Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTARRANT
Highway SH 26
From BRUMLOW/POOL
To JOHN MCCAIN
CSJ 0363-01-136
Proj ID STP 1102(295)MM
Work Type GRADING, BASE, DRAINAGE AND PAVEMENT
 
0.909 11469297.64 365598.76 6415278.32 56.8
Work Order 10-21-11
Work Began 07-16-12
Work Completed  
Time Computed 04-19-12
Contract Working Days 394
Addl Days Granted 10
Working Days Charged 479
Percent Time Used 118
Contractor(s)
AUI CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0363-01-136
TOTAL HIGHWAY MAINTENANCE, LLC (1.04%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(8.28%)
DUSTIN ALLEN, INC. (0.20%)
THELIN RECYCLING COMPANY, L.P. (0.29%)
DUSTROL, INC.(0.87%)
DURABLE SPECIALTIES, INC.(3.81%)
TEXAS STAR SAWING & SEALING(0.02%)
LINDAMOOD DEMOLITION, INC. (0.75%)
USA SWPPP INSPECTIONS, INC.(0.52%)
J/M MATERIALS, INC.(0.37%)
TEXAS INLETS, INC. (1.87%)
NORTH TEXAS REBAR, LLC (0.00%)
HAYDEN CAPITAL CORPORATION (0.98%)
ATS DRILLING, INC. (2.63%)
FOUNDATION DRILLERS, INC.(0.08%)
HAYWARD BAKER, INC.(0.30%)
J.L. STEEL REINFORCING, LLC(0.12%)
MCL CONTRACTING, LLC (3.79%)
SCOTT DERR PAINTING CO, LLC(0.10%)
TEXAS BOMANITE (0.00%)
FORTSON CONTRACTING, INC.(0.00%)
Contract # 08113208
Totals 11469297.64 365598.76 6415278.32 56.8

CountyTARRANT
Highway SH 121
From WESTERN OAKS DRIVE
To APPROX.1.2 MI N OF STONE MYERS PKWY
CSJ 0364-01-140
Proj ID CC 364-1-140
Work Type GR, BS, DR AND PAVEMENT
 
0.123 366150.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
3I CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0364-01-140
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143046
Totals 366150.05 0.00 0.00 0.0

CountyTARRANT
Highway SH 26
From GAYLORD TRAIL DRIVE
To GRAPEVINE MILLS BOULEVARD SOUTH
CSJ 0364-06-011
Proj ID STP 2011(227)TE
Work Type CROSSWALKS, ADA RAMPS & IMPROVEMENTS
 
1.360 1240195.30 110731.59 215658.47 17.3
CountyTARRANT
Highway VA
From GAYLORD TEXAN; IN GRAPEVINE
To NORTH OF GRAPEVINE MILLS MALL
CSJ 0902-48-663
Proj ID HP 2013(083)
Work Type GR, DR, STRUCTURE AND PAVEMENT
 
1.000 308901.54 0.00 0.00 0.0
Work Order 01-17-14
Work Began 05-20-14
Work Completed  
Time Computed 02-02-14
Contract Working Days 179
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 25
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0364-06-011
PORTER INTERNATIONAL CONSTRUCTION LLC( 35.37%)
Contract # 08133257
Totals 1549096.84 110731.59 215658.47 13.9

CountyTARRANT
Highway SH 121
From SOUTH OF ARBORLAWN DRIVE
To SOUTH OF OVERTON RIDGE BLVD
CSJ 0504-02-022
Proj ID STP 2009(485)ES
Work Type GR, DR, STRUCTURES AND PAVEMENT
 
0.100 116646468.88 102695.33 111322220.82 96.4
Work Order 02-01-10
Work Began 03-15-10
Work Completed  
Time Computed 02-17-10
Contract Working Days 896
Addl Days Granted 0
Working Days Charged 1,306
Percent Time Used 145
Contractor(s)
W.W. WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0504-02-022
COWTOWN TRAFFIC CONTROL, INC.(0.08%)
S & S BRIDGE PAINTING, INC.(0.04%)
INTERSTATE FOUNDATION, LLC (3.14%)
W.O.E. CONSTRUCTION(1.75%)
MARIO SINACOLA & SONS EXCAVATING, INC. ( 23.31%)
ODUM SERVICES, L.P.(0.67%)
ARLINGTON PAVERS, INC. (0.06%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(2.64%)
MICA CORPORATION (0.34%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(2.98%)
STRIPE-A-ZONE, INC.(0.23%)
MUSTANG TURF & LANDSCAPE, LLC(0.60%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.00%)
CRAIG OLDEN, INC.(5.50%)
RAMBO CONTRACTING, INC.(1.18%)
NORTH TEXAS CONTRACTING, INC.(5.20%)
INDUS CONSTRUCTION, L.P. (5.32%)
JONA CONTRACTING, INC. (0.00%)
SOUTHWEST CONSTRUCTION SERVICES(0.04%)
RMI WORLDWIDE, LLC (0.11%)
GUIDO'S TRUCKS (1.28%)
A R DANIEL CONSTRUCTION SERVICES, INC. (0.21%)
STOMPER DEMOLITION COMPANY, INC. (0.00%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.02%)
SCOTT DERR PAINTING CO, LLC(0.14%)
BRENDA PRICE TRUCKING(0.08%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.08%)
SHEA SERVICES, INC (0.46%)
TEXAS CONSTRUCTION SUPPLY, INC.(1.01%)
NORTH TEXAS TRUCKING, INC. (0.17%)
WEBBER BARRIER SERVICES, INC.(0.43%)
BIG DOG DRILLING, LLC(0.01%)
TX DOWN UNDER CONSTRUCTION LLC (0.02%)
FOUNDATION DRILLERS, INC.(0.04%)
RIVER CITIES SAWING, LLC (0.10%)
FORTSON CONTRACTING, INC.(0.00%)
RELIABLE TRUCKING(0.04%)
TEXAS MANHOLES COMPANY, INC. (0.00%)
KD SERVICES(0.38%)
GAMCOR, INC. (0.07%)
EROSION PREVENTION PRODUCTS(0.00%)
J.A. MANNING CONSTRUCTION CO., INC.(1.24%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.01%)
Contract # 11093001
Totals 116646468.88 102695.33 111322220.82 96.4

CountyJOHNSON
Highway SH 174
From AT FM 916 WB & EB INTER
To IN RIO VISTA
CSJ 0519-01-023
Proj ID STP 2013(673)
Work Type TRAFFIC SIGNAL INSTALLATION
 
0.100 315236.00 38398.66 128883.80 40.8
Work Order 11-05-13
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 60
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0519-01-023
AAA DRILLING FOUNDATION CO., INC.(3.96%)
BUYERS BARRICADES, INC.(0.52%)
GJ SEEDING, LLC(2.31%)
ROAD MASTER STRIPING LLC (0.94%)
DOWN UNDER CONSTRUCTION(1.75%)
SOUTH TEXAS ILLUMINATION, LLC( 42.08%)
BICK"S CONSTRUCTION, INC.( 14.88%)
HAROS BROS. CO.(3.96%)
Contract # 05133022
Totals 315236.00 38398.66 128883.80 40.8

CountyPALO PINTO
Highway SH 254
From FM 4 IN GRAFORD
To US 281
CSJ 0539-04-035
Proj ID STP 2013(539)
Work Type HMAC OVERLAY AND BASE REPAIR
 
11.191 2066986.35 96999.57 2002185.13 96.8
Work Order 07-31-13
Work Began 09-23-13
Work Completed  
Time Computed 08-16-13
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 75
Percent Time Used 84
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0539-04-035
W.S. CONSTRUCTION COMPANY(3.93%)
COTHRAN TRUCKING, LLC(2.87%)
TOTAL HIGHWAY MAINTENANCE, LLC (3.51%)
LONE STAR BARRIER SERVICES, LLC(2.01%)
CHEROKEE SERVICES(0.23%)
RICE ENVIRONMENTAL SERVICES(1.07%)
TEX OP CONSTRUCTION, LP(2.37%)
Contract # 04133225
Totals 2066986.35 96999.57 2002185.13 96.8

CountyPARKER
Highway FM 113
From FM 113 AT N RIPPY BRANCH (STR. #3)
To .
CSJ 0717-02-019
Proj ID BR 2013(540)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.070 446097.30 4400.00 442179.95 100.0
Work Order 09-04-13
Work Began 09-23-13
Work Completed 06-18-14
Time Computed 09-20-13
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 70
Percent Time Used 97
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0717-02-019
ACTION SERVICES(1.64%)
PEACHTREE CONSTRUCTION, LTD. ( 15.99%)
LONE STAR HIGHWAY PRODUCTS, INC. (6.73%)
Contract # 06133230
Totals 446097.30 4400.00 442179.95 100.0

CountyTARRANT
Highway FM 156
From 1000 FT NORTH OF AVONDALE-HASLETT
To 500 FT SOUTH OF AVONDALE-HASLETT RD
CSJ 0718-02-065
Proj ID STP 2013(954)
Work Type GR, BS, AND PAVEMENT
 
0.852 403357.75 3520.00 412106.60 99.9
Work Order 09-17-13
Work Began 10-21-13
Work Completed  
Time Computed 10-03-13
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 154
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0718-02-065
CROSSROADS, L.P. (1.29%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (4.98%)
FORTSON CONTRACTING, INC.(2.48%)
PEACHTREE CONSTRUCTION, LTD. ( 21.40%)
STRIPING TECHNOLOGY, L.P.(1.84%)
BRENDA PRICE TRUCKING(0.00%)
Contract # 08133261
Totals 403357.75 3520.00 412106.60 99.9

CountyTARRANT
Highway FM 157
From MITCHELL STREET; IN ARLINGTON
To IH 20
CSJ 0747-04-065
Proj ID STP 1402(034)HRR
Work Type GR, BS AND PAVEMENT
 
3.795 5294353.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 281
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE FAIN GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0747-04-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143213
Totals 5294353.95 0.00 0.00 0.0

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To DISTRICTWIDE FY 14
CSJ 0902-00-126
Proj ID STP 1302(027)
Work Type CONCRETE REPAIR
 
0.100 1413335.00 90193.09 1554316.76 99.9
Work Order 08-19-13
Work Began 10-21-13
Work Completed  
Time Computed 10-19-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 286
Percent Time Used 78
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-126
W.O.E. CONSTRUCTION(2.37%)
BRENDA PRICE TRUCKING(2.36%)
CROSSROADS, L.P. (0.23%)
Contract # 07133010
Totals 1413335.00 90193.09 1554316.76 99.9

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To DISTRICTWIDE
CSJ 0902-00-133
Proj ID STP 2013(552)
Work Type TRAFFIC SIGNAL INSTALLATION
 
0.100 815000.00 84010.00 849024.45 99.9
Work Order 04-23-13
Work Began 07-23-13
Work Completed  
Time Computed 07-23-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 368
Percent Time Used 100
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-133
ROADMASTER, INC. (1.45%)
DYNAMIC VISION CO., INC. (6.56%)
Contract # 03133030
Totals 815000.00 84010.00 849024.45 99.9

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To DISTRICT WIDE FY 2013
CSJ 0902-00-134
Proj ID NH 2013(957)G
Work Type SIGN STUCTURES
 
41.900 476055.25 0.00 0.00 0.0
Work Order 07-08-14
Work Began 00-00-00
Work Completed  
Time Computed 07-24-14
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-134
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143241
Totals 476055.25 0.00 0.00 0.0

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To DISTRICTWIDE
CSJ 0902-00-136
Proj ID STP 2014(353)G
Work Type TRAFFIC SIGNALS
 
0.100 1275000.00 0.00 0.00 0.0
Work Order 03-12-14
Work Began 00-00-00
Work Completed  
Time Computed 03-28-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-136
ROAD MASTER STRIPING LLC (0.85%)
Contract # 01143223
Totals 1275000.00 0.00 0.00 0.0

CountyTARRANT
Highway VA
From VARIOUS LOCATIONS
To ON FM 1187 AND FM 731
CSJ 0902-00-139
Proj ID STP 2014(663)
Work Type LANDSCAPING
 
0.100 317349.10 2500.00 2500.00 0.7
Work Order 05-09-14
Work Began 07-16-14
Work Completed  
Time Computed 07-16-14
Contract Working Days 107
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 7
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-139
TOTAL HIGHWAY MAINTENANCE, LLC (1.96%)
Contract # 04143237
Totals 317349.10 2500.00 2500.00 0.7

CountyWISE
Highway CR
From FOSTER RD AT TRIBUTARY OF DENTON CR
To .
CSJ 0902-20-100
Proj ID BR 2009(902)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.068 528890.88 0.00 0.00 0.0
CountyWISE
Highway CR
From CR 2560 OVER BRANCH OF DENTON CREEK
To .
CSJ 0902-20-104
Proj ID BR 2009(904)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 291911.71 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 209
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
3I CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-20-100
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143050
Totals 820802.59 0.00 0.00 0.0

CountyWISE
Highway CR
From CR 2675 (PARKER DAIRY RD) AT DENTON
To .
CSJ 0902-20-108
Proj ID BR 2012(347)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 549711.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 78
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ASHLAR CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0902-20-108
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143247
Totals 549711.00 0.00 0.00 0.0

CountyPALO PINTO
Highway VA
From VARIOUS LOCATIONS
To ON US 180 AND US 281
CSJ 0902-39-032
Proj ID STP 2014(770)
Work Type LANDSCAPING
 
0.200 191130.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-18-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 42
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-39-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143033
Totals 191130.12 0.00 0.00 0.0

CountyJACK
Highway CR
From SQUAW MOUNTAIN RD OVER W FRK TRINIT
To .
CSJ 0902-40-022
Proj ID BR 2008(528)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.083 364644.20 4920.00 357893.66 100.0
Work Order 01-17-14
Work Began 02-19-14
Work Completed 07-31-14
Time Computed 02-02-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 73
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-40-022
TOTAL HIGHWAY MAINTENANCE, LLC (1.05%)
DUSTY ALLEN, INC.(2.69%)
PRIMATE CONSTRUCTION, INC. (0.90%)
STRIPING TECHNOLOGY, L.P.(1.06%)
LANCO TURF & SEEDING, INC. (3.17%)
Contract # 12133017
Totals 364644.20 4920.00 357893.66 100.0

CountyJACK
Highway CR
From BURWICK RD AT BIG CLEVELAND CREEK
To .
CSJ 0902-40-025
Proj ID BR 2009(926)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 419877.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 115
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-40-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143034
Totals 419877.10 0.00 0.00 0.0

CountyTARRANT
Highway CS
From AT HARRISON LANE
To ON PIPELINE RD IN HURST
CSJ 0902-48-186
Proj ID STP 94(82)MM
Work Type INTERSECTION IMPROVEMENTS
 
0.010 801805.98 0.00 145395.00 18.1
Work Order 10-24-13
Work Began 01-15-14
Work Completed  
Time Computed 11-09-13
Contract Working Days 111
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 4
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-186
BRENDA PRICE TRUCKING(0.00%)
ROAD MASTER STRIPING LLC (0.41%)
GJ SEEDING, LLC(2.31%)
ALTUS TRAFFIC MANAGEMENT LLC (0.49%)
DURABLE SPECIALTIES, INC.( 12.07%)
DUSTROL, INC.(1.01%)
EROSION CONTROL MANAGEMENT SERVICES(0.50%)
MIKE ALBERT, INC.( 15.82%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(4.62%)
W.O.E. CONSTRUCTION(0.17%)
Contract # 08133062
Totals 801805.98 0.00 145395.00 18.1