Monthly State Let Construction Report For Houston District As Of Aug 16, 2018 Page 10 Of 11

Last Update: Thursday, August 16, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBRAZORIA
HighwaySH 288
FromAT SH 332 AND AT BS 288B
To.
CSJ1524-01-082
Proj IDNH 2018(419)
Work TypeREMOV & REPL CONC PV
 
1.64013895724.7568880.000.4
Work Order02-14-18
Work Began00-00-00
Work Completed
Time Computed04-15-18
Contract Working Days371
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1524-01-082
MESA ROD BUSTERS, INC. (1.63)
NORWEST SERVICES, LLC (0.61)
DURWOOD GREENE CONSTRUCTION CO. (4.34)
ANTIGO CONSTRUCTION, INC. (0.71)
A-1 EROSION CONTROL, LLC (0.91)
RAY"S THREADING AND FAB SHOP (0.62)
VERNOR MATERIAL & EQUIPMENT CO., INC. (6.06)
ROMAR UNLIMITED, INC. (1.74)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.77)
HAYDEN PAVING, INC. (2.03)
Contract #01183204
Totals13895724.754080.0068880.000.4

CountyHARRIS
HighwayFM 1960
FromAT PERRY ROAD
To.
CSJ1685-01-106
Proj IDSTP 1602(485)HES
Work TypeIMPRV TS
 
0.600647884.36644600.8799.4
Work Order12-07-16
Work Began04-19-17
Work Completed
Time Computed04-06-17
Contract Working Days91
Addl Days Granted0
Working Days Charged82
Percent Time Used90
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1685-01-106
SPECIALTY DRILLING (3.65)
SPRING CREEK CONSTRUCTION, INC. (13.50)
REPUBLIC TRAFFIC SAFETY, INC. (3.92)
Contract #10163205
Totals647884.360.00644600.8799.4

CountyHARRIS
HighwayFM 1960
FromIH 45
To6.5 MI E OF IH 45 (HUMBLE BYPASS)
CSJ1685-02-049
Proj IDNH 2013(064)
Work TypePAVEMENT MARKINGS
 
14.553546380.10517139.2495.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-18-12
Work Began11-18-12
Work Completed
Time Computed11-03-12
Contract Working Days120
Addl Days Granted79
Working Days Charged209
Percent Time Used105
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 1685-02-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09123024
Totals546380.100.00517139.2495.7

CountyHARRIS
HighwaySH 6
FromPINE FOREST LANE
To0.5 MILES NORTH OF IH 10
CSJ1685-05-108
Proj IDSTP 2017(639)HES
Work TypeSAFETY LIGHTING
 
2.9182492972.100.000.0
Work Order02-14-18
Work Began00-00-00
Work Completed
Time Computed05-15-18
Contract Working Days525
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1685-05-108
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183023
Totals2492972.100.000.000.0

CountyHARRIS
HighwaySH 6
FromVARIOUS LOCATIONS IN FORT BEND AND
ToHARRIS COUNTIES
CSJ1685-05-118
Proj IDNH 1802(411)
Work TypeADA CURB RAMPS AND SIDEWALKS
 
5.3362270623.450.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-15-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days105
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MBN ENTERPRISES LLC
SUBCONTRACTOR(S) FOR CCSJ: 1685-05-118
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183227
Totals2270623.450.000.000.0

CountyHARRIS
HighwayBF1960A
FromFM 1960 W OF LEE RD
ToFM 1960 E OF HUMBLE
CSJ1685-07-005
Proj IDC 1685-7-5
Work TypeIMPLEMENT ACCESS MANAGEMENT
 
3.9206976168.046964475.9499.8
CountyHARRIS
HighwayBF1960A
FromLEE ROAD
ToFM 1960(E)
CSJ1685-07-019
Proj IDSTP 2013(994)
Work TypeBS REP, MILL, SC INTERLAYER, OL,ETC
 
4.2006317731.977389486.1999.9
Work Order09-30-14
Work Began11-10-14
Work Completed
Time Computed11-10-14
Contract Working Days270
Addl Days Granted118
Working Days Charged382
Percent Time Used98
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1685-07-005
ANGEL BROTHERS ENTERPRISES, LTD. (27.60)
KOSSMAN CONTRACTING CO., INC. (1.14)
REGIONAL TRAFFIC SERVICES LLC (0.84)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.49)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (12.57)
H & E AGGREGATE, LLC (3.50)
SCMU (3.02)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.48)
AGGREGATE TECHNOLOGIES, INC. (0.39)
SEMARCK LANDSCAPE SERVICES, INC. (1.14)
GULF COAST PAVERS, INC. (0.21)
PEREZ CONSTRUCTION CO. (0.32)
MCA COMMUNICATIONS, INC. (1.56)
SEAMARCK LANDSCAPE SERVICES, INC (1.14)
A-1 EROSION CONTROL, LLC (0.03)
Contract #08133014
Totals13293900.0130496.7814353962.1399.9

CountyMONTGOMERY
HighwayFM 1097
FromEND OF STATE MAINTENANCE
ToFM 149
CSJ1706-03-008
Proj IDSTP 2017(115)
Work TypeBS REPR, OCST, 1.5" OL & ADD SHLDR
 
6.2575759460.115647163.0598.0
Work Order11-15-16
Work Began02-13-17
Work Completed
Time Computed02-13-17
Contract Working Days113
Addl Days Granted0
Working Days Charged96
Percent Time Used84
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1706-03-008
WILLOW CITY SIGN & RAIL, INC. (0.66)
DUSTROL, INC. (2.00)
CEN TEX HYDROSEED, INC. (6.16)
TEXAS LAND CLEARING SERVICE (3.64)
WATERS CONSTRUCTION COMPANY, INC., BOB (3.57)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.73)
J & M CONTRACTING, COMPANY (9.58)
Contract #09163029
Totals5759460.110.005647163.0598.0

CountyFORT BEND
HighwayFM 1994
FromSH 36
ToFM 361
CSJ1965-01-006
Proj IDSTP 2017(640)
Work TypeBASE REPAIR AND OVERLAY
 
7.5821774560.912302854.5699.9
Work Order03-08-17
Work Began06-05-17
Work Completed
Time Computed05-07-17
Contract Working Days45
Addl Days Granted0
Working Days Charged43
Percent Time Used95
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1965-01-006
BATTERSON,LLP (3.42)
THIRD COAST SERVICES LLC (0.93)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.83)
WEST TEXAS RUMBLE STRIP (0.21)
Contract #02173038
Totals1774560.910.002302854.5699.9

CountyMONTGOMERY
HighwayFM 1314
FromSH 105
ToSL 336
CSJ1986-01-063
Proj IDC 1986-1-63
Work TypeBASE REPAIR, OCST, LEVEL UP, OV
 
2.2141738187.360.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1986-01-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183225
Totals1738187.360.000.000.0

CountyFORT BEND
HighwayFM 2234
FromFORT BEND PARKWAY
ToFM 521
CSJ2105-01-020
Proj IDSTP 1402(122)
Work TypeGR, STRS, BS & SURF
 
4.06831094829.5517037750.1354.7
Work Order06-19-15
Work Began08-15-16
Work Completed
Time Computed07-05-15
Contract Working Days506
Addl Days Granted253
Working Days Charged492
Percent Time Used64
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2105-01-020
WILLOW CITY SIGN & RAIL, INC. (0.31)
STRIPE-A-LINE, INC. (0.71)
CREACOM, INC. (3.43)
MESA ROD BUSTERS, INC. (6.42)
ROADWAY CONSTRUCTION, LLC (2.94)
EROSION PREVENTION PRODUCTS (0.22)
QUALITY TURF FARMS, LC (2.30)
THELIN RECYCLING COMPANY, L.P. (0.37)
BORTUNCO (1.65)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.32)
Contract #05153204
Totals31094829.55616767.8417037750.1354.7

CountyMONTGOMERY
HighwayFM 2854
FromLP 336
ToIH 45
CSJ2744-01-011
Proj IDSTP 1702(640)MM
Work TypeGR, STRS, BASE AND PAVE
 
2.14018657275.420.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-02-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days448
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 2744-01-011
A-1 EROSION CONTROL, LLC (1.19)
C PAVE, INC. (0.22)
DOUBLE OAK CONSTRUCTION, INC. (0.63)
FOSTER FENCE, LTD. (0.25)
GMJ PAVING CO. (3.81)
HIGHWAY 1 LLC (0.03)
MESA ROD BUSTERS, INC. (0.00)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.71)
Contract #03183201
Totals18657275.420.000.000.0

CountyBRAZORIA
HighwayFM 2917
FromSH 35
ToFM 2004
CSJ2938-02-022
Proj IDC 2938-2-22
Work TypePVMT REPAIR, SC & ACP OVERLAY
 
9.3812791368.680.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days109
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 2938-02-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183009
Totals2791368.680.000.000.0

CountyMONTGOMERY
HighwayFM 2978
FromFM 1488
ToS OF DRY CREEK
CSJ3050-02-024
Proj IDSTP 2016(119)MM
Work TypeGR, STRS, BASE AND PAVE
 
4.07015788778.29703011.304.4
Work Order04-19-16
Work Began00-00-00
Work Completed
Time Computed06-18-16
Contract Working Days457
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 3050-02-024
MESA ROD BUSTERS, INC. (1.21)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.00)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.10)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.81)
WILLOW CITY SIGN & RAIL, INC. (0.55)
THIRD COAST SERVICES LLC (0.00)
Contract #02163202
Totals15788778.290.00703011.304.4

CountyMONTGOMERY
HighwayFM 2978
FromS OF DRY CREEK
ToCONROE HUFFSMITH
CSJ3050-02-025
Proj IDC 3050-2-25
Work TypeGR, STRS, BASE AND PAVE
 
2.4628195982.093410354.6641.6
Work Order01-29-16
Work Began03-15-16
Work Completed
Time Computed02-29-16
Contract Working Days276
Addl Days Granted17
Working Days Charged121
Percent Time Used41
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3050-02-025
THIRD COAST SERVICES LLC (2.84)
K4 ENVIRONMENTAL LLC (3.19)
LONESTAR TRAFFIC SAFETY, LLC (0.50)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.97)
ROADWAY CONSTRUCTION, LLC (0.30)
JMHP, INC. (0.86)
Contract #12153035
Totals8195982.09275710.083410354.6641.6

CountyHARRIS
HighwayFM 2978
FromAT SPRING CREEK
To.
CSJ3050-03-021
Proj IDSTP 1802(218)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.4347552754.420.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-17-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days230
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 3050-03-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183032
Totals7552754.420.000.000.0

CountyMONTGOMERY
HighwayFM 3083
FromAT UPRR
To.
CSJ3158-01-031
Proj IDC 3158-1-31
Work TypeCONSTRUCT GRADE SEPARATION
 
0.70513080676.417973034.9761.6
Work Order09-11-15
Work Began07-05-16
Work Completed
Time Computed06-07-16
Contract Working Days378
Addl Days Granted0
Working Days Charged452
Percent Time Used119
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3158-01-031
ROADSAFE TRAFFIC SYSTEMS, INC. (0.33)
J & M CONTRACTING, COMPANY (6.16)
WILLOW CITY SIGN & RAIL, INC. (0.94)
CENTEX HYDROSEED (1.70)
EROSION PREVENTION PRODUCTS (0.48)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.51)
MESA ROD BUSTERS, INC. (0.34)
DORAN STEEL, INC. (0.22)
WEBBER BARRIER SERVICES, LLC. (1.01)
PRIMATE CONSTRUCTION, INC. (0.13)
Contract #07143209
Totals13080676.41299501.557973034.9761.6

CountyMONTGOMERY
HighwayFM 3083
FromEAST OF UPRR
ToLP 336 NORTH
CSJ3158-01-032
Proj IDSTP 1802(609)
Work TypeWIDEN TO 4-LANE DIVIDED URBAN
 
1.8189047341.210.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days170
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3158-01-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08183228
Totals9047341.210.000.000.0

CountyHARRIS
HighwaySH 99
FromBS 146 EAST (SEGMENT 1-2)
ToCHAMBERS COUNTY LINE
CSJ3187-01-005
Proj IDC 3187-1-5
Work TypeCONSTRUCT TWO 2-LN FRONTAGE ROADS
 
3.10135161387.5437724482.9599.9
Work Order10-17-14
Work Began08-31-15
Work Completed
Time Computed11-02-14
Contract Working Days486
Addl Days Granted259
Working Days Charged736
Percent Time Used98
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3187-01-005
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.38)
TEXAS ENVIRONMENTAL MANAGEMENT, INC (2.19)
SOUTHERN CRUSHED CONCRETE LLC (1.13)
WILLOW CITY SIGN & RAIL, INC. (1.28)
PRIMATE CONSTRUCTION, INC. (0.19)
WEBBER BARRIER SERVICES, LLC. (0.28)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (0.87)
CHOCTAW ERECTORS, INC. (2.04)
MESA ROD BUSTERS, INC. (0.78)
MBN ENTERPRISES LLC (1.64)
SCOTT DERR PAINTING CO, LLC (0.20)
GMJ PAVING CO. (4.60)
A. H. BECK FOUNDATION CO., INC. (2.29)
JCF BRIDGE & CONCRETE, INC. (2.18)
PROFFESSIONAL TRAFFIC CONTROL, LLC. (0.41)
TEXAS FENCE, INC. (0.09)
TROY ATKINSON (0.04)
TEXAS REEXCAVATION (0.11)
E & R WELDING (0.18)
(OLD PRIME)BORING & TUNNELING COMPANY OF AMERICA, INC. (0.37)
Contract #07143003
Totals35161387.542604486.2137724482.9599.9

CountyHARRIS
HighwaySL 8
FromSOUTH GARDEN STREET
ToIH 69 (EB & WB FRNTG RDS ONLY)
CSJ3256-01-105
Proj IDNH 2017(784)
Work TypeFULL DPTH REP, PLN,SC,TOM,PV MK &TS
 
2.7003448134.333974490.0499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-08-17
Work Began07-05-17
Work Completed
Time Computed07-08-17
Contract Working Days80
Addl Days Granted0
Working Days Charged79
Percent Time Used98
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 3256-01-105
INTERSTATE BARRICADES & MARKINGS, INC. (0.37)
ISI CONTRACTING, INC. (17.12)
BATTERSON,LLP (3.22)
COX PAVING OF TEXAS, INC. (5.11)
TEXOP CONSTRUCTION (19.18)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (1.44)
THIRD COAST SERVICES LLC (9.85)
Contract #05173240
Totals3448134.330.003974490.0499.9

CountyHARRIS
HighwaySL 8
FromWEST AIRPORT BLVD
ToWESTPARK
CSJ3256-01-106
Proj IDHP 1502(450)
Work TypeLANDSCAPE DEVELOPMENT
 
5.660875730.77854259.8297.5
Work Order11-02-15
Work Began06-20-16
Work Completed
Time Computed01-31-16
Contract Working Days90
Addl Days Granted0
Working Days Charged85
Percent Time Used94
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3256-01-106
R & A BORING COMPANY (1.41)
MICKIE SERVICE, INC. (2.11)
Contract #07153020
Totals875730.772672.45854259.8297.5

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11