Monthly State Let Construction Report For San Antonio District As Of Apr 11, 2014 Page 3 Of 5

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyKERR
Highway SH 16
From SH 173
To 0.2 MI. SOUTH OF RIVER HILLS BLVD.
CSJ 0291-03-057
Proj ID STP 2014(016)
Work Type GRAD, BASE, EMBANK, STR, SURF & PAV MRK
 
1.540 1866572.26 0.00 11767.88 0.6
CountyKERR
Highway SH 16
From FROM SPUR 98
To SH 173
CSJ 0291-03-061
Proj ID STP 2014(016)
Work Type OVERLAY AND PAVEMENT MARKINGS
 
0.803 637966.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-05-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 164
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 10
Contractor(s)
ZIMMERMAN CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0291-03-057
J.D. RAMMING PAVING CO., LTD.( 43.64%)
ROADWAY SPECIALTIES, INC.(9.17%)
E-Z BEL CONSTRUCTION, LLC(4.38%)
D. I. J. CONSTRUCTION, INC.(2.19%)
FLASHER EQUIPMENT COMPANY(0.55%)
CHEROKEE SERVICES(0.20%)
DIAMOND X CONTRACTING, INC (5.07%)
PENHALL COMPANY (AUSTIN) (0.00%)
Contract # 09133025
Totals 2504539.16 0.00 11767.88 0.4

CountyBANDERA
Highway SH 16
From FM 1283 (PIPE CREEK)
To 2.3 MI. N OF FM 1283
CSJ 0291-06-043
Proj ID STP 1102(266)HES
Work Type SC, OV, PM, CMP, MBC, MBGF
 
1.306 350263.15 0.00 280860.77 85.1
CountyBANDERA
Highway SH 16
From 1.1 MI SOUTH OF SH 173
To 0.3 MI SOUTH OF SH 173
CSJ 0291-06-051
Proj ID STP 1102(457)
Work Type SC, OV, SURF, STR, PAV'T MRK, SIGNAL
 
0.814 811159.34 0.00 798291.29 98.4
CountyBANDERA
Highway SH 16
From 2.82 MI N. OF BANDERA/MEDINA CL
To 4.62 MI S. OF FM 1283 (PIPE CREEK)
CSJ 0291-07-028
Proj ID STP 1102(266)HES
Work Type BASE, SC, ACP. PM, CMP, MBC, MBGF
 
0.650 310941.78 0.00 293500.56 94.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-30-11
Work Began 12-05-11
Work Completed  
Time Computed 11-29-11
Contract Working Days 199
Addl Days Granted 7
Working Days Charged 234
Percent Time Used 113
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0291-06-043
SAECO ELECTRIC & UTILITY, LTD. (5.20%)
FLASHER EQUIPMENT COMPANY(4.19%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.35%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.53%)
DOUBLE S PAVING, INC.(2.17%)
PERFORMANCE EQUIPMENT(0.49%)
Contract # 08113211
Totals 1472364.27 0.00 1372652.62 94.4

CountyGUADALUPE
Highway SH 123
From 0.1 MI N OF RIDGE ROAD
To 0.1 MI S OF RIDGE ROAD
CSJ 0366-02-082
Proj ID STP 2013(251)
Work Type GRAD, BSE, SURF, PAV'T MRK, SIGNAL
 
0.188 1522792.45 -103384.23 1337216.53 90.3
CountyGUADALUPE
Highway SH 123
From 0.3 MI N OF FM 1339
To 0.3 MI S OF FM 1339
CSJ 0366-02-083
Proj ID STP 2013(251)
Work Type GRAD, BSE, SURF, PAV'T MRK, SIGNAL
 
0.538 3044623.79 375185.96 3218360.22 99.9
Work Order 02-13-13
Work Began 05-01-13
Work Completed  
Time Computed 04-13-13
Contract Working Days 127
Addl Days Granted 34
Working Days Charged 201
Percent Time Used 124
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0366-02-082
CRAIG OLDEN, INC.(2.67%)
E-Z BEL CONSTRUCTION, LLC(2.21%)
M.V. HENKE ENTERPRISES, INC. (0.10%)
MURRAY CONSTRUCTION(0.17%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.95%)
RICE ENVIRONMENTAL SERVICES(0.66%)
HIGHWAY TECHNOLOGIES, INC. (1.88%)
AARON CONCRETE CONTRACTORS, L.P. (0.77%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.03%)
FLASHER EQUIPMENT COMPANY(1.89%)
Contract # 12123219
Totals 4567416.24 271801.73 4555576.75 99.9

CountyGUADALUPE
Highway SH 123
From GUADALUP/WILSON COUNTY LINE
To BS 123
CSJ 0366-03-062
Proj ID C 366-3-62
Work Type GR, BSE, SURF, PAV MRK
 
9.997 3685247.34 -1458.95 2796372.71 75.9
CountyWILSON
Highway SH 123
From BS 87
To GUADALUPE/WILSON COUNTY LINE
CSJ 0366-04-019
Proj ID C 366-4-19
Work Type GR, BSE, SURF, PAV MARK
 
9.902 3807443.83 0.00 3289594.26 86.3
CountyWILSON
Highway SH 123
From WILSON/KARNES COUNTY LINE
To BS 87
CSJ 0366-05-043
Proj ID C 366-5-43
Work Type GR, BSE, SURF, PAV MRK
 
11.683 1412491.73 24826.55 775962.87 54.9
Work Order 10-24-12
Work Began 12-03-12
Work Completed  
Time Computed 12-23-12
Contract Working Days 262
Addl Days Granted 0
Working Days Charged 263
Percent Time Used 100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0366-03-062
COWBELL TRAFFIC SERVICES, INC. (0.14%)
FLASHER EQUIPMENT COMPANY(0.29%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.33%)
MURRAY CONSTRUCTION(0.38%)
RELMCO, INC. (9.54%)
ROADWAY SPECIALTIES, INC.(2.75%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(4.26%)
EGGEMEYER LAND CLEARING, LLC (0.24%)
PENNTEX MILLING, LLC (0.04%)
Contract # 08123004
Totals 8905182.90 23367.60 6861929.84 77.0

CountyBEXAR
Highway FM 1518
From AT WOMAN HOLLERING CREEK
To .
CSJ 0465-02-024
Proj ID STP 2013(033)
Work Type GR, BS, STR, PAV MRK
 
0.259 1138013.70 8797.11 1188882.44 99.9
Work Order 10-18-12
Work Began 03-18-13
Work Completed  
Time Computed 11-03-12
Contract Working Days 104
Addl Days Granted 17
Working Days Charged 116
Percent Time Used 95
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0465-02-024
RICE ENVIRONMENTAL SERVICES(3.41%)
ROADWAY SPECIALTIES, INC.(3.10%)
LONE STAR TRAFFIC SERVICE, INC.(0.35%)
PRIMATE CONSTRUCTION, INC. (0.29%)
VOGES DRILLING (4.67%)
FLASHER EQUIPMENT COMPANY(1.30%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.42%)
Contract # 09123210
Totals 1138013.70 8797.11 1188882.44 99.9

CountyBEXAR
Highway LP 13
From SPUR 122 (S. PRESA)
To IH 37
CSJ 0521-01-045
Proj ID STP 2013(853)MM
Work Type GRADE, BASE, SDWLK
 
1.856 602797.20 0.00 316336.13 52.4
CountyBEXAR
Highway LP 13
From SPUR 117
To IH 10
CSJ 0521-01-046
Proj ID STP 2013(852)MM
Work Type GRADE, BASE, SDWLK
 
4.736 973688.75 0.00 5325.00 0.5
CountyBEXAR
Highway LP 13
From SPUR 117
To IH 10
CSJ 0521-01-047
Proj ID RW 521-1-47
Work Type ADJUSTMENT OF UTILITIES
 
4.947 55128.50 0.00 98.00 0.1
CountyBEXAR
Highway LP 13
From SPUR 122 (S. PRESA)
To IH 37
CSJ 0521-01-048
Proj ID RW 521-1-48
Work Type ADJUSTMENT OF UTILITIES
 
2.043 62163.50 0.00 294.00 0.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-07-13
Work Began 01-07-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 167
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 25
Contractor(s)
F.D. CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0521-01-045
AZTEC FENCE & ORNAMENTAL IRON(5.04%)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (1.42%)
FUQUAY, INC. (3.56%)
MISTEK SPRINKLER AND LANDSCAPING (1.07%)
GILBERT"S UTILITY & CONCRETE WORK, INC.(5.82%)
Contract # 07133208
Totals 1693777.95 0.00 322053.13 19.0

CountyBEXAR
Highway IH 410
From AT IH 10
To .
CSJ 0521-04-261
Proj ID STP 2010(089)ESTE
Work Type LANDSCAPE DEVELOPMENT
 
0.001 962118.36 0.00 1032991.12 99.9
Work Order 11-02-09
Work Began 11-18-09
Work Completed  
Time Computed 11-18-09
Contract Working Days 111
Addl Days Granted 0
Working Days Charged 118
Percent Time Used 106
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0521-04-261
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(5.12%)
ACE TELECOM, INC.(2.07%)
LONE STAR TRAFFIC SERVICE, INC.(0.41%)
CORTES CONTRACTING, INC. (HUB) (0.41%)
GREATER TEXAS LANDSCAPES, INC. (7.48%)
Contract # 09093216
Totals 962118.36 0.00 1032991.12 99.9

CountyGUADALUPE
Highway IH 10
From FM 464
To SH 46
CSJ 0535-01-069
Proj ID CC 535-1-69
Work Type GRAD, BASE, STR, SURF, PAV'T MRK, SIGNS
 
1.636 3594953.05 223009.76 1869803.60 52.0
Work Order 09-05-13
Work Began 10-14-13
Work Completed  
Time Computed 09-21-13
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 113
Percent Time Used 62
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0535-01-069
RELMCO, INC. ( 15.31%)
THE LEVY COMPANY, L.P. (2.82%)
ROADWAY SPECIALTIES, INC.(2.66%)
FLASHER EQUIPMENT COMPANY(1.04%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.41%)
PRESIDIO CONTRACTING, LLC(1.16%)
Contract # 07133221
Totals 3594953.05 223009.76 1869803.60 52.0

CountyUVALDE
Highway FM 1796
From MEDINA COUNTY LINE
To FM 187
CSJ 0595-01-008
Proj ID STP 2013(034)
Work Type GRAD, BSE, SC, SURF
 
3.790 1993666.73 10798.70 1861507.26 93.3
Work Order 10-18-12
Work Began 12-03-12
Work Completed  
Time Computed 11-03-12
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 96
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0595-01-008
RELMCO, INC. ( 20.00%)
FLASHER EQUIPMENT COMPANY(2.78%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.90%)
RICE ENVIRONMENTAL SERVICES(0.64%)
Contract # 08123046
Totals 1993666.73 10798.70 1861507.26 93.3

CountyFRIO
Highway FM 140
From 1.2 MI S OF BI 35E
To 3.4 MI S OF BI 35E
CSJ 0748-01-029
Proj ID STP 2014(017)
Work Type GR, STR, BASE
 
2.168 1394945.58 0.00 118752.14 8.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-31-13
Work Began 12-12-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 4
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0748-01-029
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(4.74%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.65%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.60%)
FLASHER EQUIPMENT COMPANY(2.58%)
RICE ENVIRONMENTAL SERVICES(0.23%)
Contract # 09133016
Totals 1394945.58 0.00 118752.14 8.5

CountyMEDINA
Highway FM 462
From 0.4 MI SOUTH OF CR 540
To 1.2 MI N OF FM 2200 WEST
CSJ 0848-01-037
Proj ID STP 2014(018)
Work Type REHAB & WIDEN NARROW ROADWAY
 
7.495 4927894.74 0.00 327809.54 6.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-31-13
Work Began 02-10-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 341
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 9
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0848-01-037
RICE ENVIRONMENTAL SERVICES(3.02%)
VOGES DRILLING CO. (0.91%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.54%)
Contract # 09133035
Totals 4927894.74 0.00 327809.54 6.6

CountyMEDINA
Highway FM 462
From 1.2 MI N OF FM 2200 WEST
To 3.3 MI. S. OF FM 2200 WEST
CSJ 0848-01-038
Proj ID STP 2013(035)
Work Type REHAB & WIDEN NARROW ROADWAY
 
4.463 3295349.15 0.00 1915549.15 58.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-09-12
Work Began 03-25-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 334
Addl Days Granted 0
Working Days Charged 246
Percent Time Used 73
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0848-01-038
FLASHER EQUIPMENT COMPANY(1.35%)
MURRAY CONSTRUCTION(1.04%)
M.V. HENKE ENTERPRISES, INC. (0.36%)
ROADWAY SPECIALTIES, INC.(3.13%)
RELMCO, INC. ( 16.35%)
VOGES DRILLING CO. (1.01%)
Contract # 09123035
Totals 3295349.15 0.00 1915549.15 58.1

CountyMEDINA
Highway FM 462
From 2.7 MILES SOUTH OF FM 2200 EAST
To MEDINA / FRIO COUNTY LINE
CSJ 0848-01-039
Proj ID STP 2012(035)
Work Type REHAB, WIDEN & ADD SHOULDERS
 
2.739 2072108.71 0.00 2062829.98 99.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-02-11
Work Began 02-01-12
Work Completed  
Time Computed 00-00-00
Contract Working Days 188
Addl Days Granted 107
Working Days Charged 299
Percent Time Used 101
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0848-01-039
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.78%)
FLASHER EQUIPMENT COMPANY(1.66%)
HIGHWAY TECHNOLOGIES, INC. (0.37%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.43%)
M.V. HENKE ENTERPRISES, INC. (0.64%)
RELMCO, INC. ( 38.76%)
W. W. FOUNDATION DRILLING, LTD.(2.54%)
MURRAY CONSTRUCTION(0.37%)
Contract # 09113222
Totals 2072108.71 0.00 2062829.98 99.7

CountyATASCOSA
Highway FM 476
From SP 242
To SH 97
CSJ 0853-02-030
Proj ID STP 2014(537)
Work Type TRAFFIC SIGNALS
 
1.156 740432.64 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0853-02-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143204
Totals 740432.64 0.00 0.00 0.0

CountyCOMAL
Highway FM 306
From 0.4 MILES EAST OF FM 3424
To JACOBS CREEK PARK ROAD
CSJ 0857-01-028
Proj ID STP 2013(105)
Work Type GRD, BASE, SURF, AND PAV MARKS
 
2.584 963415.67 1705.22 934765.14 97.0
CountyCOMAL
Highway FM 306
From 0.2 MI W OF CANYON DAM ACCESS ROAD
To 1.1 MI E OF PURGATORY ROAD
CSJ 1728-02-054
Proj ID STP 2013(105)
Work Type GRD, BASE, SURF, AND PAV MARKINGS
 
6.542 2545179.77 0.00 2253383.32 88.5
Work Order 11-28-12
Work Began 12-14-12
Work Completed  
Time Computed 12-14-12
Contract Working Days 296
Addl Days Granted 0
Working Days Charged 217
Percent Time Used 73
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0857-01-028
E-Z BEL CONSTRUCTION, LLC(1.07%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.62%)
RELMCO, INC. (6.80%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(6.58%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.59%)
ROADWAY SPECIALTIES, INC.(2.67%)
FLASHER EQUIPMENT COMPANY(1.96%)
EGGEMEYER LAND CLEARING, LLC (1.96%)
Contract # 10123012
Totals 3508595.44 1705.22 3188148.46 90.8

CountyBEXAR
Highway VA
From DISTRICTWIDE GUIDESIGNS FY14
To .
CSJ 0915-00-155
Proj ID STP 2014(562)
Work Type DISTRICTWIDE GUIDESIGNS FY14
 
0.001 998524.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 208
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-155
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143205
Totals 998524.12 0.00 0.00 0.0

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2014
To .
CSJ 0915-00-156
Proj ID STP 2014(538)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 1299950.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-156
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143206
Totals 1299950.00 0.00 0.00 0.0

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2012
To .
CSJ 0915-00-158
Proj ID STP 2012(311)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 1113075.30 0.00 1055888.65 94.8
Work Order 03-12-12
Work Began 05-29-12
Work Completed  
Time Computed 06-10-12
Contract Working Days 300
Addl Days Granted 64
Working Days Charged 359
Percent Time Used 98
Contractor(s)
SAECO ELECTRIC & UTILITY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-158
HEARN CO.(1.01%)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (3.41%)
JCD CONSTRUCTION, LLC(3.84%)
JA&M CONSTRUCTION, LLC (1.07%)
Contract # 02123222
Totals 1113075.30 0.00 1055888.65 94.8

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2013
To .
CSJ 0915-00-160
Proj ID STP 2013(404)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.010 1179951.00 34136.58 140553.18 11.9
Work Order 04-19-13
Work Began 00-00-00
Work Completed  
Time Computed 07-18-13
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 20
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-160
JND CONSTRUCTION CONSULTANTS, LLC( 13.54%)
VACA UNDERGROUND UTILITIES INC (3.44%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.69%)
BEAIRD DRILLING(0.16%)
YORK & YORK FOUNDATION DRILLING, INC.(3.55%)
JCH CONSTRUCTION, INC. (0.05%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.03%)
Contract # 02133216
Totals 1179951.00 34136.58 140553.18 11.9

CountyBEXAR
Highway VA
From DISTRICTWIDE TRAFFIC CNTRL FY 2012
To .
CSJ 0915-00-163
Proj ID STP 2012(312)
Work Type DISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001 942875.75 0.00 983947.97 99.9
Work Order 03-12-12
Work Began 05-22-12
Work Completed  
Time Computed 06-10-12
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 231
Percent Time Used 77
Contractor(s)
SAECO ELECTRIC & UTILITY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-163
HEARN CO.(6.17%)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (4.03%)
JA&M CONSTRUCTION, LLC (1.33%)
JCD CONSTRUCTION, LLC(2.82%)
Contract # 02123027
Totals 942875.75 0.00 983947.97 99.9

page 1 | page 2 | page 3 | page 4 | page 5