Monthly Local Let Maintenance Report For Paris District As Of Jul 13, 2015 Page 6 Of 7

Last Update: Monday, July 13, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGRAYSON
Highway US0082
From VARIOUS LOCATIONS THROUGHOUT
To GRAYSON AND FANNIN COUNTY
CSJ 6284-82-001
Proj ID RMC - 628482001
Work Type ON CALL METAL BEAM GUARD FENCE REPAIR
 
0.001 316267.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6284-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05150102
Totals 316267.00 0.00 0.00 0.0

CountyGRAYSON
Highway US0075
From VARIOUS LOCATIONS ALONG US 75
To AND US 82 IN GRAYSON COUNTY
CSJ 6285-23-001
Proj ID RMC - 628523001
Work Type HIGH EDGE REMOVAL
 
0.001 240962.75 20295.75 20295.75 8.4
Work Order 04-23-15
Work Began 05-04-15
Work Completed  
Time Computed 05-11-15
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 23
Contractor(s)
LONE STAR BARRIER SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6285-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150102
Totals 240962.75 20295.75 20295.75 8.4

CountyGRAYSON
Highway US0377
From VARIOUS LOCATIONS IN
To GRAYSON COUNTY
CSJ 6285-24-001
Proj ID RMC - 628524001
Work Type HIGH EDGE REMOVAL
 
0.001 237443.00 136259.00 195899.00 82.5
Work Order 04-23-15
Work Began 05-04-15
Work Completed  
Time Computed 05-11-15
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 30
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150103
Totals 237443.00 136259.00 195899.00 82.5

CountyFANNIN
Highway US0082
From VARIOUS LOCATIONS
To IN FANNIN COUNTY
CSJ 6285-39-001
Proj ID SUP - 628539001
Work Type PICNIC / GROUNDS MAINTENANCE
 
0.001 41200.26 2822.67 6619.28 16.0
Work Order 04-01-15
Work Began 04-01-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
GROWING NEW GENERATIONS
SUBCONTRACTOR(S) FOR CCSJ: 6285-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150132
Totals 41200.26 2822.67 6619.28 16.0

CountyRED RIVER
Highway US0082
From RED RIVER COUNTY
To MAINT COMPLEX
CSJ 6285-40-001
Proj ID SUP - 628540001
Work Type JANITORIAL MAINTENANCE
 
0.001 8415.16 434.35 1303.05 15.4
Work Order 03-12-15
Work Began 04-01-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02150133
Totals 8415.16 434.35 1303.05 15.4

CountyDELTA
Highway SH0019
From DELTA COUNTY
To MAINT COMPLEX
CSJ 6285-41-001
Proj ID SUP - 628541001
Work Type GROUNDS MAINTENANCE
 
0.001 5425.00 340.00 850.00 15.6
Work Order 03-18-15
Work Began 04-01-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6285-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02150132
Totals 5425.00 340.00 850.00 15.6

CountyLAMAR
Highway US0271
From DISTRICT HEADQUARTERS
To COMPLEX
CSJ 6285-42-001
Proj ID SUP - 628542001
Work Type JANITORIAL MAINTENANCE
 
0.001 31700.00 1700.00 8704.00 27.4
Work Order 04-13-15
Work Began 04-13-15
Work Completed  
Time Computed 04-13-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 78
Percent Time Used 21
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150131
Totals 31700.00 1700.00 8704.00 27.4

CountyHOPKINS
Highway FM0069
From VARIOUS LOCATIONS IN HOPKINS AND
To FRANKLIN COUNTIES
CSJ 6285-81-001
Proj ID RMC - 628581001
Work Type ON CALL DITCH AND CULVERT CLEANING
 
0.001 278230.60 45640.00 45640.00 16.4
Work Order 05-20-15
Work Began 05-21-15
Work Completed  
Time Computed 05-28-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 9
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04150101
Totals 278230.60 45640.00 45640.00 16.4

CountyHUNT
Highway IH0030
From VARIOUS LOCATIONS IN HUNT AND
To RAINS COUNTIES
CSJ 6285-82-001
Proj ID RMC - 628582001
Work Type DITCH AND CULVERT CLEANING
 
0.001 267907.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-17-15
Work Began 07-01-15
Work Completed  
Time Computed 07-08-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-82-001
SOUTHWEST ENVIRONMENT SERVICES LLC (0.74%)
Contract # 05150101
Totals 267907.80 0.00 0.00 0.0

CountyLAMAR
Highway US0271
From VARIOUS LOCATIONS IN
To LAMAR COUNTY
CSJ 6286-64-001
Proj ID RMC - 628664001
Work Type PICNIC AREA MAINTENANCE
 
0.001 98501.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-16-15
Work Began 07-01-15
Work Completed  
Time Computed 07-08-15
Contract Working Days 306
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MORTON ENTERPRISE
SUBCONTRACTOR(S) FOR CCSJ: 6286-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05150108
Totals 98501.00 0.00 0.00 0.0

CountyFRANKLIN
Highway IH0030
From FRANKLIN CO MAINTENANCE
To COMPLEX
CSJ 6286-83-001
Proj ID SUP - 628683001
Work Type GROUNDS MAINTENANCE
 
0.001 6525.00 435.00 870.00 13.3
Work Order 04-29-15
Work Began 05-01-15
Work Completed  
Time Computed 05-01-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 16
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6286-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150135
Totals 6525.00 435.00 870.00 13.3

CountyHOPKINS
Highway SH0011
From HOPKINS CO MAINTENANCE
To OFFICE COMPLEX
CSJ 6286-85-001
Proj ID SUP - 628685001
Work Type GROUNDS MAINTENANCE
 
0.001 12134.00 1086.00 1448.00 11.9
Work Order 04-29-15
Work Began 00-00-00
Work Completed  
Time Computed 05-06-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 15
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6286-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150136
Totals 12134.00 1086.00 1448.00 11.9

CountyHUNT
Highway IH0030
From HUNT COUNTY AREA OFFICE AND
To MAINTENANCE COMPLEX
CSJ 6286-86-001
Proj ID SUP - 628686001
Work Type GROUNDS MAINTENANCE
 
0.001 14370.00 870.00 1305.00 9.0
Work Order 04-29-15
Work Began 00-00-00
Work Completed  
Time Computed 05-08-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 14
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6286-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150134
Totals 14370.00 870.00 1305.00 9.0

CountyRAINS
Highway US0069
From VARIOUS ROADWAYS IN
To RAINS COUNTY
CSJ 6286-87-001
Proj ID SUP - 628687001
Work Type PICNIC AREA MAINTENANCE
 
0.001 0.00 2575.00 4125.00 0.0
Work Order 04-29-15
Work Began 05-11-15
Work Completed  
Time Computed 05-11-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 13
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6286-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150133
Totals 0.00 2575.00 4125.00 0.0

CountyLAMAR
Highway BU0271B
From PARIS DISTRICT HEADQUARTERS
To AT 1365 N MAIN
CSJ 6287-51-001
Proj ID SUP - 628751001
Work Type DISTRICT GROUNDS MAINTENANCE
 
0.001 29960.00 2060.00 2840.00 9.4
Work Order 04-13-15
Work Began 04-13-15
Work Completed  
Time Computed 04-13-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04150133
Totals 29960.00 2060.00 2840.00 9.4

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS IN
To HOPKINS COUNTY
CSJ 6287-52-001
Proj ID SUP - 628752001
Work Type LANDSCAPE MAINTENANCE
 
0.001 17097.94 212.00 212.00 1.2
Work Order 05-26-15
Work Began 06-01-15
Work Completed  
Time Computed 06-01-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6287-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04150132
Totals 17097.94 212.00 212.00 1.2

CountyFANNIN
Highway US0082
From MAINTENANCE OFFICE
To COMPLEX IN FANNIN COUNTY
CSJ 6287-53-001
Proj ID SUP - 628753001
Work Type JANITORIAL MAINTENANCE
 
0.001 12704.84 0.00 2340.24 18.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-13-15
Work Began 04-13-15
Work Completed  
Time Computed 04-13-15
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04150131
Totals 12704.84 0.00 2340.24 18.4

CountyLAMAR
Highway LP0286
From LAMAR MAINT OFFICE
To MAINT AND AREA OFFICE COMPLEX
CSJ 6287-54-001
Proj ID SUP - 628754001
Work Type JANITORIAL MAINTENANCE
 
0.001 10869.20 639.10 994.44 9.1
Work Order 04-13-15
Work Began 00-00-00
Work Completed  
Time Computed 04-13-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04150134
Totals 10869.20 639.10 994.44 9.1

CountyLAMAR
Highway SL0286
From GROUNDS MAINTENANCE AT
To PARIS AREA OFFICE
CSJ 6288-04-001
Proj ID SUP - 628804001
Work Type GROUNDS MAINTENANCE
 
0.001 5700.00 750.00 1200.00 21.0
Work Order 04-13-15
Work Began 04-13-15
Work Completed  
Time Computed 04-13-15
Contract Working Days 79
Addl Days Granted 0
Working Days Charged 77
Percent Time Used 97
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04150135
Totals 5700.00 750.00 1200.00 21.0

CountyLAMAR
Highway BU0271B
From PARIS DISTRICT HEADQUARTERS
To 1365 N MAIN
CSJ 6288-68-001
Proj ID SUP - 628868001
Work Type DISTRICT HDQTRS GROUNDS MAINTENANCE
 
0.001 30858.64 3970.20 3970.20 12.8
Work Order 05-26-15
Work Began 06-01-15
Work Completed  
Time Computed 06-01-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05150132
Totals 30858.64 3970.20 3970.20 12.8