Monthly State Let Construction Report For Tyler District As Of Jun 10, 2015 Page 3 Of 3

Last Update: Wednesday, June 10, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySMITH
Highway VA
From VARIOUS LOCATIONS IN HENDERSON
To WOOD, VAN ZANDT & ANDERSON COUNTIES
CSJ 0910-00-095
Proj ID STP 2013(682)
Work Type ADA CURB RAMPS
 
1.000 1347171.00 0.00 1348475.23 99.9
Work Order 06-26-13
Work Began 08-12-13
Work Completed  
Time Computed 07-12-13
Contract Working Days 218
Addl Days Granted 0
Working Days Charged 236
Percent Time Used 108
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-00-095
PANOLA SIGN & BARRICADE, INC.(1.44%)
PAVEMENT MARKINGS INC. (2.52%)
Contract # 05133034
Totals 1347171.00 0.00 1348475.23 99.9

CountySMITH
Highway VA
From ON IH20,E OF FM757 WB,W OF FM849 EB
To IN SMITH,E OF FM1255 WB IN VANZANDT
CSJ 0910-00-098
Proj ID ITS 2004(807)
Work Type DMS INSTALLATION (FY04 ITS PGM)
 
41.884 177095.57 0.00 142375.32 92.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-14-13
Work Began 06-26-14
Work Completed  
Time Computed 11-30-13
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 111
Percent Time Used 148
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-00-098
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(1.62%)
ODUM SERVICES, L.P.(6.59%)
CARTHAGE DRILLING, INC.(1.41%)
B & B UNDERGROUND, LLC (2.42%)
TX DOWN UNDER CONSTRUCTION LLC (0.00%)
Contract # 10133219
Totals 177095.57 0.00 142375.32 92.3

CountyGREGG
Highway CR
From SPINKS-CHAPMAN RD AT RABBIT CRK
To STR# AA00-07-002
CSJ 0910-07-059
Proj ID BR 1302(076)
Work Type RPLC BRG & APPRS, GRD, ACP BS & SURF, MBGF
 
0.082 487743.10 0.00 476300.83 97.6
Work Order 04-15-14
Work Began 06-30-14
Work Completed  
Time Computed 05-01-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 74
Percent Time Used 98
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-07-059
LONE STAR BARRIER SERVICES, LLC(2.37%)
ALTUS TRAFFIC MANAGEMENT LLC (0.48%)
EROSION CONTROL MANAGEMENT SERVICES(1.63%)
FRAIRE"S REBAR, INC(1.32%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.18%)
EAST TEXAS BRIDGE, INC.(8.31%)
Contract # 03143214
Totals 487743.10 0.00 476300.83 97.6

CountyANDERSON
Highway CR
From CR 471 AT BOX CREEK
To STR # AA04-71-101
CSJ 0910-08-040
Proj ID BR 2000(274)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.161 817412.15 0.00 0.00 0.0
Work Order 04-27-15
Work Began 00-00-00
Work Completed  
Time Computed 05-13-15
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0910-08-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153203
Totals 817412.15 0.00 0.00 0.0

CountyANDERSON
Highway CR
From CR 432 AT LAKE CREEK
To STR # AA03-44-001
CSJ 0910-08-055
Proj ID BR 2007(723)
Work Type RPLC BRG & APPRS, GRD, ACP BS & SURF, MBGF
 
0.150 610062.05 0.00 607248.54 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 05-29-14
Work Completed 03-10-15
Time Computed 05-01-14
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 100
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0910-08-055
AMERICAN REMEDIATION OPTIONS, INC. (4.88%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.98%)
PANOLA SIGN & BARRICADE, INC.(1.02%)
MESA ROD BUSTERS, INC. (0.40%)
Contract # 03143203
Totals 610062.05 0.00 607248.54 100.0

CountyANDERSON
Highway CR
From CR 453 AT BEAVER CREEK
To STR# AA0349-001
CSJ 0910-08-062
Proj ID BR 1302(075)
Work Type RPLC BRG & APPR, ACP BS & SURF, GR, MBGF
 
0.080 256312.87 700.00 161119.51 62.8
Work Order 02-11-15
Work Began 03-24-15
Work Completed  
Time Computed 02-27-15
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 30
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-08-062
LONE STAR BARRIER SERVICES, LLC(4.08%)
PANOLA SIGN & BARRICADE, INC.(1.16%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 15.15%)
MESA ROD BUSTERS, INC. (0.39%)
Contract # 01153223
Totals 256312.87 700.00 161119.51 62.8

CountyVAN ZANDT
Highway CR
From CR 2702 AT LACY FORK TRIBUTARY
To STR# AA02-48-001
CSJ 0910-12-061
Proj ID STP 1302(031)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.271 1021653.72 9579.92 952515.52 93.2
Work Order 04-25-14
Work Began 05-20-14
Work Completed  
Time Computed 05-11-14
Contract Working Days 216
Addl Days Granted 0
Working Days Charged 190
Percent Time Used 87
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0910-12-061
PANOLA SIGN & BARRICADE, INC.(1.06%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.99%)
MAC TRANSPORTATION, LTD, L.L.P.(3.52%)
SAMMY G. SMALLWOOD (3.87%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.37%)
SOTO"S STEEL (0.19%)
Contract # 03143227
Totals 1021653.72 9579.92 952515.52 93.2

CountyVAN ZANDT
Highway PW
From WITHIN PURTIS CREEK STATE PARK
To OFF OF FM 316
CSJ 0910-12-128
Proj ID C 910-12-128
Work Type ADD ROAD BASE & CLEAN DITCHES
 
0.573 90549.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONSTRUCTION COMPANIES GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-12-128
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153051
Totals 90549.00 0.00 0.00 0.0

CountySMITH
Highway CR
From CR 448 AT VILLAGE CREEK
To STR# AA05-11-002
CSJ 0910-16-115
Proj ID BR 2012(167)
Work Type RPLC BRG & APPRCH, GR, ACP BS & SURF, MBGF
 
0.122 485890.80 700.00 424224.15 87.3
Work Order 09-11-14
Work Began 11-13-14
Work Completed  
Time Computed 09-27-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 47
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-115
FORTSON CONTRACTING, INC.(4.30%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.86%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.88%)
Contract # 07143237
Totals 485890.80 700.00 424224.15 87.3

CountySMITH
Highway CR
From CR 481 AT DUCK CREEK
To STR# AA06-54-001
CSJ 0910-16-117
Proj ID BR 2012(174)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.127 555839.20 47147.50 47147.50 8.4
Work Order 04-20-15
Work Began 05-18-15
Work Completed  
Time Computed 05-06-15
Contract Working Days 113
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 4
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-117
TOTAL HIGHWAY MAINTENANCE, LLC (0.71%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.53%)
FORTSON CONTRACTING, INC.(3.97%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.72%)
Contract # 03153225
Totals 555839.20 47147.50 47147.50 8.4

CountySMITH
Highway VA
From VARIOUS LOCATIONS IN
To THE CITY OF TYLER
CSJ 0910-16-128
Proj ID STP 1402(013)
Work Type TREE PLANTING
 
1.000 130690.00 1485.00 131690.00 100.0
Work Order 08-20-14
Work Began 09-15-14
Work Completed 03-13-15
Time Computed 09-05-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 46
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-128
SOUTH TEXAS ILLUMINATION, LLC(5.78%)
FLEX SUPPLY, LLC (9.64%)
Contract # 07143049
Totals 130690.00 1485.00 131690.00 100.0

CountyHENDERSON
Highway CS
From CARDINAL DR AT LITTLE DUNCAN CRK
To STR# S000-20-001, IN MURCHISON
CSJ 0910-34-028
Proj ID BR 2014(042)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 341919.44 1760.00 1760.00 0.5
Work Order 04-20-15
Work Began 00-00-00
Work Completed  
Time Computed 05-06-15
Contract Working Days 56
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HARTBEAT CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0910-34-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153018
Totals 341919.44 1760.00 1760.00 0.5

CountySMITH
Highway FM 850
From 0.445 MI SE OF FM 2607, SE
To RUSK C/L IN OVERTON
CSJ 1163-01-021
Proj ID STP 2014(735)
Work Type CRACK SEAL, PLNG, OCST, HMAC LVL - UP
 
7.533 2168937.98 26250.00 277697.93 12.8
Work Order 07-18-14
Work Began 11-03-14
Work Completed  
Time Computed 08-03-14
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 8
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1163-01-021
PANOLA SIGN & BARRICADE, INC.(0.55%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.68%)
STRIPING TECHNOLOGY, L.P.(2.75%)
DREWERY & WHEATON, LLC (0.59%)
ACU CONSTRUCTION LLC (0.37%)
RICE ENVIRONMENTAL SERVICES(0.59%)
FREDONIA CONSTRUCTION SERVICES (0.42%)
Contract # 06143234
Totals 2168937.98 26250.00 277697.93 12.8

CountyRUSK
Highway FM 1798
From FM 225, E
To US 259
CSJ 1669-03-008
Proj ID STP 1502(287)
Work Type BASE REPAIR & OVERLAY
 
7.082 1826819.49 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 1669-03-008
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153252
Totals 1826819.49 0.00 0.00 0.0

CountyGREGG
Highway LP 281
From SH 31 IN LONGVIEW, S
To 0.42 MI S OF FM 2087
CSJ 1763-03-029
Proj ID STP 1102(227)RGS
Work Type GR, STRS, HMAC BS, CONC PVT, C & G, SIGNLS
 
1.680 13235356.95 172140.91 8001870.33 60.4
Work Order 09-27-11
Work Began 03-18-13
Work Completed  
Time Computed 03-01-12
Contract Working Days 575
Addl Days Granted 0
Working Days Charged 408
Percent Time Used 70
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1763-03-029
PANOLA SIGN & BARRICADE, INC.(0.27%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.97%)
MAC TRANSPORTATION, LTD, L.L.P.(3.61%)
SCOTT DERR PAINTING CO, LLC(0.04%)
STRIPING TECHNOLOGY, L.P.(5.45%)
DUSTIN ALLEN, INC. (0.16%)
TEX OP CONSTRUCTION, LP(0.53%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.76%)
DIAMOND H SERVICES, INC. (0.03%)
DUKE IRRIGATION(0.00%)
MESA ROD BUSTERS, INC. (0.15%)
Contract # 08113205
Totals 13235356.95 172140.91 8001870.33 60.4

CountySMITH
Highway SL 323
From 0.6 MI E OF US 271(AMER LEG RD), S
To .24 MI N OF FM2767(COMMERCE)IN TYLR
CSJ 1790-02-038
Proj ID NH 2015(623)
Work Type PLNG, ACP LVL - UP & SURF, MBGF, STRS, PVMK
 
2.180 3363191.68 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-05-15
Work Began 00-00-00
Work Completed  
Time Computed 07-06-15
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1790-02-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153035
Totals 3363191.68 0.00 0.00 0.0

CountySMITH
Highway LP 323
From US 69 (N) IN TYLER, E
To LP323,.5 MI E OF US271(AMER LEG RD)
CSJ 2075-01-053
Proj ID NH 2013(466)
Work Type OCST, 2" OVERLAY
 
3.985 1965643.25 0.00 2118034.08 100.0
CountySMITH
Highway LP 323
From US 69 (N) IN TYLER, E
To LP323,.5 MI E OF US271(AMER LEG RD)
CSJ 2075-01-056
Proj ID NH 2013(466)
Work Type OCST, 2" OVERLAY
 
3.985 1828463.02 0.00 1854205.71 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-12-13
Work Began 07-16-13
Work Completed 01-28-15
Time Computed 06-28-13
Contract Working Days 50
Addl Days Granted 28
Working Days Charged 101
Percent Time Used 129
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2075-01-053
TOTAL HIGHWAY MAINTENANCE, LLC (0.32%)
ODUM SERVICES, L.P.(1.44%)
DUSTROL, INC.(1.30%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.12%)
STRIPING TECHNOLOGY, L.P.(2.01%)
J & I TRUCKING CO(0.65%)
Contract # 03133207
Totals 3794106.27 0.00 3972239.79 100.0

CountySMITH
Highway LP 323
From SH 31 (W) IN TYLER, N 0.295 MI
To ELM ST
CSJ 2075-01-055
Proj ID C 2075-1-55
Work Type GR, ACP BS & SURF, PVT MRKG
 
0.295 1520796.14 0.00 170094.27 11.1
CountySMITH
Highway LP 323
From 0.6 MI S OF SH 31 (SHAW ST), N
To SH 31 (W) IN TYLER
CSJ 2075-02-045
Proj ID C 2075-2-45
Work Type REPLACE EXISTING RAILROAD UNDERPASS
 
0.637 10467992.74 194594.07 4106727.00 39.2
Work Order 05-09-14
Work Began 05-19-14
Work Completed  
Time Computed 02-03-14
Contract Working Days 459
Addl Days Granted 0
Working Days Charged 294
Percent Time Used 64
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2075-02-045
STRIPING TECHNOLOGY, L.P.(3.86%)
PANOLA SIGN & BARRICADE, INC.(0.42%)
FORTSON CONTRACTING, INC.(0.46%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.01%)
TEX OP CONSTRUCTION, LP(0.27%)
ATS DRILLING, INC. (4.48%)
MAC TRANSPORTATION, LTD, L.L.P.(2.87%)
MCL CONTRACTING, LLC (0.30%)
OLDEN, INC.(5.30%)
BARBIN FENCE, INC. (0.12%)
TRAC-WORK, INC.(2.83%)
Contract # 11133219
Totals 11988788.88 194594.07 4276821.27 35.6

CountyGREGG
Highway FM 2275
From MCCANN RD, 0.1 MI N OF GRAYSTONE, E
To SS 502,0.6 MI S OF FM 1844 IN LNGVW
CSJ 2158-01-013
Proj ID C 2158-1-13
Work Type GR, STRS, ACP BS & SURF, CONC PVT, OCST
 
2.400 12884788.32 0.00 6361617.33 49.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-14
Work Began 04-01-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 144
Percent Time Used 40
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2158-01-013
SOUTHWEST ENVIRONMENT SERVICES LLC (1.25%)
REYNOLDS & KAY, LTD. (1.99%)
LONE STAR BARRIER SERVICES, LLC(0.19%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.91%)
STRIPING TECHNOLOGY, L.P.(4.06%)
SOTO"S STEEL (0.04%)
STRINGFELLOW LOGGING (0.00%)
Contract # 01143203
Totals 12884788.32 0.00 6361617.33 49.3

CountyWOOD
Highway FM 2869
From FM 852, S OF WINNSBORO, S
To N OF FM 2088
CSJ 2958-01-013
Proj ID SSW 2958-01-013
Work Type SBGR WDN, ACP BS, HMAC SURF, OCST, STRS
 
8.266 4585714.78 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2958-01-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153262
Totals 4585714.78 0.00 0.00 0.0