Monthly Local Let Maintenance Report For Paris District As Of Aug 12, 2014 Page 4 Of 5

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyRED RIVER
Highway US0082
From VARIOUS ROADWAYS
To IN RED RIVER COUNTY
CSJ 6266-14-001
Proj ID SUP - 626614001
Work Type PICNIC AREA MAINTENANCE
 
0.001 21795.00 2040.00 13785.00 63.2
Work Order 11-05-13
Work Began 11-17-13
Work Completed  
Time Computed 11-17-13
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 257
Percent Time Used 70
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6266-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11130131
Totals 21795.00 2040.00 13785.00 63.2

CountyLAMAR
Highway FM1502
From VARIOUS LOCATIONS IN LAMAR, DELTA,
To AND RED RIVER COUNTIES
CSJ 6266-33-001
Proj ID RMC - 626633001
Work Type CROSS DRAINAGE STRUCTURE REPLACEMENT
 
0.001 294995.00 105269.00 214847.75 73.4
Work Order 04-18-14
Work Began 05-05-14
Work Completed  
Time Computed 05-12-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 48
Percent Time Used 106
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6266-33-001
PANOLA SIGN & BARRICADE, INC.(2.37%)
Contract # 03140104
Totals 294995.00 105269.00 214847.75 73.4

CountyLAMAR
Highway US0082
From VARIOUS LOCATIONS IN LAMAR, DELTA,
To AND RED RIVER COUNTIES
CSJ 6266-40-001
Proj ID RMC - 626640001
Work Type ON CALL METAL BEAM GUARD FENCE REPAIR
 
0.001 147784.00 37770.00 81456.00 55.1
Work Order 02-10-14
Work Began 00-00-00
Work Completed  
Time Computed 02-19-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 22
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01140103
Totals 147784.00 37770.00 81456.00 55.1

CountyFANNIN
Highway US0082
From VARIOUS ROADWAYS IN
To FANNIN COUNTY
CSJ 6266-49-001
Proj ID SUP - 626649001
Work Type LITTER PICK UP
 
0.010 22982.36 0.00 20559.36 89.4
Work Order 11-25-13
Work Began 12-01-13
Work Completed  
Time Computed 12-01-13
Contract Working Days 275
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 18
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6266-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11130132
Totals 22982.36 0.00 20559.36 89.4

CountyHUNT
Highway IH0030
From VARIOUS LOCATIONS IN
To HUNT AND RAINS COUNTIES
CSJ 6267-69-001
Proj ID RMC - 626769001
Work Type ON CALL TREE REMOVAL / TRIMMING
 
0.001 223625.00 13000.00 224500.00 99.9
Work Order 03-17-14
Work Began 00-00-00
Work Completed  
Time Computed 03-28-14
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 33
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6267-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140108
Totals 223625.00 13000.00 224500.00 99.9

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS IN
To HOPKINS AND FRANKLIN COUNTIES
CSJ 6267-70-001
Proj ID RMC - 626770001
Work Type ON CALL TREE REMOVAL / TRIMMING
 
0.001 220125.00 66600.00 191625.00 87.0
Work Order 03-12-14
Work Began 03-21-14
Work Completed  
Time Computed 03-28-14
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 37
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6267-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140101
Totals 220125.00 66600.00 191625.00 87.0

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS IN
To HOPKINS, HUNT AND FRANKLIN CO.
CSJ 6267-72-001
Proj ID RMC - 626772001
Work Type REMOVAL AND DISPOSAL OF DEBRIS
 
0.001 127445.76 11845.92 27776.64 21.7
Work Order 04-10-14
Work Began 05-01-14
Work Completed  
Time Computed 05-08-14
Contract Working Days 254
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 22
Contractor(s)
FLAGSHIP SWEEPING SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140102
Totals 127445.76 11845.92 27776.64 21.7

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS
To IN PARIS DISTRICT
CSJ 6267-73-001
Proj ID BPM - 626773001
Work Type BPM - BRIDGE BEAM REPAIR
 
0.001 155900.00 0.00 179700.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-27-14
Work Began 00-00-00
Work Completed  
Time Computed 06-04-14
Contract Working Days 30
Addl Days Granted 5
Working Days Charged 26
Percent Time Used 74
Contractor(s)
DRS CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140105
Totals 155900.00 0.00 179700.00 99.9

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS
To IN HOPKINS COUNTY
CSJ 6267-87-001
Proj ID SUP - 626787001
Work Type PICNIC AREA MAINTENANCE
 
0.010 28676.00 2032.00 14223.50 49.6
Work Order 01-08-14
Work Began 01-15-14
Work Completed  
Time Computed 01-15-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 196
Percent Time Used 53
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6267-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01140131
Totals 28676.00 2032.00 14223.50 49.6

CountyLAMAR
Highway US0082
From VARIOUS LOCATION IN LAMAR
To AND DELTA COUNTIES
CSJ 6269-16-001
Proj ID RMC - 626916001
Work Type ON CALL TREE TRIMMING / REMOVAL
 
0.001 190404.00 0.00 184640.00 96.9
Work Order 04-18-14
Work Began 05-01-14
Work Completed  
Time Computed 05-08-14
Contract Working Days 175
Addl Days Granted 175
Working Days Charged 27
Percent Time Used 7
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140101
Totals 190404.00 0.00 184640.00 96.9

CountyGRAYSON
Highway US0075
From VARIOUS LOCATIONS IN
To GRAYSON AND FANNIN COUNTIES
CSJ 6269-18-001
Proj ID RMC - 626918001
Work Type METAL BEAM GUARD FENCE / CABLE REPAIR
 
0.001 195342.40 8710.75 62504.70 31.9
Work Order 04-09-14
Work Began 04-10-14
Work Completed  
Time Computed 04-17-14
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 39
Contractor(s)
LONE STAR BARRIER SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6269-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140106
Totals 195342.40 8710.75 62504.70 31.9

CountyHOPKINS
Highway IH0030
From HOPKINS COUNTY MAINT OFFICE
To AREA/MAINT OFFICE
CSJ 6269-24-001
Proj ID SUP - 626924001
Work Type JANITORIAL MAINTENANCE
 
0.001 14782.16 1413.23 6272.53 42.4
Work Order 02-04-14
Work Began 03-01-14
Work Completed  
Time Computed 03-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140131
Totals 14782.16 1413.23 6272.53 42.4

CountyGRAYSON
Highway US0075
From GRAYSON CO AREA OFFICE
To AND MAINT COMPLEX
CSJ 6269-25-001
Proj ID SUP - 626925001
Work Type JANITORIAL MAINTENANCE
 
0.001 21000.00 1050.00 7350.00 35.0
Work Order 02-04-14
Work Began 03-01-14
Work Completed  
Time Computed 03-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6269-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140132
Totals 21000.00 1050.00 7350.00 35.0

CountyHUNT
Highway SH0066
From VARIOUS LOCATIONS IN
To PARIS DISTRICT
CSJ 6269-28-001
Proj ID RMC - 626928001
Work Type CRACK SEAL
 
0.001 204600.00 0.00 203300.00 99.3
Work Order 04-29-14
Work Began 05-19-14
Work Completed  
Time Computed 05-26-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 96
Contractor(s)
DEVTEX INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140105
Totals 204600.00 0.00 203300.00 99.3

CountyFANNIN
Highway US0082
From VARIOUS LOCATIONS
To IN FANNIN COUNTY
CSJ 6269-47-001
Proj ID SUP - 626947001
Work Type PICNIC MAINTENANCE
 
0.001 40000.10 3573.94 13323.99 33.3
Work Order 03-24-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 87
Percent Time Used 23
Contractor(s)
TIBH INDUSTRIES, INC.
GROWING NEW GENERATIONS
SUBCONTRACTOR(S) FOR CCSJ: 6269-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140131
Totals 40000.10 3573.94 13323.99 33.3

CountyRED RIVER
Highway US0082
From RED RIVER COUNTY
To MAINT COMPLEX
CSJ 6269-65-001
Proj ID SUP - 626965001
Work Type JANITORIAL MAINTENANCE
 
0.001 0.00 434.35 2881.65 0.0
Work Order 03-17-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 121
Percent Time Used 33
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140135
Totals 0.00 434.35 2881.65 0.0

CountyGRAYSON
Highway US0082
From VARIOUS ROADWAYS IN GRAYSON AND
To FANNIN COUNTY
CSJ 6269-89-001
Proj ID RMC - 626989001
Work Type ON CALL TREE TRIMMING / REMOVAL
 
0.001 316175.00 6863.00 6863.00 2.1
Work Order 05-27-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 18
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140107
Totals 316175.00 6863.00 6863.00 2.1

CountyLAMAR
Highway US0271
From VARIOUS ROADWAYS IN
To LAMAR COUNTY
CSJ 6270-14-001
Proj ID RMC - 627014001
Work Type PICNIC AREA MAINTENANCE
 
0.001 53750.00 4050.00 17125.00 31.8
Work Order 04-02-14
Work Began 04-03-14
Work Completed  
Time Computed 04-10-14
Contract Working Days 306
Addl Days Granted 0
Working Days Charged 94
Percent Time Used 30
Contractor(s)
LONE STAR BARRIER SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6270-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140108
Totals 53750.00 4050.00 17125.00 31.8

CountyDELTA
Highway SH0019
From FOR THE DELTA COUNTY
To MAINTENANCE OFFICE COMPLEX
CSJ 6270-34-001
Proj ID SUP - 627034001
Work Type GROUNDS MAINTENANCE
 
0.001 5425.00 340.00 1700.00 31.3
Work Order 03-12-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 33
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6270-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140132
Totals 5425.00 340.00 1700.00 31.3

CountyLAMAR
Highway US0271
From DISTRICT HEADQUARTERS
To AT 1365 N MAIN, PARIS, TEXAS
CSJ 6270-36-001
Proj ID SUP - 627036001
Work Type JANITORIAL MAINTENANCE
 
0.001 31700.00 1700.00 11050.00 34.8
Work Order 03-26-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 121
Percent Time Used 33
Contractor(s)
TIBH INDUSTRIES, INC.
LIFENET COMMUNITY BEHAVIORAL HEALTHCARE
SUBCONTRACTOR(S) FOR CCSJ: 6270-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140133
Totals 31700.00 1700.00 11050.00 34.8