Monthly State Let Construction Report For San Antonio District As Of Jan 11, 2017 Page 5 Of 5

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMCMULLEN
HighwayVA
FromJAMES E DAUGHTEY WMA
To.
CSJ0915-51-011
Proj IDC 915-51-11
Work TypeGRADE, BASE AND SURFACE
 
0.001454942.12396284.2194.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-15-16
Work Began04-25-16
Work Completed
Time Computed00-00-00
Contract Working Days77
Addl Days Granted0
Working Days Charged132
Percent Time Used171
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-51-011
FLASHER EQUIPMENT COMPANY (1.51)
Contract #01163032
Totals454942.120.00396284.2194.2

CountyATASCOSA
HighwayFM 536
FromAT FM 1784
To.
CSJ1009-03-014
Proj IDSTP 1602(128)
Work TypeGRAD, BSE, SURF, SIGNALS, PAVMT MRK
 
0.369364903.95369723.5699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-30-16
Work Began07-27-16
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted1
Working Days Charged62
Percent Time Used95
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1009-03-014
FLASHER EQUIPMENT COMPANY (7.76)
THE LEVY COMPANY, L.P. (15.45)
Contract #05163029
Totals364903.950.00369723.5699.9

CountyCOMAL
HighwayFM 1101
FromSH 46
To0.5 MI N OF FM 306
CSJ1272-01-016
Proj IDSTP 2014(564)
Work TypeBASE, GR, STR, SIDEWALK
 
2.7976154722.50252827.804.1
Work Order06-02-14
Work Began00-00-00
Work Completed
Time Computed11-29-14
Contract Working Days354
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1272-01-016
ENVIRONMENTAL SAFETY SERVICES, INC. (3.55)
E-Z BEL CONSTRUCTION, LLC (2.42)
INTERSTATE CONCRETE & STEEL SERVICES INCORPORATED (39.55)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.21)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.71)
AUSTIN WOOD RECYCLING (0.32)
INTERSTATE BARRICADES & MARKINGS, INC. (1.80)
Contract #04143002
Totals6154722.50121760.00252827.804.1

CountyCOMAL
HighwayFM 306
FromHOFFMANN LANE
To0.5 MI NORTH OF HUNTER ROAD
CSJ1728-02-058
Proj IDSTP 1502(615)MM
Work TypeGRAD, STR, BASE, SURF
 
3.2327936418.825720955.5972.0
Work Order10-21-15
Work Began12-01-15
Work Completed
Time Computed01-19-16
Contract Working Days364
Addl Days Granted0
Working Days Charged274
Percent Time Used75
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1728-02-058
E-Z BEL CONSTRUCTION, LLC (2.34)
CATO ELECTRIC COMPANY (0.00)
HEARN CO. (0.19)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.64)
FLASHER EQUIPMENT COMPANY (0.27)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.41)
R K STEPHENS CONSTRUCTION, LLC (5.07)
TRP CONSTRUCTION GROUP, LLC (1.39)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (3.04)
AUSTIN WOOD RECYCLING (0.61)
Contract #08153016
Totals7936418.82569883.675720955.5972.0

CountyCOMAL
HighwayFM 306
FromRIVER CHASE WAY
ToHOFFMANN LANE
CSJ1728-02-059
Proj IDSTP 1602(300)MM
Work TypeGRAD, STR, BASE, SURF
 
1.3275996508.481119928.1118.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-06-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days364
Addl Days Granted0
Working Days Charged60
Percent Time Used16
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1728-02-059
OSCAR ORDUNO, INC. (10.30)
SOUTH TEXAS PAINTING COMPANY (0.32)
F & W ELECTRICAL CONTRACTORS, INC. (3.51)
FLASHER EQUIPMENT COMPANY (1.00)
ENVIRONMENTAL SAFETY SERVICES, INC. (7.37)
EGGEMEYER LAND CLEARING, LLC (0.55)
TEXAS LANDSCAPE & IRRIGATION (1.03)
Contract #07163211
Totals5996508.480.001119928.1118.6

CountyBANDERA
HighwayFM 1283
FromSH 16
ToPR 37
CSJ1730-01-040
Proj IDSTP 2017(036)HES
Work TypeINSTALL CHEVRONS, PAVEMENT MARKINGS
 
9.216496196.560.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-25-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1730-01-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09163007
Totals496196.560.000.000.0

CountyBEXAR
HighwayFM 1957
FromLOOP 1604
ToFM 3487
CSJ2104-02-032
Proj IDSTP 2017(037)HES
Work TypeGR, BASE, SURF
 
4.885979020.408800.000.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-21-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days101
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TROPICAL CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2104-02-032
FLASHER EQUIPMENT COMPANY (21.69)
ELITE CURB & CONCRETE, LLC (31.71)
Contract #09163206
Totals979020.400.008800.000.8

CountyBEXAR
HighwayFM 1560
From0.8 MILES SOUTH OF SH 16
To1.1 MILES SOUTH OF SH 16
CSJ2230-01-016
Proj IDSTP 2017(477)
Work TypeBASE, GR, STR, ACP, PAV MRKS
 
0.3001368377.480.000.0
CountyBEXAR
HighwayFM 1560
From0.8 MILES SOUTH OF SH 16
To1.1 MILES SOUTH OF SH 16
CSJ2230-01-022
Proj IDROW 2230-1-22
Work TypeUTILITY ADJUSTMENTS
 
0.30079143.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days181
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2230-01-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173233
Totals1447520.480.000.000.0

CountyBEXAR
HighwaySP 53
FromEDWARD XIMENES AVENUE
ToIH 10
CSJ2230-02-004
Proj IDSTP 2013(714)MM
Work TypeGR, STRS, BASE, SURF, ILLUM & TRAF
 
1.5326984125.755132816.0373.4
CountyBEXAR
HighwaySP 53
FromEDWARD XIMENES AVENUE
ToIH 10
CSJ2230-02-006
Proj IDRW 2230-2-6
Work TypeROW ACQ. & UTILITIES
 
1.512313245.19267884.3485.5
Work Order10-27-14
Work Began06-22-15
Work Completed
Time Computed04-25-15
Contract Working Days534
Addl Days Granted0
Working Days Charged385
Percent Time Used72
Contractor(s)
SMC CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2230-02-004
SAECO ELECTRIC & UTILITY, LTD. (7.04)
PESADO CONSTRUCTION COMPANY (1.67)
FLASHER EQUIPMENT COMPANY (1.40)
PANTHER CREEK TRANSPORTATION, INC. (1.78)
PIPE WHOLESALERS OF TEXAS, INC. (0.00)
BADECO, INC (2.38)
A BROTHERS MILLING, LLC (1.48)
ROADWAY SPECIALTIES, INC. (2.12)
HILL COUNTRY BRIDGE, INC (16.13)
EGGEMEYER LAND CLEARING, LLC (0.92)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (3.05)
VOGES DRILLING CO. (1.13)
S & S BRIDGE PAINTING, INC. (0.03)
GK CONSTRUCTION, LLC (0.22)
DISTRIBUTION CONSTRUCTION, LLC (2.23)
DC CIVIL CONSTRUCTION LLC (2.01)
WILLIAMS CONSTRUCTION (0.30)
R. W. JONES & SONS, INC. (0.96)
Contract #05143005
Totals7297370.94278917.255400700.3774.0

CountyBEXAR
HighwaySL 1604
FromFM 1957 - POTRANCO RD
ToFM 471 -CULEBRA RD
CSJ2452-01-056
Proj IDNH 1602(312)
Work TypeGR, STRS, BASE, SURF & SIGN
 
4.10157936595.263950004.536.8
CountyBEXAR
HighwaySL 1604
FromFM 1957 - POTRANCO RD
ToFM 471 -CULEBRA RD
CSJ2452-01-061
Proj IDROW 2452-1-61
Work TypeACQUISITION
 
4.1014564354.92315332.536.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days751
Addl Days Granted0
Working Days Charged23
Percent Time Used3
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 2452-01-056
BADECO, INC (1.44)
BEAIRD DRILLING (1.62)
ROADWAY SPECIALTIES, INC. (1.63)
GEOSOURCE, INC. (0.98)
GUERRA UNDERGROUND, LLC (5.05)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.20)
E-Z BEL CONSTRUCTION, LLC (1.47)
LONE STAR PAVING (16.13)
MCL CONTRACTING, LLC (0.53)
DU-MOR ENTERPRISES_INC. (0.14)
THE LEVY COMPANY, L.P. (5.26)
STRATA UNDERGROUND, LLC (0.12)
SOUTH TEXAS PAINTING COMPANY (0.02)
HOUSTON SAWING & DRILLING (0.00)
FLASHER EQUIPMENT COMPANY (0.43)
STRAIGHT LINE (0.01)
TDW SERVICES, INC. (0.22)
Contract #06163204
Totals62500950.180.004265337.066.8

CountyBEXAR
HighwaySL 1604
FromUS 90
ToFM 1957 - POTRANCO RD
CSJ2452-01-059
Proj IDNH 1602(550)
Work TypeGR, STRS, BASE, SURF & SIGN
 
3.81863342516.541641701.822.5
CountyBEXAR
HighwaySL 1604
FromUS 90
ToFM 1957 - POTRANCO RD
CSJ2452-01-063
Proj IDROW 2452-1-63
Work TypeUTILITY
 
3.818795897.920.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-26-16
Work Began11-07-16
Work Completed
Time Computed00-00-00
Contract Working Days986
Addl Days Granted0
Working Days Charged37
Percent Time Used3
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2452-01-059
RDI FOUNDATION DRILLING (2.23)
EGGEMEYER LAND CLEARING, LLC (0.15)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.32)
VALLEY PLACERS, LLC (0.15)
MCL CONTRACTING, LLC (0.73)
Contract #08163001
Totals64138414.460.001641701.822.5

CountyGUADALUPE
HighwayFM 3009
FromIH 35
ToFM 78
CSJ3107-02-034
Proj IDSTP 1502(472)MM
Work TypeGRD, BSE, SIDEWALKS
 
3.1453240269.502823711.6787.1
Work Order08-26-15
Work Began00-00-00
Work Completed
Time Computed12-24-15
Contract Working Days123
Addl Days Granted34
Working Days Charged125
Percent Time Used79
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3107-02-034
INTERSTATE BARRICADES & MARKINGS, INC. (0.65)
F & W ELECTRICAL CONTRACTORS, INC. (2.02)
ENVIRONMENTAL SAFETY SERVICES, INC. (13.82)
LONE STAR PAVING (1.41)
DELGADO"S CONSTRUCTION (1.58)
THOMAS TURF GRASS (4.53)
JE CASEY, LLC (0.63)
Contract #07153034
Totals3240269.50162331.102823711.6787.1

CountyBEXAR
HighwayMH
FromWURZBACH PARKWAY ON NEW LOCATION
ToWEST AVE TO JONES MALTSBERGER
CSJ8000-15-015
Proj IDNH 2011(837)
Work TypeGRAD, STRS, BASE & SURF
 
1.67948594617.4750676884.8599.9
CountyBEXAR
HighwayMH
FromWURZBACH PARKWAY ON NEW LOCATION
ToWEST AVE TO JONES MALTSBERGER
CSJ8000-15-017
Proj IDRW 8000-15-17
Work TypeROW UTL. ADJ.
 
1.145839700.13802974.9595.6
Work Order06-14-11
Work Began07-06-11
Work Completed
Time Computed07-05-11
Contract Working Days1,160
Addl Days Granted59
Working Days Charged1,208
Percent Time Used99
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 8000-15-015
ID/GUERRA L.P. (5.86)
BOSQUEZ ELECTRICAL, LLC. (3.79)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.12)
INDUS CONSTRUCTION, L.P. (6.69)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.51)
ROADWAY SPECIALTIES, INC. (0.64)
CLARK CONSTRUCTION OF TEXAS, INC. (1.45)
EGGEMEYER LAND CLEARING, LLC (0.17)
SCOTT DERR PAINTING CO, LLC (0.00)
BEST IN TOWN, INC. (1.49)
INTERSTATE BARRICADES & MARKINGS, INC. (0.37)
SAN ANTONIO TELEPHONE COMPANY INC. (0.02)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.57)
F & W ELECTRICAL CONTRACTORS, INC. (2.66)
RICE ENVIRONMENTAL SERVICES (1.36)
Z & L CONCRETE CONTRACTORS, INC. (0.35)
GUERRA UNDERGROUND, LLC (0.88)
HEARN CO. (0.18)
CPAVE, INC. (0.06)
Contract #04113004
Totals49434317.6026576.6251479859.8099.9

page 1 | page 2 | page 3 | page 4 | page 5