Monthly State Let Construction Report For Houston District As Of Jun 08, 2018 Page 5 Of 10

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGALVESTON
HighwayIH 45
From0.452 MI S. OF FM 518
ToN OF FM 517
CSJ0500-04-096
Proj IDC 500-4-96
Work TypeGR,WIDEN STRS, BASE & PAVEMENT
 
3.394121744991.3449587832.4540.7
Work Order10-28-16
Work Began11-14-16
Work Completed
Time Computed11-27-16
Contract Working Days1,234
Addl Days Granted0
Working Days Charged439
Percent Time Used35
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-04-096
A & A CONSTRUCTION (0.23)
BASE CONSTRUCTION (10.83)
ESSARY, HART & MACWILIAM,INC. (0.76)
GEORGE MEEKS LANDPRO, INC. (2.00)
HAYWARD BAKER, INC. (1.18)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.19)
INTERSTATE BARRICADES & MARKINGS, INC. (1.33)
SCOTT DERR PAINTING CO, LLC (0.02)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.74)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.44)
BORTUNCO (0.38)
Contract #10163201
Totals121744991.342040410.6149587832.4540.7

CountyGALVESTON
HighwayIH 45
FromN OF FM 517
ToS OF FM 1764
CSJ0500-04-106
Proj IDNH 2018(963)
Work TypeGR, WIDEN STRS, BASE & PAVEMENT
 
5.070228823555.410.000.0
CountyGALVESTON
HighwayIH 45
FromN OF FM 517
ToS OF FM 1764
CSJ0500-04-136
Proj IDROW 500-4-136
Work TypeROW ACQUISITION
 
0.0011653965.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days1,288
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-04-106
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183001
Totals230477520.510.000.000.0

CountyGALVESTON
HighwayIH 45
FromSH 6
ToGALVESTON/HARRIS COUNTY LINE
CSJ0500-04-134
Proj IDNH 1502(605)
Work TypeLANDSCAPE DEVELOPMENT
 
48.838960543.571241379.6099.9
Work Order10-19-15
Work Began01-19-16
Work Completed
Time Computed01-17-16
Contract Working Days45
Addl Days Granted52
Working Days Charged67
Percent Time Used69
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-04-134
G & A BORING (0.90)
Contract #08153221
Totals960543.57156.631241379.6099.9

CountyHARRIS
HighwaySH 225
FromBW 8
ToTIDAL RD
CSJ0502-01-210
Proj IDNH 2016(060)
Work TypeREHAB BRIDGE
 
3.1602602026.602790327.7099.9
Work Order01-29-16
Work Began04-09-16
Work Completed
Time Computed02-29-16
Contract Working Days45
Addl Days Granted18
Working Days Charged92
Percent Time Used146
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-210
CHERRY CRUSHED CONCRETE (1.87)
PRIMATE CONSTRUCTION, INC. (2.39)
LONE STAR TRAFFIC SERVICE, INC. (0.82)
BATTERSON,LLP (5.53)
BREDA COMPANY, INC. (2.39)
GMJ PAVING CO. (2.15)
WEBBER BARRIER SERVICES, LLC. (0.93)
BOSWELL CONSTRUCTION COMPANY (0.61)
Contract #10153226
Totals2602026.600.002790327.7099.9

CountyHARRIS
HighwaySH 225
FromGOODYEAR
ToBW 8 (ON EB FRONTAGE ROAD ONLY)
CSJ0502-01-212
Proj IDNH 2016(415)
Work TypeDRAINAGE IMPROVEMENTS IN SECTIONS
 
0.571992122.00951658.2896.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-13-17
Work Began03-27-17
Work Completed
Time Computed03-01-18
Contract Working Days75
Addl Days Granted0
Working Days Charged83
Percent Time Used110
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-212
BATTERSON,LLP (2.61)
IPR SOUTH CENTRAL LLC (4.78)
A-1 EROSION CONTROL, LLC (0.24)
Contract #11163225
Totals992122.000.00951658.2896.4

CountyHARRIS
HighwaySH 225
FromEB & WB FRONTAGE ROADS, RED BLUFF
ToBW 8
CSJ0502-01-213
Proj IDNH 2017(821)
Work TypeASPHALT O/L W/PV MKS
 
2.6551494920.901622577.4599.9
Work Order03-10-17
Work Began06-28-17
Work Completed
Time Computed05-09-17
Contract Working Days33
Addl Days Granted9
Working Days Charged43
Percent Time Used102
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-213
MAIN LANE INDUSTRIES LTD. (8.04)
THIRD COAST SERVICES LLC (7.03)
STRIPE LINES, INC. (5.37)
HOLES INCORPORATED (0.73)
Contract #02173221
Totals1494920.90161.761622577.4599.9

CountyHARRIS
HighwaySH 225
FromBW 8
ToBATTLEGROUND ROAD
CSJ0502-01-214
Proj IDNH 2018(665)
Work TypeUPGRADE ILLUMINATION
 
3.6602743513.010.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days220
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CREACOM, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-214
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183039
Totals2743513.010.000.000.0

CountyHARRIS
HighwaySH 225
FromIH 610
ToSH 146
CSJ0502-01-220
Proj IDNH 1702(514)
Work TypeLANDSCAPING
 
15.912988674.86968923.8598.0
Work Order08-16-17
Work Began10-24-17
Work Completed
Time Computed09-15-17
Contract Working Days105
Addl Days Granted0
Working Days Charged105
Percent Time Used100
Contractor(s)
TEXAS WALL & LANDSCAPE
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-220
FERTILE EARTH (1.19)
Contract #07173240
Totals988674.86441295.92968923.8598.0

CountyHARRIS
HighwayIH 10
FromCROSBY-LYNCHBURG ROAD
ToGARTH ROAD
CSJ0508-01-034
Proj IDIM 0107(443)
Work TypeINSTALL CTMS
 
4.7352122122.802323826.2099.9
Work Order06-23-14
Work Began03-11-15
Work Completed
Time Computed12-19-14
Contract Working Days312
Addl Days Granted0
Working Days Charged303
Percent Time Used97
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-034
JMHP, INC. (4.78)
BAY CITY TRAFFIC (1.61)
Contract #04143024
Totals2122122.800.002323826.2099.9

CountyHARRIS
HighwayIH 10
FromIH 45
ToCHAMBERS COUNTY LINE
CSJ0508-01-344
Proj IDIM 0107(445)
Work TypeLANDSCAPE DEVELOPMENT
 
0.0011351369.791370236.7399.9
Work Order07-02-14
Work Began09-04-14
Work Completed
Time Computed09-04-14
Contract Working Days90
Addl Days Granted0
Working Days Charged76
Percent Time Used84
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-344
N-LINE TRAFFIC MAINTENANCE, L.P. (0.68)
ENVIRONMENTAL ALLIES, L.P. (1.26)
Contract #04143020
Totals1351369.790.001370236.7399.9

CountyHARRIS
HighwayIH 10
FromFREEPORT ST
ToBW 8
CSJ0508-01-346
Proj IDNH 1702(180)
Work TypeSPALL REP, FULL DEPTH REP, O/L,STRP
 
8.62214771556.1411052663.5874.8
Work Order07-20-17
Work Began11-01-17
Work Completed
Time Computed08-21-17
Contract Working Days201
Addl Days Granted0
Working Days Charged116
Percent Time Used57
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-346
BATTERSON,LLP (1.76)
CAPSTONE TRUCKING (1.58)
MAIN LANE INDUSTRIES LTD. (15.55)
SOUTH TEXAS PAINTING COMPANY (0.32)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (13.42)
WILLOW CITY SIGN & RAIL, INC. (1.39)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.13)
MB WESTERN INDUSTRIAL CONTRACTING (4.08)
JMHP, INC. (0.07)
HOLES INCORPORATED (1.98)
Contract #06173004
Totals14771556.141992791.4211052663.5874.8

CountyHARRIS
HighwayIH 10
FromON ELYSIAN ST: FROM COMMERCE ST
ToHARRINGTON STREET
CSJ0508-01-351
Proj IDC 508-1-351
Work TypeREPLACE BRIDGE AND APPROACHES
 
1.20435654481.3117052969.3047.8
Work Order08-23-16
Work Began01-20-17
Work Completed
Time Computed11-21-16
Contract Working Days809
Addl Days Granted2
Working Days Charged230
Percent Time Used28
Contractor(s)
BALFOUR BEATTY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-351
PROFESSIONAL TRAFFIC CONTROL, LLC (0.10)
YELLOWSTONE LANDSCAPE - CENTRAL, INC. (0.98)
GMJ PAVING CO. (0.48)
THIRD COAST SERVICES LLC (1.32)
ROYAL REBAR (7.84)
RDI FOUNDATION DRILLING (9.30)
WILLOW CITY SIGN & RAIL, INC. (0.16)
SCOTT DERR PAINTING CO, LLC (0.36)
STATEWIDE SERVICES, INC (2.58)
HOUSTON SAWING & DRILLING (0.09)
CHOCTAW ERECTORS, INC. (1.94)
CURB PLANET INC. (0.01)
UNDER CONSTRUCTION INC. (0.40)
MAK FENCING (0.11)
Contract #06163002
Totals35654481.311641437.7917052969.3047.8

CountyHARRIS
HighwayIH 10
FromGARTH ROAD
ToCHAMBERS C/L
CSJ0508-01-356
Proj IDNH 2018(760)
Work TypeINSTALL ITS EQUIPMENT & INFRASTRCTR
 
8.0304844982.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days450
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-356
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183019
Totals4844982.300.000.000.0

CountyHARRIS
HighwayIH 10
FromIH 45
ToCHAMBERS COUNTY LINE
CSJ0508-01-360
Proj IDNH 1702(516)
Work TypeLANDSCAPING
 
31.773593718.07227250.1238.2
Work Order10-16-17
Work Began11-27-17
Work Completed
Time Computed11-15-17
Contract Working Days45
Addl Days Granted0
Working Days Charged45
Percent Time Used100
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-360
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09173027
Totals593718.071252.09227250.1238.2

CountyWALLER
HighwayFM 1098
FromUS 290
ToOWENS ROAD
CSJ0523-01-030
Proj IDCC 523-1-30
Work TypeTRANSPORTATION & ACCESS MANAGEMENT
 
0.491750614.45202150.0026.9
Work Order03-15-18
Work Began05-22-18
Work Completed
Time Computed04-14-18
Contract Working Days61
Addl Days Granted0
Working Days Charged4
Percent Time Used6
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0523-01-030
REPUBLIC TRAFFIC SAFETY, INC. (2.09)
AGGREGATE TECHNOLOGIES, INC. (2.76)
PFEIFFER & SON LTD. (16.25)
CHERRY CONCRETE REMOVAL (2.58)
OASIS LANDSCAPE CO. (28.40)
Contract #01183211
Totals750614.45202150.00202150.0026.9

CountyMONTGOMERY
HighwayFM 1488
FromFM 149
To0.3 MI E OF COMMUNITY RD AT MOSTYN
CSJ0523-10-034
Proj IDC 523-10-34
Work TypeCONSTRUCT RR GRADE SEPARATION
 
2.77927649979.1127306620.9199.3
Work Order10-22-13
Work Began02-16-15
Work Completed
Time Computed07-19-14
Contract Working Days478
Addl Days Granted40
Working Days Charged579
Percent Time Used111
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0523-10-034
PROFESSIONAL TRAFFIC CONTROL, LLC (1.11)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.67)
EUBANK EXCAVATION, L.L.C. (0.76)
BREDA COMPANY, INC. (1.41)
WILLOW CITY SIGN & RAIL, INC. (0.51)
GMJ PAVING CO. (5.71)
RDI FOUNDATION DRILLING (4.28)
HOUSTON SAWING & DRILLING (0.04)
TEX OP CONSTRUCTION, LP (0.60)
SCOTT DERR PAINTING CO (0.13)
NORTHWEST MATERIALS (0.25)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.27)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.15)
CREACOM, INC. (1.18)
VALLEY PLACERS, LLC (0.27)
APCON SERVICES, LLC (0.00)
FORDE CONSTRUCTION COMPANY, INC. (0.19)
CEN TEX HYDROSEED, INC. (0.42)
B & R WATER WELL SERVICES, LLC (0.01)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.13)
C PAVE, INC. (0.06)
WALKER GRASS & FARMS (2.73)
Contract #07133003
Totals27649979.11505042.7327306620.9199.3

CountyFORT BEND
HighwayFM 359
FromAT US 90A AND UPRR
To.
CSJ0543-02-055
Proj IDSTP 2013(734)RGS
Work TypeRR GRADE SEPARATION
 
0.40827124547.7723601189.5187.0
Work Order07-22-15
Work Began06-13-16
Work Completed
Time Computed01-19-16
Contract Working Days482
Addl Days Granted0
Working Days Charged411
Percent Time Used85
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0543-02-055
BUYERS BARRICADES, INC. (0.22)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.95)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.36)
PRIMATE CONSTRUCTION, INC. (0.12)
JAMES CONSTRUCTION GROUP, L.L.C. (8.77)
SCOTT DERR PAINTING CO, LLC (0.30)
CHERRY CRUSHED CONCRETE (0.21)
HOUSTON SAWING & DRILLING (0.04)
W. W. FOUNDATION DRILLING, LTD. (4.51)
WILLOW CITY SIGN & RAIL, INC. (1.06)
ROYAL REBAR (4.06)
MTAM CORPORATION (0.05)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.87)
CURB PLANET INC. (0.06)
DAVEY TREE & LAWN CARE (0.21)
Contract #05153205
Totals27124547.77729358.3623601189.5187.0

CountyFORT BEND
HighwayFM 762
FromFM 762/FM 2759
ToS OF LCISD SCHOOL ON CRABB RIVER RD
CSJ0543-03-067
Proj IDSTP 2018(416)MM
Work TypeGR, STRS, BASE AND PAVE
 
2.97630289272.410.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days583
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0543-03-067
BREDA COMPANY, INC. (0.87)
CURB PLANET INC. (0.07)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.18)
JB PINNACLE GROUP, LLC (4.16)
SPEEDY PAVING (1.04)
W. W. FOUNDATION DRILLING, LTD. (0.74)
WEBBER BARRIER SERVICES, LLC. (0.17)
SOUTHERN CRUSHED CONCRETE LLC (0.07)
SCOTT DERR PAINTING CO, LLC (0.06)
Contract #01183201
Totals30289272.410.000.000.0

CountyFORT BEND
HighwayFM 762
From1.524 MI. SOUTH OF BRIDLEWOOD DRIVE
ToFM 1462
CSJ0543-03-072
Proj IDSTP 2017(822)
Work TypeBASE REPAIR AND OVERLAY
 
13.9211849419.982527641.7099.9
Work Order04-24-17
Work Began07-17-17
Work Completed
Time Computed06-23-17
Contract Working Days75
Addl Days Granted5
Working Days Charged96
Percent Time Used120
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0543-03-072
WEST TEXAS RUMBLE STRIP (0.51)
DUSTROL, INC. (5.60)
WILLOW CITY SIGN & RAIL, INC. (4.92)
ROADSAFE TRAFFIC SYSTEMS, INC. (5.60)
PROFESSIONAL TRAFFIC CONTROL, LLC (5.60)
Contract #03173019
Totals1849419.98195393.352527641.7099.9

CountyBRAZORIA
HighwaySH 332
From0.102 MILES EAST OF LEVEE ROAD
To.
CSJ0586-01-065
Proj IDSTP 2017(823)
Work TypeREMOV & REPL DRAINS STR
 
0.024272166.3294243.3434.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-17
Work Began10-30-17
Work Completed
Time Computed05-24-17
Contract Working Days54
Addl Days Granted0
Working Days Charged51
Percent Time Used94
Contractor(s)
OPPORTUNITY EXCAVATION/CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0586-01-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173020
Totals272166.320.0094243.3434.6

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10