Monthly State Let Construction Report For Fort Worth District As Of Aug 11, 2017 Page 2 Of 5

Last Update: Friday, August 11, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTARRANT
HighwayUS 377
FromAT EAST BELKNAP STREET
ToIN HALTOM CITY
CSJ0081-01-046
Proj IDCM 1102(122)
Work TypeGR, DR, SIGNAL AND PAVEMENT
 
0.4514198919.204341691.1899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-25-14
Work Began11-06-14
Work Completed
Time Computed11-06-14
Contract Working Days236
Addl Days Granted164
Working Days Charged514
Percent Time Used128
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0081-01-046
PLACIDO CONSTRUCTION COMPANY (1.88)
PEACHTREE CONSTRUCTION, LTD. (8.68)
EROSION CONTROL MANAGEMENT SERVICES (0.53)
A BROTHERS MILLING, LLC (2.09)
BUYERS BARRICADES, INC. (0.72)
BRADCO, LLC (2.07)
ABC EROSION CONTROL, INC. (0.79)
MCL CONTRACTING, LLC (0.98)
VENUS CONSTRUCTION (6.92)
W.O.E. CONSTRUCTION (0.20)
A & A CONSTRUCTION (0.08)
TOTAL HIGHWAY MAINTENANCE, LLC (1.29)
COWBOY TRUCKING (3.28)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (8.56)
DFW SERVICES, LLC (2.12)
UNION ELECTRICAL CONTRACTOR, INC. (0.08)
LINDAMOOD DEMOLITION, INC. (0.08)
Contract #04143224
Totals4198919.200.004341691.1899.9

CountyTARRANT
HighwaySH 183
FromCOMMERCE ST.
ToNICHOLS ST.
CSJ0094-01-030
Proj IDBR 2011(705)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.45910591980.8911584034.6099.9
Work Order12-20-11
Work Began12-03-13
Work Completed
Time Computed06-18-12
Contract Working Days524
Addl Days Granted100
Working Days Charged780
Percent Time Used125
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0094-01-030
1 PRIORITY ENVIRONMENTAL SERVICES, INC. (2.21)
BREDA COMPANY, INC. (0.92)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.25)
ATS DRILLING, INC. (3.07)
CONCRETE CUTTING BY BOND (0.06)
COWTOWN TRAFFIC CONTROL, INC. (0.23)
DUSTROL, INC. (0.16)
FARR FOUNDATION, INC. (0.59)
HOUSTON SAWING & DRILLING (0.08)
K & S UTILITY CONTRACTORS, INC. (4.32)
MELS ELECTRIC, L.P. (1.26)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (2.14)
SCOTT DERR PAINTING CO, LLC (0.32)
TOTAL HIGHWAY MAINTENANCE, LLC (0.60)
J.L. STEEL REINFORCING, LLC (0.14)
C.B. SERVICES, INC. (0.51)
RAMBO CONTRACTING, INC. (0.69)
C & S UTILITY CONTRACTORS, INC. (0.08)
HIGH QUALITY ELECTRIC (0.21)
FORTSON CONTRACTING, INC. (0.04)
W.O.E. CONSTRUCTION (0.03)
Contract #08113203
Totals10591980.8943822.6211584034.6099.9

CountyTARRANT
HighwaySH 183
FromHANDLEY-EDERVILLE RD.
ToRUFE SNOW DRIVE; IN RICHLAND HILLS
CSJ0094-02-121
Proj IDSTP 2012(660)MM
Work TypeGR, DR AND PAVEMENT
 
1.1403732867.330.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days188
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0094-02-121
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173021
Totals3732867.330.000.000.0

CountyTARRANT
HighwaySH 10
FromIH-820
ToWEST PARK WAY
CSJ0094-02-123
Proj IDNH 2017(890)
Work TypeMILL AND OVERLAY
 
5.1812966572.10856372.7228.8
Work Order04-24-17
Work Began06-19-17
Work Completed
Time Computed05-25-17
Contract Working Days96
Addl Days Granted0
Working Days Charged25
Percent Time Used26
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0094-02-123
EROSION CONTROL MANAGEMENT SERVICES (0.10)
TEXOP CONSTRUCTION (11.20)
TRP CONSTRUCTION GROUP, LLC (5.25)
ALTUS TRAFFIC MANAGEMENT LLC (0.40)
Contract #03173230
Totals2966572.10729939.86856372.7228.8

CountyTARRANT
HighwaySH 10
FromIH 820
ToMAIN STREET
CSJ0094-02-131
Proj IDSTP 2017(512)HES
Work TypeTRAFFIC SIGNAL WORK
 
7.845314980.00161626.4051.3
Work Order02-16-17
Work Began07-05-17
Work Completed
Time Computed04-18-17
Contract Working Days180
Addl Days Granted0
Working Days Charged67
Percent Time Used37
Contractor(s)
ROADWAY SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0094-02-131
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173227
Totals314980.0065954.40161626.4051.3

CountyWISE
HighwayUS 380
FromAT FM 730/ BNSF RR
To.
CSJ0134-07-070
Proj IDBR 1702(461)
Work TypeGR, BS, DR, STR, PAV
 
0.1002383490.730.000.0
CountyWISE
HighwayUS 380
FromAT FM 730/ BNSF RR
To.
CSJ0134-07-071
Proj IDBR 1702(461)
Work TypeGR, BS, DR, STR, PAV
 
0.100884614.880.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days235
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0134-07-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173005
Totals3268105.610.000.000.0

CountyWISE
HighwayUS 380
FromSH 101
To16TH STREET
CSJ0134-07-073
Proj IDSTP 1702(462)HES
Work TypeSAFETY LIGHTING
 
1.108232455.440.000.0
CountyWISE
HighwayUS 380
From0.349 MILE WEST SH 101
ToSH 101
CSJ0134-11-037
Proj IDSTP 1702(463)HES
Work TypeSAFETY LIGHTING
 
0.3498927.380.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-07-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days107
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0134-07-073
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173244
Totals241382.820.000.000.0

CountyTARRANT
HighwaySH 199
From0.452 MI S OF HANGER CUTOFF RD
To0.486 MI N OF NINE MILE BRIDGE RD
CSJ0171-04-078
Proj IDNH 1602(430)
Work TypeGR,BS,DR,SURF
 
5.26546273495.2914644144.7731.6
Work Order01-12-17
Work Began03-06-17
Work Completed
Time Computed02-12-17
Contract Working Days438
Addl Days Granted0
Working Days Charged99
Percent Time Used22
Contractor(s)
FLATIRON CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0171-04-078
MICA CORPORATION (5.24)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (6.06)
OSCAR ORDUNO, INC. (6.02)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.38)
TEXAS SHAFTS, INC. (2.19)
DUSTROL, INC. (0.36)
ANTIGO CONSTRUCTION, INC. (0.07)
HOUSTON SAWING & DRILLING (0.04)
EROSION CONTROL MANAGEMENT SERVICES (0.22)
TOTAL HIGHWAY MAINTENANCE, LLC (0.40)
ALTUS TRAFFIC MANAGEMENT LLC (0.65)
ROYAL REBAR (1.04)
AR DANIEL CONSTRUCTION SERVICES, INC. (0.10)
Contract #11163201
Totals46273495.291682517.8814644144.7731.6

CountyTARRANT
HighwaySH 199
FromAT BYPASS CHANNEL; IN FORT WORTH
ToNEAR CBD & TRINITY RIVER
CSJ0171-05-081
Proj IDHP 2008(345)
Work TypeGRADING, DRAINAGE AND STRUCTURE
 
0.30065461507.4325447265.9738.8
Work Order08-04-14
Work Began10-28-14
Work Completed
Time Computed10-28-14
Contract Working Days919
Addl Days Granted0
Working Days Charged696
Percent Time Used75
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0171-05-081
A BROTHERS MILLING, LLC (0.31)
BANDA TRUCKING COMPANY (0.01)
MICA CORPORATION (5.94)
TOTAL HIGHWAY MAINTENANCE, LLC (0.40)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.10)
STRAIGHT LINE SAWING & SEALING (0.12)
TEXAS SHAFTS, INC. (3.19)
TRAC-WORK, INC. (0.04)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (4.92)
INDUS CONSTRUCTION, L.P. (1.95)
INLET STRUCTURE SPECIALTIES LTD. (0.41)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (1.95)
SCOTT DERR PAINTING CO (0.27)
MCL CONTRACTING, LLC (0.18)
CONCRETE PRESERVATION (0.12)
CHUBBS CONSTRUCTION, LLC (2.35)
J.C. TRUCKING (0.00)
LUZ TRUCKING, INC. (0.00)
R&D BURNS BROTHERS, INC (0.00)
FORT WORTH CIVIL CONSTRUCTORS, LLC (0.07)
ANCORTEX, INC. (0.04)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.00)
(USE 18959)GREEN SCAPING (2.59)
Contract #05143201
Totals65461507.431518936.0125447265.9738.8

CountyTARRANT
HighwayUS 287
From1.00 M SOUTH TURNER WARNELL RD
ToWALNUT CREEK DRIVE
CSJ0172-09-033
Proj IDCC 172-9-33
Work TypeGR,BS,DR,STR, AND PAV
 
2.8774196348.592746516.4965.4
Work Order12-28-16
Work Began03-07-17
Work Completed
Time Computed01-28-17
Contract Working Days277
Addl Days Granted0
Working Days Charged102
Percent Time Used36
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0172-09-033
BROCK ENVIRONMENTAL SERVICES, LLC (0.28)
CROSSROADS, L.P. (1.13)
DUSTROL, INC. (0.86)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (12.00)
SCOTT DERR PAINTING CO, LLC (0.02)
FORTSON CONTRACTING, INC. (0.90)
OSCAR ORDUNO, INC. (4.07)
TOTAL HIGHWAY MAINTENANCE, LLC (1.68)
W.O.E. CONSTRUCTION (0.20)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (1.56)
BOWMAN ENGINEERING & CONSULTING, INC (1.00)
SYNERGY SIGNS & SERVICES, LLC (4.28)
BRENDA PRICE TRUCKING (2.38)
Contract #11163022
Totals4196348.59443796.532746516.4965.4

CountyJACK ETC
HighwayUS 281 ETC
FromSH 199
ToPALO PINTO COUNTY LINE
CSJ0249-07-069
Proj IDSTP 2017(732)HESG
Work TypeCL & SHLDR TEXTURING; PVMT MARKINGS
 
47.387237243.31231412.6897.5
Work Order03-10-17
Work Began04-21-17
Work Completed
Time Computed04-10-17
Contract Working Days64
Addl Days Granted0
Working Days Charged64
Percent Time Used100
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0249-07-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173024
Totals237243.310.00231412.6897.5

CountyPALO PINTO
HighwayUS 281
FromAT BRAZOS RIVER
To.
CSJ0250-02-050
Proj IDBR 1602(431)
Work TypeREHABILITATE BRIDGE
 
0.1244656945.550.000.0
Work Order05-16-17
Work Began00-00-00
Work Completed
Time Computed06-16-17
Contract Working Days234
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0250-02-050
SOUTHEAST GRINDING & GROOVING, LLC (0.18)
S & S BRIDGE PAINTING, INC. (30.06)
LANCO TURF & SEEDING, INC. (1.26)
MCL CONTRACTING, LLC (0.12)
COMEN ENTERPRISE LLC (0.99)
TOTAL HIGHWAY MAINTENANCE, LLC (0.42)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (2.06)
DUSTROL, INC. (0.21)
Contract #04173222
Totals4656945.550.000.000.0

CountyERATH
HighwayUS 281
FromPALO PINTO COUNTY LINE
ToBU 377J, IN STEPHENVILLE
CSJ0250-03-046
Proj IDSTP 1602(432)
Work TypeGR, BS, STRUCTURES AND PAVEMENT
 
46.33124891249.3113939636.6656.0
Work Order11-16-16
Work Began01-03-17
Work Completed
Time Computed12-17-16
Contract Working Days367
Addl Days Granted0
Working Days Charged130
Percent Time Used35
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0250-03-046
FARR FOUNDATION, INC. (1.92)
D.I.J. CONSTRUCTION, INC (2.76)
EROSION CONTROL MANAGEMENT SERVICES (0.13)
TEXAS ALTERNATIVE GRASSER, INC. (0.40)
NORTHEASTERN PAVERS, INC. (65.73)
MARCOM"S MOWING SERVICE, LLC (0.50)
HJC FARMS, INC. (0.72)
RAMBO CONTRACTING, INC. (3.93)
LUZ LERMA CONSTRUCTION, INC. (2.80)
Contract #08163004
Totals24891249.312904847.7913939636.6656.0

CountyERATH
HighwayUS 281
FromAT SH 6
To.
CSJ0258-02-057
Proj IDSTP 1502(541)HES
Work TypeGRADE SEPARATION, SURF TREATMENT
 
1.0736592271.784757759.6472.1
Work Order11-12-15
Work Began01-06-16
Work Completed
Time Computed12-13-15
Contract Working Days303
Addl Days Granted8
Working Days Charged281
Percent Time Used90
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0258-02-057
SCOTT DERR PAINTING CO, LLC (0.12)
D. I. J. CONSTRUCTION, INC. (1.37)
PEACHTREE CONSTRUCTION, LTD. (15.50)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (1.15)
LUZ LERMA CONSTRUCTION, INC. (5.03)
TEXAS ALTERNATIVE GRASSER, INC. (0.36)
LIRA ELECTRIC (2.09)
ODUM SERVICES, L.P. (0.23)
ELLIS-MCGINNIS CONSTRUCTION CO. (5.60)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.47)
JUST GROOVING, LTD. (0.03)
TOTAL HIGHWAY MAINTENANCE, LLC (3.78)
FARR FOUNDATION, INC. (2.91)
MCL CONTRACTING, LLC (0.04)
MCL CONTRACTING, LLC (0.11)
Contract #08153219
Totals6592271.78239199.164757759.6472.1

CountyJOHNSON
HighwayUS 67
FromPPROX. SH 174
To0.72 MI WEST OF SPUR 102
CSJ0259-06-001
Proj IDNH 2013(835)
Work TypeGRADING, STRUCTURES, BASE, & SURF
 
3.86028488425.8625598313.2791.1
Work Order12-17-13
Work Began04-30-14
Work Completed
Time Computed04-17-14
Contract Working Days606
Addl Days Granted84
Working Days Charged829
Percent Time Used120
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0259-06-001
COWTOWN TRAFFIC CONTROL, INC. (0.10)
A.M.S. COMPANY, INC. (23.62)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.51)
RUSSO CORPORATION (1.73)
AR DANIEL CONSTRUCTION SERVICES, INC. (0.69)
W.O.E. CONSTRUCTION (0.21)
BANDA TRUCKING COMPANY (0.66)
DUSTIN ALLEN, INC. (1.00)
INDUS CONSTRUCTION, L.P. (0.89)
TOTAL HIGHWAY MAINTENANCE, LLC (0.78)
TEX OP CONSTRUCTION, LP (0.11)
HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, INC (1.53)
PREMIER PAVING, LTD. (8.34)
PEAK COMMUNICATIONS LLC (0.05)
DOUBLE S CONSTRUCTION (0.05)
A+ GRANITE AND STONE DCOR (0.05)
BRAZOS VALLEY HYDRO SEEDING (1.09)
SHALOM SERVICES CORPORATION (0.18)
CROSS ROADS, L.P. (0.01)
3I CONSTRUCTION, LLC (0.18)
WG ENGINEERING & CONSTRUCTION, LLC (0.29)
WOLFE CONSTRUCTION GROUP, INC. (0.52)
TEXAS SHAFTS, INC. (0.08)
Contract #09133004
Totals28488425.86577394.8825598313.2791.1

CountyPARKER
HighwayIH 20
FromCENTERPOINT ROAD
ToLAKESHORE DRIVE; IN HUDSON OAKS
CSJ0314-07-046
Proj IDNH 1602(434)
Work TypeGR, DR, STRUCTURES AND PAVEMENT
 
2.3708970754.030.000.0
CountyPARKER
HighwayIH 20
FromBANKHEAD HIGHWAY
ToCENTERPOINT ROAD
CSJ0314-07-052
Proj IDSTP 1602(435)MM
Work TypeGRADING, STRUCTURES AND PAVEMENT
 
1.25020879191.930.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days512
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0314-07-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173041
Totals29849945.960.000.000.0

CountyPARKER
HighwayIH 20
FromRIC WILLIAMSON MEMORIAL HIGHWAY
ToFM 1884
CSJ0314-07-054
Proj IDNH 1702(088)
Work TypeMILL AND OVERLAY
 
2.0711697511.950.000.0
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed07-15-17
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0314-07-054
ODUM SERVICES, L.P. (3.56)
APEX HIGHWAY SERVICES LLC (0.18)
TEXOP CONSTRUCTION (2.70)
TOTAL HIGHWAY MAINTENANCE, LLC (3.82)
SITE BARRICADES (0.25)
ALTUS TRAFFIC MANAGEMENT LLC (0.72)
Contract #05173007
Totals1697511.950.000.000.0

CountyTARRANT
HighwaySH 114
FromDOVE ROAD
ToKIMBALL AVE
CSJ0353-03-095
Proj IDNH 2012(065)
Work TypeLANDSCAPING
 
2.537410000.00422645.4099.9
Work Order08-19-15
Work Began04-11-16
Work Completed
Time Computed09-19-15
Contract Working Days85
Addl Days Granted28
Working Days Charged113
Percent Time Used100
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0353-03-095
AQUA BORE (4.69)
BUYERS BARRICADES, INC. (1.95)
Contract #07153265
Totals410000.001600.00422645.4099.9

CountyTARRANT
HighwaySH 26
FromHALL-JOHNSON ROAD
ToBROWN TRAIL
CSJ0363-01-139
Proj IDSTP 2014(154)TE
Work TypeGRADING, BASE,DRAINAGE AND PAVEMENT
 
3.90038223663.077981687.3820.8
Work Order03-29-16
Work Began11-07-16
Work Completed
Time Computed04-29-16
Contract Working Days555
Addl Days Granted0
Working Days Charged182
Percent Time Used32
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0363-01-139
BREDA COMPANY, INC. (0.67)
ODUM SERVICES, L.P. (0.05)
TRANSPORT TRUST (0.00)
W.O.E. CONSTRUCTION (0.18)
ROADWAY SOLUTIONS, INC. (7.74)
USA EROSION, INC. (2.25)
ALTUS TRAFFIC MANAGEMENT LLC (0.34)
TEXAS BOMANITE (1.61)
STRIPING TECHNOLOGY, L.P. (0.74)
OSCAR ORDUNO, INC. (0.23)
STRIPING SYSTEMS, INC. (0.00)
ASHLAR CONTRACTING COMPANY (6.26)
JACKSON CONSTRUCTION, LTD. (14.96)
GOLDEN TREE MAINTENANCE (0.14)
DUSTROL, INC. (2.46)
JSS BORI GROUP, LLC (5.66)
TEXAS SHAFTS, INC. (0.67)
ARK CONTRACTING SERVICES, LLC (0.50)
C.T. AND S. METALWORKS, INC. (0.14)
BRENDA PRICE TRUCKING (0.33)
AR DANIEL CONSTRUCTION SERVICES, INC. (0.22)
Contract #02163201
Totals38223663.07976271.887981687.3820.8

CountyTARRANT
HighwaySH 121
FromSH 121 AT CARSON STREET
ToIN HALTOM CITY
CSJ0363-03-049
Proj IDCC 363-3-49
Work TypeRECONSTRUCT BRIDGE & CHANNEL
 
0.1505252178.3735216.000.6
Work Order03-15-17
Work Began00-00-00
Work Completed
Time Computed04-15-17
Contract Working Days225
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0363-03-049
ACTION COMMERCIAL SERVICES, L.L.C. (0.16)
AMERICAN FENCE COMPANY, INC. (0.32)
ALTUS TRAFFIC MANAGEMENT LLC (0.53)
SHALOM SERVICES CORPORATION (15.42)
FARR FOUNDATION, INC. (2.48)
Contract #02173237
Totals5252178.370.0035216.000.6

page 1 | page 2 | page 3 | page 4 | page 5