Monthly State Let Construction Report For Tyler District As Of Sep 21, 2017 Page 2 Of 3

Last Update: Friday, September 22, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySMITH
HighwaySH 31
FromFM 757, E
To2.5 MI W OF FM 2767(NR MULEY BRC),E
CSJ0424-01-048
Proj IDSTP 2013(640)
Work TypeGR,STRS,ACP BS & SURF,PVT MRK
 
10.7347802782.956669838.0985.4
Work Order10-29-14
Work Began11-18-14
Work Completed
Time Computed11-14-14
Contract Working Days328
Addl Days Granted0
Working Days Charged300
Percent Time Used91
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0424-01-048
SOUTHWEST ENVIRONMENT SERVICES LLC (4.79)
ALTUS TRAFFIC MANAGEMENT LLC (0.48)
STRIPING TECHNOLOGY, L.P. (2.44)
C.S. TREE SERVICE (0.48)
FORTSON CONTRACTING, INC. (0.09)
MURRAY CONSTRUCTION (0.22)
TEX OP CONSTRUCTION, LP (0.79)
J & I TRUCKING CO (1.05)
HOPE SERVICES, INC. (0.70)
HARRIS TRUCKING SERVICES (1.40)
ISAACS CONSTRUCTION SERVICES, LLC. (0.93)
Contract #08143053
Totals7802782.95646593.726669838.0985.4

CountySMITH
HighwaySH 31
FromSL 323, IN TYLER, E
ToFM 850 (E)
CSJ0424-01-053
Proj IDSTP 1602(359)
Work TypeOCST, 2" PFC
 
2.9461795043.65550013.0630.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-16
Work Began07-17-17
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged17
Percent Time Used48
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0424-01-053
FLEX SUPPLY, LLC (0.22)
TEXOP CONSTRUCTION (3.71)
STRIPING TECHNOLOGY, L.P. (3.32)
STRIPING SYSTEMS, INC. (0.00)
Contract #07163028
Totals1795043.650.00550013.0630.6

CountyWOOD ETC
HighwaySH 182 ETC
From0.89 MI E OF US 69, E
ToSH 154
CSJ0429-01-023
Proj IDSTP 2017(358)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
27.8643239526.94735076.4822.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-17
Work Began04-07-17
Work Completed
Time Computed00-00-00
Contract Working Days387
Addl Days Granted0
Working Days Charged87
Percent Time Used22
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0429-01-023
TOTAL HIGHWAY MAINTENANCE, LLC (0.87)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.93)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.27)
ISAACS CONSTRUCTION SERVICES, LLC. (2.61)
Contract #01173007
Totals3239526.94104040.00735076.4822.6

CountyVAN ZANDT
HighwayIH 20
FromAT FM 314 WB EXIT RAMP
To.
CSJ0495-03-061
Proj IDNH 1602(360)
Work TypeGR,CMT TR SBGR,CONC PVT,STRS,ILLUM
 
1.1304570487.363203250.3970.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-19-16
Work Began10-13-16
Work Completed
Time Computed00-00-00
Contract Working Days215
Addl Days Granted120
Working Days Charged187
Percent Time Used55
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0495-03-061
PANOLA SIGN & BARRICADE, INC. (0.81)
ISAACS CONSTRUCTION SERVICES, LLC. (0.97)
TEXOP CONSTRUCTION (1.28)
WEST TEXAS RUMBLE STRIP (0.08)
ODUM SERVICES, L.P. (0.66)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.26)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.44)
STRIPING TECHNOLOGY, L.P. (3.55)
JEFF WILSON BORING (0.02)
CARTHAGE DRILLING, INC. (0.31)
INDUS CONSTRUCTION, L.P. (0.54)
Contract #07163232
Totals4570487.36248231.963203250.3970.0

CountySMITH
HighwayIH 20
From0.79 MI W OF US 69 IN LINDALE, E
ToEND OF CONTROL SECTION
CSJ0495-04-067
Proj IDNH 2017(747)
Work TypeTBPFC&ACP SURF,PLG,BRG JNTS,TEXTURE
 
6.7902876796.8517706.000.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-04-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged28
Percent Time Used54
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-04-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173003
Totals2876796.850.0017706.000.6

CountySMITH
HighwaySH 155
From2 MI S OF US 80 (UPSHUR C/L), S
ToIH 20
CSJ0520-01-021
Proj IDSTP 2017(087)
Work TypePLNG, ACP,OCST,PFC SURF,PVT MRKG
 
7.9785534730.865629854.5999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-16-16
Work Began03-23-17
Work Completed
Time Computed00-00-00
Contract Working Days76
Addl Days Granted0
Working Days Charged54
Percent Time Used71
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0520-01-021
PANOLA SIGN & BARRICADE, INC. (0.21)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC (9.47)
STRIPE-A-ZONE, INC. (1.98)
Contract #09163224
Totals5534730.86907575.895629854.5999.9

CountyVAN ZANDT
HighwaySH 243
FromSH 198, E
ToSH 64 IN CANTON
CSJ0522-02-037
Proj IDSTP 1702(386)
Work TypeGR, STRS, WDNG, OCST, ACP, PVT MRKG
 
1.3216654770.0615030.400.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began08-24-17
Work Completed
Time Computed00-00-00
Contract Working Days213
Addl Days Granted0
Working Days Charged5
Percent Time Used2
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0522-02-037
STRIPING TECHNOLOGY, L.P. (6.31)
PANOLA SIGN & BARRICADE, INC. (0.33)
SCOTT DERR PAINTING CO, LLC (0.11)
TEX OP CONSTRUCTION, LP (0.67)
ODUM SERVICES, L.P. (0.51)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (3.45)
MAC TRANSPORTATION, LTD, L.L.P. (1.76)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.50)
Contract #06173232
Totals6654770.0615030.4015030.400.2

CountyHENDERSON
HighwayFM 315
FromFM 314, S
ToCR 4325/4224 (END C-S)
CSJ0559-02-034
Proj IDSTP 1502(282)HES
Work TypeSUBGRADE WIDEN, LEVEL-UP, OCST
 
5.7063079333.983896469.44100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-24-15
Work Began10-19-15
Work Completed08-25-17
Time Computed00-00-00
Contract Working Days175
Addl Days Granted3
Working Days Charged177
Percent Time Used99
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0559-02-034
COLD CREEK CONSTRUCTION, LTD (1.97)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.79)
SAMMY G. SMALLWOOD (1.20)
STRIPING TECHNOLOGY, L.P. (1.64)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (4.49)
STRIPING SYSTEMS, INC. (0.04)
NIXON ENGINEERING (0.00)
FORTSON CONTRACTING, INC. (0.42)
Contract #06153229
Totals3079333.985736.223896469.44100.0

CountyCHEROKEE
HighwayFM 22
From1.5 MI W OF FM 768, (CR 1512), E
ToSH 110
CSJ0634-01-012
Proj IDSTP 2017(363)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
4.8311037127.00602705.0658.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-17
Work Began04-10-17
Work Completed
Time Computed00-00-00
Contract Working Days110
Addl Days Granted0
Working Days Charged80
Percent Time Used72
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0634-01-012
DUSTIN ALLEN, INC. (14.70)
TOTAL HIGHWAY MAINTENANCE, LLC (0.64)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.96)
ISAACS CONSTRUCTION SERVICES, LLC. (2.00)
Contract #01173012
Totals1037127.00100300.00602705.0658.1

CountyVAN ZANDT
HighwayFM 314
From2.3 MI N OF SH 64(CR 4907),S
ToFM 279 (E) IN EDOM
CSJ0745-01-015
Proj IDSTP 2014(634)
Work TypeSCAR,RESHAPE,FLX BS,SURF TRT,STRS
 
11.71211961746.069102453.3676.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-08-14
Work Began11-07-14
Work Completed
Time Computed00-00-00
Contract Working Days486
Addl Days Granted0
Working Days Charged468
Percent Time Used96
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0745-01-015
STRIPING TECHNOLOGY, L.P. (1.40)
DUSTIN ALLEN, INC. (0.74)
KENSAR LLC DBA S & S TRUCKING (4.64)
AGGREGATE HAULERS, INC. (MEXIA) (0.12)
NIXON ENGINEERING, L.L.C. (0.06)
Contract #05143203
Totals11961746.06542068.999102453.3676.0

CountySMITH
HighwayVA
FromVAR LOCS IN GREGG & RUSK COUNTIES
ToCITIES OF LONGVIEW,KILGORE,HENDERSN
CSJ0910-00-105
Proj IDSTP 2016(366)
Work TypeCURB RAMPS
 
0.1001419691.251310370.2092.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-10-17
Work Began03-15-17
Work Completed
Time Computed00-00-00
Contract Working Days145
Addl Days Granted0
Working Days Charged119
Percent Time Used82
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-00-105
STRIPING TECHNOLOGY, L.P. (0.29)
W.A. ROBBINS CONSTRUCTION CO., INC. (5.65)
STRIPE-A-ZONE, INC. (3.38)
AREA WIDE PROTECTIVE, INC. (0.50)
Contract #12163035
Totals1419691.25141359.641310370.2092.2

CountySMITH
HighwayVA
FromVARIOUS LOCATIONS IN
ToGREGG & RUSK COUNTIES
CSJ0910-00-108
Proj IDSTP 1702(466)
Work TypePLANT TREES & SHRUBS, IRRIGATION
 
0.100224599.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days98
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CENTRAL NORTH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-00-108
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173039
Totals224599.500.000.000.0

CountyGREGG
HighwayVA
FromVARIOUS LOCATIONS IN KILGORE,
ToGLADEWATER & LONGVIEW
CSJ0910-07-068
Proj IDSTP 1602(646)
Work TypePLANT TREES & SHRUBS, IRRIGATION
 
1.000254158.62241323.3694.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-16
Work Began03-20-17
Work Completed
Time Computed00-00-00
Contract Working Days92
Addl Days Granted0
Working Days Charged41
Percent Time Used44
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-07-068
TX DOWN UNDER CONSTRUCTION, LLC (2.56)
PANOLA SIGN & BARRICADE, INC. (4.09)
TURFSCAPES (1.14)
Contract #08163052
Totals254158.623000.00241323.3694.9

CountyGREGG
HighwayVA
FromVARIOUS LOCATIONS IN
ToTHE CITY OF LONGVIEW
CSJ0910-07-069
Proj IDSTP 1702(387)
Work TypeINSTALL FLASHING LT ARROWS
 
0.0101279638.810.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-07-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days141
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-07-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173215
Totals1279638.810.000.000.0

CountyANDERSON
HighwayCR
FromCR 2418 AT OTTER CREEK
ToSTR# AA03-55-001
CSJ0910-08-067
Proj IDBR 2015(257)
Work TypeRPLC BRG&APPR,GR,ACPBS&SURF,MBGF
 
0.139753675.60325524.8243.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-26-17
Work Began06-13-17
Work Completed
Time Computed00-00-00
Contract Working Days108
Addl Days Granted0
Working Days Charged56
Percent Time Used51
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0910-08-067
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.76)
AMERICAN REMEDIATION OPTIONS, INC. (4.01)
Contract #03173016
Totals753675.6077578.99325524.8243.1

CountyANDERSON
HighwayCR
FromCR 2133 AT MACK CREEK
ToSTR#AA2133101, BTWN US 79 & FM 1990
CSJ0910-08-069
Proj IDBR 2015(260)
Work TypeREPLACE BRIDGE AND APPROACHES
 
1.000499832.22459074.77100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-27-16
Work Began09-19-16
Work Completed08-29-17
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged118
Percent Time Used196
Contractor(s)
FRITCHER CONSTRUCTION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 0910-08-069
FLEX SUPPLY, LLC (0.70)
JM YANEZ CONSTRUCTION, INC. (31.12)
SOUTHWEST ENVIRONMENT SERVICES LLC (3.35)
SHINN & GREGORY, INC. (11.36)
MORRIS COUNTY CONTRACTORS, L.L.C. (2.43)
A K CONTRACTING, LLC (0.75)
Contract #04163005
Totals499832.224260.70459074.77100.0

CountyVAN ZANDT
HighwayCR
FromCR 3105 AT CROOKED CREEK
ToSTR # AA01-19-002
CSJ0910-12-034
Proj IDBR 1502(662)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.4001432779.001373177.32100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-10-16
Work Began06-13-16
Work Completed09-13-17
Time Computed00-00-00
Contract Working Days272
Addl Days Granted0
Working Days Charged211
Percent Time Used77
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-12-034
PANOLA SIGN & BARRICADE, INC. (1.08)
SOUTHWEST ENVIRONMENT SERVICES LLC (3.28)
PEACHTREE CONSTRUCTION, LTD. (9.24)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.50)
ODUM SERVICES, L.P. (3.37)
Contract #03163024
Totals1432779.001797.001373177.32100.0

CountyVAN ZANDT
HighwayCR
FromCR 1825 AT UPRR, 0.1 MI S OF US 80
ToSTR# AA01-55-001,SW OF GRAND SALINE
CSJ0910-12-066
Proj IDBR 2013(723)
Work TypeREPLACE RAILROAD OVERPASS
 
0.1231498798.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-02-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days162
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0910-12-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173016
Totals1498798.050.000.000.0

CountySMITH
HighwayPW
FromVARIOUS LOCATIONS
ToWITHIN TYLER STATE PARK
CSJ0910-16-121
Proj IDC 910-16-121
Work TypeOVERLAY
 
1.0001269696.00684939.1053.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-19-17
Work Began07-05-17
Work Completed
Time Computed00-00-00
Contract Working Days123
Addl Days Granted0
Working Days Charged39
Percent Time Used31
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-121
A. L. CONSTRUCTION, LLC (3.26)
TOTAL HIGHWAY MAINTENANCE, LLC (0.41)
STRIPE-A-ZONE, INC. (0.34)
Contract #03173028
Totals1269696.00225963.83684939.1053.9

CountySMITH
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE CITY OF TYLER
CSJ0910-16-130
Proj IDSTP 1602(439)
Work TypeGR, SIGNALS, ACP BS&SURF, PVT MRKG
 
0.5752355455.50300801.3312.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-17
Work Began07-05-17
Work Completed
Time Computed00-00-00
Contract Working Days196
Addl Days Granted0
Working Days Charged30
Percent Time Used15
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-130
PANOLA SIGN & BARRICADE, INC. (1.53)
J & M CONTRACTING, COMPANY (6.06)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.95)
STRIPING TECHNOLOGY, L.P. (15.39)
TEX OP CONSTRUCTION, LP (3.40)
ISAACS CONSTRUCTION SERVICES, LLC. (0.38)
CARTHAGE DRILLING, INC. (0.89)
STRIPING SYSTEMS, INC. (0.04)
JOHNSON CONSTRUCTION, J.C. (7.90)
Contract #03173205
Totals2355455.5096083.73300801.3312.7

page 1 | page 2 | page 3