Monthly State Let Construction Report For Houston District As Of Jun 08, 2018 Page 4 Of 10

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayIH 610
FromPOST OAK BLVD
ToIH 10 (W)
CSJ0271-17-163
Proj IDNH 2018(375)
Work TypeCONSTRUCT BUSWAY FACILITY
 
1.68557190569.4312867369.4622.4
Work Order12-21-17
Work Began03-24-18
Work Completed
Time Computed02-19-18
Contract Working Days833
Addl Days Granted0
Working Days Charged56
Percent Time Used6
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-17-163
MESA ROD BUSTERS, INC. (4.42)
BROOKLYN SWEEPS (0.43)
JMHP, INC. (0.62)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.45)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.05)
QUALITY TURF FARMS, LC (0.08)
SCOTT DERR PAINTING CO, LLC (0.31)
ROADWAY CONSTRUCTION, LLC (1.59)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.25)
BASE CONSTRUCTION (4.42)
THIRD COAST SERVICES LLC (4.25)
(OLD PRIME)BORING & TUNNELING COMPANY OF AMERICA, INC. (0.32)
CREACOM INC. (0.04)
Contract #12173202
Totals57190569.43829436.5312867369.4622.4

CountyMONTGOMERY
HighwaySH 105
FromIH 45N
ToSH 75
CSJ0338-03-088
Proj IDSTP 2014(111)TE
Work TypeTE AND ACCESS MANAGEMENT
 
0.6063484120.942745381.4278.7
Work Order08-05-16
Work Began10-04-16
Work Completed
Time Computed09-05-16
Contract Working Days227
Addl Days Granted0
Working Days Charged152
Percent Time Used66
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0338-03-088
LANDPRO, INC. (14.39)
HASSELL CONSTRUCTION COMPANY, INC. (2.72)
THIRD COAST SERVICES LLC (26.71)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.80)
CURBS, LLC (0.10)
ONLINE DIRECTIONAL BORING, LP (2.83)
J & M CONTRACTING COMPANY (7.23)
Contract #05163219
Totals3484120.9460540.552745381.4278.7

CountyGALVESTON
HighwaySH 87
FromNORTH OF SH 124 ON HIGH ISLAND
ToSEAGULL LANE
CSJ0367-02-075
Proj IDNH 1802(203)
Work TypeREHABILITATE AND RAISE ROADWAY
 
7.44920817021.430.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days244
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0367-02-075
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183205
Totals20817021.430.000.000.0

CountyHARRIS
HighwaySH 146
FromNASA 1
ToHARRIS/GALVESTON COUNTY LINE
CSJ0389-05-116
Proj IDNH 2018(852)
Work TypeGR, STRS & SURFACE
 
3.883201835272.660.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days1,549
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0389-05-116
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183201
Totals201835272.660.000.000.0

CountyHARRIS
HighwaySH 146
FromVARIOUS LOCATIONS
To.
CSJ0389-05-123
Proj IDNH 1502(604)
Work TypeLANDSCAPE DEVELOPMENT
 
10.1591376457.701119194.7381.3
Work Order00-00-00
Work Began05-02-16
Work Completed
Time Computed03-17-16
Contract Working Days75
Addl Days Granted0
Working Days Charged55
Percent Time Used73
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-05-123
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12153014
Totals1376457.7013408.501119194.7381.3

CountyGALVESTON
HighwaySH 146
FromHARRIS C/L
ToFM 1764
CSJ0389-06-106
Proj IDNH 2017(122)
Work TypeBASE REP AND ACP O/L
 
10.6407195186.607443487.4899.9
Work Order10-25-16
Work Began11-28-16
Work Completed
Time Computed11-24-16
Contract Working Days120
Addl Days Granted27
Working Days Charged147
Percent Time Used100
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0389-06-106
ROADSAFE TRAFFIC SYSTEMS, INC. (4.37)
TRAF-TEX, INC. (1.92)
PROFESSIONAL TRAFFIC CONTROL, LLC (3.33)
Contract #09163228
Totals7195186.600.007443487.4899.9

CountyGALVESTON
HighwaySH 146
FromNB AT MOSES BAYOU BRIDGE
To.
CSJ0389-06-107
Proj IDNH 2018(377)
Work TypeRAISE APPROACH AT BRIDGE
 
0.003219473.36194360.6488.5
Work Order01-10-18
Work Began02-16-18
Work Completed
Time Computed02-09-18
Contract Working Days36
Addl Days Granted0
Working Days Charged16
Percent Time Used44
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-06-107
REPUBLIC TRAFFIC SAFETY, INC. (8.06)
ROMAR UNLIMITED, INC. (3.73)
Contract #12173227
Totals219473.360.00194360.6488.5

CountyHARRIS
HighwaySH 146
FromJ.B. LEFEBVRE ROAD
ToUP RR (TO INC SH 146/SPURINTERCHGE)
CSJ0389-13-059
Proj IDNH 1602(460)
Work TypeLANDSCAPE DEVELOPMENT
 
2.7801277107.801187565.1192.9
Work Order09-16-16
Work Began10-17-16
Work Completed
Time Computed10-16-16
Contract Working Days105
Addl Days Granted0
Working Days Charged105
Percent Time Used100
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-13-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08163243
Totals1277107.800.001187565.1192.9

CountyGALVESTON
HighwayIH 45
FromEND OF CAUSEWAY
To59TH STEET
CSJ0500-01-145
Proj IDNH 2018(664)
Work TypeBASE REP, MILLING, SEAL COAT, O/L
 
2.3621551543.500.000.0
Work Order04-13-18
Work Began05-24-18
Work Completed
Time Computed05-13-18
Contract Working Days45
Addl Days Granted0
Working Days Charged1
Percent Time Used2
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0500-01-145
PROFESSIONAL TRAFFIC CONTROL, LLC (5.63)
VACA UNDERGROUND UTILITIES INC (2.01)
MAIN LANE INDUSTRIES LTD. (8.85)
HOLES INCORPORATED (0.69)
Contract #03183030
Totals1551543.500.000.000.0

CountyGALVESTON
HighwayIH 45
FromTIKI ISLAND
ToTEXAS CITY WYE
CSJ0500-01-150
Proj IDNH 1702(110)
Work TypeBS REPR, MILL, SC & TOM OVERLAY
 
2.0663322042.952891615.9587.0
Work Order06-08-17
Work Began08-21-17
Work Completed
Time Computed07-08-17
Contract Working Days105
Addl Days Granted0
Working Days Charged100
Percent Time Used95
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0500-01-150
BATTERSON,LLP (3.43)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (1.96)
INTERSTATE BARRICADES & MARKINGS, INC. (0.29)
ISI CONTRACTING, INC. (13.54)
TEXOP CONSTRUCTION (6.11)
Contract #05173224
Totals3322042.9529400.002891615.9587.0

CountyHARRIS
HighwayIH 45
From0.4808 MILES SOUTH OF EL DORADO
ToSOUTH OF MEDICAL CENTER DRIVE
CSJ0500-03-042
Proj IDNH 2013(163)
Work TypeGR, WIDEN STRS & RECONSTR PV
 
2.18092660504.6495595541.0999.9
CountyHARRIS
HighwayIH 45
From0.4808 MILES SOUTH OF EL DORADO
ToMEDICAL CENTER DRIVE
CSJ0500-03-546
Proj IDRW 500-3-546
Work TypeROW ACQUISITION,RELO & UTILITIES
 
5.530627780.60635217.5599.9
Work Order12-12-12
Work Began12-17-12
Work Completed
Time Computed12-17-12
Contract Working Days1,125
Addl Days Granted63
Working Days Charged1,180
Percent Time Used99
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-042
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.64)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.59)
ESSARY, HART & MACWILIAM,INC. (8.94)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25)
SCOTT DERR PAINTING CO, LLC (0.03)
INTERSTATE BARRICADES & MARKINGS, INC. (0.78)
CREACOM, INC. (4.12)
BASE CONSTRUCTION, L.L.P. (12.36)
BORTUNCO (0.26)
Contract #11123001
Totals93288285.24126326.6596230758.6499.9

CountyHARRIS
HighwayIH 45
FromIH 45 NB AT WHITE OAK BAYOU
To.
CSJ0500-03-044
Proj IDBR 2014(952)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.46719356558.1423436422.2599.9
CountyHARRIS
HighwayIH 45
FromIH 45 NB AT WHITE OAK BAYOU
To.
CSJ0500-03-589
Proj IDROW 500-3-589
Work TypeACQUISITION AND UTILITY ADJUSTMENTS
 
0.466281265.00314386.1699.9
Work Order09-30-14
Work Began01-21-15
Work Completed
Time Computed10-16-14
Contract Working Days575
Addl Days Granted47
Working Days Charged622
Percent Time Used100
Contractor(s)
BALFOUR BEATTY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-044
PROFESSIONAL TRAFFIC CONTROL, LLC (0.28)
EROSION CONTROL, INC. (0.34)
GMJ PAVING CO. (0.25)
THIRD COAST SERVICES LLC (0.35)
APCON SERVICES, LLC (0.32)
MESA ROD BUSTERS, INC. (6.69)
RDI FOUNDATION DRILLING (9.31)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.10)
WEBBER BARRIER SERVICES, LLC. (2.07)
SOUTHERN CRUSHED CONCRETE LLC (0.25)
SCOTT DERR PAINTING CO, LLC (0.25)
HOUSTON SAWING & DRILLING (0.09)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
T CONSTRUCTION L.L.C. (0.97)
GIBSON & ASSOCIATES, INC. (5.96)
CPAVE, INC. (0.25)
QUALITY TURF FARMS, LC (0.37)
Contract #07143201
Totals19637823.140.0023750808.4199.9

CountyHARRIS
HighwayIH 45
FromS OF NASA 1 BYPASS
ToGALVESTON COUNTY LINE
CSJ0500-03-107
Proj IDNH 2017(906)
Work TypeGR, STRS, BASE, AND PAVE
 
1.91899164261.3931985397.4132.2
CountyHARRIS
HighwayIH 45
FromS OF BAY AREA BLVD
ToS OF KOBAYASHI DRIVE
CSJ0500-03-578
Proj IDNH 2017(906)
Work TypeRESTRIPING AND SIGNING
 
1.146282079.4010353.853.6
CountyGALVESTON
HighwayFM 518
FromAT HOBBS ROAD/LAFAYETTE LANE
To.
CSJ0976-03-102
Proj IDSTP 2017(969)HES
Work TypeTS IMPRVMTS
 
0.250337135.900.000.0
Work Order05-02-17
Work Began05-15-17
Work Completed
Time Computed05-15-17
Contract Working Days1,427
Addl Days Granted0
Working Days Charged241
Percent Time Used16
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-107
VACA UNDERGROUND UTILITIES INC (1.41)
ESSARY, HART & MACWILIAM,INC. (5.39)
ROADWAY CONSTRUCTION, LLC (0.77)
GEORGE MEEKS LANDPRO, INC. (0.19)
A & A CONSTRUCTION (0.33)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.47)
TRAF-TEX, INC. (4.07)
HAYWARD BAKER, INC. (0.44)
SAFETEX,INC. (0.53)
MP TECHNOLOGIES, LLC (0.13)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17)
SCOTT DERR PAINTING CO, LLC (0.02)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.58)
Contract #04173001
Totals99783476.693013198.3931995751.2632.0

CountyHARRIS
HighwayIH 45
FromNYACK ROAD
To0.7881 MILES SOUTH OF FM 1959
CSJ0500-03-462
Proj IDC 500-3-462
Work TypeGR, STRS, BASE, AND PAVE
 
5.18877483150.8884988640.3399.9
Work Order06-15-11
Work Began06-17-11
Work Completed
Time Computed06-17-11
Contract Working Days1,135
Addl Days Granted164
Working Days Charged1,304
Percent Time Used100
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-462
BASE CONSTRUCTION, L.L.P. (11.55)
DORAN STEEL, INC. (11.03)
INTERSTATE BARRICADES & MARKINGS, INC. (1.06)
CREACOM, INC. (4.33)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.59)
WEST TEXAS RUMBLE STRIP (0.00)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.58)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.33)
SCOTT DERR PAINTING CO (0.23)
MAGNUM TUNNELING, LLC (0.05)
FOSTER FENCE, LTD. (0.05)
WESTCO GROUNDS MAINTENANCE CO., INC. (0.88)
VAQUERO CONSTRUCTION, INC. (1.21)
BATTERSON,LLP (0.22)
Contract #05113210
Totals77483150.88100522.8884988640.3399.9

CountyHARRIS
HighwayIH 45
From.112 MI N OF DIXIE FARM RD
To1.04 MI S OF FM 2351
CSJ0500-03-575
Proj IDNH 2015(246)
Work TypeHIGH MAST ILLUMINATION
 
2.6521176661.680.000.0
Work Order03-12-15
Work Began00-00-00
Work Completed
Time Computed03-28-15
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-575
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02153209
Totals1176661.680.000.000.0

CountyHARRIS
HighwayIH 45
FromNB & SB FRONTAGE RD FROM SCOTT ST
ToWAYSIDE DR
CSJ0500-03-580
Proj IDNH 2016(806)
Work TypeCONC PAVE, CONCE CURB/SIDEWALK, ETC
 
2.3195562891.966264981.8999.9
Work Order06-17-16
Work Began11-01-16
Work Completed
Time Computed08-16-16
Contract Working Days260
Addl Days Granted0
Working Days Charged300
Percent Time Used115
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-580
PROFESSIONAL TRAFFIC CONTROL, LLC (1.76)
PFEIFFER & SON LTD. (6.10)
PENHALL COMPANY (AUSTIN) (1.01)
CHERRY CONCRETE REMOVAL (1.06)
MESA ROD BUSTERS, INC. (6.05)
CENTURY ASPHALT MATERIALS (1.05)
Contract #03163219
Totals5562891.960.006264981.8999.9

CountyHARRIS
HighwayIH 45
From0.6 MILES SOUTH OF CROSSTIMBERS
To0.16 MILES NORTH OF AIRLINE DRIVE
CSJ0500-03-583
Proj IDNH 2018(685)
Work TypeRESTORATION OF FRONTAGE ROADS
 
1.1342119421.760.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days55
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-583
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183009
Totals2119421.760.000.000.0

CountyHARRIS
HighwayIH 45 ETC
From0.251 MILES SOUTH OF NASA BY PASS
ToMEDICAL CTR BLVD & VARIOUS LOC
CSJ0500-03-603
Proj IDNH 1602(363)
Work TypeLANDSCAPE ENHANCEMENTS
 
11.6332369012.032062850.5487.0
Work Order08-16-16
Work Began10-03-16
Work Completed
Time Computed10-03-16
Contract Working Days120
Addl Days Granted0
Working Days Charged120
Percent Time Used100
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-603
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07163017
Totals2369012.030.002062850.5487.0

CountyHARRIS
HighwayIH 45
FromSP 5
ToIH 69
CSJ0500-03-605
Proj IDCM 1402(183)
Work TypeENTRANCE/EXIT RAMPS, REPLACE DCS
 
1.64030330378.0325127285.6782.1
CountyHARRIS
HighwayIH 45
FromSP 5
ToIH 69
CSJ0500-03-611
Proj IDROW 500-3-611
Work TypeUTILITY ADJUSTMENTS
 
1.640123042.7087596.8471.1
Work Order02-02-17
Work Began02-20-17
Work Completed
Time Computed02-20-17
Contract Working Days644
Addl Days Granted0
Working Days Charged378
Percent Time Used58
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-605
EPOXY DESIGN SYSTEMS, INC. (0.06)
SCOTT DERR PAINTING CO, LLC (0.04)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.35)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.12)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.34)
MESA ROD BUSTERS, INC. (7.17)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.28)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (3.11)
MCA COMMUNICATIONS, INC. (0.32)
IDEAL CONTRACTING SERVICES, L.L.C. (0.02)
MAGNOLIA SERVICES INCORPORATED (0.22)
MERIDIAN FENCE AND SECURITY, L.P. (0.03)
Contract #01173004
Totals30453420.73464972.5225214882.5182.1

CountyHARRIS
HighwayIH 45
FromAT IH 610 E
To.
CSJ0500-03-606
Proj IDCM 2013(984)
Work TypeCONSTRUCT DIRECT CONNECTOR
 
5.56066590610.2546298774.6569.5
Work Order09-13-16
Work Began09-20-16
Work Completed
Time Computed09-20-16
Contract Working Days1,237
Addl Days Granted194
Working Days Charged557
Percent Time Used38
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-606
ROYAL REBAR (7.63)
QUALITY TURF FARMS, LC (0.44)
SCOTT DERR PAINTING CO (0.05)
BASE CONSTRUCTION (1.00)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.13)
TRAF-TEX, INC. (4.63)
INTERSTATE BARRICADES & MARKINGS, INC. (0.62)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.75)
BORTUNCO (0.48)
ROADWAY CONSTRUCTION, LLC (0.32)
Contract #08163201
Totals66590610.251748830.8146298774.6569.5

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10