| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | HUNT |
| Highway |
IH0030 |
| From |
VARIOUS ROADWAYS IN |
| To |
HUNT COUNTY |
| CSJ |
6249-41-001 |
| Proj ID |
RMC - 624941001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
0.001 |
165072.40 |
0.00 |
17904.00 |
10.8 |
| Work Order |
04-22-13 |
| Work Began |
04-22-13 |
| Work Completed |
|
| Time Computed |
04-29-13 |
| Contract Working Days |
39 |
| Addl Days Granted |
0 |
| Working Days Charged |
2 |
| Percent Time Used |
5 |
| Contractor(s) |
| C & C MOWING CONTRACTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6249-41-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12120107 |
|
Totals |
165072.40 |
0.00 |
17904.00 |
10.8 |
|
| County | HUNT |
| Highway |
SH0011 |
| From |
VARIOUS ROADWAYS IN |
| To |
HUNT COUNTY |
| CSJ |
6249-42-001 |
| Proj ID |
RMC - 624942001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
0.001 |
107149.14 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
03-18-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
06-10-13 |
| Contract Working Days |
26 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| GANT CONTRACTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6249-42-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12120108 |
|
Totals |
107149.14 |
0.00 |
0.00 |
0.0 |
|
| County | FRANKLIN |
| Highway |
SH0037 |
| From |
VARIOUS ROADWAYS IN |
| To |
FRANKLIN AND HOPKINS COUNTY |
| CSJ |
6249-43-001 |
| Proj ID |
RMC - 624943001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
0.001 |
83248.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
02-21-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
06-10-13 |
| Contract Working Days |
32 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| EASTGATE SERVICES |
SUBCONTRACTOR(S) FOR CCSJ: 6249-43-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12120109 |
|
Totals |
83248.00 |
0.00 |
0.00 |
0.0 |
|
| County | LAMAR |
| Highway |
US0082 |
| From |
VARIOUS ROADWAYS IN |
| To |
LAMAR COUNTY |
| CSJ |
6249-44-001 |
| Proj ID |
RMC - 624944001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
0.001 |
183175.00 |
9100.00 |
9100.00 |
4.9 |
| Work Order |
02-20-13 |
| Work Began |
05-28-13 |
| Work Completed |
|
| Time Computed |
06-04-13 |
| Contract Working Days |
66 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| RICKEY BAIRD |
SUBCONTRACTOR(S) FOR CCSJ: 6249-44-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12120110 |
|
Totals |
183175.00 |
9100.00 |
9100.00 |
4.9 |
|
| County | GRAYSON |
| Highway |
US0075 |
| From |
VARIOUS ROADWAYS IN |
| To |
GRAYSON COUNTY |
| CSJ |
6249-45-001 |
| Proj ID |
RMC - 624945001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
0.001 |
125511.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
06-05-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
06-12-13 |
| Contract Working Days |
39 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ANTHONY SERVICES |
SUBCONTRACTOR(S) FOR CCSJ: 6249-45-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12120111 |
|
Totals |
125511.00 |
0.00 |
0.00 |
0.0 |
|
| County | GRAYSON |
| Highway |
US0069 |
| From |
VARIOUS ROADWAYS IN |
| To |
GRAYSON COUNTY |
| CSJ |
6249-46-001 |
| Proj ID |
RMC - 624946001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
0.001 |
169357.72 |
65047.36 |
65047.36 |
38.4 |
| Work Order |
05-06-13 |
| Work Began |
05-13-13 |
| Work Completed |
|
| Time Computed |
05-20-13 |
| Contract Working Days |
53 |
| Addl Days Granted |
0 |
| Working Days Charged |
6 |
| Percent Time Used |
11 |
| Contractor(s) |
| ANTHONY SERVICES |
SUBCONTRACTOR(S) FOR CCSJ: 6249-46-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12120112 |
|
Totals |
169357.72 |
65047.36 |
65047.36 |
38.4 |
|
| County | HOPKINS |
| Highway |
SH0019 |
| From |
VARIOUS ROADWAYS IN |
| To |
HOPKINS COUNTY |
| CSJ |
6249-47-001 |
| Proj ID |
RMC - 624947001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
0.001 |
106697.40 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
02-21-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
06-10-13 |
| Contract Working Days |
36 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| CATOCON, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6249-47-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12120113 |
|
Totals |
106697.40 |
0.00 |
0.00 |
0.0 |
|
| County | HOPKINS |
| Highway |
IH0030 |
| From |
IH 30 THROUGH HOPKINS AND FRANKLIN |
| To |
COUNTIES AND INTERCITY AREAS |
| CSJ |
6249-48-001 |
| Proj ID |
RMC - 624948001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
0.001 |
129633.33 |
43211.11 |
43211.11 |
33.3 |
| Work Order |
02-21-13 |
| Work Began |
05-13-13 |
| Work Completed |
|
| Time Computed |
05-20-13 |
| Contract Working Days |
39 |
| Addl Days Granted |
0 |
| Working Days Charged |
6 |
| Percent Time Used |
15 |
| Contractor(s) |
| BRYDL CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6249-48-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12120114 |
|
Totals |
129633.33 |
43211.11 |
43211.11 |
33.3 |
|
| County | HOPKINS |
| Highway |
IH0030 |
| From |
VARIOUS ROADWAYS IN |
| To |
HOPKINS AND FRANKLIN COUNTIES |
| CSJ |
6250-09-001 |
| Proj ID |
RMC - 625009001 |
| Work Type |
ON - CALL RPM'S |
| |
|
0.001 |
32550.00 |
0.00 |
12399.38 |
38.0 |
| Work Order |
11-27-12 |
| Work Began |
12-04-12 |
| Work Completed |
|
| Time Computed |
12-11-12 |
| Contract Working Days |
254 |
| Addl Days Granted |
0 |
| Working Days Charged |
121 |
| Percent Time Used |
47 |
| Contractor(s) |
| BRYDL CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6250-09-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10120113 |
|
Totals |
32550.00 |
0.00 |
12399.38 |
38.0 |
|
| County | GRAYSON |
| Highway |
US0082 |
| From |
VARIOUS ROADWAYS IN GRAYSON AND |
| To |
ON OCCASION IN FANNIN COUNTY |
| CSJ |
6250-16-001 |
| Proj ID |
RMC - 625016001 |
| Work Type |
ONE WAY TRAFFIC CONTROL (FLAGGING) |
| |
|
0.001 |
69192.50 |
3459.62 |
18458.43 |
26.6 |
| Work Order |
01-07-13 |
| Work Began |
01-07-13 |
| Work Completed |
|
| Time Computed |
01-14-13 |
| Contract Working Days |
254 |
| Addl Days Granted |
0 |
| Working Days Charged |
99 |
| Percent Time Used |
38 |
| Contractor(s) |
| CHITWOOD, INC |
SUBCONTRACTOR(S) FOR CCSJ: 6250-16-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12120101 |
|
Totals |
69192.50 |
3459.62 |
18458.43 |
26.6 |
|
| County | FRANKLIN |
| Highway |
SH0037 |
| From |
FRANKLIN |
| To |
COUNTY |
| CSJ |
6250-19-001 |
| Proj ID |
RMC - 625019001 |
| Work Type |
CULVERT REPLACEMENT |
| |
|
0.001 |
41466.00 |
1700.00 |
42666.00 |
100.0 |
| Work Order |
02-25-13 |
| Work Began |
03-19-13 |
| Work Completed |
05-31-13 |
| Time Computed |
03-26-13 |
| Contract Working Days |
15 |
| Addl Days Granted |
0 |
| Working Days Charged |
3 |
| Percent Time Used |
20 |
| Contractor(s) |
| J. M. CONSTRUCTION |
SUBCONTRACTOR(S) FOR CCSJ: 6250-19-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01130106 |
|
Totals |
41466.00 |
1700.00 |
42666.00 |
100.0 |
|
| County | HOPKINS |
| Highway |
IH0030 |
| From |
LP 301 |
| To |
FRANKLIN COUNTY LINE |
| CSJ |
6250-95-001 |
| Proj ID |
RMC - 625095001 |
| Work Type |
FOG SEAL |
| |
|
0.001 |
348749.18 |
307172.40 |
307172.40 |
88.0 |
| Work Order |
04-23-13 |
| Work Began |
05-13-13 |
| Work Completed |
|
| Time Computed |
05-20-13 |
| Contract Working Days |
15 |
| Addl Days Granted |
0 |
| Working Days Charged |
6 |
| Percent Time Used |
40 |
| Contractor(s) |
| INTERMOUNTAIN SLURRY SEAL, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6250-95-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02130105 |
|
Totals |
348749.18 |
307172.40 |
307172.40 |
88.0 |
|
| County | HUNT |
| Highway |
FM2194 |
| From |
BLAND HIGH SCHOOL |
| To |
. |
| CSJ |
6251-32-001 |
| Proj ID |
RMC - 625132001 |
| Work Type |
CONSTRUCT LEFT TURN LANE |
| |
|
0.001 |
216219.59 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-30-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
06-13-13 |
| Contract Working Days |
30 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| TEXANA LAND & ASPHALT, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6251-32-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04130102 |
|
Totals |
216219.59 |
0.00 |
0.00 |
0.0 |
|
| County | LAMAR |
| Highway |
US0082 |
| From |
VARIOUS LOCATIONS IN LAMAR, DELTA |
| To |
AND RED RIVER COUNTIES |
| CSJ |
6251-58-001 |
| Proj ID |
RMC - 625158001 |
| Work Type |
ON CALL MBGF REPAIR |
| |
|
0.010 |
74694.00 |
17363.00 |
42311.00 |
56.6 |
| Work Order |
02-11-13 |
| Work Began |
02-18-13 |
| Work Completed |
|
| Time Computed |
02-25-13 |
| Contract Working Days |
306 |
| Addl Days Granted |
0 |
| Working Days Charged |
82 |
| Percent Time Used |
26 |
| Contractor(s) |
| CATOCON, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6251-58-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01130101 |
|
Totals |
74694.00 |
17363.00 |
42311.00 |
56.6 |
|
| County | HOPKINS |
| Highway |
IH0030 |
| From |
VARIOUS LOCATONS IN HOPKINS |
| To |
AND FRANKLIN COUNTIES |
| CSJ |
6251-65-001 |
| Proj ID |
RMC - 625165001 |
| Work Type |
CLEANING / SWEEPING HIGHWAYS |
| |
|
0.001 |
68700.00 |
5100.00 |
8500.00 |
12.3 |
| Work Order |
02-21-13 |
| Work Began |
03-08-13 |
| Work Completed |
|
| Time Computed |
03-15-13 |
| Contract Working Days |
508 |
| Addl Days Granted |
0 |
| Working Days Charged |
55 |
| Percent Time Used |
10 |
| Contractor(s) |
| R RESPONSE DELIVERY SERVICE |
SUBCONTRACTOR(S) FOR CCSJ: 6251-65-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01130105 |
|
Totals |
68700.00 |
5100.00 |
8500.00 |
12.3 |
|
| County | HOPKINS |
| Highway |
IH0030 |
| From |
VARIOUS ROADWAYS IN HOPKINS AND |
| To |
FRANKLIN COUNTY |
| CSJ |
6252-25-001 |
| Proj ID |
RMC - 625225001 |
| Work Type |
REMOVAL AND DISPOSAL OF DEBRIS |
| |
|
0.001 |
57056.00 |
6488.00 |
7288.00 |
12.7 |
| Work Order |
04-19-13 |
| Work Began |
04-24-13 |
| Work Completed |
|
| Time Computed |
05-01-13 |
| Contract Working Days |
254 |
| Addl Days Granted |
0 |
| Working Days Charged |
22 |
| Percent Time Used |
8 |
| Contractor(s) |
| MORTON ENTERPRISE |
SUBCONTRACTOR(S) FOR CCSJ: 6252-25-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02130102 |
|
Totals |
57056.00 |
6488.00 |
7288.00 |
12.7 |
|
| County | HOPKINS |
| Highway |
IH0030 |
| From |
VARIOUS ROADWAYS IN |
| To |
HOPKINS AND FRANKLIN COUNTIES |
| CSJ |
6252-27-001 |
| Proj ID |
RMC - 625227001 |
| Work Type |
ON - CALL TY II PAVEMENT MARKING |
| |
|
0.001 |
171800.00 |
0.00 |
49206.60 |
28.6 |
| Work Order |
03-04-13 |
| Work Began |
03-11-13 |
| Work Completed |
|
| Time Computed |
03-18-13 |
| Contract Working Days |
306 |
| Addl Days Granted |
0 |
| Working Days Charged |
64 |
| Percent Time Used |
20 |
| Contractor(s) |
| STRIPING TECHNOLOGY, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6252-27-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02130103 |
|
Totals |
171800.00 |
0.00 |
49206.60 |
28.6 |
|
| County | HOPKINS |
| Highway |
IH0030 |
| From |
VARIOUS LOCATION IN |
| To |
HOPKINS AND FRANKLIN COUNTIES |
| CSJ |
6252-28-001 |
| Proj ID |
RMC - 625228001 |
| Work Type |
ON - CALL SPECIALTY STRIPING |
| |
|
0.001 |
62008.00 |
26911.95 |
58865.00 |
94.9 |
| Work Order |
04-10-13 |
| Work Began |
04-17-13 |
| Work Completed |
|
| Time Computed |
04-24-13 |
| Contract Working Days |
254 |
| Addl Days Granted |
0 |
| Working Days Charged |
27 |
| Percent Time Used |
10 |
| Contractor(s) |
| STRIPING TECHNOLOGY, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6252-28-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03130101 |
|
Totals |
62008.00 |
26911.95 |
58865.00 |
94.9 |
|
| County | GRAYSON |
| Highway |
US0075 |
| From |
VARIOUS LOCATIONS IN |
| To |
GRAYSON AND FANNIN CO. |
| CSJ |
6252-77-001 |
| Proj ID |
RMC - 625277001 |
| Work Type |
METAL BEAM GUARD FENCE / CABLE REPAIR |
| |
|
0.001 |
167434.11 |
0.00 |
5471.10 |
3.2 |
| Work Order |
03-06-13 |
| Work Began |
03-13-13 |
| Work Completed |
|
| Time Computed |
03-20-13 |
| Contract Working Days |
306 |
| Addl Days Granted |
0 |
| Working Days Charged |
62 |
| Percent Time Used |
20 |
| Contractor(s) |
| CKORP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6252-77-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01130107 |
|
Totals |
167434.11 |
0.00 |
5471.10 |
3.2 |
|
| County | LAMAR |
| Highway |
US0082 |
| From |
VARIOUS LOCATIONS IN LAMAR, DELTA |
| To |
AND RED RIVER COUNTIES |
| CSJ |
6253-25-001 |
| Proj ID |
RMC - 625325001 |
| Work Type |
REMOVE AND INSTALL RAISED PAVEMENT MRKS |
| |
|
0.001 |
52889.76 |
28642.95 |
47444.67 |
100.0 |
| Work Order |
04-29-13 |
| Work Began |
04-29-13 |
| Work Completed |
05-15-13 |
| Time Computed |
05-06-13 |
| Contract Working Days |
30 |
| Addl Days Granted |
0 |
| Working Days Charged |
1 |
| Percent Time Used |
3 |
| Contractor(s) |
| BRYDL CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6253-25-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02130104 |
|
Totals |
52889.76 |
28642.95 |
47444.67 |
100.0 |
|