Bid Totals Page 15 of 23

Last Update: Wednesday, September 20, 2017

1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23

Text version of this page
County:JEFFERSONLet Date:08/09/17
Type:RESURFACE ROADWAYSeq No:3234
Time:60 WORKING DAYSProject ID:HP 2008(125)
Highway:CSContract #:08173234
Length:4.100CCSJ:0920-38-187
Limits: 
From:ON WASHINGTON BLVD, FROM LOMA LANECheck:$43,000
To:IH-10Misc Cost:$20,000.00
Estimate$2,135,787.10% Over/UnderCompany
Bidder 1$1,690,881.52-20.83%OLDCASTLE MATERIALS TEXAS, INC.
Bidder 2$2,323,598.40+8.79%ANGEL BROTHERS HOLDINGS CORP.
Bidder 3$2,334,637.59+9.31%PTSS INVESTMENTS, LLC
State Let Construction Projects for August, 2017

Text version of this page
County:PARKERLet Date:08/09/17
Type:GRADING, PAVEMENT, STRIPING, & SIGNSeq No:3237
Time:192 WORKING DAYSProject ID:NH 1702(087)
Highway:IH 20Contract #:08173237
Length:0.189CCSJ:0008-03-089
Limits: 
From:450 FT WEST OF FM 5Check:$92,000
To:550 FT EAST OF FM 5Misc Cost:$251,935.00
Estimate$4,579,259.11% Over/UnderCompany
Bidder 1$3,921,685.61-14.36%JAY MILLS CONTRACTING, INCORPORATED
Bidder 2$4,756,849.85+3.88%SEMA CONSTRUCTION, INC.
Bidder 3$5,149,395.37+12.45%ED BELL CONSTRUCTION COMPANY
Bidder 4$6,748,530.10+47.37%FNH CONSTRUCTION, LLC
State Let Construction Projects for August, 2017

Text version of this page
County:LAVACALet Date:08/09/17
Type:REPLACE BRIDGE AND APPROACHESSeq No:3238
Time:90 WORKING DAYSProject ID:BR 2017(117)
Highway:CRContract #:08173238
Length:0.101CCSJ:0913-29-050
Limits: 
From:AT CAMPBELL BRANCH_____CR 198Check:$9,000
To:STR# 13-143-0-AA01-02-001Misc Cost:$1,500.00
Estimate$461,364.30% Over/UnderCompany
Bidder 1$451,306.00-2.18%CONSTAR CONSTRUCTION
Bidder 2$453,672.66-1.67%TREVWAY, INC.
Bidder 3$456,618.92-1.03%ACME BRIDGE COMPANY, INC.
Bidder 4$485,606.79+5.25%CAPITAL EXCAVATION COMPANY
Bidder 5$490,797.71+6.38%HILL COUNTRY BRIDGE, INC.
Bidder 6$517,838.26+12.24%SB CONTRACTORS LLC
Bidder 7$543,534.53+17.81%A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
State Let Construction Projects for August, 2017

Text version of this page
County:REALLet Date:08/09/17
Type:INSTALL FLASHING CHEVRONS AND FLASHING BEACONSSeq No:3239
Time:77 WORKING DAYSProject ID:STP 1702(670)HES
Highway:RM 336Contract #:08173239
Length:30.881CCSJ:0554-01-034
Limits: 
From:VARIOUS LOCATIONS IN SJT DISTRICTCheck:$26,000
To:.Misc Cost:$1,000.00
Estimate$1,322,420.00% Over/UnderCompany
Bidder 1$1,191,740.00-9.88%CHAMPION INFRASTRUCTURE, LLC
Bidder 2$1,323,351.45+0.07%THE LEVY COMPANY, L.P.
Bidder 3$1,355,169.10+2.48%F & W ELECTRICAL CONTRACTORS, INC.
State Let Construction Projects for August, 2017

Text version of this page
County:SMITHLet Date:08/09/17
Type:RPLC BR&APPR,GRADING,ACP BS&SURF,MBGF,PV MKSeq No:3240
Time:100 WORKING DAYSProject ID:BR 1702(756)
Highway:FM 850Contract #:08173240
Length:0.126CCSJ:1163-01-022
Limits: 
From:AT MUD CREEKCheck:$24,000
To:.Misc Cost:$3,000.00
Estimate$1,206,583.50% Over/UnderCompany
Bidder 1$1,077,661.37-10.68%STATELINE CONSTRUCTION, LLC
Bidder 2$1,094,547.48-9.29%PIERCE R & B LLC
Bidder 3$1,126,610.12-6.63%LONGVIEW BRIDGE AND ROAD, LTD.
Bidder 4$1,149,476.57-4.73%EAST TEXAS BRIDGE, INC.
Bidder 5$1,171,873.01-2.88%HIGHWAY 19 CONSTRUCTION LLC
Bidder 6$1,177,662.50-2.40%HODGES AND SON CONSTRUCTION COMPANY, INC.
Bidder 7$1,231,288.07+2.05%CDM HOLDINGS, LLC
Bidder 8$1,363,263.65+12.99%REID CONSTRUCTION, INC.
State Let Construction Projects for August, 2017

Text version of this page
County:HARRISLet Date:08/09/17
Type:LANDSCAPINGSeq No:3241
Time:75 WORKING DAYSProject ID:NH 1702(630)
Highway:IH 10Contract #:08173241
Length:1.730CCSJ:0271-06-126
Limits: 
From:LONGHORN RANCH AVECheck:$21,000
To:BUCKEYE DRIVEMisc Cost:$1,500.00
Estimate$840,359.50% Over/UnderCompany
Bidder 1$825,265.46-1.80%YELLOWSTONE LANDSCAPE - CENTRAL, INC.
Bidder 2$945,353.45+12.49%BOYER, INC.
Bidder 3$952,693.75+13.37%TEXAS WALL & LANDSCAPE
State Let Construction Projects for August, 2017

Text version of this page
County:TARRANTLet Date:08/09/17
Type:SAFETY TREAT FIXED OBJECTSSeq No:3242
Time:24 WORKING DAYSProject ID:STP 1702(738)HESG
Highway:SH 360Contract #:08173242
Length:0.191CCSJ:2266-02-146
Limits: 
From:0.349 MI N OF SH 180Check:$5,000
To:0.158 MI N OF SH 180Misc Cost:$39,101.00
Estimate$263,490.28% Over/UnderCompany
Bidder 1$281,936.15+7.00%ARANDA BROTHERS CONSTRUCTION CO., INC.
Bidder 2$307,268.95+16.61%JAY MILLS CONTRACTING, INCORPORATED
Bidder 3$333,272.59+26.48%GIBSON & ASSOCIATES, INC.
Bidder 4$341,872.55+29.75%O. TREVINO CONSTRUCTION, LLC
Bidder 5$342,418.69+29.95%STRUCTURAL ASSURANCE, LLC
Bidder 6$425,591.30+61.52%FNH CONSTRUCTION, LLC
Bidder 7$449,853.30+70.73%ED BELL CONSTRUCTION COMPANY
Bidder 8$701,542.40+166.25%SJ&J CONSTRUCTION, LLC
State Let Construction Projects for August, 2017

Text version of this page
County:TARRANTLet Date:08/09/17
Type:INTERSECTION IMPROVEMENTSSeq No:3243
Time:165 WORKING DAYSProject ID:CM 2007(227)
Highway:CSContract #:08173243
Length:0.266CCSJ:0902-48-576
Limits: 
From:0.152 MI S OF MID CITIES BLVDCheck:$84,000
To:0.114 MI N OF MID CITIES BLVDMisc Cost:$67,705.00
Estimate$4,199,189.85% Over/UnderCompany
Bidder 1$4,658,453.87+10.94%MCMAHON CONTRACTING, L.P.
Bidder 2$4,786,542.44+13.99%RAGLE CONSTRUCTION, INC.
Bidder 3$4,861,965.37+15.78%REBCON, INC.
Bidder 4$5,069,384.19+20.72%ED BELL CONSTRUCTION COMPANY
Bidder 5$5,079,033.85+20.95%FNH CONSTRUCTION, LLC
State Let Construction Projects for August, 2017

Text version of this page
County:MILAMLet Date:08/09/17
Type:REPLACE EXISTING BRIDGESeq No:3244
Time:70 WORKING DAYSProject ID:BR 1702(780)
Highway:FM 485Contract #:08173244
Length:0.161CCSJ:0262-07-033
Limits: 
From:AT COW CREEKCheck:$13,000
To:.Misc Cost:$13,320.00
Estimate$663,629.65% Over/UnderCompany
Bidder 1$668,667.60+0.76%KNIFE RIVER CORPORATION - SOUTH
Bidder 2$696,806.87+5.00%JAMES CONSTRUCTION GROUP, L.L.C.
Bidder 3$699,502.33+5.41%3LW CIVIL LLC
Bidder 4$788,617.99+18.83%PROJECT ALLIED RESOURCES, LLC
Bidder 5$790,930.90+19.18%ELLIS-MCGINNIS CONSTRUCTION CO.
Bidder 6$853,333.48+28.59%PIERCE R & B LLC
Bidder 7$859,230.88+29.47%A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
Bidder 8$928,271.16+39.88%TREVWAY, INC.
Bidder 9$974,598.80+46.86%HODGES AND SON CONSTRUCTION COMPANY, INC.
State Let Construction Projects for August, 2017

Text version of this page
County:HARRISONLet Date:08/09/17
Type:GR,STR,BASE,SURFACINGSeq No:3245
Time:124 WORKING DAYSProject ID:CC 843-7-16
Highway:FM 2625Contract #:08173245
Length:0.433CCSJ:0843-07-016
Limits: 
From:0.45 MI. W. OF SH 43Check:$50,000
To:SH 43Misc Cost:$17,500.00
Estimate$2,544,726.15% Over/UnderCompany
Bidder 1$2,284,633.31-10.22%LONGVIEW BRIDGE AND ROAD, LTD.
Bidder 2$2,449,449.99-3.74%PIERCE R & B LLC
Bidder 3$2,532,275.73-0.49%EAST TEXAS BRIDGE, INC.
Bidder 4$2,565,815.85+0.83%3LW CIVIL LLC
Bidder 5$2,697,670.80+6.01%HIGHWAY 19 CONSTRUCTION LLC
Bidder 6$3,204,450.15+25.93%L. S. EQUIPMENT CO., INC.
Bidder 7$3,303,028.20+29.80%HODGES AND SON CONSTRUCTION COMPANY, INC.
State Let Construction Projects for August, 2017

Text version of this page
County:GRAYSONLet Date:08/08/17
Type:CRACK SEALSeq No:4002
Time:46 WProject ID:RMC - 631895001
Highway:US0082Contract #:08174002
Length:0.001CCSJ:6318-95-001
Limits: 
From:VARIOUS LOCATIONS IN GRAYSON ANDCheck:$7,000
To:FANNIN COUNTIESMisc Cost:
Estimate$342,255.20% Over/UnderCompany
Bidder 1$249,491.12-27.10%D & M CONTRACTORS, LLC
Bidder 2$287,278.08-16.06%SELECT STRIPING LLC
Bidder 3$299,995.87-12.35%JASCO
Bidder 4$347,934.56+1.66%CHAMPION INFRASTRUCTURE, LLC
Bidder 5$500,271.00+46.17%FNH CONSTRUCTION, LLC
State Let Maintenance Projects for August, 2017

Text version of this page
County:PECOSLet Date:08/08/17
Type:CLEANING AND SEALING CRACKSSeq No:4003
Time:78 WProject ID:RMC - 631917001
Highway:IH0010Contract #:08174003
Length:624.800CCSJ:6319-17-001
Limits: 
From:VARIOUSCheck:$9,000
To:VARIOUSMisc Cost:
Estimate$445,860.00% Over/UnderCompany
Bidder 1$337,396.00-24.33%L&L COMPANY
Bidder 2$342,542.00-23.17%D & M CONTRACTORS, LLC
Bidder 3$378,659.88-15.07%KEGLEY, INC.
Bidder 4$455,064.00+2.06%CHAMPION INFRASTRUCTURE, LLC
Bidder 5$512,840.00+15.02%JASCO
State Let Construction Projects for August, 2017

Text version of this page
County:WARDLet Date:08/08/17
Type:CLEANING AND SEALING CRACKSSeq No:4004
Time:58 WProject ID:RMC - 631918001
Highway:IH0020Contract #:08174004
Length:461.200CCSJ:6319-18-001
Limits: 
From:VARIOUSCheck:$7,000
To:VARIOUSMisc Cost:
Estimate$328,840.00% Over/UnderCompany
Bidder 1$271,212.40-17.52%D & M CONTRACTORS, LLC
Bidder 2$299,783.00-8.84%L&L COMPANY
Bidder 3$340,816.00+3.64%CHAMPION INFRASTRUCTURE, LLC
Bidder 4$380,960.00+15.85%JASCO
State Let Construction Projects for August, 2017

Text version of this page
County:WALLERLet Date:08/08/17
Type:ASPHALT PAVEMENT REPAIRSeq No:4006
Time:365 CALENDAR DAYSProject ID:RMC - 631612001
Highway:US0290Contract #:08174006
Length:0.001CCSJ:6316-12-001
Limits: 
From:VARIOUS HWYS IN WALLER COUNTYCheck:$11,000
To:VARIOUS HWYS IN WALLER COUNTYMisc Cost:$2,500.00
Estimate$561,430.00% Over/UnderCompany
Bidder 1$521,960.00-7.03%MAIN LANE INDUSTRIES LTD.
Bidder 2$914,900.00+62.96%CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
State Let Construction Projects for August, 2017

Text version of this page
County:DEWITTLet Date:08/08/17
Type:ON-CALL THERMO PAVEMENT MARKINGSSeq No:4007
Time:365 CALENDAR DAYSProject ID:RMC - 631882001
Highway:US0183Contract #:08174007
Length:0.001CCSJ:6318-82-001
Limits: 
From:AUSTIN, DEWITT, FAYETTE, GONZALES,Check:$13,000
To:LAVACA AND COLORADO COUNTIESMisc Cost:$1,000.00
Estimate$640,500.00% Over/UnderCompany
Bidder 1$484,590.00-24.34%BATTERSON, LLP
Bidder 2$511,370.00-20.16%PAVEMENT MARKINGS INC.
Bidder 3$535,450.00-16.40%FLASHER EQUIPMENT COMPANY
Bidder 4$612,750.00-4.33%TRP CONSTRUCTION GROUP, LLC
Bidder 5$636,700.00-0.59%INTERSTATE BARRICADES & MARKINGS, INC.
State Let Construction Projects for August, 2017

Text version of this page
County:SAN PATRICIOLet Date:08/08/17
Type:CONCRETE RIPRAP REPAIR & DITCH CLEANINGSeq No:4008
Time:365 CALENDAR DAYSProject ID:RMC - 631923001
Highway:FM0796Contract #:08174008
Length:0.999CCSJ:6319-23-001
Limits: 
From:VARIOUSCheck:$9,000
To:.Misc Cost:
Estimate$469,316.00% Over/UnderCompany
Bidder 1$457,753.32-2.46%BECK-REIT & SONS, LTD.
Bidder 2$498,591.00+6.24%CHAMPION INFRASTRUCTURE, LLC
Bidder 3$621,304.29+32.39%J. CARROLL WEAVER, INC.
Bidder 4$646,343.50+37.72%MAIN LANE INDUSTRIES LTD.
Bidder 5$2,367,311.00+404.42%JIMMY EVANS COMPANY, LTD.
State Let Construction Projects for August, 2017