Monthly State Let Construction Report For Fort Worth District As Of Oct 16, 2017 Page 5 Of 5

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyPALO PINTO
HighwayFM 2201
FromFM 4
ToUS 281
CSJ1993-01-015
Proj IDSTP 1502(334)
Work TypeGR,BS,DR, STRUC & PAVEMENT
 
6.4274655964.114695650.9399.9
Work Order08-20-15
Work Began07-11-16
Work Completed
Time Computed09-19-15
Contract Working Days277
Addl Days Granted13
Working Days Charged220
Percent Time Used75
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1993-01-015
LUZ LERMA CONSTRUCTION, INC. (12.17)
NORTHEASTERN PAVERS, INC. (10.87)
WEST TEXAS RUMBLE STRIP (0.09)
DURABLE SPECIALTIES, INC. (0.58)
MARCOM"S MOWING SERVICE, LLC (1.80)
FARR FOUNDATION, INC. (1.89)
TEXAS ALTERNATIVE GRASSER, INC. (4.64)
STRIPING TECHNOLOGY, L.P. (2.00)
Contract #06153024
Totals4655964.1125390.514695650.9399.9

CountyTARRANT
HighwayFM 1220
FromEAGLE MOUNTAIN ELEM SCHOOL
To1,100 FT. NORTH OF BAILEY BOSWELL
CSJ2079-01-043
Proj IDSTP 2013(901)
Work TypeGRADING, BASE AND PAVEMENT
 
2.8798350775.032439846.4029.2
Work Order03-31-16
Work Began01-17-17
Work Completed
Time Computed09-12-16
Contract Working Days278
Addl Days Granted12
Working Days Charged145
Percent Time Used50
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 2079-01-043
CEN CONCRETE CONSTRUCTION COMPANY, INC. (6.08)
MICA CORPORATION (1.27)
FARR FOUNDATION, INC. (1.20)
TOTAL HIGHWAY MAINTENANCE, LLC (2.02)
TINMAN ENTERPRISES (1.66)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (4.07)
W.O.E. CONSTRUCTION (3.82)
ECONOMY TREE SERVICES, LLC (0.43)
Contract #01163037
Totals8350775.0384081.692439846.4029.2

CountyJOHNSON
HighwayFM 1902
FromTARRANT COUNTY LINE
ToFM 917
CSJ2118-02-019
Proj IDSTP 1502(547)HES
Work TypeGR, BS, DR, STR, & PVT
 
7.6696740440.332910747.4843.1
Work Order09-19-16
Work Began01-24-17
Work Completed
Time Computed10-20-16
Contract Working Days354
Addl Days Granted0
Working Days Charged171
Percent Time Used48
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2118-02-019
DALLAS LITE AND BARRICADE INC. (1.44)
DUSTROL, INC. (3.23)
FORTSON CONTRACTING, INC. (2.24)
J & M CONTRACTING, COMPANY (14.47)
MARCOM"S MOWING SERVICE, LLC (0.91)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.37)
TRP CONSTRUCTION GROUP, LLC (1.63)
C & J TREE SERVICE (0.34)
W.O.E. CONSTRUCTION (0.14)
Contract #07163207
Totals6740440.33841313.212910747.4843.1

CountyTARRANT
HighwaySH 360
From0.349 MI N OF SH 180
To0.158 MI N OF SH 180
CSJ2266-02-146
Proj IDSTP 1702(738)HESG
Work TypeSAFETY TREAT FIXED OBJECTS
 
0.191281936.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days24
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2266-02-146
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173242
Totals281936.150.000.000.0

CountyPALO PINTO
HighwayFM 1821
FromUS 281
ToFM 3027
CSJ2288-01-012
Proj IDSTP 1702(090)HESG
Work TypePROFILE PAVEMENT MARKERS
 
2.59118879.800.000.0
CountyPALO PINTO
HighwayFM 1821
FromUS-281
ToUS-180
CSJ2288-01-013
Proj IDSTP 1702(089)
Work TypeOVERLAY
 
3.5911038347.401052640.8199.9
Work Order06-14-17
Work Began08-03-17
Work Completed
Time Computed07-15-17
Contract Working Days64
Addl Days Granted0
Working Days Charged41
Percent Time Used64
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2288-01-012
ODUM SERVICES, L.P. (4.92)
PENHALL COMPANY (0.51)
TOTAL HIGHWAY MAINTENANCE, LLC (4.11)
SITE BARRICADES (0.37)
ALTUS TRAFFIC MANAGEMENT LLC (0.49)
HJC FARMS, INC. (4.84)
Contract #05173032
Totals1057227.2052603.921052640.8199.5

CountyPALO PINTO
HighwayFM 2353
FromSH-16
ToPR-36
CSJ2290-01-009
Proj IDSTP 1502(335)
Work TypeGR,BS,STRUCTURE AND PAVEMENTS
 
5.8805278946.235101409.3796.6
Work Order07-31-15
Work Began10-12-15
Work Completed
Time Computed08-29-15
Contract Working Days299
Addl Days Granted35
Working Days Charged321
Percent Time Used96
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2290-01-009
LUZ LERMA CONSTRUCTION, INC. (16.74)
HJC FARMS, INC. (1.98)
ALTUS TRAFFIC MANAGEMENT LLC (0.59)
STRIPING TECHNOLOGY, L.P. (1.83)
M.A.R. TRUCKING (0.20)
WEST TEXAS RUMBLE STRIP (0.07)
NIXON ENGINEERING, L.L.C. (0.06)
Contract #06153243
Totals5278946.232320.205101409.3796.6

CountyPARKER
HighwayFM 1187
FromFM 5
ToTARRANT COUNTY LINE
CSJ2291-01-013
Proj IDSTP 2014(772)
Work TypeGR,BS,STR,SURFACE,SIGNING & MARKING
 
7.2046785848.591716042.7925.2
Work Order08-08-14
Work Began12-10-14
Work Completed
Time Computed08-24-14
Contract Working Days374
Addl Days Granted0
Working Days Charged111
Percent Time Used29
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2291-01-013
RAMBO CONTRACTING, INC. (20.05)
TEXAS ALTERNATIVE GRASSER, INC. (0.90)
NORTHEASTERN PAVERS, INC. (14.31)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED (0.49)
HJC FARMS, INC. (0.77)
WEST TEXAS RUMBLE STRIP (0.07)
TRP CONSTRUCTION GROUP, LLC (1.08)
Contract #06143231
Totals6785848.590.001716042.7925.2

CountyTARRANT
HighwayIH 20
FromEB AND WB IH 20 OVER BOWEN RD
ToEB AND WB IH 20 OVER RUSH CREEK
CSJ2374-05-081
Proj IDBR 1702(739)
Work TypeUPGRADE BRIDGE & APPROACH RAILING
 
2.010966661.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days121
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 2374-05-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173215
Totals966661.000.000.000.0

CountyTARRANT
HighwayIH 20
FromBOWEN RD WB ENTRANCE RAMP
ToBOWEN RD WB EXIT RAMP
CSJ2374-05-082
Proj IDCC 2374-5-82
Work TypeGR,BS,DR,STR, PAV
 
0.4611256871.320.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days92
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
REBCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2374-05-082
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173006
Totals1256871.320.000.000.0

CountyJOHNSON
HighwayFM 2738
FromTARRANT C/L
To0.909 MI N OF FM 917
CSJ3010-02-014
Proj IDSTP 1502(548)HES
Work TypeYR, BS, DR, STR, & PAVT
 
4.4053409657.163010638.6888.2
Work Order11-16-16
Work Began01-19-17
Work Completed
Time Computed12-17-16
Contract Working Days218
Addl Days Granted0
Working Days Charged189
Percent Time Used86
Contractor(s)
BRETT CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3010-02-014
LUZ LERMA CONSTRUCTION, INC. (11.57)
D.I.J. CONSTRUCTION, INC (1.25)
ASSOCIATED CUTTING, INC. (0.10)
TEXAS SHAFTS, INC. (2.96)
ODUM SERVICES, L.P. (1.30)
DFW REBAR, INC. (0.18)
ELLIS-MCGINNIS CONSTRUCTION CO. (0.43)
PENHALL COMPANY (0.08)
DUSTROL, INC. (0.13)
APAC-TEXAS, INC. (0.88)
Contract #08163032
Totals3409657.16170969.763010638.6888.2

CountyHOOD
HighwayFM 4
FromFM 167
ToJOHNSON COUNTY LINE
CSJ3123-01-014
Proj IDSTP 2017(925)
Work TypeGR, BS, STRUC, AND PAVEMENT
 
4.3193211242.01162268.505.0
Work Order05-22-17
Work Began07-10-17
Work Completed
Time Computed06-22-17
Contract Working Days155
Addl Days Granted0
Working Days Charged10
Percent Time Used6
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 3123-01-014
D. I. J. CONSTRUCTION, INC. (2.49)
NORTHEASTERN PAVERS, INC. (43.76)
RAMBO CONTRACTING, INC. (5.19)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.76)
TEXAS ALTERNATIVE GRASSER, INC. (2.66)
COMEN ENTERPRISE LLC (4.78)
Contract #04173011
Totals3211242.0127440.50162268.505.0

CountyJOHNSON
HighwayFM 3136
From5.213 MILES EAST OF FM 4
To10.343 MILES EAST OF FM 4
CSJ3348-01-019
Proj IDSTP 1502(549)HES
Work TypeGR, BS, DR, STR, & PAVT
 
5.1926829235.177255710.3399.9
Work Order03-28-16
Work Began07-11-16
Work Completed
Time Computed04-28-16
Contract Working Days384
Addl Days Granted12
Working Days Charged308
Percent Time Used77
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3348-01-019
DUSTROL, INC. (0.12)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.53)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.11)
TOTAL HIGHWAY MAINTENANCE, LLC (3.70)
TEXAS SHAFTS, INC. (0.64)
SYNERGY SIGNS & SERVICES, LLC (0.70)
SOUTHEAST GRINDING & GROOVING, LLC (0.05)
OSCAR ORDUNO, INC. (2.21)
NORTHEASTERN PAVERS, INC. (27.61)
FORTSON CONTRACTING, INC. (0.78)
MCL CONTRACTING, LLC (0.14)
CROSSROADS, L.P. (0.76)
Contract #01163018
Totals6829235.1760750.467255710.3399.9

page 1 | page 2 | page 3 | page 4 | page 5