| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | TARRANT |
| Highway |
VA |
| From |
VARIOUS LOCATIONS |
| To |
IN TARRANT COUNTY |
| CSJ |
0902-48-822 |
| Proj ID |
NH 2012(353) |
| Work Type |
CONSTRUCT CURB RAMPS |
| |
|
0.001 |
3378473.70 |
165674.45 |
1615784.29 |
47.8 |
| Work Order |
06-08-12 |
| Work Began |
07-16-12 |
| Work Completed |
|
| Time Computed |
06-24-12 |
| Contract Working Days |
283 |
| Addl Days Granted |
0 |
| Working Days Charged |
206 |
| Percent Time Used |
72 |
| Contractor(s) |
| KEN-DO CONTRACTING, LP |
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-822 ROAD MASTER STRIPING LLC (7.83%) MEL"S ELECTRIC SERVICE, INC. ( 21.22%) TEX OP CONSTRUCTION, LP(0.11%) ALLIANCE TRUCKING(0.18%) APAC-TEXAS, INC. (0.07%) CHAPAS TRUCKING(0.11%)
|
| Contract # |
03123020 |
|
Totals |
3378473.70 |
165674.45 |
1615784.29 |
47.8 |
|
| County | ERATH |
| Highway |
VA |
| From |
VARIOUS LOCATIONS |
| To |
AROUND STEPHENVILLE |
| CSJ |
0902-49-066 |
| Proj ID |
STP 2012(569) |
| Work Type |
LANDSCAPE ENHANCEMENT |
| |
|
0.282 |
379628.18 |
0.00 |
232655.20 |
61.2 |
| Work Order |
06-18-12 |
| Work Began |
10-01-12 |
| Work Completed |
|
| Time Computed |
07-04-12 |
| Contract Working Days |
63 |
| Addl Days Granted |
0 |
| Working Days Charged |
55 |
| Percent Time Used |
87 |
| Contractor(s) |
| JAY MILLS CONTRACTING, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 0902-49-066 MEMCO(6.42%) LONE OAK LANDSCAPE LLC ( 50.03%)
|
| Contract # |
05123017 |
|
Totals |
379628.18 |
0.00 |
232655.20 |
61.2 |
|
| County | TARRANT |
| Highway |
IH 30 |
| From |
PARKER/TARRANT COUNTY LINE |
| To |
LINKCREST |
| CSJ |
1068-01-201 |
| Proj ID |
IM 0304(096) |
| Work Type |
HMAC OVERLAY |
| |
|
2.066 |
1479637.07 |
96711.46 |
96711.46 |
6.5 |
| Work Order |
10-18-12 |
| Work Began |
04-24-13 |
| Work Completed |
|
| Time Computed |
04-17-13 |
| Contract Working Days |
48 |
| Addl Days Granted |
0 |
| Working Days Charged |
2 |
| Percent Time Used |
4 |
| Contractor(s) |
| APAC-TEXAS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1068-01-201 SCR CONSTRUCTION CO., INC. (9.05%) CROSSROADS, L.P. (0.43%) STRIPING TECHNOLOGY, L.P.(4.07%) DUSTROL, INC.( 13.19%) PENHALL COMPANY(0.10%)
|
| Contract # |
09123243 |
|
Totals |
1479637.07 |
96711.46 |
96711.46 |
6.5 |
|
| County | PARKER |
| Highway |
IH 30 |
| From |
IH 20, AT WALSH RANCH PARKWAY |
| To |
TARRANT COUNTY LINE |
| CSJ |
1068-05-009 |
| Proj ID |
IM 0304(092) |
| Work Type |
GRADING, DRAINAGE, STRUCTURE & PAVE |
| |
|
1.541 |
14593117.40 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
225 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| HAYDON BUILDING CORP. |
SUBCONTRACTOR(S) FOR CCSJ: 1068-05-009 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04133201 |
|
Totals |
14593117.40 |
0.00 |
0.00 |
0.0 |
|
| County | TARRANT |
| Highway |
FM 1187 |
| From |
NEWT PATTERSON |
| To |
BU 287P |
| CSJ |
1330-02-034 |
| Proj ID |
STP 2010(399)ES |
| Work Type |
GRADING, DRAINAGE, STRUCTURES & PAV |
| |
|
1.503 |
6895052.12 |
162915.88 |
4798371.77 |
69.5 |
| Work Order |
05-05-10 |
| Work Began |
06-17-11 |
| Work Completed |
|
| Time Computed |
11-01-10 |
| Contract Working Days |
427 |
| Addl Days Granted |
0 |
| Working Days Charged |
425 |
| Percent Time Used |
99 |
| Contractor(s) |
| LONE STAR CIVIL CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1330-02-034 UNDERGROUND COALITION, INC.(2.92%) INLET STRUCTURE SPECIALTIES LTD. (2.88%) DURABLE SPECIALTIES, INC.(2.04%) BANDA TRUCKING COMPANY (0.10%) STORM WATER MANAGEMENT, INC. (0.31%) INDUS CONSTRUCTION, L.P. (8.05%) AUSTIN BRIDGE & ROAD, LP ( 17.43%) TOTAL HIGHWAY MAINTENANCE, LLC (1.34%) DUSTROL, INC.(0.53%) JM MATERIALS, INC. (0.32%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.83%)
|
| Contract # |
03103004 |
|
Totals |
6895052.12 |
162915.88 |
4798371.77 |
69.5 |
|
| County | TARRANT |
| Highway |
FM 1187 |
| From |
0.5 MILE EAST OF IH 35W |
| To |
EAST OF OAK GROVE S (EAST INTER) |
| CSJ |
1330-02-041 |
| Proj ID |
NH 1102(093) |
| Work Type |
GR, DR, STRUC, AND PAVING |
| |
|
1.425 |
3679267.90 |
39318.50 |
2960873.02 |
80.9 |
| Work Order |
08-19-11 |
| Work Began |
02-14-12 |
| Work Completed |
|
| Time Computed |
09-04-11 |
| Contract Working Days |
256 |
| Addl Days Granted |
14 |
| Working Days Charged |
291 |
| Percent Time Used |
107 |
| Contractor(s) |
| JAGOE-PUBLIC COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1330-02-041 TEX OP CONSTRUCTION, LP(0.59%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.60%) NORTH TEXAS CONTRACTING, INC.(4.52%) FORTSON CONTRACTING, INC.(1.95%) HIGHWAY TECHNOLOGIES, INC. (3.18%) ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(7.59%) CEN CONCRETE CONSTRUCTION COMPANY, INC.(1.21%) PEACHTREE CONSTRUCTION, LTD. (1.16%) FOUNDATION DRILLERS, INC.(0.23%)
|
| Contract # |
06113235 |
|
Totals |
3679267.90 |
39318.50 |
2960873.02 |
80.9 |
|
| County | TARRANT |
| Highway |
FM 1187 |
| From |
AT BF 1187C (E. MAIN ST) |
| To |
IN CROWLEY |
| CSJ |
1330-03-002 |
| Proj ID |
CC 1330-3-2 |
| Work Type |
TRAFFIC SIGNAL |
| |
|
0.100 |
129000.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-03-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
30 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| DURABLE SPECIALTIES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1330-03-002 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12123211 |
|
Totals |
129000.00 |
0.00 |
0.00 |
0.0 |
|
| County | PARKER |
| Highway |
FM 730 |
| From |
AT LAKE WEATHERFORD |
| To |
. |
| CSJ |
1601-01-018 |
| Proj ID |
BR 2006(503) |
| Work Type |
REPLACE BRIDGE |
| |
|
0.677 |
2502493.61 |
0.00 |
2425501.55 |
96.9 |
| Work Order |
09-14-11 |
| Work Began |
10-07-11 |
| Work Completed |
|
| Time Computed |
09-30-11 |
| Contract Working Days |
256 |
| Addl Days Granted |
0 |
| Working Days Charged |
256 |
| Percent Time Used |
100 |
| Contractor(s) |
| JAY MILLS CONTRACTING, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 1601-01-018 COPPELL CONSTRUCTION CO., INC. ( 38.35%) TEXAS SHAFTS, INC. (3.46%) TEXAS ALTERNATIVE GRASSER, INC.(0.40%) FORTSON CONTRACTING, INC.(1.04%) NORTHEASTERN PAVERS, INC.( 17.00%) STRIPING TECHNOLOGY, L.P.(1.21%) HOUSTON SAWING & DRILLING(0.11%) RG PAINTING(0.39%)
|
| Contract # |
08113258 |
|
Totals |
2502493.61 |
0.00 |
2425501.55 |
96.9 |
|
| County | PARKER |
| Highway |
FM 1884 |
| From |
B.B. FIELDER ROAD |
| To |
TO END OF FM 1884 |
| CSJ |
1601-02-023 |
| Proj ID |
STP 2012(685) |
| Work Type |
GR, DRAINAGE, STRUCTURES, & PAVEMEN |
| |
|
6.305 |
6349600.35 |
84330.00 |
1370332.53 |
21.5 |
| Work Order |
11-01-12 |
| Work Began |
01-21-13 |
| Work Completed |
|
| Time Computed |
11-17-12 |
| Contract Working Days |
299 |
| Addl Days Granted |
0 |
| Working Days Charged |
62 |
| Percent Time Used |
20 |
| Contractor(s) |
| ED BELL CONSTRUCTION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1601-02-023 COWTOWN TRAFFIC CONTROL, INC.(0.23%) DUSTROL, INC.(0.30%) FORTSON CONTRACTING, INC.(1.36%) MCL CONTRACTING, LLC (0.11%) NORTHEASTERN PAVERS, INC.( 36.29%) SCOTT DERR PAINTING CO (0.04%) STRIPING TECHNOLOGY, L.P.(0.90%) SOUTHEAST GRINDING & GROOVING, LLC (0.04%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.33%) TEXAS SHAFTS, INC. (0.78%) USA EROSION, INC.(1.18%) INLET STRUCTURE SPECIALTIES LTD. (3.54%) BRENDA PRICE TRUCKING(1.23%)
|
| Contract # |
08123234 |
|
Totals |
6349600.35 |
84330.00 |
1370332.53 |
21.5 |
|
| County | TARRANT |
| Highway |
FM 1709 |
| From |
PEARSON LANE; WEST CITY LIMITS |
| To |
SH 114; EAST CITY LIMITS |
| CSJ |
1603-03-034 |
| Proj ID |
STP 2011(228)TE |
| Work Type |
GRADING, DRAINAGE, INSTALL SIDEWALKS |
| |
|
6.100 |
1320757.45 |
33172.20 |
307491.46 |
23.2 |
| Work Order |
12-03-12 |
| Work Began |
01-28-13 |
| Work Completed |
|
| Time Computed |
12-19-12 |
| Contract Working Days |
149 |
| Addl Days Granted |
0 |
| Working Days Charged |
64 |
| Percent Time Used |
42 |
| Contractor(s) |
| JAGOE-PUBLIC COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1603-03-034 ENVIRONMENTAL STANDARDS, INC.(3.97%) CONCRETE PAVER SYSTEMS, INC. (0.26%) CROSSROADS, L.P. (0.71%) HIGHWAY TECHNOLOGIES, INC. (0.52%) MIKE ALBERT, INC.( 30.01%)
|
| Contract # |
11123021 |
|
Totals |
1320757.45 |
33172.20 |
307491.46 |
23.2 |
|
| County | WISE |
| Highway |
FM 2123 |
| From |
AT SALT CREEK |
| To |
AND AT COTTONWOOD CREEK |
| CSJ |
1606-02-013 |
| Proj ID |
BR 1102(297) |
| Work Type |
REPL BRIDGES |
| |
|
0.099 |
1968338.24 |
235829.35 |
1848292.64 |
99.9 |
| Work Order |
09-14-11 |
| Work Began |
12-08-11 |
| Work Completed |
|
| Time Computed |
09-30-11 |
| Contract Working Days |
150 |
| Addl Days Granted |
0 |
| Working Days Charged |
376 |
| Percent Time Used |
250 |
| Contractor(s) |
| DOUGHTIE CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1606-02-013 COWTOWN TRAFFIC CONTROL, INC.(0.36%) BROCK ENVIRONMENTAL, LLC (0.39%) DUSTIN ALLEN, INC. (1.70%) GORRONDONA & ASSOCIATES, INC.(0.50%) HIGHWAY TECHNOLOGIES, INC. (1.28%) RG PAINTING(0.19%) TEXAS ALTERNATIVE GRASSER, INC.(0.20%) PRIMATE CONSTRUCTION, INC. (0.54%) TEX OP CONSTRUCTION, LP(0.78%) PEACHTREE CONSTRUCTION, LTD. (8.23%) EW WELLS GROUP LLC (2.13%) W. W. FOUNDATION DRILLING, LTD.(8.30%) J.L. STEEL REINFORCING, LLC(0.33%) ENVIRONMENTAL SAFETY SERVICES, INC.(8.95%) JUST GROOVING, LTD.(0.29%) JTM MATERIALS, INC.(0.17%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.42%) KYLE ERWIN CONSTRUCTION, LLC (0.13%)
|
| Contract # |
08113260 |
|
Totals |
1968338.24 |
235829.35 |
1848292.64 |
99.9 |
|
| County | WISE |
| Highway |
FM 2123 |
| From |
SH 114 |
| To |
C.R. 3355 |
| CSJ |
1606-02-018 |
| Proj ID |
STP 2012(736)HES |
| Work Type |
GRADING, BASE, DRAINAGE, STRUCTURE, PAV |
| |
|
12.330 |
4939000.01 |
594402.68 |
1729255.82 |
35.0 |
| Work Order |
12-03-12 |
| Work Began |
01-29-13 |
| Work Completed |
|
| Time Computed |
12-19-12 |
| Contract Working Days |
224 |
| Addl Days Granted |
0 |
| Working Days Charged |
69 |
| Percent Time Used |
30 |
| Contractor(s) |
| ED BELL CONSTRUCTION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1606-02-018 SIGNATURE CONTRACTING SERVICES, L.L.C. (2.47%) BUYERS BARRICADES, INC.(0.39%) W.S. CONSTRUCTION COMPANY( 13.29%) PEACHTREE CONSTRUCTION, LTD. ( 20.15%) HIGHWAY TECHNOLOGIES, INC. (2.13%) HJC FARMS, INC.(2.96%)
|
| Contract # |
11123224 |
|
Totals |
4939000.01 |
594402.68 |
1729255.82 |
35.0 |
|
| County | WISE |
| Highway |
FM 1655 |
| From |
AT BRUSHY AND SANDY CREEKS |
| To |
. |
| CSJ |
1751-01-017 |
| Proj ID |
BR 2007(274) |
| Work Type |
REPLACE BRIDGES |
| |
|
0.438 |
3479076.48 |
191.10 |
3442267.95 |
98.9 |
| Work Order |
07-19-11 |
| Work Began |
09-20-11 |
| Work Completed |
|
| Time Computed |
09-20-11 |
| Contract Working Days |
260 |
| Addl Days Granted |
12 |
| Working Days Charged |
272 |
| Percent Time Used |
100 |
| Contractor(s) |
| COPPELL CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1751-01-017 TEXAS SHAFTS, INC. (6.41%) HIGHWAY TECHNOLOGIES, INC. (0.26%) PEACHTREE CONSTRUCTION, LTD. (4.65%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.48%) JONA CONTRACTING, INC. (1.16%) TOTAL HIGHWAY MAINTENANCE, LLC (0.41%) DUSTROL, INC.(0.38%) CRAIG OLDEN, INC.(1.99%) SCOTT DERR PAINTING CO (0.73%) FORTSON CONTRACTING, INC.(0.84%) HOUSTON SAWING & DRILLING(0.22%)
|
| Contract # |
06113238 |
|
Totals |
3479076.48 |
191.10 |
3442267.95 |
98.9 |
|
| County | TARRANT |
| Highway |
FM 1938 |
| From |
0.2 MI S OF RANDOL MILL AVE. |
| To |
SH 114 |
| CSJ |
1978-01-048 |
| Proj ID |
STP 2009(880)MM |
| Work Type |
GR, BS, DR, STRUCTURES & PAVEMENT |
| |
|
2.205 |
15244573.52 |
10785.61 |
16770865.71 |
99.9 |
| Work Order |
12-03-09 |
| Work Began |
06-01-10 |
| Work Completed |
|
| Time Computed |
06-01-10 |
| Contract Working Days |
448 |
| Addl Days Granted |
44 |
| Working Days Charged |
637 |
| Percent Time Used |
129 |
| Contractor(s) |
| ED BELL CONSTRUCTION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1978-01-048 BREDA COMPANY, INC.(1.59%) HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, CORP. (1.40%) K & S UTILITY CONTRACTORS, INC.(7.15%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.03%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.86%) BROCK ENVIRONMENTAL, LLC (0.27%) BIG BIRD TREE SERVICE, INC.(0.42%) CRAIG OLDEN, INC.(1.86%) C.T. AND S. METALWORKS, INC. (1.13%) DUSTROL, INC. (ROANOKE)(0.36%) FORTSON CONTRACTING, INC.(0.27%) PAVER CONSTRUCTION COMPANY INC.(0.74%) PEACHTREE CONSTRUCTION, LTD. (8.58%) SCOTT DERR PAINTING CO, LLC(0.91%) SOUTHWEST CONSTRUCTION SERVICES(0.37%) TOTAL HIGHWAY MAINTENANCE, LLC (0.87%) LLANO RIVER FENCE(0.64%) WRIGHT CONSTRUCTION CO., INC.(0.31%) RICE TUNNELING & BORING, INC.(0.29%) JUSTIN FARMS (1.47%) HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, CORP. (0.00%) FELIX FRAYRE (0.03%)
|
| Contract # |
08093204 |
|
Totals |
15244573.52 |
10785.61 |
16770865.71 |
99.9 |
|
| County | TARRANT |
| Highway |
FM 1938 |
| From |
FM 1709 |
| To |
STANES/RUMFIELD |
| CSJ |
1978-01-053 |
| Proj ID |
STP 2013(458) |
| Work Type |
HMAC OVERLAY |
| |
|
3.942 |
2154441.29 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
86 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| NORTHEASTERN PAVERS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1978-01-053 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03133233 |
|
Totals |
2154441.29 |
0.00 |
0.00 |
0.0 |
|
| County | TARRANT |
| Highway |
FM 1938 |
| From |
SH 114 |
| To |
RANDOL MILL ROAD |
| CSJ |
1978-01-055 |
| Proj ID |
STP 2012(570) |
| Work Type |
LANDSCAPE ENHANCEMENT |
| |
|
2.205 |
856000.00 |
135840.93 |
554736.26 |
64.8 |
| Work Order |
07-12-12 |
| Work Began |
12-14-12 |
| Work Completed |
|
| Time Computed |
07-28-12 |
| Contract Working Days |
128 |
| Addl Days Granted |
0 |
| Working Days Charged |
96 |
| Percent Time Used |
75 |
| Contractor(s) |
| LEGENDS LANDSCAPES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 1978-01-055 HIGHWAY TECHNOLOGIES, INC. (0.36%)
|
| Contract # |
05123245 |
|
Totals |
856000.00 |
135840.93 |
554736.26 |
64.8 |
|
| County | TARRANT |
| Highway |
SP 303 |
| From |
WEST C/L (SHADY VALLEY DR) |
| To |
EAST C/L (W CORNERSTONE LN) |
| CSJ |
2208-01-063 |
| Proj ID |
NH 2013(289) |
| Work Type |
LANDSCAPE ENHANCEMENT |
| |
|
1.647 |
197430.50 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
81 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| GREY CONSTRUCTION |
SUBCONTRACTOR(S) FOR CCSJ: 2208-01-063 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05133037 |
|
Totals |
197430.50 |
0.00 |
0.00 |
0.0 |
|
| County | TARRANT |
| Highway |
SH 360 |
| From |
AT SH 180 (DIVISION STREET) |
| To |
AND UPRR; IN ARLINGTON |
| CSJ |
2266-02-127 |
| Proj ID |
NH 2007(806) |
| Work Type |
GR, STRS & PAVEMENT |
| |
|
0.854 |
55975100.62 |
0.00 |
57924856.13 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-07-08 |
| Work Began |
03-07-09 |
| Work Completed |
|
| Time Computed |
10-05-08 |
| Contract Working Days |
555 |
| Addl Days Granted |
75 |
| Working Days Charged |
1,044 |
| Percent Time Used |
165 |
| Contractor(s) |
| W.W. WEBBER, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 2266-02-127 COWTOWN TRAFFIC CONTROL, INC.(0.20%) EVANS ENVIRONMENTAL CONTRACTING, LLC.(0.43%) CAPROCK SPECIALITY CONTRACTORS (0.01%) CRAIG OLDEN, INC.(1.53%) FOUNDATION DRILLERS, INC.(1.00%) HAYWARD BAKER, INC.(1.52%) HIGHWAY TECHNOLOGIES, INC. (0.68%) MAGNUM TUNNELING, LLC(0.32%) MICA CORPORATION (3.87%) REYNOLDS ASPHALT & CONSTRUCTION COMPANY(7.49%) TEX OP CONSTRUCTION, LP(0.33%) DURABLE SPECIALTIES, INC.(0.67%) LAYFIELD CONSTRUCTION, INC (0.07%) BRENDA PRICE TRUCKING(4.11%) SCOTT DERR PAINTING CO (0.06%) INDUS CONSTRUCTION, L.P. (2.51%) GREAT WESTERN ERECTORS (0.05%) RAILWORKS TRACK SYSTEMS TEXAS, INC.( 11.20%) SOUTHWEST CONSTRUCTION SERVICES(0.11%) ERWIN STEEL WORKS, LLC (0.29%) MOBILE ENTERPRISES, INC. (0.39%) STOMPER DEMOLITION COMPANY, INC. (0.27%) RIVER CITIES SAWING LLC(0.01%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.41%) TOTAL HIGHWAY MAINTENANCE, LLC (0.00%)
|
| Contract # |
02083001 |
|
Totals |
55975100.62 |
0.00 |
57924856.13 |
99.9 |
|
| County | TARRANT |
| Highway |
IH 20 |
| From |
WEST END OF BU 287P BRIDGE |
| To |
FM 157 |
| CSJ |
2374-05-076 |
| Proj ID |
IM 0204(280) |
| Work Type |
REPAIR FAILURES, UTBHMWC AND STRIPE |
| |
|
6.874 |
4544378.72 |
548455.43 |
2668467.44 |
58.7 |
| Work Order |
10-18-11 |
| Work Began |
09-04-12 |
| Work Completed |
|
| Time Computed |
02-16-12 |
| Contract Working Days |
107 |
| Addl Days Granted |
17 |
| Working Days Charged |
85 |
| Percent Time Used |
68 |
| Contractor(s) |
| AUSTIN BRIDGE & ROAD, LP |
SUBCONTRACTOR(S) FOR CCSJ: 2374-05-076 BROCK ENVIRONMENTAL, LLC (0.47%) O. TREVINO CONSTRUCTION, LLC (4.81%) CHEROKEE SERVICES(9.33%) HIGHWAY TECHNOLOGIES, INC. (0.14%) TRP CONSTRUCTION GROUP, LLC( 11.33%) DUSTROL, INC.( 24.79%) HALL PAVING, INC.( 16.40%)
|
| Contract # |
09113225 |
|
Totals |
4544378.72 |
548455.43 |
2668467.44 |
58.7 |
|
| County | TARRANT |
| Highway |
IH 20 |
| From |
FM 157 |
| To |
DALLAS/TARRANT COUNTY LINE |
| CSJ |
2374-05-077 |
| Proj ID |
IM 0204(284) |
| Work Type |
RESURFACE ROADWAY |
| |
|
5.789 |
5345717.22 |
0.00 |
0.00 |
0.0 |
| Work Order |
10-18-12 |
| Work Began |
05-06-13 |
| Work Completed |
|
| Time Computed |
04-17-13 |
| Contract Working Days |
115 |
| Addl Days Granted |
0 |
| Working Days Charged |
7 |
| Percent Time Used |
6 |
| Contractor(s) |
| AUSTIN BRIDGE & ROAD, LP |
SUBCONTRACTOR(S) FOR CCSJ: 2374-05-077 BROCK ENVIRONMENTAL, LLC (0.10%) DUSTROL, INC.( 13.64%) HALL PAVING, INC.( 13.59%) HIGHWAY TECHNOLOGIES, INC. (0.10%) O. TREVINO CONSTRUCTION, LLC (4.49%) STRIPING TECHNOLOGY, L.P.(5.63%)
|
| Contract # |
09123042 |
|
Totals |
5345717.22 |
0.00 |
0.00 |
0.0 |
|