Monthly State Let Construction Report For San Antonio District As Of May 11, 2017 Page 4 Of 5

Last Update: Wednesday, May 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyATASCOSA
HighwaySH 97
FromMCMULLEN/ATASCOSA C/L
To2.0 MI N. OF MCMULLEN/ATASCOSA C/L
CSJ0328-06-028
Proj IDSTP 1402(065)
Work TypeGRADE, BASE, SC, SURF, PVMT MRK
 
2.5593835534.674470390.1299.9
CountyMCMULLEN
HighwaySH 97
FromLASALLE/MCMULLEN C/L
ToATASCOSA/MCMULLEN C/L
CSJ0328-07-016
Proj IDSTP 1402(065)
Work TypeGRADE, BASE, SC, SURF, PAVMT MRK
 
10.34014856569.6916085512.7999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-17-14
Work Began11-10-14
Work Completed
Time Computed11-10-14
Contract Working Days331
Addl Days Granted36
Working Days Charged474
Percent Time Used129
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0328-06-028
N-LINE TRAFFIC MAINTENANCE, L.P. (0.49)
LONE STAR EROSION CONTROL (3.08)
F & W ELECTRICAL CONTRACTORS, INC. (0.22)
FLASHER EQUIPMENT COMPANY (1.61)
LONE STAR PAVING (37.44)
TRINITY EAGLEFORD SERVICES LLC (1.21)
GEOSOURCE, INC. (0.99)
Contract #08143004
Totals18692104.360.0020555902.9199.9

CountyATASCOSA
HighwaySH 97
From2.6 MILES NORTH OF MCMULLEN C/L
To9.0 MI NORTH OF MCMULLEN C/L
CSJ0328-06-029
Proj IDSTP 2016(072)
Work TypeGR, BASE, STRUC, PVMT MRKINGS
 
6.44110114302.983175162.8431.3
Work Order02-10-16
Work Began00-00-00
Work Completed
Time Computed04-10-16
Contract Working Days451
Addl Days Granted0
Working Days Charged262
Percent Time Used58
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0328-06-029
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.19)
CUATRO T CONSTRUCTION, INC. (5.04)
FLASHER EQUIPMENT COMPANY (2.43)
RELMCO, INC. (1.68)
(USE 25816)D & S TEXAS ICON CONSTRUCTION, LLC. (0.53)
FUQUAY, INC. (1.61)
CHEROKEE SERVICES (0.43)
LORENZ FIELD SERVICES, LLC (0.14)
ALTUS TRAFFIC MANAGEMENT LLC (0.43)
R & P CONSTRUCTION (5.70)
Contract #09153006
Totals10114302.98165703.733175162.8431.3

CountyWILSON
HighwaySH 123
FromAT FM 537, FM 1347 AND FM 541
To.
CSJ0366-05-044
Proj IDSTP 2017(285)
Work TypeGRAD, BSE, SURF, PAVMT MRK
 
1.313611559.930.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-12-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days33
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0366-05-044
DELGADO"S CONSTRUCTION (10.77)
FLASHER EQUIPMENT COMPANY (1.30)
D. I. J. CONSTRUCTION, INC. (7.45)
GEOSOURCE, INC. (0.29)
FUQUAY, INC. (1.99)
Contract #11163011
Totals611559.930.000.000.0

CountyGUADALUPE
HighwayBS 123B
From0.2 MI NORTH OF US 90
ToIH 10
CSJ0366-12-026
Proj IDSTP 2016(176)
Work TypeGR, BASE, STR, SURF, CURB,PAV'T MRK
 
1.0225283542.961046657.1019.8
CountyGUADALUPE
HighwayBS 123B
From0.2 MI NORTH OF US 90
ToIH 10
CSJ0366-12-027
Proj IDROW 366-12-27
Work TypeACQUISITION AND UTILITIES
 
1.0221805450.79538555.7629.8
Work Order01-29-16
Work Began00-00-00
Work Completed
Time Computed05-29-16
Contract Working Days375
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0366-12-026
ENVIRONMENTAL SAFETY SERVICES, INC. (2.69)
E-Z BEL CONSTRUCTION, LLC (0.94)
2 J RESOURCES COMPANY (3.19)
FLASHER EQUIPMENT COMPANY (0.71)
DC CIVIL CONSTRUCTION LLC (16.21)
CLAUDIA SERNA DBA SERNA"S TRUCKING (0.00)
MELENDREZ BROTHERS TRUCKING, INC. (0.06)
Contract #10153217
Totals7088993.7598157.231585212.8622.3

CountyBEXAR
HighwaySL 13
FromFAIRLAWN
ToIH 10
CSJ0521-01-050
Proj IDNH 2016(668)
Work TypeSURFACE & PAVEMENT MARKINGS
 
6.0382849994.413353092.2999.9
Work Order03-09-16
Work Began04-08-16
Work Completed
Time Computed04-08-16
Contract Working Days89
Addl Days Granted14
Working Days Charged101
Percent Time Used98
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0521-01-050
INTERSTATE BARRICADES & MARKINGS, INC. (4.88)
SCR CONSTRUCTION CO., INC. (2.38)
Contract #02163006
Totals2849994.4157451.703353092.2999.9

CountyBEXAR
HighwayIH 410
FromSH 151
ToINGRAM RD.
CSJ0521-04-274
Proj IDC 521-4-274
Work TypeGRAD, STR, BASE, SURF, PAV MARKINGS
 
2.71681778634.0461340602.4275.0
CountyBEXAR
HighwayIH 410
FromSH 151
ToINGRAM RD.
CSJ0521-04-276
Proj IDROW 521-4-276
Work TypeROW UTILITY ADJUSTMENTS
 
2.716103972.0081281.5878.1
Work Order07-31-15
Work Began10-12-15
Work Completed
Time Computed10-29-15
Contract Working Days760
Addl Days Granted0
Working Days Charged464
Percent Time Used61
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0521-04-274
INDUS CONSTRUCTION, L.P. (6.72)
CPAVE, INC. (0.19)
MOBILE ENTERPRISES, INC. (0.01)
S & S BRIDGE PAINTING, INC. (1.63)
FLASHER EQUIPMENT COMPANY (0.62)
Z & L CONCRETE CONTRACTORS, INC. (3.85)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.48)
F & W ELECTRICAL CONTRACTORS, INC. (5.05)
SCOTT DERR PAINTING CO, LLC (0.30)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
Contract #06153001
Totals81882606.04219797.7861421884.0075.0

CountyBEXAR
HighwayIH 410
From0.1 MI N OF US 90
To0.3 MI S OF SH 151
CSJ0521-04-277
Proj IDNH 1602(247)
Work TypeGRAD, STR, BASE, SURF & PAV MARK
 
2.16238980576.207953611.6020.4
CountyBEXAR
HighwayIH 410
From0.1 MI N OF US 90
To0.3 MI S OF SH 151
CSJ0521-04-284
Proj IDNH 2017(417)
Work TypeROW UTILITY ADJUSTMENTS
 
2.1621565942.25865168.6355.2
CountyBEXAR
HighwayIH 410
FromAT US 90 WEST
ToINTERCHANGE
CSJ0521-05-118
Proj IDNH 1602(247)
Work TypeGRAD,STR,BASE,SURF & PAV MARK
 
0.39033369177.267198579.9921.5
CountyBEXAR
HighwayIH 410
FromAT US 90 WEST
ToINTERCHANGE
CSJ0521-05-142
Proj IDROW 521-5-142
Work TypeSA ROW ACQ AND UTILITIES
 
0.39013706.000.000.0
Work Order12-27-16
Work Began00-00-00
Work Completed
Time Computed01-16-17
Contract Working Days1,000
Addl Days Granted0
Working Days Charged90
Percent Time Used9
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0521-04-277
THE LEVY COMPANY, L.P. (4.94)
SCOTT DERR PAINTING CO, LLC (0.28)
GEOSOURCE, INC. (0.15)
EGGEMEYER LAND CLEARING, LLC (0.02)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.13)
BADECO, INC (0.27)
FLASHER EQUIPMENT COMPANY (0.56)
LONE STAR EROSION CONTROL (0.13)
AARON CONCRETE CONTRACTORS, L.P. (5.88)
JPC CONSTRUCTION INC DBA JC COMMUNICATIONS (0.16)
LONE STAR SITEWORK, LLC (0.29)
ROYAL REBAR (4.47)
Z & L CONCRETE CONTRACTORS, INC. (2.40)
ROADWAY SPECIALTIES, INC. (1.10)
PRESIDIO CONTRACTING, LLC (0.03)
Contract #12163001
Totals73929401.712014664.3016017360.2221.6

CountyBEXAR
HighwayIH 410
FromFREDRICKSBURG RD
ToIH 35
CSJ0521-04-278
Proj IDNH 2017(985)
Work TypeSURFACE & PAVEMENT MARKINGS
 
10.5223839721.960.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days88
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0521-04-278
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173219
Totals3839721.960.000.000.0

CountyBEXAR
HighwayIH 410
FromMEDINA BASE RD.
To0.6 MILES EAST OF IH 35
CSJ0521-05-139
Proj IDNH 2014(854)
Work TypeSLOPE REPAIR, OVERLAY, MBGF, PAV MK
 
4.7786711711.716684262.1499.7
Work Order08-20-14
Work Began07-07-15
Work Completed
Time Computed10-20-14
Contract Working Days110
Addl Days Granted15
Working Days Charged132
Percent Time Used105
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0521-05-139
FLASHER EQUIPMENT COMPANY (1.91)
CLAUDIA SERNA DBA SERNA"S TRUCKING (0.96)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.75)
PRIMATE CONSTRUCTION, INC. (1.44)
ALTUS TRAFFIC MANAGEMENT LLC (0.20)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (5.35)
THE LEVY COMPANY, L.P. (0.12)
Contract #06143244
Totals6711711.710.006684262.1499.7

CountyGUADALUPE
HighwayIH 10
FromSH 46
ToSH 123 B
CSJ0535-01-072
Proj IDC 535-1-72
Work TypeGRAD,BSE,STR,SURF,SIGN,PAV'T MRK
 
2.02729174029.3222610490.5977.5
Work Order07-30-15
Work Began11-30-15
Work Completed
Time Computed11-30-15
Contract Working Days782
Addl Days Granted0
Working Days Charged357
Percent Time Used45
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0535-01-072
AARON CONCRETE CONTRACTORS, L.P. (0.82)
ALTUS TRAFFIC MANAGEMENT LLC (0.32)
DIAMOND SURFACE, INC. (0.02)
FLASHER EQUIPMENT COMPANY (0.57)
RAMMING PAVING COMPANY (14.04)
ROADWAY SPECIALTIES, INC. (0.52)
DRILL TECH DRILLING & SHORING, INC. (4.11)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.36)
K.L. DURHAM CONSTRUCTION, LLC (0.07)
MURRAY CONSTRUCTION (0.28)
PENHALL COMPANY (AUSTIN) (0.07)
RICE ENVIRONMENTAL SERVICES (0.68)
SCR CONSTRUCTION CO., INC. (0.21)
VOGES DRILLING (1.00)
THE LEVY COMPANY, L.P. (5.40)
CP REBAR AND PT INSTALLATION (0.35)
FRANK JR REINFORCEMENT LLC (0.07)
TEXAS HIGHWAY WALLS (1.10)
2 J RESOURCES COMPANY (5.73)
MK1 CONSTRUCTION SERVICES, LLC (1.86)
Contract #05153003
Totals29174029.321226129.3022610490.5977.5

CountyATASCOSA
HighwaySH 16
From0.937 MI S OF FM 3350
To0.951 MI N OF CR 306
CSJ0613-02-057
Proj IDSTP 1502(276)HES
Work TypeCENTERLINE TEXTURING
 
4.00035128.400.000.0
CountyATASCOSA
HighwaySH 16
FromSH 97
To0.2 MI SOUTH OF SP 282
CSJ0613-02-058
Proj IDSTP 1502(275)
Work TypeGRADING, HMA, SURF, PAV MRK
 
7.77313453085.6311511017.1887.6
Work Order08-20-15
Work Began00-00-00
Work Completed
Time Computed10-20-15
Contract Working Days146
Addl Days Granted12
Working Days Charged374
Percent Time Used236
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0613-02-057
CHEROKEE SERVICES (0.15)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.76)
FLASHER EQUIPMENT COMPANY (1.20)
WEST TX RUMBLE STRIP (0.03)
D&S TEXAS ICON CONSTRUCTION, LLC (0.18)
FUQUAY, INC. (0.80)
CUATRO T CONSTRUCTION, INC. (2.04)
AARON CONCRETE CONTRACTORS, L.P. (0.45)
MURRAY CONSTRUCTION (0.07)
Contract #06153207
Totals13488214.033036.3111511017.1887.3

CountyUVALDE
HighwayRM 187
FromBANDERA C/L
ToCR 354
CSJ0678-01-033
Proj IDSTP 2016(407)
Work TypeLANDSCAPE DEVELOPMENT
 
1.610129489.00138827.6199.9
CountyUVALDE
HighwayRM 1050
FromSABINAL RIVER
ToRM 187
CSJ1169-01-025
Proj IDSTP 2016(407)
Work TypeLANDSCAPE DEVELOPMENT
 
0.18824373.0026742.8999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-29-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days55
Addl Days Granted36
Working Days Charged91
Percent Time Used100
Contractor(s)
M & S CONCRETE CO.
SUBCONTRACTOR(S) FOR CCSJ: 0678-01-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12153030
Totals153862.000.00165570.5099.9

CountyECTOR
HighwayVA
FromON IH 10 IN PECOS COUNTY
To.
CSJ0906-00-180
Proj IDNH 2017(558)
Work TypeINSTALL DMS
 
0.001112682.110.000.0
CountyTOM GREEN
HighwayVA
FromON IH 10 FROM KIMBLE/KERR CO LINE
ToTO CROCKETT/PECOS COUNTY LINE
CSJ0907-00-183
Proj IDNH 2017(558)
Work TypeINSTALL DMS
 
0.001683074.050.000.0
CountyBEXAR
HighwayVA
FromON IH 10 FROM CITY OF BOERNE
ToKIMBLE/KERR COUNTY LINE
CSJ0915-00-194
Proj IDNH 2017(558)
Work TypeINSTALL DMS
 
0.001960828.1611349.581.1
Work Order03-15-17
Work Began00-00-00
Work Completed
Time Computed04-14-17
Contract Working Days123
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-180
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173235
Totals1756584.3211349.5811349.580.6

CountyBEXAR
HighwayVA
FromDISTRICTWIDE GUIDESIGNS FY14
To.
CSJ0915-00-155
Proj IDSTP 2014(562)
Work TypeDISTRICTWIDE GUIDESIGNS FY14
 
0.001998524.12612045.9261.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-20-14
Work Began07-20-14
Work Completed
Time Computed07-21-14
Contract Working Days208
Addl Days Granted4
Working Days Charged208
Percent Time Used98
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-155
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04143205
Totals998524.120.00612045.9261.2

CountyBEXAR
HighwayVA
FromDISTRICTWIDE GUIDESIGNS FY16
To.
CSJ0915-00-159
Proj IDSTP 2016(902)
Work TypeDISTRICTWIDE GUIDESIGNS FY16
 
0.0012452827.791804853.8573.5
Work Order06-03-16
Work Began11-07-16
Work Completed
Time Computed07-03-16
Contract Working Days360
Addl Days Granted0
Working Days Charged108
Percent Time Used30
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-159
FLASHER EQUIPMENT COMPANY (1.14)
ENVIRONMENTAL SAFETY SERVICES, INC. (8.75)
JCD CONSTRUCTION, LLC (0.11)
AMERICAN TRAFFIC CONTROL (15.49)
Contract #04163232
Totals2452827.79183784.581804853.8573.5

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2016
To.
CSJ0915-00-166
Proj IDSTP 2016(669)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011355867.97819335.1760.4
Work Order03-28-16
Work Began06-09-16
Work Completed
Time Computed04-27-16
Contract Working Days320
Addl Days Granted0
Working Days Charged139
Percent Time Used43
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-166
FLASHER EQUIPMENT COMPANY (2.31)
HEARN CO. (6.88)
Contract #02163034
Totals1355867.9799895.00819335.1760.4

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2017
To.
CSJ0915-00-180
Proj IDSTP 2017(565)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011383517.970.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-10-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days315
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-180
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173213
Totals1383517.970.000.000.0

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2017
To.
CSJ0915-00-204
Proj IDSTP 2017(894)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011349187.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-09-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days320
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D&G ENERGY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-204
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173003
Totals1349187.000.000.000.0

CountyKENDALL
HighwayCR
FromMILL DAM ROAD, 0.6 MI S OF SH 27
ToAT GUADALUPE RIVER
CSJ0915-11-031
Proj IDBR 1602(228)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1581522927.91446715.7029.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-02-17
Work Began03-16-17
Work Completed
Time Computed00-00-00
Contract Working Days268
Addl Days Granted0
Working Days Charged35
Percent Time Used13
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-11-031
W. W. FOUNDATION DRILLING, LTD. (8.05)
(USE 07366)J.R. RAMON & SONS, INC (6.73)
ENVIRONMENTAL SAFETY SERVICES, INC. (5.52)
AUSTIN WOOD RECYCLING (2.40)
LONE STAR PAVING (1.33)
FLASHER EQUIPMENT COMPANY (0.94)
FUQUAY, INC. (0.70)
Contract #01173209
Totals1522927.910.00446715.7029.3

CountyBEXAR
HighwayCR
FromGROSS LANE AT MEDINA RIVER
To.
CSJ0915-12-439
Proj IDBR 2007(638)
Work TypeREHABILITATE BRIDGE AND APPROACHES
 
0.001527480.77734431.5599.9
Work Order03-06-15
Work Began04-13-15
Work Completed
Time Computed04-13-15
Contract Working Days69
Addl Days Granted91
Working Days Charged160
Percent Time Used100
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-439
MCL CONTRACTING, LLC (0.88)
DOUBLE S PAVING, INC. (2.26)
FLASHER EQUIPMENT COMPANY (1.81)
LONE STAR EROSION CONTROL (1.51)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.71)
ROADWAY SPECIALTIES, INC. (3.58)
ALTUS TRAFFIC MANAGEMENT LLC (0.58)
BEAIRD DRILLING (5.97)
FRANK JR REINFORCEMENT LLC (0.32)
JUST GROOVING, LTD. (0.35)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.39)
Contract #01153028
Totals527480.770.00734431.5599.9