Monthly Local Let Maintenance Report For Paris District As Of Dec 12, 2017 Page 4 Of 5

Last Update: Tuesday, December 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN LAMAR, DELTA, AND
ToRED RIVER COUNTIES
CSJ6314-94-001
Proj IDRMC - 631494001
Work TypeON CALL TY II STRIPING
 
0.001147690.0090404.5061.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-08-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged176
Percent Time Used48
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6314-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04170101
Totals147690.001942.1090404.5061.2

CountyGRAYSON
HighwayUS0075
FromVARIOUS LOCATIONS IN GRAYSON AND
ToFANNIN COUNTIES
CSJ6314-96-001
Proj IDRMC - 631496001
Work TypeON CALL TY II STRIPING
 
0.001142200.0025805.1018.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-08-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged177
Percent Time Used48
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6314-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04170102
Totals142200.000.0025805.1018.1

CountyHUNT
HighwayUS0069
FromSH276/FM1565 AND
ToUS69 FRONTAGE ROAD
CSJ6315-27-001
Proj IDRMC - 631527001
Work TypeINSTALL TRAFFIC SIGNAL
 
0.001285882.00245930.6686.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-28-17
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged43
Percent Time Used71
Contractor(s)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6315-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05170103
Totals285882.0058186.86245930.6686.0

CountyFRANKLIN
HighwayIH0030
FromFRANKLIN COUNTY MAINTENANCE
ToCOMPLEX
CSJ6316-06-001
Proj IDSUP - 631606001
Work TypeGROUNDS MAINTENANCE
 
0.0016525.003262.5050.0
Work Order04-17-17
Work Began00-00-00
Work Completed
Time Computed05-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged214
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6316-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03170131
Totals6525.00217.503262.5050.0

CountyHOPKINS
HighwaySH0011
FromHOPKINS COUNTY MAINTENANCE
ToOFFICE COMPLEX
CSJ6316-10-001
Proj IDSUP - 631610001
Work TypeGROUNDS MAINTENANCE
 
0.00112134.006516.0053.7
Work Order04-18-17
Work Began00-00-00
Work Completed
Time Computed05-06-17
Contract Working Days365
Addl Days Granted0
Working Days Charged209
Percent Time Used57
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6316-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03170132
Totals12134.000.006516.0053.7

CountyHUNT
HighwayIH0030
FromHUNT COUNTY AREA OFFICE AND
ToMAINTENANCE COMPLEX
CSJ6316-11-001
Proj IDSUP - 631611001
Work TypeGROUNDS MAINTENANCE
 
0.00114370.0010005.0069.6
Work Order04-19-17
Work Began00-00-00
Work Completed
Time Computed05-08-17
Contract Working Days365
Addl Days Granted0
Working Days Charged207
Percent Time Used56
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6316-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03170133
Totals14370.00435.0010005.0069.6

CountyRAINS
HighwayUS0069
FromVARIOUS ROADWAYS IN
ToRAINS COUNTY
CSJ6316-13-001
Proj IDSUP - 631613001
Work TypePICNIC AREA MAINTENANCE
 
0.00128200.0015650.0055.4
Work Order04-19-17
Work Began00-00-00
Work Completed
Time Computed05-11-17
Contract Working Days365
Addl Days Granted0
Working Days Charged204
Percent Time Used55
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6316-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03170134
Totals28200.001900.0015650.0055.4

CountyGRAYSON
HighwayUS0075
FromVARIOUS LOCATIONS IN GRAYSON AND
ToFANNIN COUNTIES
CSJ6316-32-001
Proj IDRMC - 631632001
Work TypeON CALL LARGE SIGN MAINTENANCE
 
0.001269962.0027670.1810.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted0
Working Days Charged19
Percent Time Used7
Contractor(s)
SOUTHERN CROSS CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05170105
Totals269962.004000.0027670.1810.2

CountyHUNT
HighwayIH0030
FromVARIOUS LOCATIONS
ToIN PARIS DISTRICT
CSJ6316-33-001
Proj IDRMC - 631633001
Work TypeON CALL LARGE SIGN MAINTENANCE
 
0.001296512.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SOUTHERN CROSS CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06170101
Totals296512.000.000.000.0

CountyGRAYSON
HighwayUS0082
FromVARIOUS ROADWAYS IN GRAYSON AND
ToFANNIN COUNTIES
CSJ6316-37-001
Proj IDRMC - 631637001
Work TypeON CALL TREE TRIMMING/REMOVAL
 
0.001236700.0021039.008.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged91
Percent Time Used24
Contractor(s)
AMELIORATION GROUP
SUBCONTRACTOR(S) FOR CCSJ: 6316-37-001
ARBORTEX (80.00)
Contract #05170101
Totals236700.0019084.0021039.008.8

CountyHUNT
HighwaySH0034
FromVARIOUS LOCATIONS IN HUNT AND
ToRAINS COUNTY
CSJ6316-46-001
Proj IDRMC - 631646001
Work TypeON CALL TREE TRIMMING
 
0.001237500.0053910.0022.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged137
Percent Time Used37
Contractor(s)
SAMMY GIST ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05170102
Totals237500.0010725.0053910.0022.6

CountyGRAYSON
HighwayUS0075
FromVARIOUS LOCATIONS
ToIN FANNIN AND GRAYSON COUNTIES
CSJ6316-50-001
Proj IDSUP - 631650001
Work TypeREM/REPL/INSTALL DEL POST/OBJ MRK, MAILB
 
0.00170000.0033445.0047.7
Work Order05-04-17
Work Began00-00-00
Work Completed
Time Computed05-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged199
Percent Time Used54
Contractor(s)
TIBH INDUSTRIES, INC.
VOCATIONAL OPPORTUNITIES CENTER NORTHEAST TEXAS,INC
SUBCONTRACTOR(S) FOR CCSJ: 6316-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03170135
Totals70000.005422.0033445.0047.7

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6316-73-001
Proj IDRMC - 631673001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.001258624.0030708.0011.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-19-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged135
Percent Time Used36
Contractor(s)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6316-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05170104
Totals258624.000.0030708.0011.8

CountyHOPKINS
HighwayIH0030
FromVARIOUS LOCATIONS IN
ToHOPKINS COUNTY
CSJ6317-32-001
Proj IDSUP - 631732001
Work TypeLANDSCAPE MAINTENANCE
 
0.00123460.7611257.8647.9
Work Order05-25-17
Work Began00-00-00
Work Completed
Time Computed06-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged183
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6317-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04170131
Totals23460.761000.9911257.8647.9

CountyLAMAR
HighwayBU0271B
FromPARIS DISTRICT HEADQUARTERS
To1365 NORTH MAIN
CSJ6317-33-001
Proj IDSUP - 631733001
Work TypeDISTRICT HDQTRS GROUNDS MAINTENANCE
 
0.00131050.0013325.0042.9
Work Order05-15-17
Work Began06-01-17
Work Completed
Time Computed06-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged183
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04170132
Totals31050.000.0013325.0042.9

CountyLAMAR
HighwaySL0286
FromLAMAR COUNTY MAINTENANCE OFFICE
ToAND AREA OFFICE COMPLET
CSJ6317-44-001
Proj IDSUP - 631744001
Work TypeJANITORIAL MAINTENANCE
 
0.00111195.164902.3043.7
Work Order05-01-17
Work Began00-00-00
Work Completed
Time Computed06-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged183
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04170133
Totals11195.16652.684902.3043.7

CountyGRAYSON
HighwayUS0075
FromVARIOUS ROADWAYS IN
ToGRAYSON CO.
CSJ6317-69-001
Proj IDRMC - 631769001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.001287638.0046062.0016.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged60
Percent Time Used16
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6317-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170101
Totals287638.000.0046062.0016.0

CountyLAMAR
HighwaySL0286
FromPARIS MAINTENANCE COMPLEX
ToAND AREA OFFICE
CSJ6318-46-001
Proj IDSUP - 631846001
Work TypeGROUNDS MAINTENANCE
 
0.0016160.001600.0025.9
Work Order05-16-17
Work Began00-00-00
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04170134
Totals6160.000.001600.0025.9

CountyFRANKLIN
HighwayIH0030
FromVARIOUS ROADWAYS IN
ToFRANKLIN COUNTY
CSJ6318-52-001
Proj IDSUP - 631852001
Work TypePICNIC MAINTENANCE
 
0.00112802.005630.0043.9
Work Order05-31-17
Work Began00-00-00
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6318-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04170135
Totals12802.00766.005630.0043.9

CountyHUNT
HighwayUS0069
FromVARIOUS LOCATIONS IN HUNT AND
ToRAINS COUNTIES
CSJ6318-93-001
Proj IDRMC - 631893001
Work TypeCRACK SEAL
 
0.001189272.73180420.8095.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-17
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged5
Percent Time Used14
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170101
Totals189272.730.00180420.8095.3

page 1 | page 2 | page 3 | page 4 | page 5