Monthly State Let Construction Report For San Antonio District As Of Oct 16, 2017 Page 3 Of 6

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
HighwayUS 281
FromIH 35
ToIH 410
CSJ0073-08-181
Proj IDNH 2016(872)
Work TypeMILL, SC, PFC OV & PAVMENT MARKINGS
 
6.1998673181.429728150.8299.9
Work Order04-19-16
Work Began07-05-16
Work Completed
Time Computed05-19-16
Contract Working Days333
Addl Days Granted20
Working Days Charged290
Percent Time Used82
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-181
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.82)
PRIMATE CONSTRUCTION, INC. (12.09)
RPV CONSTRUCTION (5.74)
CRG (16.72)
FLASHER EQUIPMENT COMPANY (4.27)
GREEN MILLING GROUP (3.80)
Contract #02163205
Totals8673181.42488189.959728150.8299.9

CountyBEXAR
HighwayUS 281
From0.6 MI S OF NAKOMA
ToIH 410
CSJ0073-08-184
Proj IDNH 2017(561)
Work TypeSURFACE & PAVEMENT MARKINGS
 
1.7491512876.02600203.7339.6
CountyBEXAR
HighwayUS 281
FromBROOKHOLLOW
To0.6 MI S OF NAKOMA
CSJ0253-04-152
Proj IDNH 2017(561)
Work TypeSURFACE & PAVEMENT MARKINGS
 
2.6431735744.96768085.5844.2
Work Order03-15-17
Work Began00-00-00
Work Completed
Time Computed03-05-17
Contract Working Days173
Addl Days Granted0
Working Days Charged73
Percent Time Used42
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-184
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (7.49)
D&S TEXAS ICON CONSTRUCTION (6.10)
E-Z BEL CONSTRUCTION, LLC (14.63)
FLASHER EQUIPMENT COMPANY (5.02)
RELMCO, INC. (1.45)
BMP SPECIALIST, LLC (1.08)
PERFORMANCE EQUIPMENT SERVICE (5.37)
HEARN CO. (2.01)
Contract #02173234
Totals3248620.9856444.481368289.3142.1

CountyBEXAR
HighwayIH 37
FromIH 10
ToIH 35
CSJ0073-08-186
Proj IDNH 2017(155)
Work TypeBSE, SC, SURF, PAV'T MRKNGS
 
3.1296072878.923284542.1954.0
CountyBEXAR
HighwayIH 37
FromFAIR AVENUE
ToIH 10
CSJ0073-08-187
Proj IDNH 2017(155)
Work TypeBSE, SC, SURF, PAV'T MRKNGS
 
0.9251972515.91853467.5743.2
Work Order12-20-16
Work Began03-20-17
Work Completed
Time Computed01-19-17
Contract Working Days132
Addl Days Granted0
Working Days Charged114
Percent Time Used86
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-186
FLASHER EQUIPMENT COMPANY (2.93)
ROADWAY SPECIALTIES, INC. (0.83)
RPV CONSTRUCTION (5.93)
PRIMATE CONSTRUCTION, INC. (9.20)
THE LEVY COMPANY, L.P. (0.82)
TEXAS CUTTING & CORING, INC. (0.46)
Contract #10163006
Totals8045394.831055486.954138009.7651.4

CountyBEXAR
HighwayUS 281
From0.6 MI SOUTH OF NAKOMA
ToLOOP 410
CSJ0073-08-188
Proj IDNH 1602(385)
Work TypeMILL, SURF & PVMT MRKS
 
1.8931963890.851983117.7099.9
CountyBEXAR
HighwayUS 281
From0.4 MI SOUTH OF NAKOMA
To0.6 MI SOUTH OF NAKOMA
CSJ0253-04-154
Proj IDNH 1602(385)
Work TypeMILL, SURF & PVMT MRKS
 
0.147167835.45167314.3499.6
Work Order08-18-16
Work Began10-03-16
Work Completed
Time Computed09-17-16
Contract Working Days64
Addl Days Granted0
Working Days Charged59
Percent Time Used92
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-188
CHEROKEE SERVICES (4.25)
FLASHER EQUIPMENT COMPANY (5.92)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.79)
Contract #07163008
Totals2131726.300.002150432.0499.9

CountyBEXAR
HighwayIH 37
From0.3 MILES S OF IH 410
To0.4 MILES N OF LP 13
CSJ0073-08-190
Proj IDNH 1702(030)
Work TypeLANDSCAPE DEVELOPMENT
 
2.500557600.00169590.0030.4
Work Order06-08-17
Work Began00-00-00
Work Completed
Time Computed07-08-17
Contract Working Days81
Addl Days Granted0
Working Days Charged44
Percent Time Used54
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-190
FLASHER EQUIPMENT COMPANY (1.50)
Contract #05173029
Totals557600.0087130.00169590.0030.4

CountyWILSON
HighwayUS 181
From0.1 MI NORTH OF FM 541
ToKARNES/WILSON COUNTY LINE
CSJ0100-04-038
Proj IDNH 2016(748)
Work TypeGRAD, BSE, SURF, PAVMT MRK
 
5.9929084167.293460604.6038.0
Work Order03-31-16
Work Began01-09-17
Work Completed
Time Computed05-30-16
Contract Working Days289
Addl Days Granted0
Working Days Charged155
Percent Time Used53
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0100-04-038
COWBELL TRAFFIC SERVICES, INC. (0.24)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (4.52)
FLASHER EQUIPMENT COMPANY (2.68)
LONE STAR EROSION CONTROL (1.37)
STRIPE-A-ZONE, INC. (0.24)
RELMCO, INC. (0.00)
Contract #02163208
Totals9084167.29488017.633460604.6038.0

CountyKENDALL
HighwayRM 473
From2.464 MI W OF US 281
To2.04 MI W OF US 281
CSJ0142-10-024
Proj IDSTP 2018(070)HESG
Work TypeCHEVRONS & PAVEMENT MARKINGS
 
0.42417307.320.000.0
CountyGUADALUPE
HighwaySH 123
FromSH 46
To0.1 MI N OF FM 1681
CSJ0366-03-067
Proj IDSTP 2018(071)HESG
Work TypePAVEMENT MARKINGS
 
9.929146084.510.000.0
CountyCOMAL
HighwayFM 3424
FromRM 32
ToFM 306
CSJ1728-01-007
Proj IDSTP 2018(072)HESG
Work TypePAVEMENT MARKINGS
 
1.35820665.820.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days59
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0142-10-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09173015
Totals184057.650.000.000.0

CountyKERR
HighwayIH 10
From0.7 MILES WEST OF FM 783
To0.3 MI EAST OF FM 783
CSJ0142-14-062
Proj IDNH 1602(227)
Work TypeGRAD, BASE, SURFACE, PVMT MARKINGS
 
1.0002211020.102251544.9396.4
Work Order11-15-16
Work Began04-24-17
Work Completed
Time Computed12-15-16
Contract Working Days87
Addl Days Granted0
Working Days Charged87
Percent Time Used100
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0142-14-062
ROADWAY SPECIALTIES, INC. (4.98)
PRIMATE CONSTRUCTION, INC. (4.94)
FLASHER EQUIPMENT COMPANY (3.09)
F & W ELECTRICAL CONTRACTORS, INC. (0.68)
WEST TEXAS RUMBLE STRIP (0.20)
Contract #09163226
Totals2211020.101061010.802251544.9396.4

CountyWILSON
HighwayUS 87
From0.5 MI EAST OF FM 538
ToWILSON/GONZALES COUNTY LINE
CSJ0143-05-032
Proj IDSTP 2017(035)
Work TypeGRAD, BSE, SURF, PAVMT MRK
 
8.9709551891.669582529.0999.9
Work Order11-01-16
Work Began01-16-17
Work Completed
Time Computed12-01-16
Contract Working Days138
Addl Days Granted0
Working Days Charged138
Percent Time Used100
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0143-05-032
FLASHER EQUIPMENT COMPANY (2.11)
WEST TEXAS RUMBLE STRIP (0.13)
ROADWAY SPECIALTIES, INC. (2.39)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.29)
CLAUDIA SERNA DBA SERNA"S TRUCKING (0.46)
Contract #09163002
Totals9551891.6668133.119582529.0999.9

CountyKERR
HighwaySH 39
From0.1 MI E OF SH 27
ToNEW INGRAM LAKE DAM
CSJ0193-02-031
Proj IDC 193-2-31
Work TypeGR, STRS, BASE & SURF
 
1.2677644985.977585284.33100.0
Work Order10-12-12
Work Began01-21-13
Work Completed08-08-17
Time Computed10-28-12
Contract Working Days345
Addl Days Granted177
Working Days Charged605
Percent Time Used115
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0193-02-031
RAMMING PAVING COMPANY (20.81)
ALLEN KELLER COMPANY (15.12)
F & W ELECTRICAL CONTRACTORS, INC. (2.78)
RICE ENVIRONMENTAL SERVICES (1.39)
W. W. FOUNDATION DRILLING, LTD. (0.89)
FLASHER EQUIPMENT COMPANY (0.78)
PRESIDIO CONTRACTING, LLC (0.41)
FRIESENHAHN PAVING (0.20)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.42)
NATIVE ROOTS LANDSCAPING (0.24)
Contract #08123027
Totals7644985.97310570.247585284.33100.0

CountyKERR
HighwaySH 39
From2.9 MI EAST OF FM 1340
To3.6 MI EAST OF FM 1340
CSJ0193-02-043
Proj IDSFT 193-2-43
Work TypeINSTALL ADV WARNING SIGNALS, ETC
 
0.70049802.5665490.7799.9
CountyKERR
HighwaySH 16
FromFM 1273
To4 MI S OF FM 1273
CSJ0291-03-065
Proj IDSFT 291-3-65
Work TypeSAFETY TREAT FIXED OBJECT, ETC
 
4.0001296470.841187318.5991.5
Work Order03-20-15
Work Began04-28-15
Work Completed
Time Computed04-28-15
Contract Working Days60
Addl Days Granted50
Working Days Charged103
Percent Time Used93
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0193-02-043
LONE STAR PAVING COMPANY (18.76)
R.P.V. CONSTRUCTION (6.88)
FLASHER EQUIPMENT COMPANY (5.85)
ENVIRONMENTAL SAFETY SERVICES, INC. (2.64)
THE LEVY COMPANY, L.P. (2.13)
GEOSOURCE, INC. (3.53)
Contract #02153211
Totals1346273.402599.441252809.3693.0

CountyCOMAL
HighwaySH 46
From0.2 MI W OF FM 3009
To0.2 MI E OF FM 3009
CSJ0215-01-043
Proj IDSTP 2018(074)HES
Work TypeGRAD, BASE, SURF & SAFETY TREAT
 
0.400431702.120.000.0
CountyCOMAL
HighwaySH 46
FromAT FM 3009
To.
CSJ0215-01-046
Proj IDSTP 2018(075)HESG
Work TypeSIGNALS, SIGNS, ILLUMINATION
 
0.400141803.700.000.0
CountyCOMAL
HighwaySH 46
From0.3 MI W OF PR 31
To0.1 MI W OF PR 31
CSJ0215-07-026
Proj IDSTP 2018(076)HESG
Work TypeGRAD, SURF, BASE & PAVEMENT MRKINGS
 
0.200108424.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days73
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0215-01-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173020
Totals681930.300.000.000.0

CountyCOMAL
HighwayBS 46-C
FromIN THE CITY OF NEW BRAUNFELS
To.
CSJ0215-02-056
Proj IDSTP 2014(112)TE
Work TypeGRAD, BSE,SURF, SIDEWALK, SIGN
 
0.661796382.00827451.4499.9
CountyCOMAL
HighwayBS 46-C
FromIN THE CITY OF NEW BRAUNFELS
To.
CSJ0215-02-058
Proj IDROW 215-2-58
Work TypeUTILITY ADJUSTMENTS
 
0.66155799.0010250.0018.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-28-16
Work Began02-01-17
Work Completed
Time Computed09-09-16
Contract Working Days129
Addl Days Granted25
Working Days Charged122
Percent Time Used79
Contractor(s)
MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0215-02-056
AUSTIN MATERIALS, LLC (16.80)
E-Z BEL CONSTRUCTION, LLC (9.12)
FLASHER EQUIPMENT COMPANY (4.35)
FUQUAY, INC. (0.86)
Contract #08163216
Totals852181.000.00837701.4498.3

CountyKENDALL
HighwaySH 46
FromUS 87
ToKENDALL / COMAL COUNTY LINE
CSJ0215-06-037
Proj IDSTP 1602(548)
Work TypeGRAD, BSE, STR, SURF, PAV'T MRK
 
3.9055575747.693495675.9262.6
CountyCOMAL
HighwaySH 46
FromCOMAL / KENDALL COUNTY LINE
ToUS 281
CSJ0215-07-022
Proj IDSTP 1602(548)
Work TypeGRAD, BSE, STR, SURF, PAV'T MRK
 
2.0503394595.791074293.8931.6
Work Order10-06-16
Work Began11-07-16
Work Completed
Time Computed11-05-16
Contract Working Days413
Addl Days Granted0
Working Days Charged220
Percent Time Used53
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0215-06-037
MPB, INC. (13.64)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (11.20)
FLASHER EQUIPMENT COMPANY (3.20)
ROADWAY SPECIALTIES, INC. (2.33)
THE LEVY COMPANY, L.P. (0.55)
EGGEMEYER LAND CLEARING, LLC (0.57)
AWP, INC. DBA AREA WIDE PROTECTIVE (0.02)
Contract #08163008
Totals8970343.48590872.684569969.8150.9

CountyCOMAL
HighwaySL 337
FromSH 46, SOUTHERLY
ToIH 35
CSJ0216-01-036
Proj IDSTP 1702(434)
Work TypeGR, STRS, BASE & SURF
 
2.99718902660.070.000.0
CountyCOMAL
HighwaySL 337
FromRIVER ROAD
ToHILLCREST DRIVE
CSJ0216-01-054
Proj IDSTP 1702(435)MM
Work TypeGR, BASE, SURF, PVMT MRK, SGNS, STR
 
1.43112457946.030.000.0
CountyCOMAL
HighwaySL 337
FromRIVER ROAD
ToSH 46
CSJ0216-01-055
Proj IDNH 1702(436)
Work TypeGR,BASE,STRS, SURF
 
2.23010947785.370.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-27-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days1,239
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0216-01-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173003
Totals42308391.470.000.000.0

CountyCOMAL
HighwaySH 46
FromIH 35
ToGUADALUPE/COMAL COUNTY LINE
CSJ0216-01-051
Proj IDSTP 2017(591)
Work TypeGRAD, BSE, SURF, PAVMT MRK
 
1.0091167074.68762688.1365.3
CountyGUADALUPE
HighwaySH 46
FromCOMAL COUNTY LINE
ToFM 758
CSJ0216-02-058
Proj IDSTP 2017(591)
Work TypeGRAD, BSE, SURF, PAVMT MRK
 
1.6491844522.931452792.4378.7
Work Order03-16-17
Work Began04-28-17
Work Completed
Time Computed04-17-17
Contract Working Days122
Addl Days Granted0
Working Days Charged91
Percent Time Used74
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0216-01-051
TRP CONSTRUCTION GROUP, LLC (1.24)
K.L. DURHAM CONSTRUCTION, LLC (4.09)
E-Z BEL CONSTRUCTION, LLC (6.39)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.79)
ROADWAY SPECIALTIES, INC. (2.13)
AWP, INC. (1.13)
Contract #02173218
Totals3011597.61199354.562215480.5673.5

CountyGUADALUPE
HighwayFM 466
FromUS 90A
ToUS 90
CSJ0216-03-032
Proj IDSTP 1602(127)
Work TypeGRAD, BSE, SURF, PAV'R MRKNGS
 
0.8201436279.691661730.1699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-19-16
Work Began09-19-16
Work Completed
Time Computed09-18-16
Contract Working Days218
Addl Days Granted0
Working Days Charged153
Percent Time Used70
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0216-03-032
E-Z BEL CONSTRUCTION, LLC (11.66)
FLASHER EQUIPMENT COMPANY (2.87)
FUQUAY, INC. (2.40)
CUATRO T CONSTRUCTION, INC. (1.11)
Contract #05163216
Totals1436279.690.001661730.1699.9

CountyCOMAL
HighwayUS 281
FromSB MAINLANE @ GUADALUPE RIVER
To.
CSJ0253-03-067
Proj IDBR 1702(038)
Work TypeGRAD,BSE,STRUCTURE,SURF,CLN & PAINT
 
0.1723271173.6039877.951.2
Work Order06-14-17
Work Began08-07-17
Work Completed
Time Computed07-14-17
Contract Working Days304
Addl Days Granted0
Working Days Charged14
Percent Time Used4
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0253-03-067
S&S BRIDGE PAINTING (39.67)
FLASHER EQUIPMENT COMPANY (0.94)
AUSTIN MATERIALS, LLC (4.28)
Contract #05173036
Totals3271173.6014000.0039877.951.2

CountyBEXAR
HighwayUS 281
FromLP 1604
To0.8 MI.NORTH OF STONE OAK
CSJ0253-04-146
Proj IDNH 2017(592)
Work TypeGR, STRS, BASE, SIGN, DELIN & PAV
 
3.778179542332.7120998740.5511.6
CountyBEXAR
HighwayUS 281
FromLP 1604
To0.8 MI.NORTH OF STONE OAK
CSJ0253-04-151
Proj IDSTP 1602(378)
Work TypeROW ACQUISITION
 
3.57712759009.88446796.003.5
Work Order03-15-17
Work Began00-00-00
Work Completed
Time Computed04-14-17
Contract Working Days1,077
Addl Days Granted0
Working Days Charged42
Percent Time Used3
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0253-04-146
FLASHER EQUIPMENT COMPANY (0.58)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.60)
LONE STAR EROSION CONTROL (0.59)
ROYAL VISTA INC. (4.54)
W. W. FOUNDATION DRILLING, LTD. (1.75)
WEBBER BARRIER SERVICES, LLC. (1.70)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (1.99)
EARTH REINFORCEMENTS LLC (0.95)
LONE STAR PAVING (7.22)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.17)
HOUSTON SAWING & DRILLING (0.03)
THE LEVY COMPANY, L.P. (5.61)
(USE 26300)BRADCO, LLC (2.06)
GEOSOURCE, INC. (0.05)
GK CONSTRUCTION, LLC (0.09)
HOSS LAND SERVICES LLC (0.01)
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (0.01)
CP REBAR AND PT INSTALLATION (0.87)
JPC CONSTRUCTION INC DBA JC COMMUNICATIONS (1.25)
DU MOR ENTERPRISES (0.50)
TEXAS HIGHWAY WALLS (0.75)
INDUS ROAD & BRIDGE, INC (2.29)
FUQUAY, INC. (1.18)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (0.17)
Contract #02173001
Totals192301342.599215233.0321445536.5511.1

CountyBANDERA
HighwaySH 16
FromKERR COUNTY LINE
ToFM 2107
CSJ0291-04-024
Proj IDSTP 2015(933)HES
Work TypeGR, BASE, SURF & PAVMT MARKINGS
 
5.6702553976.462229346.8888.1
CountyBANDERA
HighwaySH 16
FromKERR COUNTY LINE
To0.6 MI S OF MESA VERDE ROAD
CSJ0291-04-025
Proj IDSTP 2015(934)HES
Work TypeGRS, BSE, SURF, STR, MBGF
 
2.700530989.38377863.4171.1
CountyBANDERA
HighwaySH 16
From0.2 MI WEST OF WINANS CROSSING
To2.8 MI EAST OF FM 470
CSJ0291-05-046
Proj IDSTP 2015(935)HES
Work TypeSTR, MBFG, GR,BASE, SURF & PVMT_MRK
 
6.0301760096.081380386.2778.4
Work Order06-11-15
Work Began10-01-15
Work Completed
Time Computed09-10-15
Contract Working Days442
Addl Days Granted36
Working Days Charged429
Percent Time Used105
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0291-04-024
RELMCO, INC. (28.06)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (10.94)
FLASHER EQUIPMENT COMPANY (4.11)
FUQUAY, INC. (3.91)
M.V. HENKE ENTERPRISES, INC. (1.67)
GEOSOURCE, INC. (1.36)
MURRAY CONSTRUCTION (2.00)
VOGES DRILLING CO. (0.60)
Contract #04153203
Totals4845061.92386039.843987596.5682.7

page 1 | page 2 | page 3 | page 4 | page 5 | page 6