Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPALO PINTO
Highway US 180
From SW 7TH AVE, EAST
To 0.1 MILE EAST OF FM 1821
CSJ 0008-01-044
Proj ID STP 2008(826)
Work Type MILL, FABRIC UNDERSEAL AND OVERLAY
 
2.757 1854816.47 0.00 0.00 0.0
Work Order 10-09-08
Work Began 00-00-00
Work Completed  
Time Computed 10-25-08
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0008-01-044
DUSTROL, INC. (ROANOKE)(7.50%)
HIGHWAY TECHNOLOGIES (1.41%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.61%)
Contract # 08083018
Totals 1854816.47 0.00 0.00 0.0

CountyPARKER
Highway US 180
From AT BANKHEAD HIGHWAY
To IN WEATHERFORD
CSJ 0008-02-068
Proj ID STP 2008(289)
Work Type TRAFFIC SIGNAL
 
0.100 80000.00 9000.00 80262.60 99.9
Work Order 02-13-08
Work Began 06-10-08
Work Completed  
Time Computed 05-13-08
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 80
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-02-068
ROAD MASTER STRIPING LLC (6.25%)
Contract # 01083016
Totals 80000.00 9000.00 80262.60 99.9

CountyPARKER
Highway IH 20
From FRTG RDS @ FM 1187/FM 3325
To IN PARKER COUNTY
CSJ 0008-03-093
Proj ID CM 2008(737)
Work Type GR, BS, PAVT, SIGNALS, SIGN & STRIPING
 
0.152 885892.60 60798.64 60798.64 6.8
Work Order 09-16-08
Work Began 10-20-08
Work Completed  
Time Computed 10-02-08
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 13
Contractor(s)
J.L. STEEL, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0008-03-093
HIGHWAY TECHNOLOGIES (0.53%)
PEACHTREE CONSTRUCTION, LTD. ( 24.70%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(1.45%)
STRIPING TECHNOLOGY, L.P.(2.18%)
TEXAS SAFE SITE PRODUCTS, LP (0.43%)
BRENDA PRICE TRUCKING(0.29%)
MICA CORPORATION ( 26.26%)
LAYFIELD CONSTRUCTION, INC (0.90%)
DURABLE SPECIALTIES, INC.( 16.78%)
Contract # 08083229
Totals 885892.60 60798.64 60798.64 6.8

CountyTARRANT
Highway BU 287P
From AT MINTON ROAD
To IN SAGINAW
CSJ 0013-10-072
Proj ID STP 2009(084)
Work Type TRAFFIC SIGNAL
 
0.100 86500.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ROADWAY SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0013-10-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11083011
Totals 86500.00 0.00 0.00 0.0

CountyTARRANT
Highway BU 287P
From 400 FT NORTH OF BAILEY-BOSWELL ROAD
To 200 FT SOUTH OF RR BRIDGE
CSJ 0013-10-073
Proj ID NH 2007(440)
Work Type MILL, SHLDER REHAB & HMAC OVERLAY
 
4.906 5073895.15 8858.00 5046882.09 99.4
Work Order 10-12-07
Work Began 03-24-08
Work Completed  
Time Computed 10-28-07
Contract Working Days 105
Addl Days Granted 33
Working Days Charged 138
Percent Time Used 100
Contractor(s)
SUNMOUNT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0013-10-073
BREDA COMPANY, INC.(0.28%)
HIGHWAY TECHNOLOGIES (0.19%)
ODUM SERVICES, L.P.(1.36%)
STOMPER DEMOLITION (0.18%)
STRIPING TECHNOLOGY, L.P.(1.35%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.95%)
THOMAS GRINDING, INC.(0.10%)
RIVER CITY SAVING, LLC (0.73%)
METROPLEX PAVEMENT MARKINGS, LLC (0.05%)
Contract # 09073209
Totals 5073895.15 8858.00 5046882.09 99.4

CountyTARRANT
Highway BU 287P
From AT TINSLEY LANE
To IN TARRANT COUNTY
CSJ 0013-10-074
Proj ID NH 2009(051)
Work Type TRAFFIC SIGNAL INSTALLATION
 
0.100 41869.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BEAN ELECTRICAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0013-10-074
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10083211
Totals 41869.20 0.00 0.00 0.0

CountyTARRANT
Highway BU 287P
From AT PEDEN ROAD
To IN TARRANT COUNTY
CSJ 0013-10-075
Proj ID NH 2009(028)
Work Type TRAFFIC SIGNAL
 
0.100 51207.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-16-08
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REPUBLIC INTELLIGENT TRANSPORTATION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0013-10-075
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09083013
Totals 51207.80 0.00 0.00 0.0

CountyTARRANT
Highway IH 35W
From ALSBURY BLVD1187
To TARRANT COUNTY LINE
CSJ 0014-02-039
Proj ID IM 0355(135)W
Work Type GRADING, DRAINAGE, STRUCTS & PAVEMENT
 
1.545 5476865.80 0.00 5698879.20 99.9
Work Order 02-01-06
Work Began 02-22-06
Work Completed  
Time Computed 02-22-06
Contract Working Days 235
Addl Days Granted 112
Working Days Charged 409
Percent Time Used 117
Contractor(s)
AUI CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0014-02-039
BREDA COMPANY, INC.(0.38%)
CAPROCK SPECIALITY CONTRACTORS (0.29%)
CRAIG OLDEN, INC.(4.09%)
DALLAS LITE AND BARRICADE INC. (0.80%)
MCRYAN HAULING, INC. (0.60%)
DESIGNED TELECOMMUNICATIONS, INC.(3.95%)
EVANS UTILITY GROUP, INC.(0.95%)
FORTSON CONTRACTING, INC.(2.27%)
NORTH TEXAS BOMANITE, INC. (1.17%)
NORTH TEXAS BRIDGE COMPANY, INC. (1.90%)
PREMIER PAVING, LTD( 12.22%)
RAMBO CONTRACTING, INC.(0.78%)
RAYMOND PAINTING, INC. (0.14%)
STRIPING TECHNOLOGY, L.P.(1.99%)
TEX OP CONSTRUCTION, LP(0.65%)
W.W. WEBBER INC. (1.50%)
TEXAS SHAFTS, INC. (0.35%)
UNIVERSAL LIME INC.(0.59%)
APAC-TEXAS, INC. (9.90%)
J.L. STEEL, L.P. (0.06%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(0.03%)
LVI ENVIRONMENTAL SERVICES, INC. (1.45%)
AUSTIN BRIDGE & ROAD, LP (0.26%)
REPUBLIC ELECTRIC(7.17%)
STOMPER DEMOLITION (0.24%)
REX SMITH CONSTRUCTION SERVICES, INC.(0.38%)
ARLINGTON PAVERS, INC. (0.03%)
SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.14%)
EL CALA CONSTRUCTION LLC (0.10%)
Contract # 12053017
Totals 5476865.80 0.00 5698879.20 99.9

CountyTARRANT
Highway IH 35W
From AT FM 1187
To IN FORT WORTH
CSJ 0014-02-041
Proj ID CM 2007(798)
Work Type GRADING, STRUCTURES, DRAINAGE & PAV
 
0.747 8690270.92 849549.35 3141869.20 36.1
Work Order 09-24-07
Work Began 04-15-08
Work Completed  
Time Computed 03-24-08
Contract Working Days 291
Addl Days Granted 0
Working Days Charged 159
Percent Time Used 54
Contractor(s)
W.W. WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0014-02-041
CAPROCK SPECIALITY CONTRACTORS (0.04%)
INDUS CONSTRUCTION, L.P. (2.87%)
INTEGRATED ROADWAY SERVICES, INC.(5.98%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 11.46%)
SCHNABEL FOUNDATION CO. (HOUSTON)(3.68%)
SCOTT DERR PAINTING CO (0.30%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(3.22%)
TEXAS HIGHWAY MARKINGS, LLC(0.09%)
TEXAS SHAFTS, INC. (1.00%)
JLB CONTRACTING, LP(0.08%)
MR. DIRT (0.08%)
RICE TUNNELING & BORING, INC.(0.26%)
Contract # 08073005
Totals 8690270.92 849549.35 3141869.20 36.1

CountyJOHNSON
Highway IH 35W
From BETHESDA ROAD OVER IH 35W
To .
CSJ 0014-03-084
Proj ID BR 2007(610)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.215 2409268.03 0.00 2400045.39 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-08-07
Work Began 08-31-07
Work Completed  
Time Computed 08-24-07
Contract Working Days 198
Addl Days Granted 0
Working Days Charged 229
Percent Time Used 115
Contractor(s)
M. HANNA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0014-03-084
W.W. WEBBER, LLC (3.17%)
PEACHTREE CONSTRUCTION, LTD. ( 10.52%)
STOMPER DEMOLITION (2.61%)
HIGHWAY TECHNOLOGIES, L.P. (2.96%)
TEX OP CONSTRUCTION, LP(0.98%)
PRIMATE CONSTRUCTION, INC. (0.12%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.11%)
S & S BRIDGE PAINTING(0.20%)
STRIPING TECHNOLOGY, L.P.(1.17%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(4.90%)
NORTH TEXAS BRIDGE COMPANY, INC. (2.87%)
Contract # 06073026
Totals 2409268.03 0.00 2400045.39 99.9

CountyJOHNSON
Highway SH 174
From AT SOUTHWEST HULEN STREET
To N BURLESON
CSJ 0019-01-133
Proj ID CC 19-1-133
Work Type TRAFFIC SIGNAL INSTALLATION
 
0.100 57802.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-12-08
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0019-01-133
ACTION SERVICES(2.97%)
Contract # 08083216
Totals 57802.90 0.00 0.00 0.0

CountyJOHNSON
Highway SH 171
From SH 171 AT ELM CREEK
To .
CSJ 0019-02-028
Proj ID BR 2007(677)
Work Type REPLACE CULVERT
 
0.400 3698579.00 230303.12 2413906.21 65.2
Work Order 10-02-07
Work Began 10-29-07
Work Completed  
Time Computed 10-18-07
Contract Working Days 256
Addl Days Granted 0
Working Days Charged 251
Percent Time Used 98
Contractor(s)
AMERICAN CIVIL CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0019-02-028
FORTSON CONTRACTING, INC.(0.98%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.26%)
STRIPING TECHNOLOGY, L.P.(1.14%)
RAMBO CONTRACTING, INC.(3.09%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 13.22%)
J.L. STEEL, L.P. (0.91%)
Contract # 07073026
Totals 3698579.00 230303.12 2413906.21 65.2

CountyERATH
Highway US 67 ETC
From US 281
To FM 988
CSJ 0079-05-050
Proj ID NH 2008(562)
Work Type MILL AND OVERLAY
 
19.511 6340613.75 0.00 0.00 0.0
Work Order 08-15-08
Work Began 00-00-00
Work Completed  
Time Computed 08-31-08
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LINDSEY CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0079-05-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07083005
Totals 6340613.75 0.00 0.00 0.0

CountyERATH
Highway US 377
From US 377 AT PALUXY RIVER
To .
CSJ 0080-02-052
Proj ID BR 2007(644)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 1802913.95 200586.21 826123.40 45.8
Work Order 05-05-08
Work Began 08-04-08
Work Completed  
Time Computed 08-04-08
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 26
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0080-02-052
SAN-ANN-CO., INC.(0.44%)
JAY MILLS CONTRACTING, INCORPORATED( 12.95%)
FOUNDATION DRILLERS, INC.(4.70%)
GUAJARDO STEEL (0.87%)
JONA CONTRACTING, INC. (2.74%)
GARY A. CRAIN, INC.(0.40%)
SCOTT DERR PAINTING CO (0.34%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(2.35%)
PEACHTREE CONSTRUCTION, LTD. ( 12.40%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.05%)
Contract # 03083215
Totals 1802913.95 200586.21 826123.40 45.8

CountyTARRANT
Highway US 377
From APPROX 1.0 MI SOUTH OF DENTON C/L
To KELLER HICKS ROAD
CSJ 0081-02-045
Proj ID STP 2005(34)MM
Work Type GR, DR, ACP, CONC PAV, SIGN & PAV M
 
2.943 12983276.32 249604.36 12769399.26 99.9
Work Order 02-27-06
Work Began 01-25-07
Work Completed  
Time Computed 08-27-06
Contract Working Days 340
Addl Days Granted 112
Working Days Charged 446
Percent Time Used 98
Contractor(s)
SUNMOUNT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0081-02-045
A & A CONSTRUCTION (0.05%)
BREDA COMPANY, INC.(1.01%)
CAPROCK SPECIALITY CONTRACTORS (0.43%)
CEN-TEX SEEDING, INC.(1.85%)
INLET STRUCTURE SPECIALTIES LTD. (3.39%)
L & E HART ENTERPRISES, INC. (0.49%)
MCRYAN HAULING, INC. (2.31%)
MICA CORPORATION (2.99%)
LAYFIELD CONSTRUCTION, INC (0.24%)
DURABLE SPECIALTIES, INC.(1.61%)
MURRAY CONSTRUCTION(0.40%)
NORTH TEXAS CONTRACTING, INC.( 12.23%)
STOMPER DEMOLITION (0.28%)
TEXAS HIGHWAY MARKINGS, LLC(0.98%)
W.W. WEBBER INC. (1.22%)
CRAIG OLDEN, INC.(0.41%)
COWTOWN TRAFFIC CONTROL, INC.(0.87%)
MASTERPIECE GRINDING & GROOVING, LLC (0.19%)
S & S PAINTING (0.24%)
Contract # 12053204
Totals 12983276.32 249604.36 12769399.26 99.9

CountyTARRANT
Highway SH 183
From AT TRIBUTARY TO W FORK TRINITY
To WF-4
CSJ 0094-01-038
Proj ID NH 2008(827)
Work Type GR, DR, AND STR
 
0.037 1800034.85 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J.L. STEEL, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0094-01-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11083208
Totals 1800034.85 0.00 0.00 0.0

CountyTARRANT
Highway SH 183
From SH 199
To BU 287P/NORTH MAIN STREET
CSJ 0094-05-062
Proj ID NH 2008(580)
Work Type MILL, OVERLAY, C & G REPAIR & STRIPING
 
9.704 4535778.92 346210.47 1549194.73 34.1
Work Order 06-10-08
Work Began 08-04-08
Work Completed  
Time Computed 06-26-08
Contract Working Days 96
Addl Days Granted 0
Working Days Charged 70
Percent Time Used 72
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0094-05-062
J.L. STEEL, L.P. ( 15.11%)
DUSTROL, INC. (ROANOKE)(0.17%)
DURABLE SPECIALTIES, INC.(2.74%)
TEX OP CONSTRUCTION, LP(9.01%)
TOTAL HIGHWAY MAINTENANCE, LLC (5.03%)
Contract # 05083204
Totals 4535778.92 346210.47 1549194.73 34.1

CountyJACK
Highway US 380
From 5 LANES SECTION IN JACKSBORO
To YOUNG COUNTY LINE
CSJ 0134-04-032
Proj ID STP 2008(731)
Work Type MICROSURFACE
 
31.740 1728459.31 911591.33 1813610.36 99.9
CountyDENTON
Highway FM 51
From 0.7 MI EAST OF DENTON COUNTY LINE
To WISE/DENTON COUNTY LINE
CSJ 0312-02-014
Proj ID C 312-2-14
Work Type MICROSURFACING
 
0.700 36982.11 31459.00 31459.00 85.0
Work Order 08-15-08
Work Began 08-31-08
Work Completed  
Time Computed 08-31-08
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 49
Contractor(s)
MUNICIPAL CONSTRUCTION, INC
SUBCONTRACTOR(S) FOR CCSJ: 0134-04-032
DALLAS LITE AND BARRICADE INC. (0.55%)
TOTAL HIGHWAY MAINTENANCE, LLC (8.13%)
Contract # 07083216
Totals 1765441.42 943050.33 1845069.36 99.9

CountyJACK
Highway US 380
From US 281
To 9TH STREET IN JACKSBORO
CSJ 0134-04-033
Proj ID STP 2008(739)
Work Type MILL AND OVERLAY
 
11.510 2735268.45 1473883.00 1473883.00 53.8
Work Order 08-19-08
Work Began 10-07-08
Work Completed  
Time Computed 09-04-08
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 27
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0134-04-033
TOTAL HIGHWAY MAINTENANCE, LLC (3.33%)
DUSTROL, INC. (ROANOKE)(0.68%)
Contract # 07083215
Totals 2735268.45 1473883.00 1473883.00 53.8

CountyWISE
Highway US 380
From .160 KM EAST OF BU 380 E
To 2.253 KM WEST OF US 81
CSJ 0134-07-044
Proj ID NH 2004(279)
Work Type GR STRS & SURF TWO ADDL LNS
 
12.789 31486999.99 0.00 30454655.29 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-13-04
Work Began 09-13-04
Work Completed  
Time Computed 09-10-04
Contract Working Days 518
Addl Days Granted 137
Working Days Charged 950
Percent Time Used 145
Contractor(s)
SITE CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0134-07-044
AUSTIN BRIDGE & ROAD, LP (9.07%)
S & J ELECTRIC (1.07%)
STRIPING TECHNOLOGY, INC.(0.57%)
RAMBO CONTRACTING, INC.(4.42%)
JONA CONTRACTING, INC. (0.34%)
DALLAS SWEEPING & CONTRACTORS, L.P.(1.39%)
COPPELL CONSTRUCTION CO., INC. (8.72%)
C.B. SERVICES, INC.(0.12%)
MCRYAN HAULING, INC. (0.90%)
C.P.X. TRUCKING, INC.(0.19%)
BREDA COMPANY, INC.(0.60%)
TEXAS SHAFTS, INC. (1.12%)
BROCK PAVING INDUSTRIES, INC. (HUB)(0.03%)
W.W. WEBBER INC. (0.15%)
SYTCON, L.P. ( 18.51%)
Contract # 03043201
Totals 31486999.99 0.00 30454655.29 99.9