Monthly State Let Construction Report For San Antonio District As Of Dec 10, 2014 Page 1 Of 6

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCOMAL
Highway IH 35
From FM 306
To CONRADS/KOLHENBURG RD
CSJ 0016-04-104
Proj ID NH 2014(725)
Work Type GRAD, BASE, STR, PAVMNT MRKNGS
 
1.921 4156514.87 0.00 502292.38 12.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-21-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 251
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 9
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0016-04-104
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.32%)
DUSTROL, INC.(0.45%)
ENVIRONMENTAL SAFETY SERVICES, INC.(3.90%)
FLASHER EQUIPMENT COMPANY(2.20%)
GEOSOURCE, INC.(0.53%)
RAMMING PAVING COMPANY ( 19.79%)
RICE ENVIRONMENTAL SERVICES(0.27%)
S & S BRIDGE PAINTING, INC.(0.03%)
THE LEVY COMPANY, L.P. (3.49%)
Contract # 06143209
Totals 4156514.87 0.00 502292.38 12.0

CountyCOMAL
Highway IH 35 ETC
From KOHLENBERG ROAD
To COMAL/HAYES COUNTY LINE
CSJ 0016-04-110
Proj ID NH 2015(282)
Work Type SEAL COAT AND PAVEMENT MARKINGS
 
141.699 4769259.73 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-05-14
Work Began 00-00-00
Work Completed  
Time Computed 12-21-14
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0016-04-110
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143010
Totals 4769259.73 0.00 0.00 0.0

CountyCOMAL
Highway IH 35
From GUADALUPE / COMAL COUNTY LINE
To SOLMS RD
CSJ 0016-05-106
Proj ID IM 0352(345)
Work Type SEAL COAT, PFC OVERLAY, & PAV MRK
 
6.503 4541084.72 575922.25 3741182.06 83.7
CountyGUADALUPE
Highway IH 35
From 0.5 MI S OF FM 3009
To GUADALUPE / COMAL COUNTY LINE
CSJ 0016-06-045
Proj ID IM 0352(345)
Work Type SEAL COAT, PFC OVERLAY & PAV MRK
 
1.834 1306914.55 118807.21 1205043.12 92.2
Work Order 12-10-13
Work Began 04-08-14
Work Completed  
Time Computed 02-10-14
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 139
Percent Time Used 169
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0016-05-106
CHEROKEE SERVICES(0.92%)
FLASHER EQUIPMENT COMPANY(3.05%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.31%)
CLAUDIA SERNA DBA SERNA"S TRUCKING (5.69%)
Contract # 09133217
Totals 5847999.27 694729.46 4946225.18 85.6

CountyCOMAL
Highway IH 35
From AT LP 337 INTERSECTION
To .
CSJ 0016-05-107
Proj ID IM 0352(347)
Work Type RECONFIGURE INTERSECTION
 
0.206 2452584.01 321697.13 2407848.93 98.2
Work Order 02-12-14
Work Began 04-21-14
Work Completed  
Time Computed 04-21-14
Contract Working Days 149
Addl Days Granted 4
Working Days Charged 155
Percent Time Used 101
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0016-05-107
D. I. J. CONSTRUCTION, INC.(3.59%)
E-Z BEL CONSTRUCTION, LLC( 12.20%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.86%)
ROADWAY SPECIALTIES, INC.(8.27%)
TEXAS CUTTING & CORING, INC. (0.35%)
HEARN CO.(1.60%)
SAECO ELECTRIC & UTILITY, LTD. (0.07%)
CATO ELECTRIC COMPANY(0.02%)
S & S BRIDGE PAINTING, INC.(0.09%)
SURMAC, INC(0.27%)
Contract # 12133009
Totals 2452584.01 321697.13 2407848.93 98.2

CountyGUADALUPE
Highway IH 35
From BEXAR / GUADALUPE COUNTY LINE
To FM 3009
CSJ 0016-06-046
Proj ID C 16-6-46
Work Type GR, BS, STR, SURF, OVERLAY
 
2.076 9163402.10 626545.89 9732363.24 99.9
CountyBEXAR
Highway IH 35
From JUDSON ROAD
To GUADALUPE / BEXAR COUNTY LINE
CSJ 0016-07-129
Proj ID C 16-7-129
Work Type GR, BS, STR, SURF, OVERLAY
 
3.719 12427317.34 5111.76 12989940.15 99.9
Work Order 09-18-12
Work Began 10-08-12
Work Completed  
Time Computed 10-08-12
Contract Working Days 321
Addl Days Granted 136
Working Days Charged 457
Percent Time Used 100
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0016-06-046
JUST GROOVING, LTD.(0.04%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.15%)
VOGES DRILLING CO. (0.48%)
SCOTT DERR PAINTING CO, LLC(0.11%)
GK CONSTRUCTION, LLC (0.26%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.05%)
FLASHER EQUIPMENT COMPANY(2.33%)
THE LEVY COMPANY, L.P. (5.67%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.10%)
ANGEL BROTHERS ENTERPRISES, LTD. ( 42.24%)
LIGHT IT UP ELECTRIC (0.07%)
CATO DRILLING COMPANY(0.01%)
R K STEPHENS CONSTRUCTION, LLC (0.43%)
Contract # 08123037
Totals 21590719.44 631657.65 22722303.39 99.9

CountyBEXAR
Highway IH 35
From 0.2 MI N OF TOEPPERWEIN RD
To 0.2 MI S OF LOOP 1604
CSJ 0016-07-132
Proj ID IM 0352(341)
Work Type LANDSCAPE DEVELOPMENT
 
0.800 287874.50 65563.22 157669.49 54.7
Work Order 05-13-13
Work Began 10-20-14
Work Completed  
Time Computed 07-22-13
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 28
Contractor(s)
ALTEX LANDSCAPE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0016-07-132
N-LINE TRAFFIC MAINTENANCE, L.P. (1.72%)
Contract # 02133206
Totals 287874.50 65563.22 157669.49 54.7

CountyCOMAL
Highway BS 46-C
From IN NEW BRAUNFELS FROM KESSLER ST
To HAMPE ST AT UP RR
CSJ 0016-10-022
Proj ID C 16-10-22
Work Type GR, STRS, BASE & SURF
 
0.324 9677386.78 155.70 9681852.73 99.9
Work Order 11-09-12
Work Began 01-07-13
Work Completed  
Time Computed 01-07-13
Contract Working Days 243
Addl Days Granted 62
Working Days Charged 290
Percent Time Used 95
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0016-10-022
VOGES DRILLING CO. (4.47%)
ROADWAY SPECIALTIES, INC.(2.22%)
THE LEVY COMPANY, L.P. (2.92%)
R K STEPHENS CONSTRUCTION, LLC (2.70%)
HIGHWAY TECHNOLOGIES, INC. (0.64%)
ANGEL BROTHERS ENTERPRISES, LTD. (8.96%)
FLASHER EQUIPMENT COMPANY(0.56%)
Contract # 08123009
Totals 9677386.78 155.70 9681852.73 99.9

CountyBEXAR
Highway IH 35
From AT MEDINA RIVER (NB)
To .
CSJ 0017-02-075
Proj ID BR 2013(030)
Work Type GRAD, BSE, STR, SURFACE, PAV'T MRK
 
0.294 6192762.50 0.00 6325366.84 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-01-12
Work Began 01-02-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 190
Addl Days Granted 37
Working Days Charged 278
Percent Time Used 122
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0017-02-075
F & W ELECTRICAL CONTRACTORS, INC. (0.62%)
RAMMING PAVING COMPANY (9.87%)
FARR FOUNDATION, INC.(3.34%)
ROADWAY SPECIALTIES, INC.(1.03%)
VOGES DRILLING CO. (3.55%)
HIGHWAY TECHNOLOGIES, INC. (0.69%)
GK CONSTRUCTION, LLC (3.36%)
HOUSTON SAWING & DRILLING(0.09%)
FLASHER EQUIPMENT COMPANY(0.32%)
Z & L CONCRETE CONTRACTORS, INC. (2.50%)
FRANK JR REINFORCEMENT LLC (0.24%)
Contract # 09123205
Totals 6192762.50 0.00 6325366.84 99.9

CountyMEDINA
Highway IH 35
From FM 3176
To SH 173
CSJ 0017-05-092
Proj ID C 17-5-92
Work Type GRAD, BSE, SURF, PAVMNT MRK, SIGNS
 
0.733 1564899.84 0.00 1426384.47 91.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-26-13
Work Began 11-01-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 190
Addl Days Granted 12
Working Days Charged 201
Percent Time Used 99
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0017-05-092
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.74%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.51%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.85%)
FLASHER EQUIPMENT COMPANY(0.94%)
MURRAY CONSTRUCTION(0.70%)
Contract # 07133030
Totals 1564899.84 0.00 1426384.47 91.1

CountyMEDINA
Highway IH 35
From AT FM 471
To .
CSJ 0017-05-093
Proj ID IM 0352(348)
Work Type GRAD, BSE, SURF, PVMT MARKINGS
 
0.570 1339998.78 0.00 1495823.64 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-03-14
Work Began 03-10-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 127
Addl Days Granted 34
Working Days Charged 155
Percent Time Used 96
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0017-05-093
DOUBLE S PAVING, INC.(3.93%)
FLASHER EQUIPMENT COMPANY(2.51%)
ROADWAY SPECIALTIES, INC.(3.57%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.34%)
Contract # 12133218
Totals 1339998.78 0.00 1495823.64 99.9

CountyFRIO
Highway IH 35
From FM 140
To FM 1581
CSJ 0017-07-130
Proj ID IM 0352(346)
Work Type GRAD, BSE, STR, SURF, PAV'T MRK
 
1.302 3224249.18 0.00 2691391.89 83.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 219
Addl Days Granted 0
Working Days Charged 165
Percent Time Used 75
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-07-130
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.72%)
WEST TEXAS RUMBLE STRIP(0.10%)
RICE ENVIRONMENTAL SERVICES(0.25%)
ROADWAY SPECIALTIES, INC.(2.15%)
STAR OPERATIONS, INC.(7.44%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.53%)
Contract # 10133210
Totals 3224249.18 0.00 2691391.89 83.4

CountyFRIO
Highway IH 35 ETC
From FRONTAGE RDS AT FM 117
To .
CSJ 0017-07-132
Proj ID IM 0352(344)G
Work Type TRAFFIC CONTROL DEVICE
 
0.007 593552.46 17865.15 139885.24 23.5
Work Order 12-03-13
Work Began 07-15-14
Work Completed  
Time Computed 03-03-14
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 73
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-07-132
VACA UNDERGROUND UTILITIES INC (1.78%)
UNITED PAVEMENT & MARKINGS, LLC(3.30%)
YORK & YORK FOUNDATION DRILLING, INC.( 12.06%)
THOMPSON"S CONSTRUCTION STR DESIGNS( 20.92%)
M & M STRIPING & POWER WASHING, LLC(6.10%)
CATO DRILLING COMPANY(2.51%)
GREEN LIGHT IN THE GROUND(2.57%)
Contract # 09133219
Totals 593552.46 17865.15 139885.24 23.5

CountyBEXAR
Highway IH 35
From 0.2 MILES NORTH OF US 90
To 0.2 MILES SOUTH OF US 90
CSJ 0017-09-096
Proj ID NH 2014(622)
Work Type LANDSCAPE DEVELOPMENT
 
0.377 748708.00 3000.00 9548.00 1.2
Work Order 06-13-14
Work Began 10-22-14
Work Completed  
Time Computed 08-12-14
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 8
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-09-096
ALTUS TRAFFIC MANAGEMENT LLC (0.65%)
Contract # 05143018
Totals 748708.00 3000.00 9548.00 1.2

CountyBEXAR
Highway IH 35
From VARIOUS LOCATIONS ON IH 35
To LAREDO ST TO 0.2 MI W OF IH 37
CSJ 0017-10-253
Proj ID BR 2013(757)
Work Type STRUCTURE REPAIR
 
2.867 7975735.00 0.00 4133654.52 51.8
CountyBEXAR
Highway IH 10
From VARIOUS LOCATIONS ON IH 10
To MULBERRY TO POPLAR ST
CSJ 0072-12-193
Proj ID BR 2013(757)
Work Type STRUCTURE REPAIR
 
1.792 2727430.00 0.00 535853.72 19.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-13
Work Began 02-14-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 558
Addl Days Granted 0
Working Days Charged 201
Percent Time Used 36
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-253
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. ( 69.61%)
FLASHER EQUIPMENT COMPANY(0.42%)
Contract # 09133211
Totals 10703165.00 0.00 4669508.24 43.6

CountyBEXAR
Highway IH 35
From IH 410 SOUTH
To IH 410 NORTH
CSJ 0017-10-261
Proj ID IM 0352(342)
Work Type REFIG INTER, RMP, FRT & ML OP IMPRV
 
4.686 34249407.46 702789.57 13949101.49 40.7
CountyBEXAR
Highway IH 35
From AT IH 410 S
To .
CSJ 0017-10-264
Proj ID IM 0352(342)
Work Type GRAD, BSE, STR, SURF, SIGN, PAV'T MRK
 
3.115 26946957.79 730633.48 11379695.29 42.2
Work Order 10-24-13
Work Began 11-11-13
Work Completed  
Time Computed 11-09-13
Contract Working Days 916
Addl Days Granted 0
Working Days Charged 313
Percent Time Used 34
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-261
PANTHER CREEK TRANSPORTATION, INC. (1.87%)
JAG PUBLIC SAFETY, LLC (0.11%)
J. R. (JOE) RAMON & SONS, INC. (0.26%)
FARR FOUNDATION, INC.(0.66%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09%)
TEXAS HIGHWAY WALLS(6.19%)
DU MOR ENTERPRISES (0.71%)
HOUSTON SAWING & DRILLING(0.01%)
BOMANITE OF AUSTIN, LTD DBA TEXAS BOMANITE (0.04%)
M & M STRIPING & POWER WASHING, LLC(0.08%)
FLASHER EQUIPMENT COMPANY(0.85%)
CP REBAR AND PT INSTALLATION ( 11.66%)
RAMMING PAVING COMPANY ( 13.98%)
ROADWAY SPECIALTIES, INC.(1.18%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (3.41%)
THE LEVY COMPANY, L.P. (7.92%)
W. W. FOUNDATION DRILLING, LTD.(1.00%)
TEXSTAR ENTERPRISES, INC.(0.62%)
ROADWAY SPECIALTIES, INC.(0.16%)
LIGHT IT UP ELECTRIC (0.20%)
CATO DRILLING COMPANY(0.07%)
S & S BRIDGE PAINTING, INC.(0.47%)
G MARIN REBAR, INC.(0.00%)
CALAME CONTRACTING, LLC(0.43%)
WEBBER BARRIER SERVICES, LLC.(3.44%)
GW HAULERS, LLC(0.98%)
Contract # 07133001
Totals 61196365.25 1433423.05 25328796.78 41.3

CountyBEXAR
Highway IH 35
From US 281
To 0.5 MI N OF US 281
CSJ 0017-10-268
Proj ID STP 1402(062)MM
Work Type GRD, BSE, SURF, PAV T MRKS & SIGNS
 
0.460 2120939.05 16800.00 16800.00 0.7
Work Order 09-30-14
Work Began 00-00-00
Work Completed  
Time Computed 11-29-14
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-268
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143207
Totals 2120939.05 16800.00 16800.00 0.7

CountyBEXAR
Highway IH 35
From 1.1 MI S OF IH 410 SOUTH CONNECTOR
To IH 410 SOUTH CONNECTOR
CSJ 0017-10-269
Proj ID STP 1402(063)MM
Work Type GRD, BSE, SURF, PAV T MRKS & SIGNS
 
0.950 8209726.77 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-09-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 222
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-269
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143009
Totals 8209726.77 0.00 0.00 0.0

CountyBEXAR
Highway IH 35
From 0.8 MI S OF US 281
To 0.1 MI S OF US 281
CSJ 0017-10-271
Proj ID STP 1402(064)MM
Work Type MED BARRIER, PAV'T MRKS AND SIGNING
 
0.770 2254455.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-271
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143209
Totals 2254455.70 0.00 0.00 0.0

CountyFRIO
Highway SP 581 ETC
From FM 1582
To IH 35 SB FRONTAGE ROAD
CSJ 0017-15-022
Proj ID STP 2014(220)
Work Type SEAL COAT & PAVEMENT MARKINGS
 
145.708 3663584.27 0.00 3701837.21 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-13
Work Began 09-10-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 146
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 23
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-15-022
INTERSTATE BARRICADES & MARKINGS, INC. ( 15.68%)
Contract # 11133007
Totals 3663584.27 0.00 3701837.21 99.9

CountyUVALDE
Highway US 90
From KINNEY COUNTY LINE
To FM 481
CSJ 0023-05-081
Proj ID STP 2015(367)HES
Work Type GRAD, END TREAT, RAISED PAV'T MRK
 
18.618 1411820.64 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ACE ASPHALT OF ARIZONA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0023-05-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143227
Totals 1411820.64 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6