Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyRUSK
Highway FM 1798
From FM 225, E
To US 259
CSJ 1669-03-008
Proj ID STP 1502(287)
Work Type BASE REPAIR & OVERLAY
 
7.082 1826819.49 274338.10 481834.80 26.3
Work Order 07-16-15
Work Began 04-25-16
Work Completed  
Time Computed 08-16-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 68
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 1669-03-008
B & E CONSTRUCTION INC.( 13.35%)
DUSTIN ALLEN, INC. (1.27%)
PANOLA SIGN & BARRICADE, INC.(0.60%)
SOUTHWEST ENVIRONMENT SERVICES LLC ( 14.44%)
STRIPING TECHNOLOGY, L.P.(2.23%)
STRIPING SYSTEMS, INC. (0.07%)
Contract # 06153252
Totals 1826819.49 274338.10 481834.80 26.3

CountyGREGG
Highway LP 281
From SH 31 IN LONGVIEW, S
To 0.42 MI S OF FM 2087
CSJ 1763-03-029
Proj ID STP 1102(227)RGS
Work Type GR, STRS, HMAC BS, CONC PVT, C & G, SIGNLS
 
1.680 13235356.95 130990.66 11146731.43 84.2
Work Order 09-27-11
Work Began 03-18-13
Work Completed  
Time Computed 03-01-12
Contract Working Days 575
Addl Days Granted 101
Working Days Charged 651
Percent Time Used 96
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1763-03-029
PANOLA SIGN & BARRICADE, INC.(0.27%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.97%)
MAC TRANSPORTATION, LTD, L.L.P.(3.61%)
SCOTT DERR PAINTING CO, LLC(0.04%)
STRIPING TECHNOLOGY, L.P.(5.45%)
DUSTIN ALLEN, INC. (0.16%)
TEX OP CONSTRUCTION, LP(0.53%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.76%)
DIAMOND H SERVICES, INC. (0.03%)
DUKE IRRIGATION(0.00%)
MESA ROD BUSTERS, INC. (0.15%)
BARBIN FENCE, INC. (0.06%)
INDUS CONSTRUCTION, L.P. (0.00%)
Contract # 08113205
Totals 13235356.95 130990.66 11146731.43 84.2

CountySMITH
Highway LP 323
From SH 31 (W) IN TYLER, N 0.295 MI
To ELM ST
CSJ 2075-01-055
Proj ID C 2075-1-55
Work Type GR, ACP BS & SURF, PVT MRKG
 
0.295 1520796.14 88348.52 706265.11 46.4
CountySMITH
Highway LP 323
From 0.6 MI S OF SH 31 (SHAW ST), N
To SH 31 (W) IN TYLER
CSJ 2075-02-045
Proj ID C 2075-2-45
Work Type REPLACE EXISTING RAILROAD UNDERPASS
 
0.637 10467992.74 246944.97 8128692.41 77.6
Work Order 05-09-14
Work Began 05-19-14
Work Completed  
Time Computed 02-03-14
Contract Working Days 459
Addl Days Granted 5
Working Days Charged 467
Percent Time Used 100
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2075-02-045
STRIPING TECHNOLOGY, L.P.(3.86%)
PANOLA SIGN & BARRICADE, INC.(0.42%)
FORTSON CONTRACTING, INC.(0.46%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.01%)
TEX OP CONSTRUCTION, LP(0.27%)
ATS DRILLING, INC. (4.48%)
MAC TRANSPORTATION, LTD, L.L.P.(2.87%)
MCL CONTRACTING, LLC (0.30%)
OLDEN, INC.(5.30%)
BARBIN FENCE, INC. (0.12%)
TRAC-WORK, INC.(2.83%)
ROBINSON CONSTRUCTION(0.10%)
Contract # 11133219
Totals 11988788.88 335293.49 8834957.52 73.7

CountyGREGG
Highway FM 2275
From SH 300 IN N LONGVIEW, E
To MCCANN RD, 0.1 MI N OF GRAY STONE
CSJ 2158-01-011
Proj ID STP 1502(563)
Work Type GR, BRGS, STRS, ACP BS, C & G, OCST, HMAC
 
1.806 12423396.89 0.00 1882333.55 15.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-01-15
Work Began 03-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 215
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 11
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2158-01-011
S & S BRIDGE PAINTING, INC.(0.16%)
MORRIS COUNTY CONTRACTORS, L.L.C.(0.87%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.95%)
REYNOLDS & KAY, LTD. (1.87%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.80%)
STRIPING TECHNOLOGY, L.P.(0.67%)
MCL CONTRACTING, LLC (0.08%)
TRENDSETTER CONSTRUCTION, INC. (0.47%)
STRIPING SYSTEMS, INC. (0.00%)
Contract # 08153014
Totals 12423396.89 0.00 1882333.55 15.1

CountyGREGG
Highway FM 2275
From MCCANN RD, 0.1 MI N OF GRAYSTONE, E
To SS 502,0.6 MI S OF FM 1844 IN LNGVW
CSJ 2158-01-013
Proj ID C 2158-1-13
Work Type GR, STRS, ACP BS & SURF, CONC PVT, OCST
 
2.400 12884788.32 0.00 11225802.59 87.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-14
Work Began 04-01-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 337
Percent Time Used 93
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2158-01-013
SOUTHWEST ENVIRONMENT SERVICES LLC (1.25%)
REYNOLDS & KAY, LTD. (1.99%)
LONE STAR BARRIER SERVICES, LLC(0.26%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.91%)
STRIPING TECHNOLOGY, L.P.(4.06%)
SOTO"S STEEL (0.04%)
STRINGFELLOW LOGGING (0.00%)
Contract # 01143203
Totals 12884788.32 0.00 11225802.59 87.1

CountySMITH
Highway SS 248
From 1.75 MI W OF FM 848(OLD OMEN RD), E
To SH 64 SE OF TYLER
CSJ 2558-01-015
Proj ID STP 2013(211)
Work Type RECONSTR GR, STRS, BS, C & G, SURF & PAV
 
2.177 8660946.19 0.00 865729.39 9.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-09-16
Work Began 06-06-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 315
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 6
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2558-01-015
FLEX SUPPLY, LLC (0.24%)
SCOTT DERR PAINTING CO, LLC(0.06%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.90%)
ROBINSON CONSTRUCTION(4.06%)
APAC-TEXAS, INC. ( 15.95%)
SLATON BROTHERS, INC.(6.48%)
TEXOP CONSTRUCTION (0.25%)
STRIPING TECHNOLOGY, L.P.(0.78%)
JE CASEY, LLC(1.28%)
F A BROWN"S CONSTRUCTION, LLC(2.28%)
SOUTH TEXAS ILLUMINATION, LLC(1.78%)
KENSAR LLC DBA S & S TRUCKING(5.28%)
STRIPING SYSTEMS, INC. (0.01%)
Contract # 12153229
Totals 8660946.19 0.00 865729.39 9.9