Monthly State Let Construction Report For San Antonio District As Of Jul 11, 2014 Page 4 Of 5

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyATASCOSA
Highway FM 476
From SP 242
To SH 97
CSJ 0853-02-030
Proj ID STP 2014(537)
Work Type TRAFFIC SIGNALS
 
1.156 740432.64 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-05-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0853-02-030
JCD CONSTRUCTION, LLC(5.57%)
FLASHER EQUIPMENT COMPANY(1.66%)
UNITED PAVEMENT & MARKINGS, LLC(4.37%)
Contract # 03143204
Totals 740432.64 0.00 0.00 0.0

CountyCOMAL
Highway FM 306
From 0.4 MILES EAST OF FM 3424
To JACOBS CREEK PARK ROAD
CSJ 0857-01-028
Proj ID STP 2013(105)
Work Type GRD, BASE, SURF, AND PAV MARKS
 
2.584 963415.67 5225.20 941268.28 97.7
CountyCOMAL
Highway FM 306
From 0.2 MI W OF CANYON DAM ACCESS ROAD
To 1.1 MI E OF PURGATORY ROAD
CSJ 1728-02-054
Proj ID STP 2013(105)
Work Type GRD, BASE, SURF, AND PAV MARKINGS
 
6.542 2545179.77 4974.14 2260509.78 88.8
Work Order 11-28-12
Work Began 12-14-12
Work Completed  
Time Computed 12-14-12
Contract Working Days 296
Addl Days Granted 0
Working Days Charged 217
Percent Time Used 73
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0857-01-028
E-Z BEL CONSTRUCTION, LLC(1.07%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.62%)
RELMCO, INC. (6.80%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(6.58%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.59%)
ROADWAY SPECIALTIES, INC.(2.67%)
FLASHER EQUIPMENT COMPANY(1.96%)
EGGEMEYER LAND CLEARING, LLC (1.96%)
Contract # 10123012
Totals 3508595.44 10199.34 3201778.06 91.2

CountyBEXAR
Highway VA
From DISTRICTWIDE GUIDESIGNS FY14
To .
CSJ 0915-00-155
Proj ID STP 2014(562)
Work Type DISTRICTWIDE GUIDESIGNS FY14
 
0.001 998524.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-20-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 208
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-155
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143205
Totals 998524.12 0.00 0.00 0.0

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2014
To .
CSJ 0915-00-156
Proj ID STP 2014(538)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 1299950.00 8902.45 8902.45 0.6
Work Order 05-01-14
Work Began 00-00-00
Work Completed  
Time Computed 07-30-14
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-156
JCD CONSTRUCTION, LLC(2.52%)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (1.23%)
UNITED PAVEMENT & MARKINGS, LLC(0.69%)
Contract # 03143206
Totals 1299950.00 8902.45 8902.45 0.6

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2012
To .
CSJ 0915-00-158
Proj ID STP 2012(311)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 1113075.30 352.80 1057064.65 94.9
Work Order 03-12-12
Work Began 05-29-12
Work Completed  
Time Computed 06-10-12
Contract Working Days 300
Addl Days Granted 295
Working Days Charged 359
Percent Time Used 60
Contractor(s)
SAECO ELECTRIC & UTILITY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-158
HEARN CO.(1.01%)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (3.41%)
JCD CONSTRUCTION, LLC(3.84%)
JA&M CONSTRUCTION, LLC (1.07%)
Contract # 02123222
Totals 1113075.30 352.80 1057064.65 94.9

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2013
To .
CSJ 0915-00-160
Proj ID STP 2013(404)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.010 1179951.00 19079.48 278582.91 23.6
Work Order 04-19-13
Work Began 10-29-13
Work Completed  
Time Computed 07-18-13
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 116
Percent Time Used 36
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-160
JND CONSTRUCTION CONSULTANTS, LLC( 13.54%)
VACA UNDERGROUND UTILITIES INC (3.44%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.69%)
BEAIRD DRILLING(0.16%)
YORK & YORK FOUNDATION DRILLING, INC.(3.55%)
JCH CONSTRUCTION, INC. (0.05%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.03%)
Contract # 02133216
Totals 1179951.00 19079.48 278582.91 23.6

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2012
To .
CSJ 0915-00-163
Proj ID STP 2012(312)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 942875.75 267.20 984638.97 99.9
Work Order 03-12-12
Work Began 05-22-12
Work Completed  
Time Computed 06-10-12
Contract Working Days 300
Addl Days Granted 91
Working Days Charged 231
Percent Time Used 59
Contractor(s)
SAECO ELECTRIC & UTILITY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-163
HEARN CO.(6.17%)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (4.03%)
JA&M CONSTRUCTION, LLC (1.33%)
JCD CONSTRUCTION, LLC(2.82%)
Contract # 02123027
Totals 942875.75 267.20 984638.97 99.9

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2013
To .
CSJ 0915-00-164
Proj ID STP 2013(405)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.010 1218087.00 38130.29 362078.31 29.8
Work Order 04-19-13
Work Began 10-29-13
Work Completed  
Time Computed 07-18-13
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 104
Percent Time Used 32
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-164
JND CONSTRUCTION CONSULTANTS, LLC( 13.12%)
VACA UNDERGROUND UTILITIES INC (3.34%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.33%)
BEAIRD DRILLING(0.32%)
YORK & YORK FOUNDATION DRILLING, INC.(3.44%)
JCH CONSTRUCTION, INC. (0.17%)
Contract # 02133013
Totals 1218087.00 38130.29 362078.31 29.8

CountyBEXAR
Highway CS
From IN SAN ANTONIO ON SOMERSET RD
To AT LEON CREEK
CSJ 0915-12-218
Proj ID BR 96(351)
Work Type REHABILITATE BRIDGE & APPROACHES
 
0.001 425301.50 0.00 35168.50 8.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 06-11-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 21
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-218
ABC EROSION CONTROL, INC.( 14.56%)
AMERICAN SIGNAL EQUIPMENT CO.(2.16%)
ALTUS TRAFFIC MANAGEMENT LLC (0.69%)
Contract # 03143007
Totals 425301.50 0.00 35168.50 8.2

CountyBEXAR
Highway MH
From WURZBACH PARKWAY ON NEW LOCATION
To FROM FM 2696 TO WEST AVE
CSJ 0915-12-224
Proj ID C 915-12-224
Work Type GRAD, STRS, BASE & SURF
 
1.499 24686408.64 0.00 23966324.67 99.9
CountyBEXAR
Highway MH
From ON EAST-WEST PKWY FROM LOCKHILL-SEL
To IH 35 IN SAN ANTONIO
CSJ 8000-15-007
Proj ID RW 8000-15-7
Work Type ACQUISITION OF ROW
 
0.001 1762476.01 0.00 1649241.93 93.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-07-10
Work Began 01-04-11
Work Completed  
Time Computed 00-00-00
Contract Working Days 273
Addl Days Granted 297
Working Days Charged 783
Percent Time Used 137
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-224
AUSTIN WOOD RECYCLING(0.19%)
BEAIRD DRILLING(2.68%)
COLLECTIVE CONTRACTING (6.40%)
CP REBAR AND PT INSTALLATION (1.01%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.45%)
F & W ELECTRICAL CONTRACTORS, INC. (3.47%)
FUQUAY, INC. (0.45%)
HIGHWAY TECHNOLOGIES, INC. (0.57%)
LONE STAR TRAFFIC SERVICE, INC.(0.10%)
SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.09%)
Z & L CONCRETE CONTRACTORS, INC. (1.19%)
TRI COUNTY SERVICES, INC.(1.19%)
MONTELONGO"S CONCRETE(0.62%)
ROADWAY SPECIALTIES, INC.(0.45%)
S BARRY SIGNATURE HOMES, INC.(1.08%)
CRIBLEY ENTERPRISES, INC.(0.03%)
GEOSOURCE, INC.(1.20%)
SCOTT DERR PAINTING CO, LLC(0.15%)
FLASHER EQUIPMENT COMPANY(0.48%)
DUSTROL, INC.(0.13%)
TEXAS STERLING CONSTRUCTION CO.( 14.73%)
ROADWAY SPECIALTIES, INC.(0.13%)
MUNDO VERDE IRRIGATION & LANDSCAPING, INC. (0.41%)
FUQUAY, INC. (0.49%)
F & W ELECTRICAL CONTRACTORS, INC. (1.41%)
S & S BRIDGE PAINTING, INC.(0.16%)
FLASHER EQUIPMENT COMPANY(0.00%)
Contract # 08103240
Totals 26448884.65 0.00 25615566.60 99.8

CountyBEXAR
Highway VA
From IH 35 AND VARIOUS LOCATIONS_IN
To BEXAR COUNTY
CSJ 0915-12-494
Proj ID STP 2012(531)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2893180.08 0.00 2246119.50 81.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-12
Work Began 09-10-12
Work Completed  
Time Computed 00-00-00
Contract Working Days 245
Addl Days Granted 0
Working Days Charged 380
Percent Time Used 155
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-494
F & W ELECTRICAL CONTRACTORS, INC. ( 17.08%)
INTERSTATE BARRICADES & MARKINGS, INC. (3.87%)
JCD CONSTRUCTION, LLC( 46.25%)
DAVID"S QUALITY CONCRETE WORK(6.43%)
Z & L CONCRETE CONTRACTORS, INC. (2.50%)
Contract # 05123211
Totals 2893180.08 0.00 2246119.50 81.2

CountyBEXAR
Highway VA
From VARIOUS LOCATIONS IN BEXAR COUNTY
To .
CSJ 0915-12-521
Proj ID STP 2014(623)
Work Type CONSTRUCT CURB RAMPS
 
0.001 1885777.35 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-20-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 243
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
F.D. CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-521
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143224
Totals 1885777.35 0.00 0.00 0.0

CountyFRIO
Highway CR
From CR 2515 (BIEDIGER) @ SAN MIGUEL CK
To .
CSJ 0915-18-028
Proj ID BR 2012(237)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.001 235336.60 0.00 227542.38 96.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-14-14
Work Began 04-02-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 98
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-18-028
ALTUS TRAFFIC MANAGEMENT LLC (0.74%)
VOGES DRILLING CO. (9.36%)
RICE ENVIRONMENTAL SERVICES( 18.67%)
JUST GROOVING, LTD.(0.33%)
Contract # 01143011
Totals 235336.60 0.00 227542.38 96.6

CountyUVALDE
Highway PW
From IN GARNER STATE PARK
To .
CSJ 0915-20-015
Proj ID C 915-20-15
Work Type GRAD, BASE, SURF
 
0.001 891460.49 0.00 0.00 0.0
Work Order 04-15-14
Work Began 00-00-00
Work Completed  
Time Computed 06-14-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-20-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143030
Totals 891460.49 0.00 0.00 0.0

CountyGUADALUPE
Highway VA
From IN THE CITY OF SEGUIN
To ALONG WALNUT BRANCH
CSJ 0915-46-039
Proj ID STP 2011(245)TE
Work Type GRAD, BASE, SURF, STR, SIGN
 
0.001 2524283.53 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 206
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0915-46-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143017
Totals 2524283.53 0.00 0.00 0.0

CountyATASCOSA
Highway FM 541
From IH 37
To WILSON/ATASCOSA COUNTY LINE
CSJ 1011-02-017
Proj ID STP 2014(624)
Work Type GRAD, BSE, SURF, PAVMT MRK
 
10.896 6730083.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 324
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SBBI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1011-02-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143204
Totals 6730083.75 0.00 0.00 0.0

CountyUVALDE
Highway RM 1050
From RM 187
To US 83
CSJ 1169-01-023
Proj ID STP 2007(845)
Work Type GRADE, BASE, SURF TREAT & STRUCTURES
 
15.899 8459160.14 19386.55 8149920.53 96.3
Work Order 12-05-11
Work Began 09-05-12
Work Completed  
Time Computed 03-04-12
Contract Working Days 390
Addl Days Granted 12
Working Days Charged 401
Percent Time Used 99
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1169-01-023
HIGHWAY TECHNOLOGIES, INC. (1.07%)
RELMCO, INC. (9.60%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.45%)
M.V. HENKE ENTERPRISES, INC. (3.93%)
FLASHER EQUIPMENT COMPANY(2.45%)
FUQUAY, INC. (3.50%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (4.85%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.06%)
LAREDO STRIPING INC. (1.21%)
Contract # 10113002
Totals 8459160.14 19386.55 8149920.53 96.3

CountyCOMAL
Highway FM 1101
From SH 46
To 0.5 MI N OF FM 306
CSJ 1272-01-016
Proj ID STP 2014(564)
Work Type BASE, GR, STR, SIDEWALK
 
2.797 6154722.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-02-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 354
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1272-01-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143002
Totals 6154722.50 0.00 0.00 0.0

CountyFRIO
Highway FM 1582
From SH 85
To LASALLE COUNTY LINE
CSJ 1500-01-019
Proj ID STP 1102(408)
Work Type GRAD, BASE, STRUCT, SURF, & PVT MK
 
12.870 4529432.30 0.00 4864380.12 99.9
CountyLASALLE
Highway FM 1582
From FRIO COUNTY LINE
To MCMULLEN COUNTY LINE
CSJ 1500-02-009
Proj ID STP 1102(395)
Work Type GRAD, BASE, STRUCT, SURF, & PVT MRK
 
2.181 823198.55 0.00 914878.48 99.9
CountyMCMULLEN
Highway FM 1582
From LASALLE COUNTY LINE
To SH 97
CSJ 1500-03-008
Proj ID STP 1102(408)
Work Type GRAD, BASE, STRUCT, SURF, & PAV MRK
 
1.167 503847.64 0.00 549693.20 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-11-11
Work Began 06-04-12
Work Completed  
Time Computed 00-00-00
Contract Working Days 375
Addl Days Granted 0
Working Days Charged 332
Percent Time Used 88
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1500-01-019
INTERSTATE BARRICADES & MARKINGS, INC. (3.00%)
LANDS SOLUTION CONSTRUCTION(1.09%)
HIGHWAY TECHNOLOGIES, INC. (1.21%)
CABCOS CONTRACTORS LLC (1.35%)
D S TEXAS ICON CONSTRUCTION, LLC (4.25%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.69%)
Contract # 07113250
Totals 5856478.49 0.00 6328951.80 99.9

CountyFRIO
Highway FM 1582
From SP 581
To SH 85
CSJ 1500-01-023
Proj ID STP 2013(717)
Work Type GRADE, BASE, SC, SURF, PAVMT MRK
 
9.939 8831027.89 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 338
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SMC CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1500-01-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143245
Totals 8831027.89 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5