Downtown Segment (Martin Luther King Jr. Boulevard to Holly Street)
I-35 Capital Express Central Project
The project will add two high-occupancy-vehicle (HOV) managed lanes in both directions along I-35. In addition, the project will build a new frontage road boulevard through downtown, reconstruct east-west crossings at: Cesar Chavez, 4th, 5th, 6th, 7th, 11th, 12th and 15th streets and construct pedestrian-only bridges at 3rd, 4th and 15th streets.
Funding
- Estimated construction cost: $1.5 billion funded by TxDOT and CAMPO
Schedule
- Anticipated construction start: Late 2027
- Anticipated construction completion: 2032, weather permitting
Contractor
- TBD