Monthly State Let Construction Report For Fort Worth District As Of Feb 10, 2017 Page 5 Of 5

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyPARKER
HighwayFM 3028
FromFM 3028 AT ROCKY CREEK
To.
CSJ2930-02-011
Proj IDBR 1502(336)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1001561559.711564221.9099.9
Work Order08-13-15
Work Began09-22-15
Work Completed
Time Computed09-12-15
Contract Working Days130
Addl Days Granted32
Working Days Charged207
Percent Time Used127
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2930-02-011
WOLFE CONSTRUCTION GROUP, INC. (0.47)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.95)
STORM WATER MANAGEMENT, INC. (0.55)
ALTUS TRAFFIC MANAGEMENT LLC (0.37)
PEACHTREE CONSTRUCTION, LTD. (3.78)
FORTSON CONTRACTING, INC. (2.02)
TEXOP CONSTRUCTION (0.47)
STRIPING TECHNOLOGY, L.P. (0.47)
Contract #06153053
Totals1561559.710.001564221.9099.9

CountyJOHNSON
HighwayFM 2738
FromTARRANT C/L
To0.909 MI N OF FM 917
CSJ3010-02-014
Proj IDSTP 1502(548)HES
Work TypeYR, BS, DR, STR, & PAVT
 
4.4053409657.16275123.508.0
Work Order11-16-16
Work Began01-19-17
Work Completed
Time Computed12-17-16
Contract Working Days218
Addl Days Granted0
Working Days Charged14
Percent Time Used6
Contractor(s)
BRETT CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3010-02-014
LUZ LERMA CONSTRUCTION, INC. (11.57)
D.I.J. CONSTRUCTION, INC (1.25)
Contract #08163032
Totals3409657.16275123.50275123.508.0

CountyJOHNSON
HighwayFM 3136
From5.213 MILES EAST OF FM 4
To10.343 MILES EAST OF FM 4
CSJ3348-01-019
Proj IDSTP 1502(549)HES
Work TypeGR, BS, DR, STR, & PAVT
 
5.1926829235.172177343.3431.8
Work Order03-28-16
Work Began07-11-16
Work Completed
Time Computed04-28-16
Contract Working Days384
Addl Days Granted0
Working Days Charged129
Percent Time Used33
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3348-01-019
DUSTROL, INC. (0.12)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.53)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.11)
TOTAL HIGHWAY MAINTENANCE, LLC (3.70)
TEXAS SHAFTS, INC. (0.64)
SYNERGY SIGNS & SERVICES, LLC (0.70)
SOUTHEAST GRINDING & GROOVING, LLC (0.05)
OSCAR ORDUNO, INC. (2.21)
NORTHEASTERN PAVERS, INC. (27.61)
FORTSON CONTRACTING, INC. (0.78)
MCL CONTRACTING, LLC (0.14)
CROSSROADS, L.P. (0.76)
Contract #01163018
Totals6829235.17169177.312177343.3431.8

CountyPARKER
HighwayFM 3325
FromIH 20
ToFM 1886
CSJ3516-01-015
Proj IDSTP 2013(675)
Work TypeGR,BS, DR, STRUC AND PAVEMENT
 
7.1603283284.203444533.3999.9
Work Order01-06-14
Work Began01-28-14
Work Completed
Time Computed01-22-14
Contract Working Days256
Addl Days Granted125
Working Days Charged381
Percent Time Used100
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 3516-01-015
RAMBO CONTRACTING, INC. (1.36)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED (0.40)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.29)
NORTHEASTERN PAVERS, INC. (37.58)
STRIPING TECHNOLOGY, L.P. (1.71)
JM MATERIALS, INC. (2.37)
TEXAS ALTERNATIVE GRASSER, INC. (0.71)
ODUM SERVICES, L.P. (0.87)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.91)
Contract #08133054
Totals3283284.20162377.863444533.3999.9