Monthly State Let Construction Report For San Antonio District As Of Jul 14, 2017 Page 5 Of 6

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
HighwayCR
FromGROSS LANE AT MEDINA RIVER
To.
CSJ0915-12-439
Proj IDBR 2007(638)
Work TypeREHABILITATE BRIDGE AND APPROACHES
 
0.001527480.77734431.5599.9
Work Order03-06-15
Work Began04-13-15
Work Completed
Time Computed04-13-15
Contract Working Days69
Addl Days Granted91
Working Days Charged160
Percent Time Used100
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-439
MCL CONTRACTING, LLC (0.88)
DOUBLE S PAVING, INC. (2.26)
FLASHER EQUIPMENT COMPANY (1.81)
LONE STAR EROSION CONTROL (1.51)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.71)
ROADWAY SPECIALTIES, INC. (3.58)
ALTUS TRAFFIC MANAGEMENT LLC (0.58)
BEAIRD DRILLING (5.97)
FRANK JR REINFORCEMENT LLC (0.32)
JUST GROOVING, LTD. (0.35)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.39)
Contract #01153028
Totals527480.770.00734431.5599.9

CountyBEXAR
HighwayVA
FromVARIOUS BRIDGES IN BEXAR COUNY
To.
CSJ0915-12-551
Proj IDBR 1502(471)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
0.0011723801.411889206.0199.9
Work Order12-08-15
Work Began02-22-16
Work Completed
Time Computed02-06-16
Contract Working Days221
Addl Days Granted26
Working Days Charged250
Percent Time Used101
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-551
RICE ENVIRONMENTAL SERVICES (3.67)
FLASHER EQUIPMENT COMPANY (3.58)
RAMMING PAVING COMPANY (22.61)
CHEROKEE SERVICES (4.59)
Contract #10153005
Totals1723801.4144836.401889206.0199.9

CountyBEXAR
HighwayVA
FromIN SAN ANTONIO ON US 281, LOOP 345
ToFM 78 AND FM 1516 CORRIDORS
CSJ0915-12-555
Proj IDSTP 2016(870)TP
Work TypeGRD, BSE, SIDEWALKS, SIGN, PAVT MRK
 
0.0011771321.26828993.3646.8
CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-12-559
Proj IDSTP 1602(380)
Work TypeSIDEWALK
 
0.0013515369.101397186.1039.7
Work Order10-06-16
Work Began11-10-16
Work Completed
Time Computed11-05-16
Contract Working Days309
Addl Days Granted0
Working Days Charged147
Percent Time Used47
Contractor(s)
J3 COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-555
ROADWAY SPECIALTIES, INC. (2.66)
AUSTIN MATERIALS, LLC (1.91)
JARCO TRANSPORT, LLC (1.76)
LONE STAR EROSION CONTROL (4.43)
SAECO ELECTRIC & UTILITY, LTD. (0.20)
WEBB & BEXAR CONSTRUCTION, LLC. (8.59)
M & M STRIPING & POWER WASHING, LLC (0.11)
FLASHER EQUIPMENT COMPANY (0.36)
Contract #08163211
Totals5286690.36320196.322226179.4642.1

CountyBEXAR
HighwayCS
FromON INGRAM RD
ToAT RICHLAND HILLS
CSJ0915-12-570
Proj IDSTP 1702(042)HES
Work TypeINSTALL TRAFFIC SIGNAL
 
0.200188897.500.000.0
CountyBEXAR
HighwayFM 1976
FromAT MIDCROWN
To.
CSJ1890-01-048
Proj IDSTP 1702(043)HES
Work TypeTRAFFIC SIGNALS & ILLUMINATION
 
0.200217051.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-570
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173209
Totals405949.000.000.000.0

CountyMEDINA
HighwayCR
From4.1 MI SW OF FM 471
To.
CSJ0915-45-052
Proj IDBR 1502(643)
Work TypeREPLACE BRIDGE & APPROACHES
 
0.001422407.380.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-45-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173238
Totals422407.380.000.000.0

CountyKENDALL
HighwayRM 474
FromFM 473
ToKEMMER TRAIL
CSJ1042-01-032
Proj IDSTP 2013(720)
Work TypeGRAD, BSE, SURF, PAVMT MARKINGS
 
6.6734456842.620.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days261
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1042-01-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173027
Totals4456842.620.000.000.0

CountyCOMAL
HighwayFM 1101
FromSH 46
To0.5 MI N OF FM 306
CSJ1272-01-016
Proj IDSTP 2014(564)
Work TypeBASE, GR, STR, SIDEWALK
 
2.7976154722.502912522.3747.3
Work Order06-02-14
Work Began01-16-17
Work Completed
Time Computed12-01-14
Contract Working Days354
Addl Days Granted28
Working Days Charged119
Percent Time Used31
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1272-01-016
ENVIRONMENTAL SAFETY SERVICES, INC. (3.55)
E-Z BEL CONSTRUCTION, LLC (2.42)
INTERSTATE CONCRETE & STEEL SERVICES INCORPORATED (39.55)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.21)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.71)
AUSTIN WOOD RECYCLING (0.32)
INTERSTATE BARRICADES & MARKINGS, INC. (1.80)
Contract #04143002
Totals6154722.50393431.962912522.3747.3

CountyBEXAR
HighwayFM 1516
FromFM 78
ToFM 1976
CSJ1477-01-040
Proj IDSTP 2017(798)MM
Work TypeGRD, BSE, STR, SURF, PAV'T MRK
 
0.7625733862.950.000.0
CountyBEXAR
HighwayFM 1516
FromFM 78
ToFM 1976
CSJ1477-01-041
Proj IDSTP 1502(217)
Work TypeACQUISITION, RELOCATION ASSISTANCE
 
0.7621655042.650.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-26-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days586
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1477-01-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173203
Totals7388905.600.000.000.0

CountyCOMAL
HighwayFM 306
FromHOFFMANN LANE
To0.5 MI NORTH OF HUNTER ROAD
CSJ1728-02-058
Proj IDSTP 1502(615)MM
Work TypeGRAD, STR, BASE, SURF
 
3.2327936418.828016293.9099.9
Work Order10-21-15
Work Began12-01-15
Work Completed
Time Computed01-19-16
Contract Working Days364
Addl Days Granted0
Working Days Charged402
Percent Time Used110
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1728-02-058
E-Z BEL CONSTRUCTION, LLC (2.34)
CATO ELECTRIC COMPANY (0.00)
HEARN CO. (0.19)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.64)
FLASHER EQUIPMENT COMPANY (0.27)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.41)
R K STEPHENS CONSTRUCTION, LLC (5.07)
TRP CONSTRUCTION GROUP, LLC (1.39)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (3.04)
AUSTIN WOOD RECYCLING (0.61)
SCOTT DERR PAINTING CO, LLC (0.06)
Contract #08153016
Totals7936418.8287192.068016293.9099.9

CountyCOMAL
HighwayFM 306
FromRIVER CHASE WAY
ToHOFFMANN LANE
CSJ1728-02-059
Proj IDSTP 1602(300)MM
Work TypeGRAD, STR, BASE, SURF
 
1.3275996508.482844995.3847.4
Work Order09-06-16
Work Began10-06-16
Work Completed
Time Computed10-06-16
Contract Working Days364
Addl Days Granted0
Working Days Charged182
Percent Time Used50
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1728-02-059
OSCAR ORDUNO, INC. (10.30)
SOUTH TEXAS PAINTING COMPANY (0.32)
F & W ELECTRICAL CONTRACTORS, INC. (3.51)
FLASHER EQUIPMENT COMPANY (1.00)
ENVIRONMENTAL SAFETY SERVICES, INC. (7.37)
EGGEMEYER LAND CLEARING, LLC (0.55)
TEXAS LANDSCAPE & IRRIGATION (1.03)
FUQUAY, INC. (1.39)
GK CONSTRUCTION, LLC (0.19)
CENTURY ASPHALT MATERIALS (0.39)
Contract #07163211
Totals5996508.48362344.812844995.3847.4

CountyBANDERA
HighwayFM 1283
FromSH 16
ToPR 37
CSJ1730-01-040
Proj IDSTP 2017(036)HES
Work TypeINSTALL CHEVRONS, PAVEMENT MARKINGS
 
9.216496196.56475358.8495.8
Work Order10-25-16
Work Began03-01-17
Work Completed
Time Computed11-24-16
Contract Working Days60
Addl Days Granted0
Working Days Charged60
Percent Time Used100
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1730-01-040
THE LEVY COMPANY, L.P. (62.22)
Contract #09163007
Totals496196.560.00475358.8495.8

CountyMCMULLEN
HighwayFM 791
From2.19 MILES EAST OF SH 16
To2.76 MILES EAST OF SH 16
CSJ1739-04-010
Proj IDCC 1739-4-10
Work TypeGRAD, BASE, STRUCTURE & SURF
 
0.5684956163.240.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days176
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1739-04-010
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173045
Totals4956163.240.000.000.0

CountyBEXAR
HighwayFM 1957
FromLOOP 1604
ToFM 3487
CSJ2104-02-032
Proj IDSTP 2017(037)HES
Work TypeGR, BASE, SURF
 
4.885979020.40897365.7991.9
Work Order10-21-16
Work Began01-02-17
Work Completed
Time Computed11-20-16
Contract Working Days101
Addl Days Granted0
Working Days Charged105
Percent Time Used103
Contractor(s)
TROPICAL CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2104-02-032
FLASHER EQUIPMENT COMPANY (21.69)
ELITE CURB & CONCRETE, LLC (31.71)
S&S CONSTRUCTION CONTRACTORS (0.43)
Contract #09163206
Totals979020.4086160.50897365.7991.9

CountyBEXAR
HighwayFM 1560
From0.8 MILES SOUTH OF SH 16
To1.1 MILES SOUTH OF SH 16
CSJ2230-01-016
Proj IDSTP 2017(477)
Work TypeBASE, GR, STR, ACP, PAV MRKS
 
0.3001368377.48403532.7929.4
CountyBEXAR
HighwayFM 1560
From0.8 MILES SOUTH OF SH 16
To1.1 MILES SOUTH OF SH 16
CSJ2230-01-022
Proj IDROW 2230-1-22
Work TypeUTILITY ADJUSTMENTS
 
0.30079143.0028320.0035.7
Work Order03-10-17
Work Began04-14-17
Work Completed
Time Computed04-09-17
Contract Working Days181
Addl Days Granted0
Working Days Charged44
Percent Time Used24
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2230-01-016
ENVIRONMENTAL SAFETY SERVICES, INC. (1.97)
GK CONSTRUCTION, LLC (1.31)
HOUSTON SAWING & DRILLING (0.27)
TEX OP CONSTRUCTION, LP (1.16)
VOGES DRILLING CO. (2.23)
FLASHER EQUIPMENT COMPANY (1.57)
Contract #01173233
Totals1447520.48182350.37431852.7929.8

CountyBEXAR
HighwayFM 1560
FromFM 1560
ToSH 16
CSJ2230-01-018
Proj IDSTP 2016(752)MM
Work TypeGRAD, BSE, STR, SURF, PAV'T MRKNG
 
0.2323391489.6015687.400.4
CountyBEXAR
HighwayFM 1560
FromFM 1560
ToSH 16
CSJ2230-01-019
Proj IDROW 2230-1-19
Work TypeROW ACQUISITION & UTILITIES ADJS
 
0.23228195.000.000.0
Work Order05-16-17
Work Began00-00-00
Work Completed
Time Computed06-15-17
Contract Working Days271
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2230-01-018
ANGEL BROTHERS HOLDINGS CORP. (9.56)
ENVIRONMENTAL SAFETY SERVICES, INC. (6.28)
FLASHER EQUIPMENT COMPANY (1.35)
GEOSOURCE, INC. (0.44)
PANTHER CREEK TRANSPORTATION, INC. (0.30)
SOUTH TEXAS PAINTING COMPANY (0.09)
Contract #04173204
Totals3419684.6015687.4015687.400.4

CountyBEXAR
HighwaySP 53
FromEDWARD XIMENES AVENUE
ToIH 10
CSJ2230-02-004
Proj IDSTP 2013(714)MM
Work TypeGR, STRS, BASE, SURF, ILLUM & TRAF
 
1.5326984125.756846329.1398.0
CountyBEXAR
HighwaySP 53
FromEDWARD XIMENES AVENUE
ToIH 10
CSJ2230-02-006
Proj IDRW 2230-2-6
Work TypeROW ACQ. & UTILITIES
 
1.512313245.19305946.8497.6
Work Order10-27-14
Work Began06-22-15
Work Completed
Time Computed04-25-15
Contract Working Days534
Addl Days Granted0
Working Days Charged513
Percent Time Used96
Contractor(s)
SMC CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2230-02-004
SAECO ELECTRIC & UTILITY, LTD. (7.04)
PESADO CONSTRUCTION COMPANY (1.67)
FLASHER EQUIPMENT COMPANY (1.40)
PANTHER CREEK TRANSPORTATION, INC. (1.78)
PIPE WHOLESALERS OF TEXAS, INC. (0.00)
BADECO, INC (2.38)
A BROTHERS MILLING, LLC (1.48)
ROADWAY SPECIALTIES, INC. (2.12)
HILL COUNTRY BRIDGE, INC (16.13)
EGGEMEYER LAND CLEARING, LLC (0.92)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (3.05)
VOGES DRILLING CO. (1.13)
S & S BRIDGE PAINTING, INC. (0.03)
GK CONSTRUCTION, LLC (0.22)
DISTRIBUTION CONSTRUCTION, LLC (2.23)
DC CIVIL CONSTRUCTION LLC (2.01)
WILLIAMS CONSTRUCTION (0.30)
R. W. JONES & SONS, INC. (0.96)
FOUR-B PAVING, INC. (0.25)
Contract #05143005
Totals7297370.94541417.567152275.9798.0

CountyBEXAR
HighwaySL 1604
FromFM 1957 - POTRANCO RD
ToFM 471 -CULEBRA RD
CSJ2452-01-056
Proj IDNH 1602(312)
Work TypeGR, STRS, BASE, SURF & SIGN
 
4.10157936595.2617287536.5029.8
CountyBEXAR
HighwaySL 1604
FromFM 1957 - POTRANCO RD
ToFM 471 -CULEBRA RD
CSJ2452-01-061
Proj IDROW 2452-1-61
Work TypeACQUISITION
 
4.1014564354.922254349.7249.3
Work Order08-16-16
Work Began11-28-16
Work Completed
Time Computed10-17-16
Contract Working Days751
Addl Days Granted0
Working Days Charged175
Percent Time Used23
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 2452-01-056
BADECO, INC (1.44)
BEAIRD DRILLING (1.62)
ROADWAY SPECIALTIES, INC. (1.63)
GEOSOURCE, INC. (0.98)
GUERRA UNDERGROUND, LLC (5.05)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.20)
E-Z BEL CONSTRUCTION, LLC (1.47)
LONE STAR PAVING (16.13)
MCL CONTRACTING, LLC (0.53)
THE LEVY COMPANY, L.P. (5.26)
STRATA UNDERGROUND, LLC (0.12)
SOUTH TEXAS PAINTING COMPANY (0.02)
HOUSTON SAWING & DRILLING (0.02)
FLASHER EQUIPMENT COMPANY (0.43)
TDW SERVICES, INC. (0.22)
DU MOR ENTERPRISES (0.14)
UNDER CONSTRUCTION INC. (0.01)
B&E TRUCKING (0.03)
PANTHER CREEK TRANSPORTATION, INC. (0.00)
GALO EQUIPMENT & CONSTRUCTION, LLC (0.00)
G.T. SIRIZZOTTI, LTD. (0.23)
JPC CONSTRUCTION INC DBA JC COMMUNICATIONS (0.20)
CALAME CONTRACTING, LLC (0.64)
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (0.06)
Contract #06163204
Totals62500950.182522741.5819541886.2231.2

CountyBEXAR
HighwaySL 1604
FromUS 90
ToFM 1957 - POTRANCO RD
CSJ2452-01-059
Proj IDNH 1602(550)
Work TypeGR, STRS, BASE, SURF & SIGN
 
3.81863342516.5414416166.1922.7
CountyBEXAR
HighwaySL 1604
FromUS 90
ToFM 1957 - POTRANCO RD
CSJ2452-01-063
Proj IDROW 2452-1-63
Work TypeUTILITY
 
3.818795897.9234620.004.3
Work Order09-26-16
Work Began11-07-16
Work Completed
Time Computed10-26-16
Contract Working Days986
Addl Days Granted0
Working Days Charged187
Percent Time Used18
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2452-01-059
RDI FOUNDATION DRILLING (2.23)
EGGEMEYER LAND CLEARING, LLC (0.15)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.32)
VALLEY PLACERS, LLC (0.15)
MCL CONTRACTING, LLC (0.73)
ROADWAY SPECIALTIES, INC. (2.71)
TEXAS HIGHWAY WALLS (4.51)
EARTH REINFORCEMENTS LLC (0.86)
THE LEVY COMPANY, L.P. (6.13)
PANTHER CREEK TRANSPORTATION, INC. (1.49)
WEBBER BARRIER SERVICES, LLC. (0.95)
BORTUNCO (0.20)
SCOTT DERR PAINTING CO, LLC (0.00)
HOUSTON SAWING & DRILLING (0.04)
BRADCO, LLC (6.08)
JPC CONSTRUCTION INC DBA JC COMMUNICATIONS (0.11)
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (0.03)
AARON CONCRETE CONTRACTORS, L.P. (1.31)
LONE STAR SITEWORK, LLC (0.27)
Contract #08163001
Totals64138414.461641557.3714450786.1922.5

CountyBEXAR
HighwaySL 1604
FromAT SH 16
To.
CSJ2452-01-064
Proj IDNH 1702(335)
Work TypeGRAD,BSE, STR, SURF, PAVT MRK, SIGN
 
0.2327603812.830.000.0
CountyBEXAR
HighwaySL 1604
FromAT SH 16
To.
CSJ2452-01-067
Proj IDROW 2452-1-67
Work TypeUTILITY ADJUSTMENTS
 
0.499396270.350.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days314
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 2452-01-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173220
Totals8000083.180.000.000.0

CountyBEXAR
HighwaySL 1604
FromSH 16
ToROGERS RANCH
CSJ2452-02-115
Proj IDNH 2017(992)
Work TypeSURFACE & PAVEMENT MARKINGS
 
9.22013947909.960.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days186
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 2452-02-115
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173203
Totals13947909.960.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6