Monthly State Let Construction Report For Houston District As Of Jun 08, 2018 Page 7 Of 10

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyFORT BEND
HighwayCR ETC
FromMEYER ROAD AT SNAKE CREEK TRIBUTARY
To.
CSJ0912-34-176
Proj IDBR 2013(735)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.7122828589.452749638.5599.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-04-15
Work Began09-08-15
Work Completed
Time Computed09-08-15
Contract Working Days321
Addl Days Granted0
Working Days Charged397
Percent Time Used123
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-176
LONESTAR TRAFFIC SAFETY, LLC (0.55)
REGIONAL TRAFFIC SERVICES LLC (0.40)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.45)
ODUM SERVICES, L.P. (1.77)
MESA ROD BUSTERS, INC. (0.19)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.98)
EROSION PREVENTION PRODUCTS (4.81)
GARNER PAVING & CONSTRUCTION, LTD. (0.15)
CROSS TEX CURBS (0.00)
J KRU LAND SERVICES, LLC (0.06)
Contract #06153027
Totals2828589.450.002749638.5599.3

CountyFORT BEND
HighwayVA
FromVARIOUS LOCATIONS ALONG: US 59,
ToSH 6, AND US 90A
CSJ0912-34-187
Proj IDC 912-34-187
Work TypeINSTALLATION OF DMS
 
0.001992940.68990091.3699.7
Work Order04-07-16
Work Began02-13-17
Work Completed
Time Computed05-07-16
Contract Working Days91
Addl Days Granted0
Working Days Charged62
Percent Time Used68
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-187
MAIN LANE INDUSTRIES LTD. (54.26)
INTERSTATE BARRICADES & MARKINGS, INC. (0.98)
Contract #02163213
Totals992940.680.00990091.3699.7

CountyMONTGOMERY
HighwayCR
FromSUPERIOR RD AT LAKE CREEK
To.
CSJ0912-37-228
Proj IDBR 2016(616)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1241087296.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-37-228
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183235
Totals1087296.750.000.000.0

CountyMONTGOMERY
HighwayCR
FromMOUNT MIRIAH AT LAKE CREEK DRAW
To.
CSJ0912-37-229
Proj IDBR 2016(617)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2031488885.75410675.8327.5
Work Order11-13-17
Work Began02-07-18
Work Completed
Time Computed12-13-17
Contract Working Days203
Addl Days Granted0
Working Days Charged67
Percent Time Used33
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-37-229
A1 EROSION CONTROL (1.09)
LONE STAR PAVING COMPANY (12.28)
LONESTAR TRAFFIC SAFETY, LLC (0.63)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.60)
STRIPE LINES, INC. (0.53)
MESA ROD BUSTERS, INC. (0.35)
Contract #10173019
Totals1488885.7538461.00410675.8327.5

CountyHARRIS
HighwayVA
FromFANNIN & MN ST ESPLANADES CAMBRIDGE
ToMECOM FOUNTAIN
CSJ0912-70-078
Proj IDSTP 2011(255)TE
Work TypeENHANCEMENT PROJECT
 
0.8072581444.902346984.1197.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-26-13
Work Began10-21-13
Work Completed
Time Computed10-12-13
Contract Working Days176
Addl Days Granted445
Working Days Charged847
Percent Time Used136
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-078
HIGHWAY BARRICADES AND SERVICES, LLC (0.88)
DOWN UNDER CONSTRUCTION (1.83)
SPECIALTY DRILLING (0.02)
BUILDER SERVICES CO. (1.50)
LEXTEX, INC. (7.15)
BIO LANDSCAPE & MAINTENANCE, INC. (65.42)
HOGGATT, LP (5.46)
EVERY SECOND COUNTS (ESC) (5.69)
HIGHWAY BARRICADES AND SERVICES, LLC (0.48)
MIKELS CONSTRUCTION CO., INC. (2.51)
PUMPS, MOTORS & CONTROLS (0.04)
STRIPE LINES, INC. (0.15)
Contract #06133013
Totals2581444.900.002346984.1197.7

CountyHARRIS
HighwayCR
FromON FAIRMONT PKWY AT UNDERWOOD ROAD
To.
CSJ0912-70-086
Proj IDSTP 2018(966)HESG
Work TypeIMPROVE TS
 
0.202203812.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183244
Totals203812.770.000.000.0

CountyHARRIS
HighwayCS
FromWESTERLAND DRIVE; AT HCFCD DITCH
To.
CSJ0912-70-091
Proj IDBR 2014(555)
Work TypeREPL BR & APPR
 
0.1631844818.401794940.2997.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-05-16
Work Began11-03-16
Work Completed
Time Computed09-05-16
Contract Working Days254
Addl Days Granted0
Working Days Charged254
Percent Time Used100
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-091
SPECIALTY DRILLING, LTD. (6.22)
HIGHWAY 1, LLC (1.64)
Contract #04163016
Totals1844818.400.001794940.2997.2

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN HARRIS COUNTY
ToALONG FM 1960
CSJ0912-70-101
Proj IDNH 2017(160)
Work TypeCONST CURB RAMPS
 
0.0012708928.951149449.4342.4
Work Order12-12-16
Work Began04-19-17
Work Completed
Time Computed01-11-17
Contract Working Days200
Addl Days Granted0
Working Days Charged111
Percent Time Used55
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-101
STRIPE LINES, INC. (2.40)
TRAF-TEX, INC. (11.23)
BUYERS BARRICADES HOUSTON, LLC. (0.68)
Contract #10163026
Totals2708928.950.001149449.4342.4

CountyHARRIS
HighwayCS
FromMASON PARK PED/BIKE BRG, FROM TIPPS
ToST AT EVERGREEN DR TO 75TH ST
CSJ0912-70-103
Proj IDSTP 2015(559)TE
Work TypeCONST PED & BIKE BR
 
0.1805659268.003636397.0764.2
Work Order12-15-16
Work Began04-10-17
Work Completed
Time Computed02-13-17
Contract Working Days228
Addl Days Granted0
Working Days Charged225
Percent Time Used98
Contractor(s)
NBG CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-103
DORAN STEEL, INC. (0.75)
GEORGE MEEKS LANDPRO, INC. (4.41)
PFEIFFER & SON LTD. (5.13)
TAYLOR LIGHTNING PROTECTION (0.18)
LONESTAR TRAFFIC SAFETY, LLC (0.09)
CLODFELTER BRIDGE & STRUCTURES INTERNATIONAL, INC. (8.61)
Contract #06163221
Totals5659268.00733159.183636397.0764.2

CountyHARRIS
HighwayCR
FromBRAYS BAYOU, FROM MACGREGOR PARK
ToUNIVERISTY OF HOUSTON (WHEELER AVE)
CSJ0912-70-104
Proj IDSTP 2016(352)TE
Work TypeCONST BIKE/PED BR
 
0.4802330231.541900979.2782.0
Work Order09-16-16
Work Began01-23-17
Work Completed
Time Computed12-15-16
Contract Working Days150
Addl Days Granted0
Working Days Charged164
Percent Time Used109
Contractor(s)
ALTUS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-104
HOUSTON BARRICADES AND SUPPLY, LLC (0.39)
GROUND HOG FOUNDATION DRILLING (1.79)
HI-TECH CONCREE PUMPING SERVICES (0.32)
SPECIALTY DRILLING, LTD. (2.22)
LANDPRO, INC. (8.01)
COASTAL FOUNDATION DRILLING CO., INC. (1.28)
POOL CUSTOM IRON WORKS (0.16)
CONSOLIDATED CRANE & RIGGING (30.92)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.58)
SOUTHERN ELECTRICAL SERVICES, INC. (7.52)
Contract #08163055
Totals2330231.549196.921900979.2782.0

CountyHARRIS
HighwayCR
FromIH 69 S, FROM HAZARD STREET
ToMONTROSE BLVD
CSJ0912-70-105
Proj IDSTP 2014(128)TE
Work TypeINST BR LIGHT
 
0.2503061039.353452419.2899.9
Work Order05-16-16
Work Began09-12-16
Work Completed
Time Computed08-14-16
Contract Working Days157
Addl Days Granted0
Working Days Charged143
Percent Time Used91
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-105
SCOTT DERR PAINTING CO, LLC (11.59)
BUYERS BARRICADES, INC. (0.80)
Contract #02163247
Totals3061039.350.003452419.2899.9

CountyHARRIS
HighwayCS
FromCAROLINE STREET;ELGIN STREET
ToPIERCE STREET
CSJ0912-71-003
Proj IDC 912-71-3
Work TypeGR, STRS, BASE
 
0.68912380276.54156471.001.2
Work Order06-29-17
Work Began00-00-00
Work Completed
Time Computed08-28-17
Contract Working Days360
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-003
GULF COAST PAVERS, INC. (0.93)
VACA UNDERGROUND UTILITIES INC (29.69)
CONSTRUCTION ECO SERVICES (0.76)
DORAN STEEL, INC. (0.36)
LONE STAR TRAFFIC SERVICE, INC. (0.23)
S&S BRIDGE PAINTING (0.22)
REPUBLIC TRAFFIC SAFETY, INC. (0.00)
CHERRY CRUSHED CONCRETE (0.00)
STRAIGHT LINE CONCRETE (0.36)
Contract #04173038
Totals12380276.540.00156471.001.2

CountyHARRIS
HighwayCS
FromVARIOUS LOCATION IN HARRIS COUNTY
ToPRECINCT 1
CSJ0912-71-046
Proj IDC 912-71-46
Work TypeHARRIS COUNTY PRECINCT 1 RCTSS
 
0.0014241559.873834443.4290.4
Work Order10-28-14
Work Began11-13-14
Work Completed
Time Computed11-13-14
Contract Working Days300
Addl Days Granted0
Working Days Charged263
Percent Time Used87
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-046
ABC DIRECTIONAL DRILLING, INC. (4.67)
SCMU (0.00)
STRIPE LINES, INC. (1.41)
Contract #08143027
Totals4241559.870.003834443.4290.4

CountyHARRIS
HighwayCS
FromMARKET ST EB AT HUNTING BAYOU
ToHOUSTON
CSJ0912-71-078
Proj IDBR 99(271)
Work TypeREPLACE BRIDGE
 
0.1581687687.901121376.8966.5
Work Order02-07-17
Work Began10-24-17
Work Completed
Time Computed03-20-17
Contract Working Days148
Addl Days Granted0
Working Days Charged151
Percent Time Used102
Contractor(s)
TOM-MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-078
GMJ PAVING CO. (0.78)
STRIPE LINES, INC. (0.85)
FIRST KATY CONSTRUCTION (11.43)
JMHP, INC. (0.73)
CHERRY CRUSHED CONCRETE (2.67)
CURB PLANET INC. (0.04)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.39)
Contract #10163015
Totals1687687.90101528.241121376.8966.5

CountyHARRIS
HighwayMH
FromAIRPORT BLVD FROM HIRAM CLARKE ROAD
ToFM 521
CSJ0912-71-386
Proj IDHP 1702(559)
Work TypeGR, STRS & SURF
 
2.49818871436.452782711.1514.7
Work Order12-14-17
Work Began02-05-18
Work Completed
Time Computed02-12-18
Contract Working Days396
Addl Days Granted0
Working Days Charged23
Percent Time Used5
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-386
SOUTHLAND EXCAVATORS, INC. (0.51)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.96)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.69)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.46)
MESA ROD BUSTERS, INC. (0.07)
WILLOW CITY SIGN & RAIL, INC. (0.52)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.11)
PRIMATE CONSTRUCTION, INC. (0.98)
SCOTT DERR PAINTING CO, LLC (0.01)
Contract #11173002
Totals18871436.451609160.392782711.1514.7

CountyHARRIS
HighwayCS
FromON SOUTH SHAVER FROM GULF FRWY
ToSH 3
CSJ0912-71-688
Proj IDSTP 99(751)MM
Work TypeWIDEN TO 6 LANE DIVIDED
 
1.13813480682.2013529906.5199.9
Work Order04-23-13
Work Began06-24-13
Work Completed
Time Computed06-22-13
Contract Working Days404
Addl Days Granted0
Working Days Charged402
Percent Time Used99
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-688
CPAVE, INC. (0.54)
WILLOW CITY SIGN & RAIL, INC. (0.17)
INDUS CONSTRUCTION, L.P. (0.73)
APCON SERVICES, LLC (6.16)
GMJ PAVING CO. (5.12)
THIRD COAST SERVICES LLC (1.85)
EAGLE CONSTRUCTION AND ENVIRONMENTAL SERVICES, L.P. (0.70)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (1.01)
DUSTROL, INC. (0.54)
BORING & TUNNELING COMPANY OF AMERICA, INC. (0.03)
STRIPES & STOPS COMPANY, INC. (0.97)
ENVIRONMENTAL ALLIES, L.P. (0.30)
H & E AGGREGATE, LLC (2.77)
MCNORTON DEWATERING, INC. (0.06)
FIRST KATY CONSTRUCTION (1.32)
MICKIE SERVICE, INC. (0.03)
CURB PLANET INC. (0.02)
A1 EROSION CONTROL (1.07)
Contract #02133203
Totals13480682.200.0013529906.5199.9

CountyHARRIS
HighwayCS
FromBUFFALO BAYOU HERITAGE COR;MCKEE ST
ToJENSEN STREET
CSJ0912-71-799
Proj IDSTP 2002(151)TP
Work TypeGR, BS, REMOVE STRM SWR & PAV
 
1.0023745731.35428328.5011.4
Work Order01-25-18
Work Began00-00-00
Work Completed
Time Computed03-26-18
Contract Working Days162
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-799
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.93)
REPUBLIC TRAFFIC SAFETY, INC. (0.50)
SCAFFOLD MONKEY FIELD SERVICES, LLC (3.40)
Contract #11173212
Totals3745731.350.00428328.5011.4

CountyHARRIS
HighwayCS
FromGELLHORN,IH 610
ToWALLISVILLE RD.
CSJ0912-71-896
Proj IDSTP 1602(170)MM
Work TypeCONSTRUCT 4 LANE DIVIDED SECTION
 
0.7196095883.883309471.9354.2
Work Order11-01-17
Work Began01-24-18
Work Completed
Time Computed12-31-17
Contract Working Days263
Addl Days Granted0
Working Days Charged87
Percent Time Used33
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-896
PRV SERVICES, INC. (4.94)
SEMARCK LANDSCAPE SERVICES, INC. (1.65)
THIRD COAST SERVICES LLC (2.53)
MVA CONSTRUCTION LLC (0.34)
P&Z LOGISTICS INC. (0.50)
G & D DIRECCIONAL (0.19)
RUCKIT, INC. (0.15)
MONTALVO BRIDGE SYSTEMS, LLC (0.45)
Contract #06173234
Totals6095883.88659788.973309471.9354.2

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN HARRIS COUNTY
ToPRECINCT 2
CSJ0912-72-190
Proj IDC 912-72-190
Work TypeHARRIS COUNTY PRECINCT 2 RCTSS
 
0.0011906720.281785919.0793.6
Work Order10-28-14
Work Began11-13-15
Work Completed
Time Computed11-13-14
Contract Working Days220
Addl Days Granted0
Working Days Charged220
Percent Time Used100
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-190
SCMU (12.11)
ABC DIRECTIONAL DRILLING, INC. (4.29)
WALLACE CONCRETE SAWING (0.68)
BAY CITY TRAFFIC (1.68)
STRIPE LINES, INC. (1.39)
Contract #08143011
Totals1906720.2893589.491785919.0793.6

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN HARRIS COUNTY
ToPRECINCT 4
CSJ0912-72-199
Proj IDCM 2013(989)
Work TypeHARRIS COUNTY PRECINCT 4 RCTSS
 
0.0012561452.603072009.4099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-22-13
Work Began03-21-14
Work Completed
Time Computed03-21-14
Contract Working Days305
Addl Days Granted0
Working Days Charged289
Percent Time Used94
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-199
VERSALINK MEDIA (6.77)
SPRING CREEK CONSTRUCTION, INC. (17.27)
DYNAMIC VISION CO., INC. (6.55)
Contract #08133042
Totals2561452.600.003072009.4099.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10