Monthly State Let Construction Report For Houston District As Of Mar 13, 2024 Page 3 Of 13

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBRAZORIA
HighwaySH 288
From2ND STREET
ToSH 36
CSJ0111-08-124
Proj IDC 111-8-124
Work TypeOVERLAY
 
1.4102068826.464379332.9299.9
Work Order03-15-23
Work Began06-05-23
Work Completed
Time Computed04-14-23
Contract Working Days51
Addl Days Granted16
Working Days Charged58
Percent Time Used86
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0111-08-124
LONESTAR TRAFFIC SAFETY, LLC (0.17)
PENHALL COMPANY (23.55)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (8.45)
WILLOW CITY SIGN & RAIL, INC. (2.65)
BATTERSON, LLP (5.95)
HIGHWAY 1 LLC (0.35)
AGGREGATE TECHNOLOGIES, INC. (0.97)
CPAVE, INC. (1.08)
QUALITY TURF FARMS, L.C. (0.18)
Contract #02233234
Totals2068826.46231738.564379332.9299.9

CountyBRAZORIA
HighwayBS 288B
FromFM 2004
ToJOHNSON COOK ROAD
CSJ0111-08-126
Proj IDSTP 2023(348)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.6001319307.50899720.8368.1
Work Order04-12-23
Work Began00-00-00
Work Completed
Time Computed05-12-23
Contract Working Days82
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0111-08-126
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01233020
Totals1319307.500.00899720.8368.1

CountyBRAZORIA
HighwayBS 288B
FromFM 523
ToFM 521
CSJ0111-09-042
Proj IDC 111-9-42
Work TypeOVERLAY
 
5.79510948342.4310021712.1691.5
Work Order01-04-23
Work Began06-19-23
Work Completed
Time Computed05-04-23
Contract Working Days163
Addl Days Granted0
Working Days Charged165
Percent Time Used101
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0111-09-042
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (1.42)
MAIN LANE INDUSTRIES LTD. (1.69)
STRIPE LINES, INC. (2.65)
THIRD COAST SERVICES LLC (2.96)
TRAFFIC SIGNS & LINES, LLC (0.87)
INTERSTATE BARRICADES & MARKINGS, INC. (0.12)
HOLES INCORPORATED (0.06)
CREACOM, INC. (0.07)
Contract #12223210
Totals10948342.43233570.2710021712.1691.5

CountyBRAZORIA
HighwayBS 288B
FromSH 35
ToFM 523
CSJ0111-09-044
Proj IDC 111-9-44
Work TypeOVERLAY
 
4.8933933801.944542861.9599.9
Work Order05-10-22
Work Began08-17-22
Work Completed
Time Computed06-09-22
Contract Working Days144
Addl Days Granted3
Working Days Charged143
Percent Time Used97
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0111-09-044
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (2.54)
CREACOM, INC. (4.11)
INTERSTATE BARRICADES & MARKINGS, INC. (0.39)
PINNACLE GRINDING AND GROOVING LLC (8.74)
TRAFFIC SIGNS & LINES, LLC (3.60)
MAIN LANE INDUSTRIES LTD. (0.58)
Contract #04223011
Totals3933801.940.004542861.9599.9

CountyWALLER
HighwayUS 290
FromEAST OF FM 362
ToWEST OF FM 362.
CSJ0114-11-082
Proj IDNH 2B20(183)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.2014591144.057520447.2499.9
Work Order10-21-20
Work Began01-21-21
Work Completed
Time Computed11-20-20
Contract Working Days271
Addl Days Granted162
Working Days Charged506
Percent Time Used116
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-11-082
A&J REBAR LLC (0.21)
GMJ PAVING CO. (1.04)
ROMAR UNLIMITED, INC. (0.93)
REPUBLIC TRAFFIC SAFETY, INC. (1.26)
SCOTT DERR PAINTING CO, LLC (0.16)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.89)
PROFESSIONAL TRAFFIC CONTROL LLC (1.33)
CITYLYNX, INC. (5.22)
OSCAR ORDUNO, INC. (45.63)
GOULD INDUSTRIES LLC (14.23)
CURB PLANET INC. (0.16)
Contract #09203215
Totals4591144.0524690.007520447.2499.9

CountyWALLER
HighwayUS 290
FromJAMES MUSE PARKWAY
ToNORTH OF FM 362
CSJ0114-11-086
Proj IDC 114-11-86
Work TypeNEW LOCATION NON-FREEWAY
 
10942905.022868913.0326.2
Work Order04-12-23
Work Began10-12-23
Work Completed
Time Computed07-11-23
Contract Working Days304
Addl Days Granted0
Working Days Charged94
Percent Time Used30
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-11-086
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (5.03)
HOUSTON CRUSHED CONCRETE, L.L.C. (0.12)
TRAFFIC SIGNS & LINES, LLC (0.92)
FARR FOUNDATION, INC. (0.98)
MESA ROD BUSTERS, INC. (0.94)
SPECIALTY DRILLING, LLC (0.80)
THIRD COAST SERVICES LLC (6.83)
AARON CONCRETE CONTRACTORS, LLC (0.82)
MD LAWN & LANDSCAPE LLC (0.14)
Contract #11223010
Totals10942905.02394261.802868913.0326.2

CountyWALLER ETC
HighwayUS 290 ETC
FromBLASINGAME/OLD HOWTH RD (W OF SH 6)
ToWALLER/HARRIS COUNTY LINE
CSJ0114-11-088
Proj IDF 2022(096)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
47.7443145018.501822509.7257.9
Work Order12-16-21
Work Began04-03-23
Work Completed
Time Computed01-15-22
Contract Working Days120
Addl Days Granted0
Working Days Charged108
Percent Time Used90
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-11-088
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11213222
Totals3145018.5055357.171822509.7257.9

CountyHARRIS
HighwayUS 290
FromWALLER COUNTY LINE
ToEAST OF HEGAR ROAD
CSJ0114-12-012
Proj IDF 2023(685)
Work TypeOVERLAY
 
6.5343991011.244115037.9499.9
Work Order05-05-23
Work Began06-19-23
Work Completed
Time Computed06-04-23
Contract Working Days53
Addl Days Granted0
Working Days Charged128
Percent Time Used241
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0114-12-012
WILLIAMS ROAD, LLC (4.64)
HIGHWAY 1 LLC (7.32)
Contract #04233017
Totals3991011.241146852.704115037.9499.9

CountyHARRIS
HighwayUS 290
FromAT HEGAR ROAD AND FIELD STORE ROAD
To.
CSJ0114-12-015
Proj IDC 114-12-15
Work TypeCULVERT & STORM DRAINAGE WORK
 
0.379425417.80477213.9799.9
Work Order04-12-23
Work Began05-22-23
Work Completed
Time Computed05-12-23
Contract Working Days60
Addl Days Granted0
Working Days Charged51
Percent Time Used85
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-12-015
K4 ENVIRONMENTAL LLC (11.11)
ROMAR UNLIMITED, INC. (3.87)
Contract #03233238
Totals425417.800.00477213.9799.9

CountyMONTGOMERY
HighwayIH 69
FromHARRIS COUNTY LINE
ToLIBERTY COUNTY LINE
CSJ0177-05-112
Proj IDC 177-5-112
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
17.7303716482.69541164.7914.5
Work Order11-16-22
Work Began00-00-00
Work Completed
Time Computed12-16-22
Contract Working Days270
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0177-05-112
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10223204
Totals3716482.690.00541164.7914.5

CountyHARRIS
HighwayIH 69
FromSL 8 EAST
ToFM 1960
CSJ0177-07-118
Proj IDC 177-7-118
Work TypeTRAFFIC CONTROL DEVICES
 
3.407975659.051130196.8399.9
Work Order01-18-23
Work Began05-05-23
Work Completed
Time Computed02-17-23
Contract Working Days109
Addl Days Granted0
Working Days Charged89
Percent Time Used81
Contractor(s)
STRIPE LINES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0177-07-118
HIGHWAY 1 LLC (49.45)
Contract #12223018
Totals975659.0565402.301130196.8399.9

CountyHARRIS
HighwayIH 69
FromIH 69 NB
ToIH 610 WB
CSJ0177-11-159
Proj IDSTP 2023(018)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.640184301.3096507.0052.3
Work Order10-19-22
Work Began00-00-00
Work Completed
Time Computed11-18-22
Contract Working Days20
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
REPUBLIC TRAFFIC SAFETY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0177-11-159
SAFETEX,INC. (0.00)
Contract #09223229
Totals184301.3051000.0096507.0052.3

CountyHARRIS
HighwayIH 69
FromIH 69 SB
ToIH 10 EB
CSJ0177-11-160
Proj IDSTP 2024(483)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.300150592.500.000.0
CountyHARRIS
HighwayIH 10
FromIH 10 WB
ToIH 69 NB
CSJ0508-01-387
Proj IDSTP 2024(483)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
401765.000.000.0
CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS ON IH 610
To.
CSJ0912-72-744
Proj IDF 2024(482)
Work TypeTRAFFIC CONTROL DEVICES
 
31.4791350083.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-21-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days113
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 0177-11-160
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12233209
Totals1902441.000.000.000.0

CountyMONTGOMERY
HighwaySL 494
FromN OF KINGWOOD DR
ToHARRIS C/L
CSJ0177-14-010
Proj IDSTP 1802(602)
Work TypeWDN GR, STRS, BS & PAV
 
1.83514347428.7321629038.4699.9
Work Order02-20-19
Work Began07-08-19
Work Completed
Time Computed03-22-19
Contract Working Days384
Addl Days Granted331
Working Days Charged1,012
Percent Time Used141
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0177-14-010
ADCOCK 4 INVESTMENTS, LLC (5.32)
BLACKTOP INDUSTRIES LLC (0.16)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.38)
TRAF-TEX, INC. (1.89)
LONESTAR TRAFFIC SAFETY, LLC (0.22)
ROMAR UNLIMITED, INC. (0.79)
JAMES CONSTRUCTION GROUP, L.L.C. (3.31)
BATTERSON, LLP (0.87)
TEXOP CONSTRUCTION (0.97)
DORAN STEEL, INC. (1.50)
P&Z LOGISTICS INC. (0.12)
CURB PLANET INC. (0.11)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.27)
WM TRUCKING & EXCAVATING INC. (0.64)
LINDSEY CONSTRUCTION, INC. (0.00)
ARANDA BROTHERS CONSTRUCTION CO., INC. (0.00)
HOUSTON SAWING & DRILLING (0.04)
AIMS COMPANIES (0.01)
JASSO"S SAWING & SEALING (0.18)
TEXAS MATERIALS GROUP, INC. (0.33)
Contract #08183010
Totals14347428.736600.3221629038.4699.9

CountyMONTGOMERY
HighwaySL 494
FromFM 1485 WEST
ToFM 1485 EAST
CSJ0177-14-037
Proj IDC 177-14-37
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.3111321754.751803869.7099.9
Work Order01-12-22
Work Began05-02-22
Work Completed
Time Computed05-12-22
Contract Working Days92
Addl Days Granted0
Working Days Charged86
Percent Time Used93
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0177-14-037
LONESTAR TRAFFIC SAFETY, LLC (0.33)
TRAF-TEX, INC. (10.04)
T&T TRUCKING (1.03)
BATTERSON, LLP (1.79)
WILLOW CITY SIGN & RAIL, INC. (3.79)
SLS CONSTRUCTION, INC. (6.80)
JB PINNACLE GROUP, LLC (3.62)
J KRU LAND SERVICES, LLC (0.62)
SCOTT DERR PAINTING CO, LLC (0.11)
Contract #10213016
Totals1321754.7549648.751803869.7099.9

CountyMONTGOMERY
HighwaySL 494
FromAT CANEY CREEK
To.
CSJ0177-14-039
Proj IDBR 2022(511)
Work TypeBRIDGE REPLACEMENT
 
8553522.778544368.9999.8
Work Order06-09-22
Work Began09-07-22
Work Completed
Time Computed09-07-22
Contract Working Days211
Addl Days Granted0
Working Days Charged210
Percent Time Used99
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0177-14-039
J. T. B. SERVICES, INC. (1.84)
MESA ROD BUSTERS, INC. (0.64)
LONESTAR TRAFFIC SAFETY, LLC (0.08)
SCOTT DERR PAINTING CO, LLC (0.14)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.04)
WILLOW CITY SIGN & RAIL, INC. (1.27)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.81)
MESA ROD BUSTERS, INC. (0.38)
MARTIN MARIETTA MATERIALS, INC. (0.41)
PRIMATE CONSTRUCTION, LP (0.12)
AARON CONCRETE CONTRACTORS, LLC (2.06)
MTAM CORPORATION (0.09)
HIGHWAY 1 LLC (0.19)
TEXAS CUTTING & CORING GP, INC. (0.22)
Contract #05223209
Totals8553522.770.008544368.9999.8

CountyHARRIS
HighwaySH 35
FromAT BELFORT AVE
To.
CSJ0178-01-037
Proj IDSTP 2021(188)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.200313438.45403114.8799.9
Work Order01-14-21
Work Began09-15-23
Work Completed
Time Computed05-14-21
Contract Working Days38
Addl Days Granted0
Working Days Charged33
Percent Time Used86
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0178-01-037
HIGHWAY 1 LLC (2.78)
REDLINE CONSTRUCTION SERVICES LLC (10.22)
Contract #12203221
Totals313438.4542174.29403114.8799.9

CountyHARRIS
HighwaySH 35
From0.1 MILE NORTH OF SL 8
To0.1 MILE SOUTH OF SL 8
CSJ0178-01-042
Proj IDSTP 2023(893)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200685716.92200928.0029.3
CountyGALVESTON
HighwayFM 2004
FromAT FM 646
To.
CSJ2523-01-029
Proj IDSTP 2023(893)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200154561.510.000.0
CountyGALVESTON
HighwayFM 646
From0.1 MI N OF 28TH ST
To0.1 MI S OF 28TH ST
CSJ2523-03-013
Proj IDSTP 2023(893)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200145241.270.000.0
Work Order08-03-23
Work Began00-00-00
Work Completed
Time Computed12-01-23
Contract Working Days153
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0178-01-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06233633
Totals985519.70123356.00200928.0020.3

CountyBRAZORIA
HighwaySH 35
FromFM 523
ToFM 2403
CSJ0178-03-156
Proj IDC 178-3-156
Work TypeOVERLAY
 
15.40020773975.765382148.6225.9
Work Order07-06-22
Work Began10-11-22
Work Completed
Time Computed09-05-22
Contract Working Days416
Addl Days Granted30
Working Days Charged256
Percent Time Used57
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0178-03-156
NBG CONSTRUCTORS, INC. (0.50)
WEST TEXAS ROCK RESOURCES, LLC (0.10)
PROFESSIONAL TRAFFIC CONTROL LLC (2.76)
INTERSTATE BARRICADES & MARKINGS, INC. (0.11)
TRAFFIC SIGNS & LINES, LLC (2.10)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (0.83)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (1.18)
Contract #06223207
Totals20773975.767229.605382148.6225.9

CountyBRAZORIA
HighwaySH 35
FromFM 523
ToBS 288B
CSJ0178-03-158
Proj IDC 178-3-158
Work TypeOVERLAY
 
4.8944500659.534084327.1491.0
Work Order05-10-22
Work Began06-09-22
Work Completed
Time Computed06-09-22
Contract Working Days101
Addl Days Granted0
Working Days Charged114
Percent Time Used112
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0178-03-158
BATTERSON, LLP (0.26)
DUSTROL, INC. (2.25)
WILLOW CITY SIGN & RAIL, INC. (5.25)
WEST TEXAS ROCK RESOURCES, LLC (0.14)
PROFESSIONAL TRAFFIC CONTROL LLC (6.58)
MAIN LANE INDUSTRIES LTD. (6.91)
PFEIFFER & SON LTD. (4.37)
SWEEPING CORPORATION OF AMERICA, LLC (0.35)
CPAVE, INC. (0.11)
HOLES INCORPORATED (0.03)
WALLACE CONCRETE SAWING, LLC (0.80)
Contract #04223211
Totals4500659.530.004084327.1491.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13