Monthly State Let Construction Report For San Antonio District As Of May 11, 2015 Page 4 Of 6

Last Update: Monday, May 11, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCOMAL
Highway US 281
From RIVER CROSSING
To BLANCO CO LINE
CSJ 0253-03-043
Proj ID PTF 2012(530)
Work Type GR, STRS, BASE & SURF
 
5.640 22368285.39 63287.28 23030658.49 99.9
Work Order 07-12-12
Work Began 02-11-13
Work Completed  
Time Computed 01-08-13
Contract Working Days 655
Addl Days Granted 20
Working Days Charged 577
Percent Time Used 85
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0253-03-043
COWBELL TRAFFIC SERVICES, INC. (0.08%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.18%)
EGGEMEYER LAND CLEARING, LLC (1.11%)
HIGHWAY TECHNOLOGIES, INC. (1.07%)
JUST GROOVING, LTD.(0.04%)
THE LEVY COMPANY, L.P. (1.74%)
MCKINNEY DRILLING COMPANY(0.49%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.41%)
NORTH TEXAS REBAR, LLC (0.13%)
ROADWAY SPECIALTIES, INC.(1.10%)
SCOTT DERR PAINTING CO, LLC(0.04%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.69%)
CATO DRILLING COMPANY(0.06%)
CHAPMAN ROCK EXCAVATION, LLC (0.28%)
FLASHER EQUIPMENT COMPANY(1.07%)
Contract # 05123002
Totals 22368285.39 63287.28 23030658.49 99.9

CountyCOMAL
Highway US 281
From AT SH 46
To .
CSJ 0253-03-068
Proj ID C 253-3-68
Work Type CONSTRUCT TURNAROUNDS
 
0.303 3132254.40 89522.09 2218659.49 70.8
Work Order 01-09-14
Work Began 01-27-14
Work Completed  
Time Computed 01-27-14
Contract Working Days 138
Addl Days Granted 170
Working Days Charged 292
Percent Time Used 94
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0253-03-068
ALTUS TRAFFIC MANAGEMENT LLC (0.37%)
DOUBLE S PAVING, INC.(3.70%)
DUSTROL, INC.(0.44%)
FLASHER EQUIPMENT COMPANY(0.99%)
FUQUAY, INC. (0.53%)
GALO EQUIPMENT & CONSTRUCTION, LLC (0.71%)
GEOSOURCE, INC.(1.02%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(7.05%)
ROADWAY SPECIALTIES, INC.(1.58%)
SCOTT DERR PAINTING CO (0.21%)
CURTIS CONCRETE PUMPING(1.18%)
DRILL TECH DRILLING & SHORING, INC.(4.69%)
Contract # 10133225
Totals 3132254.40 89522.09 2218659.49 70.8

CountyBEXAR
Highway SS 537
From IH 410
To US 281
CSJ 0253-04-148
Proj ID NH 2015(370)
Work Type SURF, PAV'T MRKNGS
 
1.241 1046040.29 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-13-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 54
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0253-04-148
E-Z BEL CONSTRUCTION, LLC(4.26%)
INTERSTATE BARRICADES & MARKINGS, INC. (3.20%)
Contract # 12143017
Totals 1046040.29 0.00 0.00 0.0

CountyBEXAR
Highway SP 536
From BUSTILLOS DRIVE
To BONNER AVENUE
CSJ 0253-06-035
Proj ID C 253-6-35
Work Type WIDEN FOR CLTL, BIKE LANES & SDWLKS
 
0.702 2509754.04 179146.67 1049153.90 41.8
CountyBEXAR
Highway SP 536
From BUSTILLOS DRIVE
To BONNER AVENUE
CSJ 0253-06-036
Proj ID RW 253-6-36
Work Type ROW UTL. ADJ.
 
0.844 177538.00 0.00 77966.80 43.9
Work Order 08-19-13
Work Began 06-02-14
Work Completed  
Time Computed 09-04-13
Contract Working Days 272
Addl Days Granted 0
Working Days Charged 203
Percent Time Used 74
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0253-06-035
THE LEVY COMPANY, L.P. (2.01%)
INTERSTATE BARRICADES & MARKINGS, INC. (3.01%)
J.D. RAMMING PAVING CO./AUSTIN MATERIALS LLC ( 32.04%)
Contract # 06133008
Totals 2687292.04 179146.67 1127120.70 41.9

CountyFRIO
Highway US 57
From FM 140
To IH 35 WB FRONTAGE ROAD
CSJ 0276-07-029
Proj ID STP 1402(014)
Work Type GRADE, BASE, SC, SURF, PAVMT MRK
 
13.066 5946630.34 1279744.18 3209078.36 53.9
Work Order 10-17-14
Work Began 12-15-14
Work Completed  
Time Computed 11-02-14
Contract Working Days 108
Addl Days Granted 0
Working Days Charged 66
Percent Time Used 61
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0276-07-029
FLASHER EQUIPMENT COMPANY(0.29%)
A BROTHERS MILLING, LLC(3.32%)
INTERSTATE BARRICADES & MARKINGS, INC. (3.18%)
CLARK CONSTRUCTION OF TEXAS, INC.(9.70%)
PAVETEX ENGINEERING & TESTING, INC.(0.80%)
Contract # 07143050
Totals 5946630.34 1279744.18 3209078.36 53.9

CountyKERR
Highway SH 16
From KERR/GILLESPIE COUNTY LINE
To IH 10
CSJ 0291-02-034
Proj ID STP 2013(718)
Work Type GR, BSE, SURF, PAVT MRK
 
5.647 2985558.94 94445.36 1013203.17 33.9
Work Order 08-15-14
Work Began 10-09-14
Work Completed  
Time Computed 10-09-14
Contract Working Days 239
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 41
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0291-02-034
FLASHER EQUIPMENT COMPANY(3.92%)
AUSTIN WOOD RECYCLING(3.89%)
HUNTER INDUSTRIES, LTD.( 22.66%)
ROADWAY SPECIALTIES, INC.(5.01%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.30%)
THE LEVY COMPANY, L.P. (0.15%)
Contract # 06143049
Totals 2985558.94 94445.36 1013203.17 33.9

CountyKERR
Highway SH 16
From SH 173
To 0.2 MI. SOUTH OF RIVER HILLS BLVD.
CSJ 0291-03-057
Proj ID STP 2014(016)
Work Type GRAD, BASE, EMBANK, STR, SURF & PAV MRK
 
1.540 1866572.26 58661.77 893744.17 50.2
CountyKERR
Highway SH 16
From FROM SPUR 98
To SH 173
CSJ 0291-03-061
Proj ID STP 2014(016)
Work Type OVERLAY AND PAVEMENT MARKINGS
 
0.803 637966.90 0.00 585524.22 91.7
Work Order 12-05-13
Work Began 03-05-14
Work Completed  
Time Computed 03-05-14
Contract Working Days 164
Addl Days Granted 0
Working Days Charged 220
Percent Time Used 134
Contractor(s)
ZIMMERMAN CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0291-03-057
J.D. RAMMING PAVING CO., LTD.( 43.64%)
ROADWAY SPECIALTIES, INC.(9.17%)
E-Z BEL CONSTRUCTION, LLC(4.38%)
D. I. J. CONSTRUCTION, INC.(2.19%)
FLASHER EQUIPMENT COMPANY(0.55%)
CHEROKEE SERVICES(0.20%)
PENHALL COMPANY (AUSTIN) (0.00%)
CHEROKEE BRIDGE AND ROAD, LTD. (5.78%)
AARON CONCRETE CONTRACTORS, L.P. (1.20%)
SAECO ELECTRIC & UTILITY, LTD. (0.03%)
PERFORMANCE EQUIPMENT SERVICE(1.86%)
Contract # 09133025
Totals 2504539.16 58661.77 1479268.39 60.8

CountyBANDERA
Highway SH 16
From KERR COUNTY LINE
To FM 2107
CSJ 0291-04-024
Proj ID STP 2015(933)HES
Work Type GR, BASE, SURF & PAVMT MARKINGS
 
5.670 2553976.46 0.00 0.00 0.0
CountyBANDERA
Highway SH 16
From KERR COUNTY LINE
To 0.6 MI S OF MESA VERDE ROAD
CSJ 0291-04-025
Proj ID STP 2015(934)HES
Work Type GRS, BSE, SURF, STR, MBGF
 
2.700 530989.38 0.00 0.00 0.0
CountyBANDERA
Highway SH 16
From 0.2 MI WEST OF WINANS CROSSING
To 2.8 MI EAST OF FM 470
CSJ 0291-05-046
Proj ID STP 2015(935)HES
Work Type STR, MBFG, GR, BASE, SURF & PVMT_MRK
 
6.030 1760096.08 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 442
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0291-04-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153203
Totals 4845061.92 0.00 0.00 0.0

CountyATASCOSA
Highway SH 97
From 05037
To IH 37
CSJ 0328-03-032
Proj ID STP 1502(165)
Work Type GRADE, BASE, SURF, PAVMT MRK
 
6.678 11864971.99 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 286
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0328-03-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153206
Totals 11864971.99 0.00 0.00 0.0

CountyATASCOSA
Highway SH 97
From BROWN AVENUE
To FM 3510
CSJ 0328-04-042
Proj ID STP 1402(015)
Work Type GRAD, BSE, SURF, PAVMT MRK
 
2.020 5025776.24 0.00 2460625.45 48.9
CountyATASCOSA
Highway SH 97
From SH 16
To BROWN AVENUE
CSJ 0328-05-043
Proj ID STP 1402(015)
Work Type GRAD, BSE, SURF, PAVMT MRK
 
0.122 304963.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-30-14
Work Began 12-08-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 66
Percent Time Used 28
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0328-04-042
E-Z BEL CONSTRUCTION, LLC(0.54%)
D&S TEXAS ICON CONSTRUCTION, LLC (0.04%)
FLASHER EQUIPMENT COMPANY(1.71%)
Contract # 07143244
Totals 5330739.44 0.00 2460625.45 46.1

CountyATASCOSA
Highway SH 97
From 0.6 MILES EAST OF BURNETT AVE
To SH 16
CSJ 0328-05-037
Proj ID STP 1502(166)
Work Type GRADE, BASE, SC, SURF, PAVMT MRK
 
9.837 17494208.24 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 339
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0328-05-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153007
Totals 17494208.24 0.00 0.00 0.0

CountyATASCOSA
Highway SH 97
From MCMULLEN/ATASCOSA C/L
To 2.0 MI N. OF MCMULLEN/ATASCOSA C/L
CSJ 0328-06-028
Proj ID STP 1402(065)
Work Type GRADE, BASE, SC, SURF, PVMT MRK
 
2.559 3835534.67 384068.28 1190414.86 31.0
CountyMCMULLEN
Highway SH 97
From LASALLE/MCMULLEN C/L
To ATASCOSA/MCMULLEN C/L
CSJ 0328-07-016
Proj ID STP 1402(065)
Work Type GRADE, BASE, SC, SURF, PAVMT MRK
 
10.340 14856569.69 16743.90 75494.50 0.5
Work Order 10-17-14
Work Began 11-10-14
Work Completed  
Time Computed 11-10-14
Contract Working Days 331
Addl Days Granted 0
Working Days Charged 77
Percent Time Used 23
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0328-06-028
N-LINE TRAFFIC MAINTENANCE, L.P. (0.49%)
LONE STAR EROSION CONTROL(3.08%)
F & W ELECTRICAL CONTRACTORS, INC. (0.22%)
FLASHER EQUIPMENT COMPANY(1.61%)
LONE STAR PAVING ( 37.44%)
Contract # 08143004
Totals 18692104.36 400812.18 1265909.36 6.7

CountyUVALDE
Highway SH 127
From 0.2 MI E OF FRIO RIVER
To 0.2 MI W OF FRIO RIVER
CSJ 0369-01-033
Proj ID BR 2013(716)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.397 2838089.10 157104.45 1173137.62 41.3
Work Order 07-22-14
Work Began 11-06-14
Work Completed  
Time Computed 08-21-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 147
Percent Time Used 77
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0369-01-033
VOGES DRILLING CO. (3.38%)
FLASHER EQUIPMENT COMPANY(1.01%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.46%)
O & S TRAFFIC SUPPLIES (0.05%)
Contract # 06143239
Totals 2838089.10 157104.45 1173137.62 41.3

CountyMCMULLEN
Highway SH 16
From ATASCOSA/MCMULLEN COUNTY LINE
To SH 72 EAST
CSJ 0517-02-040
Proj ID STP 2014(894)
Work Type GRADE, BASE, SURF, PAVMT MRK
 
13.063 6787433.55 8082.82 379681.11 5.5
Work Order 09-30-14
Work Began 02-05-15
Work Completed  
Time Computed 12-29-14
Contract Working Days 227
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 11
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0517-02-040
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(5.13%)
D. I. J. CONSTRUCTION, INC.(3.74%)
RELMCO, INC. (2.69%)
THE LEVY COMPANY, L.P. (1.47%)
M.V. HENKE ENTERPRISES, INC. (0.41%)
ROADWAY SPECIALTIES, INC.(1.21%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.43%)
Contract # 07143008
Totals 6787433.55 8082.82 379681.11 5.5

CountyBEXAR
Highway LP 13
From SPUR 122 (S. PRESA)
To IH 37
CSJ 0521-01-045
Proj ID STP 2013(853)MM
Work Type GRADE, BASE, SDWLK
 
1.856 602797.20 13763.46 615424.17 99.9
CountyBEXAR
Highway LP 13
From SPUR 117
To IH 10
CSJ 0521-01-046
Proj ID STP 2013(852)MM
Work Type GRADE, BASE, SDWLK
 
4.736 973688.75 1260.68 896393.84 92.0
CountyBEXAR
Highway LP 13
From SPUR 117
To IH 10
CSJ 0521-01-047
Proj ID RW 521-1-47
Work Type ADJUSTMENT OF UTILITIES
 
4.947 55128.50 0.00 27698.00 50.2
CountyBEXAR
Highway LP 13
From SPUR 122 (S. PRESA)
To IH 37
CSJ 0521-01-048
Proj ID RW 521-1-48
Work Type ADJUSTMENT OF UTILITIES
 
2.043 62163.50 0.00 59333.00 95.4
Work Order 10-07-13
Work Began 01-07-14
Work Completed  
Time Computed 01-05-14
Contract Working Days 167
Addl Days Granted 15
Working Days Charged 186
Percent Time Used 102
Contractor(s)
F.D. CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0521-01-045
AZTEC FENCE & ORNAMENTAL IRON(5.04%)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (1.42%)
FUQUAY, INC. (3.56%)
MISTEK SPRINKLER AND LANDSCAPING (1.07%)
GILBERT"S UTILITY & CONCRETE WORK, INC.(5.82%)
BEST IN TOWN, INC. (4.61%)
Contract # 07133208
Totals 1693777.95 15024.14 1598849.01 94.5

CountyBEXAR
Highway IH 410
From MEDINA BASE RD.
To 0.6 MILES EAST OF IH 35
CSJ 0521-05-139
Proj ID NH 2014(854)
Work Type SLOPE REPAIR, OVERLAY, MBGF, PAV MK
 
4.778 6711711.71 0.00 0.00 0.0
Work Order 08-20-14
Work Began 00-00-00
Work Completed  
Time Computed 10-20-14
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0521-05-139
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143244
Totals 6711711.71 0.00 0.00 0.0

CountyBEXAR
Highway IH 410
From IH 37
To IH 10
CSJ 0521-06-135
Proj ID STP 2015(290)HES
Work Type RESURFACING, TEXTURIZE SHOULDERS
 
7.716 5210847.57 0.00 0.00 0.0
Work Order 01-02-15
Work Began 00-00-00
Work Completed  
Time Computed 03-03-15
Contract Working Days 67
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0521-06-135
ROADWAY SPECIALTIES, INC.(1.79%)
WEST TEXAS RUMBLE STRIP(0.29%)
CHEROKEE SERVICES(2.27%)
RELMCO, INC. (1.07%)
FLASHER EQUIPMENT COMPANY(3.43%)
CLAUDIA SERNA DBA SERNA"S TRUCKING (1.22%)
Contract # 11143215
Totals 5210847.57 0.00 0.00 0.0

CountyGUADALUPE
Highway IH 10
From FM 464
To SH 46
CSJ 0535-01-069
Proj ID CC 535-1-69
Work Type GRAD, BASE, STR, SURF, PAV'T MRK, SIGNS
 
1.636 3594953.05 0.00 3682862.72 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-05-13
Work Began 10-14-13
Work Completed 02-24-15
Time Computed 09-21-13
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 190
Percent Time Used 105
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0535-01-069
RELMCO, INC. ( 15.31%)
THE LEVY COMPANY, L.P. (2.82%)
ROADWAY SPECIALTIES, INC.(2.66%)
FLASHER EQUIPMENT COMPANY(1.04%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.41%)
PRESIDIO CONTRACTING, LLC(1.16%)
Contract # 07133221
Totals 3594953.05 0.00 3682862.72 100.0

CountyGUADALUPE
Highway IH 10
From SH 46
To SH 123 B
CSJ 0535-01-072
Proj ID C 535-1-72
Work Type GRAD, BSE, STR, SURF, SIGN, PAV'T MRK
 
2.027 29174029.32 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 782
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0535-01-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153003
Totals 29174029.32 0.00 0.00 0.0

CountyUVALDE
Highway FM 1796
From MEDINA COUNTY LINE
To FM 187
CSJ 0595-01-008
Proj ID STP 2013(034)
Work Type GRAD, BSE, SC, SURF
 
3.790 1993666.73 0.00 2049904.21 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-18-12
Work Began 12-03-12
Work Completed 06-12-14
Time Computed 11-03-12
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 246
Percent Time Used 98
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0595-01-008
RELMCO, INC. ( 20.00%)
FLASHER EQUIPMENT COMPANY(2.78%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.90%)
RICE ENVIRONMENTAL SERVICES(0.64%)
Contract # 08123046
Totals 1993666.73 0.00 2049904.21 100.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6