Monthly State Let Construction Report For Tyler District As Of Aug 16, 2016 Page 3 Of 3

Last Update: Tuesday, August 16, 2016
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGREGG
Highway LP 281
From SH 31 IN LONGVIEW, S
To 0.42 MI S OF FM 2087
CSJ 1763-03-029
Proj ID STP 1102(227)RGS
Work Type GR, STRS, HMAC BS, CONC PVT, C & G, SIGNLS
 
1.680 13235356.95 369446.22 11516177.65 87.0
Work Order 09-27-11
Work Began 03-18-13
Work Completed  
Time Computed 03-01-12
Contract Working Days 575
Addl Days Granted 101
Working Days Charged 672
Percent Time Used 99
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1763-03-029
PANOLA SIGN & BARRICADE, INC.(0.27%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.97%)
MAC TRANSPORTATION, LTD, L.L.P.(3.61%)
SCOTT DERR PAINTING CO, LLC(0.04%)
STRIPING TECHNOLOGY, L.P.(5.45%)
DUSTIN ALLEN, INC. (0.16%)
TEX OP CONSTRUCTION, LP(0.53%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.76%)
DIAMOND H SERVICES, INC. (0.03%)
DUKE IRRIGATION(0.00%)
MESA ROD BUSTERS, INC. (0.15%)
BARBIN FENCE, INC. (0.06%)
INDUS CONSTRUCTION, L.P. (0.00%)
Contract # 08113205
Totals 13235356.95 369446.22 11516177.65 87.0

CountyGREGG
Highway FM 2087
From AT SABINE RIVER, STR# 193101002
To 0.5 MI N OF IH 20 FRONTAGE RD
CSJ 1931-01-017
Proj ID BR 1602(440)
Work Type RPLC BR & APPR, GR, ACP BS & SURF, MBGF
 
0.284 3698176.83 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 174
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1931-01-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163041
Totals 3698176.83 0.00 0.00 0.0

CountySMITH
Highway LP 323
From SH 31 (W) IN TYLER, N 0.295 MI
To ELM ST
CSJ 2075-01-055
Proj ID C 2075-1-55
Work Type GR, ACP BS & SURF, PVT MRKG
 
0.295 1520796.14 44198.85 750463.96 49.3
CountySMITH
Highway LP 323
From 0.6 MI S OF SH 31 (SHAW ST), N
To SH 31 (W) IN TYLER
CSJ 2075-02-045
Proj ID C 2075-2-45
Work Type REPLACE EXISTING RAILROAD UNDERPASS
 
0.637 10467992.74 355414.87 8484107.28 81.0
Work Order 05-09-14
Work Began 05-19-14
Work Completed  
Time Computed 02-03-14
Contract Working Days 459
Addl Days Granted 5
Working Days Charged 467
Percent Time Used 100
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2075-02-045
STRIPING TECHNOLOGY, L.P.(3.86%)
PANOLA SIGN & BARRICADE, INC.(0.42%)
FORTSON CONTRACTING, INC.(0.46%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.01%)
TEX OP CONSTRUCTION, LP(0.27%)
ATS DRILLING, INC. (4.48%)
MAC TRANSPORTATION, LTD, L.L.P.(2.87%)
MCL CONTRACTING, LLC (0.30%)
OLDEN, INC.(5.30%)
BARBIN FENCE, INC. (0.12%)
TRAC-WORK, INC.(2.83%)
ROBINSON CONSTRUCTION(0.10%)
Contract # 11133219
Totals 11988788.88 399613.72 9234571.24 77.0

CountyGREGG
Highway FM 2275
From SH 300 IN N LONGVIEW, E
To MCCANN RD, 0.1 MI N OF GRAY STONE
CSJ 2158-01-011
Proj ID STP 1502(563)
Work Type GR, BRGS, STRS, ACP BS, C & G, OCST, HMAC
 
1.806 12423396.89 0.00 2391162.61 19.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-01-15
Work Began 03-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 215
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 19
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2158-01-011
S & S BRIDGE PAINTING, INC.(0.16%)
MORRIS COUNTY CONTRACTORS, L.L.C.(0.87%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.95%)
REYNOLDS & KAY, LTD. (1.87%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.80%)
STRIPING TECHNOLOGY, L.P.(0.67%)
MCL CONTRACTING, LLC (0.08%)
TRENDSETTER CONSTRUCTION, INC. (0.47%)
STRIPING SYSTEMS, INC. (0.00%)
Contract # 08153014
Totals 12423396.89 0.00 2391162.61 19.2

CountyGREGG
Highway FM 2275
From MCCANN RD, 0.1 MI N OF GRAYSTONE, E
To SS 502,0.6 MI S OF FM 1844 IN LNGVW
CSJ 2158-01-013
Proj ID C 2158-1-13
Work Type GR, STRS, ACP BS & SURF, CONC PVT, OCST
 
2.400 12884788.32 0.00 12641635.72 98.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-14
Work Began 04-01-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 356
Percent Time Used 98
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2158-01-013
SOUTHWEST ENVIRONMENT SERVICES LLC (1.25%)
REYNOLDS & KAY, LTD. (1.99%)
LONE STAR BARRIER SERVICES, LLC(0.26%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.91%)
STRIPING TECHNOLOGY, L.P.(4.06%)
SOTO"S STEEL (0.04%)
STRINGFELLOW LOGGING (0.00%)
CARTHAGE DRILLING, INC.(0.09%)
Contract # 01143203
Totals 12884788.32 0.00 12641635.72 98.1

CountySMITH
Highway SS 248
From 1.75 MI W OF FM 848(OLD OMEN RD), E
To SH 64 SE OF TYLER
CSJ 2558-01-015
Proj ID STP 2013(211)
Work Type RECONSTR GR, STRS, BS, C & G, SURF & PAV
 
2.177 8660946.19 0.00 1561858.65 18.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-09-16
Work Began 06-06-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 315
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 12
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2558-01-015
FLEX SUPPLY, LLC (0.24%)
SCOTT DERR PAINTING CO, LLC(0.06%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.90%)
ROBINSON CONSTRUCTION(4.06%)
APAC-TEXAS, INC. ( 15.95%)
SLATON BROTHERS, INC.(6.48%)
TEXOP CONSTRUCTION (0.25%)
STRIPING TECHNOLOGY, L.P.(0.78%)
JE CASEY, LLC(1.28%)
F A BROWN"S CONSTRUCTION, LLC(2.28%)
SOUTH TEXAS ILLUMINATION, LLC(1.78%)
KENSAR LLC DBA S & S TRUCKING(5.28%)
STRIPING SYSTEMS, INC. (0.01%)
Contract # 12153229
Totals 8660946.19 0.00 1561858.65 18.0