Monthly State Let Construction Report For San Antonio District As Of May 11, 2015 Page 5 Of 6

Last Update: Monday, May 11, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFRIO
Highway FM 140
From 1.2 MI S OF BI 35E
To 3.4 MI S OF BI 35E
CSJ 0748-01-029
Proj ID STP 2014(017)
Work Type GR, STR, BASE
 
2.168 1394945.58 0.00 1415153.23 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-31-13
Work Began 12-12-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 127
Addl Days Granted 3
Working Days Charged 124
Percent Time Used 95
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0748-01-029
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(4.74%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.65%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.60%)
FLASHER EQUIPMENT COMPANY(2.58%)
RICE ENVIRONMENTAL SERVICES(0.23%)
Contract # 09133016
Totals 1394945.58 0.00 1415153.23 99.9

CountyBANDERA
Highway FM 470
From RM 187
To FM 462
CSJ 0792-04-045
Proj ID STP 2015(269)HES
Work Type INSTALL ADV WARNING SIGN, ETC
 
16.786 622941.65 74018.83 515881.20 82.8
CountyBANDERA
Highway FM 470
From RM 187
To 0.1 MI. WEST OF FM 462
CSJ 0792-04-046
Proj ID STP 2015(270)
Work Type SEAL COAT AND PAVEMENT MARKINGS
 
16.826 771246.35 0.00 34020.00 4.4
Work Order 11-14-14
Work Began 00-00-00
Work Completed  
Time Computed 01-13-15
Contract Working Days 55
Addl Days Granted 1
Working Days Charged 30
Percent Time Used 53
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0792-04-045
FLASHER EQUIPMENT COMPANY( 17.41%)
THE LEVY COMPANY, L.P. (3.24%)
R.P.V. CONSTRUCTION(3.44%)
Contract # 10143223
Totals 1394188.00 74018.83 549901.20 39.4

CountyMEDINA
Highway FM 462
From 0.4 MI SOUTH OF CR 540
To 1.2 MI N OF FM 2200 WEST
CSJ 0848-01-037
Proj ID STP 2014(018)
Work Type REHAB & WIDEN NARROW ROADWAY
 
7.495 4927894.74 242366.50 3076397.67 62.4
Work Order 10-31-13
Work Began 02-10-14
Work Completed  
Time Computed 12-30-13
Contract Working Days 341
Addl Days Granted 7
Working Days Charged 275
Percent Time Used 79
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0848-01-037
RICE ENVIRONMENTAL SERVICES(3.02%)
VOGES DRILLING CO. (0.91%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.54%)
FARR FOUNDATION, INC.(0.63%)
Contract # 09133035
Totals 4927894.74 242366.50 3076397.67 62.4

CountyMEDINA
Highway FM 462
From 1.2 MI N OF FM 2200 WEST
To 3.3 MI. S. OF FM 2200 WEST
CSJ 0848-01-038
Proj ID STP 2013(035)
Work Type REHAB & WIDEN NARROW ROADWAY
 
4.463 3295349.15 0.00 3664175.13 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-09-12
Work Began 03-25-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 334
Addl Days Granted 30
Working Days Charged 355
Percent Time Used 97
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0848-01-038
FLASHER EQUIPMENT COMPANY(1.35%)
MURRAY CONSTRUCTION(1.04%)
M.V. HENKE ENTERPRISES, INC. (0.36%)
ROADWAY SPECIALTIES, INC.(3.13%)
RELMCO, INC. ( 16.35%)
VOGES DRILLING CO. (1.01%)
Contract # 09123035
Totals 3295349.15 0.00 3664175.13 99.9

CountyBEXAR
Highway FM 471
From LP 1604
To FM 3487
CSJ 0849-01-047
Proj ID STP 2015(937)HES
Work Type GR, BASE, SURF
 
2.539 485383.69 0.00 0.00 0.0
CountyBEXAR
Highway FM 471
From LP 1604
To 0.1 MI NE OF LOST LANE
CSJ 0849-01-048
Proj ID STP 2015(936)
Work Type SURF, PAV'T MRKNGS
 
5.093 1265815.54 0.00 0.00 0.0
CountyBEXAR
Highway FM 471
From LP 1604
To 0.1 MI NE OF LOST LANE
CSJ 0849-01-050
Proj ID ROW 849-1-50
Work Type ROW ACQUISITION
 
5.093 21735.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0849-01-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153008
Totals 1772934.23 0.00 0.00 0.0

CountyATASCOSA
Highway FM 476
From SP 242
To SH 97
CSJ 0853-02-030
Proj ID STP 2014(537)
Work Type TRAFFIC SIGNALS
 
1.156 740432.64 33527.17 742384.60 99.9
Work Order 05-05-14
Work Began 08-18-14
Work Completed  
Time Computed 08-03-14
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 166
Percent Time Used 92
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0853-02-030
JCD CONSTRUCTION, LLC(5.57%)
FLASHER EQUIPMENT COMPANY(1.66%)
UNITED PAVEMENT & MARKINGS, LLC(4.37%)
BADGER DAYLIGHTING CORP. (1.01%)
INTERSTATE BARRICADES & MARKINGS, INC. (4.27%)
Contract # 03143204
Totals 740432.64 33527.17 742384.60 99.9

CountyCOMAL
Highway FM 306
From 0.4 MILES EAST OF FM 3424
To JACOBS CREEK PARK ROAD
CSJ 0857-01-028
Proj ID STP 2013(105)
Work Type GRD, BASE, SURF, AND PAV MARKS
 
2.584 963415.67 0.00 943619.62 100.0
CountyCOMAL
Highway FM 306
From 0.2 MI W OF CANYON DAM ACCESS ROAD
To 1.1 MI E OF PURGATORY ROAD
CSJ 1728-02-054
Proj ID STP 2013(105)
Work Type GRD, BASE, SURF, AND PAV MARKINGS
 
6.542 2545179.77 0.00 2266257.50 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-28-12
Work Began 12-14-12
Work Completed 06-20-14
Time Computed 12-14-12
Contract Working Days 296
Addl Days Granted 0
Working Days Charged 217
Percent Time Used 73
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0857-01-028
E-Z BEL CONSTRUCTION, LLC(1.07%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.62%)
RELMCO, INC. (6.80%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(6.58%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.59%)
ROADWAY SPECIALTIES, INC.(2.67%)
FLASHER EQUIPMENT COMPANY(1.96%)
EGGEMEYER LAND CLEARING, LLC (1.96%)
Contract # 10123012
Totals 3508595.44 0.00 3209877.12 100.0

CountyBEXAR
Highway VA
From DISTRICTWIDE GUIDESIGNS FY14
To .
CSJ 0915-00-155
Proj ID STP 2014(562)
Work Type DISTRICTWIDE GUIDESIGNS FY14
 
0.001 998524.12 4095.39 573801.34 57.4
Work Order 05-20-14
Work Began 07-20-14
Work Completed  
Time Computed 07-21-14
Contract Working Days 208
Addl Days Granted 0
Working Days Charged 158
Percent Time Used 75
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-155
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143205
Totals 998524.12 4095.39 573801.34 57.4

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2014
To .
CSJ 0915-00-156
Proj ID STP 2014(538)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 1299950.00 53093.39 942304.01 73.0
Work Order 05-01-14
Work Began 08-08-14
Work Completed  
Time Computed 07-30-14
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 135
Percent Time Used 42
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-156
JCD CONSTRUCTION, LLC(2.52%)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (1.23%)
UNITED PAVEMENT & MARKINGS, LLC(0.69%)
Contract # 03143206
Totals 1299950.00 53093.39 942304.01 73.0

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2012
To .
CSJ 0915-00-158
Proj ID STP 2012(311)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 1113075.30 0.00 1057064.65 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-12
Work Began 05-29-12
Work Completed 05-07-14
Time Computed 06-10-12
Contract Working Days 300
Addl Days Granted 295
Working Days Charged 359
Percent Time Used 60
Contractor(s)
SAECO ELECTRIC & UTILITY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-158
HEARN CO.(1.01%)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (3.41%)
JCD CONSTRUCTION, LLC(3.84%)
JA&M CONSTRUCTION, LLC (1.07%)
Contract # 02123222
Totals 1113075.30 0.00 1057064.65 100.0

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2013
To .
CSJ 0915-00-160
Proj ID STP 2013(404)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.010 1179951.00 993.92 380577.24 100.0
Work Order 04-19-13
Work Began 10-29-13
Work Completed 02-10-15
Time Computed 07-18-13
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 56
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-160
JND CONSTRUCTION CONSULTANTS, LLC( 13.54%)
VACA UNDERGROUND UTILITIES INC (3.44%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.69%)
BEAIRD DRILLING(0.16%)
YORK & YORK FOUNDATION DRILLING, INC.(3.55%)
JCH CONSTRUCTION, INC. (0.05%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.03%)
Contract # 02133216
Totals 1179951.00 993.92 380577.24 100.0

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2012
To .
CSJ 0915-00-163
Proj ID STP 2012(312)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 942875.75 0.00 984638.97 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-12
Work Began 05-22-12
Work Completed 05-07-14
Time Computed 06-10-12
Contract Working Days 300
Addl Days Granted 91
Working Days Charged 231
Percent Time Used 59
Contractor(s)
SAECO ELECTRIC & UTILITY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-163
HEARN CO.(6.17%)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (4.03%)
JA&M CONSTRUCTION, LLC (1.33%)
JCD CONSTRUCTION, LLC(2.82%)
Contract # 02123027
Totals 942875.75 0.00 984638.97 100.0

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2013
To .
CSJ 0915-00-164
Proj ID STP 2013(405)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.010 1218087.00 0.00 499351.55 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-19-13
Work Began 10-29-13
Work Completed 02-10-15
Time Computed 07-18-13
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 158
Percent Time Used 49
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-164
JND CONSTRUCTION CONSULTANTS, LLC( 13.12%)
VACA UNDERGROUND UTILITIES INC (3.34%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.33%)
BEAIRD DRILLING(0.32%)
YORK & YORK FOUNDATION DRILLING, INC.(3.44%)
JCH CONSTRUCTION, INC. (0.17%)
Contract # 02133013
Totals 1218087.00 0.00 499351.55 100.0

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2015
To .
CSJ 0915-00-165
Proj ID STP 2015(584)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 1424346.61 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-20-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-165
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153033
Totals 1424346.61 0.00 0.00 0.0

CountyBEXAR
Highway CS
From IN SAN ANTONIO ON SOMERSET RD
To AT LEON CREEK
CSJ 0915-12-218
Proj ID BR 96(351)
Work Type REHABILITATE BRIDGE & APPROACHES
 
0.001 425301.50 0.00 359463.94 94.7
Work Order 04-11-14
Work Began 06-11-14
Work Completed  
Time Computed 06-11-14
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 140
Percent Time Used 212
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-218
ABC EROSION CONTROL, INC.( 14.56%)
AMERICAN SIGNAL EQUIPMENT CO.(2.16%)
ALTUS TRAFFIC MANAGEMENT LLC (0.69%)
Contract # 03143007
Totals 425301.50 0.00 359463.94 94.7

CountyBEXAR
Highway MH
From WURZBACH PARKWAY ON NEW LOCATION
To FROM FM 2696 TO WEST AVE
CSJ 0915-12-224
Proj ID C 915-12-224
Work Type GRAD, STRS, BASE & SURF
 
1.499 24686408.64 0.00 23990742.30 99.9
CountyBEXAR
Highway MH
From ON EAST-WEST PKWY FROM LOCKHILL-SEL
To IH 35 IN SAN ANTONIO
CSJ 8000-15-007
Proj ID RW 8000-15-7
Work Type ACQUISITION OF ROW
 
0.001 1762476.01 2607.81 1651849.74 93.7
Work Order 10-07-10
Work Began 01-04-11
Work Completed  
Time Computed 01-04-11
Contract Working Days 273
Addl Days Granted 297
Working Days Charged 783
Percent Time Used 137
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-224
AUSTIN WOOD RECYCLING(0.19%)
BEAIRD DRILLING(2.68%)
COLLECTIVE CONTRACTING (6.40%)
CP REBAR AND PT INSTALLATION (1.01%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.45%)
F & W ELECTRICAL CONTRACTORS, INC. (3.47%)
FUQUAY, INC. (0.45%)
HIGHWAY TECHNOLOGIES, INC. (0.57%)
LONE STAR TRAFFIC SERVICE, INC.(0.10%)
SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.09%)
Z & L CONCRETE CONTRACTORS, INC. (1.19%)
TRI COUNTY SERVICES, INC.(1.19%)
MONTELONGO"S CONCRETE(0.62%)
ROADWAY SPECIALTIES, INC.(0.45%)
S BARRY SIGNATURE HOMES, INC.(1.08%)
CRIBLEY ENTERPRISES, INC.(0.03%)
GEOSOURCE, INC.(1.20%)
SCOTT DERR PAINTING CO, LLC(0.15%)
FLASHER EQUIPMENT COMPANY(0.48%)
DUSTROL, INC.(0.13%)
TEXAS STERLING CONSTRUCTION CO.( 14.73%)
ROADWAY SPECIALTIES, INC.(0.13%)
MUNDO VERDE IRRIGATION & LANDSCAPING, INC. (0.41%)
FUQUAY, INC. (0.49%)
F & W ELECTRICAL CONTRACTORS, INC. (1.41%)
S & S BRIDGE PAINTING, INC.(0.16%)
FLASHER EQUIPMENT COMPANY(0.00%)
Contract # 08103240
Totals 26448884.65 2607.81 25642592.04 99.9

CountyBEXAR
Highway CR
From GROSS LANE AT MEDINA RIVER
To .
CSJ 0915-12-439
Proj ID BR 2007(638)
Work Type REHABILITATE BRIDGE AND APPROACHES
 
0.001 527480.77 0.00 96077.02 18.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-06-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 69
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 20
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-439
MCL CONTRACTING, LLC (0.88%)
DOUBLE S PAVING, INC.(2.26%)
FLASHER EQUIPMENT COMPANY(1.81%)
LONE STAR EROSION CONTROL(1.51%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.71%)
ROADWAY SPECIALTIES, INC.(3.58%)
ALTUS TRAFFIC MANAGEMENT LLC (0.58%)
Contract # 01153028
Totals 527480.77 0.00 96077.02 18.2

CountyBEXAR
Highway VA
From IH 35 AND VARIOUS LOCATIONS_IN
To BEXAR COUNTY
CSJ 0915-12-494
Proj ID STP 2012(531)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2893180.08 0.00 2296225.51 83.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-12
Work Began 09-10-12
Work Completed  
Time Computed 09-10-12
Contract Working Days 245
Addl Days Granted 0
Working Days Charged 386
Percent Time Used 157
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-494
F & W ELECTRICAL CONTRACTORS, INC. ( 17.08%)
INTERSTATE BARRICADES & MARKINGS, INC. (3.87%)
JCD CONSTRUCTION, LLC( 46.25%)
DAVID"S QUALITY CONCRETE WORK(6.43%)
Z & L CONCRETE CONTRACTORS, INC. (2.50%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.97%)
Contract # 05123211
Totals 2893180.08 0.00 2296225.51 83.1

CountyBEXAR
Highway VA
From VARIOUS LOCATIONS IN BEXAR COUNTY
To .
CSJ 0915-12-521
Proj ID STP 2014(623)
Work Type CONSTRUCT CURB RAMPS
 
0.001 1885777.35 102668.63 739233.49 39.2
Work Order 06-20-14
Work Began 09-18-14
Work Completed  
Time Computed 09-18-14
Contract Working Days 243
Addl Days Granted 0
Working Days Charged 114
Percent Time Used 46
Contractor(s)
F.D. CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-521
AMERICAN SIGNAL EQUIPMENT CO.(7.73%)
F & W ELECTRICAL CONTRACTORS, INC. (6.94%)
AZTEC FENCE & ORNAMENTAL IRON(1.51%)
Contract # 05143224
Totals 1885777.35 102668.63 739233.49 39.2

CountyBEXAR
Highway VA
From VARIOUS LOCATIONS IN BEXAR COUNTY
To .
CSJ 0915-12-530
Proj ID STP 2015(199)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2958588.16 0.00 2000.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-02-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 309
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 6
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-530
FLASHER EQUIPMENT COMPANY(2.66%)
4J"S SERVICES( 19.98%)
BEXAR COUNTY CONCRETE, LLC (9.74%)
Contract # 10143225
Totals 2958588.16 0.00 2000.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6