Monthly Local Let Maintenance Report For Paris District As Of Jun 12, 2017 Page 3 Of 6

Last Update: Monday, June 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyFRANKLIN
HighwayIH0030
FromFRANKLIN COUNTY MAINTENANCE COMPLEX
ToIN MT. VERNON, TX
CSJ6304-41-001
Proj IDSUP - 630441001
Work TypeJANITORIAL MAINTENANCE
 
0.00116000.1212757.8179.7
Work Order08-01-16
Work Began00-00-00
Work Completed
Time Computed08-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged304
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05160132
Totals16000.121634.5112757.8179.7

CountyHUNT
HighwayIH0030
FromVARIOUS LOCATIONS IN HUNT AND
ToRAINS COUNTIES
CSJ6304-92-001
Proj IDRMC - 630492001
Work TypeON CALL TREE REMOVAL
 
0.001138535.00156477.0099.9
Work Order09-27-16
Work Began00-00-00
Work Completed
Time Computed10-10-16
Contract Working Days365
Addl Days Granted365
Working Days Charged234
Percent Time Used32
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160101
Totals138535.000.00156477.0099.9

CountyGRAYSON
HighwayUS0082
FromVARIOUS LOCATIONS IN GRAYSON AND
ToFANNIN COUNTIES
CSJ6305-05-001
Proj IDRMC - 630505001
Work TypeON CALL METAL BEAM GUARD FENCE REPAIR
 
0.001622185.00190160.0030.5
Work Order09-26-16
Work Began00-00-00
Work Completed
Time Computed10-03-16
Contract Working Days365
Addl Days Granted0
Working Days Charged241
Percent Time Used66
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6305-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160101
Totals622185.0018910.00190160.0030.5

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN LAMAR, DELTA,
ToAND RED RIVER COUNTIES
CSJ6305-58-001
Proj IDRMC - 630558001
Work TypeON CALL DRAINAGE IMPROVEMENT
 
0.001166262.00188615.7099.9
Work Order09-29-16
Work Began00-00-00
Work Completed
Time Computed10-03-16
Contract Working Days365
Addl Days Granted365
Working Days Charged241
Percent Time Used33
Contractor(s)
ANCHOR CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6305-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160102
Totals166262.0041029.25188615.7099.9

CountyRAINS
HighwayUS0069
FromRAINS MAINTENANCE
ToCOMPLEX
CSJ6305-74-001
Proj IDSUP - 630574001
Work TypeGROUNDS MAINTENANCE
 
0.00110620.006320.0059.5
Work Order07-06-16
Work Began00-00-00
Work Completed
Time Computed08-06-16
Contract Working Days365
Addl Days Granted0
Working Days Charged299
Percent Time Used81
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6305-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160131
Totals10620.001360.006320.0059.5

CountyRED RIVER
HighwayUS0082
FromRED RIVER COUNTY MAINTENANCE
ToCOMPLEX
CSJ6305-79-001
Proj IDSUP - 630579001
Work TypeGROUNDS MAINTENANCE
 
0.0016550.002795.0042.6
Work Order07-08-16
Work Began00-00-00
Work Completed
Time Computed08-16-16
Contract Working Days365
Addl Days Granted0
Working Days Charged288
Percent Time Used78
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6305-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160132
Totals6550.00645.002795.0042.6

CountyGRAYSON
HighwayUS0075
FromVARIOUS LOCATIONS
ToIN GRAYSON COUNTY
CSJ6305-83-001
Proj IDSUP - 630583001
Work TypeLITTER PICK UP
 
0.00162390.6546599.8474.6
Work Order08-31-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6305-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160133
Totals62390.655553.1246599.8474.6

CountyHOPKINS
HighwayIH0030
FromVARIOUS LOCATIONS IN
ToHOPKINS & FRANKLIN COUNTIES
CSJ6305-98-001
Proj IDSUP - 630598001
Work TypeLITTER PICK UP
 
0.00172380.5962029.8085.6
Work Order08-15-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6305-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160134
Totals72380.592855.0262029.8085.6

CountyHUNT
HighwayIH0030
FromVARIOUS LOCATIONS IN
ToHUNT COUNTY
CSJ6305-99-001
Proj IDSUP - 630599001
Work TypeLITTER PICK UP
 
0.00196936.8563559.1065.5
Work Order08-31-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160135
Totals96936.855063.5063559.1065.5

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN
ToLAMAR/DELTA/RED RIVER COUNTIES
CSJ6306-01-001
Proj IDSUP - 630601001
Work TypeLITTER PICK UP
 
0.001132193.1691542.0969.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
VOCATIONAL OPPORTUNITIES CENTER NORTHEAST TEXAS,INC
SUBCONTRACTOR(S) FOR CCSJ: 6306-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160136
Totals132193.169063.9391542.0969.2

CountyRAINS
HighwayUS0069
FromVARIOUS LOCATIONS
ToIN RAINS COUNTY
CSJ6306-65-001
Proj IDSUP - 630665001
Work TypeLITTER PICK UP
 
0.00128288.3821378.9075.5
Work Order08-11-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6306-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160137
Totals28288.380.0021378.9075.5

CountyFANNIN
HighwayUS0082
FromVARIOUS LOCATIONS IN
ToFANNIN COUNTY
CSJ6306-67-001
Proj IDSUP - 630667001
Work TypeLITTER PICK UP
 
0.00149657.7330068.5460.5
Work Order08-31-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6306-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160138
Totals49657.731591.4430068.5460.5

CountyFANNIN
HighwaySH0056
FromSAM RAYBURN HOUSE IN
ToBONHAM, TEXAS
CSJ6307-28-001
Proj IDRMC - 630728001
Work TypePARKING LOT IMPROVEMENT
 
0.00160687.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days14
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OLD FIREHOUSE GYM LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-28-001
LYNN VESSELS CONSTRUCTION, LLC (55.02)
Contract #03170102
Totals60687.000.000.000.0

CountyFANNIN
HighwaySH0078
FromBONHAM TXDOT FACILITY AND VARIOUS
ToPICNIC AREAS IN FANNIN COUNTY
CSJ6307-38-001
Proj IDRMC - 630738001
Work TypePICNIC AREA AND GROUNDS MAINTENANCE
 
0.00132175.0021725.0067.5
Work Order09-13-16
Work Began00-00-00
Work Completed
Time Computed09-13-16
Contract Working Days365
Addl Days Granted0
Working Days Charged261
Percent Time Used71
Contractor(s)
WILLIAM CURTIS SMITH
SUBCONTRACTOR(S) FOR CCSJ: 6307-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160106
Totals32175.003725.0021725.0067.5

CountyRAINS
HighwayUS0069
FromRAINS COUNTY MAINTENANCE COMPLEX
ToIN EMORY
CSJ6307-40-001
Proj IDSUP - 630740001
Work TypeJANITORIAL MAINTENANCE
 
0.00114543.5811333.8277.9
Work Order08-16-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160131
Totals14543.581549.8811333.8277.9

CountyHUNT
HighwayUS0069
FromVARIOUS ROADWAYS IN HUNT AND
ToRAINS COUNTIES
CSJ6307-86-001
Proj IDRMC - 630786001
Work TypeDITCH AND CULVERT CLEANING
 
0.001316440.00348485.9599.9
Work Order12-16-16
Work Began00-00-00
Work Completed
Time Computed12-19-16
Contract Working Days365
Addl Days Granted0
Working Days Charged164
Percent Time Used44
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10160102
Totals316440.000.00348485.9599.9

CountyGRAYSON
HighwayUS0082
FromVARIOUS LOCATIONS IN
ToGRAYSON COUNTY
CSJ6308-06-001
Proj IDRMC - 630806001
Work TypeDEBRIS REMOVAL
 
0.001282048.00133905.0047.4
Work Order11-18-16
Work Began00-00-00
Work Completed
Time Computed11-30-16
Contract Working Days365
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
SOUTHERN CROSS CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09160101
Totals282048.0023730.00133905.0047.4

CountyGRAYSON
HighwayUS0069
FromVARIOUS
To.
CSJ6308-08-001
Proj IDSUP - 630808001
Work TypeJANITORIAL, GROUNDS, LANDSCAPING
 
0.001353918.60132355.8637.3
Work Order08-26-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged273
Percent Time Used37
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160107
Totals353918.6015029.42132355.8637.3

CountyDELTA
HighwaySH0024
FromDELTA COUNTY MAINTENANCE COMPLES
ToIN COOPER
CSJ6308-40-001
Proj IDSUP - 630840001
Work TypeJANITORIAL MAINTENANCE
 
0.00112038.077949.8466.0
Work Order09-20-16
Work Began00-00-00
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged243
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160131
Totals12038.07853.027949.8466.0

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN LAMAR, DELTA,
ToAND RED RIVER COUNTIES
CSJ6308-49-001
Proj IDRMC - 630849001
Work TypeON CALL METAL BEAM GUARD FENCE REPAIR
 
0.001191134.0081896.4042.8
Work Order11-22-16
Work Began00-00-00
Work Completed
Time Computed12-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10160101
Totals191134.007953.0081896.4042.8