Monthly State Let Construction Report For San Antonio District As Of Sep 15, 2014 Page 4 Of 5

Last Update: Monday, September 15, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGUADALUPE
Highway IH 10
From FM 464
To SH 46
CSJ 0535-01-069
Proj ID CC 535-1-69
Work Type GRAD, BASE, STR, SURF, PAV'T MRK, SIGNS
 
1.636 3594953.05 39174.42 3660252.03 99.9
Work Order 09-05-13
Work Began 10-14-13
Work Completed  
Time Computed 09-21-13
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 190
Percent Time Used 105
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0535-01-069
RELMCO, INC. ( 15.31%)
THE LEVY COMPANY, L.P. (2.82%)
ROADWAY SPECIALTIES, INC.(2.66%)
FLASHER EQUIPMENT COMPANY(1.04%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.41%)
PRESIDIO CONTRACTING, LLC(1.16%)
Contract # 07133221
Totals 3594953.05 39174.42 3660252.03 99.9

CountyUVALDE
Highway FM 1796
From MEDINA COUNTY LINE
To FM 187
CSJ 0595-01-008
Proj ID STP 2013(034)
Work Type GRAD, BSE, SC, SURF
 
3.790 1993666.73 0.00 2049904.21 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-18-12
Work Began 12-03-12
Work Completed  
Time Computed 11-03-12
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 246
Percent Time Used 98
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0595-01-008
RELMCO, INC. ( 20.00%)
FLASHER EQUIPMENT COMPANY(2.78%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.90%)
RICE ENVIRONMENTAL SERVICES(0.64%)
Contract # 08123046
Totals 1993666.73 0.00 2049904.21 99.9

CountyFRIO
Highway FM 140
From 1.2 MI S OF BI 35E
To 3.4 MI S OF BI 35E
CSJ 0748-01-029
Proj ID STP 2014(017)
Work Type GR, STR, BASE
 
2.168 1394945.58 0.00 1175040.42 84.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-31-13
Work Began 12-12-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 97
Percent Time Used 76
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0748-01-029
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(4.74%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.65%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.60%)
FLASHER EQUIPMENT COMPANY(2.58%)
RICE ENVIRONMENTAL SERVICES(0.23%)
Contract # 09133016
Totals 1394945.58 0.00 1175040.42 84.2

CountyMEDINA
Highway FM 462
From 0.4 MI SOUTH OF CR 540
To 1.2 MI N OF FM 2200 WEST
CSJ 0848-01-037
Proj ID STP 2014(018)
Work Type REHAB & WIDEN NARROW ROADWAY
 
7.495 4927894.74 0.00 1336336.78 27.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-31-13
Work Began 02-10-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 341
Addl Days Granted 5
Working Days Charged 128
Percent Time Used 36
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0848-01-037
RICE ENVIRONMENTAL SERVICES(3.02%)
VOGES DRILLING CO. (0.91%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.54%)
FARR FOUNDATION, INC.(0.63%)
Contract # 09133035
Totals 4927894.74 0.00 1336336.78 27.1

CountyMEDINA
Highway FM 462
From 1.2 MI N OF FM 2200 WEST
To 3.3 MI. S. OF FM 2200 WEST
CSJ 0848-01-038
Proj ID STP 2013(035)
Work Type REHAB & WIDEN NARROW ROADWAY
 
4.463 3295349.15 0.00 3525876.80 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-09-12
Work Began 03-25-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 334
Addl Days Granted 0
Working Days Charged 329
Percent Time Used 98
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0848-01-038
FLASHER EQUIPMENT COMPANY(1.35%)
MURRAY CONSTRUCTION(1.04%)
M.V. HENKE ENTERPRISES, INC. (0.36%)
ROADWAY SPECIALTIES, INC.(3.13%)
RELMCO, INC. ( 16.35%)
VOGES DRILLING CO. (1.01%)
Contract # 09123035
Totals 3295349.15 0.00 3525876.80 99.9

CountyMEDINA
Highway FM 462
From 2.7 MILES SOUTH OF FM 2200 EAST
To MEDINA / FRIO COUNTY LINE
CSJ 0848-01-039
Proj ID STP 2012(035)
Work Type REHAB, WIDEN & ADD SHOULDERS
 
2.739 2072108.71 0.00 2402499.07 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-02-11
Work Began 02-01-12
Work Completed  
Time Computed 00-00-00
Contract Working Days 188
Addl Days Granted 107
Working Days Charged 299
Percent Time Used 101
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0848-01-039
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.78%)
FLASHER EQUIPMENT COMPANY(1.66%)
HIGHWAY TECHNOLOGIES, INC. (0.37%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.43%)
M.V. HENKE ENTERPRISES, INC. (0.64%)
RELMCO, INC. ( 38.76%)
W. W. FOUNDATION DRILLING, LTD.(2.54%)
MURRAY CONSTRUCTION(0.37%)
Contract # 09113222
Totals 2072108.71 0.00 2402499.07 99.9

CountyATASCOSA
Highway FM 476
From SP 242
To SH 97
CSJ 0853-02-030
Proj ID STP 2014(537)
Work Type TRAFFIC SIGNALS
 
1.156 740432.64 142616.96 214523.30 28.9
Work Order 05-05-14
Work Began 00-00-00
Work Completed  
Time Computed 08-03-14
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 11
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0853-02-030
JCD CONSTRUCTION, LLC(5.57%)
FLASHER EQUIPMENT COMPANY(1.66%)
UNITED PAVEMENT & MARKINGS, LLC(4.37%)
Contract # 03143204
Totals 740432.64 142616.96 214523.30 28.9

CountyCOMAL
Highway FM 306
From 0.4 MILES EAST OF FM 3424
To JACOBS CREEK PARK ROAD
CSJ 0857-01-028
Proj ID STP 2013(105)
Work Type GRD, BASE, SURF, AND PAV MARKS
 
2.584 963415.67 0.00 943619.62 97.9
CountyCOMAL
Highway FM 306
From 0.2 MI W OF CANYON DAM ACCESS ROAD
To 1.1 MI E OF PURGATORY ROAD
CSJ 1728-02-054
Proj ID STP 2013(105)
Work Type GRD, BASE, SURF, AND PAV MARKINGS
 
6.542 2545179.77 0.00 2266257.50 89.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-28-12
Work Began 12-14-12
Work Completed  
Time Computed 12-14-12
Contract Working Days 296
Addl Days Granted 0
Working Days Charged 217
Percent Time Used 73
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0857-01-028
E-Z BEL CONSTRUCTION, LLC(1.07%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.62%)
RELMCO, INC. (6.80%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(6.58%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.59%)
ROADWAY SPECIALTIES, INC.(2.67%)
FLASHER EQUIPMENT COMPANY(1.96%)
EGGEMEYER LAND CLEARING, LLC (1.96%)
Contract # 10123012
Totals 3508595.44 0.00 3209877.12 91.4

CountyBEXAR
Highway VA
From DISTRICTWIDE GUIDESIGNS FY14
To .
CSJ 0915-00-155
Proj ID STP 2014(562)
Work Type DISTRICTWIDE GUIDESIGNS FY14
 
0.001 998524.12 119585.63 119585.63 11.9
Work Order 05-20-14
Work Began 00-00-00
Work Completed  
Time Computed 07-19-14
Contract Working Days 208
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 2
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-155
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143205
Totals 998524.12 119585.63 119585.63 11.9

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2014
To .
CSJ 0915-00-156
Proj ID STP 2014(538)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 1299950.00 133473.58 143261.23 11.0
Work Order 05-01-14
Work Began 00-00-00
Work Completed  
Time Computed 07-30-14
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 7
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-156
JCD CONSTRUCTION, LLC(2.52%)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (1.23%)
UNITED PAVEMENT & MARKINGS, LLC(0.69%)
Contract # 03143206
Totals 1299950.00 133473.58 143261.23 11.0

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2012
To .
CSJ 0915-00-158
Proj ID STP 2012(311)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 1113075.30 0.00 1057064.65 94.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-12
Work Began 05-29-12
Work Completed  
Time Computed 06-10-12
Contract Working Days 300
Addl Days Granted 295
Working Days Charged 359
Percent Time Used 60
Contractor(s)
SAECO ELECTRIC & UTILITY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-158
HEARN CO.(1.01%)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (3.41%)
JCD CONSTRUCTION, LLC(3.84%)
JA&M CONSTRUCTION, LLC (1.07%)
Contract # 02123222
Totals 1113075.30 0.00 1057064.65 94.9

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2013
To .
CSJ 0915-00-160
Proj ID STP 2013(404)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.010 1179951.00 0.00 285053.40 24.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-19-13
Work Began 10-29-13
Work Completed  
Time Computed 07-18-13
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 138
Percent Time Used 43
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-160
JND CONSTRUCTION CONSULTANTS, LLC( 13.54%)
VACA UNDERGROUND UTILITIES INC (3.44%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.69%)
BEAIRD DRILLING(0.16%)
YORK & YORK FOUNDATION DRILLING, INC.(3.55%)
JCH CONSTRUCTION, INC. (0.05%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.03%)
Contract # 02133216
Totals 1179951.00 0.00 285053.40 24.7

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2012
To .
CSJ 0915-00-163
Proj ID STP 2012(312)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 942875.75 0.00 984638.97 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-12
Work Began 05-22-12
Work Completed  
Time Computed 06-10-12
Contract Working Days 300
Addl Days Granted 91
Working Days Charged 231
Percent Time Used 59
Contractor(s)
SAECO ELECTRIC & UTILITY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-163
HEARN CO.(6.17%)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (4.03%)
JA&M CONSTRUCTION, LLC (1.33%)
JCD CONSTRUCTION, LLC(2.82%)
Contract # 02123027
Totals 942875.75 0.00 984638.97 99.9

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2013
To .
CSJ 0915-00-164
Proj ID STP 2013(405)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.010 1218087.00 0.00 395611.09 32.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-19-13
Work Began 10-29-13
Work Completed  
Time Computed 07-18-13
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 125
Percent Time Used 39
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-164
JND CONSTRUCTION CONSULTANTS, LLC( 13.12%)
VACA UNDERGROUND UTILITIES INC (3.34%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.33%)
BEAIRD DRILLING(0.32%)
YORK & YORK FOUNDATION DRILLING, INC.(3.44%)
JCH CONSTRUCTION, INC. (0.17%)
Contract # 02133013
Totals 1218087.00 0.00 395611.09 32.6

CountyBEXAR
Highway CS
From IN SAN ANTONIO ON SOMERSET RD
To AT LEON CREEK
CSJ 0915-12-218
Proj ID BR 96(351)
Work Type REHABILITATE BRIDGE & APPROACHES
 
0.001 425301.50 0.00 177664.50 41.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 06-11-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 86
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-218
ABC EROSION CONTROL, INC.( 14.56%)
AMERICAN SIGNAL EQUIPMENT CO.(2.16%)
ALTUS TRAFFIC MANAGEMENT LLC (0.69%)
Contract # 03143007
Totals 425301.50 0.00 177664.50 41.7

CountyBEXAR
Highway MH
From WURZBACH PARKWAY ON NEW LOCATION
To FROM FM 2696 TO WEST AVE
CSJ 0915-12-224
Proj ID C 915-12-224
Work Type GRAD, STRS, BASE & SURF
 
1.499 24686408.64 0.00 23966324.67 99.9
CountyBEXAR
Highway MH
From ON EAST-WEST PKWY FROM LOCKHILL-SEL
To IH 35 IN SAN ANTONIO
CSJ 8000-15-007
Proj ID RW 8000-15-7
Work Type ACQUISITION OF ROW
 
0.001 1762476.01 0.00 1649241.93 93.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-07-10
Work Began 01-04-11
Work Completed  
Time Computed 00-00-00
Contract Working Days 273
Addl Days Granted 297
Working Days Charged 783
Percent Time Used 137
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-224
AUSTIN WOOD RECYCLING(0.19%)
BEAIRD DRILLING(2.68%)
COLLECTIVE CONTRACTING (6.40%)
CP REBAR AND PT INSTALLATION (1.01%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.45%)
F & W ELECTRICAL CONTRACTORS, INC. (3.47%)
FUQUAY, INC. (0.45%)
HIGHWAY TECHNOLOGIES, INC. (0.57%)
LONE STAR TRAFFIC SERVICE, INC.(0.10%)
SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.09%)
Z & L CONCRETE CONTRACTORS, INC. (1.19%)
TRI COUNTY SERVICES, INC.(1.19%)
MONTELONGO"S CONCRETE(0.62%)
ROADWAY SPECIALTIES, INC.(0.45%)
S BARRY SIGNATURE HOMES, INC.(1.08%)
CRIBLEY ENTERPRISES, INC.(0.03%)
GEOSOURCE, INC.(1.20%)
SCOTT DERR PAINTING CO, LLC(0.15%)
FLASHER EQUIPMENT COMPANY(0.48%)
DUSTROL, INC.(0.13%)
TEXAS STERLING CONSTRUCTION CO.( 14.73%)
ROADWAY SPECIALTIES, INC.(0.13%)
MUNDO VERDE IRRIGATION & LANDSCAPING, INC. (0.41%)
FUQUAY, INC. (0.49%)
F & W ELECTRICAL CONTRACTORS, INC. (1.41%)
S & S BRIDGE PAINTING, INC.(0.16%)
FLASHER EQUIPMENT COMPANY(0.00%)
Contract # 08103240
Totals 26448884.65 0.00 25615566.60 99.8

CountyBEXAR
Highway VA
From IH 35 AND VARIOUS LOCATIONS_IN
To BEXAR COUNTY
CSJ 0915-12-494
Proj ID STP 2012(531)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2893180.08 0.00 2246119.50 81.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-12
Work Began 09-10-12
Work Completed  
Time Computed 00-00-00
Contract Working Days 245
Addl Days Granted 0
Working Days Charged 380
Percent Time Used 155
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-494
F & W ELECTRICAL CONTRACTORS, INC. ( 17.08%)
INTERSTATE BARRICADES & MARKINGS, INC. (3.87%)
JCD CONSTRUCTION, LLC( 46.25%)
DAVID"S QUALITY CONCRETE WORK(6.43%)
Z & L CONCRETE CONTRACTORS, INC. (2.50%)
Contract # 05123211
Totals 2893180.08 0.00 2246119.50 81.2

CountyBEXAR
Highway VA
From VARIOUS LOCATIONS IN BEXAR COUNTY
To .
CSJ 0915-12-521
Proj ID STP 2014(623)
Work Type CONSTRUCT CURB RAMPS
 
0.001 1885777.35 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-20-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 243
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
F.D. CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-521
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143224
Totals 1885777.35 0.00 0.00 0.0

CountyFRIO
Highway CR
From CR 2515 (BIEDIGER) @ SAN MIGUEL CK
To .
CSJ 0915-18-028
Proj ID BR 2012(237)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.001 235336.60 0.00 227542.38 96.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-14-14
Work Began 04-02-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 100
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-18-028
ALTUS TRAFFIC MANAGEMENT LLC (0.74%)
VOGES DRILLING CO. (9.36%)
RICE ENVIRONMENTAL SERVICES( 18.67%)
JUST GROOVING, LTD.(0.33%)
Contract # 01143011
Totals 235336.60 0.00 227542.38 96.6

CountyUVALDE
Highway PW
From IN GARNER STATE PARK
To .
CSJ 0915-20-015
Proj ID C 915-20-15
Work Type GRAD, BASE, SURF
 
0.001 891460.49 69496.84 148230.29 16.6
Work Order 04-15-14
Work Began 00-00-00
Work Completed  
Time Computed 06-14-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 54
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-20-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143030
Totals 891460.49 69496.84 148230.29 16.6

page 1 | page 2 | page 3 | page 4 | page 5