TxDOT Expressway
Search:
   Home   |    Contact Us   |    Tools & Plug-Ins  
 
 
Last Update: Monday, November 17, 2008
FTP Icon Text Version
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCOMAL
Highway IH 35
From 0.1 MI N OF FM 725
To HAYS COUNTY LINE
CSJ 0016-04-103
Proj ID IM 0352(321)
Work Type CORRIDOR TRAFFIC MANAGEMENT
 
80.215 4594799.12 143089.44 4567831.25 99.9
Work Order 06-13-07
Work Began 09-05-07
Work Completed  
Time Computed 06-29-07
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 117
Contractor(s)
J & V COMMUNICATION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0016-04-103
TONY A. ENTERPRISES, INC.(0.27%)
SIX LINE CONSTRUCTION, LLC (2.16%)
CARTHAGE DRILLING, INC.(3.33%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.21%)
BOYD & SONS, L.L.C.(0.44%)
Contract # 05073011
Totals 4594799.12 143089.44 4567831.25 99.9

CountyCOMAL
Highway IH 35 ETC
From SB & NB FR - HAYES COUNTY LINE
To SB & NB FR KOHLENBURGE RD
CSJ 0016-04-108
Proj ID IM 0352(325)
Work Type SEAL COAT & PAVEMENT MARKINGS
 
129.961 3343283.24 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-30-07
Work Began 05-14-08
Work Completed  
Time Computed 00-00-00
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0016-04-108
INTERSTATE BARRICADES & MARKINGS, INC. ( 29.40%)
Contract # 11073014
Totals 3343283.24 0.00 0.00 0.0

CountyCOMAL
Highway IH 35
From 0.189 MI S OF SCHMIDT STREET
To 0.093 MI NORTH OF FM 725
CSJ 0016-05-102
Proj ID CL 16-5-102
Work Type IRRIGATION AND LANDSCAPING
 
2.343 457580.00 1236.82 382211.19 88.0
Work Order 10-18-05
Work Began 12-12-05
Work Completed  
Time Computed 11-03-05
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 101
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0016-05-102
DIAMONDBACK LANDSCAPING AND LAWN CARE, INC.(3.13%)
SIDEWINDER DIRECTIONAL, INC. (0.70%)
HALL IRRIGATION SYSTEMS(8.26%)
POUNDS ENTERPRISES, INC. (0.21%)
Contract # 09053022
Totals 457580.00 1236.82 382211.19 88.0

CountyCOMAL
Highway IH 35
From 0.40 MILES NORTH ENGEL RD
To 0.55 MILES NORTH OF ENGEL RD
CSJ 0016-05-104
Proj ID NH 2007(703)
Work Type SEAL COAT, SURF, PAV'T MRK
 
0.150 41211.40 0.00 5250.00 12.7
CountyCOMAL
Highway IH 35
From 0.18 MILES NORTH OF SCHMIDT ST
To 0.35 MILES NORTH OF SCHMIDT ST
CSJ 0016-05-105
Proj ID NH 2007(703)
Work Type SEAL COAT, SURF, PAV'T MRK
 
0.170 63574.60 0.00 108838.26 99.9
CountyBEXAR
Highway IH 35
From WEIDNER
To LOOP 1604
CSJ 0016-07-026
Proj ID IM 0352(322)
Work Type MILL, OVERLAY & PAV'T MARKINGS
 
3.620 1151217.36 0.00 1316292.49 99.9
CountyZERO COUNTIES
Highway  
From  
To  
CSJ 0915-12-462
Proj ID  
Work Type  
 
  0.00 27040.86 177027.35 0.0
CountyBEXAR
Highway LP 1604
From SHIN OAK DR
To KITTY HAWK
CSJ 2452-03-102
Proj ID NH 2007(703)
Work Type GRADE, BASE, STR, SURF & PAV'T MRK
 
0.962 4607580.44 446503.98 4658728.57 99.9
Work Order 09-19-07
Work Began 10-11-07
Work Completed  
Time Computed 09-15-07
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 349
Percent Time Used 129
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 2452-03-102
CLARK CONSTRUCTION OF TEXAS, LTD.( 17.10%)
CRAIG OLDEN, INC.(5.72%)
BOSQUEZ ELECTRICAL, LLC. (0.74%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.68%)
Z-BAR TRANSPORT(4.02%)
W.W. WEBBER, LLC (1.45%)
ROADWAY SPECIALTIES, INC.(0.64%)
UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (1.22%)
SCR CONSTRUCTION CO., INC. (0.56%)
CRAWFORD YANT(1.15%)
Contract # 07073219
Totals 5863583.80 473544.84 6266136.67 99.9

CountyBEXAR
Highway IH 35
From AT SH 218
To .
CSJ 0016-07-125
Proj ID IM 0352(327)
Work Type GRAD, BASE, STR, SURF & PAV'T MRK
 
1.256 6610138.62 242847.69 4797902.14 72.5
Work Order 03-04-08
Work Began 03-13-08
Work Completed  
Time Computed 03-20-08
Contract Working Days 349
Addl Days Granted 0
Working Days Charged 159
Percent Time Used 45
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0016-07-125
AARON CONCRETE CONTRACTORS, L.P. (7.91%)
CRAIG OLDEN, INC.(1.46%)
CRAWFORD YANT(2.42%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.26%)
FLASHER EQUIPMENT COMPANY(2.64%)
L.A. UTILITIES, INC. (6.01%)
THE LEVY COMPANY, L.P. ( 12.50%)
PENNTEX MILLING, LLC (0.24%)
ROADWAY SPECIALTIES, INC.(2.68%)
SCOTT DERR PAINTING CO (0.00%)
HEARN CO.(0.57%)
SAN ANTONIO TELEPHONE COMPANY INC. (0.09%)
Contract # 12073206
Totals 6610138.62 242847.69 4797902.14 72.5

CountyBEXAR
Highway LP 368
From ON LP 368 (AUSTIN HWY)
To AT HARRY WURZBACH ROAD
CSJ 0016-08-030
Proj ID BR 2007(414)
Work Type REPLACE NARROW BRIDGE & APPROACHES
 
1.733 2236783.11 20992.43 2361634.69 99.9
Work Order 06-15-07
Work Began 10-01-07
Work Completed  
Time Computed 10-01-07
Contract Working Days 410
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 66
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0016-08-030
SCOTT DERR PAINTING CO (0.05%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.62%)
ROADWAY SPECIALTIES, INC.(1.17%)
THE LEVY COMPANY, L.P. (1.00%)
J.D. RAMMING PAVING CO., LTD.( 10.61%)
FUQUAY, INC. (0.47%)
FLASHER EQUIPMENT COMPANY(2.59%)
76 MILLING, INC. (0.78%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.51%)
VOGES DRILLING (3.57%)
GEO MATRIX, LLC(0.16%)
Contract # 04073229
Totals 2236783.11 20992.43 2361634.69 99.9

CountyCOMAL
Highway BI 35-H
From AT GUADALUPE RIVER
To .
CSJ 0016-11-015
Proj ID BR 2007(588)
Work Type REHABILITATE NARROW BDGE & APPRS
 
0.194 517888.50 72181.68 430778.54 83.1
Work Order 07-26-07
Work Began 05-28-08
Work Completed  
Time Computed 08-11-07
Contract Working Days 65
Addl Days Granted 20
Working Days Charged 85
Percent Time Used 100
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0016-11-015
PRIMATE CONSTRUCTION, INC. ( 13.93%)
S & S PAINTING (2.15%)
FLASHER EQUIPMENT COMPANY(1.38%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.( 13.14%)
JAVELINA CONSTRUCTION SOUTH, INC.(1.17%)
Contract # 06073210
Totals 517888.50 72181.68 430778.54 83.1

CountyBEXAR
Highway IH 35
From SB COLLECTOR RD 0.4 MI S OF IH 410
To 0.22 MI N OF IH 410
CSJ 0017-02-059
Proj ID BR 2007(707)
Work Type RAISE & WIDEN NARROW BRIDGE & APP
 
0.550 5086578.23 236968.62 4446672.59 87.4
Work Order 08-09-07
Work Began 09-17-07
Work Completed  
Time Computed 08-25-07
Contract Working Days 318
Addl Days Granted 0
Working Days Charged 282
Percent Time Used 88
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0017-02-059
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.15%)
ATS DRILLING, L.P. (5.21%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.56%)
FLASHER EQUIPMENT COMPANY(4.50%)
GEOSOURCE, INC.(0.86%)
J.D. RAMMING PAVING CO., LTD.(9.74%)
THE LEVY COMPANY, L.P. (0.60%)
GIBSON & ASSOCIATES, INC.(7.32%)
SCOTT DERR PAINTING CO (0.15%)
INDUS CONSTRUCTION, L.P. (0.32%)
S & S PAINTING (2.69%)
AARON CONCRETE CONTRACTORS, L.P. (1.39%)
PENNTEX MILLING INC. (0.37%)
Contract # 07073029
Totals 5086578.23 236968.62 4446672.59 87.4

CountyBEXAR
Highway IH 35 ETC
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0017-02-064
Proj ID C 17-2-64
Work Type OSB REPAIR
 
73.354 1650640.93 876.87 1735612.46 99.9
Work Order 11-15-05
Work Began 03-13-06
Work Completed  
Time Computed 12-01-05
Contract Working Days 240
Addl Days Granted 57
Working Days Charged 296
Percent Time Used 99
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0017-02-064
FUQUAY INC (SAN ANTONIO) (0.20%)
FLASHER EQUIPMENT COMPANY(5.11%)
JCD CONSTRUCTION, LLC(9.32%)
Contract # 10053016
Totals 1650640.93 876.87 1735612.46 99.9

CountyBEXAR
Highway IH 35
From IH 35S
To @ IH 410
CSJ 0017-02-068
Proj ID IM 0352(323)
Work Type LANDSCAPE DEVELOPMENT
 
0.600 331759.14 1400.00 277612.97 83.9
Work Order 10-18-07
Work Began 01-07-08
Work Completed  
Time Computed 11-05-07
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 74
Percent Time Used 102
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0017-02-068
LONE STAR TRAFFIC SERVICE, INC.(1.65%)
CAL-PERK UNDERGROUND UTILITIES (0.96%)
POENITZSCH BACKHOE SERVICE, INC. (3.01%)
GREEN GRASS, INC.( 15.19%)
Contract # 09073018
Totals 331759.14 1400.00 277612.97 83.9

CountyBEXAR
Highway IH 35
From OLD QUINTANA RD.
To FISCHER RD.
CSJ 0017-02-071
Proj ID IM 0352(328)
Work Type GRAD, BASE, STR, SURF, & PAV'T MRKNGS
 
1.989 8385286.16 653503.84 2704098.54 32.2
Work Order 03-18-08
Work Began 05-19-08
Work Completed  
Time Computed 04-03-08
Contract Working Days 383
Addl Days Granted 0
Working Days Charged 117
Percent Time Used 30
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0017-02-071
L.A. UTILITIES, INC. (7.44%)
ROADWAY SPECIALTIES, INC.(3.75%)
SCOTT DERR PAINTING CO (0.32%)
W. W. FOUNDATION DRILLING, LTD.(1.47%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.37%)
STOMPER DEMOLITION (0.74%)
MURRAY CONSTRUCTION(0.42%)
JAVELINA CONSTRUCTION SOUTH, INC.(0.29%)
GUAJARDO STEEL (0.23%)
CRAWFORD YANT(1.48%)
CAPROCK SPECIALITY CONTRACTORS (0.05%)
STAR OPERATIONS, INC.(3.47%)
FLASHER EQUIPMENT COMPANY(1.49%)
Contract # 01083003
Totals 8385286.16 653503.84 2704098.54 32.2

CountyATASCOSA
Highway IH 35
From MEDINA/ATASCOSA COUNTY LINE
To ATASCOSA/BEXAR COUNTY LINE
CSJ 0017-04-035
Proj ID IM 0352(317)
Work Type PAV REPAIR, SC, SMA, & PAVT MRKNGS
 
22.335 9212798.87 3048687.50 8519419.65 92.4
Work Order 10-12-07
Work Began 12-05-07
Work Completed  
Time Computed 04-01-08
Contract Working Days 106
Addl Days Granted 0
Working Days Charged 96
Percent Time Used 90
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-04-035
FLASHER EQUIPMENT COMPANY(2.13%)
Contract # 09073004
Totals 9212798.87 3048687.50 8519419.65 92.4

CountyATASCOSA
Highway IH 35 ETC
From FM 3175
To FM 2790
CSJ 0017-04-039
Proj ID IM 0352(329)
Work Type SEAL COAT & PAVEMENT MARKINGS
 
182.683 6799541.03 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0017-04-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11083215
Totals 6799541.03 0.00 0.00 0.0

CountyFRIO
Highway IH 35
From EAST FRONTAGE RD AT FRIO RIVER
To .
CSJ 0017-07-088
Proj ID BR 2007(779)
Work Type WIDEN NARROW BRIDGE & APPROACHES
 
0.182 676442.48 3003.41 674160.37 99.6
Work Order 11-07-07
Work Began 02-11-08
Work Completed  
Time Computed 11-23-07
Contract Working Days 131
Addl Days Granted 4
Working Days Charged 123
Percent Time Used 91
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0017-07-088
LONE STAR TRAFFIC SERVICE, INC.(1.07%)
ATS DRILLING, L.P. ( 11.75%)
FLASHER EQUIPMENT COMPANY(0.50%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.88%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(4.39%)
JAVELINA CONSTRUCTION SOUTH, INC.(1.53%)
Contract # 10073225
Totals 676442.48 3003.41 674160.37 99.6

CountyBEXAR
Highway IH 35
From @ THEO AND MALONE, DIVISION AVE
To AND SOUTHCROSS BLVD
CSJ 0017-09-072
Proj ID BR 2006(590)
Work Type REHABILITATE BRIDGES & APPROACHES
 
0.001 6049301.93 62333.97 5654221.88 94.9
CountyBEXAR
Highway IH 35
From US 90
To ZARZAMORA STREET
CSJ 0017-09-085
Proj ID C 17-9-85
Work Type OPERATIONAL IMPROVEMENTS
 
3.551 23041451.20 1747093.12 22765923.65 98.8
Work Order 09-15-06
Work Began 10-23-06
Work Completed  
Time Computed 10-01-06
Contract Working Days 400
Addl Days Granted 42
Working Days Charged 486
Percent Time Used 109
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0017-09-072
TREVCON, INC.(2.58%)
CHEROKEE SERVICES(0.36%)
AARON CONCRETE CONTRACTORS, L.P. (1.91%)
DUSTROL, INC. (ROANOKE)(0.54%)
FLASHER EQUIPMENT COMPANY(1.32%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.22%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (0.63%)
ROADWAY SPECIALTIES, INC.(0.28%)
HOUSTON SAWING & DRILLING(0.04%)
TEXAS CURB CUT, INC.(HUB)(0.45%)
STOMPER DEMOLITION (1.09%)
LEVY COMPANY (9.29%)
MICA CORPORATION (6.87%)
W. W. FOUNDATION DRILLING, LTD.(3.22%)
SCOTT DERR PAINTING CO (0.07%)
J.L. STEEL, L.P. (0.51%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.95%)
E & E STEEL(0.13%)
HEARN CO.(0.03%)
GEO MATRIX, LLC(0.15%)
Contract # 06063206
Totals 29090753.13 1809427.09 28420145.53 97.9

CountyBEXAR
Highway IH 35
From AT SP 422
To .
CSJ 0017-09-087
Proj ID C 17-9-87
Work Type LANDSCAPE DEVELOPMENT
 
0.001 565172.25 2450.00 493659.41 89.2
Work Order 02-17-06
Work Began 03-13-06
Work Completed  
Time Computed 03-05-06
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 101
Contractor(s)
CARRUTH NURSERY IRRIGATION & LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-09-087
BARTEK CONSTRUCTION CO.(0.07%)
Contract # 01063215
Totals 565172.25 2450.00 493659.41 89.2

CountyBEXAR
Highway IH 35
From AT SP 422
To .
CSJ 0017-09-092
Proj ID C 17-9-92
Work Type GRAD, STR, BASE, SC, OV & PAV'T MRKS
 
2.116 15638408.57 621295.32 8089383.05 53.8
Work Order 09-11-07
Work Began 09-27-07
Work Completed  
Time Computed 09-27-07
Contract Working Days 499
Addl Days Granted 0
Working Days Charged 235
Percent Time Used 47
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0017-09-092
CAPROCK SPECIALITY CONTRACTORS (0.01%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.60%)
DUSTROL, INC. (ROANOKE)(0.58%)
EVANS ENVIRONMENTAL CONTRACTING, LLC.(2.02%)
W. W. FOUNDATION DRILLING, LTD.(0.63%)
TREVCON, INC.(6.52%)
STOMPER DEMOLITION (0.20%)
L.A. UTILITIES, INC. (9.68%)
FLASHER EQUIPMENT COMPANY(1.86%)
F & W ELECTRICAL CONTRACTORS, INC. (7.12%)
SCOTT DERR PAINTING CO (0.05%)
GUAJARDO STEEL (0.08%)
SIDEWINDER DIRECTIONAL, INC. (0.02%)
AMERICAN SIGNAL EQUIPMENT CO. (SAN ANTONIO)(0.01%)
Contract # 08073003
Totals 15638408.57 621295.32 8089383.05 53.8

CountyBEXAR
Highway IH 35
From US 281
To GEORGE BEACH AVENUE
CSJ 0017-10-230
Proj ID IM 0352(314)
Work Type CONC MEDIAN BARRIER AND ILLUM
 
22.199 12075758.47 44287.22 11313794.10 93.6
Work Order 08-08-06
Work Began 10-16-06
Work Completed  
Time Computed 08-24-06
Contract Working Days 542
Addl Days Granted 35
Working Days Charged 565
Percent Time Used 97
Contractor(s)
W.W. WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-230
GEO MATRIX, LLC(0.28%)
SITESAFE PRODUCTS TEXAS(1.18%)
FUQUAY, INC. (NEW BRAUNFELS) (0.36%)
FLASHER EQUIPMENT COMPANY(0.75%)
MICA CORPORATION ( 24.48%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.82%)
MTAM CORPORATION (3.60%)
Contract # 06063020
Totals 12075758.47 44287.22 11313794.10 93.6

CountyBEXAR
Highway IH 35
From NEW BRAUNFELS AVE
To AT&T PARKWAY
CSJ 0017-10-231
Proj ID IM 0352(324)
Work Type GRADE, BASE, STR, SURF & PAV'T MRKGS
 
1.422 22554693.51 2723028.91 10388964.93 46.0
CountyBEXAR
Highway IH 35
From NEW BRAUNFELS AVE
To AT&T PARKWAY
CSJ 0017-10-247
Proj ID RW 17-10-247
Work Type ROW ACQUISITION, RELOC & UTIL ADJMT
 
1.422 24875.00 0.00 2600.00 10.4
Work Order 01-30-08
Work Began 03-17-08
Work Completed  
Time Computed 02-15-08
Contract Working Days 428
Addl Days Granted 0
Working Days Charged 167
Percent Time Used 39
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-231
FLASHER EQUIPMENT COMPANY(0.65%)
STAR OPERATIONS, INC.(8.93%)
STOMPER DEMOLITION (1.01%)
ROADWAY SPECIALTIES, INC.(0.86%)
LAND STABILIZER, LTD (2.19%)
J.D. RAMMING PAVING CO., LTD.(7.39%)
TRANSMISSION & DISTRIBUTION SOLUTIONS, LTD (0.77%)
JAVELINA CONSTRUCTION SOUTH, INC.(0.45%)
HARDY HOLE DRILLING(1.97%)
GUAJARDO STEEL (0.04%)
CRAIG OLDEN, INC.(5.53%)
Contract # 12073001
Totals 22579568.51 2723028.91 10391564.93 46.0

CountyBEXAR
Highway IH 35
From SB ML AT ABAND SPRR & FRANK ST.
To .
CSJ 0017-10-233
Proj ID BR 2008(297)
Work Type WIDEN NARROW BRIDGE & APPROACHES
 
0.092 939261.03 60430.77 492956.70 52.4
Work Order 02-20-08
Work Began 03-24-08
Work Completed  
Time Computed 03-07-08
Contract Working Days 196
Addl Days Granted 0
Working Days Charged 159
Percent Time Used 81
Contractor(s)
REESE CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-233
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.40%)
SEABERS SERVICES, L.L.C. (1.27%)
FLASHER EQUIPMENT COMPANY(0.79%)
PENNTEX MILLING, LLC (1.27%)
Contract # 01083034
Totals 939261.03 60430.77 492956.70 52.4

page 1 | page 2 | page 3 | page 4 | page 5 | page 6
 
spacer spacer
Disclaimer | Accessibility Policy | Privacy and Security Policy | Open Records | TxDOT Contacts