Monthly State Let Construction Report For Tyler District As Of Apr 10, 2017 Page 2 Of 3

Last Update: Monday, April 10, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGREGG
HighwaySH 149
FromAT SABINE RIVER #100930039301017
To.
CSJ0393-01-097
Proj IDBR 1502(474)
Work TypeCONC BR RAIL, MBGF, CONC STR RPR
 
0.9413114797.790.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days145
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0393-01-097
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173008
Totals3114797.790.000.000.0

CountySMITH
HighwaySH 31
FromFM 757, E
To2.5 MI W OF FM 2767(NR MULEY BRC),E
CSJ0424-01-048
Proj IDSTP 2013(640)
Work TypeGR,STRS,ACP BS & SURF,PVT MRK
 
10.7347802782.955356859.1668.6
Work Order10-29-14
Work Began11-18-14
Work Completed
Time Computed11-14-14
Contract Working Days328
Addl Days Granted0
Working Days Charged270
Percent Time Used82
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0424-01-048
SOUTHWEST ENVIRONMENT SERVICES LLC (4.79)
ALTUS TRAFFIC MANAGEMENT LLC (0.48)
STRIPING TECHNOLOGY, L.P. (2.44)
C.S. TREE SERVICE (0.48)
FORTSON CONTRACTING, INC. (0.09)
MURRAY CONSTRUCTION (0.22)
TEX OP CONSTRUCTION, LP (0.79)
J & I TRUCKING CO (1.05)
HOPE SERVICES, INC. (0.70)
HARRIS TRUCKING SERVICES (1.40)
ISAACS CONSTRUCTION SERVICES, LLC. (0.93)
Contract #08143053
Totals7802782.95167332.565356859.1668.6

CountySMITH
HighwaySH 31
FromSL 323, IN TYLER, E
ToFM 850 (E)
CSJ0424-01-053
Proj IDSTP 1602(359)
Work TypeOCST, 2" PFC
 
2.9461795043.6587505.964.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0424-01-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07163028
Totals1795043.650.0087505.964.8

CountyWOOD ETC
HighwaySH 182 ETC
From0.89 MI E OF US 69, E
ToSH 154
CSJ0429-01-023
Proj IDSTP 2017(358)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
27.8643239526.940.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days387
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0429-01-023
TOTAL HIGHWAY MAINTENANCE, LLC (0.87)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.93)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.27)
ISAACS CONSTRUCTION SERVICES, LLC. (2.61)
Contract #01173007
Totals3239526.940.000.000.0

CountyVAN ZANDT
HighwayIH 20
FromAT FM 314 WB EXIT RAMP
To.
CSJ0495-03-061
Proj IDNH 1602(360)
Work TypeGR,CMT TR SBGR,CONC PVT,STRS,ILLUM
 
1.1304570487.362258671.2849.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-19-16
Work Began10-13-16
Work Completed
Time Computed00-00-00
Contract Working Days215
Addl Days Granted0
Working Days Charged118
Percent Time Used54
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0495-03-061
PANOLA SIGN & BARRICADE, INC. (0.81)
ISAACS CONSTRUCTION SERVICES, LLC. (0.97)
TEXOP CONSTRUCTION (1.28)
WEST TEXAS RUMBLE STRIP (0.08)
ODUM SERVICES, L.P. (0.66)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.23)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.44)
STRIPING TECHNOLOGY, L.P. (3.52)
JEFF WILSON BORING (0.02)
CARTHAGE DRILLING, INC. (0.31)
INDUS CONSTRUCTION, L.P. (0.54)
Contract #07163232
Totals4570487.360.002258671.2849.4

CountySMITH
HighwayIH 20
From0.79 MI W OF US 69 IN LINDALE, E
ToEND OF CONTROL SECTION
CSJ0495-04-067
Proj IDNH 2017(747)
Work TypeTBPFC&ACP SURF,PLG,BRG JNTS,TEXTURE
 
6.7902876796.850.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-04-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-04-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173003
Totals2876796.850.000.000.0

CountySMITH
HighwaySH 155
From2 MI S OF US 80 (UPSHUR C/L), S
ToIH 20
CSJ0520-01-021
Proj IDSTP 2017(087)
Work TypePLNG, ACP,OCST,PFC SURF,PVT MRKG
 
7.9785534730.861104415.5719.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-16-16
Work Began03-23-17
Work Completed
Time Computed00-00-00
Contract Working Days76
Addl Days Granted0
Working Days Charged5
Percent Time Used6
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0520-01-021
PANOLA SIGN & BARRICADE, INC. (0.21)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC (9.47)
STRIPE-A-ZONE, INC. (1.98)
Contract #09163224
Totals5534730.860.001104415.5719.9

CountyHENDERSON
HighwayFM 315
FromFM 314, S
ToCR 4325/4224 (END C-S)
CSJ0559-02-034
Proj IDSTP 1502(282)HES
Work TypeSUBGRADE WIDEN, LEVEL-UP, OCST
 
5.7063079333.983598691.1699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-24-15
Work Began10-19-15
Work Completed
Time Computed00-00-00
Contract Working Days175
Addl Days Granted3
Working Days Charged173
Percent Time Used97
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0559-02-034
COLD CREEK CONSTRUCTION, LTD (1.97)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.79)
SAMMY G. SMALLWOOD (1.20)
STRIPING TECHNOLOGY, L.P. (1.64)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (4.49)
STRIPING SYSTEMS, INC. (0.04)
NIXON ENGINEERING (0.00)
Contract #06153229
Totals3079333.980.003598691.1699.9

CountyCHEROKEE
HighwayFM 22
From1.5 MI W OF FM 768, (CR 1512), E
ToSH 110
CSJ0634-01-012
Proj IDSTP 2017(363)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
4.8311037127.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days110
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0634-01-012
DUSTIN ALLEN, INC. (14.70)
TOTAL HIGHWAY MAINTENANCE, LLC (0.64)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.96)
ISAACS CONSTRUCTION SERVICES, LLC. (2.00)
Contract #01173012
Totals1037127.000.000.000.0

CountyGREGG
HighwayFM 449
FromUS 259 N OF LONGVIEW, E
ToFM 2751
CSJ0640-07-005
Proj IDSTP 1502(284)HES
Work TypeSUBGR WDN,ACP LVL-UP,STRS,OCST,PVMK
 
8.0124436875.014051410.4991.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-13-15
Work Began10-12-15
Work Completed
Time Computed00-00-00
Contract Working Days284
Addl Days Granted9
Working Days Charged290
Percent Time Used98
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0640-07-005
BAHENA CONSTRUCTION CO.,INC. (9.52)
COWBELL TRAFFIC SERVICES, INC. (0.26)
PANOLA SIGN & BARRICADE, INC. (0.60)
SOUTHWEST ENVIRONMENT SERVICES LLC (6.94)
STRIPE-A-ZONE, INC. (2.47)
B & E CONSTRUCTION INC. (3.23)
DUSTIN ALLEN, INC. (0.47)
Contract #06153032
Totals4436875.010.004051410.4991.3

CountyVAN ZANDT
HighwayFM 314
From2.3 MI N OF SH 64(CR 4907),S
ToFM 279 (E) IN EDOM
CSJ0745-01-015
Proj IDSTP 2014(634)
Work TypeSCAR,RESHAPE,FLX BS,SURF TRT,STRS
 
11.71211961746.066970081.2258.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-08-14
Work Began11-07-14
Work Completed
Time Computed00-00-00
Contract Working Days486
Addl Days Granted0
Working Days Charged378
Percent Time Used77
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0745-01-015
STRIPING TECHNOLOGY, L.P. (1.40)
DUSTIN ALLEN, INC. (0.74)
KENSAR LLC DBA S & S TRUCKING (4.64)
Contract #05143203
Totals11961746.060.006970081.2258.2

CountySMITH
HighwayVA
FromVARIOUS LOCATIONS IN
ToTHE TYLER DISTRICT
CSJ0910-00-100
Proj IDSTP 2017(230)
Work TypeTHERMOPLASTIC MARKINGS
 
1.000209929.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-22-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days26
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-00-100
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173027
Totals209929.700.000.000.0

CountySMITH
HighwayVA
FromVAR LOCS IN GREGG & RUSK COUNTIES
ToCITIES OF LONGVIEW,KILGORE,HENDERSN
CSJ0910-00-105
Proj IDSTP 2016(366)
Work TypeCURB RAMPS
 
0.1001419691.25325231.0022.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-10-17
Work Began03-15-17
Work Completed
Time Computed00-00-00
Contract Working Days145
Addl Days Granted0
Working Days Charged28
Percent Time Used19
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-00-105
STRIPING TECHNOLOGY, L.P. (0.07)
Contract #12163035
Totals1419691.250.00325231.0022.9

CountyGREGG
HighwayVA
FromVARIOUS LOCATIONS IN KILGORE,
ToGLADEWATER & LONGVIEW
CSJ0910-07-068
Proj IDSTP 1602(646)
Work TypePLANT TREES & SHRUBS, IRRIGATION
 
1.000254158.62106704.6041.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-16
Work Began03-20-17
Work Completed
Time Computed00-00-00
Contract Working Days92
Addl Days Granted0
Working Days Charged9
Percent Time Used9
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-07-068
TX DOWN UNDER CONSTRUCTION, LLC (2.56)
PANOLA SIGN & BARRICADE, INC. (4.09)
Contract #08163052
Totals254158.620.00106704.6041.9

CountyANDERSON
HighwayCR
FromCR 471 AT BOX CREEK
ToSTR # AA04-71-101
CSJ0910-08-040
Proj IDBR 2000(274)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.161817412.15837129.8499.9
Work Order04-27-15
Work Began06-18-15
Work Completed
Time Computed05-13-15
Contract Working Days177
Addl Days Granted0
Working Days Charged177
Percent Time Used100
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0910-08-040
AMERICAN REMEDIATION OPTIONS, INC. (5.72)
PANOLA SIGN & BARRICADE, INC. (1.06)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.81)
MESA ROD BUSTERS, INC. (0.37)
Contract #03153203
Totals817412.150.00837129.8499.9

CountyANDERSON
HighwayCR
FromCR 2418 AT OTTER CREEK
ToSTR# AA03-55-001
CSJ0910-08-067
Proj IDBR 2015(257)
Work TypeRPLC BRG&APPR,GR,ACPBS&SURF,MBGF
 
0.139753675.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days108
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0910-08-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173016
Totals753675.600.000.000.0

CountyANDERSON
HighwayCR
FromCR 2133 AT MACK CREEK
ToSTR#AA2133101, BTWN US 79 & FM 1990
CSJ0910-08-069
Proj IDBR 2015(260)
Work TypeREPLACE BRIDGE AND APPROACHES
 
1.000499832.22302579.9860.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-27-16
Work Began09-19-16
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged37
Percent Time Used61
Contractor(s)
FRITCHER CONSTRUCTION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 0910-08-069
FLEX SUPPLY, LLC (0.70)
JM YANEZ CONSTRUCTION, INC. (31.12)
SOUTHWEST ENVIRONMENT SERVICES LLC (3.35)
SHINN & GREGORY, INC. (11.36)
MORRIS COUNTY CONTRACTORS, L.L.C. (2.43)
Contract #04163005
Totals499832.220.00302579.9860.5

CountyVAN ZANDT
HighwayCR
FromCR 3105 AT CROOKED CREEK
ToSTR # AA01-19-002
CSJ0910-12-034
Proj IDBR 1502(662)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.4001432779.001058058.7173.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-10-16
Work Began06-13-16
Work Completed
Time Computed00-00-00
Contract Working Days272
Addl Days Granted0
Working Days Charged161
Percent Time Used59
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-12-034
PANOLA SIGN & BARRICADE, INC. (1.08)
SOUTHWEST ENVIRONMENT SERVICES LLC (3.28)
PEACHTREE CONSTRUCTION, LTD. (9.24)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.50)
ODUM SERVICES, L.P. (3.37)
Contract #03163024
Totals1432779.000.001058058.7173.8

CountySMITH
HighwayPW
FromVARIOUS LOCATIONS
ToWITHIN TYLER STATE PARK
CSJ0910-16-121
Proj IDC 910-16-121
Work TypeOVERLAY
 
1.0001269696.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days123
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-121
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173028
Totals1269696.000.000.000.0

CountySMITH
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE CITY OF TYLER
CSJ0910-16-130
Proj IDSTP 1602(439)
Work TypeGR, SIGNALS, ACP BS&SURF, PVT MRKG
 
0.5752355455.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days196
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-130
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173205
Totals2355455.500.000.000.0

page 1 | page 2 | page 3