Monthly State Let Construction Report For San Antonio District As Of Nov 9, 2016 Page 5 Of 5

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBEXAR
Highway VA
From IN SAN ANTONIO ON US 281, LOOP 345
To FM 78 AND FM 1516 CORRIDORS
CSJ 0915-12-555
Proj ID STP 2016(870)TP
Work Type GRD, BSE, SIDEWALKS, SIGN, PAVT MRK
 
0.001 1771321.26 0.00 0.00 0.0
CountyBEXAR
Highway VA
From VARIOUS LOCATIONS IN BEXAR COUNTY
To .
CSJ 0915-12-559
Proj ID STP 1602(380)
Work Type SIDEWALK
 
0.001 3515369.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-06-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 309
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J3 COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-555
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163211
Totals 5286690.36 0.00 0.00 0.0

CountyKERR
Highway VA
From WITHIN KERR WILDLIFE MGMT AREA
To .
CSJ 0915-15-096
Proj ID C 915-15-96
Work Type GRADE, BASE AND SURFACE
 
0.001 321149.13 9869.25 330387.28 99.9
Work Order 10-21-15
Work Began 00-00-00
Work Completed  
Time Computed 01-19-16
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 89
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-15-096
FUQUAY, INC. (8.29%)
FLASHER EQUIPMENT COMPANY(1.58%)
Contract # 09153220
Totals 321149.13 9869.25 330387.28 99.9

CountyGUADALUPE
Highway VA
From IN THE CITY OF SEGUIN
To ALONG WALNUT BRANCH
CSJ 0915-46-039
Proj ID STP 2011(245)TE
Work Type GRAD, BASE, SURF, STR, SIGN
 
0.001 2524283.53 887.32 2247567.46 92.7
Work Order 07-25-14
Work Began 10-06-14
Work Completed  
Time Computed 10-06-14
Contract Working Days 206
Addl Days Granted 31
Working Days Charged 356
Percent Time Used 150
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0915-46-039
ROADWAY SPECIALTIES, INC.(3.90%)
S & S BRIDGE PAINTING, INC.(0.11%)
DOUBLE S PAVING, INC.(0.32%)
BACKYARD RENOVATIONS (2.79%)
EGGEMEYER LAND CLEARING, LLC (3.75%)
FUQUAY, INC. (1.43%)
TRP CONSTRUCTION GROUP, LLC(0.99%)
FLASHER EQUIPMENT COMPANY(0.34%)
W. W. FOUNDATION DRILLING, LTD.(1.50%)
GK CONSTRUCTION, LLC (0.06%)
GALO EQUIPMENT & CONSTRUCTION, LLC (2.47%)
WEBB & BEXAR CONSTRUCTION, LLC.(0.49%)
LONE STAR EROSION CONTROL(0.80%)
FIRST CALL SITE SOLUTIONS, LLC (0.14%)
2 J RESOURCES COMPANY(0.30%)
SAECO ELECTRIC & UTILITY, LTD. (0.51%)
Contract # 06143017
Totals 2524283.53 887.32 2247567.46 92.7

CountyMCMULLEN
Highway VA
From JAMES E DAUGHTEY WMA
To .
CSJ 0915-51-011
Proj ID C 915-51-11
Work Type GRADE, BASE AND SURFACE
 
0.001 454942.12 0.00 319876.97 73.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-15-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 136
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-51-011
FLASHER EQUIPMENT COMPANY(1.51%)
Contract # 01163032
Totals 454942.12 0.00 319876.97 73.9

CountyATASCOSA
Highway FM 536
From AT FM 1784
To .
CSJ 1009-03-014
Proj ID STP 1602(128)
Work Type GRAD, BSE, SURF, SIGNALS, PAVMT MRK
 
0.369 364903.95 0.00 315498.85 86.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-30-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 64
Addl Days Granted 1
Working Days Charged 61
Percent Time Used 93
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1009-03-014
FLASHER EQUIPMENT COMPANY(7.76%)
THE LEVY COMPANY, L.P. ( 15.45%)
Contract # 05163029
Totals 364903.95 0.00 315498.85 86.4

CountyWILSON
Highway FM 541
From US 181
To ATASCOSA / WILSON COUNTY LINE
CSJ 1011-01-035
Proj ID STP 2015(371)
Work Type GRAD, BSE, SURF, PAVMT MRK
 
14.363 5563471.45 40678.63 5552778.89 99.8
Work Order 02-13-15
Work Began 04-20-15
Work Completed  
Time Computed 04-14-15
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 143
Percent Time Used 102
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1011-01-035
FLASHER EQUIPMENT COMPANY(1.74%)
A BROTHERS MILLING, LLC(2.20%)
MURRAY CONSTRUCTION(0.36%)
LONE STAR EROSION CONTROL(1.30%)
CUATRO T CONSTRUCTION, INC.(0.00%)
Contract # 12143030
Totals 5563471.45 40678.63 5552778.89 99.8

CountyCOMAL
Highway FM 1101
From SH 46
To 0.5 MI N OF FM 306
CSJ 1272-01-016
Proj ID STP 2014(564)
Work Type BASE, GR, STR, SIDEWALK
 
2.797 6154722.50 0.00 131067.80 2.1
Work Order 06-02-14
Work Began 00-00-00
Work Completed  
Time Computed 11-29-14
Contract Working Days 354
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1272-01-016
ENVIRONMENTAL SAFETY SERVICES, INC.(3.55%)
E-Z BEL CONSTRUCTION, LLC(2.42%)
INTERSTATE CONCRETE & STEEL SERVICES INCORPORATED( 39.55%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.21%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.71%)
Contract # 04143002
Totals 6154722.50 0.00 131067.80 2.1

CountyCOMAL
Highway FM 306
From HOFFMANN LANE
To 0.5 MI NORTH OF HUNTER ROAD
CSJ 1728-02-058
Proj ID STP 1502(615)MM
Work Type GRAD, STR, BASE, SURF
 
3.232 7936418.82 326310.29 4720934.41 59.4
Work Order 10-21-15
Work Began 12-01-15
Work Completed  
Time Computed 01-19-16
Contract Working Days 364
Addl Days Granted 0
Working Days Charged 234
Percent Time Used 64
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1728-02-058
E-Z BEL CONSTRUCTION, LLC(2.34%)
CATO ELECTRIC COMPANY(0.00%)
HEARN CO.(0.19%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.64%)
FLASHER EQUIPMENT COMPANY(0.27%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.41%)
R K STEPHENS CONSTRUCTION, LLC (5.07%)
TRP CONSTRUCTION GROUP, LLC(1.39%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.04%)
AUSTIN WOOD RECYCLING(0.61%)
Contract # 08153016
Totals 7936418.82 326310.29 4720934.41 59.4

CountyCOMAL
Highway FM 306
From RIVER CHASE WAY
To HOFFMANN LANE
CSJ 1728-02-059
Proj ID STP 1602(300)MM
Work Type GRAD, STR, BASE, SURF
 
1.327 5996508.48 0.00 338340.02 5.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-06-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 364
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 4
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1728-02-059
OSCAR ORDUNO, INC. ( 10.30%)
SOUTH TEXAS PAINTING COMPANY (0.32%)
F & W ELECTRICAL CONTRACTORS, INC. (3.51%)
FLASHER EQUIPMENT COMPANY(1.00%)
ENVIRONMENTAL SAFETY SERVICES, INC.(7.37%)
EGGEMEYER LAND CLEARING, LLC (0.55%)
TEXAS LANDSCAPE & IRRIGATION (1.03%)
Contract # 07163211
Totals 5996508.48 0.00 338340.02 5.6

CountyBANDERA
Highway FM 1283
From SH 16
To PR 37
CSJ 1730-01-040
Proj ID STP 2017(036)HES
Work Type INSTALL CHEVRONS, PAVEMENT MARKINGS
 
9.216 496196.56 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-25-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1730-01-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09163007
Totals 496196.56 0.00 0.00 0.0

CountyBEXAR
Highway FM 1957
From LOOP 1604
To FM 3487
CSJ 2104-02-032
Proj ID STP 2017(037)HES
Work Type GR, BASE, SURF
 
4.885 979020.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-21-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TROPICAL CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2104-02-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09163206
Totals 979020.40 0.00 0.00 0.0

CountyBEXAR
Highway SP 53
From EDWARD XIMENES AVENUE
To IH 10
CSJ 2230-02-004
Proj ID STP 2013(714)MM
Work Type GR, STRS, BASE, SURF, ILLUM & TRAF
 
1.532 6984125.75 152631.55 4169873.99 59.7
CountyBEXAR
Highway SP 53
From EDWARD XIMENES AVENUE
To IH 10
CSJ 2230-02-006
Proj ID RW 2230-2-6
Work Type ROW ACQ. & UTILITIES
 
1.512 313245.19 46908.30 267884.34 85.5
Work Order 10-27-14
Work Began 00-00-00
Work Completed  
Time Computed 04-25-15
Contract Working Days 534
Addl Days Granted 0
Working Days Charged 343
Percent Time Used 64
Contractor(s)
SMC CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2230-02-004
SAECO ELECTRIC & UTILITY, LTD. (7.04%)
PESADO CONSTRUCTION COMPANY(1.67%)
FLASHER EQUIPMENT COMPANY(1.40%)
PANTHER CREEK TRANSPORTATION, INC. (1.78%)
PIPE WHOLESALERS OF TEXAS, INC.(0.00%)
BADECO, INC(2.38%)
A BROTHERS MILLING, LLC(1.48%)
ROADWAY SPECIALTIES, INC.(2.12%)
HILL COUNTRY BRIDGE, INC ( 16.13%)
EGGEMEYER LAND CLEARING, LLC (0.92%)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC.(3.05%)
VOGES DRILLING CO. (1.13%)
S & S BRIDGE PAINTING, INC.(0.03%)
GK CONSTRUCTION, LLC (0.22%)
DISTRIBUTION CONSTRUCTION, LLC (2.23%)
DC CIVIL CONSTRUCTION LLC(2.01%)
WILLIAMS CONSTRUCTION(0.30%)
R. W. JONES & SONS, INC. (0.96%)
Contract # 05143005
Totals 7297370.94 199539.85 4437758.33 60.8

CountyBEXAR
Highway SL 1604
From FM 1957 - POTRANCO RD
To FM 471 -CULEBRA RD
CSJ 2452-01-056
Proj ID NH 1602(312)
Work Type GR, STRS, BASE, SURF & SIGN
 
4.101 57936595.26 0.00 0.00 0.0
CountyBEXAR
Highway SL 1604
From FM 1957 - POTRANCO RD
To FM 471 -CULEBRA RD
CSJ 2452-01-061
Proj ID ROW 2452-1-61
Work Type ACQUISITION
 
4.101 4564354.92 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-16-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 751
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 2452-01-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163204
Totals 62500950.18 0.00 0.00 0.0

CountyBEXAR
Highway SL 1604
From US 90
To FM 1957 - POTRANCO RD
CSJ 2452-01-059
Proj ID NH 1602(550)
Work Type GR, STRS, BASE, SURF & SIGN
 
3.818 63342516.54 0.00 0.00 0.0
CountyBEXAR
Highway SL 1604
From US 90
To FM 1957 - POTRANCO RD
CSJ 2452-01-063
Proj ID ROW 2452-1-63
Work Type UTILITY
 
3.818 795897.92 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-26-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 986
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2452-01-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163001
Totals 64138414.46 0.00 0.00 0.0

CountyGUADALUPE
Highway FM 3009
From IH 35
To FM 78
CSJ 3107-02-034
Proj ID STP 1502(472)MM
Work Type GRD, BSE, SIDEWALKS
 
3.145 3240269.50 173749.42 2517322.04 77.6
Work Order 08-26-15
Work Began 00-00-00
Work Completed  
Time Computed 12-24-15
Contract Working Days 123
Addl Days Granted 34
Working Days Charged 119
Percent Time Used 75
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3107-02-034
INTERSTATE BARRICADES & MARKINGS, INC. (0.65%)
F & W ELECTRICAL CONTRACTORS, INC. (2.02%)
ENVIRONMENTAL SAFETY SERVICES, INC.( 13.82%)
LONE STAR PAVING (1.41%)
DELGADO"S CONSTRUCTION (1.58%)
THOMAS TURF GRASS(4.53%)
JE CASEY, LLC(0.63%)
Contract # 07153034
Totals 3240269.50 173749.42 2517322.04 77.6

CountyBEXAR
Highway MH
From WURZBACH PARKWAY ON NEW LOCATION
To WEST AVE TO JONES MALTSBERGER
CSJ 8000-15-015
Proj ID NH 2011(837)
Work Type GRAD, STRS, BASE & SURF
 
1.679 48594617.47 338099.36 50608025.49 99.9
CountyBEXAR
Highway MH
From WURZBACH PARKWAY ON NEW LOCATION
To WEST AVE TO JONES MALTSBERGER
CSJ 8000-15-017
Proj ID RW 8000-15-17
Work Type ROW UTL. ADJ.
 
1.145 839700.13 0.00 788731.58 93.9
Work Order 06-14-11
Work Began 07-06-11
Work Completed  
Time Computed 07-05-11
Contract Working Days 1,160
Addl Days Granted 59
Working Days Charged 1,208
Percent Time Used 99
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 8000-15-015
ID/GUERRA L.P. (5.86%)
BOSQUEZ ELECTRICAL, LLC. (3.79%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.12%)
INDUS CONSTRUCTION, L.P. (6.69%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.51%)
ROADWAY SPECIALTIES, INC.(0.64%)
CLARK CONSTRUCTION OF TEXAS, INC.(1.45%)
EGGEMEYER LAND CLEARING, LLC (0.17%)
SCOTT DERR PAINTING CO, LLC(0.00%)
BEST IN TOWN, INC. (1.49%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.37%)
SAN ANTONIO TELEPHONE COMPANY INC. (0.02%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.57%)
F & W ELECTRICAL CONTRACTORS, INC. (2.66%)
RICE ENVIRONMENTAL SERVICES(1.36%)
Z & L CONCRETE CONTRACTORS, INC. (0.35%)
GUERRA UNDERGROUND, LLC(0.88%)
HEARN CO.(0.18%)
CPAVE, INC.(0.06%)
Contract # 04113004
Totals 49434317.60 338099.36 51396757.07 99.9

page 1 | page 2 | page 3 | page 4 | page 5