Monthly Local Let Maintenance Report For Paris District As Of Sep 15, 2014 Page 4 Of 5

Last Update: Monday, September 15, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHUNT
Highway IH0030
From VARIOUS LOCATIONS IN
To HUNT AND RAINS COUNTIES
CSJ 6267-69-001
Proj ID RMC - 626769001
Work Type ON CALL TREE REMOVAL / TRIMMING
 
0.001 223625.00 0.00 224500.00 99.9
Work Order 03-17-14
Work Began 00-00-00
Work Completed  
Time Computed 03-28-14
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 33
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6267-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140108
Totals 223625.00 0.00 224500.00 99.9

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS IN
To HOPKINS AND FRANKLIN COUNTIES
CSJ 6267-70-001
Proj ID RMC - 626770001
Work Type ON CALL TREE REMOVAL / TRIMMING
 
0.001 220125.00 56159.00 247784.00 99.9
Work Order 03-12-14
Work Began 03-21-14
Work Completed  
Time Computed 03-28-14
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 43
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6267-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140101
Totals 220125.00 56159.00 247784.00 99.9

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS IN
To HOPKINS, HUNT AND FRANKLIN CO.
CSJ 6267-72-001
Proj ID RMC - 626772001
Work Type REMOVAL AND DISPOSAL OF DEBRIS
 
0.001 127445.76 14705.28 42481.92 33.3
Work Order 04-10-14
Work Began 05-01-14
Work Completed  
Time Computed 05-08-14
Contract Working Days 254
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 31
Contractor(s)
FLAGSHIP SWEEPING SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140102
Totals 127445.76 14705.28 42481.92 33.3

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS
To IN PARIS DISTRICT
CSJ 6267-73-001
Proj ID BPM - 626773001
Work Type BPM - BRIDGE BEAM REPAIR
 
0.001 155900.00 0.00 179700.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-27-14
Work Began 00-00-00
Work Completed  
Time Computed 06-04-14
Contract Working Days 30
Addl Days Granted 5
Working Days Charged 26
Percent Time Used 74
Contractor(s)
DRS CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140105
Totals 155900.00 0.00 179700.00 99.9

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS
To IN HOPKINS COUNTY
CSJ 6267-87-001
Proj ID SUP - 626787001
Work Type PICNIC AREA MAINTENANCE
 
0.010 28676.00 2182.00 16405.50 57.2
Work Order 01-08-14
Work Began 01-15-14
Work Completed  
Time Computed 01-15-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 227
Percent Time Used 62
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6267-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01140131
Totals 28676.00 2182.00 16405.50 57.2

CountyLAMAR
Highway US0082
From VARIOUS LOCATION IN LAMAR
To AND DELTA COUNTIES
CSJ 6269-16-001
Proj ID RMC - 626916001
Work Type ON CALL TREE TRIMMING / REMOVAL
 
0.001 190404.00 49275.00 233915.00 99.9
Work Order 04-18-14
Work Began 05-01-14
Work Completed  
Time Computed 05-08-14
Contract Working Days 175
Addl Days Granted 175
Working Days Charged 36
Percent Time Used 10
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140101
Totals 190404.00 49275.00 233915.00 99.9

CountyGRAYSON
Highway US0075
From VARIOUS LOCATIONS IN
To GRAYSON AND FANNIN COUNTIES
CSJ 6269-18-001
Proj ID RMC - 626918001
Work Type METAL BEAM GUARD FENCE / CABLE REPAIR
 
0.001 195342.40 19596.42 82101.12 42.0
Work Order 04-09-14
Work Began 04-10-14
Work Completed  
Time Computed 04-17-14
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 89
Percent Time Used 50
Contractor(s)
LONE STAR BARRIER SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6269-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140106
Totals 195342.40 19596.42 82101.12 42.0

CountyHOPKINS
Highway IH0030
From HOPKINS COUNTY MAINT OFFICE
To AREA/MAINT OFFICE
CSJ 6269-24-001
Proj ID SUP - 626924001
Work Type JANITORIAL MAINTENANCE
 
0.001 14782.16 1016.42 7288.95 49.3
Work Order 02-04-14
Work Began 03-01-14
Work Completed  
Time Computed 03-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 184
Percent Time Used 50
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140131
Totals 14782.16 1016.42 7288.95 49.3

CountyGRAYSON
Highway US0075
From GRAYSON CO AREA OFFICE
To AND MAINT COMPLEX
CSJ 6269-25-001
Proj ID SUP - 626925001
Work Type JANITORIAL MAINTENANCE
 
0.001 21000.00 1050.00 8400.00 40.0
Work Order 02-04-14
Work Began 03-01-14
Work Completed  
Time Computed 03-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 184
Percent Time Used 50
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6269-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140132
Totals 21000.00 1050.00 8400.00 40.0

CountyFANNIN
Highway US0082
From VARIOUS LOCATIONS
To IN FANNIN COUNTY
CSJ 6269-47-001
Proj ID SUP - 626947001
Work Type PICNIC MAINTENANCE
 
0.001 40000.10 3854.71 17178.70 42.9
Work Order 03-24-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 108
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
GROWING NEW GENERATIONS
SUBCONTRACTOR(S) FOR CCSJ: 6269-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140131
Totals 40000.10 3854.71 17178.70 42.9

CountyRED RIVER
Highway US0082
From RED RIVER COUNTY
To MAINT COMPLEX
CSJ 6269-65-001
Proj ID SUP - 626965001
Work Type JANITORIAL MAINTENANCE
 
0.001 0.00 434.35 3316.00 0.0
Work Order 03-17-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 152
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140135
Totals 0.00 434.35 3316.00 0.0

CountyGRAYSON
Highway US0082
From VARIOUS ROADWAYS IN GRAYSON AND
To FANNIN COUNTY
CSJ 6269-89-001
Proj ID RMC - 626989001
Work Type ON CALL TREE TRIMMING / REMOVAL
 
0.001 316175.00 0.00 6863.00 2.1
Work Order 05-27-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 29
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140107
Totals 316175.00 0.00 6863.00 2.1

CountyLAMAR
Highway US0271
From VARIOUS ROADWAYS IN
To LAMAR COUNTY
CSJ 6270-14-001
Proj ID RMC - 627014001
Work Type PICNIC AREA MAINTENANCE
 
0.001 53750.00 4350.00 21475.00 39.9
Work Order 04-02-14
Work Began 04-03-14
Work Completed  
Time Computed 04-10-14
Contract Working Days 306
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 39
Contractor(s)
LONE STAR BARRIER SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6270-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140108
Totals 53750.00 4350.00 21475.00 39.9

CountyDELTA
Highway SH0019
From FOR THE DELTA COUNTY
To MAINTENANCE OFFICE COMPLEX
CSJ 6270-34-001
Proj ID SUP - 627034001
Work Type GROUNDS MAINTENANCE
 
0.001 5425.00 340.00 2040.00 37.6
Work Order 03-12-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6270-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140132
Totals 5425.00 340.00 2040.00 37.6

CountyLAMAR
Highway US0271
From DISTRICT HEADQUARTERS
To AT 1365 N MAIN, PARIS, TEXAS
CSJ 6270-36-001
Proj ID SUP - 627036001
Work Type JANITORIAL MAINTENANCE
 
0.001 31700.00 3100.00 14150.00 44.6
Work Order 03-26-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 152
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
LIFENET COMMUNITY BEHAVIORAL HEALTHCARE
SUBCONTRACTOR(S) FOR CCSJ: 6270-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140133
Totals 31700.00 3100.00 14150.00 44.6

CountyHUNT
Highway IH0030
From HUNT COUNTY AREA OFFICE
To AND MAINTENANCE OFFICE
CSJ 6270-37-001
Proj ID SUP - 627037001
Work Type JANITORIAL MAINTENANCE
 
0.001 24219.83 816.92 6099.57 25.1
Work Order 03-17-14
Work Began 04-03-14
Work Completed  
Time Computed 04-03-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 151
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140134
Totals 24219.83 816.92 6099.57 25.1

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS IN HOPKINS, FRANKLIN
To HUNT AND RAINS COUNTY
CSJ 6270-48-001
Proj ID RMC - 627048001
Work Type ON CALL METAL BEAM GUARD FENCE REPAIR
 
0.001 226485.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06140101
Totals 226485.00 0.00 0.00 0.0

CountyGRAYSON
Highway US0075
From STATE LINE
To COLLIN COUNTY LINE
CSJ 6270-68-001
Proj ID RMC - 627068001
Work Type INSTALL / REPLACE DELINEATORS
 
0.001 79660.00 0.00 65741.00 82.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 07-08-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 100
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6270-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140101
Totals 79660.00 0.00 65741.00 82.5

CountyFRANKLIN
Highway IH0030
From FRANKLIN CO MAINTENANCE
To COMPLEX
CSJ 6271-64-001
Proj ID SUP - 627164001
Work Type GROUNDS MAINTENANCE
 
0.001 6525.00 1087.50 3262.50 50.0
Work Order 04-07-14
Work Began 05-01-14
Work Completed  
Time Computed 05-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 123
Percent Time Used 33
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6271-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04140132
Totals 6525.00 1087.50 3262.50 50.0

CountyHOPKINS
Highway SH0011
From HOPKINS CO MAINTENANCE
To OFFICE COMPLEX
CSJ 6271-65-001
Proj ID SUP - 627165001
Work Type GROUNDS MAINTENANCE
 
0.001 6342.00 724.00 2896.00 45.6
Work Order 04-07-14
Work Began 05-06-14
Work Completed  
Time Computed 05-06-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 118
Percent Time Used 32
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6271-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04140131
Totals 6342.00 724.00 2896.00 45.6

page 1 | page 2 | page 3 | page 4 | page 5