Monthly State Let Construction Report For Fort Worth District As Of May 15, 2013 Page 4 Of 5

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To IN TARRANT COUNTY
CSJ 0902-48-822
Proj ID NH 2012(353)
Work Type CONSTRUCT CURB RAMPS
 
0.001 3378473.70 165674.45 1615784.29 47.8
Work Order 06-08-12
Work Began 07-16-12
Work Completed  
Time Computed 06-24-12
Contract Working Days 283
Addl Days Granted 0
Working Days Charged 206
Percent Time Used 72
Contractor(s)
KEN-DO CONTRACTING, LP
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-822
ROAD MASTER STRIPING LLC (7.83%)
MEL"S ELECTRIC SERVICE, INC. ( 21.22%)
TEX OP CONSTRUCTION, LP(0.11%)
ALLIANCE TRUCKING(0.18%)
APAC-TEXAS, INC. (0.07%)
CHAPAS TRUCKING(0.11%)
Contract # 03123020
Totals 3378473.70 165674.45 1615784.29 47.8

CountyERATH
Highway VA
From VARIOUS LOCATIONS
To AROUND STEPHENVILLE
CSJ 0902-49-066
Proj ID STP 2012(569)
Work Type LANDSCAPE ENHANCEMENT
 
0.282 379628.18 0.00 232655.20 61.2
Work Order 06-18-12
Work Began 10-01-12
Work Completed  
Time Computed 07-04-12
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 87
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0902-49-066
MEMCO(6.42%)
LONE OAK LANDSCAPE LLC ( 50.03%)
Contract # 05123017
Totals 379628.18 0.00 232655.20 61.2

CountyTARRANT
Highway IH 30
From PARKER/TARRANT COUNTY LINE
To LINKCREST
CSJ 1068-01-201
Proj ID IM 0304(096)
Work Type HMAC OVERLAY
 
2.066 1479637.07 96711.46 96711.46 6.5
Work Order 10-18-12
Work Began 04-24-13
Work Completed  
Time Computed 04-17-13
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 4
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1068-01-201
SCR CONSTRUCTION CO., INC. (9.05%)
CROSSROADS, L.P. (0.43%)
STRIPING TECHNOLOGY, L.P.(4.07%)
DUSTROL, INC.( 13.19%)
PENHALL COMPANY(0.10%)
Contract # 09123243
Totals 1479637.07 96711.46 96711.46 6.5

CountyPARKER
Highway IH 30
From IH 20, AT WALSH RANCH PARKWAY
To TARRANT COUNTY LINE
CSJ 1068-05-009
Proj ID IM 0304(092)
Work Type GRADING, DRAINAGE, STRUCTURE & PAVE
 
1.541 14593117.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1068-05-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133201
Totals 14593117.40 0.00 0.00 0.0

CountyTARRANT
Highway FM 1187
From NEWT PATTERSON
To BU 287P
CSJ 1330-02-034
Proj ID STP 2010(399)ES
Work Type GRADING, DRAINAGE, STRUCTURES & PAV
 
1.503 6895052.12 162915.88 4798371.77 69.5
Work Order 05-05-10
Work Began 06-17-11
Work Completed  
Time Computed 11-01-10
Contract Working Days 427
Addl Days Granted 0
Working Days Charged 425
Percent Time Used 99
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1330-02-034
UNDERGROUND COALITION, INC.(2.92%)
INLET STRUCTURE SPECIALTIES LTD. (2.88%)
DURABLE SPECIALTIES, INC.(2.04%)
BANDA TRUCKING COMPANY (0.10%)
STORM WATER MANAGEMENT, INC. (0.31%)
INDUS CONSTRUCTION, L.P. (8.05%)
AUSTIN BRIDGE & ROAD, LP ( 17.43%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.34%)
DUSTROL, INC.(0.53%)
JM MATERIALS, INC. (0.32%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.83%)
Contract # 03103004
Totals 6895052.12 162915.88 4798371.77 69.5

CountyTARRANT
Highway FM 1187
From 0.5 MILE EAST OF IH 35W
To EAST OF OAK GROVE S (EAST INTER)
CSJ 1330-02-041
Proj ID NH 1102(093)
Work Type GR, DR, STRUC, AND PAVING
 
1.425 3679267.90 39318.50 2960873.02 80.9
Work Order 08-19-11
Work Began 02-14-12
Work Completed  
Time Computed 09-04-11
Contract Working Days 256
Addl Days Granted 14
Working Days Charged 291
Percent Time Used 107
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1330-02-041
TEX OP CONSTRUCTION, LP(0.59%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.60%)
NORTH TEXAS CONTRACTING, INC.(4.52%)
FORTSON CONTRACTING, INC.(1.95%)
HIGHWAY TECHNOLOGIES, INC. (3.18%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(7.59%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(1.21%)
PEACHTREE CONSTRUCTION, LTD. (1.16%)
FOUNDATION DRILLERS, INC.(0.23%)
Contract # 06113235
Totals 3679267.90 39318.50 2960873.02 80.9

CountyTARRANT
Highway FM 1187
From AT BF 1187C (E. MAIN ST)
To IN CROWLEY
CSJ 1330-03-002
Proj ID CC 1330-3-2
Work Type TRAFFIC SIGNAL
 
0.100 129000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-03-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1330-03-002
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12123211
Totals 129000.00 0.00 0.00 0.0

CountyPARKER
Highway FM 730
From AT LAKE WEATHERFORD
To .
CSJ 1601-01-018
Proj ID BR 2006(503)
Work Type REPLACE BRIDGE
 
0.677 2502493.61 0.00 2425501.55 96.9
Work Order 09-14-11
Work Began 10-07-11
Work Completed  
Time Computed 09-30-11
Contract Working Days 256
Addl Days Granted 0
Working Days Charged 256
Percent Time Used 100
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1601-01-018
COPPELL CONSTRUCTION CO., INC. ( 38.35%)
TEXAS SHAFTS, INC. (3.46%)
TEXAS ALTERNATIVE GRASSER, INC.(0.40%)
FORTSON CONTRACTING, INC.(1.04%)
NORTHEASTERN PAVERS, INC.( 17.00%)
STRIPING TECHNOLOGY, L.P.(1.21%)
HOUSTON SAWING & DRILLING(0.11%)
RG PAINTING(0.39%)
Contract # 08113258
Totals 2502493.61 0.00 2425501.55 96.9

CountyPARKER
Highway FM 1884
From B.B. FIELDER ROAD
To TO END OF FM 1884
CSJ 1601-02-023
Proj ID STP 2012(685)
Work Type GR, DRAINAGE, STRUCTURES, & PAVEMEN
 
6.305 6349600.35 84330.00 1370332.53 21.5
Work Order 11-01-12
Work Began 01-21-13
Work Completed  
Time Computed 11-17-12
Contract Working Days 299
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 20
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1601-02-023
COWTOWN TRAFFIC CONTROL, INC.(0.23%)
DUSTROL, INC.(0.30%)
FORTSON CONTRACTING, INC.(1.36%)
MCL CONTRACTING, LLC (0.11%)
NORTHEASTERN PAVERS, INC.( 36.29%)
SCOTT DERR PAINTING CO (0.04%)
STRIPING TECHNOLOGY, L.P.(0.90%)
SOUTHEAST GRINDING & GROOVING, LLC (0.04%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.33%)
TEXAS SHAFTS, INC. (0.78%)
USA EROSION, INC.(1.18%)
INLET STRUCTURE SPECIALTIES LTD. (3.54%)
BRENDA PRICE TRUCKING(1.23%)
Contract # 08123234
Totals 6349600.35 84330.00 1370332.53 21.5

CountyTARRANT
Highway FM 1709
From PEARSON LANE; WEST CITY LIMITS
To SH 114; EAST CITY LIMITS
CSJ 1603-03-034
Proj ID STP 2011(228)TE
Work Type GRADING, DRAINAGE, INSTALL SIDEWALKS
 
6.100 1320757.45 33172.20 307491.46 23.2
Work Order 12-03-12
Work Began 01-28-13
Work Completed  
Time Computed 12-19-12
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 42
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1603-03-034
ENVIRONMENTAL STANDARDS, INC.(3.97%)
CONCRETE PAVER SYSTEMS, INC. (0.26%)
CROSSROADS, L.P. (0.71%)
HIGHWAY TECHNOLOGIES, INC. (0.52%)
MIKE ALBERT, INC.( 30.01%)
Contract # 11123021
Totals 1320757.45 33172.20 307491.46 23.2

CountyWISE
Highway FM 2123
From AT SALT CREEK
To AND AT COTTONWOOD CREEK
CSJ 1606-02-013
Proj ID BR 1102(297)
Work Type REPL BRIDGES
 
0.099 1968338.24 235829.35 1848292.64 99.9
Work Order 09-14-11
Work Began 12-08-11
Work Completed  
Time Computed 09-30-11
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 376
Percent Time Used 250
Contractor(s)
DOUGHTIE CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1606-02-013
COWTOWN TRAFFIC CONTROL, INC.(0.36%)
BROCK ENVIRONMENTAL, LLC (0.39%)
DUSTIN ALLEN, INC. (1.70%)
GORRONDONA & ASSOCIATES, INC.(0.50%)
HIGHWAY TECHNOLOGIES, INC. (1.28%)
RG PAINTING(0.19%)
TEXAS ALTERNATIVE GRASSER, INC.(0.20%)
PRIMATE CONSTRUCTION, INC. (0.54%)
TEX OP CONSTRUCTION, LP(0.78%)
PEACHTREE CONSTRUCTION, LTD. (8.23%)
EW WELLS GROUP LLC (2.13%)
W. W. FOUNDATION DRILLING, LTD.(8.30%)
J.L. STEEL REINFORCING, LLC(0.33%)
ENVIRONMENTAL SAFETY SERVICES, INC.(8.95%)
JUST GROOVING, LTD.(0.29%)
JTM MATERIALS, INC.(0.17%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.42%)
KYLE ERWIN CONSTRUCTION, LLC (0.13%)
Contract # 08113260
Totals 1968338.24 235829.35 1848292.64 99.9

CountyWISE
Highway FM 2123
From SH 114
To C.R. 3355
CSJ 1606-02-018
Proj ID STP 2012(736)HES
Work Type GRADING, BASE, DRAINAGE, STRUCTURE, PAV
 
12.330 4939000.01 594402.68 1729255.82 35.0
Work Order 12-03-12
Work Began 01-29-13
Work Completed  
Time Computed 12-19-12
Contract Working Days 224
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 30
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1606-02-018
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.47%)
BUYERS BARRICADES, INC.(0.39%)
W.S. CONSTRUCTION COMPANY( 13.29%)
PEACHTREE CONSTRUCTION, LTD. ( 20.15%)
HIGHWAY TECHNOLOGIES, INC. (2.13%)
HJC FARMS, INC.(2.96%)
Contract # 11123224
Totals 4939000.01 594402.68 1729255.82 35.0

CountyWISE
Highway FM 1655
From AT BRUSHY AND SANDY CREEKS
To .
CSJ 1751-01-017
Proj ID BR 2007(274)
Work Type REPLACE BRIDGES
 
0.438 3479076.48 191.10 3442267.95 98.9
Work Order 07-19-11
Work Began 09-20-11
Work Completed  
Time Computed 09-20-11
Contract Working Days 260
Addl Days Granted 12
Working Days Charged 272
Percent Time Used 100
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1751-01-017
TEXAS SHAFTS, INC. (6.41%)
HIGHWAY TECHNOLOGIES, INC. (0.26%)
PEACHTREE CONSTRUCTION, LTD. (4.65%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.48%)
JONA CONTRACTING, INC. (1.16%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.41%)
DUSTROL, INC.(0.38%)
CRAIG OLDEN, INC.(1.99%)
SCOTT DERR PAINTING CO (0.73%)
FORTSON CONTRACTING, INC.(0.84%)
HOUSTON SAWING & DRILLING(0.22%)
Contract # 06113238
Totals 3479076.48 191.10 3442267.95 98.9

CountyTARRANT
Highway FM 1938
From 0.2 MI S OF RANDOL MILL AVE.
To SH 114
CSJ 1978-01-048
Proj ID STP 2009(880)MM
Work Type GR, BS, DR, STRUCTURES & PAVEMENT
 
2.205 15244573.52 10785.61 16770865.71 99.9
Work Order 12-03-09
Work Began 06-01-10
Work Completed  
Time Computed 06-01-10
Contract Working Days 448
Addl Days Granted 44
Working Days Charged 637
Percent Time Used 129
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1978-01-048
BREDA COMPANY, INC.(1.59%)
HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, CORP. (1.40%)
K & S UTILITY CONTRACTORS, INC.(7.15%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.03%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.86%)
BROCK ENVIRONMENTAL, LLC (0.27%)
BIG BIRD TREE SERVICE, INC.(0.42%)
CRAIG OLDEN, INC.(1.86%)
C.T. AND S. METALWORKS, INC. (1.13%)
DUSTROL, INC. (ROANOKE)(0.36%)
FORTSON CONTRACTING, INC.(0.27%)
PAVER CONSTRUCTION COMPANY INC.(0.74%)
PEACHTREE CONSTRUCTION, LTD. (8.58%)
SCOTT DERR PAINTING CO, LLC(0.91%)
SOUTHWEST CONSTRUCTION SERVICES(0.37%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.87%)
LLANO RIVER FENCE(0.64%)
WRIGHT CONSTRUCTION CO., INC.(0.31%)
RICE TUNNELING & BORING, INC.(0.29%)
JUSTIN FARMS (1.47%)
HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, CORP. (0.00%)
FELIX FRAYRE (0.03%)
Contract # 08093204
Totals 15244573.52 10785.61 16770865.71 99.9

CountyTARRANT
Highway FM 1938
From FM 1709
To STANES/RUMFIELD
CSJ 1978-01-053
Proj ID STP 2013(458)
Work Type HMAC OVERLAY
 
3.942 2154441.29 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1978-01-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133233
Totals 2154441.29 0.00 0.00 0.0

CountyTARRANT
Highway FM 1938
From SH 114
To RANDOL MILL ROAD
CSJ 1978-01-055
Proj ID STP 2012(570)
Work Type LANDSCAPE ENHANCEMENT
 
2.205 856000.00 135840.93 554736.26 64.8
Work Order 07-12-12
Work Began 12-14-12
Work Completed  
Time Computed 07-28-12
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 96
Percent Time Used 75
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 1978-01-055
HIGHWAY TECHNOLOGIES, INC. (0.36%)
Contract # 05123245
Totals 856000.00 135840.93 554736.26 64.8

CountyTARRANT
Highway SP 303
From WEST C/L (SHADY VALLEY DR)
To EAST C/L (W CORNERSTONE LN)
CSJ 2208-01-063
Proj ID NH 2013(289)
Work Type LANDSCAPE ENHANCEMENT
 
1.647 197430.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 81
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GREY CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 2208-01-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133037
Totals 197430.50 0.00 0.00 0.0

CountyTARRANT
Highway SH 360
From AT SH 180 (DIVISION STREET)
To AND UPRR; IN ARLINGTON
CSJ 2266-02-127
Proj ID NH 2007(806)
Work Type GR, STRS & PAVEMENT
 
0.854 55975100.62 0.00 57924856.13 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-07-08
Work Began 03-07-09
Work Completed  
Time Computed 10-05-08
Contract Working Days 555
Addl Days Granted 75
Working Days Charged 1,044
Percent Time Used 165
Contractor(s)
W.W. WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2266-02-127
COWTOWN TRAFFIC CONTROL, INC.(0.20%)
EVANS ENVIRONMENTAL CONTRACTING, LLC.(0.43%)
CAPROCK SPECIALITY CONTRACTORS (0.01%)
CRAIG OLDEN, INC.(1.53%)
FOUNDATION DRILLERS, INC.(1.00%)
HAYWARD BAKER, INC.(1.52%)
HIGHWAY TECHNOLOGIES, INC. (0.68%)
MAGNUM TUNNELING, LLC(0.32%)
MICA CORPORATION (3.87%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(7.49%)
TEX OP CONSTRUCTION, LP(0.33%)
DURABLE SPECIALTIES, INC.(0.67%)
LAYFIELD CONSTRUCTION, INC (0.07%)
BRENDA PRICE TRUCKING(4.11%)
SCOTT DERR PAINTING CO (0.06%)
INDUS CONSTRUCTION, L.P. (2.51%)
GREAT WESTERN ERECTORS (0.05%)
RAILWORKS TRACK SYSTEMS TEXAS, INC.( 11.20%)
SOUTHWEST CONSTRUCTION SERVICES(0.11%)
ERWIN STEEL WORKS, LLC (0.29%)
MOBILE ENTERPRISES, INC. (0.39%)
STOMPER DEMOLITION COMPANY, INC. (0.27%)
RIVER CITIES SAWING LLC(0.01%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.41%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.00%)
Contract # 02083001
Totals 55975100.62 0.00 57924856.13 99.9

CountyTARRANT
Highway IH 20
From WEST END OF BU 287P BRIDGE
To FM 157
CSJ 2374-05-076
Proj ID IM 0204(280)
Work Type REPAIR FAILURES, UTBHMWC AND STRIPE
 
6.874 4544378.72 548455.43 2668467.44 58.7
Work Order 10-18-11
Work Began 09-04-12
Work Completed  
Time Computed 02-16-12
Contract Working Days 107
Addl Days Granted 17
Working Days Charged 85
Percent Time Used 68
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 2374-05-076
BROCK ENVIRONMENTAL, LLC (0.47%)
O. TREVINO CONSTRUCTION, LLC (4.81%)
CHEROKEE SERVICES(9.33%)
HIGHWAY TECHNOLOGIES, INC. (0.14%)
TRP CONSTRUCTION GROUP, LLC( 11.33%)
DUSTROL, INC.( 24.79%)
HALL PAVING, INC.( 16.40%)
Contract # 09113225
Totals 4544378.72 548455.43 2668467.44 58.7

CountyTARRANT
Highway IH 20
From FM 157
To DALLAS/TARRANT COUNTY LINE
CSJ 2374-05-077
Proj ID IM 0204(284)
Work Type RESURFACE ROADWAY
 
5.789 5345717.22 0.00 0.00 0.0
Work Order 10-18-12
Work Began 05-06-13
Work Completed  
Time Computed 04-17-13
Contract Working Days 115
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 6
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 2374-05-077
BROCK ENVIRONMENTAL, LLC (0.10%)
DUSTROL, INC.( 13.64%)
HALL PAVING, INC.( 13.59%)
HIGHWAY TECHNOLOGIES, INC. (0.10%)
O. TREVINO CONSTRUCTION, LLC (4.49%)
STRIPING TECHNOLOGY, L.P.(5.63%)
Contract # 09123042
Totals 5345717.22 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5