Monthly State Let Construction Report For Tyler District As Of May 15, 2013 Page 2 Of 2

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyANDERSON
Highway LP 256
From US 79 IN PALESTINE, SE & S
To US 84
CSJ 0520-09-031
Proj ID STP 2009(955)
Work Type RECONSTR GR, STRS, BS, SURF & PAV M
 
1.574 7615569.93 0.00 7704294.49 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-02-09
Work Began 12-02-09
Work Completed  
Time Computed 11-18-09
Contract Working Days 394
Addl Days Granted 0
Working Days Charged 508
Percent Time Used 128
Contractor(s)
SAFECO INSURANCE COMPANIES
SUBCONTRACTOR(S) FOR CCSJ: 0520-09-031
TOTAL HIGHWAY MAINTENANCE, LLC (0.28%)
MURRAY CONSTRUCTION(0.30%)
A & R DEMOLITION (0.78%)
WYLIE DRILLING & DRAINAGE, INC.(1.18%)
J.D. RAMMING PAVING CO., LTD.(0.00%)
STRIPING TECHNOLOGY, L.P.(5.72%)
TREVCON, INC.(0.95%)
ALLIED FENCE COMPANY (0.00%)
CENTRAL TEXAS REINFORCEMENT(0.48%)
APAC-TEXAS, INC. ( 23.00%)
HAYWARD BAKER, INC.(2.79%)
PRIMATE CONSTRUCTION, INC. (0.12%)
SCR CONSTRUCTION CO., INC. (0.73%)
SCOTT DERR PAINTING CO, LLC(0.05%)
WEBBER BARRIER SERVICES, INC.(0.92%)
AAA FENCE COMPANY OF AUSTIN, INC.(0.21%)
EAST TEXAS BRIDGE, INC.( 40.77%)
FORTSON CONTRACTING, INC.(0.11%)
TEX OP CONSTRUCTION, LP(0.25%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.31%)
MESA ROD BUSTERS, INC. (0.05%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.67%)
GIBSON & ASSOCIATES, INC.(0.14%)
Contract # 09093201
Totals 7615569.93 0.00 7704294.49 99.9

CountySMITH
Highway FM 16
From SH 110, E
To SH 155
CSJ 0522-04-028
Proj ID STP 2012(297)
Work Type OCST, HMAC SURF, PVT MRKG
 
22.879 2357887.20 0.00 764452.29 32.4
CountySMITH
Highway FM 16
From SH 110, NR GARDEN VALLEY, E
To SH 155, IN WINONA
CSJ 0522-04-029
Proj ID STP 2012(296)HES
Work Type PROFILE MARKING CNTRLN RMBL STRIPS
 
47.953 4533012.78 46966.21 3635972.23 80.2
Work Order 03-19-12
Work Began 04-11-12
Work Completed  
Time Computed 04-04-12
Contract Working Days 120
Addl Days Granted 6
Working Days Charged 110
Percent Time Used 87
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0522-04-028
STRIPING TECHNOLOGY, L.P.(5.11%)
DUSTIN ALLEN, INC. (1.38%)
HIGHWAY TECHNOLOGIES, INC. (0.31%)
MAC TRANSPORTATION, LTD, L.L.P.(1.75%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(1.37%)
Contract # 02123203
Totals 6890899.98 46966.21 4400424.52 63.8

CountyHENDERSON
Highway SH 274
From 1.4 MI S OF FM 3225 (AVANT RD), S
To SH 31 IN TRINIDAD
CSJ 0561-02-035
Proj ID STP 2013(397)HES
Work Type SUBGRADE WIDEN, LEVEL - UP, OCST
 
8.100 3239483.87 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-10-13
Work Began 00-00-00
Work Completed  
Time Computed 04-26-13
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0561-02-035
PANOLA SIGN & BARRICADE, INC.(0.68%)
Contract # 02133018
Totals 3239483.87 0.00 0.00 0.0

CountyRUSK
Highway SH 323
From 1.7 MI SE OF SH 42 (CR 4137A), SE
To 2.4 MI N OF SL 571 (CR 427D)
CSJ 0592-01-013
Proj ID STP 2012(299)HES
Work Type SUBGRADE WIDEN, LEVEL - UP, OCST
 
13.607 2078750.32 0.00 1560350.63 75.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-06-12
Work Began 03-26-12
Work Completed  
Time Computed 03-22-12
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 77
Percent Time Used 110
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0592-01-013
HIGHWAY TECHNOLOGIES, INC. (0.73%)
STRIPING TECHNOLOGY, L.P.(6.07%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.94%)
FORTSON CONTRACTING, INC.(1.49%)
Contract # 02123023
Totals 2078750.32 0.00 1560350.63 75.3

CountyRUSK
Highway FM 840
From 1 MI SE OF US 79 (PECAN CRK DR), SE
To FM 2867
CSJ 0592-02-014
Proj ID STP 2012(300)HES
Work Type SUBGRADE WIDEN, LEVEL - UP, OCST
 
13.186 3692047.24 17812.50 2459754.99 66.6
Work Order 04-05-12
Work Began 04-30-12
Work Completed  
Time Computed 04-21-12
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 145
Percent Time Used 80
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0592-02-014
STRIPING TECHNOLOGY, L.P.(3.21%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.41%)
ODUM SERVICES, L.P.(2.70%)
ROBINSON CONSTRUCTION(9.56%)
Contract # 02123224
Totals 3692047.24 17812.50 2459754.99 66.6

CountySMITH
Highway VA
From VARIOUS LOCATIONS IN HENDERSON
To WOOD, VAN ZANDT & ANDERSON COUNTIES
CSJ 0910-00-095
Proj ID STP 2013(682)
Work Type ADA CURB RAMPS
 
1.000 1347171.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 218
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY 19 CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-00-095
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133034
Totals 1347171.00 0.00 0.00 0.0

CountySMITH
Highway CR
From CR 1141 AT INDIAN CR & SO.PAC R/R
To STR# AA01-29-001 & 2, W OF TYLER
CSJ 0910-16-066
Proj ID BR 96(534)
Work Type RPLC BRGS & APPRS, GR, ACP BS & SURF, MBGF
 
0.181 1048288.84 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133232
Totals 1048288.84 0.00 0.00 0.0

CountySMITH
Highway CR
From CR 2115 AT BOWLES CREEK
To STR#AA21-15-001,0.1 MI W OF RUSK CL
CSJ 0910-16-112
Proj ID BR 2012(185)
Work Type RPLC BRG & APPR, GRDG, ACP BS & SURF, MBGF
 
0.140 422632.92 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-13-13
Work Began 00-00-00
Work Completed  
Time Computed 05-29-13
Contract Working Days 92
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-112
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133029
Totals 422632.92 0.00 0.00 0.0

CountyGREGG
Highway LP 281 ETC
From SH 31, IN SW LONGVIEW, N & W
To 0.3 MI E OF FM 2206 (ENTERPRISE)
CSJ 1763-02-028
Proj ID NH 2013(205)
Work Type INTERCONNECT SIGNALS
 
7.159 516574.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-21-13
Work Began 00-00-00
Work Completed  
Time Computed 04-06-13
Contract Working Days 67
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1763-02-028
ALTUS TRAFFIC MANAGEMENT LLC (1.82%)
GREEN LIGHT IN THE GROUND( 22.05%)
Contract # 12123017
Totals 516574.00 0.00 0.00 0.0

CountyGREGG
Highway LP 281
From SH 31 IN LONGVIEW, S
To 0.42 MI S OF FM 2087
CSJ 1763-03-029
Proj ID STP 1102(227)RGS
Work Type GR, STRS, HMAC BS, CONC PVT, C & G, SIGNLS
 
1.680 13235356.95 504309.28 1050037.16 7.9
Work Order 09-27-11
Work Began 03-18-13
Work Completed  
Time Computed 03-01-12
Contract Working Days 575
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1763-03-029
PANOLA SIGN & BARRICADE, INC.(0.27%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.97%)
MAC TRANSPORTATION, LTD, L.L.P.(3.61%)
SCOTT DERR PAINTING CO, LLC(0.04%)
STRIPING TECHNOLOGY, L.P.(5.45%)
DUSTIN ALLEN, INC. (0.16%)
TEX OP CONSTRUCTION, LP(0.53%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.76%)
DUKE IRRIGATION(0.17%)
DIAMOND H SERVICES, INC. (0.03%)
Contract # 08113205
Totals 13235356.95 504309.28 1050037.16 7.9

CountySMITH
Highway LP 323
From US 69 (N) IN TYLER, E
To LP323,.5 MI E OF US271(AMER LEG RD)
CSJ 2075-01-053
Proj ID NH 2013(466)
Work Type OCST, 2" OVERLAY
 
3.985 1965643.25 0.00 0.00 0.0
CountySMITH
Highway LP 323
From US 69 (N) IN TYLER, E
To LP323,.5 MI E OF US271(AMER LEG RD)
CSJ 2075-01-056
Proj ID NH 2013(466)
Work Type OCST, 2" OVERLAY
 
3.985 1828463.02 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2075-01-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133207
Totals 3794106.27 0.00 0.00 0.0

CountyVAN ZANDT
Highway FM 2339
From FM 1861, E
To FM 773, NR HENDERSON C/L
CSJ 2265-01-014
Proj ID STP 2012(369)
Work Type GRD, STRS, BS, SURF TRT, MBFG, PV MRK
 
4.329 1705832.33 375990.89 1182478.89 69.3
Work Order 04-11-12
Work Began 04-23-12
Work Completed  
Time Computed 04-27-12
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 90
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2265-01-014
STRIPING TECHNOLOGY, L.P.(2.17%)
BAHENA CONSTRUCTION CO.,INC. (8.33%)
COWBELL TRAFFIC SERVICES, INC. (0.41%)
CATACON, INC.(1.91%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(1.44%)
Contract # 03123224
Totals 1705832.33 375990.89 1182478.89 69.3

CountySMITH
Highway SP 364
From SH 31, SE
To SL 323 IN TYLER
CSJ 2833-01-011
Proj ID STP 2013(683)
Work Type 2" MILL, OCST, 2' INLAY
 
6.922 2870170.33 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2833-01-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133236
Totals 2870170.33 0.00 0.00 0.0

page 1 | page 2