Monthly State Let Construction Report For Fort Worth District As Of Aug 12, 2014 Page 5 Of 6

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWISE
Highway FM 920
From TRINITY RIVER
To 3.174 MI N OF SH 199
CSJ 1179-01-039
Proj ID STP 2013(900)
Work Type GR, BS AND PAVEMENT
 
12.795 5559330.74 459938.57 3029481.89 54.4
Work Order 11-14-13
Work Began 02-14-14
Work Completed  
Time Computed 11-30-13
Contract Working Days 205
Addl Days Granted 0
Working Days Charged 136
Percent Time Used 66
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1179-01-039
FORTSON CONTRACTING, INC.(0.88%)
NORTHEASTERN PAVERS, INC.( 15.58%)
CROSSROADS, L.P. (0.97%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (4.82%)
STRIPING TECHNOLOGY, L.P.(2.57%)
BRENDA PRICE TRUCKING(0.00%)
J.V. CONCRETE CONSTRUCTION ( 12.23%)
Contract # 08133251
Totals 5559330.74 459938.57 3029481.89 54.4

CountyJOHNSON
Highway FM 917
From SH 171 IN GODLEY
To SH 174 IN JOSHUA
CSJ 1181-02-035
Proj ID STP 2014(394)
Work Type HMAC OVERLAY
 
8.950 2080434.45 0.00 0.00 0.0
Work Order 04-11-14
Work Began 00-00-00
Work Completed  
Time Computed 04-27-14
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 13
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1181-02-035
ALTUS TRAFFIC MANAGEMENT LLC (0.30%)
VANN/ELLI, INC.(7.79%)
STRIPING TECHNOLOGY, L.P.(3.33%)
Contract # 02143214
Totals 2080434.45 0.00 0.00 0.0

CountyJOHNSON
Highway FM 2738
From FM-2738 IN LILIAN
To FM-917
CSJ 1181-04-043
Proj ID STP 2014(940)
Work Type SEAL COAT AND OVERLAY
 
0.761 186503.99 0.00 0.00 0.0
CountyJOHNSON
Highway FM 2738
From TARRANT COUNTY LINE
To FM-2738 IN LILLIAN
CSJ 3010-02-013
Proj ID STP 2014(940)
Work Type SEAL COAT AND OVERLAY
 
4.435 1570885.22 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3010-02-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143249
Totals 1757389.21 0.00 0.00 0.0

CountyJACK
Highway FM 1156
From FM 1156 OVER BEANS CREEK
To .
CSJ 1309-01-029
Proj ID BR 2014(771)
Work Type REPL BRIDGE AND APPROACHES
 
0.174 930482.24 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 171
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1309-01-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143022
Totals 930482.24 0.00 0.00 0.0

CountyTARRANT
Highway FM 1187
From NEWT PATTERSON
To BU 287P
CSJ 1330-02-034
Proj ID STP 2010(399)ES
Work Type GRADING, DRAINAGE, STRUCTURES & PAV
 
1.503 6895052.12 197759.29 12644207.18 99.9
Work Order 05-05-10
Work Began 06-17-11
Work Completed  
Time Computed 11-01-10
Contract Working Days 427
Addl Days Granted 325
Working Days Charged 733
Percent Time Used 97
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1330-02-034
UNDERGROUND COALITION, INC.(2.92%)
INLET STRUCTURE SPECIALTIES LTD. (2.88%)
DURABLE SPECIALTIES, INC.(2.04%)
BANDA TRUCKING COMPANY (0.10%)
STORM WATER MANAGEMENT, INC. (0.31%)
INDUS CONSTRUCTION, L.P. (8.05%)
AUSTIN BRIDGE & ROAD, LP ( 16.96%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.34%)
DUSTROL, INC.(0.53%)
JM MATERIALS, INC. (0.32%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.83%)
Contract # 03103004
Totals 6895052.12 197759.29 12644207.18 99.9

CountyJACK
Highway FM 1191
From US 380
To YOUNG COUNTY LINE
CSJ 1333-03-018
Proj ID STP 2014(664)HRR
Work Type GRADING, BASE, DRAINAGE, STRUCTURE, PAV
 
6.980 5404940.22 0.00 0.00 0.0
Work Order 06-18-14
Work Began 00-00-00
Work Completed  
Time Computed 07-04-14
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1333-03-018
EROSION CONTROL MANAGEMENT SERVICES(1.96%)
NORTH EASTERN PAVERS ( 34.25%)
Contract # 05143217
Totals 5404940.22 0.00 0.00 0.0

CountyPARKER
Highway FM 1189
From YOUNG BEND ROAD
To HOOD COUNTY LINE
CSJ 1468-01-024
Proj ID STP 1402(036)
Work Type GR, STR, FLX BS, SC, MBGF, SIGN, PVT MK
 
9.058 6481549.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 253
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1468-01-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143043
Totals 6481549.55 0.00 0.00 0.0

CountyHOOD
Highway FM 167
From FM-51
To FM-3450
CSJ 1598-01-020
Proj ID STP 2014(976)
Work Type GR, BS, DR STRUCTURE & HMAC PAVEMENT
 
2.928 2079661.57 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 61
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1598-01-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143056
Totals 2079661.57 0.00 0.00 0.0

CountyJOHNSON
Highway FM 916
From SH 171
To FM 4
CSJ 1599-02-014
Proj ID STP 1402(037)HES
Work Type GRADING, BASE AND PAVEMENT
 
6.416 3742567.71 0.00 0.00 0.0
CountyJOHNSON
Highway FM 916
From SH 171
To FM 4
CSJ 1599-02-015
Proj ID STP 1402(038)
Work Type GR, BS AND PAVEMENT
 
6.426 3182565.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 201
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1599-02-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143036
Totals 6925133.46 0.00 0.00 0.0

CountyPARKER
Highway FM 1884
From B.B. FIELDER ROAD
To TO END OF FM 1884
CSJ 1601-02-023
Proj ID STP 2012(685)
Work Type GR, DRAINAGE, STRUCTURES, & PAVEMEN
 
6.305 6349600.35 49462.27 6351110.61 99.9
Work Order 11-01-12
Work Began 01-21-13
Work Completed  
Time Computed 11-17-12
Contract Working Days 299
Addl Days Granted 15
Working Days Charged 312
Percent Time Used 99
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1601-02-023
COWTOWN TRAFFIC CONTROL, INC.(0.23%)
DUSTROL, INC.(0.30%)
FORTSON CONTRACTING, INC.(1.36%)
MCL CONTRACTING, LLC (0.11%)
NORTHEASTERN PAVERS, INC.( 36.29%)
SCOTT DERR PAINTING CO (0.04%)
STRIPING TECHNOLOGY, L.P.(0.90%)
SOUTHEAST GRINDING & GROOVING, LLC (0.04%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.33%)
TEXAS SHAFTS, INC. (0.78%)
USA EROSION, INC.(1.18%)
INLET STRUCTURE SPECIALTIES LTD. (3.54%)
BRENDA PRICE TRUCKING(1.23%)
Contract # 08123234
Totals 6349600.35 49462.27 6351110.61 99.9

CountyTARRANT
Highway FM 1709
From UP RAILROAD, WEST OF US 377
To ELM STREET; IN KELLER
CSJ 1603-03-033
Proj ID CM 2011(928)
Work Type GR, DR, STRUCT AND PAVEMENT
 
0.226 879231.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1603-03-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01143210
Totals 879231.70 0.00 0.00 0.0

CountyTARRANT
Highway FM 1709
From PEARSON LANE; WEST CITY LIMITS
To SH 114; EAST CITY LIMITS
CSJ 1603-03-034
Proj ID STP 2011(228)TE
Work Type GRADING, DRAINAGE, INSTALL SIDEWALKS
 
6.100 1320757.45 0.00 1446798.88 99.9
Work Order 12-03-12
Work Began 01-28-13
Work Completed  
Time Computed 12-19-12
Contract Working Days 149
Addl Days Granted 46
Working Days Charged 198
Percent Time Used 101
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1603-03-034
ENVIRONMENTAL STANDARDS, INC.(3.97%)
CONCRETE PAVER SYSTEMS, INC. (0.26%)
CROSSROADS, L.P. (0.71%)
HIGHWAY TECHNOLOGIES, INC. (0.52%)
MIKE ALBERT, INC.( 34.12%)
WOODLAKE OUTDOOR, INC. (2.37%)
BUYERS BARRICADES, INC.(0.28%)
BUZZ SERVICES, L.L.C.(3.76%)
Contract # 11123021
Totals 1320757.45 0.00 1446798.88 99.9

CountyPARKER
Highway FM 1886
From FM 730
To TARRANT COUNTY LINE
CSJ 1605-01-014
Proj ID STP 2014(478)
Work Type GR.BS, DR, STRUC AND PAVEMENT
 
5.748 4834822.79 262290.76 280251.96 5.7
Work Order 05-07-14
Work Began 06-12-14
Work Completed  
Time Computed 05-23-14
Contract Working Days 256
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 10
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1605-01-014
RAMBO CONTRACTING, INC.(4.85%)
BICK"S CONSTRUCTION, INC.( 16.34%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.93%)
MARCOM"S MOWING SERVICE, LLC (0.53%)
WEST TEXAS RUMBLE STRIP(0.08%)
AAA DRILLING FOUNDATION CO., INC.(0.36%)
LIRA ELECTRIC(1.57%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.81%)
Contract # 03143221
Totals 4834822.79 262290.76 280251.96 5.7

CountyWISE
Highway FM 2123
From AT SALT CREEK
To AND AT COTTONWOOD CREEK
CSJ 1606-02-013
Proj ID BR 1102(297)
Work Type REPL BRIDGES
 
0.099 1968338.24 0.00 1872436.82 99.9
Work Order 09-14-11
Work Began 12-08-11
Work Completed  
Time Computed 09-30-11
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 380
Percent Time Used 253
Contractor(s)
DOUGHTIE CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1606-02-013
COWTOWN TRAFFIC CONTROL, INC.(0.36%)
BROCK ENVIRONMENTAL, LLC (0.39%)
DUSTIN ALLEN, INC. (1.70%)
GORRONDONA & ASSOCIATES, INC.(0.50%)
HIGHWAY TECHNOLOGIES, INC. (1.28%)
RG PAINTING(0.19%)
TEXAS ALTERNATIVE GRASSER, INC.(0.20%)
PRIMATE CONSTRUCTION, INC. (0.54%)
TEX OP CONSTRUCTION, LP(0.78%)
PEACHTREE CONSTRUCTION, LTD. (8.23%)
EW WELLS GROUP LLC (2.13%)
W. W. FOUNDATION DRILLING, LTD.(8.30%)
J.L. STEEL REINFORCING, LLC(0.33%)
ENVIRONMENTAL SAFETY SERVICES, INC.(8.95%)
JUST GROOVING, LTD.(0.29%)
JTM MATERIALS, INC.(0.17%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.42%)
KYLE ERWIN CONSTRUCTION, LLC (0.13%)
Contract # 08113260
Totals 1968338.24 0.00 1872436.82 99.9

CountyWISE
Highway FM 2123
From SH 114
To C.R. 3355
CSJ 1606-02-018
Proj ID STP 2012(736)HES
Work Type GRADING, BASE, DRAINAGE, STRUCTURE, PAV
 
12.330 4939000.01 -15835.46 4513045.68 91.3
Work Order 12-03-12
Work Began 01-29-13
Work Completed  
Time Computed 12-19-12
Contract Working Days 224
Addl Days Granted 10
Working Days Charged 197
Percent Time Used 84
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1606-02-018
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.47%)
BUYERS BARRICADES, INC.(0.39%)
W.S. CONSTRUCTION COMPANY( 13.29%)
PEACHTREE CONSTRUCTION, LTD. ( 20.15%)
HIGHWAY TECHNOLOGIES, INC. (2.13%)
HJC FARMS, INC.(2.96%)
STRIPING TECHNOLOGY, L.P.(2.21%)
W.O.E. CONSTRUCTION(0.03%)
Contract # 11123224
Totals 4939000.01 15835.46 4513045.68 91.3

CountyTARRANT
Highway FM 1938
From 0.2 MILE SOUTH OF FM 1709
To RANDOL MILL RD/WESTLAKE C/L
CSJ 1978-01-050
Proj ID STP 1402(039)MM
Work Type GR, BS, DR, STRUCTURES & PAVEMENT
 
1.743 20575236.87 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 554
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 1978-01-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143005
Totals 20575236.87 0.00 0.00 0.0

CountyTARRANT
Highway FM 1938
From SH 114
To RANDOL MILL ROAD
CSJ 1978-01-055
Proj ID STP 2012(570)
Work Type LANDSCAPE ENHANCEMENT
 
2.205 856000.00 0.00 856832.28 99.9
Work Order 07-12-12
Work Began 12-14-12
Work Completed  
Time Computed 07-28-12
Contract Working Days 128
Addl Days Granted 50
Working Days Charged 178
Percent Time Used 100
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 1978-01-055
HIGHWAY TECHNOLOGIES, INC. (0.36%)
Contract # 05123245
Totals 856000.00 0.00 856832.28 99.9

CountyTARRANT
Highway FM 1220
From EAGLE MOUNTAIN ELEM SCHOOL
To 1,100 FT. NORTH OF BAILEY BOSWELL
CSJ 2079-01-041
Proj ID STP 2013(901)
Work Type GRADING, BASE AND PAVEMENT
 
2.879 5878132.94 6850.00 6850.00 0.1
Work Order 12-10-13
Work Began 00-00-00
Work Completed  
Time Computed 06-09-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2079-01-041
BRENDA PRICE TRUCKING(0.72%)
DALLAS LITE AND BARRICADE INC. (0.31%)
FARR FOUNDATION, INC.(1.36%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(0.46%)
LAYFIELD CONSTRUCTION, INC (4.47%)
J. E. GUZMAN CONSTRUCTION, INC.(5.59%)
TEX OP CONSTRUCTION, LP(2.07%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.13%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.43%)
W.O.E. CONSTRUCTION(4.76%)
NORTH TEXAS CONTRACTING, INC.( 14.65%)
STRIPING TECHNOLOGY, L.P.(1.26%)
Contract # 08133064
Totals 5878132.94 6850.00 6850.00 0.1

CountyTARRANT
Highway SP 303
From WEST C/L (SHADY VALLEY DR)
To EAST C/L (W CORNERSTONE LN)
CSJ 2208-01-063
Proj ID NH 2013(289)
Work Type LANDSCAPE ENHANCEMENT
 
1.647 197430.50 350.00 185589.42 94.0
Work Order 07-08-13
Work Began 09-25-13
Work Completed  
Time Computed 07-24-13
Contract Working Days 81
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 93
Contractor(s)
GREY CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 2208-01-063
BUYERS BARRICADES, INC.(1.41%)
UNLIMITED UTILITY CONSTRUCTION (3.62%)
L.E.D. CONCRETE, LLC (5.54%)
BOWDEN"S GUARANTEED HYDORMULCH, INC. (0.63%)
Contract # 05133037
Totals 197430.50 350.00 185589.42 94.0

CountyJOHNSON
Highway FM 2331
From SH 171
To FM 4 (NORTH)
CSJ 2213-01-013
Proj ID STP 2014(007)HES
Work Type ADDITIONAL PAVED SURFACE WIDTH
 
10.092 4289114.81 50300.00 1188729.58 27.7
Work Order 11-22-13
Work Began 01-08-14
Work Completed  
Time Computed 12-08-13
Contract Working Days 214
Addl Days Granted 5
Working Days Charged 147
Percent Time Used 67
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2213-01-013
RAMBO CONTRACTING, INC.(9.51%)
TEXAS ALTERNATIVE GRASSER, INC.(0.48%)
NORTHEASTERN PAVERS, INC.( 62.69%)
FORTSON CONTRACTING, INC.(2.11%)
D. I. J. CONSTRUCTION, INC.(1.25%)
BUYER BARRICADES (0.44%)
Contract # 09133023
Totals 4289114.81 50300.00 1188729.58 27.7