Monthly State Let Construction Report For Tyler District As Of Jul 13, 2015 Page 2 Of 4

Last Update: Monday, July 13, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySMITH
Highway SH 64
From 0.1 MI W OF FM 2661, E
To 0.6 MI W OF FM 724 (NEAR CR 1184)
CSJ 0245-05-046
Proj ID STP 2013(225)
Work Type GR, SURF, BASE, ACP, PVT MRKG
 
1.191 2387571.56 0.00 2323406.63 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-13
Work Began 08-05-13
Work Completed 01-29-15
Time Computed 07-24-13
Contract Working Days 106
Addl Days Granted 0
Working Days Charged 106
Percent Time Used 100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0245-05-046
HIGHWAY 19 CONSTRUCTION, LLC ( 25.78%)
STRIPING TECHNOLOGY, L.P.(1.24%)
MARCOM"S MOWING SERVICE, LLC (0.81%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.36%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.32%)
Contract # 05133033
Totals 2387571.56 0.00 2323406.63 100.0

CountySMITH
Highway SH 64
From FM 3226 SE OF CHAPEL HILL, SE
To SH 135 NEAR ARP
CSJ 0245-06-076
Proj ID STP 2014(590)
Work Type GR, STRS, FLX BS, LVL - UP, OCST, HMAC SRF
 
8.294 3872443.98 214267.18 1383400.65 35.7
Work Order 06-30-14
Work Began 08-21-14
Work Completed  
Time Computed 07-16-14
Contract Working Days 125
Addl Days Granted 0
Working Days Charged 94
Percent Time Used 75
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0245-06-076
PANOLA SIGN & BARRICADE, INC.(0.60%)
DREWERY & WHEATON, LLC (2.51%)
J & M CONTRACTING, COMPANY ( 10.08%)
COWBELL TRAFFIC SERVICES, INC. (0.35%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.90%)
STRIPING TECHNOLOGY, L.P.(1.96%)
TEX OP CONSTRUCTION, LP(0.52%)
DREWERY BROS TREE SERVICE, INC.(1.72%)
FREDONIA CONSTRUCTION SERVICES (0.23%)
Contract # 04143017
Totals 3872443.98 214267.18 1383400.65 35.7

CountyRUSK
Highway SH 64
From 0.17 MI W OF BS 64E IN HENDERSON,E
To 0.2 MI W OF US79/US259 (N MARSHALL)
CSJ 0245-08-040
Proj ID STP 2013(913)
Work Type GR, STRS, PLNG, HMA BS, C & G, SURF, PV MKG
 
0.338 2102152.24 133812.87 1136543.11 56.7
Work Order 08-08-13
Work Began 10-11-13
Work Completed  
Time Computed 08-24-13
Contract Working Days 100
Addl Days Granted 4
Working Days Charged 176
Percent Time Used 169
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0245-08-040
STRIPING TECHNOLOGY, L.P.(6.47%)
ROBINSON CONSTRUCTION( 11.78%)
REYNOLDS & KAY, LTD. (8.20%)
TEX OP CONSTRUCTION, LP(0.66%)
Contract # 07133246
Totals 2102152.24 133812.87 1136543.11 56.7

CountyVAN ZANDT
Highway SH 64
From FM 858 NR BEN WHEELER, SE
To 0.1 MI SE OF FM 314
CSJ 0245-19-022
Proj ID STP 2012(765)
Work Type GR, FLX BS. LVL - UP, HMAC SURF, STRS
 
6.920 7358629.82 21500.00 6211588.90 84.4
Work Order 10-18-12
Work Began 12-03-12
Work Completed  
Time Computed 11-03-12
Contract Working Days 172
Addl Days Granted 220
Working Days Charged 367
Percent Time Used 93
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0245-19-022
N-LINE TRAFFIC MAINTENANCE, L.P. (0.91%)
J. M. CONSTRUCTION (1.74%)
STRIPING TECHNOLOGY, L.P.(1.74%)
HIGHWAY 19 CONSTRUCTION, LLC (4.68%)
Contract # 08123040
Totals 7358629.82 21500.00 6211588.90 84.4

CountySMITH
Highway SH 110
From IN THE SW QUAD OF SH 110 & TOLL 49
To IN NORTHERN WHITEHOUSE
CSJ 0345-01-059
Proj ID STP 2014(633)
Work Type GRD, EMBANK, ILLUMINATN, WELCOME SIGN
 
0.110 120955.00 0.00 119853.31 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-13-14
Work Began 07-28-14
Work Completed 01-29-15
Time Computed 06-29-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0345-01-059
SOUTH TEXAS ILLUMINATION, LLC( 19.53%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.81%)
Contract # 05143029
Totals 120955.00 0.00 119853.31 100.0

CountySMITH
Highway SH 31
From FM 850, E OF TYLER, E
To FM757
CSJ 0424-01-045
Proj ID STP 2013(914)
Work Type GRADING, OCST, STRUCTURES, PVMT MRKGS
 
6.631 3431987.29 411147.64 3289256.95 96.4
Work Order 12-10-13
Work Began 01-13-14
Work Completed  
Time Computed 01-06-14
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 98
Percent Time Used 128
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0424-01-045
DUSTROL, INC.(0.64%)
REYNOLDS & KAY, LTD. ( 13.96%)
PANOLA SIGN & BARRICADE, INC.(0.23%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.50%)
STRIPING TECHNOLOGY, L.P.(1.95%)
TJT CONSTRUCTION (2.50%)
Contract # 09133040
Totals 3431987.29 411147.64 3289256.95 96.4

CountySMITH
Highway SH 31
From FM 757, E
To 2.5 MI W OF FM 2767(NR MULEY BRC),E
CSJ 0424-01-048
Proj ID STP 2013(640)
Work Type GR, STRS, ACP BS & SURF, PVT MRK
 
10.734 7802782.95 101184.73 1170962.64 15.0
Work Order 10-29-14
Work Began 11-18-14
Work Completed  
Time Computed 11-14-14
Contract Working Days 328
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 13
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0424-01-048
SOUTHWEST ENVIRONMENT SERVICES LLC (5.73%)
ALTUS TRAFFIC MANAGEMENT LLC (0.48%)
STRIPING TECHNOLOGY, L.P.(2.44%)
C.S. TREE SERVICE(0.48%)
FORTSON CONTRACTING, INC.(0.09%)
MURRAY CONSTRUCTION(0.22%)
TEX OP CONSTRUCTION, LP(0.79%)
J & I TRUCKING CO(1.05%)
HOPE SERVICES, INC.(0.70%)
HARRIS TRUCKING SERVICES (1.40%)
Contract # 08143053
Totals 7802782.95 101184.73 1170962.64 15.0

CountyGREGG
Highway FM 349
From SH 31 IN KILGORE, E
To 0.247 MI W OF US 259 (KILGORE BYPS)
CSJ 0424-03-024
Proj ID C 424-3-24
Work Type GRD, CMT TRT SBGR, FLX BS, OCST, STRS
 
0.721 1065975.37 0.00 1080368.70 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-31-13
Work Began 03-04-14
Work Completed 01-21-15
Time Computed 01-06-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 100
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0424-03-024
MAC TRANSPORTATION, LTD, L.L.P.(5.31%)
ODUM SERVICES, L.P.( 14.48%)
PANOLA SIGN & BARRICADE, INC.(0.41%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.49%)
STRIPING TECHNOLOGY, L.P.(0.98%)
TEX OP CONSTRUCTION, LP(0.55%)
C & M TREE SERVICE (0.40%)
Contract # 08133038
Totals 1065975.37 0.00 1080368.70 100.0

CountyVAN ZANDT
Highway SH 198
From SH 243, IN CANTON, SW
To 0.4 MI NE OF FM 316 NEAR PHALBA
CSJ 0443-01-028
Proj ID STP 2014(415)HES
Work Type SBGR WDN, ACP BS, OCST, STRS, PFL PV MK
 
27.237 5034636.87 154483.16 2006372.00 39.8
Work Order 03-18-14
Work Began 04-08-14
Work Completed  
Time Computed 04-03-14
Contract Working Days 227
Addl Days Granted 11
Working Days Charged 179
Percent Time Used 75
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0443-01-028
PANOLA SIGN & BARRICADE, INC.(1.18%)
STRIPING TECHNOLOGY, L.P.(4.35%)
BAHENA CONSTRUCTION CO.,INC. ( 11.44%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.48%)
FORTSON CONTRACTING, INC.(0.35%)
Contract # 02143224
Totals 5034636.87 154483.16 2006372.00 39.8

CountyHENDERSON
Highway FM 59
From FM 753, S
To 0.7 MI S OF RM 3273 (ANDERSON C/L)
CSJ 0458-01-022
Proj ID STP 2013(819)
Work Type SBGR WDN, ACP BS & SURF, OCST, MBGF, SIGN
 
12.567 6987662.21 4750.00 6712544.60 96.4
Work Order 12-04-13
Work Began 12-31-13
Work Completed  
Time Computed 12-20-13
Contract Working Days 232
Addl Days Granted 13
Working Days Charged 269
Percent Time Used 109
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0458-01-022
BAHENA CONSTRUCTION CO.,INC. (6.79%)
FORTSON CONTRACTING, INC.(0.54%)
MURRAY CONSTRUCTION(0.64%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.73%)
STRIPING TECHNOLOGY, L.P.(1.77%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.18%)
SAN-ANN-CO., INC.(0.41%)
COLD CREEK CONSTRUCTION, LTD (0.13%)
Contract # 09133223
Totals 6987662.21 4750.00 6712544.60 96.4

CountyVAN ZANDT
Highway IH 20
From 1.5 MI E OF FM 1255, E
To 3.6 MI E OF FM 314 (SMITH C/L)
CSJ 0495-03-060
Proj ID NH 2015(622)
Work Type ACP BS & SURF, OCST, MICRO, PVT MRK
 
12.800 2377778.92 882085.77 882085.77 37.0
Work Order 03-16-15
Work Began 06-22-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 15
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-03-060
SOUTHWEST ENVIRONMENT SERVICES LLC (0.56%)
ALTUS TRAFFIC MANAGEMENT LLC (0.28%)
TEXOP CONSTRUCTION (2.49%)
DUSTROL, INC.(0.76%)
STRIPING TECHNOLOGY, L.P.(2.44%)
APAC-KANSAS( 12.58%)
Contract # 02153226
Totals 2377778.92 882085.77 882085.77 37.0

CountySMITH
Highway IH 20
From US 69, IN LINDALE, E 0.819 MI
To END OF CONTROL SECTION
CSJ 0495-04-064
Proj ID IM 0206(109)
Work Type PLNG, OCST, ACP SURF, CLN & SL BRG JOINT
 
0.819 608794.45 0.00 748218.06 100.0
CountySMITH
Highway IH 20
From 0.8 MI E OF US 69, E
To 1.6 MI W OF FM 14(E OF LAVENDER RD)
CSJ 0495-05-047
Proj ID IM 0206(109)
Work Type PLNG, OCST, ACP SURF, CLN & SL BRG JOINT
 
3.857 1606311.94 0.00 1706282.73 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 07-08-14
Work Completed 01-29-15
Time Computed 05-01-14
Contract Working Days 60
Addl Days Granted 15
Working Days Charged 75
Percent Time Used 100
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-05-047
ALTUS TRAFFIC MANAGEMENT LLC (0.22%)
CHEROKEE SERVICES(8.87%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.37%)
TEX OP CONSTRUCTION, LP(1.28%)
STRIPING TECHNOLOGY, L.P.(1.74%)
APAC-KANSAS(3.78%)
DUSTROL, INC.(0.36%)
Contract # 03143223
Totals 2215106.39 0.00 2454500.79 100.0

CountyGREGG
Highway IH 20
From SH 31, E
To HARRISON C/L
CSJ 0495-07-072
Proj ID NH 1502(139)
Work Type TBPFC / ACP SURF, PLNG, BRG JNT, SHD TXT
 
8.176 5584277.98 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-18-15
Work Began 00-00-00
Work Completed  
Time Computed 07-19-15
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-07-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153026
Totals 5584277.98 0.00 0.00 0.0

CountyGREGG
Highway SH 42
From IH 20 SOUTH RAMP, S
To SH 31 IN KILGORE
CSJ 0545-04-046
Proj ID C 545-4-46
Work Type GR, STRS, SURF
 
2.082 3692466.84 7041.26 2252953.71 61.0
Work Order 09-17-13
Work Began 01-23-14
Work Completed  
Time Computed 01-13-14
Contract Working Days 88
Addl Days Granted 32
Working Days Charged 49
Percent Time Used 40
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0545-04-046
ALTUS TRAFFIC MANAGEMENT LLC (0.41%)
SOUTHWEST ENVIRONMENT SERVICES LLC (3.26%)
STRIPING TECHNOLOGY, L.P.(0.58%)
DUSTIN ALLEN, INC. (1.37%)
TEX OP CONSTRUCTION, LP(0.61%)
TRENDSETTER CONSTRUCTION, INC. (0.59%)
ROBINSON CONSTRUCTION(8.27%)
EAST TEXAS BRIDGE, INC.(1.16%)
Contract # 07133047
Totals 3692466.84 7041.26 2252953.71 61.0

CountyHENDERSON
Highway FM 315
From FM 314, S
To CR 4325/4224 (END C-S)
CSJ 0559-02-034
Proj ID STP 1502(282)HES
Work Type SUBGRADE WIDEN, LEVEL - UP, OCST
 
5.706 3079333.98 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0559-02-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153229
Totals 3079333.98 0.00 0.00 0.0

CountyCHEROKEE
Highway FM 22
From US 69 S OF JACKSONVILLE, SW
To 1.5 MI W OF FM 768(N)(GAL'N CTY LM)
CSJ 0634-01-011
Proj ID SSW 634-01-011
Work Type SBGR WDN, ACP BS & SURF, OCST, STRS, SIGN
 
14.256 7730087.27 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 138
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0634-01-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153215
Totals 7730087.27 0.00 0.00 0.0

CountyGREGG
Highway FM 449
From US 259 N OF LONGVIEW, E
To FM 2751
CSJ 0640-07-005
Proj ID STP 1502(284)HES
Work Type SUBGR WDN, ACP LVL - UP, STRS, OCST, PVMK
 
8.012 4436875.01 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 284
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0640-07-005
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153032
Totals 4436875.01 0.00 0.00 0.0

CountyVAN ZANDT
Highway FM 314
From 2.3 MI N OF SH 64(CR 4907),S
To FM 279 (E) IN EDOM
CSJ 0745-01-015
Proj ID STP 2014(634)
Work Type SCAR, RESHAPE, FLX BS, SURF TRT, STRS
 
11.712 11961746.06 0.00 2359576.42 19.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-14
Work Began 11-07-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 486
Addl Days Granted 0
Working Days Charged 85
Percent Time Used 17
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0745-01-015
STRIPING TECHNOLOGY, L.P.(1.18%)
DUSTIN ALLEN, INC. (0.74%)
KENSAR LLC DBA S & S TRUCKING(4.64%)
Contract # 05143203
Totals 11961746.06 0.00 2359576.42 19.7

CountyANDERSON
Highway FM 323 ETC
From US 84 IN PALESTINE, SE
To N OF SH 294
CSJ 0891-02-019
Proj ID STP 2015(091)HESG
Work Type PROFILE TEXTURE CENTERLINE
 
389.544 1884151.05 128900.58 791487.97 42.0
Work Order 10-02-14
Work Began 03-23-15
Work Completed  
Time Computed 10-18-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 50
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0891-02-019
PANOLA SIGN & BARRICADE, INC.(6.75%)
COWBELL TRAFFIC SERVICES, INC. (7.95%)
NE-TEX CONSTRUCTION, LTD.(0.00%)
BRYDL CONTRACTING, INC.(5.40%)
L. S. EQUIPMENT CO., INC.(5.76%)
Contract # 09143014
Totals 1884151.05 128900.58 791487.97 42.0

CountySMITH
Highway VA
From VARIOUS LOCATIONS IN
To THE TYLER DISTRICT
CSJ 0910-00-094
Proj ID STP 2015(160)
Work Type THERMOPLASTIC MARKINGS
 
1.000 296128.85 0.00 289054.48 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-02-14
Work Began 12-02-14
Work Completed 02-13-15
Time Computed 10-18-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 60
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0910-00-094
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143218
Totals 296128.85 0.00 289054.48 100.0