Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | VAN ZANDT |
Highway | CR |
From | STR NO 101, CR 1102, BUFFALO CREEK |
To | . |
CSJ | 0910-12-139 |
Proj ID | BR 2023(449) |
Work Type | BRIDGE REPLACEMENT |
|
| | 1393629.50 | | 1255283.36 | 90.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 07-26-23 |
Work Began | 09-12-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 0 |
Working Days Charged | 92 |
Percent Time Used | 76 |
Contractor(s) |
TRUE ROADS CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0910-12-139 AWP SAFETY (0.46) DUSTIN ALLEN, INC. (3.84) SOUTHWEST ENVIRONMENT SERVICES LLC (0.25) M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.06) ISAACS CONSTRUCTION SERVICES LLC (0.72) RAYFORD"S TRUCK & TRACTOR (0.97)
|
Contract # | 06233433 |
| Totals | 1393629.50 | 111437.20 | 1255283.36 | 90.0 |
|
County | VAN ZANDT |
Highway | VA |
From | VARIOUS LOCATIONS IN |
To | VAN ZANDT CO |
CSJ | 0910-12-140 |
Proj ID | STP 2B23(065)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 671280.00 | | 409680.00 | 61.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 09-06-23 |
Work Began | 02-01-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 43 |
Addl Days Granted | 0 |
Working Days Charged | 28 |
Percent Time Used | 65 |
Contractor(s) |
MARCOM'S MOWING SERVICE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0910-12-140 BUSHWACKERS CONTRACTING, LLC (11.17) AWP SAFETY (1.46) CATOCON, INC. (3.64)
|
Contract # | 08233047 |
| Totals | 671280.00 | 44998.00 | 409680.00 | 61.0 |
|
County | VAN ZANDT |
Highway | VA |
From | VARIOUS LOCATIONS IN |
To | VAN ZANDT CO |
CSJ | 0910-12-141 |
Proj ID | STP 2024(855)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 450860.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 72 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
MARCOM'S MOWING SERVICE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0910-12-141 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04243034 |
| Totals | 450860.00 | 0.00 | 0.00 | 0.0 |
|
County | SMITH |
Highway | PW |
From | VARIOUS LOCATION WITHIN |
To | OLD SABINE BOTTOM WMA |
CSJ | 0910-16-122 |
Proj ID | C 910-16-122 |
Work Type | TEXAS PARK AND WILDLIFE |
|
| 1.000 | 855380.51 | | 823433.00 | 96.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 07-19-23 |
Work Began | 08-11-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 88 |
Addl Days Granted | 0 |
Working Days Charged | 34 |
Percent Time Used | 38 |
Contractor(s) |
SCOUT 5 CONSTRUCTION LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-122 CAP RIVER LLC (3.78) LIQUID LAWNS HYDROMULCH CORPORATION (3.21)
|
Contract # | 06233235 |
| Totals | 855380.51 | 10935.75 | 823433.00 | 96.2 |
|
County | SMITH |
Highway | CS |
From | WHITTLE AT W. MUD CREEK TRIB |
To | IN TYLER, W OF FM 2493 |
CSJ | 0910-16-147 |
Proj ID | BR 2020(895) |
Work Type | BRIDGE REPLACEMENT |
|
| | 383095.26 | | 441630.49 | 99.9 |
County | SMITH |
Highway | CR |
From | CR2110 AT KICKAPOO CREEK |
To | S OF ARP, E OF SH 135 |
CSJ | 0910-16-148 |
Proj ID | BR 2020(896) |
Work Type | BRIDGE REPLACEMENT |
|
| | 460280.04 | | 487739.33 | 99.9 |
County | SMITH |
Highway | CR |
From | CR289 AT PRAIRIE CREEK |
To | BETWEEN SH 64 AND OLD OMEN RD |
CSJ | 0910-16-149 |
Proj ID | BR 2020(897) |
Work Type | BRIDGE REPLACEMENT |
|
| | 414918.40 | | 448070.65 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 02-16-22 |
Work Began | 03-17-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 0 |
Working Days Charged | 147 |
Percent Time Used | 81 |
Contractor(s) |
THK CONSTRUCTION LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-147 HODGES AND SON CONSTRUCTION COMPANY, INC. (6.45) MORRIS COUNTY CONTRACTORS, L.L.C. (4.20) PANOLA SIGN & BARRICADE, INC. (1.01) PEACHTREE CONSTRUCTION, LTD. (10.89) TORO BRAVO CONSTRUCTION, LLC (0.45) SOUTHWEST ENVIRONMENT SERVICES LLC (0.18)
|
Contract # | 01223220 |
| Totals | 1258293.70 | 0.00 | 1377440.47 | 99.9 |
|
County | SMITH |
Highway | CR |
From | RATTLESNAKE CR |
To | . |
CSJ | 0910-16-154 |
Proj ID | BR 2022(769) |
Work Type | BRIDGE REPLACEMENT |
|
| | 468056.50 | | 269172.50 | 57.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 06-14-23 |
Work Began | 01-29-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 59 |
Addl Days Granted | 0 |
Working Days Charged | 44 |
Percent Time Used | 74 |
Contractor(s) |
HIGHWAY 19 CONSTRUCTION LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-154 AWP SAFETY (0.90)
|
Contract # | 05233050 |
| Totals | 468056.50 | 27120.00 | 269172.50 | 57.5 |
|
County | SMITH |
Highway | CR |
From | STR NO 104, CR 35, HITTS CREEK TRIB |
To | . |
CSJ | 0910-16-156 |
Proj ID | BR 2022(748) |
Work Type | BRIDGE REPLACEMENT |
|
| | 4280740.25 | | 2365805.12 | 55.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 07-26-23 |
Work Began | 09-05-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 523 |
Addl Days Granted | 0 |
Working Days Charged | 111 |
Percent Time Used | 21 |
Contractor(s) |
BAKER & COMPANY CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-156 A. L. HELMCAMP, INC. (0.49) FLEX SUPPLY, LLC (0.70) NEED GRASS NOW LLC (0.47) TEXANA LAND & ASPHALT, INC. (7.45) FORTSON CONTRACTING, INC. (7.00) JM YANEZ CONSTRUCTION, INC. (26.83) COLD CREEK CONSTRUCTION, LTD (2.12) CARTHAGE DRILLING, LLC (4.59) STRIPING TECHNOLOGY, L.P. (0.13)
|
Contract # | 06233420 |
| Totals | 4280740.25 | 178492.50 | 2365805.12 | 55.2 |
|
County | SMITH |
Highway | VA |
From | STEWART PARK |
To | PEETE ELEMENTARY |
CSJ | 0910-16-162 |
Proj ID | STP 2023(201)TAPS |
Work Type | PEDESTRIAN, SIDEWALKS & CURB RAMPS |
|
| | 2988318.62 | | 1599703.40 | 53.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 09-13-23 |
Work Began | 10-03-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 209 |
Addl Days Granted | 0 |
Working Days Charged | 101 |
Percent Time Used | 48 |
Contractor(s) |
THK CONSTRUCTION LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-162 PATTERSON"S COMPLETE TREE SERVICE LLC (4.14) CAP RIVER LLC (2.50) ISAACS CONSTRUCTION SERVICES LLC (2.48) SOUTHWEST ENVIRONMENT SERVICES LLC (0.78) PANOLA SIGN & BARRICADE, INC. (0.88) STRIPING TECHNOLOGY, L.P. (2.62) J. H. ODEN CONTRACTING COMPANY (1.54)
|
Contract # | 08233233 |
| Totals | 2988318.62 | 187554.70 | 1599703.40 | 53.5 |
|
County | SMITH |
Highway | CS |
From | N BROADWAY |
To | AT W 26TH ST |
CSJ | 0910-16-163 |
Proj ID | STP 2023(726)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 95960.00 | | 92558.75 | 96.4 |
County | SMITH |
Highway | CS |
From | SHILOH RD |
To | GRANDE BLVD |
CSJ | 0910-16-164 |
Proj ID | STP 2023(726)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 643977.00 | | 626114.83 | 97.2 |
Work Order | 06-14-23 |
Work Began | 07-21-23 |
Work Completed | |
Time Computed | 07-21-23 |
Contract Working Days | 64 |
Addl Days Granted | 0 |
Working Days Charged | 63 |
Percent Time Used | 98 |
Contractor(s) |
TIGHT LINE CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-163 STRIPING TECHNOLOGY, L.P. (58.60) FLEX SUPPLY, LLC (1.31)
|
Contract # | 05233047 |
| Totals | 739937.00 | 0.00 | 718673.58 | 97.1 |
|
County | SMITH |
Highway | VA |
From | VARIOUS LOCATIONS IN SMITH COUNTY |
To | . |
CSJ | 0910-16-166 |
Proj ID | STP 2023(729)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 551528.50 | | 560610.50 | 99.9 |
County | WOOD |
Highway | VA |
From | VARIOUS LOCATIONS IN |
To | WOOD CO |
CSJ | 0910-35-040 |
Proj ID | STP 2023(729)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 374185.50 | | 368585.50 | 98.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 06-21-23 |
Work Began | 09-12-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 63 |
Addl Days Granted | 0 |
Working Days Charged | 53 |
Percent Time Used | 84 |
Contractor(s) |
CROSS PLUS CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-166 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05233240 |
| Totals | 925714.00 | 136150.00 | 929196.00 | 99.9 |
|
County | SMITH |
Highway | VA |
From | VARIOUS LOCATIONS IN |
To | TYLER STATE PARK |
CSJ | 0910-16-168 |
Proj ID | C 910-16-168 |
Work Type | TEXAS PARK AND WILDLIFE |
|
| | 921722.85 | | 947575.42 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 01-12-23 |
Work Began | 03-08-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 123 |
Addl Days Granted | 0 |
Working Days Charged | 123 |
Percent Time Used | 100 |
Contractor(s) |
EAST TEXAS BRIDGE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-168 STRIPING TECHNOLOGY, L.P. (0.52) PANOLA SIGN & BARRICADE, INC. (0.92) ISAACS CONSTRUCTION SERVICES LLC (0.62) INNOVATIVE ROADWAY SOLUTIONS, LLC (17.28)
|
Contract # | 12223024 |
| Totals | 921722.85 | 0.00 | 947575.42 | 99.9 |
|
County | SMITH |
Highway | VA |
From | VARIOUS LOCATIONS IN |
To | WHITEHOUSE |
CSJ | 0910-16-169 |
Proj ID | F 2022(028) |
Work Type | LANDSCAPE & SCENIC ENHANCEMENT |
|
| | 157495.00 | | 157155.64 | 99.7 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 10-20-21 |
Work Began | 01-03-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 86 |
Addl Days Granted | 0 |
Working Days Charged | 81 |
Percent Time Used | 94 |
Contractor(s) |
TIGHT LINE CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-169 STRIPING TECHNOLOGY, L.P. (8.32)
|
Contract # | 09213218 |
| Totals | 157495.00 | 0.00 | 157155.64 | 99.7 |
|
County | SMITH |
Highway | VA |
From | VARIOUS LOCATIONS IN |
To | THE CITY OF TYLER |
CSJ | 0910-16-178 |
Proj ID | STP 2024(808)VRU |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 1451085.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 73 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
SYNERGY SIGNS & SERVICES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-178 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03243034 |
| Totals | 1451085.00 | 0.00 | 0.00 | 0.0 |
|
County | SMITH |
Highway | VA |
From | VARIOUS LOCATIONS IN THE TYLER DISTRICT |
To | . |
CSJ | 0910-16-181 |
Proj ID | STP 2B23(178)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 143045.00 | | 89045.00 | 62.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 09-26-23 |
Work Began | 01-02-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 15 |
Addl Days Granted | 0 |
Working Days Charged | 6 |
Percent Time Used | 40 |
Contractor(s) |
TEXAS TRAFFIC CONTROL SYSTEMS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-181 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08233065 |
| Totals | 143045.00 | 0.00 | 89045.00 | 62.2 |
|
County | SMITH |
Highway | VA |
From | VARIOUS LOCATIONS IN SMITH COUNTY |
To | . |
CSJ | 0910-16-182 |
Proj ID | STP 2024(336)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 232606.44 | | 194741.95 | 83.7 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 12-21-23 |
Work Began | 02-20-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 33 |
Addl Days Granted | 0 |
Working Days Charged | 19 |
Percent Time Used | 57 |
Contractor(s) |
SNOWHILL CONTRACTING LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-182 FLEX SUPPLY, LLC (2.36)
|
Contract # | 11233221 |
| Totals | 232606.44 | 87484.25 | 194741.95 | 83.7 |
|
County | SMITH |
Highway | CS |
From | GLENEAGLES DR. |
To | SHADY OAKS DR |
CSJ | 0910-16-183 |
Proj ID | STP 2B23(179)HESG |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 108505.50 | | 109123.50 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 09-06-23 |
Work Began | 12-05-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 13 |
Addl Days Granted | 0 |
Working Days Charged | 12 |
Percent Time Used | 92 |
Contractor(s) |
MARCOM'S MOWING SERVICE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-183 AWP SAFETY (4.60) STRIPING TECHNOLOGY, L.P. (18.25)
|
Contract # | 08233064 |
| Totals | 108505.50 | 0.00 | 109123.50 | 99.9 |
|
County | HENDERSON |
Highway | VA |
From | VARIOUS LOCATIONS ON |
To | STATE LOOP 7 IN ATHENS |
CSJ | 0910-34-037 |
Proj ID | F 2022(757) |
Work Type | LANDSCAPE & SCENIC ENHANCEMENT |
|
| | 173162.00 | | 176709.34 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 07-20-22 |
Work Began | 10-07-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 64 |
Addl Days Granted | 0 |
Working Days Charged | 31 |
Percent Time Used | 48 |
Contractor(s) |
TIGHT LINE CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0910-34-037 AQUA BORE, LLC (2.65) STRIPING TECHNOLOGY, L.P. (4.99)
|
Contract # | 06223641 |
| Totals | 173162.00 | 0.00 | 176709.34 | 99.9 |
|
County | CHEROKEE |
Highway | VA |
From | VARIOUS LOCATIONS IN |
To | CHEROKEE CO |
CSJ | 0910-36-134 |
Proj ID | STP 2B23(066)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 532752.50 | | 203077.27 | 38.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 09-07-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 40 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
GARRET SHIELDS INFRASTRUCTURE |
SUBCONTRACTOR(S) FOR CCSJ: 0910-36-134 A&W FIELD SERVICES, LLC (11.26)
|
Contract # | 08233260 |
| Totals | 532752.50 | 22369.27 | 203077.27 | 38.1 |
|
County | VAN ZANDT |
Highway | FM 859 |
From | SH 19 |
To | US 80 |
CSJ | 1171-01-022 |
Proj ID | STP 2022(813)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 3629409.25 | | 3947739.97 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 09-15-22 |
Work Began | 10-17-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 166 |
Addl Days Granted | 13 |
Working Days Charged | 179 |
Percent Time Used | 100 |
Contractor(s) |
BAKER & COMPANY CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 1171-01-022 TEXANA LAND & ASPHALT, INC. (12.92) LINEAR TRAFFIC MARKINGS LLC (0.29) J. H. ODEN CONTRACTING COMPANY (1.48) FORTSON CONTRACTING, INC. (2.83) JM YANEZ CONSTRUCTION, INC. (20.17) FLEX SUPPLY, LLC (0.44) DUSTROL, INC. (0.38) COLD CREEK CONSTRUCTION, LTD (10.48) NEED GRASS NOW LLC (0.96) MISSOURI PETROLEUM PRODUCTS COMPANY LLC (0.55)
|
Contract # | 08223219 |
| Totals | 3629409.25 | 0.00 | 3947739.97 | 99.9 |
|
County | VAN ZANDT |
Highway | FM 1255 |
From | IH 20 |
To | SH 110 |
CSJ | 1322-02-017 |
Proj ID | F 2024(023) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| | 17084796.24 | | 4418693.61 | 25.8 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 10-12-23 |
Work Began | 11-15-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 363 |
Addl Days Granted | 0 |
Working Days Charged | 60 |
Percent Time Used | 16 |
Contractor(s) |
REYNOLDS & KAY, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1322-02-017 DUSTIN ALLEN, INC. (0.56) TRUE ROADS CONSTRUCTION, LLC (10.52) STRIPING TECHNOLOGY, L.P. (2.35) TEX OP CONSTRUCTION, LP (0.36) SOUTHWEST ENVIRONMENT SERVICES LLC (1.81) FLEX SUPPLY, LLC (0.18) PATTERSON"S COMPLETE TREE SERVICE LLC (0.98) ISAACS CONSTRUCTION SERVICES LLC (0.45)
|
Contract # | 09233206 |
| Totals | 17084796.24 | 1438842.10 | 4418693.61 | 25.8 |
|