Monthly State Let Construction Report For Fort Worth District As Of Feb 10, 2017 Page 2 Of 5

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTARRANT
HighwaySH 199
FromAT BYPASS CHANNEL; IN FORT WORTH
ToNEAR CBD & TRINITY RIVER
CSJ0171-05-081
Proj IDHP 2008(345)
Work TypeGRADING, DRAINAGE AND STRUCTURE
 
0.30065461507.4321667255.4833.0
Work Order08-04-14
Work Began10-28-14
Work Completed
Time Computed10-28-14
Contract Working Days919
Addl Days Granted0
Working Days Charged568
Percent Time Used61
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0171-05-081
A BROTHERS MILLING, LLC (0.31)
BANDA TRUCKING COMPANY (0.01)
MICA CORPORATION (5.94)
TOTAL HIGHWAY MAINTENANCE, LLC (0.40)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.10)
STRAIGHT LINE SAWING & SEALING (0.12)
TEXAS SHAFTS, INC. (3.19)
TRAC-WORK, INC. (0.04)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (4.92)
INDUS CONSTRUCTION, L.P. (1.95)
INLET STRUCTURE SPECIALTIES LTD. (0.41)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (1.95)
SCOTT DERR PAINTING CO (0.27)
MCL CONTRACTING, LLC (0.18)
CONCRETE PRESERVATION (0.12)
CHUBBS CONSTRUCTION, LLC (2.35)
J.C. TRUCKING (0.00)
LUZ TRUCKING, INC. (0.00)
R&D BURNS BROTHERS, INC (0.00)
FORT WORTH CIVIL CONSTRUCTORS, LLC (0.07)
ANCORTEX, INC. (0.04)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.00)
GREEN SCAPING (2.59)
Contract #05143201
Totals65461507.43451692.6521667255.4833.0

CountyTARRANT
HighwayUS 287
From1.00 M SOUTH TURNER WARNELL RD
ToWALNUT CREEK DRIVE
CSJ0172-09-033
Proj IDCC 172-9-33
Work TypeGR,BS,DR,STR, AND PAV
 
2.8774196348.590.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-28-16
Work Began00-00-00
Work Completed
Time Computed01-28-17
Contract Working Days277
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0172-09-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163022
Totals4196348.590.000.000.0

CountyJACK ETC
HighwayUS 281 ETC
FromSH 199
ToPALO PINTO COUNTY LINE
CSJ0249-07-069
Proj IDSTP 2017(732)HESG
Work TypeCL & SHLDR TEXTURING; PVMT MARKINGS
 
47.387237243.310.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0249-07-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173024
Totals237243.310.000.000.0

CountyPALO PINTO ETC
HighwayUS 281 ETC
FromJACK COUNTY LINE
ToNE 21ST STREET
CSJ0249-08-041
Proj IDSTP 2016(148)
Work TypeSEAL COAT
 
209.1698069594.958389991.8099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-29-16
Work Began05-03-16
Work Completed
Time Computed05-03-16
Contract Working Days97
Addl Days Granted0
Working Days Charged93
Percent Time Used95
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0249-08-041
FLAT LINE, INC. (15.28)
BARRICADES PLUS, LLC (1.26)
BRYDL CONTRACTING, INC. (0.62)
INNOVATIVE ROADWAY SOLUTIONS LLC (0.25)
Contract #10153210
Totals8069594.950.008389991.8099.9

CountyPALO PINTO
HighwayUS 281
FromAT BRAZOS RIVER
To.
CSJ0250-02-039
Proj IDBR 1402(032)
Work TypeGR,BS,HMAC,DR,STR,BR,SIGN,PVT MK
 
1.0825829658.605857078.1899.9
Work Order12-02-14
Work Began04-13-15
Work Completed
Time Computed02-02-15
Contract Working Days273
Addl Days Granted0
Working Days Charged256
Percent Time Used93
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0250-02-039
PREMIER PAVING, LTD. (10.91)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.17)
MCL CONTRACTING, LLC (0.58)
SCOTT DERR PAINTING CO (0.30)
PRIMATE CONSTRUCTION, INC. (0.16)
DUSTROL, INC. (0.15)
TEXAS SHAFTS, INC. (5.84)
STRIPING TECHNOLOGY, L.P. (0.55)
FORTSON CONTRACTING, INC. (1.31)
STORM WATER MANAGEMENT, INC. (0.80)
SAN-ANN-CO., INC. (0.48)
JAY MILLS CONTRACTING, INCORPORATED (12.64)
Contract #08143236
Totals5829658.600.005857078.1899.9

CountyERATH
HighwayUS 281
FromPALO PINTO COUNTY LINE
ToBU 377J, IN STEPHENVILLE
CSJ0250-03-046
Proj IDSTP 1602(432)
Work TypeGR, BS, STRUCTURES AND PAVEMENT
 
46.33124891249.311296460.545.2
Work Order11-16-16
Work Began01-03-17
Work Completed
Time Computed12-17-16
Contract Working Days367
Addl Days Granted0
Working Days Charged16
Percent Time Used4
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0250-03-046
FARR FOUNDATION, INC. (1.92)
D.I.J. CONSTRUCTION, INC (2.76)
EROSION CONTROL MANAGEMENT SERVICES (0.13)
TEXAS ALTERNATIVE GRASSER, INC. (0.40)
NORTHEASTERN PAVERS, INC. (55.38)
MARCOM"S MOWING SERVICE, LLC (0.50)
HJC FARMS, INC. (0.72)
RAMBO CONTRACTING, INC. (3.27)
LUZ LERMA CONSTRUCTION, INC. (2.34)
Contract #08163004
Totals24891249.311296460.541296460.545.2

CountyERATH
HighwayUS 281
FromAT SH 6
To.
CSJ0258-02-057
Proj IDSTP 1502(541)HES
Work TypeGRADE SEPARATION, SURF TREATMENT
 
1.0736592271.783503137.3453.1
Work Order11-12-15
Work Began01-06-16
Work Completed
Time Computed12-13-15
Contract Working Days303
Addl Days Granted8
Working Days Charged163
Percent Time Used52
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0258-02-057
SCOTT DERR PAINTING CO, LLC (0.12)
D. I. J. CONSTRUCTION, INC. (1.37)
PEACHTREE CONSTRUCTION, LTD. (15.50)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (1.15)
LUZ LERMA CONSTRUCTION, INC. (5.03)
TEXAS ALTERNATIVE GRASSER, INC. (0.36)
LIRA ELECTRIC (2.09)
ODUM SERVICES, L.P. (0.23)
ELLIS-MCGINNIS CONSTRUCTION CO. (5.60)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.47)
JUST GROOVING, LTD. (0.03)
TOTAL HIGHWAY MAINTENANCE, LLC (3.78)
FARR FOUNDATION, INC. (2.91)
MCL CONTRACTING, LLC (0.04)
MCL CONTRACTING, LLC (0.11)
Contract #08153219
Totals6592271.7852354.993503137.3453.1

CountySOMERVELL
HighwayUS 67
FromCR 2021
ToERATH COUNTY LINE
CSJ0259-02-050
Proj IDNH 2016(831)
Work TypeMILL AND OVERLAY
 
8.9528834162.225602136.7063.4
Work Order08-23-16
Work Began10-18-16
Work Completed
Time Computed09-23-16
Contract Working Days125
Addl Days Granted0
Working Days Charged46
Percent Time Used36
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0259-02-050
LUZ LERMA CONSTRUCTION, INC. (0.71)
TIN MAN WELDING SERVICES (0.84)
TOTAL HIGHWAY MAINTENANCE, LLC (2.58)
COWBELL TRAFFIC SERVICES, INC. (0.27)
Contract #06163231
Totals8834162.221464940.605602136.7063.4

CountyJOHNSON
HighwayUS 67
FromPPROX. SH 174
To0.72 MI WEST OF SPUR 102
CSJ0259-06-001
Proj IDNH 2013(835)
Work TypeGRADING, STRUCTURES, BASE, & SURF
 
3.86028488425.8623106219.5181.2
Work Order12-17-13
Work Began04-30-14
Work Completed
Time Computed04-17-14
Contract Working Days606
Addl Days Granted79
Working Days Charged701
Percent Time Used102
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0259-06-001
COWTOWN TRAFFIC CONTROL, INC. (0.10)
A.M.S. COMPANY, INC. (23.62)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.51)
RUSSO CORPORATION (1.73)
AR DANIEL CONSTRUCTION SERVICES, INC. (0.69)
W.O.E. CONSTRUCTION (0.21)
BANDA TRUCKING COMPANY (0.66)
DUSTIN ALLEN, INC. (1.00)
INDUS CONSTRUCTION, L.P. (0.89)
TOTAL HIGHWAY MAINTENANCE, LLC (0.78)
TEX OP CONSTRUCTION, LP (0.11)
HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, INC (1.53)
PREMIER PAVING, LTD. (8.34)
PEAK COMMUNICATIONS LLC (0.05)
DOUBLE S CONSTRUCTION (0.05)
A+ GRANITE AND STONE DCOR (0.05)
BRAZOS VALLEY HYDRO SEEDING (1.09)
SHALOM SERVICES CORPORATION (0.18)
CROSS ROADS, L.P. (0.01)
3I CONSTRUCTION, LLC (0.18)
WG ENGINEERING & CONSTRUCTION, LLC (0.29)
Contract #09133004
Totals28488425.86151432.2123106219.5181.2

CountyJOHNSON
HighwayUS 67
FromAT CR 213
ToIN VENUS
CSJ0260-01-056
Proj IDSTP 1602(433)
Work TypeLANDSCAPING AND IRRIGATION
 
0.20056819.850.000.0
Work Order09-21-16
Work Began00-00-00
Work Completed
Time Computed10-22-16
Contract Working Days20
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0260-01-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08163247
Totals56819.850.000.000.0

CountyWISE
HighwayFM 51
FromDENTON COUNTY LINE
ToFM 1204
CSJ0312-03-030
Proj IDSTP 2016(833)
Work TypeHMAC OVERLAY
 
31.2285354817.2629750.000.5
Work Order04-07-16
Work Began00-00-00
Work Completed
Time Computed05-08-16
Contract Working Days128
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0312-03-030
ALTUS TRAFFIC MANAGEMENT LLC (0.23)
Contract #03163004
Totals5354817.260.0029750.000.5

CountyPARKER
HighwayIH 20
FromIH20 WB FR AT PATRICK CREEK
To.
CSJ0314-01-077
Proj IDBR 2015(563)
Work TypeGR, DR, STRUC, AND PAVEMENT
 
0.1001309705.351305163.9499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-23-15
Work Began09-14-15
Work Completed
Time Computed04-08-15
Contract Working Days148
Addl Days Granted0
Working Days Charged259
Percent Time Used175
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 0314-01-077
FORTSON CONTRACTING, INC. (1.93)
LINDAMOOD DEMOLITION, INC. (2.39)
EROSION CONTROL MANAGEMENT SERVICES (1.12)
TEXOP CONSTRUCTION (0.49)
W. W. FOUNDATION DRILLING, LTD. (5.26)
NORTHEASTERN PAVERS, INC. (10.65)
TRP CONSTRUCTION GROUP, LLC (0.28)
TOTAL HIGHWAY MAINTENANCE, LLC (0.41)
LAUGHLEY BRIDGE & CONSTRUCTION, INC. (0.75)
Contract #02153218
Totals1309705.350.001305163.9499.9

CountyTARRANT
HighwaySH 114
FromDOVE ROAD
ToKIMBALL AVE
CSJ0353-03-095
Proj IDNH 2012(065)
Work TypeLANDSCAPING
 
2.537410000.00402023.9098.0
Work Order08-19-15
Work Began04-11-16
Work Completed
Time Computed09-19-15
Contract Working Days85
Addl Days Granted28
Working Days Charged113
Percent Time Used100
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0353-03-095
AQUA BORE (4.69)
BUYERS BARRICADES, INC. (1.95)
Contract #07153265
Totals410000.0023241.50402023.9098.0

CountyTARRANT
HighwaySH 26
FromHALL-JOHNSON ROAD
ToBROWN TRAIL
CSJ0363-01-139
Proj IDSTP 2014(154)TE
Work TypeGRADING, BASE,DRAINAGE AND PAVEMENT
 
3.90038223663.073312891.138.6
Work Order03-29-16
Work Began11-07-16
Work Completed
Time Computed04-29-16
Contract Working Days555
Addl Days Granted0
Working Days Charged52
Percent Time Used9
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0363-01-139
BREDA COMPANY, INC. (0.67)
ODUM SERVICES, L.P. (0.05)
TRANSPORT TRUST (0.00)
W.O.E. CONSTRUCTION (0.18)
ROADWAY SOLUTIONS, INC. (7.74)
USA EROSION, INC. (2.25)
ALTUS TRAFFIC MANAGEMENT LLC (0.34)
TEXAS BOMANITE (1.61)
STRIPING TECHNOLOGY, L.P. (0.74)
OSCAR ORDUNO, INC. (0.23)
STRIPING SYSTEMS, INC. (0.00)
ASHLAR CONTRACTING COMPANY (6.26)
JACKSON CONSTRUCTION, LTD. (14.96)
GOLDEN TREE MAINTENANCE (0.14)
DUSTROL, INC. (2.46)
JSS BORI GROUP, LLC (5.66)
TEXAS SHAFTS, INC. (0.67)
ARK CONTRACTING SERVICES, LLC (0.50)
C.T. AND S. METALWORKS, INC. (0.14)
Contract #02163201
Totals38223663.07508240.823312891.138.6

CountyTARRANT
HighwaySH 121
FromSH 121 AT CARSON STREET
ToIN HALTOM CITY
CSJ0363-03-049
Proj IDCC 363-3-49
Work TypeRECONSTRUCT BRIDGE & CHANNEL
 
0.1505252178.370.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days225
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0363-03-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173237
Totals5252178.370.000.000.0

CountyHOOD
HighwaySH 144
FromAT BROOKSHIRES
To.
CSJ0385-04-045
Proj IDER 1602(591)
Work TypeOFF SITE DRAINAGE REPLACEMENT
 
0.0022899083.650.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days149
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRETT CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0385-04-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173032
Totals2899083.650.000.000.0

CountyPARKER
HighwayFM 1885
FromPARKER/PALO PINTO COUNTY LINE
ToFM 52
CSJ0539-05-015
Proj IDSTP 1502(332)
Work TypeGR, BS, DR, STRUC. AND PAVEMENT
 
5.9435556310.373381421.8860.8
Work Order08-03-15
Work Began03-15-16
Work Completed
Time Computed09-02-15
Contract Working Days299
Addl Days Granted0
Working Days Charged174
Percent Time Used58
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0539-05-015
J & M CONTRACTING, COMPANY (16.79)
ALTUS TRAFFIC MANAGEMENT LLC (0.43)
HJC FARMS, INC. (2.97)
STRIPING TECHNOLOGY, L.P. (1.37)
Contract #06153244
Totals5556310.37423984.703381421.8860.8

CountyERATH ETC
HighwayFM 8 ETC
FromFM 988
ToEASTLAND COUNTY LINE
CSJ0550-02-038
Proj IDSTP 2017(350)
Work TypeSEAL COAT
 
188.1556225724.970.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days74
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0550-02-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173035
Totals6225724.970.000.000.0

CountyERATH
HighwayFM 914
FromFM 847
ToSH 6
CSJ0550-03-024
Proj IDSTP 2015(770)HES
Work TypeGRADING,BASE,DRAINAGE,STRUCTURE&PVT
 
8.9263426804.423376415.8298.5
Work Order03-29-16
Work Began05-09-16
Work Completed
Time Computed04-25-16
Contract Working Days215
Addl Days Granted0
Working Days Charged149
Percent Time Used69
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0550-03-024
ODUM SERVICES, L.P. (0.64)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (6.45)
D.I.J. CONSTRUCTION, INC (3.23)
LINDAMOOD DEMOLITION, INC. (0.78)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.47)
MCL CONTRACTING, LLC (0.08)
TOTAL HIGHWAY MAINTENANCE, LLC (0.64)
BEAR CREEK CONSTRUCTION, LLC (11.36)
SAN-ANN-CO., INC. (1.29)
JUST GROOVING, LTD. (0.09)
SOUTH TEXAS PAINTING COMPANY (0.13)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09)
Contract #02163238
Totals3426804.4234868.833376415.8298.5

CountyTARRANT
HighwayVA
FromVARIOUS LOCATIONS
ToDISTRICT WIDE FY 2013
CSJ0902-00-134
Proj IDNH 2013(957)G
Work TypeSIGN STUCTURES
 
41.900476055.25272603.8171.7
Work Order07-08-14
Work Began01-05-15
Work Completed
Time Computed07-24-14
Contract Working Days128
Addl Days Granted0
Working Days Charged245
Percent Time Used191
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-134
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.97)
ODUM SERVICES, L.P. (1.73)
DYNAMIC VISION CO., INC. (5.67)
CREDENCE BUILDER, INC. (15.13)
LAUGHLEY BRIDGE & CONSTRUCTION, INC. (11.29)
Contract #04143241
Totals476055.257471.82272603.8171.7

page 1 | page 2 | page 3 | page 4 | page 5