Monthly State Let Construction Report For Tyler District As Of Apr 11, 2016 Page 1 Of 3

Last Update: Monday, April 11, 2016
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyANDERSON
Highway SH 19
From 3.6 MI N OF FM 837(HENDERSON C/L),S
To 0.4 MI N OF FM 321 AT MONTALBA
CSJ 0108-06-051
Proj ID STP 2013(637)
Work Type GR, STRS, HMA BS & SURF, OCST, LVL - UP
 
11.813 12487715.87 26041.74 2845238.46 22.7
Work Order 07-10-14
Work Began 09-02-14
Work Completed  
Time Computed 07-26-14
Contract Working Days 453
Addl Days Granted 0
Working Days Charged 252
Percent Time Used 55
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0108-06-051
COLD CREEK CONSTRUCTION, LTD (0.82%)
FORTSON CONTRACTING, INC.(0.45%)
HIGHWAY 19 CONSTRUCTION, LLC ( 10.97%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.35%)
SAMMY G. SMALLWOOD (0.46%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.15%)
STRIPING TECHNOLOGY, L.P.(1.23%)
FARR FOUNDATION, INC.(0.64%)
SAN-ANN-CO., INC.(0.04%)
Contract # 05143205
Totals 12487715.87 26041.74 2845238.46 22.7

CountyANDERSON
Highway US 287 ETC
From FM 2706, E
To FM 321
CSJ 0122-04-037
Proj ID STP 2016(290)
Work Type SEAL COAT & PAVEMENT MARKINGS
 
170.365 10343177.56 0.00 542631.00 5.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-21-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0122-04-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153216
Totals 10343177.56 0.00 542631.00 5.2

CountyRUSK
Highway US 259
From 0.4 MI S OF US 79 IN HENDERSON, S
To JARRELL CREEK (END C-S)
CSJ 0138-04-045
Proj ID NH 1502(121)
Work Type BS RPR, PLNG, HMAC BS, OCST, PFC OV
 
10.136 5667818.78 386938.56 3500899.16 61.7
Work Order 07-16-15
Work Began 11-18-15
Work Completed  
Time Computed 08-16-15
Contract Working Days 110
Addl Days Granted 10
Working Days Charged 38
Percent Time Used 31
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0138-04-045
O. TREVINO CONSTRUCTION, LLC (1.50%)
B & E CONSTRUCTION INC.(2.54%)
Contract # 06153046
Totals 5667818.78 386938.56 3500899.16 61.7

CountyHENDERSON
Highway SH 31
From AT WB TRINITY RIVER, W OF TRINIDAD
To STR #101080016303040
CSJ 0163-03-048
Proj ID BR 1502(473)
Work Type GR, RIPRAP, BCKFIL, PNT, DECK RPR, MGBF
 
0.857 2305309.45 0.00 249640.00 10.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 03-15-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
OLYMPUS PAINTING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0163-03-048
ACCESS RIGGING LLC ( 16.04%)
DALLAS LITE AND BARRICADE INC. (0.23%)
STRIPING TECHNOLOGY, L.P.(1.53%)
BATTERSON,LLP(0.72%)
Contract # 12153015
Totals 2305309.45 0.00 249640.00 10.8

CountyHENDERSON
Highway SH 31
From .09 MI W OF FM 317(BGN DPRS MDN), E
To .3 MI W OF FM 773 (BGN C&G) MRCHSN
CSJ 0164-01-069
Proj ID STP 2015(621)
Work Type PFC, MBGF, CAM, OCST, BKFL, HMAC, PLNG
 
4.656 3640350.87 102210.78 3203164.53 89.1
Work Order 03-13-15
Work Began 07-27-15
Work Completed  
Time Computed 03-29-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 175
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0164-01-069
ALTUS TRAFFIC MANAGEMENT LLC (0.18%)
FORTSON CONTRACTING, INC.(0.83%)
MURRAY CONSTRUCTION(0.58%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.52%)
STRIPING TECHNOLOGY, L.P.(2.12%)
COWBELL TRAFFIC SERVICE, INC.(0.47%)
Contract # 02153210
Totals 3640350.87 102210.78 3203164.53 89.1

CountySMITH
Highway US 271
From FM 2015, N OF TYLER, S
To 0.4 MI S OF SS 147 (OAKWOOD)
CSJ 0165-01-101
Proj ID NH 2016(191)
Work Type PLNG, BR JNT RPR, ACP LVL UP, SURF TRT
 
4.542 4372572.15 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0165-01-101
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163208
Totals 4372572.15 0.00 0.00 0.0

CountyCHEROKEE
Highway US 69
From 0.37 MI S OF FM 344 (SMITH C/L), S
To 0.02 MI N OF FM 347 IN J'VILLE
CSJ 0191-02-063
Proj ID NH 2016(440)
Work Type PLNG, HMAC, MBGF, BS RPR, OCST, PFC SURF
 
9.083 5664071.15 0.00 339458.40 5.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 03-14-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 24
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0191-02-063
B & E CONSTRUCTION INC.(9.00%)
DUSTIN ALLEN, INC. (3.62%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.22%)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC( 14.90%)
PANOLA SIGN & BARRICADE, INC.(0.30%)
STRIPING TECHNOLOGY, L.P.(2.19%)
Contract # 12153212
Totals 5664071.15 0.00 339458.40 5.9

CountyHENDERSON
Highway US 175
From 0.1 MI SE OF FM 804, SE
To CR 4712 (END OF C-S)
CSJ 0198-01-023
Proj ID NH 1402(195)
Work Type RECONSTR GR, STRS, BS, SURF & PAV M
 
6.695 39261003.89 0.00 18201341.55 46.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-21-14
Work Began 04-06-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 605
Addl Days Granted 5
Working Days Charged 136
Percent Time Used 22
Contractor(s)
A. L. HELMCAMP, INC.
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0198-01-023
DUSTIN ALLEN, INC. (0.36%)
MURRAY CONSTRUCTION(0.22%)
STRIPING TECHNOLOGY, L.P.(0.31%)
SAN-ANN-CO., INC.(0.21%)
KLP COMMERCIAL, LLC(4.91%)
KENSAR LLC DBA S & S TRUCKING(1.88%)
BIG CREEK CONSTRUCTION, LTD. (0.00%)
Contract # 08143055
Totals 39261003.89 0.00 18201341.55 46.3

CountyHENDERSON
Highway US 175
From 1.1 MI E OF LP 60E @ LARUE, SE
To 0.85 MI E OF FM 315, IN POYNOR
CSJ 0198-02-027
Proj ID NH 2015(423)
Work Type RECONSTR GR, STRS, BS, SURF & PAV M
 
4.731 37849155.31 1661398.88 6974381.85 18.4
Work Order 06-30-15
Work Began 10-06-15
Work Completed  
Time Computed 07-16-15
Contract Working Days 654
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 13
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0198-02-027
N-LINE TRAFFIC MAINTENANCE, L.P. (0.20%)
WOLFE CONSTRUCTION GROUP, INC. (0.83%)
K & S UTILITY CONTRACTORS, INC.(4.02%)
OTTO TRUCKING, INC.(3.31%)
APAC-TEXAS, INC. ( 19.01%)
BREDA COMPANY, INC.(2.68%)
ANTIGO CONSTRUCTION, INC.(0.02%)
LAYFIELD CONSTRUCTION, INC (0.40%)
A BROTHERS MILLING, LLC(0.18%)
Contract # 04153201
Totals 37849155.31 1661398.88 6974381.85 18.4

CountyHENDERSON
Highway US 175
From 0.85 MI E OF FM 315, IN POYNOR
To ANDERSON C/L
CSJ 0198-02-035
Proj ID C 198-2-35
Work Type GR, SUB BS, BS, HMAC, DRAIN STRS, SIGNS
 
0.923 7052578.98 0.00 0.00 0.0
CountyANDERSON
Highway US 175
From 1.9 MI S OF FM 315 (HENDERSON C/L)
To 0.5 MI NW OF SH 155 AT FRANKSTON
CSJ 0198-03-027
Proj ID NH 1502(561)
Work Type GR, SUB BS, BS, HMAC, DRAIN STRS, SIGNS
 
3.804 20312971.66 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-17-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 571
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0198-03-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153202
Totals 27365550.64 0.00 0.00 0.0

CountyCHEROKEE
Highway US 69
From SL 456 IN JACKSONVILLE, S
To 0.058 MI N OF SL 62 IN RUSK
CSJ 0199-01-081
Proj ID NH 1502(130)
Work Type STRS, PLNG, HMAC, OCST, PFC, MBGF, BS RPR
 
10.722 11063277.59 396437.51 3317112.74 29.9
Work Order 08-24-15
Work Began 11-04-15
Work Completed  
Time Computed 09-24-15
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 75
Percent Time Used 41
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0199-01-081
DUSTIN ALLEN, INC. (0.20%)
BAHENA CONSTRUCTION CO.,INC. (1.17%)
PANOLA SIGN & BARRICADE, INC.(0.18%)
SOUTHWEST ENVIRONMENT SERVICES LLC ( 12.26%)
STRIPING TECHNOLOGY, L.P.(1.77%)
B & E CONSTRUCTION INC.(9.96%)
PLAIN DEALING TRUCKING COMPANY, INC. (0.00%)
Contract # 06153013
Totals 11063277.59 396437.51 3317112.74 29.9

CountyCHEROKEE
Highway US 69
From 0.028 MI S OF FM 343 IN RUSK, S
To 0.08 MI N OF SH 21 IN ALTO
CSJ 0199-02-057
Proj ID NH 1502(277)
Work Type STRS, PLNG, HMAC, OCST, PFC, MBGF, BS RPR
 
10.027 9380454.05 1919532.94 2948000.76 31.4
Work Order 08-20-15
Work Began 01-04-16
Work Completed  
Time Computed 09-20-15
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 44
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0199-02-057
STRIPING TECHNOLOGY, L.P.(1.99%)
BAHENA CONSTRUCTION CO.,INC. (1.69%)
PANOLA SIGN & BARRICADE, INC.(0.21%)
SOUTHWEST ENVIRONMENT SERVICES LLC ( 13.91%)
DUSTIN ALLEN, INC. (0.39%)
PLAIN DEALING TRUCKING COMPANY, INC. (0.00%)
B & E CONSTRUCTION INC.( 11.46%)
Contract # 06153014
Totals 9380454.05 1919532.94 2948000.76 31.4

CountySMITH
Highway FM 1253
From CR 462(S), 1.3 MI N OF FM 857, S
To FM 1805
CSJ 0203-08-015
Proj ID STP 1502(278)HES
Work Type SUBGRADE WIDEN, LEVEL - UP, OCST
 
12.009 7499499.38 0.00 3355569.56 44.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-10-15
Work Began 09-18-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 311
Addl Days Granted 0
Working Days Charged 118
Percent Time Used 37
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0203-08-015
PANOLA SIGN & BARRICADE, INC.(0.62%)
STRIPING TECHNOLOGY, L.P.(1.44%)
AMERICAN REMEDIATION OPTIONS, INC. (6.84%)
Contract # 06153028
Totals 7499499.38 0.00 3355569.56 44.7

CountyANDERSON
Highway US 79
From 1.6 MI SW OF LP 256 IN PALESTINE, S
To 0.4 MI SW OF FM 645
CSJ 0205-07-043
Proj ID NH 2008(510)
Work Type GR, BS, ASPH PVT, SIGS, ILLUM, SIGNS
 
8.601 41986850.19 565266.58 32063202.06 76.3
Work Order 10-24-12
Work Began 11-12-12
Work Completed  
Time Computed 11-09-12
Contract Working Days 880
Addl Days Granted 0
Working Days Charged 839
Percent Time Used 95
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0205-07-043
HIGHWAY TECHNOLOGIES, INC. (0.10%)
STRIPING TECHNOLOGY, L.P.(1.65%)
MAC TRANSPORTATION, LTD, L.L.P.(3.12%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.39%)
AMERICAN REMEDIATION OPTIONS, INC. (0.53%)
DANRIDGE CONSTRUCTION, LLC.(0.30%)
DUSTROL, INC.(0.20%)
WEST TEXAS RUMBLE STRIP(0.05%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.68%)
NORTH TEXAS REBAR, LLC (0.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.23%)
P.R. PARKER COMPANY, INC.(0.00%)
TEX OP CONSTRUCTION, LP(0.01%)
Contract # 09123003
Totals 41986850.19 565266.58 32063202.06 76.3

CountyCHEROKEE
Highway US 79
From 3 MI W OF SH 110, W
To 0.3 MI E OF SH 204(DOGWOOD) J'VILLE
CSJ 0206-04-039
Proj ID NH 2016(997)
Work Type PLN, CM TRT, BS & SURF, RF RL, MBGF, PV MK
 
3.258 5778866.01 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0206-04-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163211
Totals 5778866.01 0.00 0.00 0.0

CountyRUSK
Highway US 79
From SL 571 IN HENDERSON, SW
To FM 839
CSJ 0206-07-058
Proj ID STP 1502(281)HES
Work Type STRS, WDNG, OCST, ACP, PVT MRKGS
 
3.050 6661253.88 0.00 1080142.47 16.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-24-15
Work Began 01-15-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 9
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0206-07-058
J & M CONTRACTING, COMPANY (5.38%)
TEXOP CONSTRUCTION (0.67%)
PANOLA SIGN & BARRICADE, INC.(0.39%)
MORRIS COUNTY CONTRACTORS, L.L.C.(0.50%)
STRIPING TECHNOLOGY, L.P.(0.82%)
Contract # 06153251
Totals 6661253.88 0.00 1080142.47 16.2

CountyRUSK
Highway SH 43
From 4 MI S OF FM 2658 (CR 2136), NE
To 2.2 S OF FM 2658 (BEGIN C-S)
CSJ 0207-02-027
Proj ID STP 2016(364)
Work Type SURF TREAT, ACP SURF, MBGF, PVMT MRKG
 
8.285 4691110.39 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0207-02-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163232
Totals 4691110.39 0.00 0.00 0.0

CountyVAN ZANDT
Highway FM 279
From FM 858 IN BEN WHEELER, E
To FM 314 IN EDOM
CSJ 0245-03-021
Proj ID STP 1502(562)
Work Type 2" OVERLAY
 
17.300 2461597.14 0.00 1293559.71 52.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-23-15
Work Began 01-12-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 56
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0245-03-021
TOTAL HIGHWAY MAINTENANCE, LLC (0.45%)
W.O.E. CONSTRUCTION(0.59%)
STRIPING TECHNOLOGY, L.P.(2.15%)
TEX OP CONSTRUCTION, LP(1.59%)
HENDERSON CONCRETE, INC. (1.31%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.85%)
Contract # 08153250
Totals 2461597.14 0.00 1293559.71 52.5

CountySMITH
Highway SH 64
From FM 3226 SE OF CHAPEL HILL, SE
To SH 135 NEAR ARP
CSJ 0245-06-076
Proj ID STP 2014(590)
Work Type GR, STRS, FLX BS, LVL - UP, OCST, HMAC SRF
 
8.294 3872443.98 28279.47 3872296.83 99.9
Work Order 06-30-14
Work Began 08-21-14
Work Completed  
Time Computed 07-16-14
Contract Working Days 125
Addl Days Granted 0
Working Days Charged 206
Percent Time Used 164
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0245-06-076
PANOLA SIGN & BARRICADE, INC.(0.60%)
DREWERY & WHEATON, LLC (1.14%)
J & M CONTRACTING, COMPANY ( 10.08%)
COWBELL TRAFFIC SERVICES, INC. (0.35%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.90%)
STRIPING TECHNOLOGY, L.P.(1.96%)
TEX OP CONSTRUCTION, LP(0.52%)
DREWERY BROS TREE SERVICE, INC.(1.72%)
FREDONIA CONSTRUCTION SERVICES (0.23%)
DUSTIN ALLEN, INC. (1.04%)
AMERICAN REMEDIATION OPTIONS, INC. (0.46%)
Contract # 04143017
Totals 3872443.98 28279.47 3872296.83 99.9

CountyRUSK
Highway SH 64
From 0.17 MI W OF BS 64E IN HENDERSON,E
To 0.2 MI W OF US79/US259 (N MARSHALL)
CSJ 0245-08-040
Proj ID STP 2013(913)
Work Type GR, STRS, PLNG, HMA BS, C & G, SURF, PV MKG
 
0.338 2102152.24 0.00 1806794.33 91.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-08-13
Work Began 10-11-13
Work Completed  
Time Computed 08-24-13
Contract Working Days 100
Addl Days Granted 4
Working Days Charged 244
Percent Time Used 234
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0245-08-040
STRIPING TECHNOLOGY, L.P.(6.47%)
ROBINSON CONSTRUCTION( 11.78%)
REYNOLDS & KAY, LTD. (8.20%)
TEX OP CONSTRUCTION, LP(0.66%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.55%)
Contract # 07133246
Totals 2102152.24 0.00 1806794.33 91.1

page 1 | page 2 | page 3