 +42.13% IOC COMPANY LLC
Bidder 8 $2,309,792.45 +55.96% TEXAS CORDIA CONSTRUCTION, LLC
Bidder 9 $2,361,447.64 +59.45% FOREMOST PAVING, INC.
State Let Construction Projects for April, 2015

Text version of this page
County: JACK Let Date: 04/07/15
Type: PROFILE PAVEMENT MARKERS Seq No: 3020
Time: 107 WORKING DAYS Project ID: STP 2015(853)HES
Highway: US 281 Contract #: 04153020
Length: 19.130 CCSJ: 0249-05-028
Limits:  
From: ARCHER COUNTY LINE Check: $17,000.00
To: LYNN CREEK Misc Cost: $5,000.00
Estimate $852,773.85 % Over/Under Company
Bidder 1 $428,016.01 -49.81% TRP CONSTRUCTION GROUP, LLC
Bidder 2 $480,200.70 -43.69% D. I. J. CONSTRUCTION, INC.
Bidder 3 $541,249.10 -36.53% TOTAL HIGHWAY MAINTENANCE, LLC
Bidder 4 $545,307.86 -36.05% STRIPE-A-ZONE, INC.
State Let Construction Projects for April, 2015

Text version of this page
County: KAUFMAN Let Date: 04/07/15
Type: REHAB HIGHWAY AND PROFILE PAVEMENT MARKERS Seq No: 3023
Time: 125 WORKING DAYS Project ID: STP 2015(843)HES
Highway: SH 34 Contract #: 04153023
Length: 20.171 CCSJ: 0173-05-037
Limits:  
From: JCT US 80 Check: $27,000.00
To: HUNT COUNTY LINE Misc Cost: $11,000.00
Estimate $1,314,658.63 % Over/Under Company
Bidder 1 $1,485,048.26 +12.96% APAC-TEXAS, INC.
Bidder 2 $1,659,932.77 +26.26% ED BELL CONSTRUCTION COMPANY
Bidder 3 $1,665,901.27 +26.72% AUSTIN BRIDGE & ROAD SERVICES, LP
Bidder 4 $1,902,768.71 +44.73% PEACHTREE CONSTRUCTION, LTD.
State Let Construction Projects for April, 2015

Text version of this page
County: KNOX Let Date: 04/07/15
Type: REHABILITATION OF EXISTING ROAD Seq No: 3025
Time: 92 WORKING DAYS Project ID: NH 2015(837)
Highway: US 277 Contract #: 04153025
Length: 4.189 CCSJ: 0157-02-045
Limits:  
From: HASKELL C/L, NORTH Check: $69,000.00
To: FM 267 Misc Cost: $95,100.00
Estimate $3,461,297.20 % Over/Under Company
Bidder 1 $2,909,057.24 -15.95% DUININCK, INC.
Bidder 2 $3,132,234.63 -9.51% A. L. HELMCAMP, INC.
State Let Construction Projects for April, 2015

Text version of this page
County: LIVE OAK Let Date: 04/07/15
Type: NOVACHIP ROADWAY Seq No: 3026
Time: 68 WORKING DAYS Project ID: NH 2015(883)
Highway: IH 37 Contract #: 04153026
Length: 28.622 CCSJ: 0074-02-072
Limits:  
From: .7 MI N OF US 59 INTERS. Check: $97,000.00
To: SAN PATRICIO COUNTY LINE Misc Cost: $146,300.00
Estimate $3,989,489.35 % Over/Under Company
Bidder 1 $3,901,795.11 -2.20% HUNTER INDUSTRIES, LTD.
Bidder 2 $4,679,800.06 +17.30% ANGEL BROTHERS ENTERPRISES, LTD.
State Let Construction Projects for April, 2015

Text version of this page
County: LUBBOCK Let Date: 04/07/15
Type: PUMP STATION REPAIR Seq No: 3027
Time: 190 WORKING DAYS Project ID: STP 2015(229)
Highway: VA Contract #: 04153027
Length: 0.002 CCSJ: 0905-00-083
Limits:  
From: VARIOUS LOCATIONS ALONG Check: $30,000.00
To: IH 27 Misc Cost: $90,100.00
Estimate $1,490,400.00 % Over/Under Company
Bidder 1 $2,562,040.00 +71.90% AUSTIN ENGINEERING CO., INC.
State Let Construction Projects for April, 2015

Text version of this page
County: MARION Let Date: 04/07/15
Type: PLANING,ACP,CPCD & PAV MRKS Seq No: 3028
Time: 231 WORKING DAYS Project ID: NH 2015(995)
Highway: US 59 Contract #: 04153028
Length: 0.348 CCSJ: 0062-06-054
Limits:  
From: AT INTERSECTION OF FM 2208 Check: $44,000.00
To: . Misc Cost: $27,000.00
Estimate $2,187,352.90 % Over/Under Company
Bidder 1 $2,267,006.61 +3.64% LONGVIEW BRIDGE AND ROAD, LTD.
Bidder 2 $2,616,677.43 +19.63% EAST TEXAS BRIDGE, INC.
State Let Construction Projects for April, 2015

Text version of this page
County: MONTGOMERY Let Date: 04/07/15
Type: BASE REPAIR AND ACP O/L Seq No: 3029
Time: 81 WORKING DAYS Project ID: NH 1502(021)
Highway: FM 3083 Contract #: 04153029
Length: 16.929 CCSJ: 3158-01-037
Limits:  
From: LP 336 NORTH Check: $83,000.00
To: FM 1485 Misc Cost: $4,000.00
Estimate $4,545,254.44 % Over/Under Company
Bidder 1 $4,452,712.16 -2.04% ANGEL BROTHERS ENTERPRISES, LTD.
Bidder 2 $4,639,837.67 +2.08% SMITH & COMPANY
State Let Construction Projects for April, 2015

Text version of this page
County: NUECES Let Date: 04/07/15
Type: MILL, UNDERSEAL AND OVERLAY Seq No: 3030
Time: 85 WORKING DAYS Project ID: NH 2015(885)
Highway: IH 37 Contract #: 04153030
Length: 4.023 CCSJ: 0074-06-222
Limits:  
From: NUECES BAY BLVD Check: $91,000.00
To: SH 358 Misc Cost: $236,000.00
Estimate $4,402,904.60 % Over/Under Company
Bidder 1 $5,938,687.40 +34.88% BAY LTD.
State Let Construction Projects for April, 2015

Text version of this page
County: OCHILTREE Let Date: 04/07/15
Type: CENTERLINE TEXTURING Seq No: 3031
Time: 80 WORKING DAYS Project ID: STP 2015(797)HES
Highway: US 83 Contract #: 04153031
Length: 387.782 CCSJ: 0030-01-031
Limits:  
From: OKLAHOMA STATE LINE Check: $34,000.00
To: SH 15 Misc Cost: $5,100.00
Estimate $1,675,872.35 % Over/Under Company
Bidder 1 $1,135,663.15 -32.23% FLAT LINE, INC.
Bidder 2 $1,162,476.96 -30.63% TEXAS PANHANDLE CONSTRUCTION, INC.
Bidder 3 $1,371,223.67 -18.18% TRP CONSTRUCTION GROUP, LLC
Bidder 4 $1,398,389.21 -16.56% TOTAL HIGHWAY MAINTENANCE, LLC
Bidder 5 $1,432,826.83 -14.50% INTERSTATE BARRICADES & MARKINGS, INC.
Bidder 6 $1,576,986.44 -5.90% PAVEMENT MARKINGS INC.
State Let Construction Projects for April, 2015

Text version of this page
County: POLK Let Date: 04/07/15
Type: REPLACE BRIDGE AND APPROACHES Seq No: 3032
Time: 188 WORKING DAYS Project ID: BR 1502(017)
Highway: FM 1988 Contract #: 04153032
Length: 0.819 CCSJ: 1876-01-030
Limits:  
From: AT LONG KING CREEK Check: $57,000.00
To:   Misc Cost: $6,700.00
Estimate $2,933,447.35 % Over/Under Company
Bidder 1 $3,278,223.27 +11.75% LONGVIEW BRIDGE AND ROAD, LTD.
Bidder 2 $3,500,030.70 +19.31% HODGES AND SON CONSTRUCTION COMPANY, INC.
Bidder 3 $5,267,365.66 +79.56% MISSISSIPPI KEY, LLC
State Let Construction Projects for April, 2015

Text version of this page
County: DALLAS Let Date: 04/07/15
Type: INSTALL PROTECTION Seq No: 3033
Time: 127 WORKING DAYS Project ID: STP 2015(840)HES
Highway: US 80 Contract #: 04153033
Length: 38.053 CCSJ: 0095-02-114
Limits:  
From: EAST OF TOWN EAST BLVD Check: $17,000.00
To: KAUFMAN COUNTY LINE Misc Cost: $47,428.00
Estimate $847,498.80 % Over/Under Company
Bidder 1 $936,969.50 +10.56% ODUM SERVICES, L.P.
Bidder 2 $1,006,866.00 +18.80% FNH CONSTRUCTION, LLC
Bidder 3 $1,021,051.00 +20.48% VANN/ELLI, INC.
Bidder 4 $1,067,392.61 +25.95% ED BELL CONSTRUCTION COMPANY
Bidder 5 $1,223,660.00 +44.38% FIREMAN EXCAVATING, INC.
State Let Construction Projects for April, 2015

Text version of this page
County: RANDALL Let Date: 04/07/15
Type: REPLACE CONCRETE WATER CROSSINGS Seq No: 3034
Time: 230 WORKING DAYS Project ID: C 534-1-20
Highway: PR 5 Contract #: 04153034
Length: 0.620 CCSJ: 0534-01-020
Limits:  
From: AT WATER CROSSINGS 3, 4 AND 5 Check: $58,000.00
To: WITHIN PALO DURO CANYON STATE PARK Misc Cost: $20,000.00
Estimate $3,029,101.73 % Over/Under Company
Bidder 1 $3,768,710.10 +24.42% DCI CONTRACTING, INC.
Bidder 2 $4,324,830.50 +42.78% J. LEE MILLIGAN, INC.
Bidder 3 $4,603,031.32 +51.96% GILVIN-TERRILL, LTD.
Bidder 4 $5,995,015.00 +97.91% EARTH BUILDERS, L.P.