Monthly State Let Construction Report For San Antonio District As Of Apr 10, 2017 Page 2 Of 5

Last Update: Monday, April 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
HighwayIH 10
FromIH 10 EB AT AMANDA STREET
To.
CSJ0025-02-210
Proj IDBR 1602(546)
Work TypeGRAD,STRUC,BASE,SURF, CLEAN & PAINT
 
0.8342671455.161284730.3848.0
CountyBEXAR
HighwayIH 10
FromIH 10 WB AT AMANDA STREET
To.
CSJ0025-02-211
Proj IDBR 1602(546)
Work TypeGRAD,BSE,STRUCTURE,SURF,CLN & PAINT
 
0.8342026497.49679474.6433.5
Work Order10-26-16
Work Began01-02-17
Work Completed
Time Computed11-25-16
Contract Working Days304
Addl Days Granted0
Working Days Charged48
Percent Time Used15
Contractor(s)
J3 COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-210
ROADWAY SPECIALTIES, INC. (1.49)
F & W ELECTRICAL CONTRACTORS, INC. (0.65)
FRANK JR REINFORCEMENT LLC (0.41)
LONE STAR PAVING (12.07)
M & M STRIPING & POWER WASHING, LLC (1.18)
SHINN & GREGORY, INC. (3.79)
JARCO TRANSPORT, LLC (2.07)
SCOTT DERR PAINTING CO, LLC (0.18)
CEKRA INC. (6.48)
Contract #08163034
Totals4697952.65564386.681964205.0241.8

CountyBEXAR
HighwayFM 78
FromAT LP 1604
To.
CSJ0025-09-076
Proj IDSTP 2015(580)HES
Work TypeGR, BASE, SURF, PAVMT MRKRS,SIGNALS
 
0.1062187618.061845181.3087.4
Work Order03-20-15
Work Began08-03-15
Work Completed
Time Computed06-18-15
Contract Working Days212
Addl Days Granted31
Working Days Charged286
Percent Time Used117
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-09-076
E-Z BEL CONSTRUCTION, LLC (7.29)
RICE ENVIRONMENTAL SERVICES (2.09)
INTERSTATE BARRICADES & MARKINGS, INC. (3.08)
FLASHER EQUIPMENT COMPANY (0.54)
LONE STAR PAVING (29.07)
Contract #02153004
Totals2187618.0678495.711845181.3087.4

CountyGUADALUPE
HighwayFM 78
FromSANTA CLARA CREEK, WEST OF MARION
ToSANTA CLARA CREEK, EAST OF MARION
CSJ0025-10-073
Proj IDSTP 2013(348)
Work TypeGRAD,STRS,BASE & SURF
 
1.0804136146.754884834.7899.9
Work Order07-16-13
Work Began11-11-13
Work Completed
Time Computed11-11-13
Contract Working Days203
Addl Days Granted0
Working Days Charged202
Percent Time Used99
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-10-073
FLASHER EQUIPMENT COMPANY (0.31)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (2.51)
E-Z BEL CONSTRUCTION, LLC (1.02)
MURRAY CONSTRUCTION (0.53)
RICE ENVIRONMENTAL SERVICES (0.56)
C & C ALCOSER TRUCKING (0.00)
PROFESSIONAL TRAFFIC CONTROL, LLC (1.53)
VEGETATION MANAGEMENT SERVICES, LLC (0.00)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.26)
FUQUAY, INC. (0.14)
Contract #01133220
Totals4136146.750.004884834.7899.9

CountyUVALDE
HighwayUS 83
FromAT SH 127
To.
CSJ0036-07-033
Proj IDSTP 2017(093)HES
Work TypeGRD, BSE, SURF, PAV'T MRK
 
0.2271056313.61567552.1653.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-13-16
Work Began11-14-16
Work Completed
Time Computed00-00-00
Contract Working Days78
Addl Days Granted0
Working Days Charged67
Percent Time Used85
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0036-07-033
LONE STAR PAVING COMPANY (22.88)
DELGADO"S CONSTRUCTION (4.21)
THE LEVY COMPANY, L.P. (5.68)
FLASHER EQUIPMENT COMPANY (5.36)
FUQUAY, INC. (1.95)
Contract #09163222
Totals1056313.610.00567552.1653.7

CountyUVALDE ETC
HighwayUS 83 ETC
From0.031 MI N OF PR 29A
To0.271 MI S OF PR 29A
CSJ0036-07-036
Proj IDSTP 2017(277)HES
Work TypeBASE, SURF, GRADE & PVMT MARKINGS
 
24.0181559435.355000.000.3
Work Order12-20-16
Work Began00-00-00
Work Completed
Time Computed03-20-17
Contract Working Days123
Addl Days Granted0
Working Days Charged10
Percent Time Used8
Contractor(s)
AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 0036-07-036
FLASHER EQUIPMENT COMPANY (0.91)
E-Z BEL CONSTRUCTION, LLC (23.76)
TRP CONSTRUCTION GROUP, LLC (10.23)
ALTUS TRAFFIC MANAGEMENT LLC (0.96)
Contract #11163210
Totals1559435.355000.005000.000.3

CountyUVALDE
HighwayUS 83
FromSH 55
To0.2 MI N OF FM 1051
CSJ0036-08-051
Proj IDSTP 1502(265)HES
Work TypeINSTALL INTERC FLASHING BEACON
 
17.8001685720.931378547.3281.7
CountyUVALDE
HighwayFM 140
From1.2 MI E FM 117
To1.6 MI E FM 117
CSJ0875-01-017
Proj IDSTP 1502(264)HRR
Work TypeGRD, BSE, SURF, SIGNALS, PAV'T MRK
 
0.400480173.38100103.3220.8
Work Order07-30-15
Work Began00-00-00
Work Completed
Time Computed10-28-15
Contract Working Days308
Addl Days Granted21
Working Days Charged310
Percent Time Used94
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0036-08-051
LONE STAR PAVING (13.63)
E-Z BEL CONSTRUCTION, LLC (4.24)
FLASHER EQUIPMENT COMPANY (2.64)
Contract #06153041
Totals2165894.31129590.441478650.6468.2

CountyKENDALL
HighwayIH 10
FromSH 46
To0.4 MI WEST OF US 87
CSJ0072-06-071
Proj IDNH 2015(020)
Work TypeBASE, GR, STR, SURF, SIGN & PAV MRK
 
1.0443536440.572184980.7063.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-30-15
Work Began04-27-15
Work Completed
Time Computed04-27-15
Contract Working Days136
Addl Days Granted0
Working Days Charged200
Percent Time Used147
Contractor(s)
THE HANOVER INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0072-06-071
DOUBLE S PAVING, INC. (25.74)
DRILL TECH DRILLING & SHORING, INC. (5.25)
SAECO ELECTRIC & UTILITY, LTD. (4.55)
ENVIRONMENTAL SAFETY SERVICES, INC. (2.82)
FLASHER EQUIPMENT COMPANY (1.06)
ZIMMERMAN CONSTRUCTION CO., INC. (0.00)
PRESIDIO CONTRACTING, LLC (6.29)
Contract #09143211
Totals3536440.570.002184980.7063.5

CountyKENDALL
HighwayIH 10
FromAT SCENIC LOOP ROAD
To.
CSJ0072-06-072
Proj IDSTP 1502(610)MM
Work TypeGRD, BSE, STR, SURF, PAV'T MRK, SIG
 
0.83511578717.706507884.8156.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-28-15
Work Began01-11-16
Work Completed
Time Computed00-00-00
Contract Working Days416
Addl Days Granted4
Working Days Charged299
Percent Time Used71
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0072-06-072
RAMMING PAVING COMPANY (17.34)
E-Z BEL CONSTRUCTION, LLC (4.79)
OSCAR ORDUNO, INC. (1.98)
BRADCO, LLC (1.73)
FLASHER EQUIPMENT COMPANY (1.69)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.23)
PRESIDIO CONTRACTING, LLC (0.90)
WIMMS ENVIRONMENTAL, INC. (1.00)
VOGES DRILLING CO. (0.59)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.41)
MCL CONTRACTING, LLC (0.37)
DU-MOR ENTERPRISES_INC. (0.26)
S & S BRIDGE PAINTING, INC. (0.05)
HOUSTON SAWING & DRILLING (0.04)
TEXAS CUTTING & CORING, INC. (0.26)
W.O.E. CONSTRUCTION (0.18)
Contract #08153017
Totals11578717.700.006507884.8156.2

CountyBEXAR
HighwayIH 10
FromFM 3351
ToDOMINION DRIVE
CSJ0072-07-059
Proj IDIM 4104(382)
Work TypeSC, STRIPING, BASE
 
7.40618426875.5917996750.4698.5
CountyBEXAR
HighwayIH 10
FromFM 3351
ToDOMINION DRIVE
CSJ0072-07-065
Proj IDRW 72-7-65
Work TypeADJUSTMENT OF UTILITIES
 
7.406915396.00950330.0099.9
Work Order10-02-14
Work Began03-10-15
Work Completed
Time Computed03-10-15
Contract Working Days376
Addl Days Granted0
Working Days Charged507
Percent Time Used134
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-07-059
FUQUAY, INC. (0.61)
RELMCO, INC. (4.88)
BADECO, INC (0.66)
THE LEVY COMPANY, L.P. (6.41)
K.L. DURHAM CONSTRUCTION, LLC (0.28)
ROADWAY SPECIALTIES, INC. (2.51)
VINSON CONSTRUCTION, LLC. (0.79)
GOSNEY BROTHERS, LLC. (4.16)
OSCAR ORDUNO, INC. (3.00)
FLASHER EQUIPMENT COMPANY (0.66)
MICKIE SERVICE, INC. (0.06)
MCL CONTRACTING, LLC (0.14)
BROWN EXCAVATION & UTILITIES, LLC (0.67)
RAMMING PAVING COMPANY (1.00)
RDI FOUNDATION DRILLING (1.43)
LONE STAR PAVING (0.01)
HUNTER DEMOLITION & WRECKING CORPORATION (0.41)
PRIMATE CONSTRUCTION, INC. (0.07)
S & S BRIDGE PAINTING, INC. (0.05)
INDUSTRIAL FABRICS, INC. (0.63)
Contract #07143204
Totals19342271.59646592.2418947080.4698.8

CountyBEXAR
HighwayIH 10
FromFAIR OAKS
ToFM 3351
CSJ0072-07-066
Proj IDC 72-7-66
Work TypeGRAD, BS, STR, PVMT MRKG
 
3.39031088816.8115849662.0251.3
CountyBEXAR
HighwayIH 10
FromFAIR OAKS
ToFM 3351
CSJ0072-07-071
Proj IDROW 72-7-71
Work TypeUTILITIES
 
3.39070302.5043602.5062.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-24-15
Work Began03-21-16
Work Completed
Time Computed00-00-00
Contract Working Days793
Addl Days Granted0
Working Days Charged341
Percent Time Used43
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-07-066
AUSTIN MATERIALS, LLC (18.99)
ROADWAY SPECIALTIES, INC. (1.55)
FLASHER EQUIPMENT COMPANY (1.06)
PANTHER CREEK TRANSPORTATION, INC. (3.16)
OSCAR ORDUNO, INC. (0.84)
STRAIGHT LINE SAWING & SEALING (0.06)
MELENDREZ BROTHERS TRUCKING, INC. (0.61)
THE LEVY COMPANY, L.P. (4.54)
BEAIRD DRILLING (0.27)
PRESIDIO CONTRACTING, LLC (3.71)
LIGHT IT UP ELECTRIC (0.02)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.30)
WILLIAMS CONSTRUCTION (0.07)
PERFORMANCE EQUIPMENT (0.15)
BREDA COMPANY, INC. (0.41)
PRIMATE CONSTRUCTION, INC. (0.00)
Contract #07153205
Totals31159119.310.0015893264.5251.3

CountyBEXAR
HighwayIH 10
FromAT FAIR OAKS PARKWAY
To.
CSJ0072-07-068
Proj IDSTP 1602(184)MM
Work TypeGRD, BSE, STR, SURF, PAV'T MRK, SIG
 
0.2677586328.533058791.5740.3
Work Order08-04-16
Work Began10-03-16
Work Completed
Time Computed08-28-16
Contract Working Days387
Addl Days Granted0
Working Days Charged115
Percent Time Used29
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-07-068
AUSTIN MATERIALS, LLC (15.96)
ROADWAY SPECIALTIES, INC. (3.43)
E-Z BEL CONSTRUCTION, LLC (2.31)
W. W. FOUNDATION DRILLING, LTD. (2.13)
INTERSTATE BARRICADES & MARKINGS, INC. (1.14)
J.R. RAMON & SONS, INC. (0.48)
S & S BRIDGE PAINTING, INC. (0.13)
Contract #06163016
Totals7586328.53286978.733058791.5740.3

CountyBEXAR
HighwayIH 10
FromLP 1604
To1.0 MI N OF HUEBNER RD
CSJ0072-08-120
Proj IDSTP 1102(442)MM
Work TypeGRAD, BASE, SC, OV & PAV'T MRKNGS
 
2.51325923457.5331213702.6099.9
CountyBEXAR
HighwayIH 10
FromLP 1604
To1.0 MI N OF HUEBNER RD
CSJ0072-08-125
Proj IDNH 1102(524)
Work TypeUTIL & UTIL IN CONSTR CONTRACT
 
3.980408971.75364462.9189.1
CountyBEXAR
HighwayIH 10
From1.0 MI N OF HUEBNER RD
ToS. OF HUEBNER RD
CSJ0072-12-179
Proj IDSTP 1102(442)MM
Work TypeGRAD, BASE, SC, OV & PAV'T MRKNGS
 
1.4649635856.1210016324.2999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-19-11
Work Began01-02-12
Work Completed
Time Computed11-03-11
Contract Working Days698
Addl Days Granted312
Working Days Charged1,031
Percent Time Used102
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0072-08-120
LONE STAR TRAFFIC SERVICE, INC. (0.20)
FUQUAY, INC. (0.07)
ROADWAY SPECIALTIES, INC. (0.69)
SITESAFE PRODUCTS TEXAS (0.99)
PRIMATE CONSTRUCTION, INC. (0.03)
J. R. (JOE) RAMON & SONS, INC. (0.60)
GEOSOURCE, INC. (0.50)
FARR FOUNDATION, INC. (1.09)
DUSTROL, INC. (0.20)
BEAIRD DRILLING (0.37)
CP REBAR AND PT INSTALLATION (0.25)
COLLECTIVE CONTRACTING (1.01)
FLASHER EQUIPMENT COMPANY (1.35)
STAR OPERATIONS, INC. (15.22)
S & S BRIDGE PAINTING, INC. (0.16)
A & L UNDERGROUND, INC. (0.03)
DU-MOR ENTERPRISES_INC. (0.55)
DRILL TECH DRILLING & SHORING, INC. (2.82)
T & D SOLUTIONS, LTD (1.55)
WEBBER, LLC (113.75)
FARR FOUNDATION, INC. (1.25)
TEXAS HIGHWAY WALLS (2.73)
BEAIRD DRILLING (0.35)
FLASHER EQUIPMENT COMPANY (1.25)
STAR OPERATIONS, INC. (10.80)
GIBSON & ASSOCIATES, INC. (0.13)
HOLES OF SAN ANTONIO (0.01)
M & M CONTRACTING, LTD. (1.04)
TEXAS CURB CUT, LP (0.07)
ANGEL BROTHERS ENTERPRISES, LTD. (36.16)
WEBBER BARRIER SERVICES, LLC. (2.34)
HOUSTON SAWING & DRILLING (0.02)
CP REBAR AND PT INSTALLATION (0.14)
SIGNATURE CONTRACTING SERVICES, L.L.C. (5.48)
CRAIG OLDEN, INC. (0.99)
PENHALL COMPANY (AUSTIN) (0.00)
SAECO ELECTRIC & UTILITY, LTD. (0.03)
DCCS, LLC (5.49)
RDI FOUNDATION DRILLING (0.13)
ROADWAY SPECIALTIES, INC. (0.35)
GEOSOURCE, INC. (1.07)
M & M STRIPING & POWER WASHING, LLC (0.36)
ODUM SERVICES, L.P. (0.10)
SAN ANTONIO TELEPHONE COMPANY INC. (0.39)
METALINK CORPORATION (0.02)
SCOTT DERR PAINTING CO, LLC (0.18)
SWAF, DBA AQUALOGIC (0.36)
THE LEVY COMPANY, L.P. (0.00)
LIGHT IT UP ELECTRIC (0.00)
Contract #08113003
Totals35968285.400.0041594489.8099.9

CountyBEXAR
HighwayIH 10
FromCALLAGHAN
ToWEST AVENUE
CSJ0072-12-197
Proj IDNH 2017(560)
Work TypeSURFACE & PAVEMENT MARKINGS
 
2.6931177187.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-16-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days59
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0072-12-197
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173033
Totals1177187.950.000.000.0

CountyBEXAR
HighwayUS 281
From0.2 MI N OF STADIUM DR
ToN ST MARY'S ST
CSJ0073-08-173
Proj IDNH 2013(708)
Work TypeLANDSCAPE DEVELOPMENT
 
0.600143550.00144267.1699.9
Work Order08-12-13
Work Began09-09-13
Work Completed
Time Computed09-09-13
Contract Working Days46
Addl Days Granted0
Working Days Charged23
Percent Time Used50
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-173
N-LINE TRAFFIC MAINTENANCE, L.P. (4.33)
Contract #05133004
Totals143550.000.00144267.1699.9

CountyBEXAR
HighwayIH 37
FromS HACKBERRY STREET
ToE CESAR E CHAVEZ BLVD
CSJ0073-08-180
Proj IDNH 2015(581)
Work TypeLANDSCAPE DEVELOPMENT
 
1.950973428.36931485.8895.6
Work Order03-26-15
Work Began04-16-15
Work Completed
Time Computed04-06-15
Contract Working Days130
Addl Days Granted0
Working Days Charged111
Percent Time Used85
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-180
ABM UNDERGROUND UTILITY CONSTRUCTION COMPANY (1.95)
O & S TRAFFIC SUPPLIES (0.91)
JTEX CONTRACTING, INC (4.27)
Contract #02153205
Totals973428.363200.00931485.8895.6

CountyBEXAR
HighwayUS 281
FromIH 35
ToIH 410
CSJ0073-08-181
Proj IDNH 2016(872)
Work TypeMILL, SC, PFC OV & PAVMENT MARKINGS
 
6.1998673181.425973695.7068.8
Work Order04-19-16
Work Began07-05-16
Work Completed
Time Computed05-19-16
Contract Working Days333
Addl Days Granted20
Working Days Charged178
Percent Time Used50
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-181
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.82)
PRIMATE CONSTRUCTION, INC. (12.09)
RPV CONSTRUCTION (5.74)
CRG (16.72)
FLASHER EQUIPMENT COMPANY (4.27)
GREEN MILLING GROUP (3.80)
Contract #02163205
Totals8673181.42618902.505973695.7068.8

CountyBEXAR
HighwayUS 281
From0.6 MI S OF NAKOMA
ToIH 410
CSJ0073-08-184
Proj IDNH 2017(561)
Work TypeSURFACE & PAVEMENT MARKINGS
 
1.7491512876.020.000.0
CountyBEXAR
HighwayUS 281
FromBROOKHOLLOW
To0.6 MI S OF NAKOMA
CSJ0253-04-152
Proj IDNH 2017(561)
Work TypeSURFACE & PAVEMENT MARKINGS
 
2.6431735744.960.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-15-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days173
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-184
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173234
Totals3248620.980.000.000.0

CountyBEXAR
HighwayIH 37
FromIH 10
ToIH 35
CSJ0073-08-186
Proj IDNH 2017(155)
Work TypeBSE, SC, SURF, PAV'T MRKNGS
 
3.1296072878.92370377.816.0
CountyBEXAR
HighwayIH 37
FromFAIR AVENUE
ToIH 10
CSJ0073-08-187
Proj IDNH 2017(155)
Work TypeBSE, SC, SURF, PAV'T MRKNGS
 
0.9251972515.9129000.001.4
Work Order12-20-16
Work Began00-00-00
Work Completed
Time Computed01-19-17
Contract Working Days132
Addl Days Granted0
Working Days Charged10
Percent Time Used7
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-186
FLASHER EQUIPMENT COMPANY (2.93)
ROADWAY SPECIALTIES, INC. (0.83)
RPV CONSTRUCTION (5.93)
PRIMATE CONSTRUCTION, INC. (9.20)
THE LEVY COMPANY, L.P. (0.82)
Contract #10163006
Totals8045394.83399377.81399377.814.9

CountyBEXAR
HighwayUS 281
From0.6 MI SOUTH OF NAKOMA
ToLOOP 410
CSJ0073-08-188
Proj IDNH 1602(385)
Work TypeMILL, SURF & PVMT MRKS
 
1.8931963890.851576089.6780.2
CountyBEXAR
HighwayUS 281
From0.4 MI SOUTH OF NAKOMA
To0.6 MI SOUTH OF NAKOMA
CSJ0253-04-154
Proj IDNH 1602(385)
Work TypeMILL, SURF & PVMT MRKS
 
0.147167835.4580731.9848.1
Work Order08-18-16
Work Began10-03-16
Work Completed
Time Computed09-17-16
Contract Working Days64
Addl Days Granted0
Working Days Charged55
Percent Time Used85
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-188
CHEROKEE SERVICES (4.25)
FLASHER EQUIPMENT COMPANY (5.92)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.79)
Contract #07163008
Totals2131726.301356400.411656821.6577.7

CountyWILSON
HighwayUS 181
From0.1 MI NORTH OF FM 541
ToKARNES/WILSON COUNTY LINE
CSJ0100-04-038
Proj IDNH 2016(748)
Work TypeGRAD, BSE, SURF, PAVMT MRK
 
5.9929084167.291896769.3720.8
Work Order03-31-16
Work Began01-09-17
Work Completed
Time Computed05-30-16
Contract Working Days289
Addl Days Granted0
Working Days Charged48
Percent Time Used16
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0100-04-038
COWBELL TRAFFIC SERVICES, INC. (0.24)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (4.52)
FLASHER EQUIPMENT COMPANY (2.68)
LONE STAR EROSION CONTROL (1.37)
STRIPE-A-ZONE, INC. (0.24)
Contract #02163208
Totals9084167.29664968.211896769.3720.8

page 1 | page 2 | page 3 | page 4 | page 5