Monthly State Let Construction Report For Tyler District As Of Apr 12, 2024 Page 5 Of 6

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyVAN ZANDT
HighwayCR
FromSTR NO 101, CR 1102, BUFFALO CREEK
To.
CSJ0910-12-139
Proj IDBR 2023(449)
Work TypeBRIDGE REPLACEMENT
 
1393629.501255283.3690.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-26-23
Work Began09-12-23
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged92
Percent Time Used76
Contractor(s)
TRUE ROADS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-12-139
AWP SAFETY (0.46)
DUSTIN ALLEN, INC. (3.84)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.25)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.06)
ISAACS CONSTRUCTION SERVICES LLC (0.72)
RAYFORD"S TRUCK & TRACTOR (0.97)
Contract #06233433
Totals1393629.50111437.201255283.3690.0

CountyVAN ZANDT
HighwayVA
FromVARIOUS LOCATIONS IN
ToVAN ZANDT CO
CSJ0910-12-140
Proj IDSTP 2B23(065)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
671280.00409680.0061.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-06-23
Work Began02-01-24
Work Completed
Time Computed00-00-00
Contract Working Days43
Addl Days Granted0
Working Days Charged28
Percent Time Used65
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-12-140
BUSHWACKERS CONTRACTING, LLC (11.17)
AWP SAFETY (1.46)
CATOCON, INC. (3.64)
Contract #08233047
Totals671280.0044998.00409680.0061.0

CountyVAN ZANDT
HighwayVA
FromVARIOUS LOCATIONS IN
ToVAN ZANDT CO
CSJ0910-12-141
Proj IDSTP 2024(855)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
450860.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-12-141
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04243034
Totals450860.000.000.000.0

CountySMITH
HighwayPW
FromVARIOUS LOCATION WITHIN
ToOLD SABINE BOTTOM WMA
CSJ0910-16-122
Proj IDC 910-16-122
Work TypeTEXAS PARK AND WILDLIFE
 
1.000855380.51823433.0096.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-19-23
Work Began08-11-23
Work Completed
Time Computed00-00-00
Contract Working Days88
Addl Days Granted0
Working Days Charged34
Percent Time Used38
Contractor(s)
SCOUT 5 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-122
CAP RIVER LLC (3.78)
LIQUID LAWNS HYDROMULCH CORPORATION (3.21)
Contract #06233235
Totals855380.5110935.75823433.0096.2

CountySMITH
HighwayCS
FromWHITTLE AT W. MUD CREEK TRIB
ToIN TYLER, W OF FM 2493
CSJ0910-16-147
Proj IDBR 2020(895)
Work TypeBRIDGE REPLACEMENT
 
383095.26441630.4999.9
CountySMITH
HighwayCR
FromCR2110 AT KICKAPOO CREEK
ToS OF ARP, E OF SH 135
CSJ0910-16-148
Proj IDBR 2020(896)
Work TypeBRIDGE REPLACEMENT
 
460280.04487739.3399.9
CountySMITH
HighwayCR
FromCR289 AT PRAIRIE CREEK
ToBETWEEN SH 64 AND OLD OMEN RD
CSJ0910-16-149
Proj IDBR 2020(897)
Work TypeBRIDGE REPLACEMENT
 
414918.40448070.6599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-16-22
Work Began03-17-22
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged147
Percent Time Used81
Contractor(s)
THK CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-147
HODGES AND SON CONSTRUCTION COMPANY, INC. (6.45)
MORRIS COUNTY CONTRACTORS, L.L.C. (4.20)
PANOLA SIGN & BARRICADE, INC. (1.01)
PEACHTREE CONSTRUCTION, LTD. (10.89)
TORO BRAVO CONSTRUCTION, LLC (0.45)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.18)
Contract #01223220
Totals1258293.700.001377440.4799.9

CountySMITH
HighwayCR
FromRATTLESNAKE CR
To.
CSJ0910-16-154
Proj IDBR 2022(769)
Work TypeBRIDGE REPLACEMENT
 
468056.50269172.5057.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-23
Work Began01-29-24
Work Completed
Time Computed00-00-00
Contract Working Days59
Addl Days Granted0
Working Days Charged44
Percent Time Used74
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-154
AWP SAFETY (0.90)
Contract #05233050
Totals468056.5027120.00269172.5057.5

CountySMITH
HighwayCR
FromSTR NO 104, CR 35, HITTS CREEK TRIB
To.
CSJ0910-16-156
Proj IDBR 2022(748)
Work TypeBRIDGE REPLACEMENT
 
4280740.252365805.1255.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-26-23
Work Began09-05-23
Work Completed
Time Computed00-00-00
Contract Working Days523
Addl Days Granted0
Working Days Charged111
Percent Time Used21
Contractor(s)
BAKER & COMPANY CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-156
A. L. HELMCAMP, INC. (0.49)
FLEX SUPPLY, LLC (0.70)
NEED GRASS NOW LLC (0.47)
TEXANA LAND & ASPHALT, INC. (7.45)
FORTSON CONTRACTING, INC. (7.00)
JM YANEZ CONSTRUCTION, INC. (26.83)
COLD CREEK CONSTRUCTION, LTD (2.12)
CARTHAGE DRILLING, LLC (4.59)
STRIPING TECHNOLOGY, L.P. (0.13)
Contract #06233420
Totals4280740.25178492.502365805.1255.2

CountySMITH
HighwayVA
FromSTEWART PARK
ToPEETE ELEMENTARY
CSJ0910-16-162
Proj IDSTP 2023(201)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
2988318.621599703.4053.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-13-23
Work Began10-03-23
Work Completed
Time Computed00-00-00
Contract Working Days209
Addl Days Granted0
Working Days Charged101
Percent Time Used48
Contractor(s)
THK CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-162
PATTERSON"S COMPLETE TREE SERVICE LLC (4.14)
CAP RIVER LLC (2.50)
ISAACS CONSTRUCTION SERVICES LLC (2.48)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.78)
PANOLA SIGN & BARRICADE, INC. (0.88)
STRIPING TECHNOLOGY, L.P. (2.62)
J. H. ODEN CONTRACTING COMPANY (1.54)
Contract #08233233
Totals2988318.62187554.701599703.4053.5

CountySMITH
HighwayCS
FromN BROADWAY
ToAT W 26TH ST
CSJ0910-16-163
Proj IDSTP 2023(726)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
95960.0092558.7596.4
CountySMITH
HighwayCS
FromSHILOH RD
ToGRANDE BLVD
CSJ0910-16-164
Proj IDSTP 2023(726)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
643977.00626114.8397.2
Work Order06-14-23
Work Began07-21-23
Work Completed
Time Computed07-21-23
Contract Working Days64
Addl Days Granted0
Working Days Charged63
Percent Time Used98
Contractor(s)
TIGHT LINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-163
STRIPING TECHNOLOGY, L.P. (58.60)
FLEX SUPPLY, LLC (1.31)
Contract #05233047
Totals739937.000.00718673.5897.1

CountySMITH
HighwayVA
FromVARIOUS LOCATIONS IN SMITH COUNTY
To.
CSJ0910-16-166
Proj IDSTP 2023(729)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
551528.50560610.5099.9
CountyWOOD
HighwayVA
FromVARIOUS LOCATIONS IN
ToWOOD CO
CSJ0910-35-040
Proj IDSTP 2023(729)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
374185.50368585.5098.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-21-23
Work Began09-12-23
Work Completed
Time Computed00-00-00
Contract Working Days63
Addl Days Granted0
Working Days Charged53
Percent Time Used84
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-166
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05233240
Totals925714.00136150.00929196.0099.9

CountySMITH
HighwayVA
FromVARIOUS LOCATIONS IN
ToTYLER STATE PARK
CSJ0910-16-168
Proj IDC 910-16-168
Work TypeTEXAS PARK AND WILDLIFE
 
921722.85947575.4299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-12-23
Work Began03-08-23
Work Completed
Time Computed00-00-00
Contract Working Days123
Addl Days Granted0
Working Days Charged123
Percent Time Used100
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-168
STRIPING TECHNOLOGY, L.P. (0.52)
PANOLA SIGN & BARRICADE, INC. (0.92)
ISAACS CONSTRUCTION SERVICES LLC (0.62)
INNOVATIVE ROADWAY SOLUTIONS, LLC (17.28)
Contract #12223024
Totals921722.850.00947575.4299.9

CountySMITH
HighwayVA
FromVARIOUS LOCATIONS IN
ToWHITEHOUSE
CSJ0910-16-169
Proj IDF 2022(028)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
157495.00157155.6499.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-20-21
Work Began01-03-22
Work Completed
Time Computed00-00-00
Contract Working Days86
Addl Days Granted0
Working Days Charged81
Percent Time Used94
Contractor(s)
TIGHT LINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-169
STRIPING TECHNOLOGY, L.P. (8.32)
Contract #09213218
Totals157495.000.00157155.6499.7

CountySMITH
HighwayVA
FromVARIOUS LOCATIONS IN
ToTHE CITY OF TYLER
CSJ0910-16-178
Proj IDSTP 2024(808)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1451085.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days73
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SYNERGY SIGNS & SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-178
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243034
Totals1451085.000.000.000.0

CountySMITH
HighwayVA
FromVARIOUS LOCATIONS IN THE TYLER DISTRICT
To.
CSJ0910-16-181
Proj IDSTP 2B23(178)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
143045.0089045.0062.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-26-23
Work Began01-02-24
Work Completed
Time Computed00-00-00
Contract Working Days15
Addl Days Granted0
Working Days Charged6
Percent Time Used40
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-181
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08233065
Totals143045.000.0089045.0062.2

CountySMITH
HighwayVA
FromVARIOUS LOCATIONS IN SMITH COUNTY
To.
CSJ0910-16-182
Proj IDSTP 2024(336)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
232606.44194741.9583.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-21-23
Work Began02-20-24
Work Completed
Time Computed00-00-00
Contract Working Days33
Addl Days Granted0
Working Days Charged19
Percent Time Used57
Contractor(s)
SNOWHILL CONTRACTING LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-182
FLEX SUPPLY, LLC (2.36)
Contract #11233221
Totals232606.4487484.25194741.9583.7

CountySMITH
HighwayCS
FromGLENEAGLES DR.
ToSHADY OAKS DR
CSJ0910-16-183
Proj IDSTP 2B23(179)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
108505.50109123.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-06-23
Work Began12-05-23
Work Completed
Time Computed00-00-00
Contract Working Days13
Addl Days Granted0
Working Days Charged12
Percent Time Used92
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-183
AWP SAFETY (4.60)
STRIPING TECHNOLOGY, L.P. (18.25)
Contract #08233064
Totals108505.500.00109123.5099.9

CountyHENDERSON
HighwayVA
FromVARIOUS LOCATIONS ON
ToSTATE LOOP 7 IN ATHENS
CSJ0910-34-037
Proj IDF 2022(757)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
173162.00176709.3499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-22
Work Began10-07-22
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged31
Percent Time Used48
Contractor(s)
TIGHT LINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-34-037
AQUA BORE, LLC (2.65)
STRIPING TECHNOLOGY, L.P. (4.99)
Contract #06223641
Totals173162.000.00176709.3499.9

CountyCHEROKEE
HighwayVA
FromVARIOUS LOCATIONS IN
ToCHEROKEE CO
CSJ0910-36-134
Proj IDSTP 2B23(066)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
532752.50203077.2738.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-07-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 0910-36-134
A&W FIELD SERVICES, LLC (11.26)
Contract #08233260
Totals532752.5022369.27203077.2738.1

CountyVAN ZANDT
HighwayFM 859
FromSH 19
ToUS 80
CSJ1171-01-022
Proj IDSTP 2022(813)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3629409.253947739.9799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-22
Work Began10-17-22
Work Completed
Time Computed00-00-00
Contract Working Days166
Addl Days Granted13
Working Days Charged179
Percent Time Used100
Contractor(s)
BAKER & COMPANY CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1171-01-022
TEXANA LAND & ASPHALT, INC. (12.92)
LINEAR TRAFFIC MARKINGS LLC (0.29)
J. H. ODEN CONTRACTING COMPANY (1.48)
FORTSON CONTRACTING, INC. (2.83)
JM YANEZ CONSTRUCTION, INC. (20.17)
FLEX SUPPLY, LLC (0.44)
DUSTROL, INC. (0.38)
COLD CREEK CONSTRUCTION, LTD (10.48)
NEED GRASS NOW LLC (0.96)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC (0.55)
Contract #08223219
Totals3629409.250.003947739.9799.9

CountyVAN ZANDT
HighwayFM 1255
FromIH 20
ToSH 110
CSJ1322-02-017
Proj IDF 2024(023)
Work TypeREHABILITATION OF EXISTING ROAD
 
17084796.244418693.6125.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-12-23
Work Began11-15-23
Work Completed
Time Computed00-00-00
Contract Working Days363
Addl Days Granted0
Working Days Charged60
Percent Time Used16
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1322-02-017
DUSTIN ALLEN, INC. (0.56)
TRUE ROADS CONSTRUCTION, LLC (10.52)
STRIPING TECHNOLOGY, L.P. (2.35)
TEX OP CONSTRUCTION, LP (0.36)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.81)
FLEX SUPPLY, LLC (0.18)
PATTERSON"S COMPLETE TREE SERVICE LLC (0.98)
ISAACS CONSTRUCTION SERVICES LLC (0.45)
Contract #09233206
Totals17084796.241438842.104418693.6125.8

page 1 | page 2 | page 3 | page 4 | page 5 | page 6