Monthly State Let Construction Report For Fort Worth District As Of Aug 12, 2014 Page 4 Of 6

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTARRANT
Highway CS
From W 7TH ST OVER THE TRINITY
To .
CSJ 0902-48-505
Proj ID BR 2006(767)
Work Type REPL BR & APPRS
 
0.559 24150158.45 168543.09 24885943.21 99.9
Work Order 08-10-11
Work Began 05-07-12
Work Completed  
Time Computed 08-26-11
Contract Working Days 327
Addl Days Granted 0
Working Days Charged 327
Percent Time Used 100
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-505
COWTOWN TRAFFIC CONTROL, INC.(0.06%)
C.T. AND S. METALWORKS, INC. (1.16%)
CAIN FENCE (0.07%)
HIGHWAY TECHNOLOGIES, INC. (0.00%)
INDUS CONSTRUCTION, L.P. (1.83%)
MICA CORPORATION (2.46%)
NORTH TEXAS CONTRACTING, INC.(1.06%)
SCOTT DERR PAINTING CO, LLC(1.62%)
TEX OP CONSTRUCTION, LP(0.05%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.29%)
VSTRUCTURAL LLC(3.46%)
BURKHALTER RIGGING, INC. (7.22%)
PEACHTREE CONSTRUCTION, LTD. (0.30%)
ATS DRILLING, INC. (4.50%)
GREAT WESTERN ERECTORS (0.23%)
LINDAMOOD DEMOLITION, INC. (3.04%)
PENHALL COMPANY(0.04%)
CROSSROADS, L.P. (0.10%)
BRENDA PRICE TRUCKING(0.03%)
SKAGGS ROAD BORING INC.(0.00%)
STRIPING TECHNOLOGY, L.P.(0.10%)
INLET STRUCTURE SPECIALTIES LTD. (0.21%)
A R DANIEL CONSTRUCTION SERVICES, INC. (0.22%)
GREEN SCAPING(1.46%)
EROSION PREVENTION PRODUCTS(1.35%)
Contract # 06113245
Totals 24150158.45 168543.09 24885943.21 99.9

CountyTARRANT
Highway CS
From SOUTH STEWART STREET AT ASH CREEK
To IN AZLE
CSJ 0902-48-506
Proj ID BR 2003(356)
Work Type REPLACE BR & APPRS
 
0.135 799000.00 0.00 65370.91 8.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-06-12
Work Began 00-00-00
Work Completed  
Time Computed 06-05-12
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EMPIRE CIVIL CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-506
ACTION SERVICES(0.35%)
FORTSON CONTRACTING, INC.(1.63%)
GJ SEEDING, LLC(2.58%)
PEACHTREE CONSTRUCTION, LTD. (5.65%)
TEXAS SHAFTS, INC. (6.70%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.35%)
Contract # 01123025
Totals 799000.00 0.00 65370.91 8.1

CountyTARRANT
Highway CS
From PRECINCT LINE RD. AT WALKER BRANCH
To FORT WORTH
CSJ 0902-48-539
Proj ID BR 2006(132)
Work Type REPLACE BRIDGE
 
0.138 2287447.40 70072.26 70072.26 3.0
CountyTARRANT
Highway CS
From SH 10; ON PRECINCT LINE ROAD
To N OF TRAMMEL DAVIS; IN FT. WORTH
CSJ 0902-48-680
Proj ID HP 2007(860)
Work Type GR, DR, STR & PAVING
 
0.642 4245929.63 0.00 0.00 0.0
CountyTARRANT
Highway CS
From TRINITY BLVD; IN FORT WORTH
To AT PRECINCT LINE ROAD
CSJ 0902-48-793
Proj ID CM 2013(785)
Work Type GR, DR, PAVEMENT
 
0.420 3954288.21 0.00 0.00 0.0
Work Order 11-08-13
Work Began 00-00-00
Work Completed  
Time Computed 05-08-14
Contract Working Days 315
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-539
TOTAL HIGHWAY MAINTENANCE, LLC (0.77%)
SCOTT DERR PAINTING CO, LLC(0.13%)
TEX OP CONSTRUCTION, LP(0.62%)
STAR OPERATIONS, INC.(2.74%)
PREMIER PAVING, LTD. (8.52%)
BREDA COMPANY, INC.(0.76%)
SUNDANCE FENCE & IRON, LLC (0.19%)
GJ SEEDING, LLC(1.25%)
BUYERS BARRICADES, INC.(0.26%)
HANSON PRESSURE PIPE, INC. (0.03%)
A & A CONSTRUCTION (1.15%)
DISPLAYS UNLIMITED, INC. (0.08%)
Contract # 08133013
Totals 10487665.24 70072.26 70072.26 0.6

CountyTARRANT
Highway CS
From SILVER CREEK RD @ SILVER CREEK,FT W
To .
CSJ 0902-48-742
Proj ID BR 2009(953)
Work Type REPLACE BRIDGE
 
0.087 1031130.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CD BUILDERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-742
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143052
Totals 1031130.80 0.00 0.00 0.0

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To IN TARRANT COUNTY
CSJ 0902-48-822
Proj ID NH 2012(353)
Work Type CONSTRUCT CURB RAMPS
 
0.001 3378473.70 41572.08 3313831.06 98.1
Work Order 06-08-12
Work Began 07-16-12
Work Completed  
Time Computed 06-24-12
Contract Working Days 283
Addl Days Granted 143
Working Days Charged 429
Percent Time Used 100
Contractor(s)
KEN-DO CONTRACTING, LP
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-822
ROAD MASTER STRIPING LLC (7.83%)
MEL"S ELECTRIC SERVICE, INC. ( 21.22%)
TEX OP CONSTRUCTION, LP(0.11%)
ALLIANCE TRUCKING(0.18%)
APAC-TEXAS, INC. (0.07%)
CHAPAS TRUCKING(0.11%)
ROJO TRUCKING(0.00%)
Contract # 03123020
Totals 3378473.70 41572.08 3313831.06 98.1

CountyTARRANT
Highway CS
From ARBROOK BLVD
To BARDIN ROAD, IN ARLINGTON
CSJ 0902-48-838
Proj ID CC 902-48-838
Work Type GRADING, STRUCTURES AND PAVEMENT
 
0.740 10457967.33 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 380
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-838
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143005
Totals 10457967.33 0.00 0.00 0.0

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To IN TARRANT COUNTY
CSJ 0902-48-844
Proj ID STP 2014(071)
Work Type CURB RAMPS
 
0.001 1813396.74 60232.23 456592.06 25.1
Work Order 01-17-14
Work Began 02-10-14
Work Completed  
Time Computed 02-02-14
Contract Working Days 216
Addl Days Granted 0
Working Days Charged 104
Percent Time Used 48
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-844
ALTUS TRAFFIC MANAGEMENT LLC (0.66%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(7.68%)
Contract # 10133220
Totals 1813396.74 60232.23 456592.06 25.1

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To TARRANT COUNTY ONLY FY 2013
CSJ 0902-48-849
Proj ID STP 2013(836)
Work Type BRIDGE REPAIR
 
0.100 2687139.38 781523.55 1397657.66 52.0
Work Order 11-05-13
Work Began 04-13-14
Work Completed  
Time Computed 11-21-13
Contract Working Days 175
Addl Days Granted 22
Working Days Charged 67
Percent Time Used 34
Contractor(s)
SILVER CREEK CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-849
PEACHTREE CONSTRUCTION, LTD. ( 45.90%)
VIKING CONSTRUCTION, INC.(1.14%)
TEX OP CONSTRUCTION, LP(2.68%)
M & M STRIPING & POWER WASHING, LLC(1.78%)
COWBOY TRUCKING(0.00%)
GLORIA VALENZUELA ENTERPRISE, INC(0.00%)
Contract # 07133234
Totals 2687139.38 781523.55 1397657.66 52.0

CountyTARRANT
Highway VA
From IH 20, IH 30, IH 820, IH 35W_AT
To VARIOUS LOCATIONS IN TARRANT COUNTY
CSJ 0902-48-895
Proj ID NH 1402(035)
Work Type GR, STR
 
0.100 1299947.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SILVER CREEK CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-895
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143242
Totals 1299947.50 0.00 0.00 0.0

CountyERATH
Highway CR
From CR 266 AT GREEN CREEK
To .
CSJ 0902-49-063
Proj ID BR 2009(105)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 457947.66 102488.28 393042.33 85.8
Work Order 04-02-14
Work Began 05-07-14
Work Completed  
Time Computed 05-07-14
Contract Working Days 51
Addl Days Granted 10
Working Days Charged 50
Percent Time Used 81
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0902-49-063
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.33%)
RICE ENVIRONMENTAL SERVICES(3.46%)
LONE OAK LANDSCAPE LLC (0.26%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.50%)
MCL CONTRACTING, LLC (0.46%)
KLP COMMERCIAL, LLC(0.00%)
Contract # 02143229
Totals 457947.66 102488.28 393042.33 85.8

CountyERATH
Highway VA
From VARIOUS LOCATIONS
To AROUND STEPHENVILLE
CSJ 0902-49-066
Proj ID STP 2012(569)
Work Type LANDSCAPE ENHANCEMENT
 
0.282 379628.18 2310.00 335228.91 88.3
Work Order 06-18-12
Work Began 10-01-12
Work Completed  
Time Computed 07-04-12
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 95
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0902-49-066
MEMCO(6.42%)
LONE OAK LANDSCAPE LLC ( 50.03%)
Contract # 05123017
Totals 379628.18 2310.00 335228.91 88.3

CountyERATH
Highway VA
From US 377/SH 108 INTERSECTION
To BU377J/LILLIAN ST; IN STEPHENVILLE
CSJ 0902-49-067
Proj ID STP 2013(193)
Work Type LANDSCAPE ENHANCEMENT
 
0.100 137204.63 491.67 132839.07 96.8
Work Order 09-26-13
Work Began 10-21-13
Work Completed  
Time Computed 10-12-13
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 66
Contractor(s)
ALL AROUND LAWN CARE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-49-067
MEMCO( 14.55%)
Contract # 06133010
Totals 137204.63 491.67 132839.07 96.8

CountyJOHNSON
Highway CR
From AT KING BRANCH
To ON CR 519
CSJ 0902-50-108
Proj ID BR 2012(761)
Work Type GR, BS, STRUCTURE
 
0.083 392475.80 0.00 400108.88 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-16-13
Work Began 12-03-13
Work Completed  
Time Computed 10-02-13
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 128
Contractor(s)
REBCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-50-108
STRIPING TECHNOLOGY, L.P.(0.80%)
GJ SEEDING, LLC(3.76%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.84%)
PEACHTREE CONSTRUCTION, LTD. (6.35%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (3.66%)
FORTSON CONTRACTING, INC.(2.34%)
Contract # 08133046
Totals 392475.80 0.00 400108.88 99.9

CountyTARRANT
Highway IH 30
From AT UPRR
To IN GRAND PRAIRIE
CSJ 1068-02-129
Proj ID IM 0304(100)
Work Type BRIDGE REPAIRS
 
0.100 98730.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 29
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1068-02-129
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143036
Totals 98730.00 0.00 0.00 0.0

CountyTARRANT
Highway IH 30
From COOPER_STREET
To FIELDER_ROAD
CSJ 1068-02-140
Proj ID IM 0304(097)
Work Type GR, BS AND SURFACE
 
0.999 639953.15 0.00 632534.52 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-19-13
Work Began 09-30-13
Work Completed  
Time Computed 09-04-13
Contract Working Days 64
Addl Days Granted 1
Working Days Charged 100
Percent Time Used 153
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1068-02-140
BRENDA PRICE TRUCKING(0.00%)
CROSSROADS, L.P. (0.75%)
DUSTROL, INC.(2.47%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(9.29%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (5.98%)
STRIPING TECHNOLOGY, L.P.(3.07%)
PEACHTREE CONSTRUCTION, LTD. (9.72%)
W.O.E. CONSTRUCTION(0.16%)
Contract # 06133215
Totals 639953.15 0.00 632534.52 99.9

CountyTARRANT
Highway IH 30
From IH 820
To W OF COOPER STREET
CSJ 1068-02-141
Proj ID IM 0304(099)
Work Type HMAC OVERLAY
 
5.681 5418484.81 685800.99 1359217.10 25.0
Work Order 04-25-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 38
Percent Time Used 53
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1068-02-141
DUSTROL, INC.( 10.85%)
PRIMATE CONSTRUCTION, INC. (3.47%)
TOTAL HIGHWAY MAINTENANCE, LLC (3.27%)
ALTUS TRAFFIC MANAGEMENT LLC (0.09%)
BRENDA PRICE TRUCKING(0.90%)
COWBOY TRUCKING(2.10%)
Contract # 02143222
Totals 5418484.81 685800.99 1359217.10 25.0

CountyTARRANT
Highway SS 341
From SH-183/IH-30 INTERCHANGE
To N WHITE SETTLEMENT RD INTERCHANGE
CSJ 1068-03-021
Proj ID STP 2013(288)
Work Type LANDSCAPE ENHANCEMENT
 
1.905 124997.55 1153.00 110307.98 88.2
Work Order 09-17-13
Work Began 10-17-13
Work Completed  
Time Computed 10-03-13
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 86
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1068-03-021
ALTUS TRAFFIC MANAGEMENT LLC (2.08%)
Contract # 08133024
Totals 124997.55 1153.00 110307.98 88.2

CountyPARKER
Highway IH 30
From IH 20, AT WALSH RANCH PARKWAY
To TARRANT COUNTY LINE
CSJ 1068-05-009
Proj ID IM 0304(092)
Work Type GRADING, DRAINAGE, STRUCTURE & PAVE
 
1.541 14593117.40 495569.61 5837517.80 40.0
Work Order 09-03-13
Work Began 10-01-13
Work Completed  
Time Computed 09-19-13
Contract Working Days 225
Addl Days Granted 95
Working Days Charged 200
Percent Time Used 62
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1068-05-009
DALLAS LITE AND BARRICADE INC. (0.22%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.80%)
SCOTT DERR PAINTING CO (0.23%)
COWBOY TRUCKING(3.09%)
W.O.E. CONSTRUCTION(0.41%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(5.28%)
T-BAR FENCE, INC.(0.04%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.55%)
PEACHTREE CONSTRUCTION, LTD. (9.14%)
BUYERS BARRICADES, INC.(0.33%)
DUSTROL, INC.(0.53%)
HJC FARMS, INC.(1.45%)
ATS DRILLING, INC. (0.60%)
BREDA COMPANY, INC.(1.31%)
FORTSON CONTRACTING, INC.(0.05%)
Contract # 04133201
Totals 14593117.40 495569.61 5837517.80 40.0

CountyWISE
Highway FM 718
From SH 114
To NORTH END OF DERRETT CREEK BRIDGE
CSJ 1098-01-020
Proj ID STP 2011(599)
Work Type GRADING, DRAINAGE AND PAVEMENT
 
5.649 4598915.86 195075.54 2231084.85 48.5
Work Order 12-03-13
Work Began 02-18-14
Work Completed  
Time Computed 02-02-14
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 123
Percent Time Used 54
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1098-01-020
LANCO TURF & SEEDING, INC. (0.64%)
PEACHTREE CONSTRUCTION, LTD. (4.20%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.86%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.41%)
TEX OP CONSTRUCTION, LP(0.21%)
ALTUS TRAFFIC MANAGEMENT LLC (0.51%)
TRANSPORT TRUST(0.54%)
NORTH TEXAS CONTRACTING, INC.( 10.34%)
STORM WATER MANAGEMENT, INC. (0.51%)
STRIPING TECHNOLOGY, L.P.(1.70%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(2.93%)
Contract # 08133272
Totals 4598915.86 195075.54 2231084.85 48.5

CountyPALO PINTO
Highway FM 919
From AT PANTHER CREEK RELIEF BRIDGE
To .
CSJ 1178-01-026
Proj ID BR 2007(290)
Work Type REPLACE BRIDGE
 
0.104 391234.00 140782.81 199532.81 51.0
Work Order 05-29-14
Work Began 06-25-14
Work Completed  
Time Computed 06-14-14
Contract Working Days 46
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 45
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1178-01-026
BICK"S CONSTRUCTION, INC.( 22.02%)
FORTSON CONTRACTING, INC.(3.43%)
TRP CONSTRUCTION GROUP, LLC(0.00%)
Contract # 04143015
Totals 391234.00 140782.81 199532.81 51.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6