Monthly State Let Construction Report For Fort Worth District As Of May 11, 2015 Page 6 Of 7

Last Update: Monday, May 11, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWISE
Highway FM 2264
From CR 4431 N
To FM 407
CSJ 1310-03-025
Proj ID STP 2014(578)HES
Work Type GRADING, BASE, DRAINAGE, STRUCTURE, PAV
 
5.617 3983917.91 83207.00 536054.50 13.4
Work Order 10-30-14
Work Began 01-19-15
Work Completed  
Time Computed 11-15-14
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 20
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1310-03-025
NORTHEASTERN PAVERS, INC.(8.58%)
MARCOM"S MOWING SERVICE, LLC (0.43%)
ODUM SERVICES, L.P.(0.61%)
STORM WATER MANAGEMENT, INC. (0.83%)
CROSSROADS, L.P. (0.76%)
FARR FOUNDATION, INC.(3.07%)
STRIPING TECHNOLOGY, L.P.(1.36%)
WOLFE CONSTRUCTION GROUP, INC. (0.61%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(8.01%)
THELIN RECYCLING CO., LLC (OLD PRIME)(0.17%)
Contract # 09143040
Totals 3983917.91 83207.00 536054.50 13.4

CountyTARRANT
Highway FM 1187
From NEWT PATTERSON
To BU 287P
CSJ 1330-02-034
Proj ID STP 2010(399)ES
Work Type GRADING, DRAINAGE, STRUCTURES & PAV
 
1.503 6895052.12 0.00 12901332.42 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-05-10
Work Began 06-17-11
Work Completed  
Time Computed 11-01-10
Contract Working Days 427
Addl Days Granted 325
Working Days Charged 751
Percent Time Used 99
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1330-02-034
UNDERGROUND COALITION, INC.(2.92%)
INLET STRUCTURE SPECIALTIES LTD. (2.88%)
DURABLE SPECIALTIES, INC.(2.04%)
BANDA TRUCKING COMPANY (0.10%)
STORM WATER MANAGEMENT, INC. (0.31%)
INDUS CONSTRUCTION, L.P. (8.05%)
AUSTIN BRIDGE & ROAD, LP ( 16.96%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.34%)
DUSTROL, INC.(0.53%)
JM MATERIALS, INC. (0.32%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.83%)
CONCRETE CUTTING BY BOND (0.56%)
Contract # 03103004
Totals 6895052.12 0.00 12901332.42 99.9

CountyJACK
Highway FM 1191
From US 380
To YOUNG COUNTY LINE
CSJ 1333-03-018
Proj ID STP 2014(664)HRR
Work Type GRADING, BASE, DRAINAGE, STRUCTURE, PAV
 
6.980 5404940.22 163924.25 1088060.23 20.1
Work Order 06-18-14
Work Began 11-03-14
Work Completed  
Time Computed 07-04-14
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 38
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1333-03-018
EROSION CONTROL MANAGEMENT SERVICES(1.96%)
NORTH EASTERN PAVERS ( 34.25%)
STRIPING TECHNOLOGY, L.P.(1.09%)
Contract # 05143217
Totals 5404940.22 163924.25 1088060.23 20.1

CountyPARKER
Highway FM 1189
From YOUNG BEND ROAD
To HOOD COUNTY LINE
CSJ 1468-01-024
Proj ID STP 1402(036)
Work Type GR, STR, FLX BS, SC, MBGF, SIGN, PVT MK
 
9.058 6481549.55 0.00 44800.00 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-07-14
Work Began 00-00-00
Work Completed  
Time Computed 10-23-14
Contract Working Days 253
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1468-01-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143043
Totals 6481549.55 0.00 44800.00 0.6

CountyHOOD
Highway FM 167
From FM-51
To FM-3450
CSJ 1598-01-020
Proj ID STP 2014(976)
Work Type GR, BS, DR STRUCTURE & HMAC PAVEMENT
 
2.928 2079661.57 17500.00 2046981.02 100.0
Work Order 08-27-14
Work Began 09-15-14
Work Completed 01-23-15
Time Computed 09-12-14
Contract Working Days 61
Addl Days Granted 15
Working Days Charged 67
Percent Time Used 88
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1598-01-020
NORTHEASTERN PAVERS, INC.( 26.76%)
HJC FARMS, INC.(1.73%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.85%)
CROSSROADS, L.P. (0.47%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. ( 11.09%)
Contract # 06143056
Totals 2079661.57 17500.00 2046981.02 100.0

CountyJOHNSON
Highway FM 916
From SH 171
To FM 4
CSJ 1599-02-014
Proj ID STP 1402(037)HES
Work Type GRADING, BASE AND PAVEMENT
 
12.842 6925133.46 0.00 42900.00 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-30-14
Work Began 00-00-00
Work Completed  
Time Computed 10-16-14
Contract Working Days 201
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1599-02-014
STRIPING TECHNOLOGY, L.P.(0.77%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.67%)
RAMBO CONTRACTING, INC.(7.05%)
FARR FOUNDATION, INC.(2.15%)
PEACHTREE CONSTRUCTION, LTD. ( 21.42%)
Contract # 08143036
Totals 6925133.46 0.00 42900.00 0.6

CountyPARKER
Highway FM 1884
From B.B. FIELDER ROAD
To TO END OF FM 1884
CSJ 1601-02-023
Proj ID STP 2012(685)
Work Type GR, DRAINAGE, STRUCTURES, & PAVEMEN
 
6.305 6349600.35 0.00 6420238.45 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-01-12
Work Began 01-21-13
Work Completed 11-05-14
Time Computed 11-17-12
Contract Working Days 299
Addl Days Granted 15
Working Days Charged 312
Percent Time Used 99
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1601-02-023
COWTOWN TRAFFIC CONTROL, INC.(0.23%)
DUSTROL, INC.(0.30%)
FORTSON CONTRACTING, INC.(1.36%)
MCL CONTRACTING, LLC (0.11%)
NORTHEASTERN PAVERS, INC.( 36.29%)
SCOTT DERR PAINTING CO (0.04%)
STRIPING TECHNOLOGY, L.P.(0.90%)
SOUTHEAST GRINDING & GROOVING, LLC (0.04%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.33%)
TEXAS SHAFTS, INC. (0.78%)
USA EROSION, INC.(1.18%)
INLET STRUCTURE SPECIALTIES LTD. (3.54%)
BRENDA PRICE TRUCKING(1.23%)
Contract # 08123234
Totals 6349600.35 0.00 6420238.45 100.0

CountyTARRANT
Highway FM 1709
From UP RAILROAD, WEST OF US 377
To ELM STREET; IN KELLER
CSJ 1603-03-033
Proj ID CM 2011(928)
Work Type GR, DR, STRUCT AND PAVEMENT
 
0.226 879231.70 28925.13 313372.06 38.2
Work Order 04-02-14
Work Began 01-05-15
Work Completed  
Time Computed 09-29-14
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 86
Percent Time Used 175
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1603-03-033
A & A CONSTRUCTION (2.36%)
CLEMONS TRUCKING (3.55%)
ENVIRONMENTAL STANDARDS, INC.(1.31%)
INTEGRATED ROADWAY SERVICES, INC.( 18.42%)
PEACHTREE CONSTRUCTION, LTD. (9.54%)
STRIPE-A-ZONE, INC.(4.10%)
COWTOWN TRAFFIC CONTROL, INC.(0.82%)
LONE STAR HIGHWAY PRODUCTS, INC. (2.40%)
DUSTROL, INC.(1.65%)
METRO CUTTING AND SEALING, INC.(0.63%)
Contract # 01143210
Totals 879231.70 28925.13 313372.06 38.2

CountyTARRANT
Highway FM 1709
From PEARSON LANE; WEST CITY LIMITS
To SH 114; EAST CITY LIMITS
CSJ 1603-03-034
Proj ID STP 2011(228)TE
Work Type GRADING, DRAINAGE, INSTALL SIDEWALKS
 
6.100 1320757.45 0.00 1446798.88 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-03-12
Work Began 01-28-13
Work Completed 02-25-15
Time Computed 12-19-12
Contract Working Days 149
Addl Days Granted 46
Working Days Charged 198
Percent Time Used 101
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1603-03-034
ENVIRONMENTAL STANDARDS, INC.(3.97%)
CONCRETE PAVER SYSTEMS, INC. (0.26%)
CROSSROADS, L.P. (0.71%)
HIGHWAY TECHNOLOGIES, INC. (0.52%)
MIKE ALBERT, INC.( 34.12%)
WOODLAKE OUTDOOR, INC. (2.37%)
BUYERS BARRICADES, INC.(0.28%)
BUZZ SERVICES, L.L.C.(3.76%)
Contract # 11123021
Totals 1320757.45 0.00 1446798.88 100.0

CountyPARKER
Highway FM 1886
From FM 730
To TARRANT COUNTY LINE
CSJ 1605-01-014
Proj ID STP 2014(478)
Work Type GR.BS, DR, STRUC AND PAVEMENT
 
5.748 4834822.79 78814.95 1288612.70 26.6
Work Order 05-07-14
Work Began 06-12-14
Work Completed  
Time Computed 05-23-14
Contract Working Days 256
Addl Days Granted 0
Working Days Charged 157
Percent Time Used 61
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1605-01-014
RAMBO CONTRACTING, INC.(4.85%)
BICK"S CONSTRUCTION, INC.( 16.34%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.93%)
MARCOM"S MOWING SERVICE, LLC (0.53%)
WEST TEXAS RUMBLE STRIP(0.08%)
AAA DRILLING FOUNDATION CO., INC.(0.36%)
LIRA ELECTRIC(1.57%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.79%)
Contract # 03143221
Totals 4834822.79 78814.95 1288612.70 26.6

CountyWISE
Highway FM 2123
From AT SALT CREEK
To AND AT COTTONWOOD CREEK
CSJ 1606-02-013
Proj ID BR 1102(297)
Work Type REPL BRIDGES
 
0.099 1968338.24 0.00 1872436.82 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-14-11
Work Began 12-08-11
Work Completed  
Time Computed 09-30-11
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 380
Percent Time Used 253
Contractor(s)
DOUGHTIE CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1606-02-013
COWTOWN TRAFFIC CONTROL, INC.(0.36%)
BROCK ENVIRONMENTAL, LLC (0.39%)
DUSTIN ALLEN, INC. (1.70%)
GORRONDONA & ASSOCIATES, INC.(0.50%)
HIGHWAY TECHNOLOGIES, INC. (1.28%)
RG PAINTING(0.19%)
TEXAS ALTERNATIVE GRASSER, INC.(0.20%)
PRIMATE CONSTRUCTION, INC. (0.54%)
TEX OP CONSTRUCTION, LP(0.78%)
PEACHTREE CONSTRUCTION, LTD. (8.23%)
EW WELLS GROUP LLC (2.13%)
W. W. FOUNDATION DRILLING, LTD.(8.30%)
J.L. STEEL REINFORCING, LLC(0.33%)
ENVIRONMENTAL SAFETY SERVICES, INC.(8.95%)
JUST GROOVING, LTD.(0.29%)
JTM MATERIALS, INC.(0.17%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.42%)
KYLE ERWIN CONSTRUCTION, LLC (0.13%)
Contract # 08113260
Totals 1968338.24 0.00 1872436.82 99.9

CountyWISE
Highway FM 2123
From SH 114
To C.R. 3355
CSJ 1606-02-018
Proj ID STP 2012(736)HES
Work Type GRADING, BASE, DRAINAGE, STRUCTURE, PAV
 
12.330 4939000.01 0.00 5441185.18 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-03-12
Work Began 01-29-13
Work Completed 04-29-15
Time Computed 12-19-12
Contract Working Days 224
Addl Days Granted 10
Working Days Charged 257
Percent Time Used 109
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1606-02-018
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.47%)
BUYERS BARRICADES, INC.(0.39%)
W.S. CONSTRUCTION COMPANY( 13.29%)
PEACHTREE CONSTRUCTION, LTD. ( 20.15%)
HIGHWAY TECHNOLOGIES, INC. (2.13%)
HJC FARMS, INC.(2.96%)
STRIPING TECHNOLOGY, L.P.(2.21%)
W.O.E. CONSTRUCTION(0.03%)
Contract # 11123224
Totals 4939000.01 0.00 5441185.18 100.0

CountyWISE
Highway FM 2123
From FM 51
To CR 3585
CSJ 1606-02-019
Proj ID STP 2014(884)
Work Type GRADING, BASE, DRAIN.STRUCT. AND PAVE
 
3.078 3759624.74 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1606-02-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153052
Totals 3759624.74 0.00 0.00 0.0

CountyTARRANT
Highway FM 1938
From 0.2 MILE SOUTH OF FM 1709
To RANDOL MILL RD/WESTLAKE C/L
CSJ 1978-01-050
Proj ID STP 1402(039)MM
Work Type GR, BS, DR, STRUCTURES & PAVEMENT
 
1.743 20575236.87 1098791.44 1353946.50 6.5
Work Order 01-16-15
Work Began 03-23-15
Work Completed  
Time Computed 02-01-15
Contract Working Days 554
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 4
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1978-01-050
DALLAS LITE AND BARRICADE INC. (0.38%)
GJ SEEDING, LLC(0.59%)
THELIN RECYCLING COMPANY, L.P. (0.25%)
AUSTCO, INC. (0.05%)
NORTH TEXAS CONTRACTING, INC.( 20.92%)
LIRA ELECTRIC(2.38%)
FARR FOUNDATION, INC.(0.60%)
BREDA COMPANY, INC.(0.50%)
W.O.E. CONSTRUCTION(8.79%)
TEXAS SHAFTS, INC. (0.76%)
CROSSROADS DECORATIVE PAVEMENT (0.09%)
USA SWPPP INSPECTIONS, INC.(2.75%)
SCOTT DERR PAINTING CO, LLC(0.06%)
TRP CONSTRUCTION GROUP, LLC(0.66%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (5.68%)
A & A CONSTRUCTION (0.06%)
MARCOM"S MOWING SERVICE, LLC (0.32%)
BRENDA PRICE TRUCKING(0.68%)
INLET STRUCTURE SPECIALTIES LTD. (3.04%)
JM MATERIALS, INC. (0.50%)
KLP COMMERCIAL, LLC(8.05%)
Contract # 08143005
Totals 20575236.87 1098791.44 1353946.50 6.5

CountyTARRANT
Highway FM 1938
From SH 114
To RANDOL MILL ROAD
CSJ 1978-01-055
Proj ID STP 2012(570)
Work Type LANDSCAPE ENHANCEMENT
 
2.205 856000.00 0.00 856832.28 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-12
Work Began 12-14-12
Work Completed  
Time Computed 07-28-12
Contract Working Days 128
Addl Days Granted 50
Working Days Charged 178
Percent Time Used 100
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 1978-01-055
HIGHWAY TECHNOLOGIES, INC. (0.36%)
Contract # 05123245
Totals 856000.00 0.00 856832.28 99.9

CountyTARRANT
Highway FM 1220
From EAGLE MOUNTAIN ELEM SCHOOL
To 1,100 FT. NORTH OF BAILEY BOSWELL
CSJ 2079-01-041
Proj ID STP 2013(901)
Work Type GRADING, BASE AND PAVEMENT
 
2.879 5878132.94 0.00 27400.00 0.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-13
Work Began 00-00-00
Work Completed  
Time Computed 06-09-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2079-01-041
BRENDA PRICE TRUCKING(0.72%)
DALLAS LITE AND BARRICADE INC. (0.31%)
FARR FOUNDATION, INC.(1.36%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(0.46%)
LAYFIELD CONSTRUCTION, INC (4.47%)
J. E. GUZMAN CONSTRUCTION, INC.(5.59%)
TEX OP CONSTRUCTION, LP(2.07%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.13%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.43%)
W.O.E. CONSTRUCTION(4.76%)
NORTH TEXAS CONTRACTING, INC.( 14.65%)
STRIPING TECHNOLOGY, L.P.(1.26%)
Contract # 08133064
Totals 5878132.94 0.00 27400.00 0.4

CountyTARRANT
Highway SP 303
From WEST C/L (SHADY VALLEY DR)
To EAST C/L (W CORNERSTONE LN)
CSJ 2208-01-063
Proj ID NH 2013(289)
Work Type LANDSCAPE ENHANCEMENT
 
1.647 197430.50 350.00 192277.58 97.3
Work Order 07-08-13
Work Began 09-25-13
Work Completed  
Time Computed 07-24-13
Contract Working Days 81
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 93
Contractor(s)
GREY CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 2208-01-063
BUYERS BARRICADES, INC.(1.41%)
UNLIMITED UTILITY CONSTRUCTION (3.62%)
L.E.D. CONCRETE, LLC (5.54%)
BOWDEN"S GUARANTEED HYDORMULCH, INC. (0.63%)
Contract # 05133037
Totals 197430.50 350.00 192277.58 97.3

CountyJOHNSON
Highway FM 2331
From SH 171
To FM 4 (NORTH)
CSJ 2213-01-013
Proj ID STP 2014(007)HES
Work Type ADDITIONAL PAVED SURFACE WIDTH
 
10.092 4289114.81 42755.12 4907037.63 99.9
Work Order 11-22-13
Work Began 01-08-14
Work Completed  
Time Computed 12-08-13
Contract Working Days 214
Addl Days Granted 52
Working Days Charged 333
Percent Time Used 125
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2213-01-013
RAMBO CONTRACTING, INC.(9.51%)
TEXAS ALTERNATIVE GRASSER, INC.(0.48%)
NORTHEASTERN PAVERS, INC.( 62.69%)
FORTSON CONTRACTING, INC.(2.11%)
D. I. J. CONSTRUCTION, INC.(1.25%)
BUYER BARRICADES (0.44%)
Contract # 09133023
Totals 4289114.81 42755.12 4907037.63 99.9

CountyTARRANT
Highway SH 360
From AT SH 180 (DIVISION STREET)
To AND UPRR; IN ARLINGTON
CSJ 2266-02-127
Proj ID NH 2007(806)
Work Type GR, STRS & PAVEMENT
 
0.854 55975100.62 0.00 59587176.17 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-07-08
Work Began 03-07-09
Work Completed 08-12-14
Time Computed 10-05-08
Contract Working Days 555
Addl Days Granted 509
Working Days Charged 1,064
Percent Time Used 100
Contractor(s)
W.W. WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2266-02-127
COWTOWN TRAFFIC CONTROL, INC.(0.20%)
EVANS ENVIRONMENTAL CONTRACTING, LLC.(0.43%)
CAPROCK SPECIALITY CONTRACTORS (0.01%)
CRAIG OLDEN, INC.(1.53%)
FOUNDATION DRILLERS, INC.(1.00%)
HAYWARD BAKER, INC.(1.52%)
HIGHWAY TECHNOLOGIES, INC. (0.68%)
MAGNUM TUNNELING, LLC(0.32%)
MICA CORPORATION (3.87%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(7.49%)
TEX OP CONSTRUCTION, LP(0.33%)
DURABLE SPECIALTIES, INC.(0.67%)
LAYFIELD CONSTRUCTION, INC (0.07%)
BRENDA PRICE TRUCKING(4.11%)
SCOTT DERR PAINTING CO (0.06%)
INDUS CONSTRUCTION, L.P. (2.51%)
GREAT WESTERN ERECTORS (0.05%)
RAILWORKS TRACK SYSTEMS TEXAS, INC.( 11.20%)
SOUTHWEST CONSTRUCTION SERVICES(0.11%)
ERWIN STEEL WORKS, LLC (0.29%)
MOBILE ENTERPRISES, INC. (0.39%)
STOMPER DEMOLITION COMPANY, INC. (0.27%)
RIVER CITIES SAWING LLC(0.01%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.41%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.00%)
Contract # 02083001
Totals 55975100.62 0.00 59587176.17 100.0

CountyPARKER
Highway FM 1187
From FM 5
To TARRANT COUNTY LINE
CSJ 2291-01-013
Proj ID STP 2014(772)
Work Type GR, BS, STR, SURFACE, SIGNING & MARKING
 
7.204 6785848.59 293444.54 1270403.89 18.7
Work Order 08-08-14
Work Began 12-10-14
Work Completed  
Time Computed 08-24-14
Contract Working Days 374
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 15
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2291-01-013
RAMBO CONTRACTING, INC.( 20.05%)
TEXAS ALTERNATIVE GRASSER, INC.(0.90%)
NORTHEASTERN PAVERS, INC.( 14.31%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(0.49%)
HJC FARMS, INC.(0.77%)
WEST TEXAS RUMBLE STRIP(0.07%)
TRP CONSTRUCTION GROUP, LLC(1.08%)
Contract # 06143231
Totals 6785848.59 293444.54 1270403.89 18.7