| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | KERR |
| Highway |
CR |
| From |
LAZY VALLEY RD AT CYPRESS CREEK |
| To |
. |
| CSJ |
0915-15-085 |
| Proj ID |
BR 2008(112) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.055 |
364307.64 |
0.00 |
272662.89 |
74.8 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
08-21-12 |
| Work Began |
01-07-13 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
71 |
| Addl Days Granted |
0 |
| Working Days Charged |
66 |
| Percent Time Used |
92 |
| Contractor(s) |
| SHANNON-MONK, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0915-15-085 HILL COUNTRY BRIDGE, INC.( 61.65%) AVAILABLE CONSTRUCTION AND TRANSPORT SERVICES, INC.( 15.85%) ROADWAY SPECIALTIES, INC.(8.59%) FLASHER EQUIPMENT COMPANY(1.18%) O & S TRAFFIC SUPPLIES (0.87%) J. R. (JOE) RAMON & SONS, INC. (1.50%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.19%) JUST GROOVING, LTD.(0.23%)
|
| Contract # |
07123030 |
|
Totals |
364307.64 |
0.00 |
272662.89 |
74.8 |
|
| County | COMAL |
| Highway |
CR |
| From |
CR 227 AT GUADALUPE RIVER |
| To |
. |
| CSJ |
0915-17-048 |
| Proj ID |
BR 2007(637) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.089 |
634238.75 |
8897.70 |
643461.52 |
100.0 |
| County | COMAL |
| Highway |
CR |
| From |
CR 227 AT GUADALUPE RIVER |
| To |
. |
| CSJ |
0915-17-060 |
| Proj ID |
RW 915-17-60 |
| Work Type |
UTILITY ADJUSTMENTS |
| |
|
0.089 |
51755.75 |
0.00 |
57811.05 |
100.0 |
| Work Order |
05-18-11 |
| Work Began |
11-21-11 |
| Work Completed |
04-23-13 |
| Time Computed |
07-07-11 |
| Contract Working Days |
120 |
| Addl Days Granted |
0 |
| Working Days Charged |
157 |
| Percent Time Used |
130 |
| Contractor(s) |
| STRILAND CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0915-17-048 LONE STAR TRAFFIC SERVICE, INC.(0.40%) HIGHWAY TECHNOLOGIES, INC. (0.26%) SITE-SAFE PRODUCTS OF TEXAS, L.P.(4.39%) RICE ENVIRONMENTAL SERVICES(6.01%) BOYLE PLUMBING AND CONTRACTING, INC. (5.46%) A. H. BECK FOUNDATION CO., INC.(2.04%) BEAIRD DRILLING(0.43%) BILLINGSLEY HOUSE MOVING INC.(1.30%) BIG-TEX PAVING, INC. (0.98%)
|
| Contract # |
04113007 |
|
Totals |
685994.50 |
8897.70 |
701272.57 |
100.0 |
|
| County | GUADALUPE |
| Highway |
VA |
| From |
VARIOUS LOCATIONS IN SEGUIN |
| To |
ON IH 10, US 90 US 90A, SH 123 |
| CSJ |
0915-46-036 |
| Proj ID |
STP 2010(092)ESTE |
| Work Type |
LANDSCAPE DEVELOPMENT |
| |
|
0.001 |
614743.40 |
750.00 |
595365.54 |
96.8 |
| Work Order |
10-16-09 |
| Work Began |
11-01-09 |
| Work Completed |
|
| Time Computed |
11-01-09 |
| Contract Working Days |
125 |
| Addl Days Granted |
0 |
| Working Days Charged |
98 |
| Percent Time Used |
78 |
| Contractor(s) |
| LEGENDS LANDSCAPES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0915-46-036 ACE TELECOM, INC.(4.06%) LONE STAR TRAFFIC SERVICE, INC.(0.65%) GREATER TEXAS LANDSCAPES, INC. (8.19%)
|
| Contract # |
09093217 |
|
Totals |
614743.40 |
750.00 |
595365.54 |
96.8 |
|
| County | GUADALUPE |
| Highway |
CS |
| From |
SCHOOL CAMPUSES IN MARION, TX |
| To |
. |
| CSJ |
0915-46-038 |
| Proj ID |
STP 1102(123)SRS |
| Work Type |
SDWLK, SIGNING, STRIPING, BIKE RACKS |
| |
|
0.001 |
542082.00 |
2000.00 |
458921.95 |
84.6 |
| Work Order |
07-12-12 |
| Work Began |
08-13-12 |
| Work Completed |
|
| Time Computed |
09-10-12 |
| Contract Working Days |
120 |
| Addl Days Granted |
0 |
| Working Days Charged |
117 |
| Percent Time Used |
97 |
| Contractor(s) |
| ENCINO LANDSCAPE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0915-46-038 LONE STAR TRAFFIC SERVICE, INC.(0.55%)
|
| Contract # |
06123012 |
|
Totals |
542082.00 |
2000.00 |
458921.95 |
84.6 |
|
| County | MCMULLEN |
| Highway |
PW |
| From |
DAUGHTREY WILDLIFE MANAGEMENT AREA |
| To |
. |
| CSJ |
0915-51-009 |
| Proj ID |
C 915-51-9 |
| Work Type |
BSE, SURF |
| |
|
0.416 |
308546.45 |
587.50 |
318356.10 |
99.9 |
| Work Order |
12-07-12 |
| Work Began |
01-02-13 |
| Work Completed |
|
| Time Computed |
12-23-12 |
| Contract Working Days |
29 |
| Addl Days Granted |
1 |
| Working Days Charged |
28 |
| Percent Time Used |
93 |
| Contractor(s) |
| SALINAS CONSTRUCTION TECHNOLOGIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0915-51-009 DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.80%) FLASHER EQUIPMENT COMPANY(1.66%) INTERSTATE BARRICADES & MARKINGS, INC. (0.63%) BLACKTOPPER TECHNOLOGY, INC. ( 23.41%) ABC EROSION CONTROL, INC.(1.86%)
|
| Contract # |
11123016 |
|
Totals |
308546.45 |
587.50 |
318356.10 |
99.9 |
|
| County | KENDALL |
| Highway |
RM 474 |
| From |
0.9 MI N OF US 87 |
| To |
1.5 MI N OF US 87 (ADLER ST.) |
| CSJ |
1042-01-029 |
| Proj ID |
STP 2012(036) |
| Work Type |
GR, BS, STR, SURF, & PAV MRK |
| |
|
0.634 |
2053020.89 |
0.00 |
2183833.47 |
99.9 |
| Work Order |
11-03-11 |
| Work Began |
02-15-12 |
| Work Completed |
|
| Time Computed |
02-01-12 |
| Contract Working Days |
166 |
| Addl Days Granted |
0 |
| Working Days Charged |
125 |
| Percent Time Used |
75 |
| Contractor(s) |
| DEAN WORD COMPANY, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1042-01-029 ROADWAY SPECIALTIES, INC.(8.13%) E-Z BEL CONSTRUCTION, LLC(4.81%) F & W ELECTRICAL CONTRACTORS, INC._(SAN ANTONIO) (1.19%) FLASHER EQUIPMENT COMPANY(2.35%)
|
| Contract # |
09113013 |
|
Totals |
2053020.89 |
0.00 |
2183833.47 |
99.9 |
|
| County | BANDERA |
| Highway |
PR 37 |
| From |
0.5 MI SW OF SCENIC MOUNTAIN |
| To |
1.5 MI NE OF SCENIC MOUNTAIN |
| CSJ |
1066-01-022 |
| Proj ID |
STP 2013(173)HES |
| Work Type |
GRADING, BASE, SURF, PAV MRK, SIGNS |
| |
|
2.000 |
792516.32 |
189389.93 |
372983.49 |
47.0 |
| Work Order |
11-30-12 |
| Work Began |
01-29-13 |
| Work Completed |
|
| Time Computed |
02-20-13 |
| Contract Working Days |
103 |
| Addl Days Granted |
0 |
| Working Days Charged |
43 |
| Percent Time Used |
41 |
| Contractor(s) |
| V.K. KNOWLTON CONSTRUCTION AND UTILITIES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1066-01-022 RICE ENVIRONMENTAL SERVICES( 14.30%) 3LW MANAGEMENT, LLC( 11.49%) FLASHER EQUIPMENT COMPANY(3.36%)
|
| Contract # |
11123005 |
|
Totals |
792516.32 |
189389.93 |
372983.49 |
47.0 |
|
| County | KERR |
| Highway |
FM 1341 |
| From |
1.5 MI E OF SP 534 |
| To |
1.6 MI W OF RED ROSE |
| CSJ |
1135-03-026 |
| Proj ID |
STP 2012(422)HES |
| Work Type |
GRADING, BASE, SURF, PAV MRK, SIGNS |
| |
|
0.506 |
367231.00 |
0.00 |
289504.78 |
78.8 |
| Work Order |
05-09-12 |
| Work Began |
09-10-12 |
| Work Completed |
|
| Time Computed |
05-25-12 |
| Contract Working Days |
71 |
| Addl Days Granted |
0 |
| Working Days Charged |
67 |
| Percent Time Used |
94 |
| Contractor(s) |
| WAGNER MATERIALS & CONSTRUCTION |
SUBCONTRACTOR(S) FOR CCSJ: 1135-03-026 ROADWAY SPECIALTIES, INC.(9.41%) INTERSTATE CONCRETE & STEEL SERVICES INCORPORATED( 10.96%) FLASHER EQUIPMENT COMPANY(7.47%) RAY FARIS, INC.( 35.54%) DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.20%)
|
| Contract # |
03123214 |
|
Totals |
367231.00 |
0.00 |
289504.78 |
78.8 |
|
| County | UVALDE |
| Highway |
FM 1049 |
| From |
SH 127 |
| To |
4.6 MI SOUTH OF SH 127 |
| CSJ |
1168-02-015 |
| Proj ID |
STP 2013(036) |
| Work Type |
BASE, GR, STRS, PAV MARK |
| |
|
4.606 |
2094080.99 |
292609.86 |
1466935.62 |
70.0 |
| Work Order |
10-03-12 |
| Work Began |
12-03-12 |
| Work Completed |
|
| Time Computed |
12-02-12 |
| Contract Working Days |
154 |
| Addl Days Granted |
0 |
| Working Days Charged |
111 |
| Percent Time Used |
72 |
| Contractor(s) |
| V.K. KNOWLTON CONSTRUCTION AND UTILITIES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1168-02-015 WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(4.03%) FLASHER EQUIPMENT COMPANY(1.96%)
|
| Contract # |
08123248 |
|
Totals |
2094080.99 |
292609.86 |
1466935.62 |
70.0 |
|
| County | UVALDE |
| Highway |
RM 1050 |
| From |
RM 187 |
| To |
US 83 |
| CSJ |
1169-01-023 |
| Proj ID |
STP 2007(845) |
| Work Type |
GRADE, BASE, SURF TREAT & STRUCTURES |
| |
|
15.899 |
8459160.14 |
480211.76 |
2645876.63 |
31.2 |
| Work Order |
12-05-11 |
| Work Began |
09-05-12 |
| Work Completed |
|
| Time Computed |
03-04-12 |
| Contract Working Days |
390 |
| Addl Days Granted |
0 |
| Working Days Charged |
186 |
| Percent Time Used |
47 |
| Contractor(s) |
| DEAN WORD COMPANY, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1169-01-023 HIGHWAY TECHNOLOGIES, INC. (1.07%) RELMCO, INC. (9.60%) DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.45%) M.V. HENKE ENTERPRISES, INC. (3.93%) FLASHER EQUIPMENT COMPANY(2.45%) FUQUAY, INC. (3.50%) ALTEX LANDSCAPE CONSTRUCTION, INC. (4.85%) AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.06%)
|
| Contract # |
10113002 |
|
Totals |
8459160.14 |
480211.76 |
2645876.63 |
31.2 |
|
| County | FRIO |
| Highway |
FM 1582 |
| From |
SH 85 |
| To |
LASALLE COUNTY LINE |
| CSJ |
1500-01-019 |
| Proj ID |
STP 1102(408) |
| Work Type |
GRAD, BASE, STRUCT, SURF, & PVT MK |
| |
|
12.870 |
4529432.30 |
0.00 |
3574061.13 |
78.9 |
| County | LASALLE |
| Highway |
FM 1582 |
| From |
FRIO COUNTY LINE |
| To |
MCMULLEN COUNTY LINE |
| CSJ |
1500-02-009 |
| Proj ID |
STP 1102(395) |
| Work Type |
GRAD, BASE, STRUCT, SURF, & PVT MRK |
| |
|
2.181 |
823198.55 |
0.00 |
28675.89 |
3.4 |
| County | MCMULLEN |
| Highway |
FM 1582 |
| From |
LASALLE COUNTY LINE |
| To |
SH 97 |
| CSJ |
1500-03-008 |
| Proj ID |
STP 1102(408) |
| Work Type |
GRAD, BASE, STRUCT, SURF, & PAV MRK |
| |
|
1.167 |
503847.64 |
0.00 |
124202.47 |
24.6 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
08-11-11 |
| Work Began |
06-04-12 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
375 |
| Addl Days Granted |
0 |
| Working Days Charged |
209 |
| Percent Time Used |
55 |
| Contractor(s) |
| ANDERSON COLUMBIA CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1500-01-019 INTERSTATE BARRICADES & MARKINGS, INC. (3.00%) LANDS SOLUTION CONSTRUCTION(1.09%) HIGHWAY TECHNOLOGIES, INC. (1.21%) CABCOS CONTRACTORS LLC (1.35%) D S TEXAS ICON CONSTRUCTION, LLC (4.25%)
|
| Contract # |
07113250 |
|
Totals |
5856478.49 |
0.00 |
3726939.49 |
63.6 |
|
| County | UVALDE |
| Highway |
FM 481 |
| From |
AT NUECES RIVER |
| To |
. |
| CSJ |
1590-01-021 |
| Proj ID |
BR 2012(755) |
| Work Type |
GRAD, STRS, BASE & SURF |
| |
|
0.332 |
2663512.88 |
0.00 |
20500.00 |
0.7 |
| Work Order |
09-24-12 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
10-10-12 |
| Contract Working Days |
231 |
| Addl Days Granted |
0 |
| Working Days Charged |
22 |
| Percent Time Used |
9 |
| Contractor(s) |
| RELMCO, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1590-01-021 W. W. FOUNDATION DRILLING, LTD.(2.16%) FLASHER EQUIPMENT COMPANY(0.50%) O & S TRAFFIC SUPPLIES (0.33%)
|
| Contract # |
08123039 |
|
Totals |
2663512.88 |
0.00 |
20500.00 |
0.7 |
|
| County | COMAL |
| Highway |
FM 306 |
| From |
0.5 MI NORTH OF HUNTER ROAD |
| To |
IH 35 |
| CSJ |
1728-02-037 |
| Proj ID |
STP 2012(694) |
| Work Type |
GRAD, STR, BASE, SURF |
| |
|
2.046 |
6197894.34 |
670341.37 |
1826492.06 |
29.4 |
| County | COMAL |
| Highway |
FM 306 |
| From |
IN NEW BRAUNFELS AT UPRR CROSSING |
| To |
DOT 415536E |
| CSJ |
1728-02-049 |
| Proj ID |
STP 2012(695)RGS |
| Work Type |
CONSTRUCT RR GRADE SEPARATION STR & |
| |
|
0.500 |
7368312.94 |
489236.77 |
761696.20 |
10.3 |
| County | COMAL |
| Highway |
FM 306 |
| From |
IN NEW BRAUNFELS AT UPRR CROSSING |
| To |
. |
| CSJ |
1728-02-050 |
| Proj ID |
STP 2012(695)RGS |
| Work Type |
CONSTRUCT RR GRADE SEPARATION STR & |
| |
|
0.530 |
9572658.52 |
442018.90 |
948260.85 |
9.9 |
| Work Order |
10-24-12 |
| Work Began |
03-12-13 |
| Work Completed |
|
| Time Computed |
04-22-13 |
| Contract Working Days |
587 |
| Addl Days Granted |
0 |
| Working Days Charged |
36 |
| Percent Time Used |
6 |
| Contractor(s) |
| HUNTER INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1728-02-037 HIGHWAY TECHNOLOGIES, INC. (0.88%) DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.91%) ENVIRONMENTAL SAFETY SERVICES, INC.(1.10%) GK CONSTRUCTION, LLC (0.35%) PRIMATE CONSTRUCTION, INC. (0.05%) THE LEVY COMPANY, L.P. (1.15%) R K STEPHENS CONSTRUCTION, LLC (2.48%) ROADWAY SPECIALTIES, INC.(0.18%) SCOTT DERR PAINTING CO, LLC(0.17%) VOGES DRILLING CO. (1.00%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.57%) CATO DRILLING COMPANY(0.01%)
|
| Contract # |
08123202 |
|
Totals |
23138865.80 |
1601597.04 |
3536449.11 |
15.2 |
|
| County | FRIO |
| Highway |
FM 462 |
| From |
MOORE (STA 0+15) |
| To |
FM 472 IN BIG FOOT |
| CSJ |
1729-01-015 |
| Proj ID |
STP 2013(106) |
| Work Type |
GRAD, STR, BASE, SURF |
| |
|
8.382 |
4686835.06 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
03-15-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
360 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| RAY FARIS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1729-01-015 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10123218 |
|
Totals |
4686835.06 |
0.00 |
0.00 |
0.0 |
|
| County | ATASCOSA |
| Highway |
FM 2504 |
| From |
SH 173 |
| To |
1.8 MI S OF FM 476 |
| CSJ |
1738-02-013 |
| Proj ID |
C 1738-2-13 |
| Work Type |
GRADE, BASE & SURF |
| |
|
7.750 |
3839024.80 |
0.00 |
685844.14 |
17.8 |
| County | ATASCOSA |
| Highway |
FM 2504 |
| From |
1.8 MI S OF FM 476 |
| To |
FM 476 |
| CSJ |
1740-02-028 |
| Proj ID |
C 1740-2-28 |
| Work Type |
GRADE, BASE & SURF |
| |
|
1.841 |
1065719.82 |
0.00 |
860243.80 |
80.7 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
08-01-12 |
| Work Began |
10-15-12 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
186 |
| Addl Days Granted |
0 |
| Working Days Charged |
133 |
| Percent Time Used |
71 |
| Contractor(s) |
| RAY FARIS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1738-02-013 DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.21%) M.V. HENKE ENTERPRISES, INC. (0.40%) TEXAS ALTERNATIVE GRASSER, INC.(1.51%) E-Z BEL CONSTRUCTION, LLC(0.53%) FLASHER EQUIPMENT COMPANY(3.30%) RICE ENVIRONMENTAL SERVICES(2.73%) RELMCO, INC. (3.73%)
|
| Contract # |
06123204 |
|
Totals |
4904744.62 |
0.00 |
1546087.94 |
31.5 |
|
| County | BEXAR |
| Highway |
LP 1604 |
| From |
AT SH 151 |
| To |
. |
| CSJ |
2452-01-043 |
| Proj ID |
NH 2007(705) |
| Work Type |
CONSTR I / C |
| |
|
0.407 |
14882512.77 |
0.00 |
2944947.61 |
19.7 |
| County | BEXAR |
| Highway |
LP 1604 |
| From |
AT SH 151 |
| To |
. |
| CSJ |
2452-01-048 |
| Proj ID |
RW 2452-1-48 |
| Work Type |
ROW UTL. ADJ. |
| |
|
0.407 |
244327.22 |
0.00 |
18481.21 |
7.5 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
03-12-12 |
| Work Began |
04-17-12 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
382 |
| Addl Days Granted |
0 |
| Working Days Charged |
84 |
| Percent Time Used |
21 |
| Contractor(s) |
| LIBERTY MUTUAL INSURANCE COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 2452-01-043 ROADWAY SPECIALTIES, INC.(0.74%) MUNDO VERDE IRRIGATION & LANDSCAPING, INC. (0.64%) Z & L CONCRETE CONTRACTORS, INC. (2.07%) FUQUAY, INC. (0.22%) FLASHER EQUIPMENT COMPANY(0.18%) DU-MOR ENTERPRISES_INC.(1.09%) BADECO, INC(1.35%) BEAIRD DRILLING(0.31%) F & W ELECTRICAL CONTRACTORS, INC. (3.18%) AUSTIN WOOD RECYCLING(0.20%) G.T. SIRIZZOTTI, LTD.(5.63%) HIGHWAY TECHNOLOGIES, INC. (0.61%) TEXAS STERLING CONSTRUCTION CO.(1.40%) C & C ALCOSER TRUCKING (0.13%) MUNDO VERDE IRRIGATION & LANDSCAPING, INC. (0.06%)
|
| Contract # |
01123001 |
|
Totals |
15126839.99 |
0.00 |
2963428.82 |
19.5 |
|
| County | BEXAR |
| Highway |
LP 1604 |
| From |
AT MARBACH ROAD |
| To |
. |
| CSJ |
2452-01-051 |
| Proj ID |
C 2452-1-51 |
| Work Type |
GRAD, BASE, STR, SURF, PVT MRK, SIGN |
| |
|
1.281 |
11250793.65 |
859982.43 |
2199450.68 |
19.5 |
| Work Order |
12-07-12 |
| Work Began |
01-21-13 |
| Work Completed |
|
| Time Computed |
12-23-12 |
| Contract Working Days |
233 |
| Addl Days Granted |
0 |
| Working Days Charged |
70 |
| Percent Time Used |
30 |
| Contractor(s) |
| CAPITAL EXCAVATION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 2452-01-051 DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.40%) ROADWAY SPECIALTIES, INC.(0.04%) STAR OPERATIONS, INC.(2.93%) M & M INDUSTRIAL PAINTING( 10.25%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.28%) PRIMATE CONSTRUCTION, INC. (0.00%) TEXAS HIGHWAY WALLS( 24.68%) RAMMING PAVING COMPANY ( 20.52%) VOGES DRILLING CO. (1.01%) FLASHER EQUIPMENT COMPANY(0.92%) C & C ALCOSER TRUCKING (0.00%)
|
| Contract # |
09123005 |
|
Totals |
11250793.65 |
859982.43 |
2199450.68 |
19.5 |
|
| County | BEXAR |
| Highway |
LP 1604 |
| From |
AT IH 10 |
| To |
. |
| CSJ |
2452-02-081 |
| Proj ID |
NH 2012(038) |
| Work Type |
GRAD, BASE, STR, SURF, PAV'T MRKNG |
| |
|
0.606 |
1684204.08 |
0.00 |
1696397.41 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
10-19-11 |
| Work Began |
01-09-12 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
85 |
| Addl Days Granted |
21 |
| Working Days Charged |
193 |
| Percent Time Used |
182 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 2452-02-081 MENADE, INC. ( 19.43%) MICA CORPORATION ( 11.01%) FLASHER EQUIPMENT COMPANY(2.15%) JET UNDERGROUND UTILITIES, INC.( 19.32%) J & M CONTRACTING, COMPANY (2.53%) ROADWAY SPECIALTIES, INC.(2.41%) SCOTT DERR PAINTING CO (2.27%) S & S BRIDGE PAINTING, INC.( 12.72%) F & W ELECTRICAL CONTRACTORS, INC. (0.86%)
|
| Contract # |
09113004 |
|
Totals |
1684204.08 |
0.00 |
1696397.41 |
99.9 |
|
| County | BEXAR |
| Highway |
LP 1604 |
| From |
AT VANCE JACKSON |
| To |
. |
| CSJ |
2452-02-082 |
| Proj ID |
C 2452-2-82 |
| Work Type |
GRAD, BASE, STR, SURF, PAV'T MRK |
| |
|
0.048 |
3175995.00 |
0.00 |
1974691.90 |
62.1 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
09-13-12 |
| Work Began |
10-26-12 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
163 |
| Addl Days Granted |
0 |
| Working Days Charged |
145 |
| Percent Time Used |
88 |
| Contractor(s) |
| AUSTIN BRIDGE & ROAD, LP |
SUBCONTRACTOR(S) FOR CCSJ: 2452-02-082 ROADWAY SPECIALTIES, INC.(2.25%) GK CONSTRUCTION, LLC (2.26%) FLASHER EQUIPMENT COMPANY(0.92%) AARON CONCRETE CONTRACTORS, L.P. (2.07%) RAMMING PAVING COMPANY (1.82%) SOUTH TEXAS PAINTING COMPANY (0.13%) PRIMATE CONSTRUCTION, INC. (0.11%) MCKINNEY DRILLING COMPANY(8.61%) THE LEVY COMPANY, L.P. ( 11.16%) A. H. BECK FOUNDATION CO., INC.(2.23%) CATO DRILLING COMPANY(0.51%)
|
| Contract # |
07123209 |
|
Totals |
3175995.00 |
0.00 |
1974691.90 |
62.1 |
|
| County | ATASCOSA |
| Highway |
FM 2924 |
| From |
FM 99 |
| To |
FM 791 |
| CSJ |
2975-01-008 |
| Proj ID |
STP 2013(349) |
| Work Type |
GRAD, BSE, SURF, PAVM'T MRK |
| |
|
4.136 |
2186637.48 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-10-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
214 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| SALINAS CONSTRUCTION TECHNOLOGIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 2975-01-008 F & W ELECTRICAL CONTRACTORS, INC._(SAN ANTONIO) (0.93%) FUQUAY, INC. (1.03%) FLASHER EQUIPMENT COMPANY(2.46%)
|
| Contract # |
01133004 |
|
Totals |
2186637.48 |
0.00 |
0.00 |
0.0 |
|