Monthly Local Let Maintenance Report For Paris District As Of Mar 10, 2015 Page 5 Of 7

Last Update: Wednesday, March 11, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHOPKINS
Highway SH0011
From HOPKINS CO MAINTENANCE
To OFFICE COMPLEX
CSJ 6271-65-001
Proj ID SUP - 627165001
Work Type GROUNDS MAINTENANCE
 
0.001 6342.00 0.00 5068.00 79.9
Work Order 04-07-14
Work Began 05-06-14
Work Completed  
Time Computed 05-06-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 299
Percent Time Used 81
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6271-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04140131
Totals 6342.00 0.00 5068.00 79.9

CountyHUNT
Highway IH0030
From HUNT COUNTY AREA OFFICE AND
To MAINTENANCE COMPLEX
CSJ 6271-66-001
Proj ID SUP - 627166001
Work Type GROUNDS MAINTENANCE
 
0.001 0.00 0.00 9570.00 0.0
Work Order 05-08-14
Work Began 05-08-14
Work Completed  
Time Computed 05-08-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 296
Percent Time Used 80
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6271-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140133
Totals 0.00 0.00 9570.00 0.0

CountyRAINS
Highway US0069
From VARIOUS ROADWAYS IN
To RAINS COUNTY
CSJ 6271-67-001
Proj ID SUP - 627167001
Work Type PICNIC AREA MAINTENANCE
 
0.001 28200.00 1225.00 21850.00 77.4
Work Order 05-09-14
Work Began 05-11-14
Work Completed  
Time Computed 05-11-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 293
Percent Time Used 80
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6271-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140132
Totals 28200.00 1225.00 21850.00 77.4

CountyGRAYSON
Highway US0075
From VARIOUS
To .
CSJ 6271-95-001
Proj ID SUP - 627195001
Work Type JANITORIAL, GROUNDS, LANDSCAPING
 
0.001 75244.62 0.00 68255.87 90.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-14
Work Began 00-00-00
Work Completed  
Time Computed 04-01-14
Contract Working Days 153
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6271-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140136
Totals 75244.62 0.00 68255.87 90.7

CountyLAMAR
Highway LP0286
From GROUNDS MAINTENANCE AT
To PARIS_AREA OFFICE
CSJ 6271-99-001
Proj ID SUP - 627199001
Work Type GROUNDS MAINTENANCE
 
0.001 5700.00 150.00 2700.00 47.3
Work Order 06-24-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 243
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
LIFENET COMMUNITY BEHAVIORAL HEALTHCARE
SUBCONTRACTOR(S) FOR CCSJ: 6271-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06140131
Totals 5700.00 150.00 2700.00 47.3

CountyLAMAR
Highway BU0271B
From PARIS DISTRICT HEADQUARTERS
To AT 1365 N MAINT
CSJ 6272-42-001
Proj ID SUP - 627242001
Work Type GROUNDS MAINTENANCE
 
0.001 29960.00 1280.00 17380.00 58.0
Work Order 06-01-14
Work Began 06-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 271
Percent Time Used 74
Contractor(s)
TIBH INDUSTRIES, INC.
LIFENET COMMUNITY BEHAVIORAL HEALTHCARE
SUBCONTRACTOR(S) FOR CCSJ: 6272-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140134
Totals 29960.00 1280.00 17380.00 58.0

CountyFANNIN
Highway US0082
From MAINTENANCE OFFICE
To LOCATED IN FANNIN COUNTY
CSJ 6272-60-001
Proj ID SUP - 627260001
Work Type JANITORIAL MAINTENANCE
 
0.001 12704.84 1892.07 9378.63 73.8
Work Order 05-27-14
Work Began 06-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 74
Contractor(s)
TIBH INDUSTRIES, INC.
LIFENET COMMUNITY BEHAVIORAL HEALTHCARE
SUBCONTRACTOR(S) FOR CCSJ: 6272-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140136
Totals 12704.84 1892.07 9378.63 73.8

CountyLAMAR
Highway LP0286
From LAMAR MAINT OFFICE
To LOCATION IN LAMAR CO
CSJ 6272-61-001
Proj ID SUP - 627261001
Work Type JANITORIAL MAINTENANCE
 
0.001 10869.20 639.10 7826.90 72.0
Work Order 05-27-14
Work Began 06-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 74
Contractor(s)
TIBH INDUSTRIES, INC.
LIFENET COMMUNITY BEHAVIORAL HEALTHCARE
SUBCONTRACTOR(S) FOR CCSJ: 6272-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140135
Totals 10869.20 639.10 7826.90 72.0

CountyFRANKLIN
Highway IH0030
From VARIOUS ROADWAYS IN
To FRANKLIN COUNTY
CSJ 6273-71-001
Proj ID SUP - 627371001
Work Type PICNIC AREA MAINTENANCE
 
0.001 13010.00 580.00 7170.00 55.1
Work Order 06-23-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 243
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6273-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06140132
Totals 13010.00 580.00 7170.00 55.1

CountyFRANKLIN
Highway IH0030
From FRANKLIN COUNTY MAINT COMPLEX
To AT MT VERNON
CSJ 6275-09-001
Proj ID SUP - 627509001
Work Type JANITORIAL MAINTENANCE
 
0.001 16000.12 1122.04 8879.22 55.4
Work Order 07-29-14
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 57
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06140133
Totals 16000.12 1122.04 8879.22 55.4

CountyRAINS
Highway US0069
From RAINS COUNTY
To MAINT COMPLEX
CSJ 6275-10-001
Proj ID SUP - 627510001
Work Type GROUNDS MAINTENANCE
 
0.001 10620.00 0.00 3410.00 32.1
Work Order 07-11-14
Work Began 08-06-14
Work Completed  
Time Computed 08-06-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 207
Percent Time Used 56
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6275-10-001
CARTHAGE DRILLING, INC.(0.00%)
Contract # 06140134
Totals 10620.00 0.00 3410.00 32.1

CountyRED RIVER
Highway US0082
From MAINTENANCE COMPLEX
To IN RED RIVER COUNTY
CSJ 6275-11-001
Proj ID SUP - 627511001
Work Type GROUNDS MAINTENANCE
 
0.001 6550.00 0.00 1075.00 16.4
Work Order 07-11-14
Work Began 08-17-14
Work Completed  
Time Computed 08-17-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 196
Percent Time Used 53
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6275-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06140135
Totals 6550.00 0.00 1075.00 16.4

CountyHUNT
Highway IH0030
From VARIOUS LOCATIONS IN
To HUNT AND RAINS COUNTIES
CSJ 6275-56-001
Proj ID RMC - 627556001
Work Type ON CALL TREE REMOVAL
 
0.001 133485.00 0.00 0.00 0.0
Work Order 01-28-15
Work Began 02-05-15
Work Completed  
Time Computed 02-12-15
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 2
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12140101
Totals 133485.00 0.00 0.00 0.0

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS IN
To HOPKINS AND FRANKLIN COUNTIES
CSJ 6275-57-001
Proj ID RMC - 627557001
Work Type ON CALL TREE REMOVAL
 
0.001 123650.00 40197.00 59644.00 48.2
Work Order 01-12-15
Work Began 01-20-15
Work Completed  
Time Computed 01-27-15
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 6
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12140102
Totals 123650.00 40197.00 59644.00 48.2

CountyGRAYSON
Highway US0075
From VARIOUS LOCATIONS
To IN GRAYSON COUNTY
CSJ 6276-39-001
Proj ID SUP - 627639001
Work Type LITTER PICK UP
 
0.001 44328.43 2943.73 22836.68 51.5
Work Order 08-22-14
Work Began 09-01-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6276-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08140131
Totals 44328.43 2943.73 22836.68 51.5

CountyHOPKINS
Highway IH0030
From VARIOUS LOCAITONS IN
To HOPKINS/FRANKLIN COUNTIES
CSJ 6276-40-001
Proj ID SUP - 627640001
Work Type LITTER PICKUP
 
0.001 87552.32 3038.44 44901.64 51.2
Work Order 08-28-14
Work Began 09-01-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6276-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08140132
Totals 87552.32 3038.44 44901.64 51.2

CountyHUNT
Highway IH0030
From VARIOUS LOCATIONS IN
To HUNT COUNTY
CSJ 6276-41-001
Proj ID SUP - 627641001
Work Type LITTER PICKUP
 
0.001 85656.68 3759.30 52052.16 60.7
Work Order 08-28-14
Work Began 00-00-00
Work Completed  
Time Computed 09-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6276-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08140133
Totals 85656.68 3759.30 52052.16 60.7

CountyLAMAR
Highway US0082
From VARIOUS LOCATIONS IN
To LAMAR/DELTA/RED RIVER COUNTIES
CSJ 6276-42-001
Proj ID SUP - 627642001
Work Type LITTER PICKUP
 
0.001 123059.60 9275.16 63361.25 51.4
Work Order 08-22-14
Work Began 09-01-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
VOCATIONAL OPPORTUNITIES CENTER NORTHEAST TEXAS,INC
SUBCONTRACTOR(S) FOR CCSJ: 6276-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08140134
Totals 123059.60 9275.16 63361.25 51.4

CountyRAINS
Highway US0069
From VARIOUS LOCATIONS
To IN RAINS COUNTY
CSJ 6276-43-001
Proj ID SUP - 627643001
Work Type LITTER PICKUP
 
0.001 34149.21 7301.92 20160.79 59.0
Work Order 08-28-14
Work Began 09-01-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6276-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08140135
Totals 34149.21 7301.92 20160.79 59.0

CountyFANNIN
Highway US0082
From VARIOUS LOCATIONS IN
To FANNIN COUNTY
CSJ 6276-44-001
Proj ID SUP - 627644001
Work Type LITTER PICKUP
 
0.001 33263.81 0.00 11392.29 34.2
Work Order 08-22-14
Work Began 09-01-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 136
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6276-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08140136
Totals 33263.81 0.00 11392.29 34.2

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7