Monthly State Let Construction Report For San Antonio District As Of Aug 10, 2015 Page 2 Of 7

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMEDINA
Highway US 90
From AVENUE C IN HONDO
To 1.6 MILES EAST OF SH 173
CSJ 0024-05-095
Proj ID NH 2014(361)
Work Type OVERLAY & PAVEMENT MARKINGS
 
1.398 911816.80 0.00 1018176.97 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-14-14
Work Began 06-30-14
Work Completed 04-08-15
Time Computed 03-02-14
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 102
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0024-05-095
PERFORMANCE EQUIPMENT(3.47%)
DUSTROL, INC.(0.64%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.83%)
ROADWAY SPECIALTIES, INC.(4.86%)
TRP CONSTRUCTION GROUP, LLC(3.70%)
Contract # 01143018
Totals 911816.80 0.00 1018176.97 100.0

CountyBEXAR
Highway US 90
From LP 1604
To 0.8 MI. WEST OF IH 410
CSJ 0024-07-058
Proj ID NH 1502(164)
Work Type GRD, BSE, SC, SURF, SIGN, PAV'T MRK
 
2.505 20101916.49 0.00 0.00 0.0
CountyBEXAR
Highway US 90
From 0.8 MI. WEST OF IH 410
To IH 410
CSJ 0024-08-130
Proj ID NH 1502(164)
Work Type GRD, BSE, SC, SURF, SIGN, PAV'T MRK
 
0.768 2614553.83 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-30-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 511
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0024-07-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153203
Totals 22716470.32 0.00 0.00 0.0

CountyBEXAR
Highway US 90
From 1.0 MILE WEST OF LOOP 13
To 1.0 MILE EAST OF LOOP 13
CSJ 0024-08-131
Proj ID NH 1502(263)
Work Type LANDSCAPE DEVELOPMENT
 
2.000 355044.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-14-15
Work Began 00-00-00
Work Completed  
Time Computed 09-13-15
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0024-08-131
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153211
Totals 355044.00 0.00 0.00 0.0

CountyBEXAR
Highway IH 10
From S PINE STREET
To ROLAND AVENUE
CSJ 0025-02-194
Proj ID C 25-2-194
Work Type MILL, RETAINING WALL, SURFACE
 
0.800 12027793.24 217107.14 14784256.81 99.9
Work Order 06-14-13
Work Began 08-12-13
Work Completed  
Time Computed 08-12-13
Contract Working Days 349
Addl Days Granted 75
Working Days Charged 385
Percent Time Used 90
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-194
ANGEL BROTHERS ENTERPRISES, LTD. ( 22.61%)
DANRIDGE CONSTRUCTION, LLC.(0.67%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.79%)
FLASHER EQUIPMENT COMPANY(0.75%)
HALL AND SONS TRANSPORT, INC.(7.88%)
RICE ENVIRONMENTAL SERVICES(0.60%)
THE LEVY COMPANY, L.P. ( 12.82%)
LIGHT IT UP ELECTRIC (0.22%)
TEXSTAR ENTERPRISES, INC.(1.62%)
ANTIGO CONSTRUCTION, INC.(0.20%)
CALAME CONTRACTING, LLC(1.95%)
DU-MOR ENTERPRISES_INC.(0.81%)
WEBBER BARRIER SERVICES, LLC.(0.41%)
BEAIRD DRILLING(0.03%)
R K STEPHENS CONSTRUCTION, LLC (1.07%)
Contract # 04133217
Totals 12027793.24 217107.14 14784256.81 99.9

CountyBEXAR
Highway IH 10
From IH 35
To 0.1 MI W. OF S. NEW BRAUNFELS AVE.
CSJ 0025-02-196
Proj ID NH 2014(853)
Work Type OVERLAY AND PAVEMENT MARKINGS
 
2.990 4673604.88 221665.50 221665.50 4.7
CountyBEXAR
Highway IH 10
From 0.1 MI E. OF S. WALTERS ST
To IH 410 EAST
CSJ 0025-02-197
Proj ID NH 2014(853)
Work Type BASE REPAIR, MILL, OV & PVMT MRKING
 
4.530 5828747.87 0.00 0.00 0.0
Work Order 09-09-14
Work Began 00-00-00
Work Completed  
Time Computed 11-08-14
Contract Working Days 112
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 16
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-196
RPV CONSTRUCTION ( 10.52%)
CPAVE, INC.(5.31%)
THE LEVY COMPANY, L.P. (1.04%)
FLASHER EQUIPMENT COMPANY(3.18%)
CLAUDIA SERNA DBA SERNA"S TRUCKING (6.39%)
FUQUAY, INC. (0.67%)
Contract # 06143004
Totals 10502352.75 221665.50 221665.50 2.1

CountyBEXAR
Highway IH 10 ETC
From 0.2 MI WEST OF GRAYTOWN
To 0.2 MI EAST OF PFEIL
CSJ 0025-02-201
Proj ID STP 2015(195)HESG
Work Type SAFETY LIGHTING
 
13.723 2712741.65 148660.69 1209879.13 44.5
Work Order 11-14-14
Work Began 02-17-15
Work Completed  
Time Computed 02-12-15
Contract Working Days 234
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 38
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-201
DS TEXAS ICON CONSTRUCTION (0.59%)
FLASHER EQUIPMENT COMPANY(0.51%)
Contract # 10143002
Totals 2712741.65 148660.69 1209879.13 44.5

CountyBEXAR
Highway IH 10 ETC
From AT IH 35
To .
CSJ 0025-02-202
Proj ID STP 2015(723)HES
Work Type TEXTURIZE SHOULDERS
 
63.761 1108928.80 303742.54 827421.24 74.6
Work Order 03-13-15
Work Began 00-00-00
Work Completed  
Time Computed 05-11-15
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 41
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-202
THE LEVY COMPANY, L.P. (7.45%)
Contract # 02153236
Totals 1108928.80 303742.54 827421.24 74.6

CountyBEXAR
Highway FM 78 ETC
From AT WALZEM
To .
CSJ 0025-09-075
Proj ID STP 2014(981)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.703 356499.50 19278.68 288086.86 80.8
Work Order 08-20-14
Work Began 06-01-15
Work Completed  
Time Computed 11-18-14
Contract Working Days 73
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 58
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0025-09-075
ALAMO CRANE SERVICE, INC.(1.82%)
HEARN CO.(1.45%)
CATO ELECTRIC COMPANY(2.83%)
FLASHER EQUIPMENT COMPANY(3.83%)
Contract # 07143045
Totals 356499.50 19278.68 288086.86 80.8

CountyBEXAR
Highway FM 78
From AT LP 1604
To .
CSJ 0025-09-076
Proj ID STP 2015(580)HES
Work Type GR, BASE, SURF, PAVMT MRKRS, SIGNALS
 
0.106 2187618.06 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-20-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 212
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-09-076
E-Z BEL CONSTRUCTION, LLC(7.29%)
RICE ENVIRONMENTAL SERVICES(2.09%)
INTERSTATE BARRICADES & MARKINGS, INC. (3.08%)
FLASHER EQUIPMENT COMPANY(0.54%)
LONE STAR PAVING ( 29.07%)
Contract # 02153004
Totals 2187618.06 0.00 0.00 0.0

CountyGUADALUPE
Highway FM 78
From SANTA CLARA CREEK, WEST OF MARION
To SANTA CLARA CREEK, EAST OF MARION
CSJ 0025-10-073
Proj ID STP 2013(348)
Work Type GRAD, STRS, BASE & SURF
 
1.080 4136146.75 38209.35 4661139.67 99.9
Work Order 07-16-13
Work Began 11-11-13
Work Completed  
Time Computed 11-11-13
Contract Working Days 203
Addl Days Granted 0
Working Days Charged 245
Percent Time Used 120
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-10-073
FLASHER EQUIPMENT COMPANY(0.31%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (2.51%)
E-Z BEL CONSTRUCTION, LLC(1.02%)
MURRAY CONSTRUCTION(0.53%)
RICE ENVIRONMENTAL SERVICES(0.56%)
C & C ALCOSER TRUCKING (0.00%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.53%)
VEGETATION MANAGEMENT SERVICES, LLC(0.00%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.26%)
Contract # 01133220
Totals 4136146.75 38209.35 4661139.67 99.9

CountyUVALDE
Highway US 83
From SH 55
To 0.2 MI N OF FM 1051
CSJ 0036-08-051
Proj ID STP 1502(265)HES
Work Type INSTALL INTERC FLASHING BEACON
 
17.800 1685720.93 0.00 0.00 0.0
CountyUVALDE
Highway FM 140
From 1.2 MI E FM 117
To 1.6 MI E FM 117
CSJ 0875-01-017
Proj ID STP 1502(264)HRR
Work Type GRD, BSE, SURF, SIGNALS, PAV'T MRK
 
0.400 480173.38 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-30-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 308
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0036-08-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153041
Totals 2165894.31 0.00 0.00 0.0

CountyKENDALL
Highway IH 10
From SH 46
To 0.4 MI WEST OF US 87
CSJ 0072-06-071
Proj ID NH 2015(020)
Work Type BASE, GR, STR, SURF, SIGN & PAV MRK
 
1.044 3536440.57 0.00 846896.11 23.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-30-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 136
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 44
Contractor(s)
ZIMMERMAN CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-06-071
DOUBLE S PAVING, INC.( 25.74%)
DRILL TECH DRILLING & SHORING, INC.(5.25%)
SAECO ELECTRIC & UTILITY, LTD. (4.55%)
ENVIRONMENTAL SAFETY SERVICES, INC.(2.82%)
FLASHER EQUIPMENT COMPANY(1.06%)
Contract # 09143211
Totals 3536440.57 0.00 846896.11 23.9

CountyKENDALL
Highway IH 10
From AT SCENIC LOOP ROAD
To .
CSJ 0072-06-072
Proj ID STP 1502(610)MM
Work Type GRD, BSE, STR, SURF, PAV'T MRK, SIG
 
0.835 11578717.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 416
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0072-06-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153017
Totals 11578717.70 0.00 0.00 0.0

CountyBEXAR
Highway IH 10
From FM 3351
To DOMINION DRIVE
CSJ 0072-07-059
Proj ID IM 4104(382)
Work Type SC, STRIPING, BASE
 
7.406 18426875.59 883853.10 3280214.50 17.8
CountyBEXAR
Highway IH 10
From FM 3351
To DOMINION DRIVE
CSJ 0072-07-065
Proj ID RW 72-7-65
Work Type ADJUSTMENT OF UTILITIES
 
7.406 915396.00 132570.00 387010.00 42.2
Work Order 10-02-14
Work Began 03-10-15
Work Completed  
Time Computed 03-10-15
Contract Working Days 376
Addl Days Granted 0
Working Days Charged 94
Percent Time Used 25
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-07-059
FUQUAY, INC. (0.61%)
RELMCO, INC. (4.88%)
BADECO, INC(0.66%)
THE LEVY COMPANY, L.P. (6.41%)
K.L. DURHAM CONSTRUCTION, LLC(0.28%)
ROADWAY SPECIALTIES, INC.(2.51%)
VINSON CONSTRUCTION, LLC.(0.79%)
GOSNEY BROTHERS, LLC.(4.16%)
OSCAR ORDUNO, INC. (3.00%)
FLASHER EQUIPMENT COMPANY(0.66%)
MICKIE SERVICE, INC. (0.06%)
MCL CONTRACTING, LLC (0.14%)
BROWN EXCAVATION & UTILITIES, LLC(0.67%)
RAMMING PAVING COMPANY (1.00%)
RDI FOUNDATION DRILLING(1.43%)
LONE STAR PAVING (0.01%)
HUNTER DEMOLITION & WRECKING CORPORATION (0.41%)
Contract # 07143204
Totals 19342271.59 1016423.10 3667224.50 18.9

CountyBEXAR
Highway IH 10
From FM 3351 (RALPH FAIR RD)
To BOERNE STAGE RD
CSJ 0072-07-060
Proj ID C 72-7-60
Work Type GRAD, BS, STR, PVMT MRKG
 
0.871 6345951.80 474179.33 5729386.58 88.8
Work Order 08-06-13
Work Began 03-24-14
Work Completed  
Time Computed 08-22-13
Contract Working Days 311
Addl Days Granted 0
Working Days Charged 310
Percent Time Used 99
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-07-060
J.D. RAMMING PAVING CO., LTD.( 15.45%)
SIEMENS INDUSTRY, INC. (3.77%)
PRESIDIO CONTRACTING, LLC(2.35%)
FARR FOUNDATION, INC.(2.29%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.90%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.44%)
D GUERRA CONSTRUCTION, LLC (1.68%)
FLASHER EQUIPMENT COMPANY(1.19%)
VOGES DRILLING CO. (1.20%)
A-Z REBAR CONTRACTOR (0.37%)
SCOTT DERR PAINTING CO (0.08%)
STAR OPERATIONS, INC.(4.42%)
TEXAS HIGHWAY WALLS(5.43%)
PENNTEX MILLING INC. (0.60%)
GEOSOURCE, INC.(0.35%)
Contract # 06133205
Totals 6345951.80 474179.33 5729386.58 88.8

CountyBEXAR
Highway IH 10
From FAIR OAKS
To FM 3351
CSJ 0072-07-066
Proj ID C 72-7-66
Work Type GRAD, BS, STR, PVMT MRKG
 
3.390 31088816.81 0.00 0.00 0.0
CountyBEXAR
Highway IH 10
From FAIR OAKS
To FM 3351
CSJ 0072-07-071
Proj ID ROW 72-7-71
Work Type UTILITIES
 
3.390 70302.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 793
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-07-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153205
Totals 31159119.31 0.00 0.00 0.0

CountyBEXAR
Highway IH 10
From LP 1604
To 1.0 MI N OF HUEBNER RD
CSJ 0072-08-120
Proj ID STP 1102(442)MM
Work Type GRAD, BASE, SC, OV & PAV'T MRKNGS
 
2.513 25923457.53 1503576.18 26924819.98 99.9
CountyBEXAR
Highway IH 10
From LP 1604
To 1.0 MI N OF HUEBNER RD
CSJ 0072-08-125
Proj ID NH 1102(524)
Work Type UTIL & UTIL IN CONSTR CONTRACT
 
3.980 408971.75 0.00 364462.91 89.1
CountyBEXAR
Highway IH 10
From 1.0 MI N OF HUEBNER RD
To S. OF HUEBNER RD
CSJ 0072-12-179
Proj ID STP 1102(442)MM
Work Type GRAD, BASE, SC, OV & PAV'T MRKNGS
 
1.464 9635856.12 378394.29 8432167.85 87.5
Work Order 10-19-11
Work Began 01-02-12
Work Completed  
Time Computed 11-03-11
Contract Working Days 698
Addl Days Granted 312
Working Days Charged 830
Percent Time Used 82
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0072-08-120
LONE STAR TRAFFIC SERVICE, INC.(0.20%)
FUQUAY, INC. (0.07%)
ROADWAY SPECIALTIES, INC.(0.69%)
SITESAFE PRODUCTS TEXAS(0.99%)
PRIMATE CONSTRUCTION, INC. (0.03%)
J. R. (JOE) RAMON & SONS, INC. (0.60%)
GEOSOURCE, INC.(0.50%)
FARR FOUNDATION, INC.(1.09%)
DUSTROL, INC.(0.20%)
BEAIRD DRILLING(0.37%)
CP REBAR AND PT INSTALLATION (0.25%)
COLLECTIVE CONTRACTING (1.01%)
FLASHER EQUIPMENT COMPANY(1.35%)
STAR OPERATIONS, INC.( 15.22%)
S & S BRIDGE PAINTING, INC.(0.16%)
A & L UNDERGROUND, INC.(0.03%)
DU-MOR ENTERPRISES_INC.(0.55%)
DRILL TECH DRILLING & SHORING, INC.(2.82%)
T & D SOLUTIONS, LTD (1.55%)
WEBBER, LLC(113.73%)
FARR FOUNDATION, INC.(1.25%)
TEXAS HIGHWAY WALLS(2.73%)
BEAIRD DRILLING(0.35%)
FLASHER EQUIPMENT COMPANY(1.25%)
STAR OPERATIONS, INC.( 10.80%)
GIBSON & ASSOCIATES, INC.(0.13%)
HOLES OF SAN ANTONIO (0.01%)
M & M CONTRACTING, LTD.(1.04%)
TEXAS CURB CUT, LP (0.07%)
ANGEL BROTHERS ENTERPRISES, LTD. ( 36.16%)
WEBBER BARRIER SERVICES, LLC.(2.34%)
HOUSTON SAWING & DRILLING(0.02%)
CP REBAR AND PT INSTALLATION (0.14%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (5.48%)
CRAIG OLDEN, INC.(0.99%)
PENHALL COMPANY (AUSTIN) (0.00%)
SAECO ELECTRIC & UTILITY, LTD. (0.03%)
DCCS, LLC(1.66%)
RDI FOUNDATION DRILLING(0.13%)
ROADWAY SPECIALTIES, INC.(0.35%)
GEOSOURCE, INC.(1.07%)
M & M STRIPING & POWER WASHING, LLC(0.36%)
ODUM SERVICES, L.P.(0.00%)
SAN ANTONIO TELEPHONE COMPANY INC. (0.39%)
METALINK CORPORATION (0.02%)
SCOTT DERR PAINTING CO, LLC(0.00%)
Contract # 08113003
Totals 35968285.40 1881970.47 35721450.74 97.9

CountyBEXAR
Highway LP 345
From AT MEDICAL DRIVE
To .
CSJ 0072-08-134
Proj ID RW 72-8-134
Work Type ROW UTL. ADJ.
 
0.150 1621558.09 0.00 1439725.76 88.7
CountyBEXAR
Highway LP 345
From AT MEDICAL DRIVE
To .
CSJ 0072-08-136
Proj ID HP 1102(265)
Work Type GRAD, BASE, STR, SURF & PAV'T MRKNG
 
0.150 12261538.68 141124.01 12675055.07 99.9
Work Order 06-26-13
Work Began 09-24-13
Work Completed  
Time Computed 09-24-13
Contract Working Days 400
Addl Days Granted 97
Working Days Charged 509
Percent Time Used 102
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0072-08-136
CP REBAR AND PT INSTALLATION (0.26%)
AUSTIN WOOD RECYCLING(0.35%)
BADECO, INC(1.64%)
C & C ALCOSER TRUCKING (1.39%)
DU-MOR ENTERPRISES_INC.(1.69%)
DUSTROL, INC.(0.11%)
FLASHER EQUIPMENT COMPANY(0.18%)
FUQUAY, INC. (0.26%)
HOUSTON SAWING & DRILLING(0.03%)
KELLYSTONE, INC(0.00%)
PROFESSIONAL TRAFFIC CONTROL, LLC(0.59%)
SCOTT DERR PAINTING CO, LLC(0.05%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.10%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (2.48%)
STAR OPERATIONS, INC.(3.74%)
W. W. FOUNDATION DRILLING, LTD.( 10.27%)
RDI FOUNDATION DRILLING(1.18%)
CRIBLEY ENTERPRISES, INC.(0.53%)
Contract # 04133032
Totals 13883096.77 141124.01 14114780.83 99.9

CountyKENDALL
Highway US 87
From AT CIBOLO CREEK
To .
CSJ 0072-14-024
Proj ID C 72-14-24
Work Type WIDEN NARROW BRIDGE AND APPROACHES
 
0.238 943105.79 0.00 940219.53 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-21-12
Work Began 01-07-13
Work Completed 04-08-15
Time Computed 01-06-13
Contract Working Days 166
Addl Days Granted 15
Working Days Charged 318
Percent Time Used 175
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-14-024
BEAIRD DRILLING(3.82%)
O & S TRAFFIC SUPPLIES (1.27%)
J.D. RAMMING PAVING CO., LTD.(8.58%)
FLASHER EQUIPMENT COMPANY(1.73%)
S & S BRIDGE PAINTING, INC.(0.90%)
Contract # 07123021
Totals 943105.79 0.00 940219.53 100.0

CountyBEXAR
Highway US 281 ETC
From LP 1604
To BEXAR/ATASCOSA C/L
CSJ 0073-02-069
Proj ID NH 2015(284)
Work Type SEAL COAT AND PAVEMENT MARKINGS
 
113.302 4909119.80 2354535.12 3836950.02 78.1
Work Order 12-05-14
Work Began 06-13-15
Work Completed  
Time Computed 12-21-14
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 43
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0073-02-069
FLASHER EQUIPMENT COMPANY( 14.60%)
WEST TEXAS RUMBLE STRIP(0.09%)
Contract # 11143205
Totals 4909119.80 2354535.12 3836950.02 78.1