Bid Totals Page 7 of 21

Last Update: Wednesday, October 18, 2017

1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21

Text version of this page
County:LAMARLet Date:08/09/17
Type:CRACK SEALSeq No:4201
Time:39 WProject ID:RMC - 631894001
Highway:US0082Contract #:08174201
Length:0.001CCSJ:6318-94-001
Limits: 
From:VARIOUS LOCATIONS IN LAMAR, DELTA,Check:$6,000
To:RED RIVER COUNTIESMisc Cost:
Estimate$305,385.84% Over/UnderCompany
Bidder 1$243,224.96-20.35%CHAMPION INFRASTRUCTURE, LLC
Bidder 2$248,374.16-18.67%SELECT STRIPING LLC
Bidder 3$251,897.18-17.52%JASCO
Bidder 4$258,074.19-15.49%D & M CONTRACTORS, LLC
State Let Construction Projects for August, 2017

Text version of this page
County:MARTINLet Date:08/09/17
Type:SPECIALTY MARKINGSSeq No:4202
Time:40 WProject ID:RMC - 631534001
Highway:IH0020Contract #:08174202
Length:0.001CCSJ:6315-34-001
Limits: 
From:VARIOUSCheck:$7,000
To:VARIOUSMisc Cost:
Estimate$364,204.50% Over/UnderCompany
Bidder 1$361,435.41-0.76%PMI PAVEMENT MARKING, INC.
Bidder 2$374,145.40+2.73%PAVEMENT MARKINGS INC.
Bidder 3$381,169.00+4.66%DOUBLE A CONTRACTING, L.P.
Bidder 4$392,985.50+7.90%MIJELUM
Bidder 5$448,762.30+23.22%TOTAL HIGHWAY MAINTENANCE, LLC
Bidder 6$524,985.70+44.15%STRIPE-A-ZONE, INC.
Bidder 7$540,580.95+48.43%BARRICADES UNLIMITED
State Let Construction Projects for August, 2017

Text version of this page
County:ECTORLet Date:08/09/17
Type:SPECIALTY MARKINGSSeq No:4203
Time:40 WProject ID:RMC - 631911001
Highway:IH0020Contract #:08174203
Length:0.001CCSJ:6319-11-001
Limits: 
From:VARIOUSCheck:$10,000
To:VARIOUSMisc Cost:
Estimate$521,063.25% Over/UnderCompany
Bidder 1$549,273.52+5.41%PMI PAVEMENT MARKING, INC.
Bidder 2$566,515.40+8.72%DOUBLE A CONTRACTING, L.P.
Bidder 3$577,772.80+10.88%MIJELUM
Bidder 4$651,168.40+24.97%TOTAL HIGHWAY MAINTENANCE, LLC
Bidder 5$719,568.15+38.10%BARRICADES UNLIMITED
Bidder 6$863,429.40+65.71%STRIPE-A-ZONE, INC.
State Let Construction Projects for August, 2017

Text version of this page
County:HARRISLet Date:08/09/17
Type:MNT OF ILLUMINATION SYSSeq No:4204
Time:730 CALENDAR DAYSProject ID:RMC - 631505001
Highway:IH0610Contract #:08174204
Length:0.001CCSJ:6315-05-001
Limits: 
From:VARIOUS HWYS IN HOUSTON DISTRICTCheck:$47,000
To:VARIOUS HWYS IN HOUSTON DISTRICTMisc Cost:$23,500.00
Estimate$2,303,752.57% Over/UnderCompany
Bidder 1$1,982,955.00-13.93%VACA UNDERGROUND UTILITIES INC
Bidder 2$2,093,955.00-9.11%LINDSEY ELECTRIC, L.P.
Bidder 3$2,497,200.00+8.40%IIPL USA LLC
Bidder 4$2,705,586.25+17.44%TRAF-TEX, INC.
State Let Construction Projects for August, 2017

Text version of this page
County:FORT BENDLet Date:08/09/17
Type:CLEANING AND SWEEPING OF HIGHWAYSSeq No:4205
Time:365 CALENDAR DAYSProject ID:RMC - 631870001
Highway:US0059Contract #:08174205
Length:0.001CCSJ:6318-70-001
Limits: 
From:VARIOUS HWYS IN FORT BEND COUNTYCheck:$17,000
To:VARIOUS HWYS IN FORT BEND COUNTYMisc Cost:
Estimate$872,214.70% Over/UnderCompany
Bidder 1$695,757.92-20.23%EXPERT MAINTENANCE & CONSTRUCTION SERVICES LLC
Bidder 2$698,921.20-19.87%SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
Bidder 3$967,276.80+10.90%PANNELL INDUSTRIES, INC.
Bidder 4$973,528.70+11.62%CEN-TEX IRRIGATION SYSTEMS, INC.
State Let Construction Projects for August, 2017

Text version of this page
County:BRAZOSLet Date:08/09/17
Type:SPOT BASE REPAIRSeq No:4206
Time:118 WProject ID:RMC - 631740001
Highway:SH0006Contract #:08174206
Length:0.001CCSJ:6317-40-001
Limits: 
From:VARIOUSCheck:$20,000
To:VARIOUSMisc Cost:
Estimate$1,019,919.25% Over/UnderCompany
Bidder 1$816,109.50-19.98%KNIFE RIVER CORPORATION - SOUTH
Bidder 2$837,235.50-17.91%BIG CREEK CONSTRUCTION, LTD.
Bidder 3$898,300.00-11.92%GLENN FUQUA, INC.
Bidder 4$916,435.00-10.15%ANGEL BROTHERS HOLDINGS CORP.
Bidder 5$938,320.00-8.00%A. L. HELMCAMP, INC.
Bidder 6$1,066,015.00+4.52%CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
Bidder 7$1,643,815.00+61.17%TEXCON GENERAL CONTRACTORS
Bidder 8$5,275,875.00+417.28%FNH CONSTRUCTION, LLC
State Let Construction Projects for August, 2017

Text version of this page
County:JEFFERSONLet Date:08/09/17
Type:PAVEMENT MARKINGSSeq No:4207
Time:365 CALENDAR DAYSProject ID:RMC - 631492001
Highway:US0069Contract #:08174207
Length:0.001CCSJ:6314-92-001
Limits: 
From:DISTRICTWIDECheck:$24,000
To:DISTRICTWIDEMisc Cost:$5,000.00
Estimate$1,183,207.00% Over/UnderCompany
Bidder 1$912,897.50-22.85%CRABTREE BARRICADE SYSTEMS, INC.
Bidder 2$1,171,422.50-1.00%BATTERSON, LLP
State Let Construction Projects for August, 2017

Text version of this page
County:LIBERTYLet Date:08/09/17
Type:OVERLAYSeq No:4208
Time:30 WProject ID:RMC - 631719001
Highway:SH0105Contract #:08174208
Length:2.656CCSJ:6317-19-001
Limits: 
From:SH 321Check:$15,000
To:FM 2518Misc Cost:$13,000.00
Estimate$715,765.54% Over/UnderCompany
Bidder 1$605,866.50-15.35%SMITH & COMPANY
Bidder 2$648,662.97-9.37%CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
Bidder 3$663,185.56-7.35%FORDE CONSTRUCTION COMPANY, INC.
Bidder 4$705,632.41-1.42%OLDCASTLE MATERIALS TEXAS, INC.
Bidder 5$784,892.18+9.66%ANGEL BROTHERS HOLDINGS CORP.
State Let Construction Projects for August, 2017

Text version of this page
County:HIDALGOLet Date:08/09/17
Type:ACP OVERLAY WORKSeq No:4209
Time:80 WProject ID:RMC - 629679001
Highway:FM1015Contract #:08174209
Length:0.010CCSJ:6296-79-001
Limits: 
From:HIDALGO COUNTYCheck:$100,000
To:ZAPATA COUNTYMisc Cost:$20,000.00
Estimate$5,139,906.19% Over/UnderCompany
Bidder 1$4,485,273.80-12.74%IOC COMPANY LLC
Bidder 2$4,573,927.33-11.01%FOREMOST PAVING, INC.
Bidder 3$5,059,906.00-1.56%TEXAS SAI, INC.
Bidder 4$5,823,734.94+13.30%EARTHWORKS ENTERPRISE
State Let Construction Projects for August, 2017

Text version of this page
County:BROWNLet Date:08/09/17
Type:MISCELLANEOUS BRIDGE REPAIRSeq No:4210
Time:65 WProject ID:BPM - 631959001
Highway:US0067Contract #:08174210
Length:0.001CCSJ:6319-59-001
Limits: 
From:VARIOUSCheck:$9,000
To:***Misc Cost:$15,000.00
Estimate$445,453.50% Over/UnderCompany
Bidder 1$564,232.00+26.66%FNH CONSTRUCTION, LLC
Bidder 2$616,640.00+38.43%HODGES AND SON CONSTRUCTION COMPANY, INC.
Bidder 3$644,628.00+44.71%SJ&J CONSTRUCTION, LLC
Bidder 4$670,470.00+50.51%GILVIN-TERRILL, LTD.
Bidder 5$674,350.00+51.39%RESTEK, INC.
Bidder 6$774,520.00+73.87%L.C. JORDAN & SON
State Let Construction Projects for August, 2017

Text version of this page
County:BEXARLet Date:08/09/17
Type:TRAFFIC CONTROLSeq No:4211
Time:365 CALENDAR DAYSProject ID:RMC - 632054001
Highway:IH0010Contract #:08174211
Length:0.001CCSJ:6320-54-001
Limits: 
From:VARIOUSCheck:$66,000
To:VARIOUSMisc Cost:
Estimate$3,300,000.00% Over/UnderCompany
Bidder 1$1,099,124.85-66.69%ALTUS TRAFFIC MANAGEMENT LLC
Bidder 2$1,271,434.35-61.47%AREA WIDE PROTECTIVE, INC.
Bidder 3$1,400,335.00-57.57%FLASHER EQUIPMENT COMPANY
Bidder 4$1,583,125.00-52.03%K-BAR SERVICES, INC.
Bidder 5$1,991,175.00-39.66%SHORT-LINE CORPORATION
Bidder 6$3,173,925.00-3.82%TOTAL HIGHWAY MAINTENANCE, LLC
Bidder 7$3,238,000.00-1.88%NIXON ENGINEERING
State Let Construction Projects for August, 2017

Text version of this page
County:KIMBLELet Date:08/09/17
Type:METAL BEAM GUARDFENCESeq No:4212
Time:180 WProject ID:RMC - 631676001
Highway:IH0010Contract #:08174212
Length:0.001CCSJ:6316-76-001
Limits: 
From:VARIOUS LOCATIONS IN SAN ANGELO DISCheck:$7,000
To:VARIOUS LOCATIONS IN SAN ANGELO DISMisc Cost:
Estimate$330,439.00% Over/UnderCompany
Bidder 1$356,197.60+7.80%K-BAR SERVICES, INC.
State Let Construction Projects for August, 2017

Text version of this page
County:HOUSTONLet Date:08/09/17
Type:MILL AND INLAYSeq No:4213
Time:40 WProject ID:RMC - 632099001
Highway:US0287Contract #:08174213
Length:0.100CCSJ:6320-99-001
Limits: 
From:VARIOUS LOCATIONS IN HOUSTON, POLK,Check:$32,000
To:TRINITY AND SAN JACINTO MAINT. SECTMisc Cost:$1,000.00
Estimate$1,605,280.25% Over/UnderCompany
Bidder 1$1,387,213.56-13.58%BIG CREEK CONSTRUCTION, LTD.
Bidder 2$1,418,657.51-11.63%MOORE BROTHERS CONSTRUCTION COMPANY
Bidder 3$1,443,121.65-10.10%DREWERY CONSTRUCTION COMPANY, INCORPORATED
Bidder 4$1,737,377.96+8.23%SMITH & COMPANY
Bidder 5$2,000,439.38+24.62%FNH CONSTRUCTION, LLC
State Let Construction Projects for August, 2017

Text version of this page
County:HILLLet Date:08/09/17
Type:CRACK SEAL - HOT APPLICATIONSeq No:4214
Time:100 WProject ID:RMC - 631912001
Highway:SH0022Contract #:08174214
Length:0.010CCSJ:6319-12-001
Limits: 
From:VARIOUS LOCATIONS IN BOSQUE,CORYELLCheck:$11,000
To:FALLS,HAMILTON,HILL & MCLENNAN COUNMisc Cost:
Estimate$566,400.03% Over/UnderCompany
Bidder 1$422,070.87-25.48%CHAMPION INFRASTRUCTURE, LLC
Bidder 2$429,806.00-24.12%GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
Bidder 3$438,266.63-22.62%JASCO
Bidder 4$468,847.24-17.22%D & M CONTRACTORS, LLC
Bidder 5$490,110.24-13.47%SELECT STRIPING LLC
Bidder 6$494,179.06-12.75%KEGLEY, INC.
State Let Construction Projects for August, 2017

Text version of this page
County:ELLISLet Date:08/09/17
Type:REHABILITATION OF EXISTING CULVERTSSeq No:4215
Time:365 CALENDAR DAYSProject ID:RMC - 631001001
Highway:FM0984Contract #:08174215
Length:0.001CCSJ:6310-01-001
Limits: 
From:FM 984, FM 985 IN ELLIS COUNTYCheck:$5,000
To:AND FM 3194 IN NAVARRO COUNTYMisc Cost:$1.00
Estimate$236,437.48% Over/UnderCompany
Bidder 1$244,090.00+3.24%L.C. JORDAN & SON
Bidder 2$339,995.00+43.80%O. TREVINO CONSTRUCTION, LLC
State Let Construction Projects for August, 2017

Text version of this page
County:EL PASOLet Date:08/10/17
Type:CHAIN LINK FENCE REPAIRSeq No:2401
Time:365 CALENDAR DAYSProject ID:RMC - 631705001
Highway:SL0375Contract #:08172401
Length:0.000CCSJ:6317-05-001
Limits: 
From:VARIOUS LOCATIONSCheck:$3,000
To:VARIOUS LOCATIONSMisc Cost:
Estimate$168,450.00% Over/UnderCompany
Bidder 1$187,345.46+11.22%KEGLEY, INC.
Bidder 2$268,118.95+59.17%SYNERGY PROJECT CONSULTANTS, INC.
Local Let Projects for August, 2017