Monthly State Let Construction Report For San Antonio District As Of Aug 10, 2015 Page 5 Of 7

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMCMULLEN
Highway SH 16
From ATASCOSA/MCMULLEN COUNTY LINE
To SH 72 EAST
CSJ 0517-02-040
Proj ID STP 2014(894)
Work Type GRADE, BASE, SURF, PAVMT MRK
 
13.063 6787433.55 988254.15 2762164.28 40.6
Work Order 09-30-14
Work Began 02-05-15
Work Completed  
Time Computed 12-29-14
Contract Working Days 227
Addl Days Granted 0
Working Days Charged 74
Percent Time Used 32
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0517-02-040
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(5.13%)
D. I. J. CONSTRUCTION, INC.(3.74%)
RELMCO, INC. (2.69%)
THE LEVY COMPANY, L.P. (1.47%)
M.V. HENKE ENTERPRISES, INC. (0.41%)
ROADWAY SPECIALTIES, INC.(1.21%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.43%)
Contract # 07143008
Totals 6787433.55 988254.15 2762164.28 40.6

CountyBEXAR
Highway LP 13
From SPUR 122 (S. PRESA)
To IH 37
CSJ 0521-01-045
Proj ID STP 2013(853)MM
Work Type GRADE, BASE, SDWLK
 
1.856 602797.20 3131.40 618825.57 99.9
CountyBEXAR
Highway LP 13
From SPUR 117
To IH 10
CSJ 0521-01-046
Proj ID STP 2013(852)MM
Work Type GRADE, BASE, SDWLK
 
4.736 973688.75 0.00 896843.84 92.1
CountyBEXAR
Highway LP 13
From SPUR 117
To IH 10
CSJ 0521-01-047
Proj ID RW 521-1-47
Work Type ADJUSTMENT OF UTILITIES
 
4.947 55128.50 0.00 27698.00 50.2
CountyBEXAR
Highway LP 13
From SPUR 122 (S. PRESA)
To IH 37
CSJ 0521-01-048
Proj ID RW 521-1-48
Work Type ADJUSTMENT OF UTILITIES
 
2.043 62163.50 0.00 59333.00 95.4
Work Order 10-07-13
Work Began 01-07-14
Work Completed  
Time Computed 01-05-14
Contract Working Days 167
Addl Days Granted 15
Working Days Charged 186
Percent Time Used 102
Contractor(s)
F.D. CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0521-01-045
AZTEC FENCE & ORNAMENTAL IRON(5.04%)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (1.42%)
FUQUAY, INC. (3.56%)
MISTEK SPRINKLER AND LANDSCAPING (1.07%)
GILBERT"S UTILITY & CONCRETE WORK, INC.(5.82%)
BEST IN TOWN, INC. (4.61%)
Contract # 07133208
Totals 1693777.95 3131.40 1602700.41 94.8

CountyBEXAR
Highway IH 410
From SH 151
To INGRAM RD.
CSJ 0521-04-274
Proj ID C 521-4-274
Work Type GRAD, STR, BASE, SURF, PAV MARKINGS
 
2.716 81778634.04 0.00 0.00 0.0
CountyBEXAR
Highway IH 410
From SH 151
To INGRAM RD.
CSJ 0521-04-276
Proj ID ROW 521-4-276
Work Type ROW UTILITY ADJUSTMENTS
 
2.716 103972.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-31-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 760
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0521-04-274
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153001
Totals 81882606.04 0.00 0.00 0.0

CountyBEXAR
Highway IH 410
From MEDINA BASE RD.
To 0.6 MILES EAST OF IH 35
CSJ 0521-05-139
Proj ID NH 2014(854)
Work Type SLOPE REPAIR, OVERLAY, MBGF, PAV MK
 
4.778 6711711.71 487780.53 487780.53 7.2
Work Order 08-20-14
Work Began 00-00-00
Work Completed  
Time Computed 10-20-14
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 17
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0521-05-139
FLASHER EQUIPMENT COMPANY(1.91%)
CLAUDIA SERNA DBA SERNA"S TRUCKING (0.96%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.75%)
PRIMATE CONSTRUCTION, INC. (1.44%)
Contract # 06143244
Totals 6711711.71 487780.53 487780.53 7.2

CountyBEXAR
Highway IH 410
From IH 37
To IH 10
CSJ 0521-06-135
Proj ID STP 2015(290)HES
Work Type RESURFACING, TEXTURIZE SHOULDERS
 
7.716 5210847.57 1013753.37 1013753.37 19.4
Work Order 01-02-15
Work Began 00-00-00
Work Completed  
Time Computed 03-03-15
Contract Working Days 67
Addl Days Granted 6
Working Days Charged 19
Percent Time Used 26
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0521-06-135
ROADWAY SPECIALTIES, INC.(1.79%)
WEST TEXAS RUMBLE STRIP(0.29%)
CHEROKEE SERVICES(2.27%)
RELMCO, INC. (1.07%)
FLASHER EQUIPMENT COMPANY(3.43%)
CLAUDIA SERNA DBA SERNA"S TRUCKING (1.22%)
Contract # 11143215
Totals 5210847.57 1013753.37 1013753.37 19.4

CountyGUADALUPE
Highway IH 10
From FM 464
To SH 46
CSJ 0535-01-069
Proj ID CC 535-1-69
Work Type GRAD, BASE, STR, SURF, PAV'T MRK, SIGNS
 
1.636 3594953.05 0.00 3693054.42 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-05-13
Work Began 10-14-13
Work Completed 02-24-15
Time Computed 09-21-13
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 190
Percent Time Used 105
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0535-01-069
RELMCO, INC. ( 15.31%)
THE LEVY COMPANY, L.P. (2.82%)
ROADWAY SPECIALTIES, INC.(2.66%)
FLASHER EQUIPMENT COMPANY(1.04%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.41%)
PRESIDIO CONTRACTING, LLC(1.16%)
Contract # 07133221
Totals 3594953.05 0.00 3693054.42 100.0

CountyGUADALUPE
Highway IH 10
From SH 46
To SH 123 B
CSJ 0535-01-072
Proj ID C 535-1-72
Work Type GRAD, BSE, STR, SURF, SIGN, PAV'T MRK
 
2.027 29174029.32 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-30-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 782
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0535-01-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153003
Totals 29174029.32 0.00 0.00 0.0

CountyUVALDE
Highway FM 1796
From MEDINA COUNTY LINE
To FM 187
CSJ 0595-01-008
Proj ID STP 2013(034)
Work Type GRAD, BSE, SC, SURF
 
3.790 1993666.73 0.00 2049904.21 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-18-12
Work Began 12-03-12
Work Completed 06-12-14
Time Computed 11-03-12
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 246
Percent Time Used 98
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0595-01-008
RELMCO, INC. ( 20.00%)
FLASHER EQUIPMENT COMPANY(2.78%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.90%)
RICE ENVIRONMENTAL SERVICES(0.64%)
Contract # 08123046
Totals 1993666.73 0.00 2049904.21 100.0

CountyATASCOSA
Highway SH 16
From 0.937 MI S OF FM 3350
To 0.951 MI N OF CR 306
CSJ 0613-02-057
Proj ID STP 1502(276)HES
Work Type CENTERLINE TEXTURING
 
4.000 35128.40 0.00 0.00 0.0
CountyATASCOSA
Highway SH 16
From SH 97
To 0.2 MI SOUTH OF SP 282
CSJ 0613-02-058
Proj ID STP 1502(275)
Work Type GRADING, HMA, SURF, PAV MRK
 
7.773 13453085.63 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 146
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0613-02-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153207
Totals 13488214.03 0.00 0.00 0.0

CountyFRIO
Highway FM 140
From 1.2 MI S OF BI 35E
To 3.4 MI S OF BI 35E
CSJ 0748-01-029
Proj ID STP 2014(017)
Work Type GR, STR, BASE
 
2.168 1394945.58 0.00 1429523.51 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-31-13
Work Began 12-12-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 127
Addl Days Granted 3
Working Days Charged 124
Percent Time Used 95
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0748-01-029
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(4.74%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.65%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.60%)
FLASHER EQUIPMENT COMPANY(2.58%)
RICE ENVIRONMENTAL SERVICES(0.23%)
Contract # 09133016
Totals 1394945.58 0.00 1429523.51 99.9

CountyBANDERA
Highway FM 470
From RM 187
To FM 462
CSJ 0792-04-045
Proj ID STP 2015(269)HES
Work Type INSTALL ADV WARNING SIGN, ETC
 
16.786 622941.65 -71429.52 449451.68 72.1
CountyBANDERA
Highway FM 470
From RM 187
To 0.1 MI. WEST OF FM 462
CSJ 0792-04-046
Proj ID STP 2015(270)
Work Type SEAL COAT AND PAVEMENT MARKINGS
 
16.826 771246.35 680974.06 714994.06 92.7
Work Order 11-14-14
Work Began 00-00-00
Work Completed  
Time Computed 01-13-15
Contract Working Days 55
Addl Days Granted 1
Working Days Charged 45
Percent Time Used 80
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0792-04-045
FLASHER EQUIPMENT COMPANY( 17.41%)
THE LEVY COMPANY, L.P. (3.24%)
R.P.V. CONSTRUCTION(3.44%)
Contract # 10143223
Totals 1394188.00 609544.54 1164445.74 83.5

CountyMEDINA
Highway FM 462
From 0.4 MI SOUTH OF CR 540
To 1.2 MI N OF FM 2200 WEST
CSJ 0848-01-037
Proj ID STP 2014(018)
Work Type REHAB & WIDEN NARROW ROADWAY
 
7.495 4927894.74 186001.99 3711689.07 75.3
Work Order 10-31-13
Work Began 02-10-14
Work Completed  
Time Computed 12-30-13
Contract Working Days 341
Addl Days Granted 7
Working Days Charged 330
Percent Time Used 94
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0848-01-037
RICE ENVIRONMENTAL SERVICES(3.02%)
VOGES DRILLING CO. (0.91%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.54%)
FARR FOUNDATION, INC.(0.63%)
Contract # 09133035
Totals 4927894.74 186001.99 3711689.07 75.3

CountyMEDINA
Highway FM 462
From 1.2 MI N OF FM 2200 WEST
To 3.3 MI. S. OF FM 2200 WEST
CSJ 0848-01-038
Proj ID STP 2013(035)
Work Type REHAB & WIDEN NARROW ROADWAY
 
4.463 3295349.15 0.00 3665047.39 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-09-12
Work Began 03-25-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 334
Addl Days Granted 30
Working Days Charged 355
Percent Time Used 97
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0848-01-038
FLASHER EQUIPMENT COMPANY(1.35%)
MURRAY CONSTRUCTION(1.04%)
M.V. HENKE ENTERPRISES, INC. (0.36%)
ROADWAY SPECIALTIES, INC.(3.13%)
RELMCO, INC. ( 16.35%)
VOGES DRILLING CO. (1.01%)
Contract # 09123035
Totals 3295349.15 0.00 3665047.39 99.9

CountyBEXAR
Highway FM 471
From LP 1604
To FM 3487
CSJ 0849-01-047
Proj ID STP 2015(937)HES
Work Type GR, BASE, SURF
 
2.539 485383.69 27627.47 27627.47 5.6
CountyBEXAR
Highway FM 471
From LP 1604
To 0.1 MI NE OF LOST LANE
CSJ 0849-01-048
Proj ID STP 2015(936)
Work Type SURF, PAV'T MRKNGS
 
5.093 1265815.54 21076.13 21076.13 1.6
CountyBEXAR
Highway FM 471
From LP 1604
To 0.1 MI NE OF LOST LANE
CSJ 0849-01-050
Proj ID ROW 849-1-50
Work Type ROW ACQUISITION
 
5.093 21735.00 0.00 0.00 0.0
Work Order 06-19-15
Work Began 00-00-00
Work Completed  
Time Computed 08-19-15
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 6
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0849-01-047
S.A. CONCEPTS CONSTRUCTION ( 24.65%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.27%)
INTERSTATE BARRICADES & MARKINGS, INC. (5.51%)
Contract # 04153008
Totals 1772934.23 48703.60 48703.60 2.7

CountyATASCOSA
Highway FM 476
From SP 242
To SH 97
CSJ 0853-02-030
Proj ID STP 2014(537)
Work Type TRAFFIC SIGNALS
 
1.156 740432.64 0.00 744430.46 99.9
Work Order 05-05-14
Work Began 08-18-14
Work Completed  
Time Computed 08-03-14
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 179
Percent Time Used 99
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0853-02-030
JCD CONSTRUCTION, LLC(5.57%)
FLASHER EQUIPMENT COMPANY(1.66%)
UNITED PAVEMENT & MARKINGS, LLC(4.37%)
BADGER DAYLIGHTING CORP. (1.01%)
INTERSTATE BARRICADES & MARKINGS, INC. (4.27%)
Contract # 03143204
Totals 740432.64 0.00 744430.46 99.9

CountyCOMAL
Highway FM 306
From 0.4 MILES EAST OF FM 3424
To JACOBS CREEK PARK ROAD
CSJ 0857-01-028
Proj ID STP 2013(105)
Work Type GRD, BASE, SURF, AND PAV MARKS
 
2.584 963415.67 0.00 943619.62 100.0
CountyCOMAL
Highway FM 306
From 0.2 MI W OF CANYON DAM ACCESS ROAD
To 1.1 MI E OF PURGATORY ROAD
CSJ 1728-02-054
Proj ID STP 2013(105)
Work Type GRD, BASE, SURF, AND PAV MARKINGS
 
6.542 2545179.77 0.00 2266257.50 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-28-12
Work Began 12-14-12
Work Completed 06-20-14
Time Computed 12-14-12
Contract Working Days 296
Addl Days Granted 0
Working Days Charged 217
Percent Time Used 73
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0857-01-028
E-Z BEL CONSTRUCTION, LLC(1.07%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.62%)
RELMCO, INC. (6.80%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(6.58%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.59%)
ROADWAY SPECIALTIES, INC.(2.67%)
FLASHER EQUIPMENT COMPANY(1.96%)
EGGEMEYER LAND CLEARING, LLC (1.96%)
Contract # 10123012
Totals 3508595.44 0.00 3209877.12 100.0

CountyBEXAR
Highway VA
From DISTRICTWIDE GUIDESIGNS FY14
To .
CSJ 0915-00-155
Proj ID STP 2014(562)
Work Type DISTRICTWIDE GUIDESIGNS FY14
 
0.001 998524.12 0.00 586883.33 58.7
Work Order 05-20-14
Work Began 07-20-14
Work Completed  
Time Computed 07-21-14
Contract Working Days 208
Addl Days Granted 0
Working Days Charged 199
Percent Time Used 95
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-155
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143205
Totals 998524.12 0.00 586883.33 58.7

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2014
To .
CSJ 0915-00-156
Proj ID STP 2014(538)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 1299950.00 34542.99 1103338.26 85.4
Work Order 05-01-14
Work Began 08-08-14
Work Completed  
Time Computed 07-30-14
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 56
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-156
JCD CONSTRUCTION, LLC(2.52%)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (1.23%)
UNITED PAVEMENT & MARKINGS, LLC(0.69%)
Contract # 03143206
Totals 1299950.00 34542.99 1103338.26 85.4

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2012
To .
CSJ 0915-00-158
Proj ID STP 2012(311)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 1113075.30 0.00 1057064.65 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-12
Work Began 05-29-12
Work Completed 05-07-14
Time Computed 06-10-12
Contract Working Days 300
Addl Days Granted 295
Working Days Charged 359
Percent Time Used 60
Contractor(s)
SAECO ELECTRIC & UTILITY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-158
HEARN CO.(1.01%)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (3.41%)
JCD CONSTRUCTION, LLC(3.84%)
JA&M CONSTRUCTION, LLC (1.07%)
Contract # 02123222
Totals 1113075.30 0.00 1057064.65 100.0

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2013
To .
CSJ 0915-00-160
Proj ID STP 2013(404)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.010 1179951.00 0.00 380577.24 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-19-13
Work Began 10-29-13
Work Completed 02-10-15
Time Computed 07-18-13
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 56
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-160
JND CONSTRUCTION CONSULTANTS, LLC( 13.54%)
VACA UNDERGROUND UTILITIES INC (3.44%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.69%)
BEAIRD DRILLING(0.16%)
YORK & YORK FOUNDATION DRILLING, INC.(3.55%)
JCH CONSTRUCTION, INC. (0.05%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.03%)
Contract # 02133216
Totals 1179951.00 0.00 380577.24 100.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7