Monthly State Let Construction Report For Tyler District As Of May 15, 2013 Page 1 Of 2

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCHEROKEE
Highway SH 294
From .9 MI E OF FM 23,E
To 3 MI W OF FM 752 (CR 2326)
CSJ 0058-04-018
Proj ID STP 2013(241)HES
Work Type SBGR WDN, LVL - UP, OCST, STRS, OCST, MBGF
 
19.881 6037332.46 2496778.00 4319550.05 71.5
Work Order 01-18-13
Work Began 02-22-13
Work Completed  
Time Computed 02-03-13
Contract Working Days 170
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 27
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0058-04-018
FORTSON CONTRACTING, INC.(1.58%)
COWBELL TRAFFIC SERVICES, INC. (0.25%)
AMERICAN REMEDIATION OPTIONS, INC. (0.51%)
STRIPING TECHNOLOGY, L.P.(2.56%)
J. M. CONSTRUCTION (0.00%)
J & M CONSTRUCTION (0.00%)
HIGHWAY 19 CONSTRUCTION, LLC (3.94%)
Contract # 12123012
Totals 6037332.46 2496778.00 4319550.05 71.5

CountyVAN ZANDT
Highway US 80 ETC
From .4 MI W OF FM1504(EDGWD W CTY LIM)E
To SH 19
CSJ 0095-06-066
Proj ID STP 2013(165)
Work Type SEAL COAT & PAVEMENT MARKINGS
 
196.928 8515839.36 437194.11 1949620.67 22.8
Work Order 01-04-13
Work Began 00-00-00
Work Completed  
Time Computed 06-01-13
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0095-06-066
STRIPE-A-ZONE, INC.( 12.68%)
BRYDL CONTRACTING, INC.(0.91%)
Contract # 11123222
Totals 8515839.36 437194.11 1949620.67 22.8

CountyGREGG
Highway US 80
From 0.35 MI E OF SH 42 IN WHITE OAK, E
To 1.4 MI W OF SL 281(FISHER RD)IN LVW
CSJ 0096-04-065
Proj ID STP 2013(206)
Work Type GR, BS, HMAC SURF, STRM SWR, C & G, SIGNS
 
1.558 3482669.95 240752.81 815471.53 23.4
Work Order 01-31-13
Work Began 02-18-13
Work Completed  
Time Computed 02-16-13
Contract Working Days 221
Addl Days Granted 3
Working Days Charged 50
Percent Time Used 22
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0096-04-065
RICE ENVIRONMENTAL SERVICES(1.23%)
COWBELL TRAFFIC SERVICES, INC. (0.38%)
DUSTROL, INC.(1.15%)
G & L FLOWERS TRUCKING (2.00%)
STRIPING TECHNOLOGY, L.P.(1.14%)
Contract # 12123218
Totals 3482669.95 240752.81 815471.53 23.4

CountyHENDERSON
Highway SH 19
From 4.1 MI N OF FM 837 (CR 468N), N
To 3.5 MI S OF FM 1615 (COON CRK BRG)
CSJ 0108-05-014
Proj ID C 108-5-14
Work Type GR, STRS, HMA BS & SURF, OCST, LVL - UP
 
4.636 6385017.81 144154.89 1355631.42 21.2
Work Order 10-18-12
Work Began 11-19-12
Work Completed  
Time Computed 11-03-12
Contract Working Days 265
Addl Days Granted 0
Working Days Charged 83
Percent Time Used 31
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0108-05-014
HIGHWAY TECHNOLOGIES, INC. (0.29%)
COX PAVING COMPANY, L.P. (4.37%)
D. I. J. CONSTRUCTION, INC.(1.01%)
FORTSON CONTRACTING, INC.(1.50%)
3LW MANAGEMENT, LLC(9.06%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(1.51%)
Contract # 08123224
Totals 6385017.81 144154.89 1355631.42 21.2

CountyANDERSON
Highway US 84
From 0.8 MI S OF US 79 (REAGAN ST), S
To US 287/US 84 SPLIT IN PALESTINE
CSJ 0109-01-056
Proj ID STP 2013(396)
Work Type PLANING, OCST, ACP SURF, PVMT MRKG
 
2.009 1122811.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 06-01-13
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0109-01-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133205
Totals 1122811.60 0.00 0.00 0.0

CountyRUSK
Highway US 259
From AT FM 1798, NEAR MINDEN
To .
CSJ 0138-05-052
Proj ID STP 1102(218)SB
Work Type GR, STRS, FLX & ACP BS, SURF, SIGN, ILUMTN
 
0.766 5497236.41 369774.56 4131796.12 75.1
Work Order 08-11-11
Work Began 06-04-12
Work Completed  
Time Computed 01-02-12
Contract Working Days 263
Addl Days Granted 60
Working Days Charged 250
Percent Time Used 77
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0138-05-052
AMERICAN REMEDIATION OPTIONS, INC. (2.06%)
STRIPING TECHNOLOGY, L.P.(2.83%)
COWBELL TRAFFIC SERVICES, INC. (0.09%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.05%)
SCOTT DERR PAINTING CO, LLC(0.10%)
PANOLA SIGN & BARRICADE, INC.(0.23%)
MAC TRANSPORTATION, LTD, L.L.P.(3.32%)
MESA ROD BUSTERS, INC. (0.07%)
R & R TELCO ENTERPRISES, INC.(0.12%)
Contract # 06113241
Totals 5497236.41 369774.56 4131796.12 75.1

CountyHENDERSON
Highway SH 31
From 0.34 MI W OF FM 773 (BEG C&G), E
To 1.1 MI W OF FM 1803(W) IN MURCHISON
CSJ 0164-01-068
Proj ID STP 2013(549)
Work Type PVMT RPR, PLNG, CAM, OCST, HARST, HMAC
 
7.862 4945961.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0164-01-068
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133218
Totals 4945961.90 0.00 0.00 0.0

CountyHENDERSON
Highway BU 175G
From 0.5 MI S OF US175/LP7 (PATTERSON),S
To 0.6 MI S OF US175/LP7 IN ATHENS
CSJ 0197-06-049
Proj ID NH 2011(838)
Work Type STRUCTURE, IRRIG SYST, SOD, PLANTS
 
0.087 125575.00 500.00 129121.85 99.9
Work Order 04-19-11
Work Began 05-24-11
Work Completed  
Time Computed 05-05-11
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 97
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0197-06-049
HIGHWAY TECHNOLOGIES, INC. (0.99%)
Contract # 03113205
Totals 125575.00 500.00 129121.85 99.9

CountyHENDERSON
Highway US 175
From 1.4 MI NW OF OF SL 60(N), SE
To 1.4 MI SE OF SL 60(S) (CR 4403)
CSJ 0198-02-032
Proj ID STP 2012(147)HES
Work Type SBGR WDN, ACP BS, OCST, SURF, STRS, PVMK
 
8.556 3425092.38 75250.00 2383237.97 70.7
CountyHENDERSON
Highway FM 773
From 0.2 MI S OF FM2339(VAN ZANDT C/L),S
To SH 31 IN MURCHISON
CSJ 1099-02-015
Proj ID STP 2012(146)
Work Type SEAL COAT & PAVEMENT MARKINGS
 
6.660 306620.16 0.00 44141.00 14.3
Work Order 01-24-12
Work Began 03-19-12
Work Completed  
Time Computed 02-09-12
Contract Working Days 162
Addl Days Granted 0
Working Days Charged 205
Percent Time Used 126
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0198-02-032
J & M CONTRACTING, COMPANY ( 13.83%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.96%)
STRIPING TECHNOLOGY, L.P.(2.68%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.66%)
Contract # 12113016
Totals 3731712.54 75250.00 2427378.97 66.1

CountyANDERSON
Highway US 79
From 1.6 MI SW OF LP 256 IN PALESTINE, S
To 0.4 MI SW OF FM 645
CSJ 0205-07-043
Proj ID NH 2008(510)
Work Type GR, BS, ASPH PVT, SIGS, ILLUM, SIGNS
 
8.601 41986850.19 347610.54 6471644.63 15.4
Work Order 10-24-12
Work Began 11-12-12
Work Completed  
Time Computed 11-09-12
Contract Working Days 880
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 11
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0205-07-043
HIGHWAY TECHNOLOGIES, INC. (0.34%)
STRIPING TECHNOLOGY, L.P.(1.65%)
MAC TRANSPORTATION, LTD, L.L.P.(3.12%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.39%)
AMERICAN REMEDIATION OPTIONS, INC. (0.53%)
DANRIDGE CONSTRUCTION, LLC.(0.30%)
DUSTROL, INC.(0.20%)
WEST TEXAS RUMBLE STRIP(0.05%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(1.30%)
NORTH TEXAS REBAR, LLC (0.02%)
Contract # 09123003
Totals 41986850.19 347610.54 6471644.63 15.4

CountySMITH
Highway SH 64
From 0.1 MI W OF FM 2661, E
To 0.6 MI W OF FM 724 (NEAR CR 1184)
CSJ 0245-05-046
Proj ID STP 2013(225)
Work Type GR, SURF, BASE, ACP, PVT MRKG
 
1.191 2387571.56 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 106
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0245-05-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133033
Totals 2387571.56 0.00 0.00 0.0

CountyVAN ZANDT
Highway SH 64
From 0.1 MI SE OF FM 314, SE
To 4.1 MI. NW OF FM 279 IN REDLAND
CSJ 0245-19-019
Proj ID STP 1102(345)
Work Type GRD, FLX BS, HMAC SURF, STRS, PV MK
 
21.135 6387594.18 2920.00 4971398.52 78.8
Work Order 08-15-11
Work Began 10-11-11
Work Completed  
Time Computed 08-31-11
Contract Working Days 203
Addl Days Granted 0
Working Days Charged 263
Percent Time Used 129
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0245-19-019
COLD CREEK CONSTRUCTION, LTD (1.71%)
BAHENA CONSTRUCTION CO.,INC. (4.61%)
PANOLA SIGN & BARRICADE, INC.(0.30%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.41%)
AMERICAN REMEDIATION OPTIONS, INC. (0.51%)
COWBELL TRAFFIC SERVICES, INC. (0.24%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.23%)
A. L. HELMCAMP, INC. (0.51%)
Contract # 06113250
Totals 6387594.18 2920.00 4971398.52 78.8

CountyVAN ZANDT
Highway SH 64
From FM 858 NR BEN WHEELER, SE
To 0.1 MI SE OF FM 314
CSJ 0245-19-022
Proj ID STP 2012(765)
Work Type GR, FLX BS. LVL - UP, HMAC SURF, STRS
 
6.920 7358629.82 20735.33 1689261.14 22.9
Work Order 10-18-12
Work Began 12-03-12
Work Completed  
Time Computed 11-03-12
Contract Working Days 172
Addl Days Granted 0
Working Days Charged 75
Percent Time Used 43
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0245-19-022
N-LINE TRAFFIC MAINTENANCE, L.P. (0.91%)
J. M. CONSTRUCTION (1.74%)
STRIPING TECHNOLOGY, L.P.(1.74%)
HIGHWAY 19 CONSTRUCTION, LLC (4.68%)
Contract # 08123040
Totals 7358629.82 20735.33 1689261.14 22.9

CountyWOOD
Highway SH 154
From 1 MI N OF FM 288(LAKE FORK RES BR)S
To SH 37 (MAIN ST) IN QUITMAN
CSJ 0401-02-026
Proj ID STP 2013(118)
Work Type WDN GR, STRS, REPL BR, ACP BS & SURF, P
 
5.626 5801592.45 93301.00 1186692.08 20.4
Work Order 11-30-12
Work Began 03-04-13
Work Completed  
Time Computed 03-01-13
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 26
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0401-02-026
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.80%)
BAHENA CONSTRUCTION CO.,INC. (7.81%)
STRIPING TECHNOLOGY, L.P.(1.03%)
BLACKTOPPER TECHNOLOGY, INC. (1.52%)
TEX OP CONSTRUCTION, LP(0.14%)
RK HALL, LLC ( 40.26%)
COWBELL TRAFFIC SERVICES, INC. (0.24%)
COX PAVING COMPANY, L.P. (2.53%)
DUSTIN ALLEN, INC. (0.31%)
FARR FOUNDATION, INC.(0.71%)
Contract # 10123007
Totals 5801592.45 93301.00 1186692.08 20.4

CountyWOOD
Highway SH 154
From AT DRY CREEK, 0.7 MI W OF SH 37
To STR #004, W OF QUITMAN
CSJ 0401-02-031
Proj ID BR 2012(719)
Work Type RPLC BR & APPR, GRDG, OCST, ACP BS & SURF
 
0.492 2484893.73 57670.73 1376337.08 55.3
Work Order 09-17-12
Work Began 10-03-12
Work Completed  
Time Computed 10-03-12
Contract Working Days 145
Addl Days Granted 0
Working Days Charged 98
Percent Time Used 67
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0401-02-031
PANOLA SIGN & BARRICADE, INC.(0.33%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(1.18%)
SCOTT DERR PAINTING CO (0.12%)
FORTSON CONTRACTING, INC.(2.25%)
MAC TRANSPORTATION, LTD, L.L.P.(2.51%)
STRIPING TECHNOLOGY, L.P.(0.68%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.91%)
TEX OP CONSTRUCTION, LP(0.65%)
NORTH TEXAS REBAR, LLC (0.38%)
Contract # 08123044
Totals 2484893.73 57670.73 1376337.08 55.3

CountySMITH
Highway FM 2767
From FM 757, E
To 1 MI NW OF SH 31 (GREGG C/L)
CSJ 0424-07-009
Proj ID STP 1102(051)
Work Type SUBGRADE WIDEN, ACP BASE & SURF, STRS
 
32.759 3944945.51 0.00 3433006.44 89.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-15-11
Work Began 10-18-11
Work Completed  
Time Computed 07-31-11
Contract Working Days 114
Addl Days Granted 0
Working Days Charged 248
Percent Time Used 217
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0424-07-009
PANOLA SIGN & BARRICADE, INC.(0.30%)
TOTAL HIGHWAY MAINTENANCE, LLC (4.93%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(1.68%)
J & M CONTRACTING, COMPANY (2.69%)
TEX OP CONSTRUCTION, LP(2.47%)
Contract # 06113022
Totals 3944945.51 0.00 3433006.44 89.2

CountyWOOD
Highway FM 778
From SH 37 IN QUITMAN, SE
To FM 49 IN HAINESVILLE
CSJ 0429-02-008
Proj ID STP 2012(368)HES
Work Type SBGRD WDN, HOTMIX BS, OCST, STRS, PV MK
 
14.738 2178792.43 0.00 1929893.07 88.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-16-12
Work Began 05-03-12
Work Completed  
Time Computed 05-02-12
Contract Working Days 70
Addl Days Granted 14
Working Days Charged 90
Percent Time Used 107
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0429-02-008
STRIPING TECHNOLOGY, L.P.(3.54%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(0.85%)
PANOLA SIGN & BARRICADE, INC.(0.24%)
DUSTIN ALLEN, INC. (0.57%)
MAC TRANSPORTATION, LTD, L.L.P.(2.47%)
Contract # 03123028
Totals 2178792.43 0.00 1929893.07 88.7

CountyVAN ZANDT
Highway FM 17
From 3.0 MI S OF SH 110 (CR 1226), S
To IH 20
CSJ 0443-03-017
Proj ID STP 2012(424)
Work Type WDN & CMT TRT SBGD, FLX BS, TCST, STRS
 
7.459 3737909.64 122604.28 1486652.18 39.7
Work Order 04-11-12
Work Began 04-30-12
Work Completed  
Time Computed 04-27-12
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 62
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0443-03-017
COWBELL TRAFFIC SERVICES, INC. (0.42%)
BAHENA CONSTRUCTION CO.,INC. (7.87%)
MOORE CONSTRUCTION, INC. (0.70%)
STRIPING TECHNOLOGY, L.P.(2.37%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(0.89%)
FORTSON CONTRACTING, INC.(0.44%)
RK HALL, LLC (6.35%)
Contract # 03123024
Totals 3737909.64 122604.28 1486652.18 39.7

CountySMITH
Highway FM 14
From FM 16 AT RED SPRINGS, S
To IH 20
CSJ 0492-01-033
Proj ID STP 2012(500)
Work Type SBGR WDN, BS, OCST, HMAC SURF, STRS
 
5.578 2193886.50 431619.85 727663.70 33.1
Work Order 06-28-12
Work Began 01-03-13
Work Completed  
Time Computed 01-02-13
Contract Working Days 78
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 76
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0492-01-033
STRIPING TECHNOLOGY, L.P.(2.27%)
AMERICAN REMEDIATION OPTIONS, INC. (1.53%)
MAC TRANSPORTATION, LTD, L.L.P.(2.28%)
WEST TEXAS RUMBLE STRIP(0.20%)
PANOLA SIGN & BARRICADE, INC.(0.33%)
TEX OP CONSTRUCTION, LP(0.36%)
Contract # 05123045
Totals 2193886.50 431619.85 727663.70 33.1

CountySMITH
Highway FM 14
From 2.4 MI S OF IH 20(CR329/FORD RD), S
To 1.2 MI N OF LP 323 (CR3154/HOYT RD)
CSJ 0492-01-039
Proj ID STP 2013(550)
Work Type SBGRD WDN, ACP BS, OCST, HMAC, PVT MK
 
0.856 931556.38 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0492-01-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133026
Totals 931556.38 0.00 0.00 0.0

page 1 | page 2