Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyANDERSON
Highway US 79
From 1.6 MI SW OF LP 256 IN PALESTINE, S
To 0.4 MI SW OF FM 645
CSJ 0205-07-043
Proj ID NH 2008(510)
Work Type GR, BS, ASPH PVT, SIGS, ILLUM, SIGNS
 
8.601 41986850.19 899944.72 30592780.58 72.8
Work Order 10-24-12
Work Began 11-12-12
Work Completed  
Time Computed 11-09-12
Contract Working Days 880
Addl Days Granted 0
Working Days Charged 795
Percent Time Used 90
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0205-07-043
HIGHWAY TECHNOLOGIES, INC. (0.10%)
STRIPING TECHNOLOGY, L.P.(1.65%)
MAC TRANSPORTATION, LTD, L.L.P.(3.12%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.39%)
AMERICAN REMEDIATION OPTIONS, INC. (0.53%)
DANRIDGE CONSTRUCTION, LLC.(0.30%)
DUSTROL, INC.(0.20%)
WEST TEXAS RUMBLE STRIP(0.05%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.68%)
NORTH TEXAS REBAR, LLC (0.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.23%)
P.R. PARKER COMPANY, INC.(0.00%)
TEX OP CONSTRUCTION, LP(0.01%)
Contract # 09123003
Totals 41986850.19 899944.72 30592780.58 72.8

CountyANDERSON
Highway US 79
From SL 256 IN PALESTINE, SW
To 1.4 MI SW OF FM 1990(TILE FCTRY RD)
CSJ 0205-07-075
Proj ID NH 1502(049)
Work Type PLNG, SUPERAVE, OCST, PFC, PVT MRKG
 
1.663 2318824.87 0.00 2286102.37 98.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-19-15
Work Began 08-16-15
Work Completed  
Time Computed 06-19-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0205-07-075
PANOLA SIGN & BARRICADE, INC.(0.23%)
STRIPING TECHNOLOGY, L.P.(1.37%)
Contract # 04153251
Totals 2318824.87 0.00 2286102.37 98.5

CountyRUSK
Highway US 79
From SL 571, NE & N
To SH 64 AT TRAFFIC STAR IN HENDERSON
CSJ 0206-07-057
Proj ID NH 1502(132)
Work Type BS RPR, PLNG, SUPRPV, HMAC, OCST, PFC OV
 
4.440 5221369.21 14262.36 5201126.38 99.6
Work Order 06-19-15
Work Began 09-08-15
Work Completed  
Time Computed 07-20-15
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 82
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0206-07-057
PANOLA SIGN & BARRICADE, INC.(0.15%)
STRIPING TECHNOLOGY, L.P.(2.05%)
L. S. EQUIPMENT CO., INC.(8.13%)
Contract # 05153043
Totals 5221369.21 14262.36 5201126.38 99.6

CountyRUSK
Highway US 79
From SL 571 IN HENDERSON, SW
To FM 839
CSJ 0206-07-058
Proj ID STP 1502(281)HES
Work Type STRS, WDNG, OCST, ACP, PVT MRKGS
 
3.050 6661253.88 0.00 379162.56 5.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-24-15
Work Began 01-15-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 3
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0206-07-058
J & M CONTRACTING, COMPANY (5.38%)
TEXOP CONSTRUCTION (0.67%)
PANOLA SIGN & BARRICADE, INC.(0.39%)
MORRIS COUNTY CONTRACTORS, L.L.C.(0.50%)
STRIPING TECHNOLOGY, L.P.(0.82%)
Contract # 06153251
Totals 6661253.88 0.00 379162.56 5.6

CountyRUSK
Highway SH 43
From 4 MI S OF FM 2658 (CR 2136), NE
To 2.2 S OF FM 2658 (BEGIN C-S)
CSJ 0207-02-027
Proj ID STP 2016(364)
Work Type SURF TREAT, ACP SURF, MBGF, PVMT MRKG
 
8.285 4691110.39 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0207-02-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163232
Totals 4691110.39 0.00 0.00 0.0

CountyVAN ZANDT
Highway FM 279
From FM 858 IN BEN WHEELER, E
To FM 314 IN EDOM
CSJ 0245-03-021
Proj ID STP 1502(562)
Work Type 2" OVERLAY
 
17.300 2461597.14 0.00 146775.75 5.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-23-15
Work Began 01-12-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 4
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0245-03-021
TOTAL HIGHWAY MAINTENANCE, LLC (0.45%)
W.O.E. CONSTRUCTION(0.59%)
STRIPING TECHNOLOGY, L.P.(2.15%)
TEX OP CONSTRUCTION, LP(1.59%)
HENDERSON CONCRETE, INC. (1.31%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.21%)
Contract # 08153250
Totals 2461597.14 0.00 146775.75 5.9

CountySMITH
Highway SH 64
From 0.1 MI W OF FM 2661, E
To 0.6 MI W OF FM 724 (NEAR CR 1184)
CSJ 0245-05-046
Proj ID STP 2013(225)
Work Type GR, SURF, BASE, ACP, PVT MRKG
 
1.191 2387571.56 0.00 2323406.63 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-13
Work Began 08-05-13
Work Completed 01-29-15
Time Computed 07-24-13
Contract Working Days 106
Addl Days Granted 0
Working Days Charged 106
Percent Time Used 100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0245-05-046
HIGHWAY 19 CONSTRUCTION, LLC ( 25.78%)
STRIPING TECHNOLOGY, L.P.(1.24%)
MARCOM"S MOWING SERVICE, LLC (0.81%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.36%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.32%)
Contract # 05133033
Totals 2387571.56 0.00 2323406.63 100.0

CountySMITH
Highway SH 64
From FM 3226 SE OF CHAPEL HILL, SE
To SH 135 NEAR ARP
CSJ 0245-06-076
Proj ID STP 2014(590)
Work Type GR, STRS, FLX BS, LVL - UP, OCST, HMAC SRF
 
8.294 3872443.98 169205.25 3825857.35 99.9
Work Order 06-30-14
Work Began 08-21-14
Work Completed  
Time Computed 07-16-14
Contract Working Days 125
Addl Days Granted 0
Working Days Charged 206
Percent Time Used 164
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0245-06-076
PANOLA SIGN & BARRICADE, INC.(0.60%)
DREWERY & WHEATON, LLC (1.14%)
J & M CONTRACTING, COMPANY ( 10.08%)
COWBELL TRAFFIC SERVICES, INC. (0.35%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.90%)
STRIPING TECHNOLOGY, L.P.(1.96%)
TEX OP CONSTRUCTION, LP(0.52%)
DREWERY BROS TREE SERVICE, INC.(1.72%)
FREDONIA CONSTRUCTION SERVICES (0.23%)
DUSTIN ALLEN, INC. (1.04%)
AMERICAN REMEDIATION OPTIONS, INC. (0.46%)
Contract # 04143017
Totals 3872443.98 169205.25 3825857.35 99.9

CountyRUSK
Highway SH 64
From 0.17 MI W OF BS 64E IN HENDERSON,E
To 0.2 MI W OF US79/US259 (N MARSHALL)
CSJ 0245-08-040
Proj ID STP 2013(913)
Work Type GR, STRS, PLNG, HMA BS, C & G, SURF, PV MKG
 
0.338 2102152.24 25923.83 1803680.13 91.0
Work Order 08-08-13
Work Began 10-11-13
Work Completed  
Time Computed 08-24-13
Contract Working Days 100
Addl Days Granted 4
Working Days Charged 244
Percent Time Used 234
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0245-08-040
STRIPING TECHNOLOGY, L.P.(6.47%)
ROBINSON CONSTRUCTION( 11.78%)
REYNOLDS & KAY, LTD. (8.20%)
TEX OP CONSTRUCTION, LP(0.66%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.55%)
Contract # 07133246
Totals 2102152.24 25923.83 1803680.13 91.0

CountyVAN ZANDT
Highway SH 64
From FM 858 NR BEN WHEELER, SE
To 0.1 MI SE OF FM 314
CSJ 0245-19-022
Proj ID STP 2012(765)
Work Type GR, FLX BS. LVL - UP, HMAC SURF, STRS
 
6.920 7358629.82 102922.48 8786766.44 99.9
Work Order 10-18-12
Work Began 12-03-12
Work Completed  
Time Computed 11-03-12
Contract Working Days 172
Addl Days Granted 220
Working Days Charged 455
Percent Time Used 116
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0245-19-022
N-LINE TRAFFIC MAINTENANCE, L.P. (0.91%)
J. M. CONSTRUCTION (1.74%)
STRIPING TECHNOLOGY, L.P.(1.74%)
HIGHWAY 19 CONSTRUCTION, LLC (4.68%)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC(4.37%)
BIG CREEK CONSTRUCTION, LTD. ( 24.57%)
WEST TEXAS RUMBLE STRIP(0.04%)
Contract # 08123040
Totals 7358629.82 102922.48 8786766.44 99.9

CountySMITH
Highway SH 110
From IN THE SW QUAD OF SH 110 & TOLL 49
To IN NORTHERN WHITEHOUSE
CSJ 0345-01-059
Proj ID STP 2014(633)
Work Type GRD, EMBANK, ILLUMINATN, WELCOME SIGN
 
0.110 120955.00 0.00 119853.31 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-13-14
Work Began 07-28-14
Work Completed 01-29-15
Time Computed 06-29-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0345-01-059
SOUTH TEXAS ILLUMINATION, LLC( 19.53%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.81%)
Contract # 05143029
Totals 120955.00 0.00 119853.31 100.0

CountySMITH
Highway SH 31
From FM 850, E OF TYLER, E
To FM757
CSJ 0424-01-045
Proj ID STP 2013(914)
Work Type GRADING, OCST, STRUCTURES, PVMT MRKGS
 
6.631 3431987.29 46881.00 3364381.00 98.6
Work Order 12-10-13
Work Began 01-13-14
Work Completed  
Time Computed 01-06-14
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 98
Percent Time Used 128
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0424-01-045
DUSTROL, INC.(0.64%)
REYNOLDS & KAY, LTD. ( 13.96%)
PANOLA SIGN & BARRICADE, INC.(0.23%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.50%)
STRIPING TECHNOLOGY, L.P.(1.95%)
TJT CONSTRUCTION (2.50%)
Contract # 09133040
Totals 3431987.29 46881.00 3364381.00 98.6

CountySMITH
Highway SH 31
From FM 757, E
To 2.5 MI W OF FM 2767(NR MULEY BRC),E
CSJ 0424-01-048
Proj ID STP 2013(640)
Work Type GR, STRS, ACP BS & SURF, PVT MRK
 
10.734 7802782.95 36128.73 1937811.27 24.8
Work Order 10-29-14
Work Began 11-18-14
Work Completed  
Time Computed 11-14-14
Contract Working Days 328
Addl Days Granted 0
Working Days Charged 124
Percent Time Used 37
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0424-01-048
SOUTHWEST ENVIRONMENT SERVICES LLC (5.73%)
ALTUS TRAFFIC MANAGEMENT LLC (0.48%)
STRIPING TECHNOLOGY, L.P.(2.44%)
C.S. TREE SERVICE(0.48%)
FORTSON CONTRACTING, INC.(0.09%)
MURRAY CONSTRUCTION(0.22%)
TEX OP CONSTRUCTION, LP(0.79%)
J & I TRUCKING CO(1.05%)
HOPE SERVICES, INC.(0.70%)
HARRIS TRUCKING SERVICES (1.40%)
Contract # 08143053
Totals 7802782.95 36128.73 1937811.27 24.8

CountyGREGG
Highway FM 349
From SH 31 IN KILGORE, E
To 0.247 MI W OF US 259 (KILGORE BYPS)
CSJ 0424-03-024
Proj ID C 424-3-24
Work Type GRD, CMT TRT SBGR, FLX BS, OCST, STRS
 
0.721 1065975.37 0.00 1080368.70 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-31-13
Work Began 03-04-14
Work Completed 01-21-15
Time Computed 01-06-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 100
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0424-03-024
MAC TRANSPORTATION, LTD, L.L.P.(5.31%)
ODUM SERVICES, L.P.( 14.48%)
PANOLA SIGN & BARRICADE, INC.(0.41%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.49%)
STRIPING TECHNOLOGY, L.P.(0.98%)
TEX OP CONSTRUCTION, LP(0.55%)
C & M TREE SERVICE (0.40%)
Contract # 08133038
Totals 1065975.37 0.00 1080368.70 100.0

CountyVAN ZANDT
Highway SH 198
From SH 243, IN CANTON, SW
To 0.4 MI NE OF FM 316 NEAR PHALBA
CSJ 0443-01-028
Proj ID STP 2014(415)HES
Work Type SBGR WDN, ACP BS, OCST, STRS, PFL PV MK
 
27.237 5034636.87 507351.98 3682321.79 73.1
Work Order 03-18-14
Work Began 04-08-14
Work Completed  
Time Computed 04-03-14
Contract Working Days 227
Addl Days Granted 54
Working Days Charged 282
Percent Time Used 100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0443-01-028
PANOLA SIGN & BARRICADE, INC.(1.18%)
STRIPING TECHNOLOGY, L.P.(4.35%)
BAHENA CONSTRUCTION CO.,INC. ( 11.46%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.48%)
FORTSON CONTRACTING, INC.(0.35%)
Contract # 02143224
Totals 5034636.87 507351.98 3682321.79 73.1

CountyHENDERSON
Highway FM 59
From FM 753, S
To 0.7 MI S OF RM 3273 (ANDERSON C/L)
CSJ 0458-01-022
Proj ID STP 2013(819)
Work Type SBGR WDN, ACP BS & SURF, OCST, MBGF, SIGN
 
12.567 6987662.21 0.00 6760620.72 100.0
Work Order 12-04-13
Work Began 12-31-13
Work Completed 12-01-15
Time Computed 12-20-13
Contract Working Days 232
Addl Days Granted 13
Working Days Charged 269
Percent Time Used 109
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0458-01-022
BAHENA CONSTRUCTION CO.,INC. (6.79%)
FORTSON CONTRACTING, INC.(0.54%)
MURRAY CONSTRUCTION(0.64%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.73%)
STRIPING TECHNOLOGY, L.P.(1.77%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.18%)
SAN-ANN-CO., INC.(0.41%)
COLD CREEK CONSTRUCTION, LTD (0.13%)
Contract # 09133223
Totals 6987662.21 0.00 6760620.72 100.0

CountyVAN ZANDT
Highway IH 20
From 1.5 MI E OF FM 1255, E
To 3.6 MI E OF FM 314 (SMITH C/L)
CSJ 0495-03-060
Proj ID NH 2015(622)
Work Type ACP BS & SURF, OCST, MICRO, PVT MRK
 
12.800 2377778.92 0.00 2305515.51 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-16-15
Work Began 06-22-15
Work Completed 12-01-15
Time Computed 04-01-15
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 100
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-03-060
SOUTHWEST ENVIRONMENT SERVICES LLC (0.56%)
ALTUS TRAFFIC MANAGEMENT LLC (0.28%)
TEXOP CONSTRUCTION (2.49%)
DUSTROL, INC.(0.76%)
STRIPING TECHNOLOGY, L.P.(2.44%)
APAC-KANSAS( 12.58%)
Contract # 02153226
Totals 2377778.92 0.00 2305515.51 100.0

CountySMITH
Highway IH 20
From US 69, IN LINDALE, E 0.819 MI
To END OF CONTROL SECTION
CSJ 0495-04-064
Proj ID IM 0206(109)
Work Type PLNG, OCST, ACP SURF, CLN & SL BRG JOINT
 
0.819 608794.45 0.00 748218.06 100.0
CountySMITH
Highway IH 20
From 0.8 MI E OF US 69, E
To 1.6 MI W OF FM 14(E OF LAVENDER RD)
CSJ 0495-05-047
Proj ID IM 0206(109)
Work Type PLNG, OCST, ACP SURF, CLN & SL BRG JOINT
 
3.857 1606311.94 0.00 1706282.73 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 07-08-14
Work Completed 01-29-15
Time Computed 05-01-14
Contract Working Days 60
Addl Days Granted 15
Working Days Charged 75
Percent Time Used 100
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-05-047
ALTUS TRAFFIC MANAGEMENT LLC (0.22%)
CHEROKEE SERVICES(8.87%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.37%)
TEX OP CONSTRUCTION, LP(1.28%)
STRIPING TECHNOLOGY, L.P.(1.74%)
APAC-KANSAS(3.78%)
DUSTROL, INC.(0.36%)
Contract # 03143223
Totals 2215106.39 0.00 2454500.79 100.0

CountyGREGG
Highway IH 20
From SH 31, E
To HARRISON C/L
CSJ 0495-07-072
Proj ID NH 1502(139)
Work Type TBPFC / ACP SURF, PLNG, BRG JNT, SHD TXT
 
8.176 5584277.98 376941.53 5046031.86 90.9
Work Order 06-18-15
Work Began 07-30-15
Work Completed  
Time Computed 07-19-15
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 96
Percent Time Used 147
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-07-072
PANOLA SIGN & BARRICADE, INC.(0.11%)
COWBELL TRAFFIC SERVICES, INC. (0.36%)
STRIPING TECHNOLOGY, L.P.(4.56%)
CHEROKEE SERVICES(2.98%)
Contract # 05153026
Totals 5584277.98 376941.53 5046031.86 90.9

CountyGREGG
Highway SH 42
From IH 20 SOUTH RAMP, S
To SH 31 IN KILGORE
CSJ 0545-04-046
Proj ID C 545-4-46
Work Type GR, STRS, SURF
 
2.082 3692466.84 50126.85 3344807.92 91.0
Work Order 09-17-13
Work Began 01-23-14
Work Completed  
Time Computed 01-13-14
Contract Working Days 88
Addl Days Granted 32
Working Days Charged 139
Percent Time Used 115
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0545-04-046
ALTUS TRAFFIC MANAGEMENT LLC (0.41%)
SOUTHWEST ENVIRONMENT SERVICES LLC (3.26%)
STRIPING TECHNOLOGY, L.P.(0.58%)
DUSTIN ALLEN, INC. (1.37%)
TEX OP CONSTRUCTION, LP(0.61%)
TRENDSETTER CONSTRUCTION, INC. (0.59%)
ROBINSON CONSTRUCTION(8.27%)
EAST TEXAS BRIDGE, INC.(1.16%)
L & L ASPHALT(0.00%)
Contract # 07133047
Totals 3692466.84 50126.85 3344807.92 91.0