Monthly State Let Construction Report For San Antonio District As Of Apr 11, 2016 Page 2 Of 6

Last Update: Monday, April 11, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBEXAR
Highway IH 10 ETC
From 0.2 MI WEST OF GRAYTOWN
To 0.2 MI EAST OF PFEIL
CSJ 0025-02-201
Proj ID STP 2015(195)HESG
Work Type SAFETY LIGHTING
 
13.723 2712741.65 182707.00 2460495.44 90.7
Work Order 11-14-14
Work Began 02-17-15
Work Completed  
Time Computed 02-12-15
Contract Working Days 234
Addl Days Granted 0
Working Days Charged 227
Percent Time Used 97
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-201
DS TEXAS ICON CONSTRUCTION (0.59%)
FLASHER EQUIPMENT COMPANY(0.51%)
CALAME CONTRACTING, LLC(3.66%)
Contract # 10143002
Totals 2712741.65 182707.00 2460495.44 90.7

CountyBEXAR
Highway FM 78 ETC
From AT WALZEM
To .
CSJ 0025-09-075
Proj ID STP 2014(981)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.703 356499.50 18002.17 406874.69 99.9
Work Order 08-20-14
Work Began 06-01-15
Work Completed  
Time Computed 11-18-14
Contract Working Days 73
Addl Days Granted 0
Working Days Charged 72
Percent Time Used 98
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0025-09-075
ALAMO CRANE SERVICE, INC.(1.82%)
HEARN CO.(1.45%)
CATO ELECTRIC COMPANY(2.83%)
FLASHER EQUIPMENT COMPANY(3.83%)
Contract # 07143045
Totals 356499.50 18002.17 406874.69 99.9

CountyBEXAR
Highway FM 78
From AT LP 1604
To .
CSJ 0025-09-076
Proj ID STP 2015(580)HES
Work Type GR, BASE, SURF, PAVMT MRKRS, SIGNALS
 
0.106 2187618.06 40313.40 1157181.53 53.9
Work Order 03-20-15
Work Began 00-00-00
Work Completed  
Time Computed 06-18-15
Contract Working Days 212
Addl Days Granted 0
Working Days Charged 158
Percent Time Used 74
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-09-076
E-Z BEL CONSTRUCTION, LLC(7.29%)
RICE ENVIRONMENTAL SERVICES(2.09%)
INTERSTATE BARRICADES & MARKINGS, INC. (3.08%)
FLASHER EQUIPMENT COMPANY(0.54%)
LONE STAR PAVING ( 29.07%)
Contract # 02153004
Totals 2187618.06 40313.40 1157181.53 53.9

CountyGUADALUPE
Highway FM 78
From SANTA CLARA CREEK, WEST OF MARION
To SANTA CLARA CREEK, EAST OF MARION
CSJ 0025-10-073
Proj ID STP 2013(348)
Work Type GRAD, STRS, BASE & SURF
 
1.080 4136146.75 0.00 4683738.15 99.9
Work Order 07-16-13
Work Began 11-11-13
Work Completed  
Time Computed 11-11-13
Contract Working Days 203
Addl Days Granted 0
Working Days Charged 245
Percent Time Used 120
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-10-073
FLASHER EQUIPMENT COMPANY(0.31%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (2.51%)
E-Z BEL CONSTRUCTION, LLC(1.02%)
MURRAY CONSTRUCTION(0.53%)
RICE ENVIRONMENTAL SERVICES(0.56%)
C & C ALCOSER TRUCKING (0.00%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.53%)
VEGETATION MANAGEMENT SERVICES, LLC(0.00%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.26%)
FUQUAY, INC. (0.14%)
Contract # 01133220
Totals 4136146.75 0.00 4683738.15 99.9

CountyUVALDE
Highway US 83 ETC
From 1.0 MI SOUTH OF SH 127
To SH 127
CSJ 0036-07-032
Proj ID STP 2016(861)HES
Work Type TEXTURIZE SHOULDERS
 
61.202 620124.44 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0036-07-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163023
Totals 620124.44 0.00 0.00 0.0

CountyUVALDE
Highway US 83
From SH 55
To 0.2 MI N OF FM 1051
CSJ 0036-08-051
Proj ID STP 1502(265)HES
Work Type INSTALL INTERC FLASHING BEACON
 
17.800 1685720.93 79122.76 414934.41 24.6
CountyUVALDE
Highway FM 140
From 1.2 MI E FM 117
To 1.6 MI E FM 117
CSJ 0875-01-017
Proj ID STP 1502(264)HRR
Work Type GRD, BSE, SURF, SIGNALS, PAV'T MRK
 
0.400 480173.38 0.00 0.00 0.0
Work Order 07-30-15
Work Began 00-00-00
Work Completed  
Time Computed 10-28-15
Contract Working Days 308
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 26
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0036-08-051
LONE STAR PAVING ( 13.63%)
E-Z BEL CONSTRUCTION, LLC(4.24%)
FLASHER EQUIPMENT COMPANY(2.64%)
Contract # 06153041
Totals 2165894.31 79122.76 414934.41 19.1

CountyKENDALL
Highway IH 10
From SH 46
To 0.4 MI WEST OF US 87
CSJ 0072-06-071
Proj ID NH 2015(020)
Work Type BASE, GR, STR, SURF, SIGN & PAV MRK
 
1.044 3536440.57 0.00 2184980.70 63.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-30-15
Work Began 00-00-00
Work Completed  
Time Computed 04-27-15
Contract Working Days 136
Addl Days Granted 0
Working Days Charged 200
Percent Time Used 147
Contractor(s)
ZIMMERMAN CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-06-071
DOUBLE S PAVING, INC.( 25.74%)
DRILL TECH DRILLING & SHORING, INC.(5.25%)
SAECO ELECTRIC & UTILITY, LTD. (4.55%)
ENVIRONMENTAL SAFETY SERVICES, INC.(2.82%)
FLASHER EQUIPMENT COMPANY(1.06%)
Contract # 09143211
Totals 3536440.57 0.00 2184980.70 63.5

CountyKENDALL
Highway IH 10
From AT SCENIC LOOP ROAD
To .
CSJ 0072-06-072
Proj ID STP 1502(610)MM
Work Type GRD, BSE, STR, SURF, PAV'T MRK, SIG
 
0.835 11578717.70 0.00 2451953.92 21.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-28-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 416
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 12
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0072-06-072
RAMMING PAVING COMPANY ( 17.34%)
E-Z BEL CONSTRUCTION, LLC(4.79%)
OSCAR ORDUNO, INC. (1.98%)
BRADCO, LLC(1.73%)
FLASHER EQUIPMENT COMPANY(1.69%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.22%)
PRESIDIO CONTRACTING, LLC(0.90%)
WIMMS ENVIRONMENTAL, INC.(1.00%)
VOGES DRILLING CO. (0.59%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.41%)
MCL CONTRACTING, LLC (0.37%)
DU-MOR ENTERPRISES_INC.(0.26%)
S & S BRIDGE PAINTING, INC.(0.05%)
HOUSTON SAWING & DRILLING(0.04%)
TEXAS CUTTING & CORING, INC. (0.26%)
Contract # 08153017
Totals 11578717.70 0.00 2451953.92 21.1

CountyKENDALL
Highway IH 10 ETC
From RANGER CREEK ROAD
To BEXAR/KENDALL C/L
CSJ 0072-06-073
Proj ID NH 2016(300)
Work Type SEAL COAT AND PAVEMENT MARKINGS
 
188.603 6910844.54 0.00 475486.35 6.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 53
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0072-06-073
VIZCAINO, INC. ( 21.81%)
FLASHER EQUIPMENT COMPANY(1.38%)
Contract # 11153025
Totals 6910844.54 0.00 475486.35 6.8

CountyBEXAR
Highway IH 10
From FM 3351
To DOMINION DRIVE
CSJ 0072-07-059
Proj ID IM 4104(382)
Work Type SC, STRIPING, BASE
 
7.406 18426875.59 1193028.83 9526842.07 51.7
CountyBEXAR
Highway IH 10
From FM 3351
To DOMINION DRIVE
CSJ 0072-07-065
Proj ID RW 72-7-65
Work Type ADJUSTMENT OF UTILITIES
 
7.406 915396.00 87565.50 850952.00 92.9
Work Order 10-02-14
Work Began 03-10-15
Work Completed  
Time Computed 03-10-15
Contract Working Days 376
Addl Days Granted 0
Working Days Charged 256
Percent Time Used 68
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-07-059
FUQUAY, INC. (0.61%)
RELMCO, INC. (4.88%)
BADECO, INC(0.66%)
THE LEVY COMPANY, L.P. (6.41%)
K.L. DURHAM CONSTRUCTION, LLC(0.28%)
ROADWAY SPECIALTIES, INC.(2.51%)
VINSON CONSTRUCTION, LLC.(0.79%)
GOSNEY BROTHERS, LLC.(4.16%)
OSCAR ORDUNO, INC. (3.00%)
FLASHER EQUIPMENT COMPANY(0.66%)
MICKIE SERVICE, INC. (0.06%)
MCL CONTRACTING, LLC (0.14%)
BROWN EXCAVATION & UTILITIES, LLC(0.67%)
RAMMING PAVING COMPANY (1.00%)
RDI FOUNDATION DRILLING(1.43%)
LONE STAR PAVING (0.01%)
HUNTER DEMOLITION & WRECKING CORPORATION (0.41%)
PRIMATE CONSTRUCTION, INC. (0.07%)
Contract # 07143204
Totals 19342271.59 1280594.33 10377794.07 53.6

CountyBEXAR
Highway IH 10
From FM 3351 (RALPH FAIR RD)
To BOERNE STAGE RD
CSJ 0072-07-060
Proj ID C 72-7-60
Work Type GRAD, BS, STR, PVMT MRKG
 
0.871 6345951.80 0.00 5883829.94 91.6
Work Order 08-06-13
Work Began 03-24-14
Work Completed  
Time Computed 08-22-13
Contract Working Days 311
Addl Days Granted 0
Working Days Charged 332
Percent Time Used 106
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-07-060
J.D. RAMMING PAVING CO., LTD.( 15.45%)
SIEMENS INDUSTRY, INC. (3.77%)
PRESIDIO CONTRACTING, LLC(2.35%)
FARR FOUNDATION, INC.(2.29%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.90%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.44%)
D GUERRA CONSTRUCTION, LLC (1.68%)
FLASHER EQUIPMENT COMPANY(1.19%)
VOGES DRILLING CO. (1.20%)
A-Z REBAR CONTRACTOR (0.37%)
SCOTT DERR PAINTING CO (0.08%)
STAR OPERATIONS, INC.(4.42%)
TEXAS HIGHWAY WALLS(5.43%)
PENNTEX MILLING INC. (0.60%)
GEOSOURCE, INC.(0.35%)
Contract # 06133205
Totals 6345951.80 0.00 5883829.94 91.6

CountyBEXAR
Highway IH 10
From FAIR OAKS
To FM 3351
CSJ 0072-07-066
Proj ID C 72-7-66
Work Type GRAD, BS, STR, PVMT MRKG
 
3.390 31088816.81 0.00 1076742.00 3.4
CountyBEXAR
Highway IH 10
From FAIR OAKS
To FM 3351
CSJ 0072-07-071
Proj ID ROW 72-7-71
Work Type UTILITIES
 
3.390 70302.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-24-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 793
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 0
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-07-066
AUSTIN MATERIALS, LLC( 18.99%)
ROADWAY SPECIALTIES, INC.(1.55%)
FLASHER EQUIPMENT COMPANY(1.06%)
PANTHER CREEK TRANSPORTATION, INC. (3.16%)
OSCAR ORDUNO, INC. (0.84%)
Contract # 07153205
Totals 31159119.31 0.00 1076742.00 3.4

CountyBEXAR
Highway IH 10
From LP 1604
To 1.0 MI N OF HUEBNER RD
CSJ 0072-08-120
Proj ID STP 1102(442)MM
Work Type GRAD, BASE, SC, OV & PAV'T MRKNGS
 
2.513 25923457.53 0.00 30895080.47 99.9
CountyBEXAR
Highway IH 10
From LP 1604
To 1.0 MI N OF HUEBNER RD
CSJ 0072-08-125
Proj ID NH 1102(524)
Work Type UTIL & UTIL IN CONSTR CONTRACT
 
3.980 408971.75 0.00 364462.91 89.1
CountyBEXAR
Highway IH 10
From 1.0 MI N OF HUEBNER RD
To S. OF HUEBNER RD
CSJ 0072-12-179
Proj ID STP 1102(442)MM
Work Type GRAD, BASE, SC, OV & PAV'T MRKNGS
 
1.464 9635856.12 0.00 9879700.81 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-19-11
Work Began 01-02-12
Work Completed  
Time Computed 11-03-11
Contract Working Days 698
Addl Days Granted 312
Working Days Charged 969
Percent Time Used 95
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0072-08-120
LONE STAR TRAFFIC SERVICE, INC.(0.20%)
FUQUAY, INC. (0.07%)
ROADWAY SPECIALTIES, INC.(0.69%)
SITESAFE PRODUCTS TEXAS(0.99%)
PRIMATE CONSTRUCTION, INC. (0.03%)
J. R. (JOE) RAMON & SONS, INC. (0.60%)
GEOSOURCE, INC.(0.50%)
FARR FOUNDATION, INC.(1.09%)
DUSTROL, INC.(0.20%)
BEAIRD DRILLING(0.37%)
CP REBAR AND PT INSTALLATION (0.25%)
COLLECTIVE CONTRACTING (1.01%)
FLASHER EQUIPMENT COMPANY(1.35%)
STAR OPERATIONS, INC.( 15.22%)
S & S BRIDGE PAINTING, INC.(0.16%)
A & L UNDERGROUND, INC.(0.03%)
DU-MOR ENTERPRISES_INC.(0.55%)
DRILL TECH DRILLING & SHORING, INC.(2.82%)
T & D SOLUTIONS, LTD (1.55%)
WEBBER, LLC(113.75%)
FARR FOUNDATION, INC.(1.25%)
TEXAS HIGHWAY WALLS(2.73%)
BEAIRD DRILLING(0.35%)
FLASHER EQUIPMENT COMPANY(1.25%)
STAR OPERATIONS, INC.( 10.80%)
GIBSON & ASSOCIATES, INC.(0.13%)
HOLES OF SAN ANTONIO (0.01%)
M & M CONTRACTING, LTD.(1.04%)
TEXAS CURB CUT, LP (0.07%)
ANGEL BROTHERS ENTERPRISES, LTD. ( 36.16%)
WEBBER BARRIER SERVICES, LLC.(2.34%)
HOUSTON SAWING & DRILLING(0.02%)
CP REBAR AND PT INSTALLATION (0.14%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (5.48%)
CRAIG OLDEN, INC.(0.99%)
PENHALL COMPANY (AUSTIN) (0.00%)
SAECO ELECTRIC & UTILITY, LTD. (0.03%)
DCCS, LLC(5.49%)
RDI FOUNDATION DRILLING(0.13%)
ROADWAY SPECIALTIES, INC.(0.35%)
GEOSOURCE, INC.(1.07%)
M & M STRIPING & POWER WASHING, LLC(0.36%)
ODUM SERVICES, L.P.(0.10%)
SAN ANTONIO TELEPHONE COMPANY INC. (0.39%)
METALINK CORPORATION (0.02%)
SCOTT DERR PAINTING CO, LLC(0.18%)
SWAF, DBA AQUALOGIC(0.36%)
THE LEVY COMPANY, L.P. (0.00%)
Contract # 08113003
Totals 35968285.40 0.00 41139244.19 99.9

CountyBEXAR
Highway LP 345
From AT MEDICAL DRIVE
To .
CSJ 0072-08-134
Proj ID RW 72-8-134
Work Type ROW UTL. ADJ.
 
0.150 1621558.09 20879.07 1460604.83 90.0
CountyBEXAR
Highway LP 345
From AT MEDICAL DRIVE
To .
CSJ 0072-08-136
Proj ID HP 1102(265)
Work Type GRAD, BASE, STR, SURF & PAV'T MRKNG
 
0.150 12261538.68 30716.39 13015818.06 99.9
Work Order 06-26-13
Work Began 09-24-13
Work Completed  
Time Computed 09-24-13
Contract Working Days 400
Addl Days Granted 120
Working Days Charged 509
Percent Time Used 97
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0072-08-136
CP REBAR AND PT INSTALLATION (0.26%)
AUSTIN WOOD RECYCLING(0.35%)
BADECO, INC(1.64%)
C & C ALCOSER TRUCKING (1.39%)
DU-MOR ENTERPRISES_INC.(1.69%)
DUSTROL, INC.(0.11%)
FLASHER EQUIPMENT COMPANY(0.18%)
FUQUAY, INC. (0.26%)
HOUSTON SAWING & DRILLING(0.03%)
KELLYSTONE, INC(0.00%)
PROFESSIONAL TRAFFIC CONTROL, LLC(0.59%)
SCOTT DERR PAINTING CO, LLC(0.05%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.10%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (2.48%)
STAR OPERATIONS, INC.(3.74%)
W. W. FOUNDATION DRILLING, LTD.( 10.27%)
RDI FOUNDATION DRILLING(1.18%)
CRIBLEY ENTERPRISES, INC.(0.53%)
Contract # 04133032
Totals 13883096.77 51595.46 14476422.89 99.9

CountyBEXAR
Highway US 281 ETC
From LP 1604
To BEXAR/ATASCOSA C/L
CSJ 0073-02-069
Proj ID NH 2015(284)
Work Type SEAL COAT AND PAVEMENT MARKINGS
 
113.302 4909119.80 0.00 4324598.62 88.5
Work Order 12-05-14
Work Began 06-13-15
Work Completed  
Time Computed 12-21-14
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 78
Percent Time Used 141
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0073-02-069
FLASHER EQUIPMENT COMPANY( 14.60%)
WEST TEXAS RUMBLE STRIP(0.09%)
Contract # 11143205
Totals 4909119.80 0.00 4324598.62 88.5

CountyATASCOSA
Highway US 281
From BEXAR COUNTY LINE
To 0.443 MI N OF FM 3006
CSJ 0073-03-063
Proj ID STP 2015(021)HESG
Work Type SAFETY TREAT FIXED OBJECTS
 
8.668 167947.99 8950.00 186536.80 99.9
CountyBEXAR
Highway SS 122
From LP 13
To IH 410
CSJ 0100-02-061
Proj ID STP 2015(022)HESG
Work Type SAFETY TREAT FIXED OBJECTS
 
3.020 310980.86 0.00 335286.56 99.9
Work Order 10-09-14
Work Began 02-17-15
Work Completed  
Time Computed 12-08-14
Contract Working Days 88
Addl Days Granted 12
Working Days Charged 100
Percent Time Used 100
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0073-03-063
ROADWAY SPECIALTIES, INC.(2.82%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) ( 10.77%)
FLASHER EQUIPMENT COMPANY(1.22%)
WEBB & BEXAR CONSTRUCTION, LLC ( 23.38%)
Contract # 09143012
Totals 478928.85 8950.00 521823.36 99.9

CountyATASCOSA
Highway IH 37
From 1.1 MI SOUTH OF US 281
To ATASCOSA RIVER
CSJ 0073-05-065
Proj ID IM 0372(088)
Work Type MILL, BS, SURF, SC, OV & PAV MRK (SBML)
 
11.482 4592624.13 19234.00 4679922.98 99.9
CountyATASCOSA
Highway IH 37
From 0.9 MILES NORTH OF US 281
To 1.1 MILES SOUTH OF US 281
CSJ 0073-10-050
Proj ID IM 0372(088)
Work Type MILL, SURF, SC, OV & PAV MRK
 
2.000 803126.55 3586.00 1132206.48 99.9
Work Order 08-02-13
Work Began 09-11-13
Work Completed  
Time Computed 09-11-13
Contract Working Days 78
Addl Days Granted 37
Working Days Charged 115
Percent Time Used 100
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-05-065
N-LINE TRAFFIC MAINTENANCE, L.P. (0.22%)
FLASHER EQUIPMENT COMPANY(1.00%)
PAVEOVER, INC( 15.72%)
SCR CONSTRUCTION CO., INC. ( 17.44%)
Contract # 07133049
Totals 5395750.68 22820.00 5812129.46 99.9

CountyATASCOSA
Highway IH 37
From 0.4 MI SOUTH OF US 281
To 0.2 MI SOUTH OF FM 541
CSJ 0073-05-068
Proj ID STP 2015(733)HES
Work Type GR, BASE & PAVEMENT MARKINGS
 
6.067 2293599.14 156841.83 1903593.35 85.0
CountyATASCOSA
Highway IH 37
From 1.1 MI SOUTH OF US 281
To 0.2 MI NORTH OF SP 199
CSJ 0073-10-051
Proj ID STP 2015(734)HES
Work Type GRADE, BASE, SURF, PAVMT MARKINGS
 
1.810 1352503.96 9288.15 1230401.93 90.9
Work Order 05-08-15
Work Began 09-08-15
Work Completed  
Time Computed 06-08-15
Contract Working Days 57
Addl Days Granted 7
Working Days Charged 112
Percent Time Used 175
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-05-068
ROADWAY SPECIALTIES, INC.(1.46%)
CLAUDIA SERNA DBA SERNA"S TRUCKING (1.63%)
DAN WILLIAMS COMPANY ( 16.63%)
FLASHER EQUIPMENT COMPANY(3.98%)
FRANK JR REINFORCEMENT LLC (0.31%)
Contract # 03153010
Totals 3646103.10 166129.98 3133995.28 87.2

CountyBEXAR
Highway IH 37
From 0.4 MI N OF LP 13
To 0.4 MI S OF LP 13
CSJ 0073-08-167
Proj ID IM 0372(085)
Work Type LANDSCAPE DEVELOPMENT
 
0.850 520750.01 0.00 500960.02 96.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-18-11
Work Began 10-19-11
Work Completed  
Time Computed 01-03-13
Contract Working Days 81
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 100
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-167
DOWN UNDER CONSTRUCTION(0.96%)
LONE STAR TRAFFIC SERVICE, INC.(0.57%)
CRUZ CONTRACTING OF TEXAS, LLC (0.96%)
Contract # 08113005
Totals 520750.01 0.00 500960.02 96.1

CountyBEXAR
Highway US 281
From 0.25 MILES N OF IH 410
To 0.3 MI S OF JONES MALTSBERGER RD
CSJ 0073-08-168
Proj ID NH 2012(288)
Work Type LANDSCAPE DEVELOPMENT
 
1.150 662704.00 2000.00 676814.20 99.9
Work Order 03-16-12
Work Began 04-02-12
Work Completed  
Time Computed 04-02-12
Contract Working Days 93
Addl Days Granted 29
Working Days Charged 116
Percent Time Used 95
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-168
LONE STAR TRAFFIC SERVICE, INC.(0.41%)
FUQUAY, INC. (1.59%)
Contract # 02123205
Totals 662704.00 2000.00 676814.20 99.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6