Monthly State Let Construction Report For Tyler District As Of Jan 11, 2017 Page 3 Of 3

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyRUSK
HighwayFM 1798
FromFM 225, E
ToUS 259
CSJ1669-03-008
Proj IDSTP 1502(287)
Work TypeBASE REPAIR & OVERLAY
 
7.0821826819.491860336.9099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-16-15
Work Began04-25-16
Work Completed
Time Computed08-16-15
Contract Working Days45
Addl Days Granted0
Working Days Charged59
Percent Time Used131
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 1669-03-008
B & E CONSTRUCTION INC. (13.35)
DUSTIN ALLEN, INC. (1.27)
PANOLA SIGN & BARRICADE, INC. (0.60)
SOUTHWEST ENVIRONMENT SERVICES LLC (14.44)
STRIPING TECHNOLOGY, L.P. (2.23)
STRIPING SYSTEMS, INC. (0.07)
Contract #06153252
Totals1826819.490.001860336.9099.9

CountyGREGG
HighwayLP 281
FromSH 31 IN LONGVIEW, S
To0.42 MI S OF FM 2087
CSJ1763-03-029
Proj IDSTP 1102(227)RGS
Work TypeGR,STRS,HMAC BS,CONC PVT,C&G,SIGNLS
 
1.68013235356.9512844872.6897.0
Work Order09-27-11
Work Began03-18-13
Work Completed
Time Computed03-01-12
Contract Working Days575
Addl Days Granted231
Working Days Charged736
Percent Time Used91
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1763-03-029
PANOLA SIGN & BARRICADE, INC. (0.27)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.97)
MAC TRANSPORTATION, LTD, L.L.P. (3.61)
SCOTT DERR PAINTING CO, LLC (0.04)
STRIPING TECHNOLOGY, L.P. (5.45)
DUSTIN ALLEN, INC. (0.16)
TEX OP CONSTRUCTION, LP (0.53)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.76)
DIAMOND H SERVICES, INC. (0.03)
DUKE IRRIGATION (0.00)
MESA ROD BUSTERS, INC. (0.15)
BARBIN FENCE, INC. (0.06)
INDUS CONSTRUCTION, L.P. (0.00)
TNT MASONRY, INC. (1.16)
Contract #08113205
Totals13235356.95144960.9212844872.6897.0

CountyGREGG
HighwayFM 2087
FromAT SABINE RIVER, STR# 193101002
To0.5 MI N OF IH 20 FRONTAGE RD
CSJ1931-01-017
Proj IDBR 1602(440)
Work TypeRPLC BR&APPR,GR,ACP BS&SURF,MBGF
 
0.2843698176.831241231.7233.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-14-16
Work Began10-11-16
Work Completed
Time Computed00-00-00
Contract Working Days174
Addl Days Granted0
Working Days Charged44
Percent Time Used25
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1931-01-017
ISAACS CONSTRUCTION SERVICES, LLC. (2.87)
ODUM SERVICES, L.P. (1.45)
PANOLA SIGN & BARRICADE, INC. (0.89)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.56)
STRIPE-A-ZONE, INC. (0.33)
Contract #08163041
Totals3698176.830.001241231.7233.5

CountySMITH
HighwayLP 323
FromSH 31 (W) IN TYLER, N 0.295 MI
ToELM ST
CSJ2075-01-055
Proj IDC 2075-1-55
Work TypeGR, ACP BS & SURF, PVT MRKG
 
0.2951520796.141216356.1879.9
CountySMITH
HighwayLP 323
From0.6 MI S OF SH 31 (SHAW ST), N
ToSH 31 (W) IN TYLER
CSJ2075-02-045
Proj IDC 2075-2-45
Work TypeREPLACE EXISTING RAILROAD UNDERPASS
 
0.63710467992.749763684.5893.3
Work Order05-09-14
Work Began05-19-14
Work Completed
Time Computed02-03-14
Contract Working Days459
Addl Days Granted5
Working Days Charged467
Percent Time Used100
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2075-01-055
STRIPING TECHNOLOGY, L.P. (3.92)
PANOLA SIGN & BARRICADE, INC. (0.42)
FORTSON CONTRACTING, INC. (0.46)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.01)
TEX OP CONSTRUCTION, LP (0.27)
ATS DRILLING, INC. (4.48)
MAC TRANSPORTATION, LTD, L.L.P. (2.87)
MCL CONTRACTING, LLC (0.30)
OLDEN, INC. (5.30)
BARBIN FENCE, INC. (0.12)
TRAC-WORK, INC. (2.83)
ROBINSON CONSTRUCTION (0.10)
CARTHAGE DRILLING, INC. (0.06)
Contract #11133219
Totals11988788.8874792.1010980040.7691.6

CountyGREGG
HighwayFM 2275
FromSH 300 IN N LONGVIEW, E
ToMCCANN RD, 0.1 MI N OF GRAY STONE
CSJ2158-01-011
Proj IDSTP 1502(563)
Work TypeGR,BRGS,STRS,ACP BS,C&G,OCST,HMAC
 
1.80612423396.894515630.1436.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-15
Work Began03-01-16
Work Completed
Time Computed00-00-00
Contract Working Days215
Addl Days Granted0
Working Days Charged121
Percent Time Used56
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2158-01-011
S & S BRIDGE PAINTING, INC. (0.16)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.87)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.95)
REYNOLDS & KAY, LTD. (1.87)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.80)
STRIPING TECHNOLOGY, L.P. (0.67)
MCL CONTRACTING, LLC (0.08)
TRENDSETTER CONSTRUCTION, INC. (0.47)
STRIPING SYSTEMS, INC. (0.01)
Contract #08153014
Totals12423396.890.004515630.1436.3

CountyGREGG
HighwayFM 2275
FromMCCANN RD, 0.1 MI N OF GRAYSTONE, E
ToSS 502,0.6 MI S OF FM 1844 IN LNGVW
CSJ2158-01-013
Proj IDC 2158-1-13
Work TypeGR,STRS,ACP BS&SURF,CONC PVT,OCST
 
2.40012884788.3213038711.2999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-18-14
Work Began04-01-14
Work Completed
Time Computed00-00-00
Contract Working Days360
Addl Days Granted22
Working Days Charged379
Percent Time Used99
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2158-01-013
SOUTHWEST ENVIRONMENT SERVICES LLC (1.25)
REYNOLDS & KAY, LTD. (1.99)
LONE STAR BARRIER SERVICES, LLC (0.26)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.91)
STRIPING TECHNOLOGY, L.P. (4.06)
SOTO"S STEEL (0.04)
STRINGFELLOW LOGGING (0.00)
CARTHAGE DRILLING, INC. (0.09)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.27)
Contract #01143203
Totals12884788.320.0013038711.2999.9

CountySMITH
HighwaySS 248
From1.75 MI W OF FM 848(OLD OMEN RD), E
ToSH 64 SE OF TYLER
CSJ2558-01-015
Proj IDSTP 2013(211)
Work TypeRECONSTR GR,STRS,BS,C&G, SURF & PAV
 
2.1778660946.192816860.0132.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-09-16
Work Began06-06-16
Work Completed
Time Computed00-00-00
Contract Working Days315
Addl Days Granted0
Working Days Charged109
Percent Time Used34
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2558-01-015
FLEX SUPPLY, LLC (0.24)
SCOTT DERR PAINTING CO, LLC (0.06)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.89)
ROBINSON CONSTRUCTION (4.06)
APAC-TEXAS, INC. (15.95)
SLATON BROTHERS, INC. (6.48)
TEXOP CONSTRUCTION (0.25)
STRIPING TECHNOLOGY, L.P. (0.78)
JE CASEY, LLC (1.28)
F A BROWN"S CONSTRUCTION, LLC (2.28)
SOUTH TEXAS ILLUMINATION, LLC (1.78)
KENSAR LLC DBA S & S TRUCKING (5.28)
STRIPING SYSTEMS, INC. (0.01)
ISAACS CONSTRUCTION SERVICES, LLC. (1.01)
JOHNSON CONSTRUCTION, J.C. (1.09)
Contract #12153229
Totals8660946.190.002816860.0132.5

CountyGREGG
HighwaySL 281
FromUS 80 IN LONGVIEW, N
ToSHOFNER DR (0.35 MI N OF FM 1845)
CSJ2642-01-046
Proj IDNH 1602(441)
Work TypeGR, STRS, ACP BASE & SURF, PVT MRKG
 
0.5394546219.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-06-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days234
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2642-01-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10163226
Totals4546219.500.000.000.0