Monthly State Let Construction Report For Houston District As Of Aug 16, 2018 Page 3 Of 11

Last Update: Thursday, August 16, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayIH 69
FromLITTLE YORK ROAD
ToFM 1960
CSJ0177-07-112
Proj IDNH 1702(628)
Work TypeLANDSCAPING
 
16.785598752.64364277.1760.8
Work Order09-18-17
Work Began12-04-17
Work Completed
Time Computed10-18-17
Contract Working Days60
Addl Days Granted0
Working Days Charged58
Percent Time Used96
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0177-07-112
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173025
Totals598752.641670.02364277.1760.8

CountyHARRIS
HighwayIH 69
FromIH 69 SOUTHBOUND
ToIH 10 EASTBOUND CONNECTOR
CSJ0177-11-154
Proj IDSTP 1802(608)HES
Work TypeHFST
 
0.265248819.100.000.0
CountyHARRIS
HighwayIH 610
FromN. BRAESWOOD BLVD
ToWESTPARK DR (FRONTAGE ROADS)
CSJ0271-17-164
Proj IDC 271-17-164
Work TypePLANING, SEAL COAT, O/L
 
3.0002358320.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days110
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0177-11-154
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08183047
Totals2607139.850.000.000.0

CountyMONTGOMERY
HighwaySL 494
FromN OF KINGWOOD DR
ToHARRIS C/L
CSJ0177-14-010
Proj IDSTP 1802(602)
Work TypeWDN GR, STRS, BS & PAV
 
1.83514347428.730.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days384
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0177-14-010
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08183010
Totals14347428.730.000.000.0

CountyHARRIS
HighwaySH 35
FromIH 610
ToAIRPORT
CSJ0178-01-036
Proj IDNH 2018(659)
Work TypeCONC REPR,MILL,SC,1"(TOM)OL&PAV MRK
 
2.7851495895.221276882.8885.3
Work Order04-13-18
Work Began06-24-18
Work Completed
Time Computed06-12-18
Contract Working Days60
Addl Days Granted0
Working Days Charged29
Percent Time Used48
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0178-01-036
THIRD COAST SERVICES LLC (4.28)
HIGHWAY 1 LLC (4.94)
PROFESSIONAL TRAFFIC CONTROL, LLC (6.39)
MAIN LANE INDUSTRIES LTD. (1.42)
Contract #03183222
Totals1495895.221170658.421276882.8885.3

CountyBRAZORIA
HighwaySH 35
FromBS 35C
ToSH 6
CSJ0178-02-089
Proj IDC 178-2-89
Work TypeDIAMOND GRINDING & O/L
 
4.9334772337.960.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days145
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DIAMOND SURFACE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0178-02-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183033
Totals4772337.960.000.000.0

CountyBRAZORIA
HighwayFM 523
FromAT CAMPUS DRIVE
To.
CSJ0178-04-005
Proj IDSTP 2018(663)HES
Work TypeTS IMPRVMTS
 
0.870801468.520.000.0
Work Order04-09-18
Work Began00-00-00
Work Completed
Time Computed07-08-18
Contract Working Days117
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0178-04-005
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183213
Totals801468.520.000.000.0

CountyBRAZORIA
HighwaySH 35
FromAT JAMISON SLOUGH
ToAND AT OYSTER CREEK
CSJ0179-01-048
Proj IDSTP 1702(629)
Work TypeBR DECK REPLACEMENT
 
1.1992037263.051476694.9572.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-03-17
Work Began12-04-17
Work Completed
Time Computed12-02-17
Contract Working Days307
Addl Days Granted0
Working Days Charged138
Percent Time Used44
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0179-01-048
RAMPART HYDRO SERVICES (24.62)
PROFESSIONAL TRAFFIC CONTROL, LLC (2.18)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.12)
LONE STAR TRAFFIC SERVICE, INC. (0.56)
TLC TRUCKING & CONTRACTING, INC. (3.87)
Contract #08173024
Totals2037263.050.001476694.9572.4

CountyFORT BEND
HighwaySS 10
FromUS 59 SOUTH
ToSH 36
CSJ0187-05-048
Proj IDSTP 1602(587)MM
Work TypeGR, STRS, BASE & SURF
 
4.82511736891.3411351467.3696.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-16
Work Began09-26-16
Work Completed
Time Computed11-14-16
Contract Working Days219
Addl Days Granted0
Working Days Charged210
Percent Time Used95
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0187-05-048
SCOTT DERR PAINTING CO (0.00)
QUALITY TURF FARMS, LC (3.34)
MESA ROD BUSTERS, INC. (1.27)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.45)
WILLOW CITY SIGN & RAIL, INC. (0.72)
BATTERSON,LLP (1.90)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (13.32)
SHAW DRILLING, LLC (1.91)
Contract #08163006
Totals11736891.340.0011351467.3696.7

CountyFORT BEND
HighwaySH 6
FromN OF BROOKS ST
ToLEXINGTON BLVD
CSJ0192-01-093
Proj IDSTP 2018(958)MM
Work TypeWIDEN FROM 6 TO 8 LANES
 
1.4856992340.390.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0192-01-093
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183224
Totals6992340.390.000.000.0

CountyBRAZORIA
HighwaySH 6
FromFORT BEND COUNTY LINE
ToBS 35-C
CSJ0192-02-050
Proj IDCM 1602(269)
Work TypeACCESS MANAGEMENT IMPROVEMENTS
 
17.9164942808.255354013.1899.9
Work Order08-29-16
Work Began01-03-17
Work Completed
Time Computed11-27-16
Contract Working Days237
Addl Days Granted14
Working Days Charged250
Percent Time Used99
Contractor(s)
HASSELL CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0192-02-050
GMJ PAVING CO. (2.51)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.22)
THIRD COAST SERVICES LLC (15.34)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.65)
CHERRY CRUSHED CONCRETE (0.14)
BATTERSON,LLP (12.75)
SPEEDY PAVING (4.83)
CURB PLANET INC. (0.43)
SPECIALTY DRILLING, LTD. (0.33)
LANDSHARK HYDROEXCAVATION SERVICES, INC. (0.05)
ISI CONTRACTING, INC. (1.72)
HOLES INCORPORATED (0.69)
WALLACE CONCRETE SAWING, LLC (0.23)
Contract #07163038
Totals4942808.253226.505354013.1899.9

CountyBRAZORIA
HighwaySH 6
FromBS 35C
ToGALVESTON COUNTY LINE
CSJ0192-03-017
Proj IDNH 2018(561)
Work TypePV REP & ACP O/L
 
3.1851534308.5595204.756.2
Work Order03-12-18
Work Began00-00-00
Work Completed
Time Computed05-11-18
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0192-03-017
THIRD COAST SERVICES LLC (8.58)
JMHP, INC. (2.17)
BATTERSON,LLP (6.47)
MAIN LANE INDUSTRIES LTD. (1.43)
Contract #02183017
Totals1534308.555000.0095204.756.2

CountyWALLER
HighwayIH 10
FromBRAZOS RIVER
ToFM 359
CSJ0271-04-071
Proj IDNH 1702(007)
Work TypeCONST 1 MORE ML EACH DIRECTION
 
5.820141496478.1246004980.3332.5
Work Order07-06-17
Work Began07-26-17
Work Completed
Time Computed07-26-17
Contract Working Days1,391
Addl Days Granted0
Working Days Charged289
Percent Time Used20
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-04-071
ALLSTATE SIGNAL & CONSTRUCTION, LLC (4.14)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.99)
ROADWAY SPECIALTIES, INC. (0.96)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.82)
BROOKLYN SWEEPS (0.24)
MESA ROD BUSTERS, INC. (0.63)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.19)
SCOTT DERR PAINTING CO, LLC (0.04)
VACA UNDERGROUND UTILITIES INC (1.25)
A R DANIEL CONSTRUCTION SERVICES, INC. (0.37)
AREA WIDE PROTECTIVE, INC. (1.03)
BAY CITY TRAFFIC (0.12)
ROADWAY CONSTRUCTION, LLC (0.47)
Contract #06173201
Totals141496478.121457330.8446004980.3332.5

CountyFORT BEND
HighwayIH 10
FromAT FM 1463
To.
CSJ0271-05-043
Proj IDNH 2017(487)
Work TypeCONSTRUCT INTERSECTION IMPROVEMENTS
 
0.1181107205.60836991.3278.0
Work Order03-08-17
Work Began06-05-17
Work Completed
Time Computed05-07-17
Contract Working Days81
Addl Days Granted0
Working Days Charged121
Percent Time Used149
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0271-05-043
NBG CONSTRUCTORS, INC. (37.33)
INTERSTATE BARRICADES & MARKINGS, INC. (1.04)
BATTERSON,LLP (3.44)
THIRD COAST SERVICES LLC (9.11)
QUALITY TURF FARMS, LC (1.00)
Contract #01173240
Totals1107205.6046351.32836991.3278.0

CountyHARRIS
HighwayIH 10
FromAT MASON CREEK
To.
CSJ0271-06-120
Proj IDNH 1802(603)
Work TypeEROSION REP AND CHANNEL PROTECTION
 
0.0361785427.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0271-06-120
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08183045
Totals1785427.000.000.000.0

CountyHARRIS
HighwayIH 10
FromLONGHORN RANCH AVENUE
ToBUCKEYE DRIVE
CSJ0271-06-126
Proj IDNH 1702(630)
Work TypeLANDSCAPING
 
1.730825265.53542496.6065.7
Work Order09-18-17
Work Began10-30-17
Work Completed
Time Computed10-18-17
Contract Working Days75
Addl Days Granted0
Working Days Charged70
Percent Time Used93
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-06-126
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173241
Totals825265.5328514.14542496.6065.7

CountyHARRIS
HighwayIH 10
FromBW 8
ToWEST OF SH 6
CSJ0271-07-305
Proj IDSTP 1502(445)MM
Work TypePV MKS FOR OPER IMPRVMTS
 
4.9261166377.541114201.5695.9
Work Order05-02-16
Work Began10-24-16
Work Completed
Time Computed07-01-16
Contract Working Days67
Addl Days Granted0
Working Days Charged75
Percent Time Used111
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0271-07-305
TRAF-TEX, INC. (14.04)
SCR CIVIL CONSTRUCTION, LLC (4.58)
REPUBLIC TRAFFIC SAFETY, INC. (13.41)
HOLES INCORPORATED (0.77)
INTERSTATE BARRICADES & MARKINGS, INC. (33.92)
Contract #01163224
Totals1166377.548550.551114201.5695.9

CountyHARRIS
HighwayIH 10
FromEAST OF GESSNER ROAD
ToNORTH POST OAK ROAD
CSJ0271-07-312
Proj IDNH 2016(414)
Work TypeDIAMOND GRIND AND GROOVE PAV SURF
 
4.77112293403.1314116093.8199.9
Work Order11-16-16
Work Began02-13-17
Work Completed
Time Computed01-15-17
Contract Working Days170
Addl Days Granted47
Working Days Charged317
Percent Time Used146
Contractor(s)
PENHALL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0271-07-312
SIMPLEX CONSTRUCTION SUPPLIES, INC. (2.29)
BATTERSON,LLP (15.05)
Contract #08163007
Totals12293403.130.0014116093.8199.9

CountyHARRIS ETC
HighwayIH 10 ETC
FromSH 6
ToHOGAN STEET
CSJ0271-07-318
Proj IDNH 2018(960)
Work TypeLANDSCAPE ENHANCEMENTS
 
75.427496320.360.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-19-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-07-318
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183238
Totals496320.360.000.000.0

CountyWALLER
HighwayUS 90
FromAT CANE ISLAND PARKWAY
To.
CSJ0271-09-022
Proj IDCC 271-9-22
Work TypeCONSTRUCT NEW INTERSECTION
 
0.3232321743.042068432.9090.7
Work Order09-14-16
Work Began11-28-16
Work Completed
Time Computed11-28-16
Contract Working Days163
Addl Days Granted0
Working Days Charged211
Percent Time Used129
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0271-09-022
TLC TRUCKING & CONTRACTING, INC. (0.23)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.88)
AAA ASPHALT PAVING, INC. (7.03)
JMHP, INC. (0.98)
TRAF-TEX, INC. (7.86)
BATTERSON,LLP (3.16)
FIRST KATY CONSTRUCTION (0.24)
CHERRY CRUSHED CONCRETE (0.12)
MVA CONSTRUCTION LLC (0.45)
BOMANITE OF HOUSTON (0.52)
CPAVE, INC. (0.14)
Contract #05163205
Totals2321743.044486.022068432.9090.7

CountyHARRIS
HighwayIH 610
FromW OF W 34TH ST ON US 290 (SEG 3)
ToON IH 610
CSJ0271-14-213
Proj IDCM 2013(991)
Work TypeGR, STRS, BASE AND PAVE
 
0.198151543734.14138914458.5185.3
Work Order12-11-13
Work Began12-31-13
Work Completed
Time Computed07-07-14
Contract Working Days1,095
Addl Days Granted130
Working Days Charged934
Percent Time Used76
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-213
CPAVE, INC. (0.07)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.37)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.75)
SCOTT DERR PAINTING CO, LLC (0.21)
HOUSTON SAWING & DRILLING (0.07)
TEXAS ENVIRONMENTAL MANAGEMENT, INC (0.28)
ESSARY, HART & MACWILIAM,INC. (9.64)
BORTUNCO (0.53)
INTERSTATE BARRICADES & MARKINGS, INC. (0.57)
RAY"S THREADING AND FAB SHOP (0.39)
Contract #11133201
Totals151543734.141015679.50138914458.5185.3

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11