Monthly State Let Construction Report For Tyler District As Of Jul 14, 2017 Page 2 Of 3

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySMITH
HighwaySH 31
FromSL 323, IN TYLER, E
ToFM 850 (E)
CSJ0424-01-053
Proj IDSTP 1602(359)
Work TypeOCST, 2" PFC
 
2.9461795043.6587505.964.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0424-01-053
FLEX SUPPLY, LLC (0.22)
TEXOP CONSTRUCTION (3.71)
STRIPING TECHNOLOGY, L.P. (3.32)
STRIPING SYSTEMS, INC. (0.00)
Contract #07163028
Totals1795043.650.0087505.964.8

CountyWOOD ETC
HighwaySH 182 ETC
From0.89 MI E OF US 69, E
ToSH 154
CSJ0429-01-023
Proj IDSTP 2017(358)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
27.8643239526.94604362.4818.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-17
Work Began04-07-17
Work Completed
Time Computed00-00-00
Contract Working Days387
Addl Days Granted0
Working Days Charged55
Percent Time Used14
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0429-01-023
TOTAL HIGHWAY MAINTENANCE, LLC (0.87)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.93)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.27)
ISAACS CONSTRUCTION SERVICES, LLC. (2.61)
Contract #01173007
Totals3239526.9481479.48604362.4818.6

CountyVAN ZANDT
HighwayIH 20
FromAT FM 314 WB EXIT RAMP
To.
CSJ0495-03-061
Proj IDNH 1602(360)
Work TypeGR,CMT TR SBGR,CONC PVT,STRS,ILLUM
 
1.1304570487.362842504.5662.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-19-16
Work Began10-13-16
Work Completed
Time Computed00-00-00
Contract Working Days215
Addl Days Granted0
Working Days Charged150
Percent Time Used69
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0495-03-061
PANOLA SIGN & BARRICADE, INC. (0.81)
ISAACS CONSTRUCTION SERVICES, LLC. (0.97)
TEXOP CONSTRUCTION (1.28)
WEST TEXAS RUMBLE STRIP (0.08)
ODUM SERVICES, L.P. (0.66)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.26)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.44)
STRIPING TECHNOLOGY, L.P. (3.55)
JEFF WILSON BORING (0.02)
CARTHAGE DRILLING, INC. (0.31)
INDUS CONSTRUCTION, L.P. (0.54)
Contract #07163232
Totals4570487.36279588.712842504.5662.1

CountySMITH
HighwayIH 20
From0.79 MI W OF US 69 IN LINDALE, E
ToEND OF CONTROL SECTION
CSJ0495-04-067
Proj IDNH 2017(747)
Work TypeTBPFC&ACP SURF,PLG,BRG JNTS,TEXTURE
 
6.7902876796.8517706.000.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-04-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged9
Percent Time Used17
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-04-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173003
Totals2876796.850.0017706.000.6

CountySMITH
HighwaySH 155
From2 MI S OF US 80 (UPSHUR C/L), S
ToIH 20
CSJ0520-01-021
Proj IDSTP 2017(087)
Work TypePLNG, ACP,OCST,PFC SURF,PVT MRKG
 
7.9785534730.864139027.1574.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-16-16
Work Began03-23-17
Work Completed
Time Computed00-00-00
Contract Working Days76
Addl Days Granted0
Working Days Charged33
Percent Time Used43
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0520-01-021
PANOLA SIGN & BARRICADE, INC. (0.21)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC (9.47)
STRIPE-A-ZONE, INC. (1.98)
Contract #09163224
Totals5534730.86350487.194139027.1574.7

CountyVAN ZANDT
HighwaySH 243
FromSH 198, E
ToSH 64 IN CANTON
CSJ0522-02-037
Proj IDSTP 1702(386)
Work TypeGR, STRS, WDNG, OCST, ACP, PVT MRKG
 
1.3216654770.060.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days213
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0522-02-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173232
Totals6654770.060.000.000.0

CountyHENDERSON
HighwayFM 315
FromFM 314, S
ToCR 4325/4224 (END C-S)
CSJ0559-02-034
Proj IDSTP 1502(282)HES
Work TypeSUBGRADE WIDEN, LEVEL-UP, OCST
 
5.7063079333.983841657.6699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-24-15
Work Began10-19-15
Work Completed
Time Computed00-00-00
Contract Working Days175
Addl Days Granted3
Working Days Charged177
Percent Time Used99
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0559-02-034
COLD CREEK CONSTRUCTION, LTD (1.97)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.79)
SAMMY G. SMALLWOOD (1.20)
STRIPING TECHNOLOGY, L.P. (1.64)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (4.49)
STRIPING SYSTEMS, INC. (0.04)
NIXON ENGINEERING (0.00)
FORTSON CONTRACTING, INC. (0.42)
Contract #06153229
Totals3079333.98240756.333841657.6699.9

CountyCHEROKEE
HighwayFM 22
From1.5 MI W OF FM 768, (CR 1512), E
ToSH 110
CSJ0634-01-012
Proj IDSTP 2017(363)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
4.8311037127.00413798.4039.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-17
Work Began04-10-17
Work Completed
Time Computed00-00-00
Contract Working Days110
Addl Days Granted0
Working Days Charged44
Percent Time Used40
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0634-01-012
DUSTIN ALLEN, INC. (14.70)
TOTAL HIGHWAY MAINTENANCE, LLC (0.64)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.96)
ISAACS CONSTRUCTION SERVICES, LLC. (2.00)
Contract #01173012
Totals1037127.0077366.00413798.4039.8

CountyVAN ZANDT
HighwayFM 314
From2.3 MI N OF SH 64(CR 4907),S
ToFM 279 (E) IN EDOM
CSJ0745-01-015
Proj IDSTP 2014(634)
Work TypeSCAR,RESHAPE,FLX BS,SURF TRT,STRS
 
11.71211961746.068122253.4467.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-08-14
Work Began11-07-14
Work Completed
Time Computed00-00-00
Contract Working Days486
Addl Days Granted0
Working Days Charged429
Percent Time Used88
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0745-01-015
STRIPING TECHNOLOGY, L.P. (1.40)
DUSTIN ALLEN, INC. (0.74)
KENSAR LLC DBA S & S TRUCKING (4.64)
AGGREGATE HAULERS, INC. (MEXIA) (0.12)
Contract #05143203
Totals11961746.06573051.358122253.4467.9

CountySMITH
HighwayVA
FromVAR LOCS IN GREGG & RUSK COUNTIES
ToCITIES OF LONGVIEW,KILGORE,HENDERSN
CSJ0910-00-105
Proj IDSTP 2016(366)
Work TypeCURB RAMPS
 
0.1001419691.25954666.9967.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-10-17
Work Began03-15-17
Work Completed
Time Computed00-00-00
Contract Working Days145
Addl Days Granted0
Working Days Charged83
Percent Time Used57
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-00-105
STRIPING TECHNOLOGY, L.P. (0.07)
W.A. ROBBINS CONSTRUCTION CO., INC. (5.24)
STRIPE-A-ZONE, INC. (3.38)
AWP, INC. (0.50)
Contract #12163035
Totals1419691.2589399.15954666.9967.2

CountyGREGG
HighwayVA
FromVARIOUS LOCATIONS IN KILGORE,
ToGLADEWATER & LONGVIEW
CSJ0910-07-068
Proj IDSTP 1602(646)
Work TypePLANT TREES & SHRUBS, IRRIGATION
 
1.000254158.62235323.3692.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-16
Work Began03-20-17
Work Completed
Time Computed00-00-00
Contract Working Days92
Addl Days Granted0
Working Days Charged41
Percent Time Used44
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-07-068
TX DOWN UNDER CONSTRUCTION, LLC (2.56)
PANOLA SIGN & BARRICADE, INC. (4.09)
Contract #08163052
Totals254158.629963.10235323.3692.5

CountyGREGG
HighwayVA
FromVARIOUS LOCATIONS IN
ToTHE CITY OF LONGVIEW
CSJ0910-07-069
Proj IDSTP 1702(387)
Work TypeINSTALL FLASHING LT ARROWS
 
0.0101279638.810.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days141
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-07-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173215
Totals1279638.810.000.000.0

CountyANDERSON
HighwayCR
FromCR 2418 AT OTTER CREEK
ToSTR# AA03-55-001
CSJ0910-08-067
Proj IDBR 2015(257)
Work TypeRPLC BRG&APPR,GR,ACPBS&SURF,MBGF
 
0.139753675.60141170.7818.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-26-17
Work Began06-13-17
Work Completed
Time Computed00-00-00
Contract Working Days108
Addl Days Granted0
Working Days Charged18
Percent Time Used16
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0910-08-067
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.76)
AMERICAN REMEDIATION OPTIONS, INC. (4.01)
Contract #03173016
Totals753675.60141170.78141170.7818.7

CountyANDERSON
HighwayCR
FromCR 2133 AT MACK CREEK
ToSTR#AA2133101, BTWN US 79 & FM 1990
CSJ0910-08-069
Proj IDBR 2015(260)
Work TypeREPLACE BRIDGE AND APPROACHES
 
1.000499832.22376452.3979.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-27-16
Work Began09-19-16
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged94
Percent Time Used156
Contractor(s)
FRITCHER CONSTRUCTION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 0910-08-069
FLEX SUPPLY, LLC (0.70)
JM YANEZ CONSTRUCTION, INC. (31.12)
SOUTHWEST ENVIRONMENT SERVICES LLC (3.35)
SHINN & GREGORY, INC. (11.36)
MORRIS COUNTY CONTRACTORS, L.L.C. (2.43)
Contract #04163005
Totals499832.2235071.80376452.3979.3

CountyVAN ZANDT
HighwayCR
FromCR 3105 AT CROOKED CREEK
ToSTR # AA01-19-002
CSJ0910-12-034
Proj IDBR 1502(662)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.4001432779.001368354.3295.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-10-16
Work Began06-13-16
Work Completed
Time Computed00-00-00
Contract Working Days272
Addl Days Granted0
Working Days Charged211
Percent Time Used77
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-12-034
PANOLA SIGN & BARRICADE, INC. (1.08)
SOUTHWEST ENVIRONMENT SERVICES LLC (3.28)
PEACHTREE CONSTRUCTION, LTD. (9.24)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.50)
ODUM SERVICES, L.P. (3.37)
Contract #03163024
Totals1432779.0083848.991368354.3295.5

CountyVAN ZANDT
HighwayCR
FromCR 1825 AT UPRR, 0.1 MI S OF US 80
ToSTR# AA01-55-001,SW OF GRAND SALINE
CSJ0910-12-066
Proj IDBR 2013(723)
Work TypeREPLACE RAILROAD OVERPASS
 
0.1231498798.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days162
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0910-12-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173016
Totals1498798.050.000.000.0

CountySMITH
HighwayPW
FromVARIOUS LOCATIONS
ToWITHIN TYLER STATE PARK
CSJ0910-16-121
Proj IDC 910-16-121
Work TypeOVERLAY
 
1.0001269696.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-19-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days123
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-121
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173028
Totals1269696.000.000.000.0

CountySMITH
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE CITY OF TYLER
CSJ0910-16-130
Proj IDSTP 1602(439)
Work TypeGR, SIGNALS, ACP BS&SURF, PVT MRKG
 
0.5752355455.5013600.000.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days196
Addl Days Granted0
Working Days Charged7
Percent Time Used3
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-130
PANOLA SIGN & BARRICADE, INC. (1.53)
Contract #03173205
Totals2355455.5013200.0013600.000.5

CountySMITH
HighwayVA
FromON SH110,FRM HAGAN,.7 MI S OF FM346
To0.1 MI S OF LEXINGTON SPA IN WHTHSE
CSJ0910-16-138
Proj IDSTP 2017(928)
Work TypeCONSTRUCT SIDEWALKS AND CURB RAMPS
 
0.30097066.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-22-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days48
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
M & M STRIPING & POWER WASHING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-138
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173225
Totals97066.000.000.000.0

CountyVAN ZANDT
HighwayFM 1256
FromFM 316, E
ToSH 19
CSJ1172-01-007
Proj IDSSW 1172-1-7
Work TypeGR, FLEX BS, TCST, STRS, PV MK
 
7.9545779955.802161560.5937.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-02-16
Work Began07-08-16
Work Completed
Time Computed00-00-00
Contract Working Days206
Addl Days Granted0
Working Days Charged91
Percent Time Used44
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1172-01-007
ODUM SERVICES, L.P. (0.69)
STRIPING TECHNOLOGY, L.P. (1.35)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.68)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.40)
PANOLA SIGN & BARRICADE, INC. (0.50)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.73)
STRIPING SYSTEMS, INC. (0.02)
MAC TRANSPORTATION, LTD, L.L.P. (0.87)
KENSAR LLC DBA S & S TRUCKING (1.49)
Contract #04163210
Totals5779955.80437028.872161560.5937.3

page 1 | page 2 | page 3