|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | COMAL |
| Highway |
IH 35 |
| From |
0.1 MI N OF FM 725 |
| To |
HAYS COUNTY LINE |
| CSJ |
0016-04-103 |
| Proj ID |
IM 0352(321) |
| Work Type |
CORRIDOR TRAFFIC MANAGEMENT |
| |
|
80.215 |
4594799.12 |
143089.44 |
4567831.25 |
99.9 |
| Work Order |
06-13-07 |
| Work Began |
09-05-07 |
| Work Completed |
|
| Time Computed |
06-29-07 |
| Contract Working Days |
180 |
| Addl Days Granted |
0 |
| Working Days Charged |
212 |
| Percent Time Used |
117 |
| Contractor(s) |
| J & V COMMUNICATION SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0016-04-103 TONY A. ENTERPRISES, INC.(0.27%) SIX LINE CONSTRUCTION, LLC (2.16%) CARTHAGE DRILLING, INC.(3.33%) DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.21%) BOYD & SONS, L.L.C.(0.44%)
|
| Contract # |
05073011 |
|
Totals |
4594799.12 |
143089.44 |
4567831.25 |
99.9 |
|
| County | COMAL |
| Highway |
IH 35 ETC |
| From |
SB & NB FR - HAYES COUNTY LINE |
| To |
SB & NB FR KOHLENBURGE RD |
| CSJ |
0016-04-108 |
| Proj ID |
IM 0352(325) |
| Work Type |
SEAL COAT & PAVEMENT MARKINGS |
| |
|
129.961 |
3343283.24 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
11-30-07 |
| Work Began |
05-14-08 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
105 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| CLARK CONSTRUCTION OF TEXAS, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0016-04-108 INTERSTATE BARRICADES & MARKINGS, INC. ( 29.40%)
|
| Contract # |
11073014 |
|
Totals |
3343283.24 |
0.00 |
0.00 |
0.0 |
|
| County | COMAL |
| Highway |
IH 35 |
| From |
0.189 MI S OF SCHMIDT STREET |
| To |
0.093 MI NORTH OF FM 725 |
| CSJ |
0016-05-102 |
| Proj ID |
CL 16-5-102 |
| Work Type |
IRRIGATION AND LANDSCAPING |
| |
|
2.343 |
457580.00 |
1236.82 |
382211.19 |
88.0 |
| Work Order |
10-18-05 |
| Work Began |
12-12-05 |
| Work Completed |
|
| Time Computed |
11-03-05 |
| Contract Working Days |
51 |
| Addl Days Granted |
0 |
| Working Days Charged |
52 |
| Percent Time Used |
101 |
| Contractor(s) |
| K-BAR SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0016-05-102 DIAMONDBACK LANDSCAPING AND LAWN CARE, INC.(3.13%) SIDEWINDER DIRECTIONAL, INC. (0.70%) HALL IRRIGATION SYSTEMS(8.26%) POUNDS ENTERPRISES, INC. (0.21%)
|
| Contract # |
09053022 |
|
Totals |
457580.00 |
1236.82 |
382211.19 |
88.0 |
|
| County | COMAL |
| Highway |
IH 35 |
| From |
0.40 MILES NORTH ENGEL RD |
| To |
0.55 MILES NORTH OF ENGEL RD |
| CSJ |
0016-05-104 |
| Proj ID |
NH 2007(703) |
| Work Type |
SEAL COAT, SURF, PAV'T MRK |
| |
|
0.150 |
41211.40 |
0.00 |
5250.00 |
12.7 |
| County | COMAL |
| Highway |
IH 35 |
| From |
0.18 MILES NORTH OF SCHMIDT ST |
| To |
0.35 MILES NORTH OF SCHMIDT ST |
| CSJ |
0016-05-105 |
| Proj ID |
NH 2007(703) |
| Work Type |
SEAL COAT, SURF, PAV'T MRK |
| |
|
0.170 |
63574.60 |
0.00 |
108838.26 |
99.9 |
| County | BEXAR |
| Highway |
IH 35 |
| From |
WEIDNER |
| To |
LOOP 1604 |
| CSJ |
0016-07-026 |
| Proj ID |
IM 0352(322) |
| Work Type |
MILL, OVERLAY & PAV'T MARKINGS |
| |
|
3.620 |
1151217.36 |
0.00 |
1316292.49 |
99.9 |
| County | ZERO COUNTIES |
| Highway |
|
| From |
|
| To |
|
| CSJ |
0915-12-462 |
| Proj ID |
|
| Work Type |
|
| |
|
|
0.00 |
27040.86 |
177027.35 |
0.0 |
| County | BEXAR |
| Highway |
LP 1604 |
| From |
SHIN OAK DR |
| To |
KITTY HAWK |
| CSJ |
2452-03-102 |
| Proj ID |
NH 2007(703) |
| Work Type |
GRADE, BASE, STR, SURF & PAV'T MRK |
| |
|
0.962 |
4607580.44 |
446503.98 |
4658728.57 |
99.9 |
| Work Order |
09-19-07 |
| Work Began |
10-11-07 |
| Work Completed |
|
| Time Computed |
09-15-07 |
| Contract Working Days |
270 |
| Addl Days Granted |
0 |
| Working Days Charged |
349 |
| Percent Time Used |
129 |
| Contractor(s) |
| TEXAS STERLING CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 2452-03-102 CLARK CONSTRUCTION OF TEXAS, LTD.( 17.10%) CRAIG OLDEN, INC.(5.72%) BOSQUEZ ELECTRICAL, LLC. (0.74%) DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.68%) Z-BAR TRANSPORT(4.02%) W.W. WEBBER, LLC (1.45%) ROADWAY SPECIALTIES, INC.(0.64%) UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (1.22%) SCR CONSTRUCTION CO., INC. (0.56%) CRAWFORD YANT(1.15%)
|
| Contract # |
07073219 |
|
Totals |
5863583.80 |
473544.84 |
6266136.67 |
99.9 |
|
| County | BEXAR |
| Highway |
IH 35 |
| From |
AT SH 218 |
| To |
. |
| CSJ |
0016-07-125 |
| Proj ID |
IM 0352(327) |
| Work Type |
GRAD, BASE, STR, SURF & PAV'T MRK |
| |
|
1.256 |
6610138.62 |
242847.69 |
4797902.14 |
72.5 |
| Work Order |
03-04-08 |
| Work Began |
03-13-08 |
| Work Completed |
|
| Time Computed |
03-20-08 |
| Contract Working Days |
349 |
| Addl Days Granted |
0 |
| Working Days Charged |
159 |
| Percent Time Used |
45 |
| Contractor(s) |
| HUNTER INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0016-07-125 AARON CONCRETE CONTRACTORS, L.P. (7.91%) CRAIG OLDEN, INC.(1.46%) CRAWFORD YANT(2.42%) DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.26%) FLASHER EQUIPMENT COMPANY(2.64%) L.A. UTILITIES, INC. (6.01%) THE LEVY COMPANY, L.P. ( 12.50%) PENNTEX MILLING, LLC (0.24%) ROADWAY SPECIALTIES, INC.(2.68%) SCOTT DERR PAINTING CO (0.00%) HEARN CO.(0.57%) SAN ANTONIO TELEPHONE COMPANY INC. (0.09%)
|
| Contract # |
12073206 |
|
Totals |
6610138.62 |
242847.69 |
4797902.14 |
72.5 |
|
| County | BEXAR |
| Highway |
LP 368 |
| From |
ON LP 368 (AUSTIN HWY) |
| To |
AT HARRY WURZBACH ROAD |
| CSJ |
0016-08-030 |
| Proj ID |
BR 2007(414) |
| Work Type |
REPLACE NARROW BRIDGE & APPROACHES |
| |
|
1.733 |
2236783.11 |
20992.43 |
2361634.69 |
99.9 |
| Work Order |
06-15-07 |
| Work Began |
10-01-07 |
| Work Completed |
|
| Time Computed |
10-01-07 |
| Contract Working Days |
410 |
| Addl Days Granted |
0 |
| Working Days Charged |
273 |
| Percent Time Used |
66 |
| Contractor(s) |
| CAPITAL EXCAVATION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0016-08-030 SCOTT DERR PAINTING CO (0.05%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.62%) ROADWAY SPECIALTIES, INC.(1.17%) THE LEVY COMPANY, L.P. (1.00%) J.D. RAMMING PAVING CO., LTD.( 10.61%) FUQUAY, INC. (0.47%) FLASHER EQUIPMENT COMPANY(2.59%) 76 MILLING, INC. (0.78%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.51%) VOGES DRILLING (3.57%) GEO MATRIX, LLC(0.16%)
|
| Contract # |
04073229 |
|
Totals |
2236783.11 |
20992.43 |
2361634.69 |
99.9 |
|
| County | COMAL |
| Highway |
BI 35-H |
| From |
AT GUADALUPE RIVER |
| To |
. |
| CSJ |
0016-11-015 |
| Proj ID |
BR 2007(588) |
| Work Type |
REHABILITATE NARROW BDGE & APPRS |
| |
|
0.194 |
517888.50 |
72181.68 |
430778.54 |
83.1 |
| Work Order |
07-26-07 |
| Work Began |
05-28-08 |
| Work Completed |
|
| Time Computed |
08-11-07 |
| Contract Working Days |
65 |
| Addl Days Granted |
20 |
| Working Days Charged |
85 |
| Percent Time Used |
100 |
| Contractor(s) |
| DEAN WORD COMPANY, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0016-11-015 PRIMATE CONSTRUCTION, INC. ( 13.93%) S & S PAINTING (2.15%) FLASHER EQUIPMENT COMPANY(1.38%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.( 13.14%) JAVELINA CONSTRUCTION SOUTH, INC.(1.17%)
|
| Contract # |
06073210 |
|
Totals |
517888.50 |
72181.68 |
430778.54 |
83.1 |
|
| County | BEXAR |
| Highway |
IH 35 |
| From |
SB COLLECTOR RD 0.4 MI S OF IH 410 |
| To |
0.22 MI N OF IH 410 |
| CSJ |
0017-02-059 |
| Proj ID |
BR 2007(707) |
| Work Type |
RAISE & WIDEN NARROW BRIDGE & APP |
| |
|
0.550 |
5086578.23 |
236968.62 |
4446672.59 |
87.4 |
| Work Order |
08-09-07 |
| Work Began |
09-17-07 |
| Work Completed |
|
| Time Computed |
08-25-07 |
| Contract Working Days |
318 |
| Addl Days Granted |
0 |
| Working Days Charged |
282 |
| Percent Time Used |
88 |
| Contractor(s) |
| CAPITAL EXCAVATION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0017-02-059 HIGHWAY PAVEMENT SPECIALTIES, INC. (0.15%) ATS DRILLING, L.P. (5.21%) DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.56%) FLASHER EQUIPMENT COMPANY(4.50%) GEOSOURCE, INC.(0.86%) J.D. RAMMING PAVING CO., LTD.(9.74%) THE LEVY COMPANY, L.P. (0.60%) GIBSON & ASSOCIATES, INC.(7.32%) SCOTT DERR PAINTING CO (0.15%) INDUS CONSTRUCTION, L.P. (0.32%) S & S PAINTING (2.69%) AARON CONCRETE CONTRACTORS, L.P. (1.39%) PENNTEX MILLING INC. (0.37%)
|
| Contract # |
07073029 |
|
Totals |
5086578.23 |
236968.62 |
4446672.59 |
87.4 |
|
| County | BEXAR |
| Highway |
IH 35 ETC |
| From |
VARIOUS LOCATIONS DISTRICTWIDE |
| To |
. |
| CSJ |
0017-02-064 |
| Proj ID |
C 17-2-64 |
| Work Type |
OSB REPAIR |
| |
|
73.354 |
1650640.93 |
876.87 |
1735612.46 |
99.9 |
| Work Order |
11-15-05 |
| Work Began |
03-13-06 |
| Work Completed |
|
| Time Computed |
12-01-05 |
| Contract Working Days |
240 |
| Addl Days Granted |
57 |
| Working Days Charged |
296 |
| Percent Time Used |
99 |
| Contractor(s) |
| THE LEVY COMPANY, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0017-02-064 FUQUAY INC (SAN ANTONIO) (0.20%) FLASHER EQUIPMENT COMPANY(5.11%) JCD CONSTRUCTION, LLC(9.32%)
|
| Contract # |
10053016 |
|
Totals |
1650640.93 |
876.87 |
1735612.46 |
99.9 |
|
| County | BEXAR |
| Highway |
IH 35 |
| From |
IH 35S |
| To |
@ IH 410 |
| CSJ |
0017-02-068 |
| Proj ID |
IM 0352(323) |
| Work Type |
LANDSCAPE DEVELOPMENT |
| |
|
0.600 |
331759.14 |
1400.00 |
277612.97 |
83.9 |
| Work Order |
10-18-07 |
| Work Began |
01-07-08 |
| Work Completed |
|
| Time Computed |
11-05-07 |
| Contract Working Days |
72 |
| Addl Days Granted |
0 |
| Working Days Charged |
74 |
| Percent Time Used |
102 |
| Contractor(s) |
| LEGENDS LANDSCAPES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0017-02-068 LONE STAR TRAFFIC SERVICE, INC.(1.65%) CAL-PERK UNDERGROUND UTILITIES (0.96%) POENITZSCH BACKHOE SERVICE, INC. (3.01%) GREEN GRASS, INC.( 15.19%)
|
| Contract # |
09073018 |
|
Totals |
331759.14 |
1400.00 |
277612.97 |
83.9 |
|
| County | BEXAR |
| Highway |
IH 35 |
| From |
OLD QUINTANA RD. |
| To |
FISCHER RD. |
| CSJ |
0017-02-071 |
| Proj ID |
IM 0352(328) |
| Work Type |
GRAD, BASE, STR, SURF, & PAV'T MRKNGS |
| |
|
1.989 |
8385286.16 |
653503.84 |
2704098.54 |
32.2 |
| Work Order |
03-18-08 |
| Work Began |
05-19-08 |
| Work Completed |
|
| Time Computed |
04-03-08 |
| Contract Working Days |
383 |
| Addl Days Granted |
0 |
| Working Days Charged |
117 |
| Percent Time Used |
30 |
| Contractor(s) |
| HUNTER INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0017-02-071 L.A. UTILITIES, INC. (7.44%) ROADWAY SPECIALTIES, INC.(3.75%) SCOTT DERR PAINTING CO (0.32%) W. W. FOUNDATION DRILLING, LTD.(1.47%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.37%) STOMPER DEMOLITION (0.74%) MURRAY CONSTRUCTION(0.42%) JAVELINA CONSTRUCTION SOUTH, INC.(0.29%) GUAJARDO STEEL (0.23%) CRAWFORD YANT(1.48%) CAPROCK SPECIALITY CONTRACTORS (0.05%) STAR OPERATIONS, INC.(3.47%) FLASHER EQUIPMENT COMPANY(1.49%)
|
| Contract # |
01083003 |
|
Totals |
8385286.16 |
653503.84 |
2704098.54 |
32.2 |
|
| County | ATASCOSA |
| Highway |
IH 35 |
| From |
MEDINA/ATASCOSA COUNTY LINE |
| To |
ATASCOSA/BEXAR COUNTY LINE |
| CSJ |
0017-04-035 |
| Proj ID |
IM 0352(317) |
| Work Type |
PAV REPAIR, SC, SMA, & PAVT MRKNGS |
| |
|
22.335 |
9212798.87 |
3048687.50 |
8519419.65 |
92.4 |
| Work Order |
10-12-07 |
| Work Began |
12-05-07 |
| Work Completed |
|
| Time Computed |
04-01-08 |
| Contract Working Days |
106 |
| Addl Days Granted |
0 |
| Working Days Charged |
96 |
| Percent Time Used |
90 |
| Contractor(s) |
| H. L. ZUMWALT CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0017-04-035 FLASHER EQUIPMENT COMPANY(2.13%)
|
| Contract # |
09073004 |
|
Totals |
9212798.87 |
3048687.50 |
8519419.65 |
92.4 |
|
| County | ATASCOSA |
| Highway |
IH 35 ETC |
| From |
FM 3175 |
| To |
FM 2790 |
| CSJ |
0017-04-039 |
| Proj ID |
IM 0352(329) |
| Work Type |
SEAL COAT & PAVEMENT MARKINGS |
| |
|
182.683 |
6799541.03 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
120 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| BRANNAN PAVING CO., LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0017-04-039 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11083215 |
|
Totals |
6799541.03 |
0.00 |
0.00 |
0.0 |
|
| County | FRIO |
| Highway |
IH 35 |
| From |
EAST FRONTAGE RD AT FRIO RIVER |
| To |
. |
| CSJ |
0017-07-088 |
| Proj ID |
BR 2007(779) |
| Work Type |
WIDEN NARROW BRIDGE & APPROACHES |
| |
|
0.182 |
676442.48 |
3003.41 |
674160.37 |
99.6 |
| Work Order |
11-07-07 |
| Work Began |
02-11-08 |
| Work Completed |
|
| Time Computed |
11-23-07 |
| Contract Working Days |
131 |
| Addl Days Granted |
4 |
| Working Days Charged |
123 |
| Percent Time Used |
91 |
| Contractor(s) |
| SALINAS CONSTRUCTION TECHNOLOGIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0017-07-088 LONE STAR TRAFFIC SERVICE, INC.(1.07%) ATS DRILLING, L.P. ( 11.75%) FLASHER EQUIPMENT COMPANY(0.50%) DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.88%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(4.39%) JAVELINA CONSTRUCTION SOUTH, INC.(1.53%)
|
| Contract # |
10073225 |
|
Totals |
676442.48 |
3003.41 |
674160.37 |
99.6 |
|
| County | BEXAR |
| Highway |
IH 35 |
| From |
@ THEO AND MALONE, DIVISION AVE |
| To |
AND SOUTHCROSS BLVD |
| CSJ |
0017-09-072 |
| Proj ID |
BR 2006(590) |
| Work Type |
REHABILITATE BRIDGES & APPROACHES |
| |
|
0.001 |
6049301.93 |
62333.97 |
5654221.88 |
94.9 |
| County | BEXAR |
| Highway |
IH 35 |
| From |
US 90 |
| To |
ZARZAMORA STREET |
| CSJ |
0017-09-085 |
| Proj ID |
C 17-9-85 |
| Work Type |
OPERATIONAL IMPROVEMENTS |
| |
|
3.551 |
23041451.20 |
1747093.12 |
22765923.65 |
98.8 |
| Work Order |
09-15-06 |
| Work Began |
10-23-06 |
| Work Completed |
|
| Time Computed |
10-01-06 |
| Contract Working Days |
400 |
| Addl Days Granted |
42 |
| Working Days Charged |
486 |
| Percent Time Used |
109 |
| Contractor(s) |
| AUSTIN BRIDGE & ROAD, LP |
SUBCONTRACTOR(S) FOR CCSJ: 0017-09-072 TREVCON, INC.(2.58%) CHEROKEE SERVICES(0.36%) AARON CONCRETE CONTRACTORS, L.P. (1.91%) DUSTROL, INC. (ROANOKE)(0.54%) FLASHER EQUIPMENT COMPANY(1.32%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.22%) LANDSCAPE CONTRACTING AND IRRIGATION, INC. (0.63%) ROADWAY SPECIALTIES, INC.(0.28%) HOUSTON SAWING & DRILLING(0.04%) TEXAS CURB CUT, INC.(HUB)(0.45%) STOMPER DEMOLITION (1.09%) LEVY COMPANY (9.29%) MICA CORPORATION (6.87%) W. W. FOUNDATION DRILLING, LTD.(3.22%) SCOTT DERR PAINTING CO (0.07%) J.L. STEEL, L.P. (0.51%) DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.95%) E & E STEEL(0.13%) HEARN CO.(0.03%) GEO MATRIX, LLC(0.15%)
|
| Contract # |
06063206 |
|
Totals |
29090753.13 |
1809427.09 |
28420145.53 |
97.9 |
|
| County | BEXAR |
| Highway |
IH 35 |
| From |
AT SP 422 |
| To |
. |
| CSJ |
0017-09-087 |
| Proj ID |
C 17-9-87 |
| Work Type |
LANDSCAPE DEVELOPMENT |
| |
|
0.001 |
565172.25 |
2450.00 |
493659.41 |
89.2 |
| Work Order |
02-17-06 |
| Work Began |
03-13-06 |
| Work Completed |
|
| Time Computed |
03-05-06 |
| Contract Working Days |
89 |
| Addl Days Granted |
0 |
| Working Days Charged |
90 |
| Percent Time Used |
101 |
| Contractor(s) |
| CARRUTH NURSERY IRRIGATION & LANDSCAPE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0017-09-087 BARTEK CONSTRUCTION CO.(0.07%)
|
| Contract # |
01063215 |
|
Totals |
565172.25 |
2450.00 |
493659.41 |
89.2 |
|
| County | BEXAR |
| Highway |
IH 35 |
| From |
AT SP 422 |
| To |
. |
| CSJ |
0017-09-092 |
| Proj ID |
C 17-9-92 |
| Work Type |
GRAD, STR, BASE, SC, OV & PAV'T MRKS |
| |
|
2.116 |
15638408.57 |
621295.32 |
8089383.05 |
53.8 |
| Work Order |
09-11-07 |
| Work Began |
09-27-07 |
| Work Completed |
|
| Time Computed |
09-27-07 |
| Contract Working Days |
499 |
| Addl Days Granted |
0 |
| Working Days Charged |
235 |
| Percent Time Used |
47 |
| Contractor(s) |
| HUNTER INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0017-09-092 CAPROCK SPECIALITY CONTRACTORS (0.01%) DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.60%) DUSTROL, INC. (ROANOKE)(0.58%) EVANS ENVIRONMENTAL CONTRACTING, LLC.(2.02%) W. W. FOUNDATION DRILLING, LTD.(0.63%) TREVCON, INC.(6.52%) STOMPER DEMOLITION (0.20%) L.A. UTILITIES, INC. (9.68%) FLASHER EQUIPMENT COMPANY(1.86%) F & W ELECTRICAL CONTRACTORS, INC. (7.12%) SCOTT DERR PAINTING CO (0.05%) GUAJARDO STEEL (0.08%) SIDEWINDER DIRECTIONAL, INC. (0.02%) AMERICAN SIGNAL EQUIPMENT CO. (SAN ANTONIO)(0.01%)
|
| Contract # |
08073003 |
|
Totals |
15638408.57 |
621295.32 |
8089383.05 |
53.8 |
|
| County | BEXAR |
| Highway |
IH 35 |
| From |
US 281 |
| To |
GEORGE BEACH AVENUE |
| CSJ |
0017-10-230 |
| Proj ID |
IM 0352(314) |
| Work Type |
CONC MEDIAN BARRIER AND ILLUM |
| |
|
22.199 |
12075758.47 |
44287.22 |
11313794.10 |
93.6 |
| Work Order |
08-08-06 |
| Work Began |
10-16-06 |
| Work Completed |
|
| Time Computed |
08-24-06 |
| Contract Working Days |
542 |
| Addl Days Granted |
35 |
| Working Days Charged |
565 |
| Percent Time Used |
97 |
| Contractor(s) |
| W.W. WEBBER, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-230 GEO MATRIX, LLC(0.28%) SITESAFE PRODUCTS TEXAS(1.18%) FUQUAY, INC. (NEW BRAUNFELS) (0.36%) FLASHER EQUIPMENT COMPANY(0.75%) MICA CORPORATION ( 24.48%) DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.82%) MTAM CORPORATION (3.60%)
|
| Contract # |
06063020 |
|
Totals |
12075758.47 |
44287.22 |
11313794.10 |
93.6 |
|
| County | BEXAR |
| Highway |
IH 35 |
| From |
NEW BRAUNFELS AVE |
| To |
AT&T PARKWAY |
| CSJ |
0017-10-231 |
| Proj ID |
IM 0352(324) |
| Work Type |
GRADE, BASE, STR, SURF & PAV'T MRKGS |
| |
|
1.422 |
22554693.51 |
2723028.91 |
10388964.93 |
46.0 |
| County | BEXAR |
| Highway |
IH 35 |
| From |
NEW BRAUNFELS AVE |
| To |
AT&T PARKWAY |
| CSJ |
0017-10-247 |
| Proj ID |
RW 17-10-247 |
| Work Type |
ROW ACQUISITION, RELOC & UTIL ADJMT |
| |
|
1.422 |
24875.00 |
0.00 |
2600.00 |
10.4 |
| Work Order |
01-30-08 |
| Work Began |
03-17-08 |
| Work Completed |
|
| Time Computed |
02-15-08 |
| Contract Working Days |
428 |
| Addl Days Granted |
0 |
| Working Days Charged |
167 |
| Percent Time Used |
39 |
| Contractor(s) |
| DAN WILLIAMS COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-231 FLASHER EQUIPMENT COMPANY(0.65%) STAR OPERATIONS, INC.(8.93%) STOMPER DEMOLITION (1.01%) ROADWAY SPECIALTIES, INC.(0.86%) LAND STABILIZER, LTD (2.19%) J.D. RAMMING PAVING CO., LTD.(7.39%) TRANSMISSION & DISTRIBUTION SOLUTIONS, LTD (0.77%) JAVELINA CONSTRUCTION SOUTH, INC.(0.45%) HARDY HOLE DRILLING(1.97%) GUAJARDO STEEL (0.04%) CRAIG OLDEN, INC.(5.53%)
|
| Contract # |
12073001 |
|
Totals |
22579568.51 |
2723028.91 |
10391564.93 |
46.0 |
|
| County | BEXAR |
| Highway |
IH 35 |
| From |
SB ML AT ABAND SPRR & FRANK ST. |
| To |
. |
| CSJ |
0017-10-233 |
| Proj ID |
BR 2008(297) |
| Work Type |
WIDEN NARROW BRIDGE & APPROACHES |
| |
|
0.092 |
939261.03 |
60430.77 |
492956.70 |
52.4 |
| Work Order |
02-20-08 |
| Work Began |
03-24-08 |
| Work Completed |
|
| Time Computed |
03-07-08 |
| Contract Working Days |
196 |
| Addl Days Granted |
0 |
| Working Days Charged |
159 |
| Percent Time Used |
81 |
| Contractor(s) |
| REESE CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-233 M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.40%) SEABERS SERVICES, L.L.C. (1.27%) FLASHER EQUIPMENT COMPANY(0.79%) PENNTEX MILLING, LLC (1.27%)
|
| Contract # |
01083034 |
|
Totals |
939261.03 |
60430.77 |
492956.70 |
52.4 |
|