|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | PALO PINTO |
| Highway |
US 180 |
| From |
SW 7TH AVE, EAST |
| To |
0.1 MILE EAST OF FM 1821 |
| CSJ |
0008-01-044 |
| Proj ID |
STP 2008(826) |
| Work Type |
MILL, FABRIC UNDERSEAL AND OVERLAY |
| |
|
2.757 |
1854816.47 |
0.00 |
0.00 |
0.0 |
| Work Order |
10-09-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
10-25-08 |
| Contract Working Days |
40 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| AUSTIN BRIDGE & ROAD, LP |
SUBCONTRACTOR(S) FOR CCSJ: 0008-01-044 DUSTROL, INC. (ROANOKE)(7.50%) HIGHWAY TECHNOLOGIES (1.41%) TOTAL HIGHWAY MAINTENANCE, LLC (1.61%)
|
| Contract # |
08083018 |
|
Totals |
1854816.47 |
0.00 |
0.00 |
0.0 |
|
| County | PARKER |
| Highway |
US 180 |
| From |
AT BANKHEAD HIGHWAY |
| To |
IN WEATHERFORD |
| CSJ |
0008-02-068 |
| Proj ID |
STP 2008(289) |
| Work Type |
TRAFFIC SIGNAL |
| |
|
0.100 |
80000.00 |
9000.00 |
80262.60 |
99.9 |
| Work Order |
02-13-08 |
| Work Began |
06-10-08 |
| Work Completed |
|
| Time Computed |
05-13-08 |
| Contract Working Days |
30 |
| Addl Days Granted |
0 |
| Working Days Charged |
24 |
| Percent Time Used |
80 |
| Contractor(s) |
| DURABLE SPECIALTIES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0008-02-068 ROAD MASTER STRIPING LLC (6.25%)
|
| Contract # |
01083016 |
|
Totals |
80000.00 |
9000.00 |
80262.60 |
99.9 |
|
| County | PARKER |
| Highway |
IH 20 |
| From |
FRTG RDS @ FM 1187/FM 3325 |
| To |
IN PARKER COUNTY |
| CSJ |
0008-03-093 |
| Proj ID |
CM 2008(737) |
| Work Type |
GR, BS, PAVT, SIGNALS, SIGN & STRIPING |
| |
|
0.152 |
885892.60 |
60798.64 |
60798.64 |
6.8 |
| Work Order |
09-16-08 |
| Work Began |
10-20-08 |
| Work Completed |
|
| Time Computed |
10-02-08 |
| Contract Working Days |
45 |
| Addl Days Granted |
0 |
| Working Days Charged |
6 |
| Percent Time Used |
13 |
| Contractor(s) |
| J.L. STEEL, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0008-03-093 HIGHWAY TECHNOLOGIES (0.53%) PEACHTREE CONSTRUCTION, LTD. ( 24.70%) TEXAS ENVIRONMENTAL MANAGEMENT, INC(1.45%) STRIPING TECHNOLOGY, L.P.(2.18%) TEXAS SAFE SITE PRODUCTS, LP (0.43%) BRENDA PRICE TRUCKING(0.29%) MICA CORPORATION ( 26.26%) LAYFIELD CONSTRUCTION, INC (0.90%) DURABLE SPECIALTIES, INC.( 16.78%)
|
| Contract # |
08083229 |
|
Totals |
885892.60 |
60798.64 |
60798.64 |
6.8 |
|
| County | TARRANT |
| Highway |
BU 287P |
| From |
AT MINTON ROAD |
| To |
IN SAGINAW |
| CSJ |
0013-10-072 |
| Proj ID |
STP 2009(084) |
| Work Type |
TRAFFIC SIGNAL |
| |
|
0.100 |
86500.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
30 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ROADWAY SOLUTIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0013-10-072 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11083011 |
|
Totals |
86500.00 |
0.00 |
0.00 |
0.0 |
|
| County | TARRANT |
| Highway |
BU 287P |
| From |
400 FT NORTH OF BAILEY-BOSWELL ROAD |
| To |
200 FT SOUTH OF RR BRIDGE |
| CSJ |
0013-10-073 |
| Proj ID |
NH 2007(440) |
| Work Type |
MILL, SHLDER REHAB & HMAC OVERLAY |
| |
|
4.906 |
5073895.15 |
8858.00 |
5046882.09 |
99.4 |
| Work Order |
10-12-07 |
| Work Began |
03-24-08 |
| Work Completed |
|
| Time Computed |
10-28-07 |
| Contract Working Days |
105 |
| Addl Days Granted |
33 |
| Working Days Charged |
138 |
| Percent Time Used |
100 |
| Contractor(s) |
| SUNMOUNT CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 0013-10-073 BREDA COMPANY, INC.(0.28%) HIGHWAY TECHNOLOGIES (0.19%) ODUM SERVICES, L.P.(1.36%) STOMPER DEMOLITION (0.18%) STRIPING TECHNOLOGY, L.P.(1.35%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.95%) THOMAS GRINDING, INC.(0.10%) RIVER CITY SAVING, LLC (0.73%) METROPLEX PAVEMENT MARKINGS, LLC (0.05%)
|
| Contract # |
09073209 |
|
Totals |
5073895.15 |
8858.00 |
5046882.09 |
99.4 |
|
| County | TARRANT |
| Highway |
BU 287P |
| From |
AT TINSLEY LANE |
| To |
IN TARRANT COUNTY |
| CSJ |
0013-10-074 |
| Proj ID |
NH 2009(051) |
| Work Type |
TRAFFIC SIGNAL INSTALLATION |
| |
|
0.100 |
41869.20 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
30 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| BEAN ELECTRICAL, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0013-10-074 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10083211 |
|
Totals |
41869.20 |
0.00 |
0.00 |
0.0 |
|
| County | TARRANT |
| Highway |
BU 287P |
| From |
AT PEDEN ROAD |
| To |
IN TARRANT COUNTY |
| CSJ |
0013-10-075 |
| Proj ID |
NH 2009(028) |
| Work Type |
TRAFFIC SIGNAL |
| |
|
0.100 |
51207.80 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
10-16-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
30 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| REPUBLIC INTELLIGENT TRANSPORTATION SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0013-10-075 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09083013 |
|
Totals |
51207.80 |
0.00 |
0.00 |
0.0 |
|
| County | TARRANT |
| Highway |
IH 35W |
| From |
ALSBURY BLVD1187 |
| To |
TARRANT COUNTY LINE |
| CSJ |
0014-02-039 |
| Proj ID |
IM 0355(135)W |
| Work Type |
GRADING, DRAINAGE, STRUCTS & PAVEMENT |
| |
|
1.545 |
5476865.80 |
0.00 |
5698879.20 |
99.9 |
| Work Order |
02-01-06 |
| Work Began |
02-22-06 |
| Work Completed |
|
| Time Computed |
02-22-06 |
| Contract Working Days |
235 |
| Addl Days Granted |
112 |
| Working Days Charged |
409 |
| Percent Time Used |
117 |
| Contractor(s) |
| AUI CONTRACTORS, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0014-02-039 BREDA COMPANY, INC.(0.38%) CAPROCK SPECIALITY CONTRACTORS (0.29%) CRAIG OLDEN, INC.(4.09%) DALLAS LITE AND BARRICADE INC. (0.80%) MCRYAN HAULING, INC. (0.60%) DESIGNED TELECOMMUNICATIONS, INC.(3.95%) EVANS UTILITY GROUP, INC.(0.95%) FORTSON CONTRACTING, INC.(2.27%) NORTH TEXAS BOMANITE, INC. (1.17%) NORTH TEXAS BRIDGE COMPANY, INC. (1.90%) PREMIER PAVING, LTD( 12.22%) RAMBO CONTRACTING, INC.(0.78%) RAYMOND PAINTING, INC. (0.14%) STRIPING TECHNOLOGY, L.P.(1.99%) TEX OP CONSTRUCTION, LP(0.65%) W.W. WEBBER INC. (1.50%) TEXAS SHAFTS, INC. (0.35%) UNIVERSAL LIME INC.(0.59%) APAC-TEXAS, INC. (9.90%) J.L. STEEL, L.P. (0.06%) REYNOLDS ASPHALT & CONSTRUCTION COMPANY(0.03%) LVI ENVIRONMENTAL SERVICES, INC. (1.45%) AUSTIN BRIDGE & ROAD, LP (0.26%) REPUBLIC ELECTRIC(7.17%) STOMPER DEMOLITION (0.24%) REX SMITH CONSTRUCTION SERVICES, INC.(0.38%) ARLINGTON PAVERS, INC. (0.03%) SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.14%) EL CALA CONSTRUCTION LLC (0.10%)
|
| Contract # |
12053017 |
|
Totals |
5476865.80 |
0.00 |
5698879.20 |
99.9 |
|
| County | TARRANT |
| Highway |
IH 35W |
| From |
AT FM 1187 |
| To |
IN FORT WORTH |
| CSJ |
0014-02-041 |
| Proj ID |
CM 2007(798) |
| Work Type |
GRADING, STRUCTURES, DRAINAGE & PAV |
| |
|
0.747 |
8690270.92 |
849549.35 |
3141869.20 |
36.1 |
| Work Order |
09-24-07 |
| Work Began |
04-15-08 |
| Work Completed |
|
| Time Computed |
03-24-08 |
| Contract Working Days |
291 |
| Addl Days Granted |
0 |
| Working Days Charged |
159 |
| Percent Time Used |
54 |
| Contractor(s) |
| W.W. WEBBER, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0014-02-041 CAPROCK SPECIALITY CONTRACTORS (0.04%) INDUS CONSTRUCTION, L.P. (2.87%) INTEGRATED ROADWAY SERVICES, INC.(5.98%) REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 11.46%) SCHNABEL FOUNDATION CO. (HOUSTON)(3.68%) SCOTT DERR PAINTING CO (0.30%) TEXAS ENVIRONMENTAL MANAGEMENT, INC(3.22%) TEXAS HIGHWAY MARKINGS, LLC(0.09%) TEXAS SHAFTS, INC. (1.00%) JLB CONTRACTING, LP(0.08%) MR. DIRT (0.08%) RICE TUNNELING & BORING, INC.(0.26%)
|
| Contract # |
08073005 |
|
Totals |
8690270.92 |
849549.35 |
3141869.20 |
36.1 |
|
| County | JOHNSON |
| Highway |
IH 35W |
| From |
BETHESDA ROAD OVER IH 35W |
| To |
. |
| CSJ |
0014-03-084 |
| Proj ID |
BR 2007(610) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.215 |
2409268.03 |
0.00 |
2400045.39 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
08-08-07 |
| Work Began |
08-31-07 |
| Work Completed |
|
| Time Computed |
08-24-07 |
| Contract Working Days |
198 |
| Addl Days Granted |
0 |
| Working Days Charged |
229 |
| Percent Time Used |
115 |
| Contractor(s) |
| M. HANNA CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0014-03-084 W.W. WEBBER, LLC (3.17%) PEACHTREE CONSTRUCTION, LTD. ( 10.52%) STOMPER DEMOLITION (2.61%) HIGHWAY TECHNOLOGIES, L.P. (2.96%) TEX OP CONSTRUCTION, LP(0.98%) PRIMATE CONSTRUCTION, INC. (0.12%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.11%) S & S BRIDGE PAINTING(0.20%) STRIPING TECHNOLOGY, L.P.(1.17%) TEXAS ENVIRONMENTAL MANAGEMENT, INC(4.90%) NORTH TEXAS BRIDGE COMPANY, INC. (2.87%)
|
| Contract # |
06073026 |
|
Totals |
2409268.03 |
0.00 |
2400045.39 |
99.9 |
|
| County | JOHNSON |
| Highway |
SH 174 |
| From |
AT SOUTHWEST HULEN STREET |
| To |
N BURLESON |
| CSJ |
0019-01-133 |
| Proj ID |
CC 19-1-133 |
| Work Type |
TRAFFIC SIGNAL INSTALLATION |
| |
|
0.100 |
57802.90 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
09-12-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
30 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| DURABLE SPECIALTIES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0019-01-133 ACTION SERVICES(2.97%)
|
| Contract # |
08083216 |
|
Totals |
57802.90 |
0.00 |
0.00 |
0.0 |
|
| County | JOHNSON |
| Highway |
SH 171 |
| From |
SH 171 AT ELM CREEK |
| To |
. |
| CSJ |
0019-02-028 |
| Proj ID |
BR 2007(677) |
| Work Type |
REPLACE CULVERT |
| |
|
0.400 |
3698579.00 |
230303.12 |
2413906.21 |
65.2 |
| Work Order |
10-02-07 |
| Work Began |
10-29-07 |
| Work Completed |
|
| Time Computed |
10-18-07 |
| Contract Working Days |
256 |
| Addl Days Granted |
0 |
| Working Days Charged |
251 |
| Percent Time Used |
98 |
| Contractor(s) |
| AMERICAN CIVIL CONSTRUCTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0019-02-028 FORTSON CONTRACTING, INC.(0.98%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.26%) STRIPING TECHNOLOGY, L.P.(1.14%) RAMBO CONTRACTING, INC.(3.09%) REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 13.22%) J.L. STEEL, L.P. (0.91%)
|
| Contract # |
07073026 |
|
Totals |
3698579.00 |
230303.12 |
2413906.21 |
65.2 |
|
| County | ERATH |
| Highway |
US 67 ETC |
| From |
US 281 |
| To |
FM 988 |
| CSJ |
0079-05-050 |
| Proj ID |
NH 2008(562) |
| Work Type |
MILL AND OVERLAY |
| |
|
19.511 |
6340613.75 |
0.00 |
0.00 |
0.0 |
| Work Order |
08-15-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
08-31-08 |
| Contract Working Days |
64 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| LINDSEY CONTRACTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0079-05-050 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07083005 |
|
Totals |
6340613.75 |
0.00 |
0.00 |
0.0 |
|
| County | ERATH |
| Highway |
US 377 |
| From |
US 377 AT PALUXY RIVER |
| To |
. |
| CSJ |
0080-02-052 |
| Proj ID |
BR 2007(644) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.100 |
1802913.95 |
200586.21 |
826123.40 |
45.8 |
| Work Order |
05-05-08 |
| Work Began |
08-04-08 |
| Work Completed |
|
| Time Computed |
08-04-08 |
| Contract Working Days |
230 |
| Addl Days Granted |
0 |
| Working Days Charged |
62 |
| Percent Time Used |
26 |
| Contractor(s) |
| ELLIS-MCGINNIS CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0080-02-052 SAN-ANN-CO., INC.(0.44%) JAY MILLS CONTRACTING, INCORPORATED( 12.95%) FOUNDATION DRILLERS, INC.(4.70%) GUAJARDO STEEL (0.87%) JONA CONTRACTING, INC. (2.74%) GARY A. CRAIN, INC.(0.40%) SCOTT DERR PAINTING CO (0.34%) TEXAS ENVIRONMENTAL MANAGEMENT, INC(2.35%) PEACHTREE CONSTRUCTION, LTD. ( 12.40%) TOTAL HIGHWAY MAINTENANCE, LLC (1.05%)
|
| Contract # |
03083215 |
|
Totals |
1802913.95 |
200586.21 |
826123.40 |
45.8 |
|
| County | TARRANT |
| Highway |
US 377 |
| From |
APPROX 1.0 MI SOUTH OF DENTON C/L |
| To |
KELLER HICKS ROAD |
| CSJ |
0081-02-045 |
| Proj ID |
STP 2005(34)MM |
| Work Type |
GR, DR, ACP, CONC PAV, SIGN & PAV M |
| |
|
2.943 |
12983276.32 |
249604.36 |
12769399.26 |
99.9 |
| Work Order |
02-27-06 |
| Work Began |
01-25-07 |
| Work Completed |
|
| Time Computed |
08-27-06 |
| Contract Working Days |
340 |
| Addl Days Granted |
112 |
| Working Days Charged |
446 |
| Percent Time Used |
98 |
| Contractor(s) |
| SUNMOUNT CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 0081-02-045 A & A CONSTRUCTION (0.05%) BREDA COMPANY, INC.(1.01%) CAPROCK SPECIALITY CONTRACTORS (0.43%) CEN-TEX SEEDING, INC.(1.85%) INLET STRUCTURE SPECIALTIES LTD. (3.39%) L & E HART ENTERPRISES, INC. (0.49%) MCRYAN HAULING, INC. (2.31%) MICA CORPORATION (2.99%) LAYFIELD CONSTRUCTION, INC (0.24%) DURABLE SPECIALTIES, INC.(1.61%) MURRAY CONSTRUCTION(0.40%) NORTH TEXAS CONTRACTING, INC.( 12.23%) STOMPER DEMOLITION (0.28%) TEXAS HIGHWAY MARKINGS, LLC(0.98%) W.W. WEBBER INC. (1.22%) CRAIG OLDEN, INC.(0.41%) COWTOWN TRAFFIC CONTROL, INC.(0.87%) MASTERPIECE GRINDING & GROOVING, LLC (0.19%) S & S PAINTING (0.24%)
|
| Contract # |
12053204 |
|
Totals |
12983276.32 |
249604.36 |
12769399.26 |
99.9 |
|
| County | TARRANT |
| Highway |
SH 183 |
| From |
AT TRIBUTARY TO W FORK TRINITY |
| To |
WF-4 |
| CSJ |
0094-01-038 |
| Proj ID |
NH 2008(827) |
| Work Type |
GR, DR, AND STR |
| |
|
0.037 |
1800034.85 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
71 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| J.L. STEEL, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0094-01-038 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11083208 |
|
Totals |
1800034.85 |
0.00 |
0.00 |
0.0 |
|
| County | TARRANT |
| Highway |
SH 183 |
| From |
SH 199 |
| To |
BU 287P/NORTH MAIN STREET |
| CSJ |
0094-05-062 |
| Proj ID |
NH 2008(580) |
| Work Type |
MILL, OVERLAY, C & G REPAIR & STRIPING |
| |
|
9.704 |
4535778.92 |
346210.47 |
1549194.73 |
34.1 |
| Work Order |
06-10-08 |
| Work Began |
08-04-08 |
| Work Completed |
|
| Time Computed |
06-26-08 |
| Contract Working Days |
96 |
| Addl Days Granted |
0 |
| Working Days Charged |
70 |
| Percent Time Used |
72 |
| Contractor(s) |
| APAC-TEXAS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0094-05-062 J.L. STEEL, L.P. ( 15.11%) DUSTROL, INC. (ROANOKE)(0.17%) DURABLE SPECIALTIES, INC.(2.74%) TEX OP CONSTRUCTION, LP(9.01%) TOTAL HIGHWAY MAINTENANCE, LLC (5.03%)
|
| Contract # |
05083204 |
|
Totals |
4535778.92 |
346210.47 |
1549194.73 |
34.1 |
|
| County | JACK |
| Highway |
US 380 |
| From |
5 LANES SECTION IN JACKSBORO |
| To |
YOUNG COUNTY LINE |
| CSJ |
0134-04-032 |
| Proj ID |
STP 2008(731) |
| Work Type |
MICROSURFACE |
| |
|
31.740 |
1728459.31 |
911591.33 |
1813610.36 |
99.9 |
| County | DENTON |
| Highway |
FM 51 |
| From |
0.7 MI EAST OF DENTON COUNTY LINE |
| To |
WISE/DENTON COUNTY LINE |
| CSJ |
0312-02-014 |
| Proj ID |
C 312-2-14 |
| Work Type |
MICROSURFACING |
| |
|
0.700 |
36982.11 |
31459.00 |
31459.00 |
85.0 |
| Work Order |
08-15-08 |
| Work Began |
08-31-08 |
| Work Completed |
|
| Time Computed |
08-31-08 |
| Contract Working Days |
85 |
| Addl Days Granted |
0 |
| Working Days Charged |
42 |
| Percent Time Used |
49 |
| Contractor(s) |
| MUNICIPAL CONSTRUCTION, INC |
SUBCONTRACTOR(S) FOR CCSJ: 0134-04-032 DALLAS LITE AND BARRICADE INC. (0.55%) TOTAL HIGHWAY MAINTENANCE, LLC (8.13%)
|
| Contract # |
07083216 |
|
Totals |
1765441.42 |
943050.33 |
1845069.36 |
99.9 |
|
| County | JACK |
| Highway |
US 380 |
| From |
US 281 |
| To |
9TH STREET IN JACKSBORO |
| CSJ |
0134-04-033 |
| Proj ID |
STP 2008(739) |
| Work Type |
MILL AND OVERLAY |
| |
|
11.510 |
2735268.45 |
1473883.00 |
1473883.00 |
53.8 |
| Work Order |
08-19-08 |
| Work Began |
10-07-08 |
| Work Completed |
|
| Time Computed |
09-04-08 |
| Contract Working Days |
55 |
| Addl Days Granted |
0 |
| Working Days Charged |
15 |
| Percent Time Used |
27 |
| Contractor(s) |
| AUSTIN BRIDGE & ROAD, LP |
SUBCONTRACTOR(S) FOR CCSJ: 0134-04-033 TOTAL HIGHWAY MAINTENANCE, LLC (3.33%) DUSTROL, INC. (ROANOKE)(0.68%)
|
| Contract # |
07083215 |
|
Totals |
2735268.45 |
1473883.00 |
1473883.00 |
53.8 |
|
| County | WISE |
| Highway |
US 380 |
| From |
.160 KM EAST OF BU 380 E |
| To |
2.253 KM WEST OF US 81 |
| CSJ |
0134-07-044 |
| Proj ID |
NH 2004(279) |
| Work Type |
GR STRS & SURF TWO ADDL LNS |
| |
|
12.789 |
31486999.99 |
0.00 |
30454655.29 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-13-04 |
| Work Began |
09-13-04 |
| Work Completed |
|
| Time Computed |
09-10-04 |
| Contract Working Days |
518 |
| Addl Days Granted |
137 |
| Working Days Charged |
950 |
| Percent Time Used |
145 |
| Contractor(s) |
| SITE CONCRETE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0134-07-044 AUSTIN BRIDGE & ROAD, LP (9.07%) S & J ELECTRIC (1.07%) STRIPING TECHNOLOGY, INC.(0.57%) RAMBO CONTRACTING, INC.(4.42%) JONA CONTRACTING, INC. (0.34%) DALLAS SWEEPING & CONTRACTORS, L.P.(1.39%) COPPELL CONSTRUCTION CO., INC. (8.72%) C.B. SERVICES, INC.(0.12%) MCRYAN HAULING, INC. (0.90%) C.P.X. TRUCKING, INC.(0.19%) BREDA COMPANY, INC.(0.60%) TEXAS SHAFTS, INC. (1.12%) BROCK PAVING INDUSTRIES, INC. (HUB)(0.03%) W.W. WEBBER INC. (0.15%) SYTCON, L.P. ( 18.51%)
|
| Contract # |
03043201 |
|
Totals |
31486999.99 |
0.00 |
30454655.29 |
99.9 |
|