Monthly State Let Construction Report For San Antonio District As Of Sep 21, 2017 Page 5 Of 6

Last Update: Friday, September 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-00-178
Proj IDSTP 1702(555)
Work TypeCONSTRUCT CURB RAMPS
 
0.0013495290.120.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days335
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
F. D. CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-178
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173237
Totals3495290.120.000.000.0

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2017
To.
CSJ0915-00-180
Proj IDSTP 2017(565)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011383517.973087.000.2
Work Order03-10-17
Work Began00-00-00
Work Completed
Time Computed04-09-17
Contract Working Days315
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-180
M & M STRIPING & POWER WASHING, LLC (1.37)
Contract #02173213
Totals1383517.970.003087.000.2

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-186
Proj IDSTP 1702(556)
Work TypeTRAFFIC SIGNAL REHAB/UPGRADE
 
0.0012664496.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days319
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-186
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173035
Totals2664496.900.000.000.0

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2017
To.
CSJ0915-00-204
Proj IDSTP 2017(894)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011349187.00274050.1020.3
Work Order05-09-17
Work Began07-18-17
Work Completed
Time Computed07-03-17
Contract Working Days320
Addl Days Granted0
Working Days Charged30
Percent Time Used9
Contractor(s)
D&G ENERGY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-204
L & R FOUNDATION DRILLING, INC. (1.03)
M & M STRIPING & POWER WASHING, LLC (4.15)
Contract #04173003
Totals1349187.00174390.10274050.1020.3

CountyKENDALL
HighwayCR
FromMILL DAM ROAD, 0.6 MI S OF SH 27
ToAT GUADALUPE RIVER
CSJ0915-11-031
Proj IDBR 1602(228)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1581522927.911296581.9185.1
Work Order03-02-17
Work Began03-16-17
Work Completed
Time Computed02-04-17
Contract Working Days268
Addl Days Granted0
Working Days Charged135
Percent Time Used50
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-11-031
W. W. FOUNDATION DRILLING, LTD. (8.05)
(USE 07366)J.R. RAMON & SONS, INC (6.73)
ENVIRONMENTAL SAFETY SERVICES, INC. (5.52)
AUSTIN WOOD RECYCLING (2.40)
LONE STAR PAVING (1.33)
FLASHER EQUIPMENT COMPANY (0.94)
FUQUAY, INC. (0.70)
PENHALL COMPANY (0.41)
Contract #01173209
Totals1522927.91153644.111296581.9185.1

CountyBEXAR
HighwayCR
FromGROSS LANE AT MEDINA RIVER
To.
CSJ0915-12-439
Proj IDBR 2007(638)
Work TypeREHABILITATE BRIDGE AND APPROACHES
 
0.001527480.77734431.5599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-06-15
Work Began04-13-15
Work Completed
Time Computed04-13-15
Contract Working Days69
Addl Days Granted91
Working Days Charged160
Percent Time Used100
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-439
MCL CONTRACTING, LLC (0.88)
DOUBLE S PAVING, INC. (2.26)
FLASHER EQUIPMENT COMPANY (1.81)
LONE STAR EROSION CONTROL (1.51)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.71)
ROADWAY SPECIALTIES, INC. (3.58)
ALTUS TRAFFIC MANAGEMENT LLC (0.58)
BEAIRD DRILLING (5.97)
FRANK JR REINFORCEMENT LLC (0.32)
JUST GROOVING, LTD. (0.35)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.39)
Contract #01153028
Totals527480.770.00734431.5599.9

CountyBEXAR
HighwayVA
FromVARIOUS BRIDGES IN BEXAR COUNY
To.
CSJ0915-12-551
Proj IDBR 1502(471)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
0.0011723801.411906439.6199.9
Work Order12-08-15
Work Began02-22-16
Work Completed
Time Computed02-06-16
Contract Working Days221
Addl Days Granted26
Working Days Charged250
Percent Time Used101
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-551
RICE ENVIRONMENTAL SERVICES (3.67)
FLASHER EQUIPMENT COMPANY (3.58)
RAMMING PAVING COMPANY (22.61)
CHEROKEE SERVICES (4.59)
Contract #10153005
Totals1723801.4110864.701906439.6199.9

CountyBEXAR
HighwayVA
FromIN SAN ANTONIO ON US 281, LOOP 345
ToFM 78 AND FM 1516 CORRIDORS
CSJ0915-12-555
Proj IDSTP 2016(870)TP
Work TypeGRD, BSE, SIDEWALKS, SIGN, PAVT MRK
 
0.0011771321.261033858.8458.3
CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-12-559
Proj IDSTP 1602(380)
Work TypeSIDEWALK
 
0.0013515369.101647582.0446.8
Work Order10-06-16
Work Began11-10-16
Work Completed
Time Computed11-05-16
Contract Working Days309
Addl Days Granted0
Working Days Charged184
Percent Time Used59
Contractor(s)
J3 COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-555
ROADWAY SPECIALTIES, INC. (2.66)
AUSTIN MATERIALS, LLC (1.91)
JARCO TRANSPORT, LLC (1.76)
LONE STAR EROSION CONTROL (4.43)
SAECO ELECTRIC & UTILITY, LTD. (0.20)
WEBB & BEXAR CONSTRUCTION, LLC. (8.59)
M & M STRIPING & POWER WASHING, LLC (0.11)
FLASHER EQUIPMENT COMPANY (0.36)
Contract #08163211
Totals5286690.36225194.172681440.8850.7

CountyBEXAR
HighwayCS
FromON INGRAM RD
ToAT RICHLAND HILLS
CSJ0915-12-570
Proj IDSTP 1702(042)HES
Work TypeINSTALL TRAFFIC SIGNAL
 
0.200188897.500.000.0
CountyBEXAR
HighwayFM 1976
FromAT MIDCROWN
To.
CSJ1890-01-048
Proj IDSTP 1702(043)HES
Work TypeTRAFFIC SIGNALS & ILLUMINATION
 
0.200217051.500.000.0
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed07-14-17
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-570
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173209
Totals405949.000.000.000.0

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-12-591
Proj IDNH 1702(678)
Work TypeLANDSCAPE DEVELOPMENT
 
0.001510193.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days95
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-591
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173010
Totals510193.000.000.000.0

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-12-592
Proj IDNH 1702(679)
Work TypeLANDSCAPE DEVELOPMENT
 
0.001682419.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days82
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-592
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173230
Totals682419.000.000.000.0

CountyMEDINA
HighwayCR
From4.1 MI SW OF FM 471
To.
CSJ0915-45-052
Proj IDBR 1502(643)
Work TypeREPLACE BRIDGE & APPROACHES
 
0.001422407.380.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-23-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-45-052
12-1 HIGHWAY AND ENVIRONMENTAL SERVICES, LLC (4.83)
BEAIRD DRILLING (6.07)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.70)
AZA BARRICADES (0.66)
Contract #07173238
Totals422407.380.000.000.0

CountyKENDALL
HighwayRM 474
FromFM 473
ToKEMMER TRAIL
CSJ1042-01-032
Proj IDSTP 2013(720)
Work TypeGRAD, BSE, SURF, PAVMT MARKINGS
 
6.6734456842.620.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days261
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1042-01-032
RELMCO, INC. (23.70)
GEOSOURCE, INC. (3.41)
D.I.J. CONSTRUCTION, INC (2.59)
FLASHER EQUIPMENT COMPANY (1.89)
LONE STAR EROSION CONTROL (1.58)
Contract #06173027
Totals4456842.620.000.000.0

CountyMEDINA
HighwayPR 37
FromSH 16
ToBANDERA C/L
CSJ1066-02-017
Proj IDSTP 2018(078)HESG
Work TypeGRAD, SURF, BASE, PAVEMENT MARKINGS
 
4.2861099115.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days153
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1066-02-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09173010
Totals1099115.250.000.000.0

CountyCOMAL
HighwayFM 1101
FromSH 46
To0.5 MI N OF FM 306
CSJ1272-01-016
Proj IDSTP 2014(564)
Work TypeBASE, GR, STR, SIDEWALK
 
2.7976154722.503734866.7960.6
Work Order06-02-14
Work Began01-16-17
Work Completed
Time Computed12-01-14
Contract Working Days354
Addl Days Granted28
Working Days Charged161
Percent Time Used42
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1272-01-016
ENVIRONMENTAL SAFETY SERVICES, INC. (3.55)
E-Z BEL CONSTRUCTION, LLC (2.42)
INTERSTATE CONCRETE & STEEL SERVICES INCORPORATED (39.55)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.21)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.71)
AUSTIN WOOD RECYCLING (0.32)
INTERSTATE BARRICADES & MARKINGS, INC. (1.80)
Contract #04143002
Totals6154722.50276439.463734866.7960.6

CountyBEXAR
HighwayFM 1516
FromFM 78
ToFM 1976
CSJ1477-01-040
Proj IDSTP 2017(798)MM
Work TypeGRD, BSE, STR, SURF, PAV'T MRK
 
0.7625733862.950.000.0
CountyBEXAR
HighwayFM 1516
FromFM 78
ToFM 1976
CSJ1477-01-041
Proj IDSTP 1502(217)
Work TypeACQUISITION, RELOCATION ASSISTANCE
 
0.7621655042.650.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-26-17
Work Began00-00-00
Work Completed
Time Computed07-28-17
Contract Working Days586
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1477-01-040
DU-MOR ENTERPRISES_INC. (0.39)
FUQUAY, INC. (0.58)
AUSTIN WOOD RECYCLING (0.17)
LONE STAR PAVING (13.50)
E-Z BEL CONSTRUCTION, LLC (5.71)
FLASHER EQUIPMENT COMPANY (1.44)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.15)
ROADWAY SPECIALTIES, INC. (0.71)
Contract #03173203
Totals7388905.600.000.000.0

CountyCOMAL
HighwayFM 306
FromHOFFMANN LANE
To0.5 MI NORTH OF HUNTER ROAD
CSJ1728-02-058
Proj IDSTP 1502(615)MM
Work TypeGRAD, STR, BASE, SURF
 
3.2327936418.828172848.3399.9
Work Order10-21-15
Work Began12-01-15
Work Completed
Time Computed01-19-16
Contract Working Days364
Addl Days Granted0
Working Days Charged421
Percent Time Used115
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1728-02-058
E-Z BEL CONSTRUCTION, LLC (2.34)
CATO ELECTRIC COMPANY (0.00)
HEARN CO. (0.19)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.64)
FLASHER EQUIPMENT COMPANY (0.27)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.41)
R K STEPHENS CONSTRUCTION, LLC (5.07)
TRP CONSTRUCTION GROUP, LLC (1.39)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (3.04)
AUSTIN WOOD RECYCLING (0.61)
SCOTT DERR PAINTING CO, LLC (0.06)
Contract #08153016
Totals7936418.826575.608172848.3399.9

CountyCOMAL
HighwayFM 306
FromRIVER CHASE WAY
ToHOFFMANN LANE
CSJ1728-02-059
Proj IDSTP 1602(300)MM
Work TypeGRAD, STR, BASE, SURF
 
1.3275996508.483544844.6559.1
Work Order09-06-16
Work Began10-06-16
Work Completed
Time Computed10-06-16
Contract Working Days364
Addl Days Granted0
Working Days Charged210
Percent Time Used57
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1728-02-059
OSCAR ORDUNO, INC. (10.30)
SOUTH TEXAS PAINTING COMPANY (0.32)
F & W ELECTRICAL CONTRACTORS, INC. (3.51)
FLASHER EQUIPMENT COMPANY (1.00)
ENVIRONMENTAL SAFETY SERVICES, INC. (7.37)
EGGEMEYER LAND CLEARING, LLC (0.55)
TEXAS LANDSCAPE & IRRIGATION (1.03)
FUQUAY, INC. (1.39)
GK CONSTRUCTION, LLC (0.19)
CENTURY ASPHALT MATERIALS (0.39)
Contract #07163211
Totals5996508.48158515.673544844.6559.1

CountyMCMULLEN
HighwayFM 791
From2.19 MILES EAST OF SH 16
To2.76 MILES EAST OF SH 16
CSJ1739-04-010
Proj IDCC 1739-4-10
Work TypeGRAD, BASE, STRUCTURE & SURF
 
0.5684956163.240.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days176
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1739-04-010
EGGEMEYER LAND CLEARING, LLC (0.40)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.41)
PRIMATE CONSTRUCTION, INC. (0.13)
AREA WIDE PROTECTIVE, INC. (0.37)
ROADWAY SPECIALTIES, INC. (2.17)
D. I. J. CONSTRUCTION, INC. (1.09)
Contract #07173045
Totals4956163.240.000.000.0

CountyBEXAR
HighwayFM 1957
FromLOOP 1604
ToFM 3487
CSJ2104-02-032
Proj IDSTP 2017(037)HES
Work TypeGR, BASE, SURF
 
4.885979020.40984294.9299.9
Work Order10-21-16
Work Began01-02-17
Work Completed
Time Computed11-20-16
Contract Working Days101
Addl Days Granted0
Working Days Charged105
Percent Time Used103
Contractor(s)
TROPICAL CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2104-02-032
FLASHER EQUIPMENT COMPANY (21.69)
ELITE CURB & CONCRETE, LLC (31.71)
S&S CONSTRUCTION CONTRACTORS (0.43)
Contract #09163206
Totals979020.4021288.30984294.9299.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6